{"document":{"slug":"rec-20260424-5196","title":"Reply of Old Dominion Electric Cooperative to Responses to Initial Briefs of PJM Interconnection, L.L.C. and Indicated Transmission Owners","issued":"2026-04-24","accession":"20260424-5196","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Old Dominion Electric Cooperative","kind":"brief","file":"sources/filings/text/20260424-5196_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260424-5196","tier":"record","sha256":"de5bbbad2d4394d03219f3f4c8ab6d9657403ee11229d60bb8b685cf8d7bc3df","pages":8,"tokens":1658,"emptyPages":[],"textThemes":["colo","flex"]},"pages":[{"page":1,"startToken":0,"endToken":183,"text":"1 \n \n \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C. \nAllegheny Electric Cooperative, Inc. \nAmerican Transmission Systems, Incorporated \nAtlantic City Electric Company \nBaltimore Gas and Electric Company \nDelmarva Power & Light Company \nDuke Energy Ohio, Inc. \nDuke Energy Kentucky, Inc. \nEast Kentucky Power Cooperative, Inc. \nEssential Power Rock Springs, LLC \nHudson Transmission Partners, LLC \nJersey Central Power & Light Company \nMid-Atlantic Interstate Transmission, LLC \nNeptune Regional Transmission System, LLC \nOld Dominion Electric Cooperative \nPECO Energy Company \nPPL Electric Utilities Corporation \nPotomac Electric Power Company \nPublic Service Electric and Gas Company \nRockland Electric Company \nTrans-Allegheny Interstate Line Company \nTransource West Virginia, LLC \nUGI Utilities, Inc. \nMonongahela Power Company \nThe Potomac Edison Company \nCommonwealth Edison Company \nCommonwealth Edison Company of Indiana, Inc. \nThe Dayton Power and Light Company  \nAEP Appalachian Transmission Company, Inc. \nAEP Indiana Michigan Transmission Company, Inc. AEP \nKentucky Transmission Company, Inc. \nAEP Ohio Transmission Company, Inc. \nAEP West Virginia Transmission Company, Inc. \nAppalachian Power Company \nIndiana Michigan Power Company \nKentucky Power Company \nKingsport Power Company \nOhio Power Company \nWheeling Power Company \nDuquesne Light Company\n   Docket Nos.  EL25-49-000 \nEL25-49-001"},{"page":2,"startToken":183,"endToken":430,"text":"2 \n \nVirginia Electric and Power Company \nLinden VFT, LLC \nCity of Cleveland, Department of Public Utilities, Division \nof Cleveland Public Power \nCity of Hamilton, OH \nSouthern Maryland Electric Cooperative, Inc. \nOhio Valley Electric Corporation \nAMP Transmission, LLC \nSilver Run Electric, LLC \nNextEra Energy Transmission MidAtlantic Indiana, Inc. \nWabash Valley Power Association, Inc. \nKeystone Appalachian Transmission Company \n \nLarge Loads Co-Located at Generating Facilities  \n \nConstellation Energy Generation, LLC \n \nv.  \n \nPJM Interconnection, L.L.C.\n \n \n \n \n \n \n \n \n \n \n \n \n \n AD24-11-000 \n \n EL25-20-000 \n(Consolidated) \n \nREPLY OF OLD DOMINION ELECTRIC COOPERATIVE \nTO RESPONSES TO INITIAL BRIEFS OF PJM INTERCONNECTION, L.L.C. AND \nTHE INDICATED PJM TRANSMISSION OWNERS \n \nPursuant to the Order issued in the above-referenced proceeding on December 18, 2025, \nand the Notice of Extension of Time issued on January 23, 2026, Old Dominion Electric \nCooperative (“ODEC”) submits this reply to certain of the responses to the Initial Brief and Joint \nResponses of the PJM Transmission Owners to Paper Hearing Questions and the Initial Brief of \nPJM Interconnection, L.L.C. (“PJM”).  \nIn its Reply Brief, ODEC expressed its general agreement with the proposals submitted by \nPJM and the Indicated TOs. ODEC also expressed its willingness to adopt the Indicated TOs’ \nproposed rates for the new Firm Contract Demand and Non-Firm Contract Demand, subject to \nclarification. ODEC explained its support for the Commission’s acceptance of both filings, subject \nto further compliance filings as necessary to address the following issues described in its Reply \nBrief: (1) clarification of PJM’s proposed requirement that an Eligible Customer must be"},{"page":3,"startToken":430,"endToken":731,"text":"3 \n \ndesignated to take transmission service on behalf of a Co-Located Load and provide PJM with an \nauthorization from its Relevant Electric Retail Regulatory Authority (“RERRA”); (2) with respect \nto the PJM TOs’ proposal for PJM to provide billing credits to reflect revenues associated with the \nnew Grid Reliance Charge as well as revenues for Non-Firm Contract Demand Service, the \nindividual TOs will need to either confirm that their formula or stated rates and metrics reporting \nenable the direct crediting by PJM, or provide whatever revisions are necessary in order to do so; \n(3) PJM and the PJM Transmission Owners will need to address how to charge regulation and \nblack start service to an Eligible Customer taking service on behalf of Co-Located Load; and (4) \nthe Commission consider whether any protections are needed for local utilities or TOs should they \nneed to take the extraordinary measure of disconnecting an Eligible Customer taking service on \nbehalf of Co-Located Loads, if the Eligible Customer’s use of the transmission system exceeds \ncontract demand or are called upon for Load Shedding and Curtailment.  In such instances, the \nlocal utility or TO should not be liable for legal, financial or other damages that might be \nexperienced by an Eligible Customer.  \nODEC’s position on PJM and the Indicated TOs’ filings remains as stated in ODEC’s \nReply Brief. ODEC reiterates its request that the Commission address these issues, particularly \nclarification regarding how a generation and transmission cooperative like ODEC will meet PJM’s \nproposed requirement that an Eligible Customer must be designated to take transmission service \non behalf of a Co-Located Load and provide PJM with an authorization from its RERRA.1 ODEC \nsubmits this brief response to address two issues; the proposed measures to protect reliability, and \nthe proposed Grid Reliance Charge.  \n \n1 ODEC Reply Brief at 6-7."},{"page":4,"startToken":731,"endToken":1014,"text":"4 \n \nA. PJM Must Ensure that Service to Co-Located Loads Does Not Adversely \nImpact Reliability \nODEC continues to express its support for PJM’s proposal for escalating penalties in the \nform of disqualification and pauses in service for failures to shed load or curtail, as well as for \nfailures in control technology, and/or protection system misoperation.2 However, as ODEC \ndiscussed in its Reply Brief, clarification is needed regarding how the Eligible Customer and \nRERRA for Co-Located Loads will be applied to generation and transmission cooperatives like \nODEC.3 PJM’s implementation of its penalties must not subject ODEC or its member distribtion \ncooperatives to service interruptions or disqualification, or financial penalties, as a result of \nrequiring ODEC to serve as the Eligible Customer. Instead, such penalties must be limited to and \nborne by the Co-Located Loads.  \nODEC also continues to support development of financial penalties, while recognizing that \nfinancial penalties alone will not be sufficient to preserve reliability. The need to ensure reliability \nof the transmission system is paramount. To that end, ODEC disagrees with parties who have \nsuggested that financial penalties alone will suffice, and that PJM’s proposed remedial measures \nare overly harsh.4 ODEC does not agree that PJM’s proposed suspension and disqualification \nmeasures are unfairly imposed regardless of fault and will make the services unduly risky for many \nloads.5 Reliability of the transmission system is critical and financial penalties imposed on the \nEligible Customer, alone, will neither preserve reliability nor protect other users of the \n \n2 Id. at 11. \n3 ODEC Reply Brief at 6-7. \n4 Constellation Reply Brief at 19-20; Vistra Reply Brief at 29-31; Joint Co-Location Developers Reply \nBrief at 23-27. \n5 Constellation Reply Brief at 19-20."},{"page":5,"startToken":1014,"endToken":1313,"text":"5 \n \ntransmission system from adverse impacts on reliability where an Eligible Customer exceeds \nreliable use of the transmission system. \nODEC also agrees with the Indicated PJM TOs that PJM should clarify that (1) each new \ntransmission service, including Firm Contract Demand Transmission Service, will be conditioned \non the implementation of control technologies and protection systems that will ensure Co-Located \nLoads do not exceed their specified level of transmission service; and (2) necessary control \ntechnologies and protection systems may be required on both the customer’s side and the \nTransmission Owner’s side of the point of interconnection.6  \nB. The Commission Should Accept the Indicated PJM TOs’ Grid Reliance \nCharge \nThe Indicated PJM TOs proposed a Grid Reliance Charge to reflect the fact that Co-\nLocation Arrangements are physically connected to and synchronized to the transmission system7 \nand use the transmission system.8 Although some have asserted there should be no charge at all \nfor customers that reserve zero to a de minimis amount of transmission service,9 the disagreement \namong parties is not focused on whether there should be a Grid Reliance Charge, but instead on \nhow such charges should be determined.10 ODEC continues to support the Indicated PJM TOs’ \nGrid Reliance Charge, in addition to charges for Black Start and Regulation Services. These \nservices may not reflect the full use or reliance on the transmission system by Co-Location \nArrangements, and Co-Located Loads must pay their fair share. While other proposals might be \n \n6 Joint Response of the Indicated PJM Transmission Owners (“Indicated PJM TOs Response”) at 7-8. \n7 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“Hearing Order”) at P 164. \n8 See id. at P 177.  \n9 Vistra Initial Brief at 21. \n10 See Constellation Reply Brief at 25-28 (arguing for an alternative calculation methodology)."},{"page":6,"startToken":1313,"endToken":1569,"text":"6 \n \njust and reasonable, the Indicated PJM TOs have adequately supported their proposed Grid \nReliance Charge and the Commission should accept it as filed. \nWHEREFORE, for the foregoing reasons, ODEC requests that the Commission consider \nthis response as well as the requests in ODEC’s Reply Brief and accept PJM’s and the Indicated \nPJM Transmission Owners’ proposals for transmission service to Co-Located Loads, subject \ncompliance filings as necessary to address the following: (1) clarification of PJM’s proposed \nrequirement that an Eligible Customer must be designated to take transmission service on behalf \nof a Co-Located Load and provide PJM with an authorization from its RERRA; (2) with respect \nto the PJM TOs’ proposal for PJM to provide billing credits to reflect revenues associated with the \nnew Grid Reliance Charge as well as revenues for Non-Firm Contract Demand Service, the \nindividual TOs will need to either confirm that their formula or stated rates and metrics reporting \nenable the direct crediting by PJM, or provide whatever revisions are necessary in order to do so; \n(3) PJM and the PJM Transmission Owners will need to address how to charge regulation and \nblack start service to an Eligible Customer taking service on behalf of Co-Located Load; and (4) \nthe Commission consider whether any protections are needed for local utilities or TOs should they \nneed to take the extraordinary measure of disconnecting an Eligible Customer taking service on \nbehalf of Co-Located Loads, if the Eligible Customer’s use of the transmission system exceeds \ncontract demand or are called upon for Load Shedding and Curtailment."},{"page":7,"startToken":1569,"endToken":1616,"text":"7 \n \n \nRespectfully submitted, \n \n /s/ Adrienne E. Clair \nAdrienne E. Clair \nJenna Cliatt \nThompson Coburn LLP \n1909 K Street, N.W., Suite 600 \nWashington, D.C.  20006-1167 \n(202) 585-6900 \n(202) 585-6969 (fax) \naclair@thompsoncoburn.com  \njcliatt@thompsoncoburn.com \n \nAttorneys for Old Dominion Electric \nCooperative \nDated: April 24, 2026"},{"page":8,"startToken":1616,"endToken":1658,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that on this 24th day of April 2026, I have caused a copy of the foregoing \nto be served upon each party designated on the Commission’s Official Service List for this \nproceeding. \n \n /s/Adrienne E. Clair"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":4,"endAt":5,"startToken":0,"endToken":732},{"p":4,"at":5,"title":"A. PJM Must Ensure that Service to Co-Located Loads Does Not Adversely","method":"printed heading","endPage":5,"endAt":665,"startToken":732,"endToken":1110},{"p":5,"at":665,"title":"B. The Commission Should Accept the Indicated PJM TOs’ Grid Reliance","method":"printed heading","endPage":8,"endAt":0,"startToken":1110,"endToken":1616},{"p":8,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":8,"endAt":247,"startToken":1616,"endToken":1658}]}