{"document":{"slug":"rec-20260424-5247","title":"Reply Brief of PJM Interconnection, L.L.C","issued":"2026-04-24","accession":"20260424-5247","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"PJM Interconnection, L.L.C.","kind":"brief","file":"sources/filings/text/20260424-5247_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260424-5247","tier":"record","sha256":"8558c8942d2ef16f1125e0652364326598a8b63454fe8152e4988001605131c7","pages":111,"tokens":34853,"emptyPages":[],"textThemes":["colo","flex","study","cost"]},"pages":[{"page":1,"startToken":0,"endToken":187,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \nPJM Interconnection, L.L.C. \nAllegheny Electric Cooperative, Inc. \nAmerican Transmission Systems, Incorporated \nAtlantic City Electric Company \nBaltimore Gas and Electric Company \nDelmarva Power & Light Company \nDuke Energy Ohio, Inc. \nDuke Energy Kentucky, Inc. \nEast Kentucky Power Cooperative, Inc. \nEssential Power Rock Springs, LLC \nHudson Transmission Partners, LLC \nJersey Central Power & Light Company \nMid-Atlantic Interstate Transmission, LLC \nNeptune Regional Transmission System, LLC \nOld Dominion Electric Cooperative \nPECO Energy Company \nPPL Electric Utilities Corporation \nPotomac Electric Power Company \nPublic Service Electric and Gas Company \nRockland Electric Company \nTrans-Allegheny Interstate Line Company \nTransource West Virginia, LLC \nUGI Utilities, Inc. \nMonongahela Power Company \nThe Potomac Edison Company \nCommonwealth Edison Company \nCommonwealth Edison Company of Indiana, \nInc. \nThe Dayton Power and Light Company  \nAEP Appalachian Transmission Company, Inc. \nAEP Indiana Michigan Transmission Company, \nInc. AEP Kentucky Transmission Company, Inc. \nAEP Ohio Transmission Company, Inc. \nAEP West Virginia Transmission Company, Inc. \nAppalachian Power Company \nIndiana Michigan Power Company \nKentucky Power Company \nKingsport Power Company \nOhio Power Company \nWheeling Power Company \nDuquesne Light Company \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n \n              Docket Nos. EL25-49-000\n                                   EL25-49-001"},{"page":2,"startToken":187,"endToken":362,"text":"Virginia Electric and Power Company \nLinden VFT, LLC \nCity of Cleveland, Department of Public \nUtilities, Division of Cleveland Public Power \nCity of Hamilton, OH \nSouthern Maryland Electric Cooperative, Inc. \nOhio Valley Electric Corporation \nAMP Transmission, LLC \nSilver Run Electric, LLC \nNextEra Energy Transmission MidAtlantic \nIndiana, Inc. \nWabash Valley Power Association, Inc. \nKeystone Appalachian Transmission Company \nLarge Loads Co-Located at Generating Facilities \nConstellation Energy Generation, LLC \nv.  \nPJM Interconnection, L.L.C. \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n \n \n \n \n \n \n \n \n \n \n \n \n \n \n                                  AD24-11-000\n \n                                   EL25-20-000\n                                 (Consolidated)\n                                                    \nREPLY BRIEF OF PJM INTERCONNECTION, L.L.C. \nCraig Glazer \nVice President – Federal Government Policy \nPJM Interconnection, L.L.C. \n1200 G Street, NW, Suite 600 \nWashington, DC  20005 \n(202) 423-4743 \ncraig.glazer@pjm.com \n \nMark J. Stanisz \nAssociate General Counsel \nThomas DeVita \nAssociate General Counsel \nPJM Interconnection, L.L.C.  \n2750 Monroe Blvd, \nAudubon, PA  19403 \n(610) 666-8800 \nmark.stanisz@pjm.com \nthomas.devita@pjm.com \nRyan J. Collins \nRuth M. Porter \nWright & Talisman, P.C. \n1200 G Street, NW, Suite 600 \nWashington, DC  20005 \n(202) 393-1200 \ncollins@wrightlaw.com \nporter@wrightlaw.com \n \n \n \n \n \n \n \n \nCounsel for \nPJM Interconnection, L.L.C."},{"page":3,"startToken":362,"endToken":615,"text":"TABLE OF CONTENTS \nI. \nINTRODUCTION .................................................................................................. 3 \nII. \nRESPONSE TO ISSUES RAISED IN REPLY BRIEFS ........................................ 6 \nA. \nContract Demand Transmission Service ..................................................... 6 \n1. \nNon-Firm Contract Demand Transmission Service will be available \nwhen the Co-Located Generating Facility is on outage .................. 6 \n2. \nProvision of Non-Firm Contract Demand Transmission Service . 13 \nB. \nInterim NITS Customers Should Not Be Allowed Access to Co-Located \nGeneration when PJM Has Curtailed the Load......................................... 16 \nC. \nThe Illustrative Tariff Properly Details How PJM Will Study Requests for \nNew Transmission Services and Determine the Level of Service that Can \nBe Reliably Provided ................................................................................ 22 \n1. \nThe Illustrative Tariff provisions regarding transmission studies and \ndetermination of service build from existing Tariff provisions .... 23 \n2. \nThe Illustrative Tariff provisions reflect that PJM requires discretion \nin studying to determine the amount of transmission service that can \nbe provided reliably ...................................................................... 25 \n3. \nThe Illustrative Tariff appropriately provides sufficient notice while \nallowing for implementation details to be in the PJM Manuals ... 30 \n4. \nThe Illustrative Tariff reasonably requires PJM to determine \nwhether the requested level of transmission service can be “reliably \nprovided”....................................................................................... 35 \n5. \nThe Illustrative Tariff can accommodate phased-in Co-Located \nLoads ............................................................................................. 37 \nD. \nNon-Monetary Penalties Are Just and Reasonable and Necessary to Support \nthe Reliable Operation of the Grid ............................................................ 39 \n1. \nThe size and pace of large load integration give rise to heightened \nreliability risk that calls for non-monetary penalties in addition to \nfinancial penalties ......................................................................... 41 \n2. \nPJM’s non-monetary penalties and requirements on Eligible \nCustomers using necessary control technologies or protection \nsystems are not unduly discriminatory ......................................... 43"},{"page":4,"startToken":615,"endToken":852,"text":"ii \n3. \nDisqualification penalties that require Eligible Customers to \ntransition to taking NITS do not effectively deny service to Eligible \nCustomers and are a measured response ....................................... 47 \n4. \nThe Commission did not foreclose non-monetary penalties, \nparticularly where financial penalties alone are insufficient to \nsafeguard reliability ...................................................................... 49 \n5. \nRequiring disqualified Eligible Customers to take NITS on behalf \nof Co-Located Load enables necessary, proactive planning of the \nsystem to support reliable service ................................................. 52 \n6. \nRevisions to the Illustrative Tariff language address certain \nintervenors’ critiques of disqualification penalties ....................... 54 \nE. \nEffective Date ........................................................................................... 55 \n1. \nUpon Commission setting the terms and conditions for the new \ntransmission services, PJM can begin receiving requests for such \nservices and studying applications ................................................ 55 \n2. \nA June 1, 2029 effective date is required to procure capacity for the \ncapacity backed Firm Contract Demand Transmission Service ... 56 \n3. \nA June 1, 2029 effective date is required for the provision of these \nnew, curtailable services ............................................................... 57 \nF. \nIssues Beyond the Scope of This Proceeding ........................................... 58 \n1. \nAdvanced Energy United and Solar Energy Industries Association \nimproperly assert PJM should not study all interconnecting \ngenerators ...................................................................................... 58 \n2. \nThe Commission should ignore other issues raised that are beyond \nthe scope of this paper hearing ...................................................... 59 \nIII. \nREVISIONS TO ILLUSTRATIVE TARIFF FILED WITH INITIAL BRIEF..... 60 \nIV. \nADDITIONAL ILLUSTRATIVE TARIFF LANGUAGE TO INTEGRATE NEW \nTRANSMISSION SERVICES AND RESERVATION OF RIGHTS TO \nFURTHER SUPPLEMENT FILING .................................................................... 64 \nV. \nDOCUMENT ENCLOSED .................................................................................. 66 \nVI. \nCONCLUSION ..................................................................................................... 66"},{"page":5,"startToken":852,"endToken":1313,"text":"REPLY BRIEF OF PJM INTERCONNECTION, L.L.C. \n \nPJM Interconnection, L.L.C.’s (“PJM”) Initial Brief1 set forth just and reasonable \nterms and conditions for providing three new transmission services:  Interim Network \nIntegration Transmission Service (“NITS”), Firm Contract Demand Transmission Service, \nand Non-Firm Contract Demand Transmission Service.  As envisioned by the Show Cause \nOrder, these new services should allow Co-Located Loads to connect to the system and \nobtain transmission service faster than under the current paradigm,2 while adhering to two \nkey principles:  (1) the services are designed to serve loads that are “willing and able to \ncontrol their withdrawals from the transmission system;”3 and (2) the services are designed \nto allow PJM to maintain system reliability.4   \nPJM designed the new Interim NITS to basically be treated the same as regular, full \nNITS, except that the service would be curtailable prior to PJM initiating a pre-emergency \n \n1 PJM Interconnection, L.L.C., Initial Brief of PJM Interconnection, L.L.C., Docket Nos. EL25-49-000, et \nal. (Feb. 23, 2026) (“Initial Brief”).  PJM submitted its Initial Brief and this reply brief pursuant to \nparagraph 219 and ordering paragraphs (D) and (E) of the Order on Show Cause Proceeding, Directing \nCompliance Filings, Establishing Paper Hearing, and Granting in Part and Denying in Part Complaint issued \nby the Federal Energy Regulatory Commission (“FERC” or “Commission”) on December 18, 2025, in the \nabove-captioned proceeding.  PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“Show Cause \nOrder”); see also PJM Interconnection, L.L.C., Notice of Extension of Time, Docket Nos. EL25-49-000, et \nal., at 3 (Jan. 23, 2026) (granting a seven-day extension of the deadline in ordering paragraph (D) of the Show \nCause Order for PJM to submit its initial brief). \n2 See Show Cause Order, 193 FERC ¶ 61,217, at P 205 (“Parties further argue that Co-Located Loads may \nbe able to receive transmission service faster with use of a new, limited transmission service product than \nthey would if they selected NITS . . . .”). \n3 Show Cause Order, 193 FERC ¶ 61,217, at P 204. \n4 See, e.g., Show Cause Order, 193 FERC ¶ 61,217, at PP 201 (“[T]his new interim, non-firm transmission \nservice will facilitate the timely provision of transmission service to Eligible Customers taking transmission \nservice on behalf of Co-Located Loads, while preserving reliability for other transmission customers.”), 212 \n(“We also note that, as discussed in the briefing questions below, PJM will determine the technical and \nengineering requirements of special protection schemes to help address reliability risks associated with \nunreserved use of the transmission system.”), 227 (discussing requirement that would “provide additional \nclarity and transparency regarding the steps that PJM and Interconnection Customers are taking to maintain \ntransmission system reliability before an existing generating facility can serve Co-Located Load”)."},{"page":6,"startToken":1313,"endToken":1695,"text":"2 \nevent,5 i.e., dispatching the Pre-Emergency Load Response Program6 as further set forth in \nthe PJM Manuals,7 or in response to a transfer capability shortage.8  Interim NITS would \nonly be available consistent with PJM’s studies as to the level of such service that can be \nreliably provided, and would naturally and automatically transition to full NITS once the \nnecessary network upgrades go into service.9  This is fully consistent with the Show Cause \nOrder,10 as discussed below and in PJM’s Initial Brief. \nTo best implement the Show Cause Order and adhere to the two key principles, \nPJM designed the two Contract Demand Transmission Services to work together to provide \noptions beyond full NITS to Eligible Customers taking service on behalf of Co-Located \nLoads that are “willing and able to control their withdrawals from the transmission \nsystem.”11  PJM’s terms and conditions for the two Contract Demand Transmission \nServices allow for the portion of the Co-Located Load for which the Co-Located \nGenerating Facility will dedicate its output (in whole or in part) to be covered by Non-Firm \nContract Demand Transmission Service, but any portion of the gross demand of the Co-\nLocated Load not served by the Co-Located Generating Facility must be covered by Firm \n \n5 See Initial Brief at 67 (“Generally speaking, the non-rate terms and conditions for Interim NITS are the \nsame as for NITS . . . .”). \n6 Capitalized terms not otherwise defined herein have the meanings set forth in PJM’s Open Access \nTransmission Tariff (“Tariff”) or the Amended and Restated Operating Agreement of PJM Interconnection, \nL.L.C. (“Operating Agreement”). \n7 The Tariff provides that the Pre-Emergency Load Response Program is “the program by which Curtailment \nService Providers may be compensated by PJM for Demand Resources that will reduce load when dispatched \nby PJM during pre-emergency conditions, and is described in Operating Agreement, Schedule 1, section 8 \nand the parallel provisions of Tariff, Attachment K-Appendix, section 8.”  Tariff, Definitions – O – P - Q. \n8 See Illustrative Tariff, Part XI, Subpart B, section 713.4. \n9 See Illustrative Tariff, Part XI, Subpart A, section 701.1; Illustrative Tariff, Attachment F-3A; Initial Brief \nat 68, 75. \n10 See Show Cause Order, 193 FERC ¶ 61,217, at PP 200-03. \n11 Show Cause Order, 193 FERC ¶ 61,217, at PP 204, 206."},{"page":7,"startToken":1695,"endToken":2028,"text":"3 \nContract Demand Transmission Service.  This approach offers flexibility to Eligible \nCustomers to mix and match between Firm and Non-Firm Contract Demand Transmission \nService when taking service on behalf of Co-Located Load, so long as the combination of \nthe two services covers the entire gross demand of the Co-Located Load.  PJM’s approach \nalso ensures that there is the opportunity to take transmission service and withdraw energy \nfrom the grid even in the event a Co-Located Generating Facility is unable to provide \nenergy consistent with its dedicated quantity.   \nPJM included Illustrative Tariff language setting forth just and reasonable non-rate \nterms and conditions for each of these new transmission services to facilitate the \nCommission’s development of a replacement rate.  However, as PJM explained in its Initial \nBrief, integration of these new transmission services requires complex revisions to PJM’s \ntransmission planning, interconnection, and operational procedures, as well as PJM’s \nmarkets and settlements rules.  PJM continues to examine its Governing Documents to \nevaluate how to best integrate these new services.  This reply brief addresses comments \nand issues raised by other parties as to the appropriate terms and conditions for the new \ntransmission services. \nI. \nINTRODUCTION \nAs a Regional Transmission Organization (“RTO”) and North American Electric \nReliability Corporation (“NERC”) Reliability Coordinator, PJM’s core function is to \ndeliver energy to loads at least cost while maintaining system reliability.12  Thus, as the \n \n12 See, e.g., 18 C.F.R. § 35.34(j)(iv)(4) (“Short-term reliability.  The Regional Transmission Organization \nmust have exclusive authority for maintaining the short-term reliability of the grid that it operates.  The \nRegional Transmission Organization must include, as part of its demonstration with respect to reliability, a \ndemonstration that it meets the following:  (i) The Regional Transmission Organization must have exclusive \nauthority for receiving, confirming and implementing all interchange schedules. (ii) The Regional \nTransmission Organization must have the right to order redispatch of any generator connected to transmission \nfacilities it operates if necessary for the reliable operation of these facilities. (iii) When the Regional"},{"page":8,"startToken":2028,"endToken":2334,"text":"4 \nRTO and Transmission Provider for the PJM Region, PJM offers a unique perspective on \nthe design of new transmission services.   \nPJM’s Initial Brief set forth just and reasonable terms and conditions that provide \nthe multiple pathways envisioned by the Show Cause Order for Co-Located Loads to \ninterconnect to the grid and obtain transmission service faster than under the current \nparadigm, all while ensuring that PJM will be able to maintain system reliability.13  Parties \ncan achieve the benefits of co-location arrangements—faster interconnections to the \nsystem, reduced costs to interconnect (through fewer upgrades, or using existing and \nalready planned infrastructure, all else equal), at transmission rates that reflect their usage \nof the Transmission System—under terms and conditions in the Illustrative Tariff.   \nPJM has provided a framework for achieving these benefits while still allowing it \nto fulfill its core reliability functions.  PJM cannot sacrifice the reliable operation of the \nTransmission System overall to accommodate specific commercial interests.  The system \nis built and maintained for the benefit of all network loads in the PJM Region.  PJM must \nensure that new facilities and services are added to the system in a way that does not \nundermine reliability.  For example, PJM has processes in place for new generators to \ninterconnect with the Transmission System in a safe and reliable manner.14  So long as \n \nTransmission Organization operates transmission facilities owned by other entities, the Regional \nTransmission Organization must have authority to approve or disapprove all requests for scheduled outages \nof transmission facilities to ensure that the outages can be accommodated within established reliability \nstandards. . . .”). \n13 See generally Show Cause Order, 193 FERC ¶ 61,217. \n14 See generally Interconnection Projects Department, PJM Manual 14H: New Service Requests Cycle \nProcess, \nPJM \nInterconnection, \nL.L.C. \n(rev. \n03, \nSep. \n25, \n2025), \nhttps://www.pjm.com/-\n/media/DotCom/documents/manuals/m14h.pdf."},{"page":9,"startToken":2334,"endToken":2669,"text":"5 \nreliability is maintained, PJM is agnostic as to generation resource type, size, location, and \nownership.  The same is true for load.   \nSome parties allege that PJM’s terms and conditions would “render[] the new \ntransmission services commercially unworkable”15 and that PJM is “resisting” co-location \narrangements or “saying no to innovation.”16  These parties appear to posit uses of the \nTransmission System that differ from its design standards and that could require PJM to \noperate the Transmission System near its physical limits with a significantly reduced ability \nto deal with contingencies.  PJM’s terms and conditions are not the product of some ill-\nfounded resistance to change.  Rather, as the RTO and Reliability Coordinator, PJM must \noperate the Transmission System for the benefit of all loads.  And, PJM has identified a \nmeans to integrate these new transmission services to accommodate the desire to sidestep \nexisting transmission service procedures while being able maintain reliability—albeit at a \nreduced margin for error.  Given the critical importance of integrating the new services \nwhile maintaining reliability, PJM’s proposal fits the new services within the limitations of \nthe Transmission System. \n \n15 PJM Interconnection, L.L.C., Reply Brief of Joint Co-Location Developers and Motion to Intervene Out-\nof-Time of Calibrant Energy, Convergent Energy and Power, U.S. Energy Storage Coalition, and Verrus, \nLLC, Docket Nos. EL25-49-000, et al., at 2 (Mar. 25, 2026) (“Joint Co-Location Developers Reply Brief”); \nsee also PJM Interconnection, L.L.C., Reply Brief and Protest of Enchanted Rock, Docket Nos. EL25-49-\n000, et al., at 7-9 (Mar. 25, 2026) (“Enchanted Rock Reply Brief”) (arguing that PJM’s proposal “renders \nInterim NITS entirely unworkable”); PJM Interconnection, L.L.C., Reply Brief of Advanced Energy United \nand Solar Energy Industries Association, Docket Nos. EL25-49-000, et al., at 6 (Mar. 25, 2026) (“Advanced \nEnergy/SEIA Reply Brief”) (arguing PJM’s proposal “render[] the service commercially unworkable”).   \n16 PJM Interconnection, L.L.C., Reply Brief of Constellation Energy Generation, LLC, Docket Nos. \nEL25-49-000, et al., at 3 (Mar. 25, 2026) (“Constellation Reply Brief”)."},{"page":10,"startToken":2669,"endToken":3013,"text":"6 \nII. \nRESPONSE TO ISSUES RAISED IN REPLY BRIEFS  \nA. \nContract Demand Transmission Service \n1. \nNon-Firm Contract Demand Transmission Service will be available \nwhen the Co-Located Generating Facility is on outage  \nA number of parties argue that Non-Firm Contract Demand Transmission Service \nshould be generally available during normal system operations instead of limited to \ncircumstances where the Co-Located Generating Facility is on outage.17  PJM’s proposed \nlimitation, however, is just and reasonable, consistent with the scope of services \ncontemplated in the Show Cause Order, and appropriate given the nature of the new service \nlevel and reliability and operational issues inherent in providing this service on PJM’s \ncurrent Transmission System. \nThe Show Cause Order required PJM to develop three new transmission services:  \nNon-Firm Contract Demand Transmission Service, Firm Contract Demand Transmission \nService, and Interim NITS.18  Interim NITS is an inherently temporary service, as it is only \noffered as an interim measure while the system upgrades necessary for full NITS are being \nconstructed.19  Conversely, Firm and Non-Firm Contract Demand Transmission Service \nare  intended to provide a permanent alternative to NITS for customers that are willing and \nable to limit their energy withdrawals from the system.20  If customers were permitted to \ntake unlimited Non-Firm Contract Demand Transmission Service as some commenters \n \n17 See Joint Co-Location Developers Reply Brief at 3, 6-12; Advanced Energy/SEIA Reply Brief at 5-6. \n18 See Show Cause Order, 193 FERC ¶ 61,217, at P 206. \n19 Show Cause Order, 193 FERC ¶ 61,217, at P 200 (“We reiterate that this interim, non-firm transmission \nservice should be temporary—only available to Eligible Customers that have requested NITS on behalf of \nCo-Located Loads that cannot yet be reliably served with NITS—and available only until the necessary \nNetwork Upgrades are completed and the Co-Located Load is designated as Network Load.”).  \n20 See Show Cause Order, 193 FERC ¶ 61,217, at P 206 (“These new transmission services will serve as \npermanent alternatives to existing transmission services, unlike the new interim, non-firm transmission \nservice described above in Part IV.B.45.b.ii.”)."},{"page":11,"startToken":3013,"endToken":3365,"text":"7 \nsuggest, this would be tantamount to PJM offering a permanent Interim NITS, which was \nnot contemplated by the Show Cause Order.21  The Show Cause Order specified that the \nNon-Firm Contract Demand Transmission Service would be available to customers “as \nneeded”22 for customers that are able to limit their withdrawals from the system, which \nsuggests that the Commission did not intend for this service to be a product that is used on \nan everyday basis up to 8,760 hours per year.23  Accordingly, PJM reasonably limited this \nservice to outage or temporary derate conditions consistent with the requirements of the \nShow Cause Order. \nIn addition to the requirements of the Show Cause Order, PJM appropriately limited \nNon-Firm Contract Demand Transmission Service to circumstances where the Co-Located \nGenerating Facility is on temporary derate or outage given the inherent risks to the \nTransmission System and operational complexities associated with providing this service \non a continuous basis, given the limited period the non-firm service will be required.  Put \nsimply, the Transmission System was not and will not be planned and designed to \naccommodate these non-firm services under the NERC reliability standards.  Therefore, \nproviding these services continuously, rather than on a limited duration and condition basis, \nincreases system reliability risks.   \n \n21 See Show Cause Order, 193 FERC ¶ 61,217, at P 206. \n22 Show Cause Order, 193 FERC ¶ 61,217, at P 215 (emphasis added). \n23 Show Cause Order, 193 FERC ¶ 61,217, at P 214 (“Eligible Customers taking service on behalf of such \nloads may, however, still seek to withdraw energy from the transmission system from time to time when \ntransmission capacity is available and not needed by firm customers.  For example, an Eligible Customer \ncould seek a transmission reservation for a Co-Located Load in advance for the duration of an expected \noutage of the associated generator.”); id. concur op. (Commissioner Rosner) at P 6 (“The data center may \ninstead elect to purchase Non-Firm Contract Demand Transmission Service if, for example, it only plans to \npull energy from the grid temporarily while its co-located generator is undergoing scheduled maintenance \n(see Figure 3).”)."},{"page":12,"startToken":3365,"endToken":3665,"text":"8 \nThe NERC reliability standards require PJM to engage in system planning on a \nrange of time horizons.24  For long-term planning, the NERC reliability standards require \nPJM to model and assess the Transmission System at least annually looking at expected \nperformance over the next several years.25  As part of this evaluation, PJM must conduct a \nplanning assessment to evaluate how the system will perform under peak conditions, \nincluding a sensitivity analysis to evaluate how the system will perform when different \naspects of the analysis are changed to stress the system model (e.g., real and reactive load \nforecast, expected transfers, etc.).26  If the results of the Planning Analysis demonstrate that \nthe system will not meet performance requirements, PJM is then required to include a \nCorrective Action Plan to address how the performance requirements will be met.27  This \nCorrective Action Plan may include the installation, modification, or removal of \nTransmission or generation facilities, protection schemes, or installation or modification of \nautomatic generation runback to achieve system performance.28  The Corrective Action \nPlan may also utilize Operating Procedures necessary to achieve system performance, \nprovided the plan specifies how long the Operating Procedures will be needed.29  This long-\nterm planning is designed to ensure that the Transmission System can operate reliably \nunder a range of system conditions.  \n \n24 See TPL-001-5.1, Transmission System Planning Performance Requirements, North American Electric \nReliability \nCorporation \n(June \n12, \n2025), \nhttps://www.nerc.com/globalassets/standards/reliability-\nstandards/tpl/tpl-001-5.1.pdf (“NERC Standard TPL-001-5.1”). \n25 See NERC Standard TPL-001-5.1. \n26 See NERC Standard TPL-001-5.1 at R2.2.1. \n27 See NERC Standard TPL-001-5.1 at R2.2.7. \n28 See NERC Standard TPL-001-5.1 at R2.2.7.1. \n29 See NERC Standard TPL-001-5.1 at R2.2.7.1."},{"page":13,"startToken":3665,"endToken":4033,"text":"9 \nIn the operational time frame, PJM is obligated to establish and operate the system \nwithin System Operating Limits (“SOLs”) and Interconnection Reliability Operating \nLimits (“IROLs”) under various NERC Standards.30  For example, PJM is required to have \na methodology for setting SOLs for operations that respect the various facility ratings and \nSystem Voltage Limits.31  As part of this, PJM is required to specify stability performance \ncriteria, including required margins for operations.32  PJM must also assess whether \nplanned operations for the next-day will exceed the SOLs and IROLs within its Wide Area \nand make Operating Plans to address these potential exceedances.33  PJM is also required \nto implement its Operating Plans to mitigate system emergencies if they arise.34  \nGiven the range of requirements of the NERC reliability standards, several aspects \nof Non-Firm Contract Demand Transmission Service make the provision of this service \nchallenging from a reliability perspective.  First, the nature of Non-Firm Contract Demand \nTransmission Service dictates that PJM will not include this service in PJM’s long-term \n \n30 See, e.g., FAC-011-04, System Operating Limits Methodology for the Operations Horizon, North American \nElectric Reliability Corporation (Dec. 9, 2025), https://www.nerc.com/globalassets/standards/reliability-\nstandards/fac/fac-011-4.pdf (“NERC Standard FAC-011-04”); FAC-014-3, Establish and Communicate \nSystem Operating Limits, North American Electric Reliability Corporation (Dec. 9, 2025), \nhttps://www.nerc.com/globalassets/standards/reliability-standards/fac/fac-014-3.pdf; \nTOP-001-6, \nTransmission Operations, North American Electric Reliability Corporation (June 12, 2025), \nhttps://www.nerc.com/globalassets/standards/reliability-standards/top/top-001-6.pdf; \nTOP-002-5, \nOperations \nPlanning, \nNorth \nAmerican \nElectric \nReliability \nCorporation \n(June \n12, \n2025), \nhttps://www.nerc.com/globalassets/standards/reliability-standards/top/top-002-5.pdf \n(“NERC \nStandard \nTOP-002-5”); IRO-006-5, Reliability Coordination — Transmission Loading Relief, North American Electric \nReliability \nCorporation \n(June \n12, \n2025), \nhttps://www.nerc.com/globalassets/standards/reliability-\nstandards/iro/iro-006-5.pdf; IRO-008-3, Reliability Coordinator Operational Analyses and Real-time \nAssessments, \nNorth \nAmerican \nElectric \nReliability \nCorporation \n(Dec. \n4, \n2025), \nhttps://www.nerc.com/globalassets/standards/reliability-standards/iro/iro-008-3.pdf (“NERC Standard IRO-\n008-3”). \n31 See NERC Standard FAC-011-04.  \n32 See NERC Standard FAC-011-04.  \n33 See NERC Standard IRO-008-3.  \n34 See EOP-011-4, Emergency Operations, North American Electric Reliability Corporation (June 12, 2025), \nhttps://www.nerc.com/globalassets/standards/reliability-standards/eop/eop-011-4.pdf."},{"page":14,"startToken":4033,"endToken":4299,"text":"10 \ntransmission planning (i.e., the Regional Transmission Expansion Plan) and the system will \nnot be evaluated for potential Corrective Action Plans nor will PJM have procured capacity \nto serve this load.  Requests for Non-Firm Contract Demand Transmission Service will \noccur in the operations time horizon because an Eligible Customer is likely to request this \nservice when the Co-Located Generating Facility faces either a planned or unplanned \noutage condition requiring load withdrawals from the Transmission System exceeding their \ncontracted Firm Contract Demand Transmission Service level.  The ability of the system \nto accommodate this service will depend on the system conditions at the time of the request \nand any constraints that may arise regarding energy and reliability.  For energy, the Co-\nLocated Generating Facility’s outage may coincide with high demand conditions on the \nTransmission System or where system conditions otherwise (e.g., seasonal outages) may \nnot allow such transmission service or energy to be offered reliably.  With regard to \nreliability, the transmission network conditions, including any ongoing transmission \noutages for maintenance or construction may prevent reliable service at the level requested.  \nPJM will need to perform an assessment for each service request to identify the level of \nservice that can be provided for the relevant timeframe.  In essence, Non-Firm Contract \nDemand Transmission Service is intended to provide whatever level of service the \nTransmission System can reliably accommodate at that snapshot in time without any \nadvanced planning for transmission or capacity.   \nWhen load that has not been planned for from a capacity or transmission \nperspective takes service from the grid, this erodes the system safeguards that help ensure"},{"page":15,"startToken":4299,"endToken":4619,"text":"11 \nreliable operations under N-1 conditions and more severe contingencies.35  As part of its \ntransmission planning, to ensure that the system can reliably meet expected operating \ndemands while respecting system limits, PJM looks at a range of operating conditions, \nincluding summer peak, winter peak, and light load conditions.36  As part of this planning \nprocess, PJM builds the system to accommodate different contingencies.37   \nBecause Non-Firm Contract Demand Transmission Service relies on not-currently \nused Transmission System capacity, PJM is unlikely to be in a position to provide Non-\nFirm Contract Demand Transmission Service during peaks or other times when the system \nis operating under stressed conditions (otherwise, PJM would need to expand the \nTransmission System, which would be contrary to the logic underlying this transmission \nservice).  During off-peak shoulder months, the Transmission System is often constrained \nby generators taking planned outages.  And, from a generation capacity perspective, \nplanned outages during off-peak shoulder months can lead to tight conditions.  For \nexample, during the period of April 14-16, 2026, PJM declared a Hot Weather Alert for \nmuch of the PJM Region, expecting loads from 109,000 megawatts (“MW”) to 114,000 \nMW.  During this period, there were originally 54,000 MW of installed capacity that was \nscheduled to be on planned outage.38  Due to the forecasted load, 12,500 MW of the planned \noutages were deferred.  For reference the 2025/2026 Base Residual Auction cleared just \n \n35 See NERC Standard TPL-001-5.1.  While this is also true for Interim NITS, the temporary nature of such \ntransmission service, and the fact that the Transmission System will be built to accommodate such demands \ngenerally alleviates the concern. \n36 Initial Brief, Affidavit of Matthew Wharton (Attachment C) ¶ 13 (“Wharton Aff.”). \n37 Wharton Aff. ¶ 13. \n38 \nSee \nGeneration \nOutage \nfor \nSeven \nDays \nby \nType, \nPJM \nInterconnection, \nL.L.C., \nhttps://dataminer2.pjm.com/feed/gen_outages_by_type/definition (last visited Apr. 23, 2026)."},{"page":16,"startToken":4619,"endToken":4904,"text":"12 \nover 135,000 MW (Unforced Capacity).39  As this illustrates, even during shoulder periods, \nthere may not be a large surplus of generation or transmission capacity sitting idle to \naccommodate Non-Firm Contract Demand Transmission Service.  Therefore, from a \ntransmission planning perspective, Non-Firm Contract Demand Transmission Service \nincreases the operational risk of SOL/IROL exceedances by operating the system with a \nreduced margin for contingency to accommodate high-volume loads.  This increases the \nrisk of an emergency occurring if unexpected conditions occur (e.g., unusual weather \npatterns, loss of multiple facilities, local area oscillations, and/or voltage swings, etc.). \nFrom an operational perspective, consistent with the NERC requirements, PJM \nconducts Operational Planning Analysis a day ahead to address potential SOL/IROL \nexceedances with an Operating Plan.40  Consistent with Good Utility Practice and the \nNERC reliability standards, PJM operates the Transmission System within the \nSOLs/IROLs and facility ratings.41  PJM’s provision of the Non-Firm Contract Demand \nTransmission Service, however, will almost inevitably require the significant adjustments \nto PJM’s Operating Plan to mitigate exceedances of SOLs/IROLs each time service is \nprovided due to the nature of the service.42  PJM plans the Transmission System to move \nelectricity from where it is generated to the load that needs it.  By definition, Non-Firm \nContract Demand Transmission Service involves a customer drawing large quantities of \npower over transmission facilities that were not designed to serve that load and thus will \n \n39 2025/2026 Base Residual Auction Report, PJM Interconnection, L.L.C., 3 (July 30, 2024), \nhttps://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2025-2026/2025-2026-base-\nresidual-auction-report.pdf. \n40 NERC Standard IRO-008-3 at R1, R2, R4, R7. \n41 See NERC Standard TOP-002-5.  \n42 See Wharton Aff. ¶ 22."},{"page":17,"startToken":4904,"endToken":5292,"text":"13 \nalmost certainly necessitate flowing power over various facilities near system limits.  As a \nresult, PJM limited the availability of Non-Firm Contract Demand Transmission Service \nto circumstances where the Co-Located Generating Facility is on outage or temporary \nderate, as determined in accordance with the PJM Manuals,43 to limit the risk to the \nTransmission System consistent with Good Utility Practice and the NERC reliability \nstandards. \n2. \nProvision of Non-Firm Contract Demand Transmission Service \nContrary to Vistra Corp.’s (“Vistra”) assertions, Non-Firm Contract Demand \nTransmission Service is not easy to implement from an operations perspective, particularly \nat scale, and in addition to exposing the system to higher reliability risks, will also require \nPJM to modify key systems.44  As previously explained, the provision of Non-Firm \nContract Demand Transmission Service will require significant changes to PJM’s core \nMarkets and Operations systems, including the Intermediate and Real-time Security \nConstrained Economic Dispatch, the Day-ahead Market software, and PJM dispatch \ntools.45  This is not simply about changes for Curtailment of Non-Firm Contract Demand \nTransmission Service.  Rather, changes to the Energy Management System are needed to \n \n43 See Operations Planning Division, PJM Manual 14D: Generator Operational Requirements, PJM \nInterconnection, \nL.L.C. \n(rev. \n70, \nDec. \n17, \n2025), \nhttps://www.pjm.com/-\n/media/DotCom/documents/manuals/m14d.pdf. \n44 Those co-location arrangements Vistra discusses that want “no service” from the grid should island.  \nConnections to the grid—whether by generators or by load—must be studied to ensure necessary \naccommodations are made (e.g., transmission upgrades) in order to maintain reliability.  New loads cannot \nsimply connect, regardless of whether they intend to take little to no service; the grid must be planned to \nensure it can handle serving those loads without jeopardizing reliability of others.  PJM Interconnection, \nL.L.C., Response Brief of Vistra Corp., Docket Nos. EL25-49-000, et al., at 12-13 (Mar. 25, 2026) (“Vistra \nReply Brief”) (“If a customer elects [regulation and black start services only], the Non-Firm Contract \nDemand Transmission Service associated with that co-location arrangement consists of ex post invoicing of \ncharges for regulation and black start services . . . .  That should not be difficult to implement, particularly \ngiven that the black start and regulation services will be based on gross load, which customers will be required \nto report.”).   \n45 See Initial Brief, Affidavit of Timothy Horger (Attachment D) ¶ 16 (“Horger Aff.”)."},{"page":18,"startToken":5292,"endToken":5573,"text":"14 \nensure that PJM’s systems are able to properly account for the provision of energy to the \nCo-Located Load in the Day-ahead and Real-time Market and to determine when \nCurtailment may be necessary.  Incorporating Co-Located Load into these systems is no \nsimple task.  Indeed, it is particularly challenging to model contingencies associated with \nnon-firm loads that the Transmission System was not designed and built to accommodate.     \nCurrently, PJM’s Energy Management System does not have the ability to \ndistinguish between different types of load.  This capability must be added to the Energy \nManagement System to allow PJM to evaluate when to curtail Co-Located Load before \nimplementing emergency procedures.  In addition, PJM must determine how to properly \nmodel and reflect Non-Firm Contract Demand Transmission Service and Co-Located Load \nin the different systems given that Non-Firm Contract Demand Transmission Service \nrequires the Transmission System to operate on reduced contingency margins.  Finally, \nbecause PJM will have to rely on Operating Plans for Non-Firm Contract Demand \nTransmission Service, PJM must be able to “dispatch” (i.e., curtail) Non-Firm Contract \nDemand Transmission Service with little to no advance notification to respond to \nsignificant SOL/IROL exceedances.46  This will require significant modifications to the \nmarket clearing engines utilized in both the Day-ahead and Real-time Markets.  These \nmodifications must be carefully developed and tested to ensure there are no adverse \nimpacts to other market participants. \nEven after PJM’s systems are updated to incorporate Non-Firm Contract Demand \nTransmission Service, the provision of this service will still be challenging from an \n \n46 Transmission Operations, PJM Manual 3: Transmission Operations, PJM Interconnection, L.L.C., § 2 \n(rev. 70, Mar. 4, 2026), https://www.pjm.com/-/media/DotCom/documents/manuals/m03.pdf."},{"page":19,"startToken":5573,"endToken":5878,"text":"15 \noperational perspective.  PJM’s systems must not only accurately reflect how Non-Firm \nContract Demand Transmission Service affects the system, but also PJM must account for \nthis service in the Operating Plans, including potential SOL/IROL exceedances, and then \nimplement those plans manually when needed in real time.  When PJM is creating an \nOperating Plan from the Day-ahead Market, it will address SOL/IROL exceedances with \nswitching solutions, generation changes, and system changes (e.g., putting reactive devices \nin service).  Because the system is not designed to accommodate Non-Firm Contract \nDemand Transmission Service, it will likely trigger many more SOL/IROL exceedances \nfor PJM to mitigate in the Operating Plan and require operations at or near operating limits.  \nAs a result, the system will have less flexibility to respond to unexpected changes during \noperations.  For example, if a storm moves through an area and trips multiple facilities, \nPJM may be facing several unexpected SOL exceedances and will need to rapidly \nimplement manual actions to restore the system to a stable state.  When Non-Firm Contract \nDemand Transmission Service is taking service from the grid, it is very likely that it will \nbe significantly contributing to these exceedances because the system was not reinforced \nto accommodate the additional load.  As a result, it will be imperative that these loads can \nbe removed from the system as soon as possible in addition to the other activities that the \nPJM operator needs to undertake, such as generation redispatch, utilization of emergency \nback-up plans, etc. which entail voice-to-voice communication with generation and \ntransmission owners to implement.  Non-Firm Contract Demand Transmission Service \nintroduces another entity that PJM will need to coordinate with during this chain of events, \nwhich will inevitably lengthen the time it takes to restore the system to a stable state and \navoid additional damage to equipment and/or reliability."},{"page":20,"startToken":5878,"endToken":6240,"text":"16 \nOnce PJM determines how to incorporate Non-Firm Contract Demand \nTransmission Service into its systems, PJM will need additional language in its Tariff and \nPJM Manuals to operationalize requests for service.  PJM is still evaluating appropriate \nTariff language to do this, and reserves the right to further supplement the record in this \nproceeding if and when PJM develops such Tariff language.  For example, PJM will need \ntariff language that reflects the time needed for PJM to evaluate requests for Non-Firm \nContract Demand Transmission Service and the tools that will be utilized.  Finally, given \nthe system risks associated with the provision of this service, the Tariff must be clear that \nPJM has full discretion to curtail this service.  PJM believes the Connect and Manage \nSenior Task Force will significantly inform these issues.47 \nB. \nInterim NITS Customers Should Not Be Allowed Access to Co-Located \nGeneration when PJM Has Curtailed the Load  \nSeveral entities commented that the Commission should allow Eligible Customers \ntaking Interim NITS the ability to draw energy from the Co-Located Generating Facility \nwhen the Eligible Customer is curtailed and the Co-Located Load is no longer allowed to \ndraw energy from the Transmission System.48  The Show Cause Order suggested such \nopportunity may be available, but only “if PJM’s Tariff otherwise allows.”49  Thus, in \nresponse to the Show Cause Order’s suggestion and at the urging of stakeholders, PJM \nthoroughly examined whether the Tariff should allow Interim NITS customers to directly \n \n47 \nSee \nConnect \nand \nManage \nSenior \nTask \nForce, \nPJM \nInterconnection, \nL.L.C., \nhttps://www.pjm.com/committees-and-groups/task-forces/camstf (last visited Apr. 22, 2026). \n48 Advanced Energy/SEIA Reply Brief at 19; Joint Co-Location Developers Reply Brief at 18; Enchanted \nRock Reply Brief at 7-8; PJM Interconnection, L.L.C., Response of the Data Center Coalition, Docket Nos. \nEL25-49-000, et al., at 3-4 (Mar. 25, 2026) (“Data Center Coalition Response”). \n49 Show Cause Order, 193 FERC ¶ 61,217, at P 201 (“We further note that, when curtailed, Eligible Customers \ntaking this transmission service on behalf of Co-Located Loads may be able to continue to take energy from \nthe Interconnection Customer with which they are co-located if PJM’s Tariff otherwise allows.”)."},{"page":21,"startToken":6240,"endToken":6662,"text":"17 \ntake energy from the Co-Located Generating Facility when PJM has curtailed the Eligible \nCustomer’s access to the Transmission System.50  PJM determined that the answer is no, \nfor the several reasons discussed below. \nOne, as directed by the Show Cause Order, Interim NITS (as well as the Contract \nDemand Transmission Services) must be designed based on two key principles:  (1) the \nservices are designed to serve loads that are “willing and able to control their withdrawals \nfrom the transmission system;”51 and (2) the services are designed to allow PJM to \nmaintain system reliability.52  Consistent then are PJM’s Illustrative Tariff provisions which \ncall for the Curtailment of Interim NITS prior to dispatching PJM’s Pre-Emergency Load \nResponse Program, i.e., before Demand Response resources are called upon to reduce load \nto stave off emergency procedures, or in response to a transfer capability shortage as a \nresult of system reliability conditions.53  As such, the instances in which Curtailment would \noccur are when there are serious reliability issues facing the Transmission System.  Stated \nsimply, Interim NITS will be curtailed when the system cannot support it in real time, \nwhether with sufficient generation or transmission capacity.54   \n \n50 Indeed, PJM discussed this specific issue with stakeholders at a March 16, 2026 workshop.  See Co-Located \nLoad Use Cases: Co-Located Load Order Workshop, PJM Interconnection, L.L.C., 12 (Mar. 16, 2026), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/workshops/cllsco/2026/20260316/20260316-\nitem-02---co-located-load-use-cases---presentation.pdf.  \n51 Show Cause Order, 193 FERC ¶ 61,217, at P 204. \n52 See, e.g., Show Cause Order, 193 FERC ¶ 61,217, at PP 201 (“[T]his new interim, non-firm transmission \nservice will facilitate the timely provision of transmission service to Eligible Customers taking transmission \nservice on behalf of Co-Located Loads, while preserving reliability for other transmission customers.”), 212 \n(“We also note that, as discussed in the briefing questions below, PJM will determine the technical and \nengineering requirements of special protection schemes to help address reliability risks associated with \nunreserved use of the transmission system.”), 227 (discussing requirement that would “provide additional \nclarity and transparency regarding the steps that PJM and Interconnection Customers are taking to maintain \ntransmission system reliability before an existing generating facility can serve Co-Located Load”). \n53 See Illustrative Tariff, Part XI, Subpart A, section 705.2; see Initial Brief at 63-64, 71-73. \n54 Curtailment in advance of pre-emergency procedures is consistent with the Show Cause Order’s directive \nthat Interim NITS customers would “avoid paying generator capacity costs in return for their willingness to"},{"page":22,"startToken":6662,"endToken":7036,"text":"18 \nTwo, such an outcome would remove the co-located generator from serving the \nTransmission System as a whole during emergency or pre-emergency conditions—times \nwhen PJM needs all resources at its disposal to maintain reliability.  PJM would endeavor \nto dispatch all network resources—as well as all other generation resources on the \nsystem—to the maximum extent possible to reduce the likelihood of Interim NITS \nCurtailment.  Indeed, PJM would dispatch the co-located generator to minimize any \ntransmission constraints on the system, including any constraints that would cause the Co-\nLocated Load to be curtailed, reducing the risk of Curtailment for transmission reliability.  \nBut, Interim NITS must be designed to allow PJM to maintain system reliability—both \nfrom a transmission and capacity perspective,55 and allowing an interruptible customer to \npreclude PJM from accessing a generation resource during times of system stress would be \ncontrary to that objective, and could undermine reliability of the PJM Region. \nFurther, to the extent the co-located generator is a committed Capacity Resource, \nthe PJM Region has first call on such resource’s energy to meet the region’s needs.  There \nshould not be a situation where the co-located generator is allowed to make the economic \nchoice of meeting its capacity commitment and performing to serve the region as a whole, \nor incurring Performance Assessment Charges to serve the Co-Located Load.  Allowing \n \ncurtail their withdrawals in advance of emergency condition” and such “willingness to curtail would \npotentially allow them to obtain service more quickly.”  Show Cause Order, 193 FERC ¶ 61,217, at P 201. \n55 See, e.g., Show Cause Order, 193 FERC ¶ 61,217, at PP 201 (“[T]his new interim, non-firm transmission \nservice will facilitate the timely provision of transmission service to Eligible Customers taking transmission \nservice on behalf of Co-Located Loads, while preserving reliability for other transmission customers.”), 212 \n(“We also note that, as discussed in the briefing questions below, PJM will determine the technical and \nengineering requirements of special protection schemes to help address reliability risks associated with \nunreserved use of the transmission system.”), 227 (discussing requirement that would “provide additional \nclarity and transparency regarding the steps that PJM and Interconnection Customers are taking to maintain \ntransmission system reliability before an existing generating facility can serve Co-Located Load”)."},{"page":23,"startToken":7036,"endToken":7321,"text":"19 \nsuch an economic choice to occur would be contrary to the Show Cause Order’s key \nprinciples for offering these new transmission services.   \nInterim NITS, under normal, non-emergency conditions would be directly supplied \nfrom the Co-Located Generating Facility (without exposure to transmission constraints) so \nlong as that is the economic resource to serve the load.  This is due to the physics of the \nconnection.  The risk exposure to Interim NITS in terms of Curtailment is limited primarily \nby the conditions where:  (1) PJM cannot “reliably” supply any additional withdrawals \nfrom the network beyond the output of the Co-Located Generating Facility; or (2) PJM is \nexperiencing system-wide resource emergency conditions.  For the first condition, the Co-\nLocated Load would have to be curtailed regardless to a net-zero exchange at the Point of \nInterconnection, limiting its withdrawal from the Transmission System.  Given that the first \ncondition relates to transmission reliability risk, the Co-Located Load would still have \ndirect, physical access to the output of the Co-Located Generating Facility.  For the second \ncondition, given that the Interim NITS-served Co-Located Load is not backed by any \ncapacity procurement, such load cannot obtain preferential access to the Co-Located \nGenerating Facility, which has capacity obligations to PJM. \nThree, as a type of Network Integration Transmission Service, Interim NITS is \nserved by the pool of network resources and not any one “dedicated” resource, particularly \nnot resources that would facilitate the provision of network integration service on a net \nbasis.  As PJM explained in its Initial Brief, “[g]enerally speaking, the non-rate terms and \nconditions for Interim NITS are the same as for NITS,56 with modifications necessary to \n \n56 Compare Illustrative Tariff, Part XI, Subpart A, sections 700-07, with Tariff, Part III."},{"page":24,"startToken":7321,"endToken":7683,"text":"20 \nimplement the interim and non-firm nature of the service.”57  And, PJM intends to service \nInterim NITS and NITS loads in the same manner—up until there are system reliability \nissues that require Curtailment of Interim NITS.  As such, PJM would serve Interim NITS \nloads through its security constrained economic dispatch (both day-ahead and in real-time) \nin the exact same manner it serves its NITS loads today.  Said another way, all generating \nresources that are available (i.e., not on outage or otherwise unable to be brought on-line \nin a timely manner) will be utilized to serve the Interim NITS customer.  The Interim NITS \ncustomer would only be curtailed after these actions are taken and if the system is in an \nunreliable state due to transmission system violations or capacity/reserve shortages.  If the \ncustomer was not curtailed solely due to its proximity to the Co-Located Generating \nFacility, the system would not be in a reliable state, which would jeopardize equipment and \nreliability. \nThis is in stark contrast to co-location arrangements under Contract Demand \nTransmission Services, where the Co-Located Generating Facility would “dedicate” a MW \nlevel of output to the Co-Located Load, i.e., the Co-Located Load would therefore be able \nto take energy from the Co-Located Generating Facility without concern for Curtailment \ndue to system issues.  Allowing an Interim NITS-served Co-Located Load to take energy \nfrom the Co-Located Generating Facility during Curtailment would allow the Interim NITS \ncustomer to effectively transform its service to something akin to Contract Demand \nTransmission Service at times when the system is stressed.  But, if the Co-Located Load \n \n57 Initial Brief at 67.  This is consistent with the Show Cause Order’s directive that Interim NITS is designed \nto merely be a transition service until the system can support the customer’s NITS request.  See Show Cause \nOrder, 193 FERC ¶ 61,217, at P 200 (“We reiterate that this interim, non-firm transmission service should be \ntemporary—only available to Eligible Customers that have requested NITS on behalf of Co-Located Loads \nthat cannot yet be reliably served with NITS—and available only until the necessary Network Upgrades are \ncompleted and the Co-Located Load is designated as Network Load.”)."},{"page":25,"startToken":7683,"endToken":8056,"text":"21 \nwants to avoid relying on the Transmission System to meet its energy needs during times \nof system stress and instead rely on the Co-Located Generator, then it should sign up for \nNon-Firm Contract Demand Transmission Service where the co-located generator has no \nobligation to serve PJM system load.58 \nFour, such an outcome would be illogical.  Interim NITS is predicated on the Co-\nLocated Load’s “willingness to curtail.”59  Allowing an Interim NITS-served Co-Located \nLoad access to the Co-Located Generating Facility for its own individual use during times \nof system stress would be wholly contrary to that foundational element of the Show Cause \nOrder’s justification for Interim NITS.  Instead of curtailing to help address the system \nreliability issue, the Interim NITS customer would be allowed to continue drawing energy \nfrom a resource connected to the system.  Further, it would be illogical to grant this right \nto the transitional, temporary Interim NITS when such right is not available to full NITS \ncustomers.60 \n \n58 See Show Causer Order, 193 FERC ¶ 61,217, at P 196 (“The Commission explained that its existing policy \nalready provides customers with the opportunity to reduce network service costs to the extent a customer is \nnot relying on the transmission system to meet its energy needs (i.e., by taking [Point-to-Point Service] \ninstead of NITS).”) (citing Preventing Undue Discrimination and Preference in Transmission Service, Order \nNo. 890, 118 FERC ¶ 61,119, at P 1619, order on reh’g, Order No. 890-A, 121 FERC ¶ 61,297 (2007), order \non reh’g & clarification, Order No. 890-B, 123 FERC ¶ 61,299 (2008), order on reh’g & clarification, Order \nNo. 890-C, 126 FERC ¶ 61,228, order on clarification, Order No. 890-D, 129 FERC ¶ 61,126 (2009)). \n59 Show Cause Order, 193 FERC ¶ 61,217, at P 201. \n60 See Show Cause Order, 193 FERC ¶ 61,217, at P 196 (explaining that it is unlawful for NITS customers to \nnet dedicated generation and that “‘splitting a discrete load is antithetical to the concept of network service’ \nbecause ‘a load at a discrete point of delivery cannot be partially integrated—it is either fully integrated or \nnot integrated’” (quoting Order No. 888-A, 78 FERC ¶ 61,220, 1996–2000 FERC Stats. & Regs., Regs. \nPreambles ¶ 31,048, at 30,262))."},{"page":26,"startToken":8056,"endToken":8350,"text":"22 \nC. \nThe Illustrative Tariff Properly Details How PJM Will Study Requests for \nNew Transmission Services and Determine the Level of Service that Can \nBe Reliably Provided  \nSeveral entities commented that PJM’s Illustrative Tariff provisions do not provide \nsufficient detail surrounding the processes through which PJM will study requests for \nInterim NITS and Contract Demand Transmission Services.61  In particular, Vistra and \nConstellation Energy Generation, LLC (“Constellation”) complain that the Illustrative \nTariff provisions62 reserve too much discretion to PJM and the applicable PJM \nTransmission Owner(s),63 lack sufficient detail,64 and “allow for the perpetuation of \nexisting discrimination, delays, tying, and encumbrances of large load configurations by \nTransmission Owners.”65  These claims lack merit.  As discussed below, the Illustrative \nTariff provisions appropriately detail PJM’s process, role, and standards for studying \nrequests for these new transmission services to serve load.  Further, PJM will work with \nstakeholders to develop implementation details for such study process, which will be set \nforth in the PJM Manuals.   \n \n61 Vistra Reply Brief at 31-32; Constellation Reply Brief at 14-15; Advanced Energy/SEIA Reply Brief at 15-\n16. \n62 See Initial Brief, Illustrative Tariff, Part XI, Subpart A, section 704 (Study Procedures for Interim Network \nIntegration Transmission Service Requests) and Subpart B, section 712 (Study Procedures for Contract \nDemand Transmission Service). \n63 Vistra Reply Brief at 31-38. \n64 Constellation Reply Brief at 14-16. \n65 Constellation Reply Brief at 15-16.  For their part, the PJM Transmission Owners contend that the Tariff \nshould specify the sequencing of studies as between PJM and the applicable PJM Transmission Owner(s), \nsuch that the Transmission Owner’s load integration study should be completed first.  Joint Response of \nIndicated PJM Transmission Owners, Docket Nos. EL25-49-000, et al., at 6 (Mar. 25, 2026) (“Indicated PJM \nTransmission Owners Response”)."},{"page":27,"startToken":8350,"endToken":8706,"text":"23 \n1. \nThe Illustrative Tariff provisions regarding transmission studies and \ndetermination of service build from existing Tariff provisions \nTo accommodate the new transmission services directed by the Show Cause Order, \nPJM has built on its existing processes for studying requests for new transmission services \nto serve loads within the PJM Region (as distinct from transmission service to PJM’s \nborders), with additional processes necessary to study the novel aspects of Interim NITS \nand Firm and Non-Firm Contract Demand Transmission Services.   \nCurrently, in PJM, the Transmission Owners study in the first instance all requests \nto connect new loads to the transmission system (as opposed to transmission service to the \nborder), and entities requesting new transmission service to serve such loads must apply \nfor NITS from PJM.66  For each Zone, the Transmission Owner studies the integration of \nthe requested load and identifies upgrades (i.e., Supplemental Projects) necessary to \naccommodate the new loads’ demands on the transmission system.  PJM then performs \nwhat is commonly referred to as a “do no harm” analysis, which analyzes how those \nTransmission Owner-identified upgrades would affect the regional Transmission System, \ni.e., the Bulk Electric System, and ensure the integration of the new load and associated \ntransmission upgrades do not cause harm to the PJM interconnected transmission system.  \nFor this, PJM looks at how the Transmission Owner-identified facilities needed to serve \nthe load interact with the current-year Regional Transmission Expansion Plan (“RTEP”) \n \n66 This is generally true across the country.  See, e.g., Interconnection of Large Loads to the Interstate \nTransmission System, Initial Comments of the MISO Transmission Owners, Docket No. RM26-4-000, at 5 \n(Nov. 21, 2025) (“MISO Transmission Owners Initial Comments”) (“The interconnection of load to the \ntransmission system, regardless of size, is largely a matter of state jurisdiction.  As such, the transmission \nowner, load serving entity (“LSE”), and the load owner play lead roles in managing and interconnecting load \nto the transmission system.  Specifically, the load owner seeking to interconnect to [Midcontinent \nIndependent System Operator, Inc.’s (“MISO”)] transmission system coordinates with the appropriate \ntransmission owner and LSE, which are the same entity in a large part of the MISO region.”)."},{"page":28,"startToken":8706,"endToken":9215,"text":"24 \nbase case, NERC’s transmission planning criteria, and the Transmission Owners’ FERC \nForm 715 planning criteria, as applicable, to determine whether any further upgrades are \nnecessary to integrate those facilities while maintaining reliability or whether more \nefficient or cost effective baseline upgrades are needed that may replace any of the \ncontemplated Transmission Owner-identified upgrades.67  NITS can then be provided \nconsistent with the in-service date of the identified upgrades.   \nThe allocation of responsibilities between the Transmission Owners and PJM in the \ncurrent study process follows the division of rights recently affirmed by both Commission \nand reviewing courts (i.e., Transmission Owners’ reservation of rights over local planning \nand PJM’s responsibility for the regional Transmission System).68  PJM maintains this \ndivision of labor in the Illustrative Tariff provisions.69  For example, upon receipt of an \napplication for Contract Demand Transmission Service, PJM will notify the affected \n \n67 PJM performs such do no harm analyses regularly—often monthly—and studies Transmission \nOwner-identified upgrades together.  See Transmission Planning Department, PJM Manual 14B: PJM \nRegional Transmission Planning Process, PJM Interconnection, L.L.C., § 1.1 (rev. 58, Dec. 17, 2025), \nhttps://www.pjm.com/-/media/DotCom/documents/manuals/m14b.pdf \n(“[P]rior \nto \nintegrating \na \nSupplemental Project into the RTEP base case PJM performs a ‘do no harm study’ to evaluate whether a \nproposed Supplemental Project will adversely impact the reliability of the Transmission System as \nrepresented in the planning models used in all other PJM reliability planning studies.  If as a result of the ‘do \nno harm study’, system upgrades are required, then the system upgrades will be considered part of the \nSupplemental Project and are the responsibility of the Transmission Owner sponsoring the Supplemental \nProject.”).  Pursuant to the do no harm study, PJM analyzes the impact of a contemplated local project to \ndetermine whether it would adversely affect PJM reliability criteria.  If PJM identifies an adverse reliability \nimpact, PJM notifies the PJM Transmission Owner that it has identified system upgrades necessary to \nmaintain the reliability of the transmission system.  Such system upgrades must be incorporated into the local \nproject before the local planning facilities can be incorporated into the PJM Transmission Owners’ local plan \nand submitted for inclusion into the RTEP.  See PJM Transmission Owners Attachment M-3 Process \nGuidelines, \nPJM \nInterconnection, \nL.L.C., \n6 \n(Aug. 15, \n2022), \nhttps://www.pjm.com/-\n/media/DotCom/planning/rtep-dev/pjm-to-attachment-m3-process-guidelines.pdf. \n68 See, e.g., PJM Interconnection, L.L.C., 172 FERC ¶ 61,136, order addressing arguments raised on reh’g, \n173 FERC ¶ 61,225, at P 19 (2020), aff’d sub nom. Am. Mun. Power, Inc. v. FERC, 86 F.4th 922 (D.C. Cir. \n2023); PJM Interconnection, L.L.C., 173 FERC ¶ 61,242 (2020), order addressing arguments raised on reh’g, \n176 FERC ¶ 61,053 (2021), aff’d sub nom. Am. Mun. Power, Inc., 86 F.4th 922; Monongahela Power Co., \n164 FERC ¶ 61,217, at P 14 (2018); Appalachian Power Co., 170 FERC ¶ 61,196, at P 59 (2020). \n69 See Illustrative Tariff, Part XI, Subpart A, section 704 and Subpart B, section 712."},{"page":29,"startToken":9215,"endToken":9536,"text":"25 \nTransmission Owner(s)70 and then “will coordinate” with them to “complete studies, \nincluding load integration studies”71 to determine “whether (and to what level as \napplicable) (i) Firm Contract Demand Transmission Service can be reliably provided and \nidentify any necessary enhancements to the Transmission System to accommodate the \nrequested level of service, and/or (ii) Non-Firm Contract Demand Transmission Services \ncan be reliably provided.”72  PJM will also evaluate whether PJM needs to do additional \nstudies of its own, and make that determination “in accordance with the PJM Manuals.”73  \nPJM will rely on the studies to determine whether (and to what level as applicable) it can \n“reliably provide[]” the requested Contract Demand Transmission Service.74   \n2. \nThe Illustrative Tariff provisions reflect that PJM requires discretion \nin studying to determine the amount of transmission service that can \nbe provided reliably \nContrary to the assertions made by Vistra and Constellation,75 the Illustrative Tariff \naffords PJM and/or the affected Transmission Owner(s) an appropriate amount of \ndiscretion.  First, PJM is not seeking any more discretion than it currently has under its \nexisting study processes for study processes.  The Illustrative Tariff follows PJM’s existing \npractice, which has been in place for decades. \n \n70 See Illustrative Tariff, Part XI, Subpart B, section 712.1. \n71 Illustrative Tariff, Part XI, Subpart B, section 710.3. \n72 Illustrative Tariff, Part XI, Subpart B, section 710.3. \n73 Illustrative Tariff, Part XI, Subpart B, section 712.1. \n74 Illustrative Tariff, Part XI, Subpart B, section 710.3 (“Following completion of all studies, Transmission \nProvider will make the determination, in consultation with the affected PJM Transmission Owner(s), about \nwhether (and to what level as applicable) Firm Contract Demand Transmission Service or Non-Firm Contract \nDemand Transmission Services can be reliably provided for an Application, and if so, what level of service \nmay be provided.”). \n75 Vistra Reply Brief at 33; Constellation Reply Brief at 14-16."},{"page":30,"startToken":9536,"endToken":9829,"text":"26 \nSecond, PJM’s evaluation of the Transmission System to determine whether it can \nreliably provide the requested transmission service requires an exercise of engineering \njudgment, which inherently entails a reasonable exercise of discretion.  Evaluation of firm \nservice requests will require and follow similar study procedures to what is now required \nfor NITS.  For non-firm services, i.e., Interim NITS and Non-Firm Contract Demand \nTransmission Service, the study approach could differ widely for each request, given the \ndifferent nature of the risks involved, as the system would be operated on an as-conditions-\npermit basis.  The details of the studies involved will depend on a number of factors, \nincluding:  (1) how constrained is the area/zone of interconnection; (2) the actual conditions \nat which the load is expected to require the level of non-firm service; and (3) the nature of \nthe constraints present (e.g., powerflow, stability, and short circuit).  The varying constraint \nand risk levels, as well as complexities of implementing remedial actions or control \nschemes to manage these risks, will require varying levels of scrutiny to ensure system \nreliability is maintained, and that sufficient guardrails are present to protect the system \nagainst identified risks.   \nBecause PJM operates the Transmission System for the benefit of all loads, PJM \nhas myriad factors and considerations to keep in mind when making such determinations.  \nPJM is not a gatekeeper and does not discriminate in favor of any type of load in performing \nthese evaluations.  Rather, PJM’s job is to evaluate each request for transmission service \nfrom all perspectives to ensure that it can reliably provide the requested service to serve \nthe load.  Ultimately, as previously noted, the implementation details in the PJM Manual \nwill be developed publicly by PJM and its stakeholders will develop PJM Manual language"},{"page":31,"startToken":9829,"endToken":10149,"text":"27 \nto publicly provide the implementation details as to how PJM will determine whether it \ncan reliably provide the requested service.76  \nThird, in response to Vistra’s specific claim that PJM’s reservation of discretion as \nto whether a study is required for Interim NITS,77 Vistra overlooks that the Illustrative \nTariff provides that, after receiving a request for Interim NITS, PJM “shall determine on a \nnon-discriminatory basis whether additional studies are needed beyond what was required \nto evaluate the Eligible Customer’s request for Network Integration Transmission \nService.”78  That is, PJM will evaluate the study for the customer’s NITS request to \ndetermine whether additional studies are needed—or if the NITS study does or can provide \nsufficient information.  This is reasonable for a number of reasons.  One, if the customer \nrequests NITS and Interim NITS at the same time, then such requests could be examined \nin the same study.  This is precisely the type of implementation detail that can be set forth \nin the PJM Manuals.  Two, if PJM determines that the NITS study already conclusively \nanswers the question of whether and how much Interim NITS may be provided until the \nneeded upgrades are in service, then it makes no sense to perform an additional study that \nwould reach the same result.  This is particularly true where the current NITS study \nprovides that the customer could go ahead and get the requested level of Interim NITS \nimmediately.  A requirement for PJM (and/or applicable Transmission Owner(s)) to \nperform additional studies would only unnecessarily delay the provision of Interim NITS.   \nMore generally, any PJM decision to not study will be based on its knowledge of \nthe system in that area, earlier and ongoing studies information in the area, and the \n \n76 See Illustrative Tariff, Part XI, Subpart B, section 710.3. \n77 See Vistra Reply Brief at 33. \n78 Illustrative Tariff, Part XI, Subpart A, section 704.1 (emphasis added)."},{"page":32,"startToken":10149,"endToken":10462,"text":"28 \ninformation already available to PJM and whether PJM needs to perform a study should be \nwithin its discretion.  PJM should not be required to perform a study that is not needed to \nevaluate the service request.  Any concerns that PJM will summarily reject service requests \nwithout basis are unfounded.  Requests for NITS and Firm Contract Demand Transmission \nService will generally be granted; the only variable is whether new transmission facilities \nmust be installed to accommodate the requests.  Requests for Interim NITS will be granted \nconsistent with the results of any NITS study and/or additional study if necessary.  Finally, \nwith respect to Non-Firm Contract Demand Transmission Service requests, to the extent \nPJM determines that none or only a portion of the requested level of service can be reliably \nprovided, the Illustrative Tariff would require PJM to “provide a written explanation of its \nreasons for” whole or partial denial of service.79  Such written explanation would provide \nthe customer basis to understand PJM’s reasoning for the denial and could form the basis \nof any complaint to the Commission.  Generally speaking, PJM is not going to turn people \naway or deny service; rather, PJM will study the system and identify changes that would \nneed to be made to accommodate the request. \nFourth, as to the timeline for performing the studies, as discussed, PJM’s evaluation \nof any request for transmission service to serve loads in PJM is dependent on the load \nintegration studies performed by the applicable Transmission Owner(s).  Given that such \nload integration studies are a matter of local transmission planning, PJM does not have the \nauthority to dictate timelines to the Transmission Owners to complete their studies.  Like \nall transmission owners across the country, PJM’s Transmission Owners are grappling with \nhow to accommodate the increasing requests for large loads to interconnect.   \n \n79 See Illustrative Tariff, Part XI, Subpart B, section 710.3."},{"page":33,"startToken":10462,"endToken":10761,"text":"29 \nHowever, experience appears to be leading to more efficient processes.  In this \nregard, Exelon Corporation (“Exelon”), the parent of several Transmission Owners, \nrecently filed testimony detailing its large load study process.  Exelon noted that “[t]he \ndetails of the study process are evolving,” which makes sense given the new issues \npresented by integrating so many large loads at once.80  Exelon explained that it has adopted \na cluster study process through which it studies all requests submitted within a given \n“window” collectively to determine their “cumulative impact on the transmission \nsystem.”81  And, it is “[t]hrough this analysis” that Exelon “identifies whether any \ntransmission or high voltage system reinforcements or expansions are needed to ensure the \nsafety, reliability, and efficiency of those systems, as well as the utility’s ability to serve \nall its customers.”82  Exelon explained that it adopted the cluster study process because the \npre-existing “one-by-one studies” were too slow and “delayed” its ability to process the \nrequests.83  Only once such Transmission Owner’s studies are complete is PJM able to \nconduct its studies and identify any additional Transmission System facilities necessary to \naccommodate the transmission service request.84 \nAdditionally, while PJM and the Transmission Owners have much experience \nstudying requests for NITS to serve load in PJM and Point-to-Point Transmission Service \nto the PJM border, they do not have much experience with studying non-firm transmission \n \n80 PJM Interconnection, L.L.C., Answer of Exelon Corporation to the Motion for Leave and Supplemental \nProtest of Constellation Energy Generation, LLC, Docket Nos. ER26-1088-000 & ER26-1479-000 (Apr. 14, \n2026) (“Exelon Answer”); id., Declaration of David Weaver, PE (Attachment A) ¶ 6 (“Weaver Declaration”). \n81 Weaver Declaration ¶ 6. \n82 Weaver Declaration ¶ 6. \n83 Weaver Declaration ¶ 7. \n84 PJM studies Transmission Owner-identified facilities necessary to integrate loads on a cluster basis."},{"page":34,"startToken":10761,"endToken":11119,"text":"30 \nservices to serve loads in PJM.  To tackle this nascent issue and provide an opportunity for \na fulsome analysis of providing non-firm transmission service to large loads, PJM intends \nto soon initiate discussions with stakeholders to develop PJM Manual language to \nimplement the Illustrative Tariff.  This stakeholder process likely will include discussions \non the processes for studying and providing Interim NITS and Non-Firm Contract Demand \nTransmission Service.   \n3. \nThe Illustrative Tariff appropriately provides sufficient notice while \nallowing for implementation details to be in the PJM Manuals \nVistra and Constellation complain that the Illustrative Tariff is “missing \ninformation” related to the performance of the studies for transmission service to serve \nloads in PJM, and thus runs contrary to the Commission’s “rule of reason”85 and would \nallow for discrimination by Transmission Owners.86  These claims miss the mark.   \nThe Illustrative Tariff puts all parties on sufficient notice as to how PJM will \ndetermine whether (and to what level) it can provide the requested transmission service \nand the study procedures to arrive at that determination.87  The Illustrative Tariff provides \nthe standard to which PJM will evaluate the requests—whether the requested level of \nservice can be provided reliably.88  For Firm Contract Demand Transmission Service, the \n \n85 Vistra Reply Brief at 36-38. \n86 Constellation Reply Brief at 14. \n87 See Illustrative Tariff, Part XI, Subpart A, section 702.3 (Determination of Whether Interim Network \nIntegration Transmission Service Can Be Reliably Provided); id., section 704.1 (Notice of Need for Study); \nIllustrative Tariff, Part XI, Subpart B, section 710.3 (Determination of Whether Firm Contract Demand \nTransmission Service and Non-Firm Contract Demand Transmission Service Can Be Reliably Provided); id., \nsection 712.1 (Study Procedures for Firm Contract Demand Transmission Service); id., section 712.2 (Study \nProcedures for Non-Firm Contract Demand Transmission Service). \n88 See Illustrative Tariff, Part XI, Subpart A, section 702.3 (Determination of Whether Interim Network \nIntegration Transmission Service Can Be Reliably Provided); Illustrative Tariff, Part XI, Subpart B, \nsection 710.3 (Determination of Whether Firm Contract Demand Transmission Service and Non-Firm \nContract Demand Transmission Service Can Be Reliably Provided); see also Show Cause Order, 193 FERC"},{"page":35,"startToken":11119,"endToken":11413,"text":"31 \nIllustrative Tariff provides that PJM “and the affected Transmission Owner(s) shall \ncoordinate to study the effects of providing the requested Firm Contract Demand \nTransmission Service on the affected Transmission Owner(s)’s system pursuant to the \napplicable affected Transmission Owner requirements.”89  And, PJM will “determine, in \naccordance with the PJM Manuals, any necessary studies for reliably providing the \nrequested Firm Contract Demand Transmission Service.”90  The studies will “provide data \nrelevant to the determination of whether (and to what level as applicable) (i) Firm Contract \nDemand Transmission Service can be reliably provided and identify any necessary \nenhancements to the Transmission System to accommodate the requested level of service, \nand/or (ii) Non-Firm Contract Demand Transmission Services can be reliably provided.”91  \nFurther, as discussed, the Illustrative Tariff describes the coordination and consultation \nbetween PJM and the applicable Transmission Owner(s) necessary to reliably provide \ntransmission service to serve loads in PJM.92 \nWhile the Illustrative Tariff describes the procedures and studies for the new \nContract Demand Transmission Services, such level of detail and work is generally not \nrequired for Interim NITS determinations given that such service is derivative of the \n \n¶ 61,217, at P 200 (The Commission recognizing that Interim NITS “would only be available to the extent \nPJM determines that it can provide some level of interim service reliably.” (emphasis added)). \n89 Illustrative Tariff, Part XI, Subpart B, section 712.1.  In response to Vistra’s request for the Transmission \nOwners’ planning criteria, Vistra Reply Brief at 33, those criteria are often set forth in each Transmission \nOwner’s FERC Form 715.   \n90 Illustrative Tariff, Part XI, Subpart B, section 712.1. \n91 Illustrative Tariff, Part XI, Subpart B, section 710.3. \n92 Illustrative Tariff, Part XI, Subpart B, section 710.3."},{"page":36,"startToken":11413,"endToken":11750,"text":"32 \ncustomer’s existing NITS request and associated studies, although the Illustrative Tariff \nauthorizes PJM to perform additional studies if needed.93 \nCourts have made clear that the Commission has “broad bounds of discretion” in \napplying the rule of reason,94 and “even specifiable practices that significantly affect rates \nneed not be included if they are clearly implied by the tariff’s express terms.”95  The \nCommission understands that “study assumptions and parameters are likely to change over \ntime as planners gain experience in implementing the new planning procedures.  Thus, \nrigid specifications or formulas set out in the Tariff would likely lead to less reliable \nassessments due to the inability of planners to adapt to changing circumstances.”96  Indeed, \nreliability reviews inherently require PJM to make judgment calls as the Transmission \nProvider and a NERC-designated Reliability Coordinator, and the flexibility to determine \nwhether new transmission facilities are reasonably likely to be in-service fits squarely \nwithin PJM’s expertise.   \nThus, the Illustrative Tariff provides more than enough detail to meet the rule of \nreason, as it provides sufficient detail, “while leaving PJM and stakeholders with sufficient \ndiscretion to improve various implementation details over time as they gain experience \nwith [the new transmission services].”97  Indeed, the Illustrative Tariff calls for such further \ndevelopment.  For Contract Demand Transmission Services, the Illustrative Tariff provides \n \n93 See Illustrative Tariff, Part XI, Subpart A, section 704.1. \n94 City of Cleveland v. FERC, 773 F.2d 1368, 1376 (D.C. Cir. 1985). \n95 Hecate Energy Greene Cnty. 3 LLC v. FERC, 72 F.4th 1307, 1314 (D.C. Cir. 2023). \n96 Sw. Power Pool, Inc., 136 FERC ¶ 61,050, at P 37 (2011); see also Midcontinent Indep. Sys. Operator, \nInc., 190 FERC ¶ 61,147, at P 23 (2025) (“It is beneficial for MISO to retain discretion—within Tariff \nboundaries—to improve study assumptions and parameters over time as it gains experience and learns from \nstakeholders.  Rigid specification would hamper this discretion.”). \n97 PJM Interconnection, L.L.C., 175 FERC ¶ 61,084, at P 65 (2021)."},{"page":37,"startToken":11750,"endToken":12096,"text":"33 \nthat “[d]escriptions of [PJM’s] and/or the applicable Transmission Owner(s)’ specific \nmethodology for assessing whether [the request service] can be reliably provided, will be \nset forth in Tariff, Part XI, Subpart B, section 712, in the PJM Manuals, and in Transmission \nOwner standards, as applicable.”98   \nPJM develops PJM Manual provisions in consultation with stakeholders99 and the \nPJM Manuals are publicly posted.100  This means that (1) the PJM Manuals will provide \nguidance as to when PJM may need to perform such a study; and (2) stakeholders, like \nConstellation and Vistra who complain about the Illustrative Tariff language, will have a \nfulsome opportunity to participate in the development of such PJM Manual language.101  \nThis is a benefit—that such implementation details will be developed in consultation with \nstakeholders, including parties interested in co-location arrangements and Transmission \nOwners.   \nAs the Show Cause Order recognized, co-location arrangements are a fairly novel \nconcern.  Thus, PJM, its stakeholders, the Commission, and others have not had much \nexperience with serving these arrangements, studying or providing non-firm service to \nloads, or studying large loads in the number and scale the county is currently seeing.  While \nPJM has been working diligently to develop just and reasonable terms and conditions, as \n \n98 Illustrative Tariff, Part XI, Subpart B, section 710.3. \n99 PJM employs a formalized, collaborative stakeholder process for the creation and revision of business \npractices manuals, so that PJM seeks endorsement by stakeholders.  See Stakeholder Affairs Department, \nPJM Manual 34: PJM Stakeholder Process, PJM Interconnection, L.L.C., § 11.15 (rev. 22, Sep. 25, 2025), \nhttps://www.pjm.com/-/media/DotCom/documents/manuals/m34.pdf (discussing stakeholder process to \nrevise PJM Manuals). \n100 See Manuals, PJM Interconnection, L.L.C., https://www.pjm.com/library/manuals.aspx (last visited \nApr. 22, 2026). \n101 The development of the Manual implementation details will occur once the Commission rules on the \nappropriate terms and conditions for the transmission services.  This sequencing is logical, as PJM and its \nstakeholders cannot know how to implement the terms and conditions until they are determined."},{"page":38,"startToken":12096,"endToken":12408,"text":"34 \nset forth in the Illustrative Tariff provisions, and has engaged in regular consultation with \nits stakeholders regarding the same,102 the development timeline has been compressed.  \nHowever, as discussed, PJM and its stakeholders continue to examine these issues outside \nthis proceeding, and the ongoing Connect and Manage Senior Task Force103 may benefit \nand inform how PJM should study these new non-firm transmission services.  Indeed, PJM, \nin the near future intends to collaborate with stakeholders on the development of PJM \nManual language to implement the Illustrative Tariff, which would allow Co-Located Load \narrangement application submission, necessary studies, and agreement preparation to move \nforward.104 \nRegardless, at root, Vistra’s and Constellation’s complaints regarding the level of \ndetail in PJM’s study procedures generally concern the Transmission Owner’s load \nintegration studies.  But any “lack of detail” regarding load integration studies comports \nwith the jurisdictional boundaries of the Federal Power Act (“FPA”), as recognized by the \nShow Cause Order, which was careful to assert jurisdiction only over the Eligible \nCustomers taking transmission service on behalf of Co-Located Loads.  The Transmission \nOwners’ processes for studying the integration of new loads on to the transmission system, \nand identifying upgrades (i.e., Supplemental Projects) to accommodate such loads, does \nnot inherently implicate the Commission’s FPA jurisdiction.   \n \n102 PJM has held nine stakeholder workshops to discuss compliance with the Show Cause Order and \nimplementation of its directives.  See Co-Located Load Order Workshop, PJM Interconnection, L.L.C., \nhttps://www.pjm.com/committees-and-groups/workshops/cllsco (last visited Apr. 22, 2026).  \n103 \nSee \nConnect \nand \nManage \nSenior \nTask \nForce, \nPJM \nInterconnection, \nL.L.C., \nhttps://www.pjm.com/committees-and-groups/task-forces/camstf (last visited Apr. 22, 2026).  \n104 PJM also intends to explore with stakeholders whether and how to study the impacts of both the Co-\nLocated Load and Co-Located Generating Facility together, as appropriate and as compatible with the service \ntype requested."},{"page":39,"startToken":12408,"endToken":12673,"text":"35 \n4. \nThe Illustrative Tariff reasonably requires PJM to determine \nwhether the requested level of transmission service can be “reliably \nprovided” \nVistra asserts that “[i]t is therefore unclear what it means to ensure that non-firm \ntransmission service can be provided ‘reliably.’”105  Vistra bases this contention on the \nargument that, because an Eligible Customer has “agreed to be curtailable,” its use of the \nTransmission System is limited only by use of “transmission customers of higher \npriority.”106  Apparently, in Vistra’s view, entities can simply utilize any unused \ntransmission capacity for use on a non-firm basis without concern for transmission \nreliability.  This is overly simplistic and incorrect.  As explained above, it is not the case \nthat the Transmission System has significantly underutilized capacity to provide the \nenvisioned services.   \nAs discussed, PJM’s Transmission System is extremely complex and highly \nintegrated, with over 1,400 interconnecting generators, a record summer peak load of \n165,563 MW (set in 2006), and serves over 67 million people within the PJM Region.  In \naddition, PJM must manage loop flows from neighboring regions, congestion management \nalong its seams, and manage day to day, planned and unplanned outages that need the \nremnant capability on the system to be enabled.  Continuously filling all remnant \ntransmission capability on the PJM system will limit and complicate the necessary outage \nscheduling for both generation and transmission facilities further imposing higher \noperational risk.  This operational risk needs to be carefully identified and managed by \nPJM beforehand instead of spontaneously managing non-firm load under an increasingly \n \n105 Vistra Reply Brief at 39. \n106 Vistra Reply Brief at 39."},{"page":40,"startToken":12673,"endToken":13009,"text":"36 \nstressed system.  Furthermore, as load continues to grow by the forecasted approximately \n5-6 gigawatts (“GW”) each year due predominantly to large loads with a very high capacity \nfactor, any historic generation/transmission operating margins are rapidly shrinking.  This \nis not just a peak day concern, but rather a year-round concern due to the high capacity \nfactor of these new loads.  Not only does the load increase complicate operations, the \nsignificant, both in scope and quantity, baseline upgrades that have been identified to be \nin-service over the next several years require major, long term transmission outages of \nmultiple extra-high voltage lines, transformers, buses and substations that need to be \ncoordinated across the Transmission System.   \nIt is well understood that everything on the system interacts and there can be ripple \neffects from even the smallest incident.107  Thus, PJM cannot naively grant service requests \nwithout proper studies.  Many of the large load service requests may directly affect, both \nphysically and performance-wise, the operation and reliability of key generating plants, \nwhich in turn can have a major impact on the overall system.  PJM must ensure the \nreliability of the system is maintained for a specific time frame (requested interim or non-\nfirm service duration) and be prepared to manage reliably within such pre-specified and \nstudied state.  The Commission recognized this basic fact in the Show Cause Order.  There, \nit stated that Interim NITS “would only be available to the extent PJM determines that it \ncan provide some level of interim service reliably.”108   \n \n107 The 2003 Northeast Blackout was precipitated, in part, by overloaded high-voltage power lines in northern \nOhio sagging due to heat and contacting overgrown trees.  U.S.-Canada Power System Outage Task Force, \nFinal Report on the August 14, 2003 Blackout in the United States and Canada: Causes and \nRecommendations, \nNorth \nAmerican \nElectric \nReliability \nCorporation, \n18-20 \n(Apr. \n2004), \nhttps://www.nerc.com/globalassets/our-work/reports/event-reports/august_2003_blackout_final_report.pdf.  \n108 Show Cause Order, 193 FERC ¶ 61,217, at P 200 (emphasis added)."},{"page":41,"startToken":13009,"endToken":13285,"text":"37 \nTo do so, PJM, as the Transmission Provider and Reliability Coordinator, must be \nsure that provision of any service would not impair system reliability.  The reliable \ninterconnection of large loads requires assessment of thermal, voltage, and stability issues, \namong others, which may be mitigated with new transmission facilities, or upgrades, all of \nwhich are necessary to ensure these new large loads are served with the reliability level \ncompliant with the planning standards given their potential role in national security.  Such \nassessment is not as simple as looking at a single transmission path element performance \nunder one operating condition.  Rather, PJM must ensure that it does not violate \nSOLs/IROLs in the event of contingencies or abnormal system conditions.   \n5. \nThe Illustrative Tariff can accommodate phased-in Co-Located \nLoads \nThe Data Center Coalition argues that the Illustrative Tariff provisions would not \n“accommodate the phased and incremental development that characterizes large load \nprojects.”109  This is incorrect.  PJM has presented in the Illustrative Tariff broad terms and \nconditions to process and approved requests for Interim NITS and Contract Demand \nTransmission Services to serve Co-Located Loads.   \nThe Illustrative Tariff provides a workable pathway for phased development or load \nramping.  The obvious path for Co-Located Load that increases over time and “align[s] \ntransmission service with phased project development”110 is NITS—a transmission service \ndesigned to accommodate load growth.  To the extent, the Eligible Customer elects \nContract Demand Transmission Service, a service which by its name is for a defined MW, \ncontracted amount, and any change to the contracted MW quantity would require a new \n \n109 Data Center Coalition Response at 6. \n110 Data Center Coalition Response at 6."},{"page":42,"startToken":13285,"endToken":13623,"text":"38 \nservice request to be studied.  This is reasonable, and entirely consistent with how generator \ninterconnections are treated across the county.111   \nThe customer can elect to request Interim NITS or Firm Contract Demand \nTransmission Service for their full load amount ahead of time and utilize that capacity as \ntheir demand increases up to the applied for firm service level.  The advantage of such \napproach is to ensure the transmission facilities needed to provide reliable service are \nefficiently identified and addressed with the initial application.  This is an economic \ntradeoff that ensures lower interruption levels and certainty of service as well as associated \ncost. Importantly, the Commission directed PJM to offer Contract Demand Transmission \nService as an alternative to NITS.  Thus, at this time, it is reasonable for Contract Demand \nTransmission Service to not have the same load growth accommodating attributes as NITS. \nWith respect to the Data Center Coalition’s suggestion that the rules should provide \nfor a “transition between service constructs,”112 the Illustrative Tariff allows for customers \nto submit a request for the type of transmission service they want.  PJM will then evaluate \nwhether it needs to perform a study or it can grant the request without a study.  Given that \ndifferent transmission services place different demand on the Transmission System, PJM \nmust have the opportunity to examine the request to determine whether the requested level \nof service can be provided reliably.  \n \n111 See Improvements to Generator Interconnection Procedures and Agreements, Order No. 2023, 184 FERC \n¶ 61,054, at P 1409 (“Once the executed facilities study agreement is returned, the transmission provider may \ndecide to automatically treat requests to add a generating facility to an existing interconnection request as \nmaterial modifications without review.”), limited order on reh’g, 185 FERC ¶ 61,063 (2023), order on reh’g \n& clarification, Order No. 2023-A, 186 FERC ¶ 61,199, errata notice, 188 FERC ¶ 61,134 (2024), appeals \npending sub nom. Advanced Energy United v. FERC, Nos. 23-1282, et al. (D.C. Cir. Oct. 6, 2023).  \n112 Data Center Coalition Response at 6."},{"page":43,"startToken":13623,"endToken":13946,"text":"39 \nD. \nNon-Monetary Penalties Are Just and Reasonable and Necessary to \nSupport the Reliable Operation of the Grid \nA number of parties object to the non-monetary operational penalties set forth in \nthe Illustrative Tariff, which would work in tandem with financial penalties to ensure \nreliability of the Bulk Electric System.113  Contrary to their claims, these non-monetary \noperational penalties are not “extreme punishments that were not contemplated by the \n[Show Cause Order].”114  These penalties do not “effectively deny customers service after \na single failure to curtail or shed load[.]”115  Rather, as discussed below, non-monetary, \noperational penalties are effectively remedial actions that would be taken to support \nreliability.   \nIn brief, the non-monetary penalties described in PJM’s Initial Brief are:  (1) in the \nevent of a misoperation of the necessary control technology and protection system installed \nto limit the Co-Located Load’s withdrawal of energy from the Transmission System, a \ntemporary pause in service of up to 120 days to permit time to investigate, identify, and fix \ncontrol technologies or protection system schemes that have misoperated; and (2) a \ndisqualification penalty that would require Eligible Customers to transition to taking NITS.   \nParties’ critiques focus primarily on the disqualification penalties.  Such complaints \nare without regard to the impacts of having two misoperations at the same facility; each of \nwhich exposes the system to major reliability risks, and together demonstrate that the \n \n113 Joint Co-Location Developers Reply Brief at 23-27; Constellation Reply Brief at 18-21; Vistra Reply Brief \nat 30; Data Center Coalition Response at 7-8.  \n114 Constellation Reply Brief at 19; see also Joint Co-Location Developers Reply Brief at 24 (“The threat of \nan extreme penalty like disqualification” is “not needed to protect system reliability.”); Data Center Coalition \nResponse at 7 (“PJM proposes an extremely stringent penalty framework under which a single failure to \ncomply with load shedding or curtailment instructions results in automatic disqualification from service.”). \n115 Joint Co-Location Developers Reply Brief at 23."},{"page":44,"startToken":13946,"endToken":14255,"text":"40 \ncustomer unable and/or unwilling to perform under their contracted terms and conditions.  \nRequesting monetary penalties, in place on non-monetary penalties, undermines the value \nof reliability and hands it to a single site or a class of load that may decide to pay the penalty \nin place of operate as agreed to ensuring overall system reliability.  A temporary pause up \nto 120 days is consistent with NERC requirements,116 and disqualification penalties do not \ndisqualify Eligible Customers from taking transmission service, but rather align Eligible \nCustomers’ demonstrated use of the system with the type of transmission service best suited \nto their usage.  Where Eligible Customers have been disqualified from taking Firm Contract \nDemand Transmission Service, Non-Firm Contract Demand Transmission Service, or \nInterim NITS on behalf of Co-Located Load, they retain the option to take NITS which, in \nand of itself, addresses Curtailment, Load Shed, and control technology or protection \nscheme misoperation risk.   \nImportantly, only Eligible Customers who use the system in a manner detrimental \nto the reliability of the Transmission System would be subject to non-monetary penalties.  \nThat is, only Eligible Customers who elect to take Firm/Non-Firm Contract Demand \nTransmission Service or Interim NITS but then either (1) fail to follow dispatch instructions \nto shed load or curtail; or (2) have requisite control technologies or protection system \nschemes that misoperate would be subject to non-monetary penalties.  These co-location \narrangements may involve physical and/or electrical interconnections with critical power \nplants that their reliable and predictable operation is crucial to the reliability of the overall \n \n116 See, e.g., PRC-004-6 — Protection System Misoperation Identification and Correction, North American \nElectric Reliability Corporation (June 12, 2025), https://www.nerc.com/globalassets/standards/reliability-\nstandards/prc/prc-004-6.pdf; PRC-012-2 — Remedial Action Schemes, North American Electric Reliability \nCorporation (June 12, 2025), https://www.nerc.com/globalassets/standards/reliability-standards/prc/prc-012-\n2.pdf."},{"page":45,"startToken":14255,"endToken":14537,"text":"41 \nPJM interconnected system.  The non-monetary operational penalties are designed to \nensure that customers are offered the flexibility of these new transmission services only to \nthe extent they are willing and able to manage their load in a way that maintains overall \nsystem reliability.   \nAs discussed below, the non-monetary operational penalties described in PJM’s \nInitial Brief represent a measured approach that balances significant reliability concerns \nwith the interest in integrating large loads quickly.  That said, in response to concerns raised \nby intervenors about the application of disqualification penalties regardless of cause, PJM \nalso describes, below, revisions to the Illustrative Tariff language that add some \ndiscretionary language to the strict application of non-monetary operational penalties. \n1. \nThe size and pace of large load integration give rise to heightened \nreliability risk that calls for non-monetary penalties in addition to \nfinancial penalties  \nThe cost of unreliability—whether measured in dollars, frequency of rolling \nblackouts, impacts on national security or economic development, or loss-of-life—must \nnot be underestimated.  Reliability underscores every aspect of the penalty scheme \ndescribed in PJM’s Initial Brief. \nNERC has found that “[t]he size and speed at which data centers are being \nconnected to and operated on the [Bulk Electric System] is creating one of the greatest \nnear-term reliability challenges.”117  In one incident, highlighted in NERC’s 2025 State of \nReliability Overview, “approximately 1,500 MW of data centers disconnected \nsimultaneously and unexpectedly from the [Bulk Electric System] due to a transmission \n \n117 2025 State of Reliability: Assessment Overview of 2024 Bulk Power System Performance, North American \nElectric \nReliability \nCorporation, \n8 \n(June \n2025), \nhttps://www.nerc.com/globalassets/programs/rapa/pa/nerc_sor_2025_overview.pdf (“NERC 2025 State of \nReliability Overview”)."},{"page":46,"startToken":14537,"endToken":14894,"text":"42 \nline fault in 2024.”118  NERC compared “[a] loss of load of this size . . . to a large nuclear \npower plant coming on-line immediately and unexpectedly, creating an imbalance due to \ntoo much generation on the system.”119  \nNERC’s latest Long Term Reliability Assessment found that PJM faces a “high \nrisk” of potential electricity supply shortfalls under normal and extreme weather conditions \nby 2029, and is presently already at “elevated risk” of experiencing such shortfalls due \nprimarily to “vigorous large-load and data center development.”120  Likewise, PJM’s long-\nterm 2026 Load Forecast expects that, driven primarily by data centers, summer peak \ndemand will rise from 160 GW in 2025, to 222 GW by 2036, and 253 GW by 2046.121 \nThe Commission, in this proceeding, has recognized that the speed with which large \nloads are being added and the unprecedented size of the projected loads present unique \nchallenges and risks to reliability.122  As PJM’s Independent Market Monitor states plainly, \nNon-Firm Contract Demand Transmission Service and Interim NITS “create significant \nreliability risks for the transmission system.”123   \nUndoubtedly, the rapid influx of large load presents reliability challenges.  But as \nChairman Swett recently observed in a keynote speech to the Energy Bar Association, \n \n118 NERC 2025 State of Reliability Overview at 8 (citing Incident Review: Considering Simultaneous \nVoltage-Sensitive Load Reductions, North American Electric Reliability Corporation (Jan. 8, 2025), \nhttps://www.nerc.com/globalassets/our-work/reports/event-\nreports/incident_review_large_load_loss.pdf#search=load%20loss%20data%20center).  \n119 NERC 2025 State of Reliability Overview at 8. \n120 Long-Term Reliability Assessment, North American Electric Reliability Corporation, 7-9, 91 (Jan. 29, \n2026), https://www.nerc.com/globalassets/our-work/assessments/nerc_ltra_2025.pdf. \n121 PJM Resource Adequacy Planning Department, 2026 PJM Load Forecast Report, PJM Interconnection, \nL.L.C., 6 (Jan. 14, 2026), https://www.pjm.com/-/media/DotCom/library/reports-notices/load-forecast/2026-\nload-report.pdf (“PJM 2026 Load Forecast”). \n122 Show Cause Order, 193 FERC ¶ 61,217, at P 6. \n123 PJM Interconnection, L.L.C., Reply Brief of the Independent Market Monitor for PJM, Docket Nos. EL25-\n49-000, et al., at 2 (Mar. 26, 2026) (“IMM Reply Brief”)."},{"page":47,"startToken":14894,"endToken":15177,"text":"43 \nmaintaining a reliable grid need not be in tension with integrating large loads.124  Large \nloads can be responsibly integrated in a manner that mitigates reliability risk.  Non-\nmonetary operational penalties are essential to the responsible integration of large loads.    \n2. \nPJM’s non-monetary penalties and requirements on Eligible \nCustomers using necessary control technologies or protection \nsystems are not unduly discriminatory \nCommission precedent undermines Vistra’s assertion that non-monetary penalties, \nas well as requirements on Eligible Customers using necessary control technologies or \nprotection systems, violate the “comparability requirement” and are thus unduly \ndiscriminatory.125  According to Vistra, these requirements treat Eligible Customers serving \nCo-Located Loads “differently from any other entities . . . including the PJM Transmission \nOwners.”126   \nThe comparability principle “requires that transmission providers treat similarly \nsituated customers comparably in the transmission planning process.”127  However, the \nprinciple applies only to similarly situated customers.  Where customers are not similarly \nsituated, the comparability principles do not apply.   \nThe Commission has found that where an RTO or Independent System Operator \nhas shown that customers serving large loads differ from customers serving more \ntraditional loads, different treatment may be warranted.  Earlier this year, the Commission \n \n124 See James Downing, Swett Wants to ‘Push Right up to’ the Edge of Precedent as FERC Chair, RTO Insider \n(Apr. 15, 2026), https://www.rtoinsider.com/130267-ferc-swett-wants-to-push-precedent-to-edge/.  \n125 Vistra Reply Brief at 30-31. \n126 Vistra Reply Brief at 30. \n127 Building for the Future Through Electric Regional Transmission Planning and Cost Allocation, Order \nNo. 1920-A, 189 FERC ¶ 61,126, at P 318 (2024), order on reh’g & clarification, Order No. 1920-B, 191 \nFERC ¶ 61,026 (2025), appeals pending sub nom. Appalachian Voices v. FERC, Nos. 24-1650, et al. (4th \nCir. July 16, 2024)."},{"page":48,"startToken":15177,"endToken":15588,"text":"44 \naccepted Southwest Power Pool, Inc.’s (“SPP”) High Impact Large Load (“HILL”) and \nHigh Impact Large Load Generation Assessment (“HILLGA”) processes,128 finding that \nSPP had “shown that unprecedented growth in large loads in the SPP region presents \nsignificant and unique operational and planning challenges.”129  The Commission \nconcluded that SPP’s proposed processes for “new large loads into SPP’s transmission \nsystem” were not unduly discriminatory despite differing from processes applicable to \nother loads “given their unique operating characteristics.”130  Imposing “more stringent \neligibility requirements for the HILLGA process, compared to the requirements set forth \nin the Commission’s pro forma [Large Generator Interconnection Procedures]” was \ndetermined to be “just and reasonable and not unduly discriminatory or preferential \nbecause they will help deter speculative interconnection requests[.]”131  While SPP is \nstructurally very different from PJM and there is a different allocation of rights between \nSPP and its transmission owners than in PJM—making SPP’s HILL/HILLGA \ndistinguishable from the facts facing PJM, that does not affect the fundamental premise \nthat treatment of Co-Located Loads may differ from treatment of more traditional loads \nwithout being unduly discriminatory.132   \n \n128 Sw. Power Pool, Inc., 194 FERC ¶ 61,031, at P 60 (2026) (“HILL/HILLGA Order”). \n129 HILL/HILLGA Order, 194 FERC ¶ 61,031, at P 60. \n130 HILL/HILLGA Order, 194 FERC ¶ 61,031, at P 61. \n131 HILL/HILLGA Order, 194 FERC ¶ 61,031, at P 65. \n132 HILL/HILLGA Order, 194 FERC ¶ 61,031, at PP 65-66; id. concur op. (Commissioner Rosner) at P 3 \n(“There are also clear parallels between SPP’s approach in its HILLs and HILLGA processes and the new \ntransmission services the Commission recently directed PJM to create for load co-located with generation.  \nWhile the mechanics of these approaches are distinct between the different regions, . . . [t]he common thread \nis a recognition that when generation is paired with load that is physically proximate, the impacts on the \ntransmission system are lower than they are in the status quo, in which large loads and generation are planned \nseparately.”); see, e.g., Hess Corp. v. PJM Interconnection, L.L.C., 142 FERC ¶ 61,040, at P 35 (2013) \n(“Discrimination is undue when there is a difference in rates or services among similarly situated customers \nthat is not justified by some legitimate factor.” (citing City of Anaheim, 113 FERC ¶ 61,091, at P 130 (2005))); \nViridity Energy, Inc. v. PJM Interconnection, L.L.C., 155 FERC ¶ 61,060, at P 22 (2016)."},{"page":49,"startToken":15588,"endToken":15872,"text":"45 \nSimilarly, in this proceeding, the Commission has recognized that the speed with \nwhich large loads are being added and the unprecedented size of the projected loads present \nunique challenges and risks to reliability and resource adequacy.133  Furthermore, as \ndiscussed in Section II.D.1, above, NERC, the Independent Market Monitor for PJM, and \nPJM’s 2026 Load Forecast each demonstrate that the new large loads integrating into PJM’s \nTransmission System are not similarly situated to traditional loads, create unique reliability \nand resource adequacy risks, and are of an unprecedented size and scale. \nBecause SPP had shown that the new large loads in SPP’s transmission system are \nnot similarly situated to traditional loads, the Commission held that different and even \ncomparatively more stringent treatment of new large loads was not unduly \ndiscriminatory.134  First, as stated in PJM’s Initial Brief, each and every Service Agreement \nfor Non-Firm Contract Demand Transmission Service must include any appropriate \nnecessary control technologies and/or protection systems PJM determines are necessary to \nensure the reliability and stability of PJM’s Transmission System.135  The control \ntechnologies and protection systems necessary to provide Non-Firm Contract Demand \nTransmission Service (and Interim NITS) are emblematic of the complexity associated \nwith Non-Firm Contract Demand Transmission Service from an operations and planning \nperspective.136  Second, the non-monetary penalties are necessary to effectuate that Eligible \nCustomers are “willing and able to control their withdrawals from the transmission \n \n133 Show Cause Order, 193 FERC ¶ 61,217, at P 6 & n.16 (citing PJM Interconnection, L.L.C., 190 FERC \n¶ 61,115, at P 83 (2025)). \n134 HILL/HILLGA Order, 194 FERC ¶ 61,031, at P 60. \n135 Initial Brief at 35. \n136 See Initial Brief at 34-35."},{"page":50,"startToken":15872,"endToken":16129,"text":"46 \nsystem”137 and that services are designed to allow PJM to maintain system reliability.138  \nDisqualification penalties support the Commission’s underlying value proposition, as \ndescribed in the Show Cause Order.   \nConstellation asserts that the disqualification penalties described in PJM’s Initial \nBrief are “extreme punishments . . . not contemplated by the [Show Cause Order].”139  \nContrary to Constellation’s claim, at bottom, disqualification penalties support the central \nvalue proposition expressly contemplated in the Show Cause Order—that Eligible \nCustomers can take the level of “transmission service that aligns with their use of the \ntransmission system and therefore aligns the charges for service with the benefits \nreceived.”140   \nThe Show Cause Order does not grant Eligible Customers an inalienable right to \nFirm/Non-Firm Contract Demand Transmission Services or Interim NITS.  Rather, Eligible \nCustomers who are “willing to limit their energy withdrawals” need not be limited to taking \nNITS.141  Conversely, an Eligible Customer who is unwilling to limit energy withdrawals \nwhen directed should take the level of “transmission service that aligns with their use of \nthe transmission system[.]”142   \nAs the Show Cause Order explains, Eligible Customers should be allowed to choose \nthe level of transmission service that aligns transmission service charges “with the benefits \n \n137 See Show Cause Order, 193 FERC ¶ 61,217, at P 204. \n138 Initial Brief at 42. \n139 Constellation Reply Brief at 19. \n140 Show Cause Order, 193 FERC ¶ 61,217, at P 199. \n141 Show Cause Order, 193 FERC ¶ 61,217, at P 199. \n142 Show Cause Order, 193 FERC ¶ 61,217, at P 199."},{"page":51,"startToken":16129,"endToken":16395,"text":"47 \nreceived.”143  In other words, Eligible Customers who do not use all of the benefits of NITS \nmay choose a comparatively less flexible and, generally, less expensive level of \ntransmission service.  Likewise, Eligible Customers should not receive benefits beyond the \nlevel of transmission service that they have paid for.    \n3. \nDisqualification penalties that require Eligible Customers to \ntransition to taking NITS do not effectively deny service to Eligible \nCustomers and are a measured response   \nSeveral parties argue that the disqualification penalties are “draconian,” “extreme,” \nand “effectively deny customers service.”144  These arguments are pure hyperbole.   \nDisqualification penalties do not foreclose Eligible Customers from taking \ntransmission service entirely.  They simply uphold the requirement, rooted in longstanding \nCommission precedent and PJM’s planning, markets, and operation functions, that Eligible \nCustomers take the level of service that aligns with their demonstrated use of the system.  \nWhere Eligible Customers demonstrate that they cannot (or are unwilling to) limit \nwithdrawals, as may be required when Eligible Customers choose to take Firm/Non-Firm \nContract Demand Transmission Service or Interim NITS, it is appropriate for those Eligible \nCustomers to take NITS. \nNITS, in and of itself, addresses Curtailment, Load Shed, and control technology \nor protection scheme misoperation risks.  Where Eligible Customers demonstrate that their \nuse of the Transmission System exposes the grid to such risks, transitioning such customers \nto taking NITS is a remedial measure that in fact better aligns an Eligible Customer’s needs \nto their level of service. \n \n143 Show Cause Order, 193 FERC ¶ 61,217, at P 199. \n144 Joint Co-Location Developers Reply Brief at 23-24; Vistra Reply Brief at 26."},{"page":52,"startToken":16395,"endToken":16698,"text":"48 \nThe distinction among NITS, the new Firm/Non-Firm Contract Demand \nTransmission Services, and Interim NITS is rooted in the long-recognized distinction \nbetween Point-to-Point Transmission Service and NITS.  As the Commission observed in \nOrder No. 890, these services “are not precisely the same, nor were they intend[ed] to be \nidentical.”145  Order No. 888 created the distinction between these two services “to \nrecognize the different ways in which transmission providers typically use their system.”146  \nAccording to Order No. 890, “[c]ustomers of network service retain flexibility that is not \nenjoyed by point-to-point customers.”147  Indeed, far from being an “excessively” punitive \nresult, PJM customers have previously sought to convert from point-to-point service to \nnetwork service to better align their transmission service with their needs.148   \nPJM’s processes have been built around the long-held practice and expectation that \nload internal to PJM will take NITS.149  Unlike point-to-point service, NITS is flexible, \nincorporated in PJM’s system planning studies and processes as well as PJM’s capacity \nmarket, and always firm.150  NITS is not only the default transmission service taken by load \ninternal to PJM, but it is a significantly more comprehensive and a higher quality of service \nwhen compared to point-to-point service.151  Thus, far from being “not commensurate with \nany potential damage[,]”152 the disqualification penalties simply require non-compliant \n \n145 Order No. 890, 118 FERC ¶ 61,119, at P 928. \n146 Order No. 890, 118 FERC ¶ 61,119, at P 928. \n147 Order No. 890, 118 FERC ¶ 61,119, at P 929.  \n148 See, e.g., FirstEnergy Sols. Corp., 127 FERC ¶ 61,208 (2009). \n149 Initial Brief at 48. \n150 Initial Brief at 48; Wharton Aff. ¶ 10. \n151 Initial Brief at 48; id., Affidavit of Dr. Sami Abdulsalam (Attachment B) ¶ 7 (“Abdulsalam Aff.”). \n152 Joint Co-Location Developers Reply Brief at 26-27."},{"page":53,"startToken":16698,"endToken":16997,"text":"49 \nEligible Customers to take the default transmission service.  Further, disqualification is not \na denial of service; rather, it allows for transitioning the customer to the service that aligns \nwith its usage of the Transmission System.  Any interval in which the customer must wait \nfor transmission upgrades to be constructed to accommodate the customer’s demonstrated \nusage is necessary and reasonable to maintain the reliability of the Transmission System \nfor all other users. \n4. \nThe Commission did not foreclose non-monetary penalties, \nparticularly where financial penalties alone are insufficient to \nsafeguard reliability   \nSeveral entities suggest that penalties other than financial penalties exceed the \nscope of the Commission’s Show Cause Order153 and/or suggest that, even if the \nCommission permits non-monetary penalties, financial penalties alone should be sufficient \nto incent Eligible Customers to limit their use of the transmission system to their chosen \nlevel of Contract Demand or Interim NITS.154  Neither positions withstand scrutiny. \nFirst, while the Commission specifically directed application of a penalty rate to \nEligible Customers, the Commission did not, as some intervenors suggest, limit potential \nremedies to financial penalties.  In fact, in the same paragraph in which the Show Cause \nOrder directs “PJM to apply a penalty rate,”155 the Show Cause Order “also direct[s] parties \nto brief . . . any other remedial action that PJM should take to address withdrawals in excess \nof the contract demand.”156  Thus, the Commission, in addition to requiring a financial \npenalty, also expressly solicited briefing on other actions that PJM should take when \n \n153 Constellation Reply Brief at 19; Vistra Reply Brief at 29-30. \n154 See Constellation Reply Brief at 20-21; Joint Co-Location Developers Reply Brief at 25. \n155 Show Cause Order, 193 FERC ¶ 61,217, at P 212. \n156 Show Cause Order, 193 FERC ¶ 61,217, at P 212 (emphasis added)."},{"page":54,"startToken":16997,"endToken":17307,"text":"50 \nEligible Customers withdraw energy from the PJM Transmission System in excess of \ncontract demand.   \nSecond, financial penalties alone are insufficient to support reliability in light of the \nvolume of load that is anticipated to come online in short order and the nature of how these \nnew loads will seek to connect through co-locating with potentially critical generating \nfacilities within the interconnection.  According to the Commission’s longstanding \nprecedent, to incent compliance with reliability requirements, “[a] monetary penalty must \nbe assessed and structured in such a way that a user, owner or operator of the Bulk-Power \nSystem does not consider its imposition as simply an economic choice or a cost of doing \nbusiness.”157  In other words, to have meaningful deterrence value, large loads cannot be \npermitted to simply buy out of behavior that risks the reliability of the Bulk Power System; \nthe monetary penalty cannot simply be an opportunity cost given the grave reliability risks \nthese large loads present to the Transmission System if not properly managed.   \nWhile the Commission has, as Vistra notes, previously found that tailored financial \npenalties were appropriate and sufficient for penalizing unreserved use in the past,158 that \ncertainly does not mean financial penalties are sufficient based on the facts and \ncircumstances before the Commission in this proceeding.  As noted above, based on PJM’s \nlatest long-term load forecast, while the summer peak demand in 2025 was 160 GW, driven \nlargely by data centers, it is forecasted to grow to 222 GW by 2036 and 253 GW by 2046.159  \n \n157 See Rules Concerning Certification of the Electric Reliability Organization; and Procedures for the \nEstablishment, Approval, and Enforcement of Electric Reliability Standards, Order No. 672, 114 FERC \n¶ 61,104, at P 455, order on reh’g, Order No. 672-A, 114 FERC ¶ 61,328 (2006). \n158 Vistra Reply Brief at 29. \n159 PJM 2026 Load Forecast at 6."},{"page":55,"startToken":17307,"endToken":17722,"text":"51 \nGiven the size and pace of large load growth, no monetary penalty alone can accurately \nreflect the value of maintaining reliability in the face of unprecedented load growth.160   \nThird, while Vistra would paint non-monetary penalties as a departure from \nCommission precedent, the Commission has long held that where monetary penalties are \nfound to be insufficient to incentivize actions consistent with reliability, it may be necessary \nto implement “a range of non-monetary and monetary penalties” to promote behavior that \nsupports and improves the reliability of the Bulk Power System.161  The Commission \ndiscussed, at length, the usefulness of non-monetary penalties after the Energy Policy Act \nof 2005162 granted the Commission the authority to certify a national Electric Reliability \nOrganization to create and enforce mandatory, rather than voluntary, reliability standards.  \nSuch non-monetary penalties included, for example, limits to certain “activities, functions \nor operations” such as “a ban on engaging in certain transactions or limiting the operation \nof facilities.”163  As such, not only are non-monetary operational penalties well within the \nscope of this proceeding, they have long been considered by the Commission to be a \nsignificant tool to support grid reliability.   \n \n160 This is particularly true given that, tech hyperscalers—Amazon Web Services, Inc., Alphabet Inc. \n(Google), Microsoft Corporation, Meta Platforms, Inc., and Oracle Corporation—driving much of the \noutsized load growth announced over $600 billion in capital expenditures for 2026—“a 36% jump from 2025 \nand more than 4x what the entire publicly traded U.S. energy sector spends to drill wells, refine oil and deliver \ngasoline” with approximately $450 billion of that capitalize expenditure going directly to AI infrastructure.  \nJaachi Mbachu, Big Tech Will Spend $600B on AI in 2026: 5 Stocks Cashing the Checks, Investing.com \n(Feb. 6, \n2026), \nhttps://www.investing.com/analysis/big-tech-will-spend-600b-on-ai-in-2026-5-stocks-\ncashing-the-checks-200674615.  In 2025, the total combined revenue of just the top five tech hyperscalers, \noften referred to as the “Big Five,” reached approximately $1.15 trillion.  Sarath C P, Fortune 500 Companies \nList (2025), Eqvista (Aug. 22, 2025), https://eqvista.com/fortune-500-companies-in-the-us/. \n161 See Order No. 672, 114 FERC ¶ 61,104, at PP 49, 455 (amending regulations to incorporate criteria to \nqualify as Electric Reliability Organization and discussing range of monetary and non-monetary penalties). \n162 Energy Policy Act of 2005, Pub. L. No. 109-58, 119 Stat. 594 (codified as amended in scattered sections \nof 42 U.S.C. and 16 U.S.C.). \n163 See Order No. 672, 114 FERC ¶ 61,104, at P 552 (emphasis added)."},{"page":56,"startToken":17722,"endToken":18016,"text":"52 \nFourth, the Joint Co-Location Developers’ suggestion that “PJM should adopt \nfinancial penalties sufficient to deter intentional gaming of transmission service \nsubscription”164 is misguided.  The penalty structure described in PJM’s Initial Brief and \nthe Illustrative Tariff is not intended to address gaming, which is subject to the oversight \nof FERC’s Office of Enforcement and Regulatory Accounting.  Gaming exposes entities, \nincluding individuals, to civil penalties of up to $1.5 million per violation per day, as well \nas other remedial actions under the Commission’s enforcement powers.165  Joint Co-\nLocation Developers propose that PJM similarly consider “intent” before determining \nwhether to impose disqualification penalties, and appear to suggest that disqualification \npenalties are more akin to violations of the Commission’s Anti-Market Manipulation Rule, \nwhich does require a showing of intent or recklessness.166  But while an Eligible \nCustomer’s failure to operate within the limits of their chosen level of transmission service \nmay have enforcement implications, the penalty scheme described in this proceeding is, \nfirst and foremost, based on incenting behavior that supports reliability.  \n5. \nRequiring disqualified Eligible Customers to take NITS on behalf of \nCo-Located Load enables necessary, proactive planning of the \nsystem to support reliable service   \nThe Joint Co-Location Developers suggest that PJM’s disqualification penalties are \nunnecessary, because “[t]ransmission owners always have the ability to manually \ndisconnect a facility in case of potential severe reliability risk.”167  This claim is \nfoundationally incorrect since neither PJM nor the Transmission Owner, will become aware \n \n164 Joint Co-Location Developers Reply Brief at 24-25. \n165 18 C.F.R. § 1b. \n166 18 C.F.R. § 1c.2 (Prohibition of electric energy market manipulation).  For a comparison with the \nSecurities Exchange Commission Rule, see 17 C.F.R. § 240.10b-5. \n167 Joint Co-Location Developers Reply Brief at 24."},{"page":57,"startToken":18016,"endToken":18276,"text":"53 \nof an improperly set-up protection scheme only after the misoperation incident, which will \nexpose the PJM interconnected system to risk.  Shifting responsibility away from the \nEligible Customer (and Co-Located Load) to appropriately limit their energy withdrawals \nis inconsistent with the reliable operation of the Transmission System. Protecting against \nsevere reliability risk is of course not simply a matter of Transmission Owners, sua sponte, \nconnecting and disconnecting facilities at will in a just-in-time manner.  It requires careful \ncoordination between PJM and Transmission Owners and data-driven system planning, \nwhere NITS plays a central role.168   \nThe contention that “transmission owners’ abilities to manually disconnect a \nfacility in case of severe reliability risk defangs any possible justification for PJM’s \n[penalty] regime”169 is not grounded in reality.  PJM is a centrally dispatched Balancing \nAuthority which uses Security Constrained Economic Dispatch to apply least-cost \nsolutions, while also controlling active transmission constraints over PJM’s 88,333 miles \nof transmission lines and ensuring PJM’s 67 million customers are reliably served.170  The \nconnectivity of the Bulk Power System means that when a transmission owner manually \ncuts load suddenly, without proper coordination, it can have disastrous and dangerous \ncascading system effects. \nAs the region’s Balancing Authority, PJM relies on NITS to ensure that generation \nis not bottled and is deliverable to load on a second-by-second basis, 365 days a year.171  \nFurthermore, NITS is incorporated into PJM’s system planning studies processes as well \n \n168 Wharton Aff. ¶¶ 10, 13-14. \n169 Joint Co-Location Developers Reply Brief at 26 (footnote omitted). \n170 Wharton Aff. ¶¶ 10-11. \n171 Wharton Aff. ¶ 10."},{"page":58,"startToken":18276,"endToken":18531,"text":"54 \nas PJM’s capacity market.  Put simply, PJM relies on NITS to proactively plan for the \noverall level of service needed.172  NITS provides a level of transparency to PJM’s system \nplanning functions that other types of transmission service do not afford. \n6. \nRevisions to the Illustrative Tariff language address certain \nintervenors’ critiques of disqualification penalties \nSeveral parties have sought reconsideration of the “strict liability” or “no fault” \napplication of the disqualification penalties.173  After careful consideration of parties’ \nconcerns about disqualification penalties applying regardless of cause or fault on a strict \nliability basis, PJM has made certain revisions to the Illustrative Tariff language, as set \nforth in Illustrative Tariff, Part XI, Subpart A, section 705.6(d) and Subpart B, \nsection 713.7(d) to permit, where appropriate, PJM to exercise discretion in determining \nwhen disqualification penalties are appropriate based on PJM’s assessment of factors \nincluding the reliability impact of the failure to curtail or shed load or the misoperation of \ncontrol technologies or protection system schemes.   \nSpecifically, PJM has included language that would allow PJM, based on the facts \nand circumstances present to determine that the Eligible Customer was not at fault for \n(1) not following established Load Shedding and Curtailment procedures; and/or (2) the \nmisoperation of the Eligible Customer’s necessary control technology or protection system.  \nThus, with these new provisions, the Eligible Customer will not be held liable for the \nactions of others.  \n \n172 See Abdulsalam Aff. ¶ 7. \n173 Joint Co-Location Developers Reply Brief at 23-27; Constellation Reply Brief at 18-21."},{"page":59,"startToken":18531,"endToken":18905,"text":"55 \nE. \nEffective Date  \n1. \nUpon Commission setting the terms and conditions for the new \ntransmission services, PJM can begin receiving requests for such \nservices and studying applications \nSeveral entities complain that a June 1, 2029 effective date for the Illustrative Tariff \nwould be unjust and unreasonable.174  In its Initial Brief, PJM explained that June 1, 2029, \nis a reasonable and appropriate effective date for these new transmission services.  PJM \ndetailed, with supporting testimony, a number of reasons why PJM cannot provide these \nnew transmission services until June 1, 2029.175  Stated another way, PJM discussed June 1, \n2029, as the effective date for the commencement of the transmission services.  PJM was \nnot specific as to when it could start accepting requests for these new services and \ncommence the appropriate studies. \nConsistent with this clarification that June 1, 2029, is the effective date for \nproviding the new transmission services, PJM further clarifies that, once the Commission \nestablishes the terms and conditions for the new transmission services—and the \nCommission has accepted the corresponding Tariff provisions, PJM is willing to start \naccepting requests for the new transmission services and processing such applications.  \nThis approach is reasonable.  PJM cannot start studying requests until it knows what it is \nstudying, which will be unsettled until the Commission fixes the terms and conditions.176  \nNonetheless, as discussed, PJM intends to get a headstart on establishing the details as to \n \n174 See Vistra Reply Brief at 5-7; Joint Co-Location Developers Reply Brief at 27-30. \n175 Initial Brief at 79-82; Horger Aff. ¶¶ 6-17. \n176 See 16 U.S.C. § 824e(a); PJM Interconnection, L.L.C., 175 FERC ¶ 61,137, at P 93 (“While the January \n2017 Order set an effective date of January 19, 2017 for PJM’s compliance filing, when the Commission acts \nunder section 206 of the FPA, it cannot make the rate effective under the filed rate doctrine until it sets out \nthe just and reasonable rate with the ‘necessary predictability’ so that the ‘numerical rate is specified clearly \nenough that customers know what the utility or pipeline will do.’” (citing Aera Energy LLC v. FERC, 789 \nF.3d 184, 190-92 (D.C. Cir. 2015))), order on requests for clarification & reh’g, 176 FERC ¶ 61,027 (2021)."},{"page":60,"startToken":18905,"endToken":19169,"text":"56 \nhow PJM would implement the Illustrative Tariff by soon commencing discussions with \nstakeholders regarding implementation details, to be stated in PJM Manuals, for these new \ntransmission services.  Part of those discussions likely will focus on the details for studying \nrequests for these new transmission services.  Thus, once the Commission fixes the terms \nand conditions for Interim NITS, Eligible Customers serving Co-Located Loads with \npending NITS applications would be able to apply for Interim NITS, and PJM would be \nable to study such requests. \nWith these clarifications, there is no need to establish a “[t]ransitional \n[m]echanism” for pending NITS applications, as Constellation suggests.177   \n2. \nA June 1, 2029 effective date is required to procure capacity for the \ncapacity backed Firm Contract Demand Transmission Service \nAs PJM explained in its Initial Brief, with supporting testimony, given current tight \nconditions, any Co-Located Load to be served through these new transmission services \nmust be reflected in the load forecasts used for RPM Auctions to ensure that PJM procures \nneeded capacity.178  As of the date of the filing of this brief, the Base Residual Auction for \nthe 2029/2030 Delivery Year, starting June 1, 2029, is the first Base Residual Auction in \nwhich the effects of these transmission services for Eligible Customers can be considered \n(including procuring necessary capacity for firm transmission services).179   \n \n177 See Constellation Reply Brief at 14. \n178 See Initial Brief at 79 (citing Horger Aff. ¶ 11). \n179 PJM explained why Incremental Auctions would not be the appropriate vehicle to procure capacity for \nthese services.  See Initial Brief at 80-81."},{"page":61,"startToken":19169,"endToken":19459,"text":"57 \n3. \nA June 1, 2029 effective date is required for the provision of these \nnew, curtailable services \nAs PJM explained in its Initial Brief, with supporting testimony, the provision of \nthe new transmission services will require significant changes to PJM’s core Markets and \nOperations systems.180  While some entities question this claim,181 the Independent Market \nMonitor for PJM recognizes that “PJM will be required to significantly modify core \nsystems, including software changes, to address, among other things, curtailing the load of \na customer’s co-located Load being served by two different levels of transmission service,” \nand that such software changes would be “pervasive[].”182 \nThe Joint Co-Location Developers fault PJM for failing to support the specific \ntimeline for software development.183  However, as PJM explained, because these are new \ntypes of transmission services to serve loads in PJM and the terms and conditions are \ncurrently unknown, a more exact development schedule cannot be determined at this \ntime.184   \n \n180 Initial Brief at 80 (citing Horger Aff. ¶ 16). \n181 See Joint Co-Location Developers Reply Brief at 29-30. \n182 IMM Reply Brief at 8. \n183 See Joint Co-Location Developers Reply Brief at 29. \n184 See Initial Brief at 81 & n.227 (“Changes to these systems will necessarily be dependent on vendor \navailability, the speed with which the system changes can be designed, and the interaction of these requested \nchanges with other competing priorities, including system changes to implement other Commission-directed \ninitiatives.  In particular, PJM anticipates that, implementing the proposed Curtailment priorities applicable \nto Interim NITS and Non-Firm Contract Demand Transmission Service, which can affect prices and dispatch \ninstructions, will require PJM to work with vendors to develop system automation that will avoid \nnon-optimal, untimely, and inefficient outcomes.” (citing Horger Aff. ¶ 16))."},{"page":62,"startToken":19459,"endToken":19811,"text":"58 \nF. \nIssues Beyond the Scope of This Proceeding \n1. \nAdvanced Energy United and Solar Energy Industries Association \nimproperly assert PJM should not study all interconnecting \ngenerators \nAdvanced Energy United and Solar Energy Industries Association contend that \n“PJM’s proposal appears to require all co-located generating facilities participating in the \nnew transmission services will be required to go through PJM’s interconnection queue,” \nand “subjecting non-exporting resources to the full interconnection queue imposes costs, \ndelays, and administrative burdens that are wholly disproportionate to the reliability \nbenefits achieved,” given that these resources’ “output is dedicated entirely to serving its \nco-located load and . . . will never inject power into the system.”185  The Commission can \neasily reject this contention both procedurally and on the merits.   \nFirst, the Show Cause Order did not direct PJM to alter the scope of its \ninterconnection studies for generators, and therefore this claim is beyond the scope of this \nproceeding.186   \nSecond, on the merits, to maintain system reliability, PJM must study all \ninterconnecting generators—but the scope of the study will be dictated by the \ninterconnection request.  Thus, for example, if an interconnection request specifies that the \nresource will be energy-only (not capacity) and does not intend to output energy onto the \n \n185 Advanced Energy/SEIA Reply Brief at 15-16. \n186 See, e.g., Midwest Indep. Sys. Operator, Inc., 156 FERC ¶ 61,034, at P 58 (2016) (rejecting arguments as \nbeyond the scope of a paper hearing), order on reh’g & clarification, 164 FERC ¶ 61,191 (2018); cf. N. Ind. \nPub. Serv. Co. v. Midcontinent Indep. Sys. Operator, Inc., 158 FERC ¶ 61,049, at P 60 n.122 (2017) (“As the \nCommission stated, it ‘has long established that compliance filings must be limited to the specific directives \nordered by the Commission.  The purpose of a compliance filing is to make the directed changes and the \nCommission’s focus in reviewing them is whether they comply with the Commission’s previously-stated \ndirectives.’” (quoting Cal. Indep. Sys. Operator Corp., 148 FERC ¶ 61,023, at P 23 n.27 (2014))); Midwest \nIndep. Transmission Sys. Operator, Inc., 125 FERC ¶ 61,156, at P 57 n.51 (2008) (same)."},{"page":63,"startToken":19811,"endToken":20112,"text":"59 \nTransmission System, because the equipment being connected behind that Point of \nInterconnection will still interact with the Transmission System, PJM would perform short \ncircuit and stability studies.  These studies would allow PJM to understand this interaction \nand identify any reliability concerns.  Further, such studies are required because PJM \ncannot assume that an interconnected generator will never output energy onto the system.  \nFor example, if the large load is never constructed, goes out of business, or changes its \ndemand level or profile, the dedicated generator would need to sell energy to the PJM \nsystem in order to be economic.  It is unrealistic to think the generator would go away if \nthe Co-Located Load disappeared.  In short, any generator synchronized to the grid must \nhave an agreement governing its parallel operation.   \n2. \nThe Commission should ignore other issues raised that are beyond \nthe scope of this paper hearing \nSeveral parties raised issues that are not within the scope of this paper hearing.  The \nShow Cause Order defined the scope of the paper hearing as “the appropriate rates, terms, \nand conditions” of the new transmission services.187  The Commission confined the other \nissues addressed in the Show Cause Order to the two compliance filings.  Thus, any order \non the paper hearing should ignore as beyond the scope issues regarding transmission \nservice for charging energy storage resources188 and Behind the Meter Generation.189   \n \n187 Show Cause Order, 193 FERC ¶ 61,217, at P 194 (“With respect to the new transmission services that we \nrequire, we establish paper hearing procedures to determine the appropriate rates, terms, and conditions of \nthose services.”). \n188 See Joint Co-Location Developers Reply Brief at 13-17. \n189 See PJM Interconnection, L.L.C., Responsive Brief of Industrial Customer Organizations and Amtrak, \nDocket Nos. EL25-49-000, et al., at 13-23 (Mar. 25, 2026)."},{"page":64,"startToken":20112,"endToken":20432,"text":"60 \nIII. \nREVISIONS TO ILLUSTRATIVE TARIFF FILED WITH INITIAL BRIEF \nTo aid the Commission in determining the appropriate terms and conditions for \nInterim NITS and the two Contract Demand Transmission Services and facilitate swift \nadoption of these new transmission services, PJM included as Attachment A to PJM’s \nInitial Brief Illustrative Tariff language that sets forth just and reasonable non-rate terms \nand conditions for the new transmission services available to Eligible Customers taking \nservice on behalf of Co-Located Loads.  The Illustrative Tariff also offered other \nparticipants the opportunity to review and provide comment on how to improve PJM’s \nterms and conditions for these transmission services.   \nUpon further review and in consideration of others’ comments, particularly those \nby the Indicated PJM Transmission Owners, PJM believes certain revisions to the \nIllustrative Tariff are warranted, as discussed below.  Attachment A to this reply brief shows \nthose revisions to the Illustrative Tariff in redline against the version included in PJM’s \nInitial Brief.  Specifically, PJM makes the following revisions to the Illustrative Tariff. \nIllustrative Tariff, Part XI, Subpart A – Interim Network Integration Transmission \nService \n• Section 702.3:  Consistent with the Show Cause Order’s holding that Interim NITS \n“would only be available to the extent PJM determines that it can provide some \nlevel of interim service reliably,”190 PJM has revised this section to provide that \nPJM will, in consultation with the affected Transmission Owner(s), determine how \nmuch Interim NITS “can be provided reliably to an Eligible Customer.”   \n• Section 702.4:  Given the key role of Transmission Owners in interconnecting loads \nto the system, PJM agrees with the comments of the Indicated PJM Transmission \nOwners191 that the technical requirements required before Interim NITS may \ncommence should include any technical requirements identified by applicable \nTransmission Owner(s), and is adding this in the list of technical requirements. \n \n190 Show Cause Order, 193 FERC ¶ 61,217, at P 200. \n191 See Indicated PJM Transmission Owners Response at 13."},{"page":65,"startToken":20432,"endToken":20904,"text":"61 \n• Section 703.2:  PJM revises this section to clarify that, prior to providing an \nEligible Customer NITS for a given Co-Located Load arrangement, to the extent \nan Eligible Customer designates a new Co-Located Load, or increases the size of \nthe designated Co-Located Load, such “new Co-Located Load or increase to a \ndesignated Co-Located Load shall be studied pursuant to a new Application.”  In \nother words, to the extent, the Eligible Customer changes the Co-Located Load to \nbe served by a given service request prior to the commencement of NITS (e.g., \nduring the period in which Interim NITS may be provided), PJM will need to study \nsuch change. \n• Section 703.3:  This section requires the Eligible Customer to annually update PJM \nas to the specifics of the Co-Located Load and Co-Located Generating Facility, and \nimposes an ongoing obligation to provide PJM with timely notice of any material \nchange to the Co-Located Load and Co-Located Generating Facility.  PJM agrees \nwith the comments of the Indicated PJM Transmission Owners, that the applicable \nTransmission Owner(s) should also receive such notice, and has revised the section \nto require the Eligible Customer to provide notice to both PJM and the applicable \nTransmission Owner(s).  In addition, PJM adds a reference to the PJM Manuals for \ngreater description of what would constitute a “material change.”192 \n• Section 705.1:  PJM agrees with the Indicated PJM Transmission Owners that both \nthe Eligible Customer and the applicable Transmission Owner(s) will play key roles \nin implementing any Curtailments, and therefore is revising section 705.1 to \nprovide that PJM will also notify the applicable Transmission Owner(s):  “Prior to \nthe Service Commencement Date, the Eligible Customer shall demonstrate its \nability to fully comply with the Load Shedding and Curtailment procedures \npursuant to this section 705, and the Service Agreement for Interim Network \nIntegration Transmission Service.  The Eligible Customer shall implement any \nLoad Shedding and/or Curtailment directive given by Transmission Provider.  To \nthe extent practicable, the Transmission Provider will notify the Eligible Customer \nand applicable Transmission Owner(s) of any Curtailment in a timely manner.”   \n• Section 705.5:  Given the role of Transmission Owners in managing their \ntransmission systems and interconnecting loads, PJM agrees with the Indicated \nPJM Transmission Owners193 that any functional modification to an installed \nnecessary control technologies and protection systems required to provide Interim \nNITS should be approved by PJM “and coordinated with the affected Transmission \nOwner(s).” \n• Section 705.6:  As discussed above in Section II.D.6, PJM agrees with the \ncomments that the consequences for failure to follow PJM instructions or \nmisoperation of the necessary control technology and protection systems should \narise only when the Eligible Customer (or the served Co-Located Load) is actually \n \n192 See Indicated PJM Transmission Owners Response at 14. \n193 See Indicated PJM Transmission Owners Response at 16."},{"page":66,"startToken":20904,"endToken":21322,"text":"62 \nthe party at fault.  Accordingly, PJM is including a new section 705.6(d) to establish \nthis rule. \n• Section 706.2:  PJM agrees with the Indicated PJM Transmission Owners that \nTransmission Owners should not pay redispatch costs caused by the Eligible \nCustomer,194 and is revising section 706.2 accordingly.  \nIllustrative Tariff, Part XI, Subpart B – Contract Demand Transmission Services \n• Section 710.4:  Consistent with the revision to section 702.4 described above, PJM \nis revising the list of technical requirements an Eligible Customer must meet before \nContract Demand Transmission Service may commence to include any technical \nrequirements identified by applicable Transmission Owner(s).   \nPJM is also revising technical requirements to include the “demonstration that the \nEligible Customer has operational control to respond to operating instructions from \nthe Transmission Provider to reduce energy withdrawals or disconnect the Co-\nLocated Load within five (5) minutes or as specified in the PJM Manuals.”  PJM \ninadvertently omitted this temporal requirement in the Initial Brief’s Illustrative \nTariff.  However, this requirement is necessary in order for the Contract Demand \nTransmission Services to be curtailable and the loads to be dispatchable and \nimplements the rule in section 713.1 that “Eligible Customers must respond to any \nreal time instruction to curtail or otherwise reduce load within five (5) minutes.”  \nPJM’s markets operate in five-minute intervals, and they require behavior \nmodification to occur correspondingly.  This language also mirrors the technical \nrequirements for Interim NITS in section 702.4. \n• Section 710.5:  PJM is adding a proviso that nothing in the description of the \nEligible Customer facilities in section 710.5 “precludes the installation of any \nTransmission Owner-side protection facilities.”195 \n• Section 711.3:  Consistent with the revision to section 703.3 described above, PJM \nis revising the ongoing obligation to provide PJM with timely notice of any material \nchange to the Co-Located Load and Co-Located Generating Facility to provide that \nthe applicable Transmission Owner(s) should also receive such notice.  In addition, \nPJM adds a reference to the PJM Manuals for greater description of what would \nconstitute a “material change.”196 \n• Section 712.2:  PJM agrees with the Indicated PJM Transmission Owners that the \napplicable Transmission Owner(s) should be notified of any request for Non-Firm \nContract Demand Transmission Service and is revising section 712.2 accordingly:  \n“After receiving a request for Non-Firm Contract Demand Transmission Service, \n \n194 See Indicated PJM Transmission Owners Response at 17. \n195 See Indicated PJM Transmission Owners Response at 20. \n196 See Indicated PJM Transmission Owners Response at 20-21."},{"page":67,"startToken":21322,"endToken":21747,"text":"63 \nthe Transmission Provider shall determine on a non-discriminatory basis, and in \naccordance with the PJM Manuals, whether studies are needed to assess whether \nthe Transmission System has sufficient available capacity to provide Non-Firm \nContract Demand Transmission Service, and if so, which studies are appropriate.  \nTransmission Provider maywill notify the affected Transmission Owner of such \nrequest for Non-Firm Contract Demand Transmission Service, and the \nTransmission Provider will also consider the results of any studies conducted by \nthe affected Transmission Owner(s).” \n• Section 713.1:  PJM agrees with the Indicated PJM Transmission Owners that both \nthe Eligible Customer and the applicable Transmission Owner(s) will play key roles \nin implementing any curtailments, and therefore is revising section 713.1 to provide \nthat PJM will also notify the applicable Transmission Owner(s):  “Prior to the \nService Commencement Date, the Eligible Customer shall demonstrate its ability \nto fully comply with the Load Shedding and Curtailment procedures pursuant to \nthis section 713, the PJM Manuals, and the Service Agreement for Contract \nDemand Transmission Service, as provided in Attachment F-4.  The Eligible \nCustomer shall implement any Load Shedding and/or Curtailment directive given \nby Transmission Provider.  To the extent practicable, the Transmission Provider \nwill notify the Eligible Customer and applicable Transmission Customer(s) of any \nCurtailment in a timely manner.  Eligible Customers must respond to any real time \ninstruction to curtail or otherwise reduce load within five (5) minutes.  Curtailments \nwill be made on a non-discriminatory basis.”   \n• Section 713.7:  As discussed above in Section II.D.6, PJM agrees with the \ncomments that the consequences for failure to follow PJM instructions or \nmisoperation of the necessary control technology and protection systems should \narise only when the Eligible Customer (or the served Co-Located Load) is actually \nthe party at fault.  Accordingly, PJM is including a new section 713.7(d) to establish \nthis rule. \n• Section 714.3:  PJM agrees with the Indicated PJM Transmission Owners that \nTransmission Owners should not pay redispatch costs caused by the Eligible \nCustomer,197 and is revising section 714.3 accordingly.  \nIllustrative Tariff, Attachment F-3A – Service Agreement For Regional Network \nIntegration Transmission Service And/or Interim Network Integration Transmission \nService (For Co-Located Load) \n• Section 2.0:  PJM agrees with the Indicated PJM Transmission Owners that there \nis a typo and is removing an errant “not” as follows:  “Until the facilities listed \nabove are completed, the Transmission Owner provides a Notice of Completion to \nPJM, and the facilities listed above are in service, the Eligible Customer may \n \n197 See Indicated PJM Transmission Owners Response at 22."},{"page":68,"startToken":21747,"endToken":22115,"text":"64 \nnotonly receive Interim Regional Network Integration Transmission Service \nsubject to the conditions of Part XI of the Tariff.” \nIllustrative Tariff, Part III – Network Integration Transmission Service \n• Section 29.2(x):  As PJM discussed in its Initial Brief, to ensure PJM is aware of \nand properly studies any Co-Located Loads to be served via NITS, PJM included \nan additional set of Application Procedures for Eligible Customers taking service \non behalf of Co-Located Load seeking NITS in Part III.198  However, upon \nreflection and based on comments received on PJM’s compliance filing, PJM is \nchanging the provision as follows:  “For Eligible Customers taking service on \nbehalf of Co-Located Load: (1) a demonstration that  the Co-Located Load on \nbehalf of which the Eligible Customer is seekingtaking to obtain service and the \nCo-Located Generating Facility are located on the same side of the Delivery Point \nto the Transmission Provider’s Transmission System as the Co-Located Load . . . .” \nIV. \nADDITIONAL ILLUSTRATIVE TARIFF LANGUAGE TO INTEGRATE \nNEW TRANSMISSION SERVICES AND RESERVATION OF RIGHTS TO \nFURTHER SUPPLEMENT FILING  \nAs PJM discussed in its Initial Brief, the addition of three new transmission services \nto offer new means for Eligible Customers to serve Co-Located Load, requires complex \nrevisions to PJM’s transmission planning, interconnection, and operational procedures.  \nPJM cautioned that the Illustrative Tariff does not represent all the potential tariff language \nand revisions necessary to implement these new services and fully integrate them into \nPJM’s planning, interconnection, and operational processes.199  Additional changes are and \nwill be necessary to fully integrate these new services into PJM, including into PJM’s \nenergy, ancillary services, and capacity markets.200  Indeed, PJM will need to develop Tariff \nprocedures (and implementing PJM Manual language) for taking and serving requests for \nNon-Firm Contract Demand Transmission Service in advance of the service request period.  \n \n198 Illustrative Tariff, Part III (Network Integration Transmission Service), section 29.2(x). \n199 See Initial Brief at 78-79. \n200 For example, PJM will need to revise its existing Tariff provisions addressing Real-time and Day-ahead \nEnergy Market settlements to account for the new transmission services given that the current-effective \nprovisions generally determine charges based on Network Load, and load served by Firm and Non-Firm \nContract Demand Transmission Service cannot be Network Load."},{"page":69,"startToken":22115,"endToken":22386,"text":"65 \nPJM will continue to review its Governing Documents and reserves the right to supplement \nits filing with additional terms and conditions needed to effectuate these new transmission \nservices to allow the paper hearing the benefit of such additional information.  And, PJM \nrecently initiated a new stakeholder body, the Connect and Manage Senior Task Force, that \nwill examine issues that are very likely to bear on the terms and conditions of these new \ntransmission services.   \nHowever, since filing its Initial Brief, PJM has determined that changes to the \nAuction Revenue Rights rules will need to be modified to recognize that Firm Contract \nDemand Transmission Service customers will contribute towards enhancing and \nmaintaining the Transmission System and therefore should have the right to request \nAuction Revenue Rights.  As shown in the updated Illustrative Tariff in Attachment A to \nthis filing, PJM believes that Eligible Customers taking Firm Contract Demand \nTransmission Service should be treated similarly as Firm Point-to-Point Transmission \nService customers for purposes of receiving Auction Revenue Rights.  Accordingly, \nEligible Customers taking Firm Contract Demand Transmission Service should be allowed \nto request Auction Revenue Rights in stage 2 of the allocation process, which is when Firm \nPoint-to-Point Transmission Service customers are allowed to request Auction Revenue \nRights.  To effectuate this, PJM has provided a revision to the existing language in \nOperating Agreement, Schedule 1, section 7.4.2(d) to insert “Eligible Customers taking \nFirm Contract Demand Transmission Service” alongside “Transmission Customers,” i.e., \nFirm Point-to-Point Transmission Service customers.  Plus, PJM has included what would \nbe a new Operating Agreement, Schedule 1, section 7.4.2(l) to detail the Auction Revenue"},{"page":70,"startToken":22386,"endToken":22589,"text":"66 \nRights rules specific to Eligible Customers taking Firm Contract Demand Transmission \nService.201 \nV. \nDOCUMENT ENCLOSED  \n \nIn addition to this reply brief, PJM encloses the following: \n1. \nAttachment A: Redlines on Reply Brief to Illustrative Language for New \nTariff, Part XI; Attachments F-3A and F-4; and Other \nIllustrative Tariff Revisions \nVI. \nCONCLUSION  \nPJM respectfully requests that the Commission find that the Illustrative Tariff, as \nrevised through this reply brief, forms part of a just and reasonable replacement rate in \naccordance with the requirements of the Show Cause Order. \nRespectfully submitted, \n/s/ Ryan J. Collins \n \nCraig Glazer \nVice President – Federal Government Policy \nPJM Interconnection, L.L.C. \n1200 G Street, NW, Suite 600 \nWashington, DC  20005 \n(202) 423-4743 \ncraig.glazer@pjm.com \n \nMark J. Stanisz \nAssociate General Counsel \nThomas DeVita \nAssociate General Counsel \nPJM Interconnection, L.L.C.  \n2750 Monroe Blvd, \nAudubon, PA  19403 \n(610) 666-8800 \nmark.stanisz@pjm.com \nthomas.devita@pjm.com \nRyan J. Collins \nRuth M. Porter \nWright & Talisman, P.C. \n1200 G Street, NW, Suite 600 \nWashington, DC  20005 \n(202) 393-1200 \ncollins@wrightlaw.com \nporter@wrightlaw.com \n \n \n \n \n \n \n \n \nCounsel for \nPJM Interconnection, L.L.C. \nApril 24, 2026 \n \n201 Illustrative Tariff, Operating Agreement, Schedule 1, section 7.4.2(l)."},{"page":71,"startToken":22589,"endToken":22612,"text":"Attachment A \n \n \n \n \n \n \nRedlines on Reply Brief to \nIllustrative Language for New Tariff, Part XI; \nAttachments F-3A and F-4; and \nOther Illustrative Tariff Revisions"},{"page":72,"startToken":22612,"endToken":23024,"text":"1 \nTariff, Part XI \nTransmission Services Available for Eligible Customers Taking Service  \non Behalf of Co-Located Loads \n \nSubpart A – Interim Network Integration Transmission Service \n700 Provision of Interim Network Integration Transmission Service \nThe Transmission Provider may provide Interim Network Integration Transmission Service to an \nEligible Customer requesting Network Integration Transmission Service on behalf of a Co-\nLocated Load pursuant to the applicable terms and conditions contained in the Tariff and the \nService Agreement for Interim Network Integration Transmission Service, which is provided in \nAttachment F-3A.  PJMSettlement shall be the Counterparty to the Interim Network Integration \nTransmission Service transactions under this Tariff. \nRequests for Interim Network Integration Transmission Service must be made through the \nTransmission Provider.  These requests shall require the filing of an Application as set forth in \nTariff, Part XI, Subpart A, section 702 and be submitted in accordance with the applicable terms \nand conditions in the Tariff. \n \n \n701 Nature of Interim Network Integration Transmission Service \n701.1 Scope of Service  \nInterim Network Integration Transmission Service is a transmission service that allows an Eligible \nCustomer taking service on behalf of a Co-Located Load that has requested Network Integration \nTransmission Service pursuant to Tariff, Part III, to receive transmission service on behalf of a \nCo-Located Load on a non-firm, interruptible basis for the period until the transmission upgrades \nrequired to provide the requested level of Network Integration Transmission Service are completed \nand placed in service.  Such upgrades required to provide the requested level of Network \nIntegration Transmission Service, along with the expected in-service dates, shall be set forth in the \nService Agreement for Interim Network Integration Transmission Service.   \nOnce the required transmission upgrades are completed and placed in service, according to the \nterms of the Service Agreement for Interim Network Integration Transmission Service in \nAttachment F-3A, the transmission service provided to the Eligible Customer will automatically \nconvert from Interim Network Integration Transmission Service to Network Integration \nTransmission Service.  As a result, the Co-Located Load will be designated as Network Load under \nTariff, Part III, section 31.1. \nAn Eligible Customer taking transmission service on behalf of a Co-Located Load may not take \nNetwork Integration Transmission Service or Interim Network Integration Transmission Service \nfor that Co-Located Load at the same time it is taking Firm Contract Demand Transmission Service \nor Non-Firm Contract Demand Transmission Service on behalf of that Co-Located Load. \nThe Eligible Customer taking Interim Network Integration Transmission Service must obtain or \nprovide Ancillary Services pursuant to Tariff, Part I, section 3."},{"page":73,"startToken":23024,"endToken":23395,"text":"2 \n701.2 Interim Network Integration Transmission Service  \nThe Transmission Provider may provide non-firm, interruptible transmission service over the \nTransmission System to the Eligible Customer for the delivery of capacity and energy to serve the \nCo-Located Load. \n701.3 Restrictions on Use of Service \nThe Eligible Customer shall not use Interim Network Integration Transmission Service for (i) sales \nof capacity and energy to loads other than the Co-Located Load designated in its Service \nAgreement for Interim Network Integration Transmission Service, or (ii) direct or indirect \nprovision of transmission service by the Eligible Customer to third parties.   \n701.4 Termination of Interim Network Integration Transmission Service \nThe provision of Interim Network Integration Transmission Service shall terminate upon \ncompletion of all upgrades identified in the Service Agreement for Interim Network Integration \nTransmission Service necessary to provide Eligible Customer with Network Integration \nTransmission Service under Tariff, Part III, according to the terms of the Service Agreement.   \n \n \n702 Initiating Service \n702.1 Conditions Precedent for Receiving Service \nSubject to the terms and conditions of Tariff, Part XI, the Transmission Provider may provide \nInterim Network Integration Transmission Service to any Eligible Customer taking transmission \nservice on behalf of Co-Located Load, provided that: \n(i) \nThe Eligible Customer has been designated to take transmission service on behalf \nof a Co-Located Load in the relevant Application, Service Agreement, or the \nGeneration Interconnection Agreement for the Co-Located Generating Facility; \n(ii) \nThe Eligible Customer has provided the information specified in, and otherwise \ncomplied with, the “PJM Credit Policy” set forth in Tariff, Attachment Q hereto;   \n(iii) \nThe Eligible Customer executes a Service Agreement for Interim Network \nIntegration Transmission Service with the Transmission Provider pursuant to Tariff, \nAttachment F-3A, or requests in writing that the Transmission Provider file a \nproposed unexecuted Service Agreement for Interim Network Integration \nTransmission Service;  \n(iv) \nThe Eligible Customer has certified, in accordance with the PJM Manuals, that it is \nwilling and able to limit energy withdrawals from the Transmission System when \nrequested by the Transmission Provider; and \n(v) \nAn Eligible Customer requesting Interim Network Integration Transmission \nService and taking Interim Network Integration Transmission Service shall \notherwise execute, if necessary, and comply with the PJM Governing Agreements. \nThe Eligible Customer shall submit an Application under this section 702."},{"page":74,"startToken":23395,"endToken":23887,"text":"3 \n702.2 Application Procedures \nAn Eligible Customer seeking Network Integration Transmission Service may apply for Network \nIntegration Transmission Service and Interim Network Integration Transmission Service at the \nsame time.  However, an Eligible Customer shall not apply for Interim Network Integration \nService without applying for Network Integration Transmission Service. \nTo apply for Interim Network Integration Transmission Service, an Eligible Customer must pay a \nstudy fee under Tariff, Part XI, Subpart A, section 704.2, which is in addition to the study fee \nrequired under an Application for Network Integration Transmission Service under Tariff, Part III, \nsection 32.2. \n702.3 Determination of Whether Interim Network Integration Transmission Service Can Be \nReliably Provided \nThe Transmission Provider, in consultation with the affected Transmission Owner(s), will \ndetermine the amount of Interim Network Integration Transmission Service that can be provided \nreliably to an Eligible Customer, including through the use of temporary solutions, while \nmaintaining the reliability of the Transmission System.  This determination will consider the \nresults of the study procedures set forth in Tariff, Part XI, Subpart A, section 704. \n702.4 Technical Requirements Prior to Commencement of Service \nInterim Network Integration Transmission Service shall not commence until the Transmission \nProvider, the affected Transmission Owner(s), and the Eligible Customer, or a third party, have \ncompleted installation of all equipment specified under the Service Agreement for Interim \nNetwork Integration Transmission Service, consistent with Good Utility Practice and any \nadditional requirements reasonably and consistently imposed to ensure the reliable operation of \nthe Transmission System.  The Transmission Provider and the affected Transmission Owner(s) \nshall exercise reasonable efforts, in coordination with the Eligible Customer, to complete such \narrangements as soon as practicable taking into consideration the Service Commencement Date. \nThese technical requirements include, but are not limited to: (i) installation of necessary hardware \nand software to limit energy withdrawals, including metering equipment; (ii) provision of an \noperational contact and backup contact for the Eligible Customer, available twenty-four (24) hours \na day and seven (7) days a week; (iii) certification from the Eligible Customer that it is staffed \nwith PJM Certified Operators pursuant to PJM Manual 40; (iv) demonstration from the Eligible \nCustomer of its ability to receive voice and electronic signals from the Transmission Provider; (v) \ndemonstration that the Eligible Customer has operational control to respond to operating \ninstructions from the Transmission Provider to reduce or disconnect the Co-Located Load within \nfive (5) minutes or as specified in PJM Manuals; (vi) satisfaction of any technical requirements \nidentified by the applicable Transmission Owner(s); and (vii) demonstration that the Eligible \nCustomer has operational control of the necessary control technologies and protection systems set \nforth in Tariff, Part XI, Subpart A, section 705, as applicable.   \n702.5 Eligible Customer Facilities \nThe provision of Interim Network Integration Transmission Service shall be conditioned upon the \nEligible Customer constructing, maintaining, and operating the facilities on its side of the Delivery \nPoint necessary to reliably deliver capacity and energy from the Transmission Provider’s"},{"page":75,"startToken":23887,"endToken":24331,"text":"4 \nTransmission System to the Eligible Customer or, with respect to service provided pursuant to a \nstate required retail access program, for otherwise arranging for the delivery of its energy from the \nDelivery Point or interconnection.  The Eligible Customer shall be solely responsible for \nconstructing or installing all facilities on the Eligible Customer’s side of such Delivery Point or, \nwith respect to service provided pursuant to a state required retail access program, for otherwise \narranging for the delivery of its energy from the Delivery Point or interconnection. \n702.6 Filing of Service Agreement \nThe Transmission Provider will file the Service Agreement for Interim Network Integration \nTransmission Service, provided in Attachment F-3A, with the Commission in compliance with \napplicable Commission regulations. \n \n \n703 Designation of Co-Located Load \n703.1 Co-Located Load \nThe Eligible Customer must designate the individual Co-Located Load on whose behalf the \nTransmission Provider will provide Interim Network Integration Transmission Service.  \nThe Co-Located Load shall be specified in the Service Agreement for Interim Network Integration \nTransmission Service except with respect to loads served pursuant to state required retail access \nprograms for which the Transmission Customer shall provide information regarding Network \nLoads using the Transmission Provider’s specified electronic information system for such \nprograms in accordance with the Service Agreement. \n703.2 New Co-Located Loads or Increase to Designated Co-Located Loads Connected with the \nTransmission Provider  \nPrior to the Service Commencement Date of Network Integration Transmission Service, if an \nEligible Customer designates a new Co-Located Load, or increases the size of the designated Co-\nLocated Load, the new Co-Located Load or increase to a designated Co-Located Load shall be \nstudied pursuant to a new Application.   \n703.3 Information Updates \nThe Eligible Customer shall provide the Transmission Provider with annual updates of (i) the \ndemand characteristics of the Co-Located Load, and (ii) the supply characteristics of the Co-\nLocated Generating Facility, both consistent with those included in its Application for Network \nIntegration Transmission Service under Tariff, Part III, Section 31.6. \nIn addition, the Eligible Customer also shall have an ongoing obligation to provide the \nTransmission Provider and applicable Transmission Owner(s) with timely written or electronic \nnotice of material changes, as discussed in the PJM Manuals, in the foregoing sentence as well as \nany other information listed in Tariff, Part XI, Subpart A, section 702 or provided in its Application \nfor Network Integration Transmission Service pursuant to Tariff, Part III, section 31.6 relating to \nthe Eligible Customer’s Co-Located Load or other aspects of its facilities or operations affecting \nthe Transmission Provider’s ability to provide reliable service.  Failure to timely inform the \nTransmission Provider of a material change in (i) the demand characteristics of the Co-Located"},{"page":76,"startToken":24331,"endToken":24758,"text":"5 \nLoad, or (ii) the supply characteristics of the Co-Located Generating Facility may constitute a \nbreach of the Eligible Customer’s Service Agreement. \n \n \n704 Study Procedures for Interim Network Integration Transmission Service Requests \n704.1 Notice of Need for Study \nAfter receiving a request for Interim Network Integration Transmission Service, the Transmission \nProvider shall determine on a non-discriminatory basis whether additional studies are needed \nbeyond what was required to evaluate the Eligible Customer’s request for Network Integration \nTransmission Service.  \nIf the Transmission Provider determines that additional studies are necessary to evaluate the \nrequested service, it shall inform the Eligible Customer of those studies as soon as practicable.  In \nsuch cases, the Transmission Provider shall, within thirty (30) days of receipt of a Completed \nApplication, tender an Application and Studies Agreement pursuant to which the Eligible \nCustomer shall agree to reimburse the Transmission Provider for the required studies.  For a service \nrequest to remain a Completed Application, the Eligible Customer shall execute the Application \nand Studies Agreement and return it to the Transmission Provider within fifteen (15) days and \nprovide a study fee pursuant to Tariff, Part XI, Subpart A, section 704.2.  If the Eligible Customer \nelects not to execute the Application and Studies Agreement, its Application for Interim Network \nIntegration Transmission Service shall be deemed withdrawn and its study fee shall be returned \nwith interest. \n704.2 Study Fee for Interim Network Integration Transmission Service \nEligible Customer shall pay a study fee, as determined by the Transmission Provider, to apply for \nInterim Network Integration Transmission Service. \n \n \n705 Load Shedding and Curtailments \n705.1 General \nPrior to the Service Commencement Date, the Eligible Customer shall demonstrate its ability to \nfully comply with the Load Shedding and Curtailment procedures pursuant to this section 705, and \nthe Service Agreement for Interim Network Integration Transmission Service.  The Eligible \nCustomer shall implement any Load Shedding and/or Curtailment directive given by Transmission \nProvider.  To the extent practicable, the Transmission Provider will notify the Eligible Customer \nand applicable Transmission Owner(s) of any Curtailment in a timely manner.  The Eligible \nCustomer must respond to any real time instructions to curtail or otherwise reduce load within five \n(5) minutes.  Curtailments will be made on a non-discriminatory basis.  Any requests by the \nTransmission Provider to Curtail will be consistent with Good Utility Practice. \n705.2 Curtailment of Interim Network Integration Transmission Service \nInterim Network Integration Transmission Service shall be Curtailed before Firm Contract \nDemand Transmission Service and Network Integration Transmission Service.  The Transmission \nProvider may curtail Interim Network Integration Transmission Service prior to dispatching the"},{"page":77,"startToken":24758,"endToken":25240,"text":"6 \nPre-Emergency Load Response Program as further set forth in the PJM Manuals, or in response to \na transfer capability shortage as a result of system reliability conditions.  \n705.3 Load Shedding \nTo the extent that a system contingency exists on the Transmission Provider’s Transmission \nSystem and the Transmission Provider determines that it is necessary for the Transmission Owners \nand the Eligible Customer taking Interim Network Integration Transmission Service to shed load, \nthe Eligible Customer and the Transmission Owners shall shed load in accordance with previously \nestablished procedures under the Service Agreement for Interim Network Integration \nTransmission Service and the PJM Manuals. \n705.4 System Reliability \nNotwithstanding any other provisions of this Tariff, the Transmission Provider reserves the right, \nconsistent with Good Utility Practice and on a not unduly discriminatory basis, to Curtail Interim \nNetwork Integration Transmission Service without liability on the Transmission Provider’s part \nfor the purpose of making necessary adjustments to, changes in, or repairs on its lines, substations \nand facilities, and in cases where the continuance of Interim Network Integration Transmission \nService would endanger persons or property.  In the event of any adverse condition(s) or \ndisturbance(s) on the Transmission Provider’s Transmission System or on any other system(s) \ndirectly or indirectly interconnected with the Transmission Provider’s Transmission System, the \nTransmission Provider, consistent with Good Utility Practice, also may Curtail Interim Network \nIntegration Transmission Service in order to (i) limit the extent or damage of the adverse \ncondition(s) or disturbance(s); (ii) prevent damage to generating or transmission facilities; or (iii) \nexpedite restoration of service.  The Transmission Provider will give the Eligible Customer as \nmuch advance notice as is practicable in the event of such Curtailment.    \n705.5 Necessary Control Technologies and Protection Systems \nTo ensure protection of the Transmission System, and to ensure that the Eligible Customer taking \nInterim Network Integration Transmission Service on behalf of a Co-Located Load limits its \nenergy withdrawals from the Transmission System to its approved level of Interim Network \nIntegration Transmission Service, including during a period in which the Transmission Provider \nhas directed Curtailment or Load Shedding, prior to the Service Commencement Date, the \nTransmission Provider, affected Transmission Owner(s), and the Eligible Customer shall establish \nnecessary control technologies and protection systems in accordance with the PJM Manuals, which \nmay include a Remedial Action Scheme, for each Service Agreement for Interim Network \nIntegration Transmission Service.  The necessary control technologies and protection systems \nmust be developed in accordance with the PJM Manuals and be approved by the Transmission \nProvider.  The necessary control technologies and protection systems may be functionally \nmodified from time to time in accordance with the PJM Manuals.  Any functional modification to \nthe necessary control technologies and protection systems must be developed with the affected \nTransmission Owner(s) and, before taking effect, such functional modification must be approved \nby the Transmission Provider and coordinated with the affected Transmission Owner(s)."},{"page":78,"startToken":25240,"endToken":25632,"text":"7 \n705.6 Consequences of Failure to Follow Instructions or Misoperation of Necessary Control \nTechnologies and Protection Systems \n(a) \nIn the first instance that an Eligible Customer fails to respond to established Load \nShedding and Curtailment procedures, as set forth in this section 705, the Eligible Customer shall \nbe disqualified from taking Interim Network Integration Transmission Service. \n(b) \nIn the first instance that a necessary control technology or protection system for a \ngiven Service Agreement misoperates, the Eligible Customer shall be prohibited from taking \ntransmission service under its Service Agreement or otherwise withdrawing energy from the \nTransmission System for a period of up to one hundred and twenty (120) days from such event, \nwhich may be shortened or extended per mutual agreement, to allow for an analysis of the such \nevent, which may be shortened or extended per mutual agreement, to allow for an analysis of the \noperational performance of the necessary control technologies and protection systems.   \nIn the second instance that an Eligible Customer’s necessary control technology or protection \nsystem associated with a Service Agreement misoperates, the Eligible Customer shall be \ndisqualified from taking Interim Network Integration Transmission Service. \n(c) \nFollowing disqualification in accordance with subsections (a) or (b) above, to \nreceive transmission service on behalf of the subject Co-Located Load, the Eligible Customer may \nonly take Network Integration Transmission Service and such service may only commence after \nall upgrades necessary for the Transmission Provider to provide Network Integration Transmission \nService are placed into service.   \n(d) \nThe Transmission Provider may, in its sole discretion and on a prospective basis \nonly, determine that the facts and circumstances demonstrate that Eligible Customer was not at \nfault for (i) an Eligible Customer’s, or the Co-Located Load’s served by the Eligible Customer, \nfailure to implement Load Shedding and Curtailment procedures or (ii) a misoperation of the \nEligible Customer’s necessary control technology or protection system associated with a Service \nAgreement.  In the event, the Transmission Provider makes such a no fault determination, the \nprecipitating event shall not be considered toward disqualification under this section 705.     \n705.7 Penalty for Unreserved Use of Interim Network Integration Transmission Service \n[Reserved] \n \n \n706 Rates and Charges \n706.1 Monthly Demand Charge \n[Reserved] \n706.2 Redispatch Charge \nThe Eligible Customer and each Transmission Owner shall pay any redispatch costs as set forth in \nTariff, Attachment K. \n706.3 Stranded Cost Recovery"},{"page":79,"startToken":25632,"endToken":25953,"text":"8 \nAny Transmission Owner may seek to recover stranded costs from the Eligible Customer pursuant \nto this Tariff in accordance with the terms, conditions and procedures set forth in FERC Order No. \n888.  However, the Transmission Owner must separately file any proposal to recover stranded \ncosts under section 205 of the Federal Power Act. \n706.4 Other Charges \nEligible Customer shall pay administrative services charges under Tariff, Schedule 1A; Tariff, \nSchedule 9; and Tariff, Schedule 10, consistent with the charges assessed to loads taking Network \nIntegration Transmission Service. \nEligible Customer shall pay Ancillary Services charges in accordance with Tariff, Part I, section 3.  \nEligible Customer shall pay Black Start Service charges in accordance with Tariff, Schedule 6A. \n \n \n707 Operating Agreement \n707.1 Operation under The Operating Agreement \nThe Eligible Customer shall plan, construct, operate, and maintain its facilities in accordance with \nGood Utility Practice and in conformance with the Operating Agreement.   \nThe terms and conditions under which the Eligible Customer shall operate its facilities and the \ntechnical and operational matters associated with the implementation of Tariff, Part XI shall be \nspecified in the Operating Agreement.   \nThe Operating Agreement shall provide for the Eligible Customer and Transmission Provider to \n(i) operate and maintain equipment necessary for integrating the Eligible Customer within the \nTransmission Provider’s Transmission System (including, but not limited to, remote terminal units, \nmetering, communications equipment and relaying equipment); (ii) transfer data between the \nTransmission Provider and the Eligible Customer (including, but not limited to, heat rates and \noperational characteristics of Network Resources, generation schedules for units outside the \nTransmission Provider’s Transmission System, interchange schedules, required unit outputs for \nredispatch, voltage schedules, loss factors and other real time data); (iii) use software programs \nrequired for data links and constraint dispatching; (iv) exchange data on forecasted loads and \nresources necessary for long-term planning; and (v) address any other technical and operational \nconsiderations required for implementation of Tariff, Part XI, including scheduling protocols."},{"page":80,"startToken":25953,"endToken":26379,"text":"9 \nSubpart B – Contract Demand Transmission Services \n708 Provision of Contract Demand Transmission Services \n(a) \nThe Transmission Provider will provide Firm Contract Demand Transmission \nService or Non-Firm Contract Demand Transmission Service, or both, to an Eligible Customer \ntaking service on behalf of a Co-Located Load pursuant to the applicable terms and conditions \ncontained in Tariff, Part XI and the Service Agreement for Contract Demand Transmission \nServices, provided in Attachment F-4.  Firm Contract Demand Transmission Service or Non-Firm \nContract Demand Transmission Service are for an Eligible Customer taking service on behalf of a \nCo-Located Load that is willing and able to limit withdrawals of energy from the Transmission \nSystem when required by the Transmission Provider. \n \n(b) \nFirm Contract Demand Transmission Service is for the transfer of capacity and \nenergy to an Eligible Customer on behalf of a designated Co-Located Load, up to a defined, \npredetermined megawatt level of transmission service as requested by the Eligible Customer and \nconfirmed by the Transmission Provider, using capacity and energy procured by the Transmission \nProvider.  Non-Firm Contract Demand Transmission Service is for the transmission of energy to \nan Eligible Customer on behalf of a designated Co-Located Load, on an as-available basis, up to \na defined, predetermined megawatt level of transmission service as requested by the Eligible \nCustomer and confirmed by the Transmission Provider, using energy procured by the \nTransmission Provider.  PJMSettlement shall be the Counterparty to the Firm Contract Demand \nTransmission Service and Non-Firm Contract Demand Transmission Service transactions under \nthis Tariff. \n \n(c) \nPrior to the Commencement of Service, for an Eligible Customer to take Non-Firm \nContract Demand Transmission Service on behalf of a Co-Located Load, the Eligible Customer \nmust demonstrate the implementation of the necessary control technologies and protection systems, \napproved by the Transmission Provider to allow the Eligible Customer to effectively limit \nwithdrawals from the Transmission System to serve such Co-Located Load. \n \n(d) \nRequests for Firm Contract Demand Transmission Service or Non-Firm Contract \nDemand Transmission Service, or both, must be made through the Transmission Provider.  These \nrequests shall (i) require the filing of an Application as set forth in Tariff, Part XI, Subpart B, \nsection 710.1 and Tariff, Part XI, Subpart B, section 710.2, and (ii) be submitted in accordance \nwith the applicable terms and conditions in the Tariff. \n \n \n709 Nature of Firm and Non-Firm Contract Demand Transmission Service \n709.1  Priority of Service \nFirm Contract Demand Transmission Service will always have priority over Non-Firm Contract \nDemand Transmission Service under the Tariff.  All Firm Contract Demand Transmission Service \nwill have equal priority with Network Integration Transmission Service."},{"page":81,"startToken":26379,"endToken":26912,"text":"10 \n709.2  Scope of Service \n(a)  \nFirm Contract Demand Transmission Service is a transmission service that allows \nan Eligible Customer taking service on behalf of a Co-Located Load to receive firm transmission \nservice on behalf of that Co-Located Load up to a defined, predetermined megawatt level of service \npursuant to the applicable terms and conditions contained in the Tariff and the Service Agreement \nfor Contract Demand Transmission Service provided in Tariff, Attachment F-4.  An Eligible \nCustomer taking service on behalf of a Co-Located Load must apply for Firm Contract Demand \nTransmission Service for no less than the megawatt level of the gross demand of the Co-Located \nLoad that will not be served by the dedicated level of energy from the Co-Located Generating \nFacility. \n(b)  \nNon-Firm Contract Demand Transmission Service is a transmission service that \nallows an Eligible Customer taking service on behalf of Co-Located Loads to obtain non-firm, \ninterruptible transmission service on behalf of a Co-Located Load in the event the Co-Located \nGenerating Facility is on outage and unable to provide any of the dedicated level of energy, and \nreceive that service up to defined, predetermined megawatt level of service pursuant to the \napplicable terms and conditions contained in the Tariff and Service Agreement for Contract \nDemand Transmission Service, provided in Tariff Attachment F-4.  An Eligible Customer taking \nservice on behalf of a Co-Located Load must apply for Non-Firm Contract Demand Transmission \nService equivalent to the megawatt level of the Co-Located Generating Facility dedicated to \nserving the Co-Located Load; provided however, that the level of service required under the \nforegoing may be reduced to the extent the amount of Firm Contract Demand Transmission \nService contracted exceeds megawatt level of the gross demand of the Co-Located Load that will \nnot be served by the dedicated level of energy from the Co-Located Generating Facility.  An \nEligible Customer with an effective Service Agreement will be eligible to obtain Non-Firm \nContract Demand Transmission Service on a given Operating Day only to the extent the portion \nof the Co-Located Generating Facility dedicated to serving the Co-Located Load is on outage. \n(c)  \nThe cumulative amount of Firm Contract Demand Transmission Service and Non-\nFirm Contract Demand Transmission Service requested by the Eligible Customer on behalf of the \nCo-Located Load must equal the entire gross demand of the Co-Located Load.  \n(d)  \nFor any given Co-Located Load, once an Eligible Customer has taken, or is \napplying for, Network Integration Transmission Service or Interim Network Integration \nTransmission Service on behalf of such Co-Located Load, an Eligible Customer shall not be \neligible to apply for or take Firm Contract Demand Transmission Service or Non-Firm Contract \nDemand Transmission Service for that same Co-Located Load.   \n(e)  \nAfter an Eligible Customer has submitted an Application for Contract Demand \nTransmission Service for a given Co-Located Load, any material change in the megawatt level of \nthe gross-demand of the Co-Located Load or in the megawatt level of the Co-Located Generating \nFacility dedicated to the Co-Located Load would require a new Application. \n709.3 Restrictions on Use of Service \nThe Eligible Customer shall not use Firm Contract Demand Transmission Service or Non-Firm \nContract Demand Transmission Service for (i) sales of capacity and energy to loads other than the"},{"page":82,"startToken":26912,"endToken":27364,"text":"11 \nCo-Located Load designated in its Service Agreement for Contract Demand Transmission Service, \nor (ii) direct or indirect provision of transmission service by the Eligible Customer to third parties.   \n709.4 Anti-Toggling Provision \nTo the extent permitted in accordance with section 709.2, for the portion of the Co-Located Load \nserved by Firm Contract Demand Transmission Service, the Eligible Customer, or its successor, \nshall not seek Non-Firm Contract Demand Transmission Service for five (5) years following the \neffective date of the Service Agreement for Contract Demand Transmission Service. \nHowever, the foregoing limitation in this subsection shall not apply in the event of (i) a physical \nchange to the Co-Located Generating Facility that would materially and permanently alter the \nmegawatt level dedicated to the Co-Located Load, or (ii) a physical change to the Co-Located \nLoad that would materially and permanently alter the megawatt level of its gross demand. \n \n \n710 Initiating Service \n710.1 Conditions Precedent for Receiving Service \nSubject to the terms and conditions of Tariff, Part XI, the Transmission Provider will provide Firm \nContract Demand Transmission Service or Non-Firm Contract Demand Transmission Service, or \nboth, to any Eligible Customer taking transmission service on behalf of Co-Located Load, \nprovided that: \n(i) \nThe Eligible Customer has been designated to take transmission service on behalf \nof a Co-Located Load in the relevant Application, Service Agreement, or the \nGeneration Interconnection Agreement for the Co-Located Generating Facility; \n(ii) \nThe subject Co-Located Load has not been served by any Eligible Customer on \nbehalf of such Co-Located Load taking, or applying to take, Network Integration \nTransmission Service or Interim Network Integration Transmission Service; \n(iii) \nThe Eligible Customer has provided the information specified in, and otherwise \ncomplied with, the “PJM Credit Policy” set forth in Tariff, Attachment Q hereto;  \n(iv) \nThe Eligible Customer has executed a Service Agreement for Contract Demand \nTransmission Service with the Transmission Provider pursuant to Tariff, \nAttachment F-4, or requests in writing that the Transmission Provider file a \nproposed unexecuted Service Agreement for Contract Demand Transmission \nService; such Service Agreement shall include (a) for Non-Firm Contract Demand \nTransmission Service, the operational procedures necessary to implement \nnecessary control technologies and protection systems approved by the \nTransmission Provider that will limit energy withdrawals consistent with the terms \nof the Service Agreement; and (b) its agreement to be curtailed under certain \nconditions set forth in the Service Agreement and in the PJM Tariff; \n(v) \nThe Eligible Customer has certified, in accordance with the PJM Manuals, that it is \nwilling and able to limit energy withdrawals from the Transmission System when \nrequested by the Transmission Provider; \n(vi) \nThe Eligible Customer must, in accordance with the PJM Manuals, submit to the \nTransmission Provider an authorization or certification from its Relevant Electric"},{"page":83,"startToken":27364,"endToken":27835,"text":"12 \nRetail Regulatory Authority which affirms that the Eligible Customer is authorized \nto provide energy to the Co-Located Load; and \n(vii) \nEligible Customer has completed other certification requirements provided in the \nPJM Manuals, including to be an Electric Distributor, as applicable; and  \n(viii) The Eligible Customer taking Contract Demand Transmission Service on behalf of \na Co-Located Load shall otherwise execute, if necessary, and comply with the PJM \nGoverning Agreements. \n710.2 Application Procedures \nAn Eligible Customer may apply for Firm Contract Demand Transmission Service or Non-Firm \nContract Demand Transmission Service, or both, to take service on behalf of a Co-Located Load.  \nThe entire gross demand of the Co-Located Load must be served by a combination of Firm \nContract Demand Transmission Service and Non-Firm Contract Demand Transmission Service.   \nTo the extent the dedicated portion of the Co-Located Generating Facility does not meet the entire \ngross demand of the Co-Located Load, an Eligible Customer seeking Contract Demand \nTransmission Service must apply for:  (i) Firm Contract Demand Transmission Service for at least \nthe portion of the gross demand of the Co-Located Load not served by dedicated output from the \nCo-Located Generating Facility; and (ii) Non-Firm Contract Demand Transmission Service for the \nportion of the gross demand of the Co-Located Load served by dedicated output from the Co-\nLocated Generating Facility; provided however, that the level of Non-Firm Contract Demand \nTransmission Service required may be reduced to the extent the amount of Firm Contract Demand \nTransmission Service contracted exceeds megawatt level of the gross demand of the Co-Located \nLoad that will not be served by the dedicated level of energy from the Co-Located Generating \nFacility.   \nIf requested by the Transmission Provider, an Application for Firm Contract Demand \nTransmission Service and/or Non-Firm Contract Demand Transmission Service shall provide all \nof the information included in 18 C.F.R. § 2.20, including but not limited to the following: \n(i) \nThe identity, address, email address, and telephone number of the entity requesting \nservice; \n(ii) \nA statement that the entity requesting service is, or will be upon Commencement \nof Service, an Eligible Customer under the Tariff; \n(iii) \nA demonstration that the Co-Located Load on behalf of which the Eligible \nCustomer is seeking to obtain service and the Co-Located Generating Facility are \nlocated on the same side of the Delivery Point to the Transmission Provider’s \nTransmission System as the Co-Located Load; \n(iv) \nA description of the supply characteristics of the Co-Located Generating Facility \nidentified in subsection (iii) above, including the generation profile, its Maximum \nFacility Output, the megawatt level dedicated to serving the Co-Located Load, and \nother technical specifications as may be requested by the Transmission Provider; \n(v) \nA description of the demand characteristics of the Co-Located Load identified in \nsubsection (iii) above, including the demand profile and other technical \nspecifications as may be requested by the Transmission Provider;"},{"page":84,"startToken":27835,"endToken":28337,"text":"13 \n(vi) \nThe requested Service Commencement Date; \n(vii) \nThe transmission capacity requested for the Delivery Point on the Transmission \nProvider’s Transmission System behind which the Co-Located Load and Co-Located \nGenerating Facility are located; and \n(viii) Any additional information required by the Transmission Provider. \nThe Transmission Provider shall treat this information consistent with the standards of conduct \ncontained in Part 37 of the Commission’s regulations. \nIf an Application fails to meet the requirements of the Tariff, the Transmission Provider shall \nnotify the Eligible Customer requesting service within fifteen (15) days of receipt of the reasons \nfor such failure.  The Transmission Provider will attempt to remedy minor deficiencies in the \nApplication through informal communications with the Eligible Customer.  If such efforts are \nunsuccessful, the Transmission Provider shall return the Application, along with any deposit, with \ninterest.  Upon receipt of a new or revised Application that fully complies with the requirements \nof this section 710, the Eligible Customer shall be assigned a new queued time and/or Project \nIdentifier, as applicable, consistent with the date of the new or revised Application. \n710.3 Determination of Whether Firm Contract Demand Transmission Service and Non-Firm \nContract Demand Transmission Service Can Be Reliably Provided \nPursuant to Tariff, Part XI, Subpart B, section 712, Transmission Provider will coordinate with the \naffected Transmission Owner(s) to complete studies, including load integration studies, which will \nprovide data relevant to the determination of whether (and to what level as applicable) (i) Firm \nContract Demand Transmission Service can be reliably provided and identify any necessary \nenhancements to the Transmission System to accommodate the requested level of service, and/or \n(ii) Non-Firm Contract Demand Transmission Services can be reliably provided.  During this study \nperiod, Transmission Provider may also perform other studies.   \nFollowing completion of all studies, Transmission Provider will make the determination, in \nconsultation with the affected PJM Transmission Owner(s), about whether (and to what level as \napplicable) Firm Contract Demand Transmission Service or Non-Firm Contract Demand \nTransmission Services can be reliably provided for an Application, and if so, what level of service \nmay be provided. \nIf the Transmission Provider determines that only a portion of the Non-Firm Contract Demand \nTransmission Service requested by Eligible Customer can be provided reliably, the Transmission \nProvider will provide a written explanation of its reasons for partial denial of service.  In such an \nevent, the Eligible Customer must apply for either (i) Firm Contract Demand Transmission Service \nfor the balance of the gross demand of its Co-Located Load, consistent with Tariff, Part XI, Subpart \nB, section 709.2, or (ii) Network Integration Transmission Service under Tariff, Part III. \nIf the Transmission Provider determines that no level of Non-Firm Contract Demand Transmission \nService requested by Eligible Customer can be provided reliably, the Transmission Provider will \nprovide a written explanation of its reasons for denial of service.  In such an event, to receive \nContract Demand Transmission Service, the Eligible Customer must apply for either (i) Firm \nContract Demand Transmission Service for the entire gross demand of its Co-Located Load,"},{"page":85,"startToken":28337,"endToken":28850,"text":"14 \nconsistent with Tariff, Part XI, Subpart B, section 709.2, or (ii) Network Integration Transmission \nService under Tariff, Part III. \nDescriptions of the Transmission Provider’s and/or the applicable Transmission Owner(s)’ \nspecific methodology for assessing whether Firm Contract Demand Transmission Service or Non-\nFirm Contract Demand Transmission Service, or both, can be reliably provided, will be set forth \nin Tariff, Part XI, Subpart B, section 712, in the PJM Manuals, and in Transmission Owner \nstandards, as applicable. \n710.4 Technical Requirements Prior to Commencement of Service \nFirm Contract Demand Transmission Service and Non-Firm Contract Demand Transmission \nService shall not commence until the Transmission Provider, the affected Transmission Owner(s), \nand the Eligible Customer, or a third party, have completed installation of all equipment specified \nunder the Service Agreement for Contract Demand Transmission Service, as provided in \nAttachment F-4, consistent with Good Utility Practice and any additional requirements reasonably \nand consistently imposed to ensure the reliable operation of the Transmission System.  The \nTransmission Provider and the affected Transmission Owner(s) are to complete such arrangements \nas soon as practicable taking into consideration the Service Commencement Date. \nAs applicable, these technical requirements may include, but are not limited to: (i) installation of \nnecessary hardware and software to limit energy withdrawals, including metering equipment and \nany facilities necessary to implement the necessary control technologies and protection systems \nassociated with the provisions of Non-Firm Contract Demand Transmission Service set forth in \nthe Service Agreement for Contract Demand Transmission Service; (ii) provision of an operational \ncontact and backup contact for the Eligible Customer, available twenty-four (24) hours a day and \nseven (7) days a week; (iii) certification from the Eligible Customer that it is staffed with PJM \nCertified Operators (PJM Manual 40); (iv) demonstration from the Eligible Customer of its ability \nto receive voice and electronic signals from the Transmission Provider; (v) demonstration that the \nEligible Customer has operational control to respond to operating instructions from the \nTransmission Provider to reduce energy withdrawals or disconnect the Co-Located Load within \nfive (5) minutes or as specified in the PJM Manuals; (vi) satisfaction of any technical requirements \nidentified by the applicable Transmission Owner(s); and (vii) as applicable, demonstration that the \nEligible Customer has operational control of the necessary control technologies and protection \nsystems required pursuant to Tariff, Part XI, Subpart B, section 713 and set forth in the Service \nAgreement for Contract Demand Transmission Service.  \n710.5 Eligible Customer Facilities and Network Facilities \nThe provision of Firm Contract Demand Transmission Service or Non-Firm Contract Demand \nTransmission Service, or both, shall be conditioned upon the Eligible Customer constructing, \nmaintaining, and operating the facilities (i) on its side of the Delivery Point necessary to reliably \ndeliver and receive energy and capacity; and (ii) only in the case of Non-Firm Contract Demand \nTransmission Service, to implement the necessary control technologies and protection systems \nrequired pursuant to Tariff, Part XI, Subpart B, section 713 and specified in the Service Agreement \nfor Contract Demand Transmission Service, as Transmission Provider may require.  Nothing \nherein precludes the installation of any Transmission Owner-side protection facilities."},{"page":86,"startToken":28850,"endToken":29279,"text":"15 \nAs set forth in the Service Agreement for Contract Demand Transmission Service, the Eligible \nCustomer may also be responsible for the cost of network upgrades from the Transmission \nProvider’s Transmission System to the Delivery Point.  In the case of Firm Contract Demand \nTransmission Service, the Transmission Provider shall be responsible for ensuring the \nTransmission System can deliver and receive energy and capacity to the Delivery Point.   \nThe Eligible Customer shall be solely responsible for constructing or installing all facilities on the \nEligible Customer’s side of each such Delivery Point or, with respect to service provided pursuant \nto a state required retail access program, for otherwise arranging for the delivery of its energy from \nthe Delivery Point. \n710.6 Execution and Filing of Service Agreement \nThe Transmission Provider will file the Service Agreement for Contract Demand Transmission \nService, as set forth in Attachment F-4, with the Commission in compliance with applicable \nCommission regulations, and subject to the provisions below. \n(a) \nTransmission Provider shall provide the final Service Agreement for Contract \nDemand Transmission Service, along with any applicable schedules, to the parties in electronic \nform.  Not later than fifteen (15) Business Days after receipt of the Service Agreement for Contract \nDemand Transmission Service, Eligible Customer shall: \n(i) \nexecute the final Service Agreement for Contract Demand Transmission \nService in electronic form and return it to Transmission Provider \nelectronically; \n(ii) \nrequest in writing dispute resolution as allowed under Tariff, Part I, \nsection 12; or \n(iii) \nrequest in writing that Transmission Provider file with the Commission the \nfinal Service Agreement for Contract Demand Transmission Service in \nunexecuted form.  The unexecuted Service Agreement for Contract Demand \nTransmission Service shall contain terms and conditions deemed \nappropriate by Transmission Provider for the Application. \nAs needed for Firm Contract Demand Transmission Service, the Eligible Customer shall also \nprovide any required adjustments to Security for facility upgrades. \n(b) \nIf the Eligible Customer determines that final agreement negotiations are at an \nimpasse, the Eligible Customer shall notify Transmission Provider of the impasse, and Eligible \nCustomer may request Transmission Provider to file the unexecuted agreement with FERC or \nrequest in writing dispute resolution as allowed under Tariff, Part I, section 12.  If Transmission \nProvider, in its sole discretion, determines that the negotiations are at an impasse, Transmission \nProvider shall notify the Eligible Customer of the impasse, and may file the unexecuted agreement \nwith the FERC. \n(c) \nEligible Customer and Transmission Provider may not proceed under such Service \nAgreement for Contract Demand Transmission Service until:  \n(i) \nthirty (30) days after such agreement, if executed and nonconforming, has \nbeen filed with FERC;"},{"page":87,"startToken":29279,"endToken":29707,"text":"16 \n(ii) \nsuch agreement, if unexecuted, has been filed with and accepted by FERC; \nor  \n(iii) \nthe earlier of thirty (30) days after such agreement, if conforming, has been \nexecuted or has been reported in Transmission Provider’s Electronic \nQuarterly Reports. \n710.7 Termination \nAlthough the Service Agreement for Contract Demand Transmission Service is presumed to \ncontinue without expiration, it may be terminated where: \n(a) \nAn incumbent Eligible Customer will be replaced by a successor Eligible Customer, \nin which case the incumbent’s service shall only terminate if the successor agrees to commence \nthe taking of the service, the appropriate service agreement is executed, and all other applicable \nterms and conditions of the Tariff and PJM Governing Agreements are satisfied; \n(b) \nAn incumbent Eligible Customer seeks to terminate its service and no successor \nEligible Customer exists, in which case the incumbent must provide PJM with forty-two (42) \nmonths’ notice prior to the commencement of a Delivery Year in which Eligible Customer seeks \nthe termination, subject to receiving all necessary regulatory approvals for such termination, if \nany;  \n(c) \nAn Eligible Customer is disqualified from receiving Contract Demand \nTransmission Service under Tariff, Part XI, Subpart B, section 713.7;  \n(d) \nThe Eligible Customer is in breach of its obligations under the Service Agreement \nor the Tariff, Part XI.  For example, to the extent any material changes to the gross demand of the \nCo-Located Load or the design, configuration, or output of the Co-Located Generating Facility \noccur without being studied by the Transmission Provider to determine whether such changes \nwould affect the Transmission Provider’s ability to reliably provide the level of service specified \nin the Eligible Customer’s Contract Demand Transmission Service Agreement, the Eligible \nCustomer may be considered in breach of its obligations and the agreement may be subject to \ntermination in accordance with the provisions of this Tariff and/or the Service Agreement for \nContract Demand Transmission Service; or \n(e) \nOn such other date as mutually agreed upon by the parties. \n \n \n711 Designation of Co-Located Load and Co-Located Generating Facility \n711.1 Required Designations \n(a) \nThe Eligible Customer must designate the individual Co-Located Load on behalf \nof which it is taking Firm Contract Demand Transmission Service, or Non-Firm Contract Demand \nTransmission Service, or both.  The Co-Located Load shall be specified in the Service Agreement \nfor Contract Demand Transmission Service, provided in Attachment F-4. \n(b) \nThe Eligible Customer must designate the individual Co-Located Generating \nFacility that will serve the individual Co-Located Load in subsection (a) and provide the megawatt \nlevel of energy from the Co-Located Generating Facility dedicated to serving the Co-Located Load."},{"page":88,"startToken":29707,"endToken":30093,"text":"17 \n711.2 No Change in Delivery Point \nNo change in the Delivery Point for any Firm Contract Demand Transmission Service or Non-\nFirm Contract Demand Transmission Service shall be permitted. \n711.3 Information Updates \nThe Eligible Customer shall provide the Transmission Provider with annual updates of (i) the \ndemand characteristics of the Co-Located Load, and (ii) the supply characteristics of the \ndesignated Co-Located Generating Facility, both consistent with the information included in its \nApplication for Contract Demand Transmission Service under Tariff, Part XI.   \nIn addition, the Eligible Customer also shall have an ongoing obligation to provide the \nTransmission Provider and applicable Transmission Owner(s) with timely written or electronic \nnotice of material changes, as discussed in the PJM Manuals, in the foregoing sentence as well as \nany other information listed in Tariff, Part XI, Subpart B, section 710 or provided in its Application \nfor Contract Demand Transmission Service or other aspects of its facilities or operations affecting \nthe Transmission Provider’s ability to provide reliable service.  Failure to timely inform the \nTransmission Provider of a material change in (i) the demand characteristics of the Co-Located \nLoad, or (ii) the supply characteristics of the Co-Located Generating Facility may constitute a \nbreach of the Eligible Customer’s Service Agreement and subject to termination under Tariff, Part \nXI, Subpart B, section 710.7. \n \n \n712 Study Procedures for Contract Demand Transmission Service \n712.1 Study Procedures for Firm Contract Demand Transmission Service \nAfter the Eligible Customer submits a Completed Application for Firm Contract Demand \nTransmission Service, the Transmission Provider shall notify the affected Transmission Owner(s) \nof the Completed Application.  As necessary, Transmission Provider and the affected \nTransmission Owner(s) shall coordinate to study the effects of providing the requested Firm \nContract Demand Transmission Service on the affected Transmission Owner(s)’s system pursuant \nto the applicable affected Transmission Owner requirements. \nAfter receiving the Application for Firm Contract Demand Transmission Service, the \nTransmission Provider shall determine, in accordance with the PJM Manuals, any necessary \nstudies for reliably providing the requested Firm Contract Demand Transmission Service.  If the \nTransmission Provider determines that such studies are necessary to evaluate the requested service, \nit shall inform the Eligible Customer of those studies as soon as practicable.  The Transmission \nProvider will also consider the results of any studies conducted by the affected Transmission \nOwner(s)."},{"page":89,"startToken":30093,"endToken":30534,"text":"18 \n712.2 Study Procedures for Non-Firm Contract Demand Transmission Service \nAfter receiving a request for Non-Firm Contract Demand Transmission Service, the Transmission \nProvider shall determine on a non-discriminatory basis, and in accordance with the PJM Manuals, \nwhether studies are needed to assess whether the Transmission System has sufficient available \ncapacity to provide Non-Firm Contract Demand Transmission Service, and if so, which studies \nare appropriate.  Transmission Provider maywill notify the affected Transmission Owner of such \nrequest for Non-Firm Contract Demand Transmission Service, and the Transmission Provider will \nalso consider the results of any studies conducted by the affected Transmission Owner(s).   \n712.3 Application and Studies Agreement \nIn the event the Transmission Provider determines studies are necessary to evaluate the requested \nContract Demand Transmission Service, the Transmission Provider shall tender an Application \nand Studies Agreement pursuant to which the Eligible Customer shall agree to reimburse the \nTransmission Provider for the required studies.  For a service request to remain a Completed \nApplication, the Eligible Customer shall execute the Application and Studies Agreement and \nreturn it to the Transmission Provider within fifteen (15) Business Days and provide the study fee \npursuant to Tariff, Part XI, Subpart B, section 712.4.  If the Eligible Customer elects not to execute \nthe Application and Studies Agreement, its Application shall be deemed withdrawn and its fee \nshall be returned with interest. \n712.4 Study Fee  \nEligible Customer shall pay a study fee, as determined by the Transmission Provider, to apply for \nFirm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission \nService. \n \n \n713 Load Shedding and Curtailments for Contract Demand Transmission Service \n713.1 General \nPrior to the Service Commencement Date, the Eligible Customer shall demonstrate its ability to \nfully comply with the Load Shedding and Curtailment procedures pursuant to this section 713, the \nPJM Manuals, and the Service Agreement for Contract Demand Transmission Service, as provided \nin Attachment F-4.  The Eligible Customer shall implement any Load Shedding and/or Curtailment \ndirective given by Transmission Provider.  To the extent practicable, the Transmission Provider \nwill notify the Eligible Customer and applicable Transmission Owner(s) of any Curtailment in a \ntimely manner.  Eligible Customers must respond to any real time instruction to curtail or otherwise \nreduce load within five (5) minutes.  Curtailments will be made on a non-discriminatory basis. \n713.2 Load Shedding \nTo the extent that a system contingency exists on the Transmission Provider’s Transmission \nSystem and the Transmission Provider determines that it is necessary for the Eligible Customer to \nshed load at the designated Co-Located Load, the Eligible Customer shall shed load in accordance \nwith previously established procedures under the Service Agreement for Contract Demand \nTransmission Service."},{"page":90,"startToken":30534,"endToken":31013,"text":"19 \n713.3 Curtailment of Firm Contract Demand Transmission Service \nFor purposes of Curtailment, Firm Contract Demand Transmission Service shall be treated as the \nequivalent of Network Integration Transmission Service.  \n713.4 Curtailment of Non-Firm Contract Demand Transmission Service \nNon-Firm Contract Demand Transmission Service shall be Curtailed before Firm Contract \nDemand Transmission Service and Network Integration Transmission Service.  The Transmission \nProvider may Curtail Non-Firm Contract Demand Transmission Service prior to dispatching the \nPre-Emergency Load Response Program as further set forth in the PJM Manuals, or in response to \na transfer capability shortage as a result of system reliability conditions.   \n713.5 System Reliability \nNotwithstanding any other provisions of this Tariff, the Transmission Provider reserves the right, \nconsistent with Good Utility Practice and on a not unduly discriminatory basis, to Curtail Firm \nContract Demand Transmission Service or Non-Firm Contract Demand Transmission Service, or \nboth, without liability on the Transmission Provider’s part, for the purpose of making necessary \nadjustments to, changes in, or repairs on its lines, substations, and facilities, and in cases where \nthe continuance of Firm Contract Demand Transmission Service or Non-Firm Contract Demand \nTransmission Service, or both, would endanger persons or property.  In the event of any adverse \ncondition(s) or disturbance(s) on the Transmission Provider’s Transmission System or on any \nother system(s) directly or indirectly interconnected with the Transmission Provider’s \nTransmission System, the Transmission Provider, consistent with Good Utility Practice, also may \nCurtail Firm Contract Demand Transmission Service or Non-Firm Contract Demand Transmission \nService in order to (i) limit the extent or damage of the adverse condition(s) or disturbance(s), (ii) \nprevent damage to generating or transmission facilities, or (iii) expedite restoration of service.  The \nTransmission Provider will give the Eligible Customer as much advance notice as is practicable in \nthe event of such Curtailment. \n713.6 Necessary Control Technologies and Protection Systems for Non-Firm Contract Demand \nTransmission Service \nTo ensure protection of the Transmission System and that the Eligible Customer limits its energy \nwithdrawals from the Transmission System to the level of Contract Demand Transmission Service \nprovided in its Service Agreement for Contract Demand Transmission Service, including during a \nperiod in which the Transmission Provider has directed Curtailment or Load Shedding, prior to \nthe Service Commencement Date, the Transmission Provider, affected Transmission Owner(s), \nand the Eligible Customer shall establish necessary control technologies and protection systems in \naccordance with the PJM Manuals, which may include a Remedial Action Scheme, for each \nService Agreement for Non-Firm Contract Demand Transmission Service.  The necessary control \ntechnologies and protection systems must be developed in accordance with the PJM Manuals and \nbe approved by the Transmission Provider.  The necessary control technologies and protection \nsystems may be functionally modified from time to time.  Any functional modification to the \nnecessary control technologies and protection systems must be developed with the affected \nTransmission Owner(s) and approved by the Transmission Provider."},{"page":91,"startToken":31013,"endToken":31423,"text":"20 \n713.7 Consequences of Failure to Follow Instructions or Misoperation of Necessary Control \nTechnologies and Protection Systems in a Contract Demand Transmission Service Agreement \n(a) \nIn the first instance that an Eligible Customer taking Firm Contract Demand \nTransmission Service or Non-Firm Contract Demand Transmission Service fails to respond to \nestablished Load Shedding and Curtailment procedures, as set forth in this section 713, the Eligible \nCustomer shall be disqualified from taking Firm Contract Demand Transmission Service and Non-\nFirm Contract Demand Transmission Service. \n(b) \nIn the first instance that a necessary control technology or protection system for a \ngiven Service Agreement for Non-Firm Contract Demand Transmission Service misoperate, the \nEligible Customer shall be prohibited from taking transmission service under its Service \nAgreement (both Firm Contract Demand Transmission Service and Non-Firm Contract Demand \nTransmission Service) or otherwise withdrawing energy from the Transmission System for a \nperiod of up to one hundred and twenty (120) days from such event, which may be shortened or \nextended per mutual agreement, to allow for an analysis of the operational performance of the \nnecessary control technologies and protection systems.   \nIn the second instance that an Eligible Customer’s necessary control technology or protection \nsystem associated with a Service Agreement for Non-Firm Contract Demand Transmission Service \nmisoperate, the Eligible Customer shall be disqualified from taking Firm Contract Demand \nTransmission Service and Non-Firm Contract Demand Transmission Service. \n(c) \nFollowing disqualification under subsections (a) or (b) above, to receive any \ntransmission service over the Transmission System, the Eligible Customer must apply for Network \nIntegration Transmission Service under Tariff, Part III, with the option to qualify for Interim \nNetwork Integration Transmission Service under Tariff, Part XI subject to the provisions of the \nTariff.   \n(d) \nThe Transmission Provider may, in its sole discretion and on a prospective basis \nonly, determine that the facts and circumstances demonstrate that Eligible Customer was not at \nfault for (i) an Eligible Customer’s, or the Co-Located Load’s served by the Eligible Customer, \nfailure to implement Load Shedding and Curtailment procedures or (ii) a misoperation of the \nEligible Customer’s necessary control technology or protection system associated with a Service \nAgreement.  In the event, the Transmission Provider makes such a no fault determination, the \nprecipitating event shall not be considered toward disqualification under this section 713. \n \n713.8 Penalty for Unreserved Use of Contract Demand Transmission Service \n[Reserved] \n \n \n714 Rates and Charges for Firm Contract Demand Transmission Service \n714.1 Monthly Demand Charge \n[Reserved] \n714.2 Network Upgrade Charge"},{"page":92,"startToken":31423,"endToken":31744,"text":"21 \n[Reserved] \n714.3 Redispatch Charge \nThe Eligible Customer and each Transmission Owner shall pay any redispatch costs as set forth in \nTariff, Attachment K. \n714.4 Stranded Cost Recovery \nAny Transmission Owner may seek to recover stranded costs from the Eligible Customer pursuant \nto this Tariff in accordance with the terms, conditions and procedures set forth in FERC Order No. \n888.  However, the Transmission Owner must separately file any proposal to recover stranded \ncosts under section 205 of the Federal Power Act. \n714.5 Other Charges \nEligible Customer shall pay administrative services charges under Tariff, Schedule 1A; Tariff, \nSchedule 9; and Tariff, Schedule 10 based on the total quantity of MWHs of energy delivered \nusing Firm Contract Demand Transmission Service, except in the case of any capacity-related \ncharges under these schedules, which shall be based on the Eligible Customer’s Unforced Capacity \nObligation. \nEligible Customer shall pay Ancillary Services charges, except for Regulation, based on the total \nquantity in MWhs of energy delivered to the Co-Located Load using Firm Contract Demand \nTransmission Service in accordance with Tariff, Part I, section 3.  \nEligible Customer shall pay Black Start Service charges based on the gross demand of the Co-\nLocated Load in accordance with Tariff, Schedule 6A. \nEligible Customer shall pay Regulation charges based on the gross demand of the Co-Located \nLoad.   \n \n \n715 Rates and Charges for Non-Firm Contract Demand Transmission Service \n715.1 Monthly Demand Charge \n[Reserved] \n715.2 Redispatch Charge \nThe Eligible Customer and each Transmission Owner shall pay any redispatch costs as set forth in \nTariff, Attachment K. \n715.3 Stranded Cost Recovery \nAny Transmission Owner may seek to recover stranded costs from the Eligible Customer pursuant \nto this Tariff in accordance with the terms, conditions and procedures set forth in FERC Order No. \n888.  However, the Transmission Owner must separately file any proposal to recover stranded \ncosts under section 205 of the Federal Power Act. \n715.4 Other Charges"},{"page":93,"startToken":31744,"endToken":32104,"text":"22 \nEligible Customer shall pay administrative services charges under Tariff, Schedule 1A; Tariff, \nSchedule 9; and Tariff, Schedule 10 based on the total quantity of MWhs of energy delivered using \nNon-Firm Contract Demand Transmission Service, except any capacity-related charges under \nthese schedules will not apply. \nEligible Customer shall pay Ancillary Services charges, except for Regulation, based on the total \nquantity in MWhs of energy delivered to the Co-Located Load using Non-Firm Contract Demand \nTransmission Service in accordance with Tariff, Part I, section 3.  \nTo the extent the Eligible Customer does not have an effective Service Agreement for Firm \nContract Demand Transmission Service, Eligible Customer shall pay Black Start Service charges \nbased on the gross demand of the Co-Located Load in accordance with Tariff, Schedule 6A. \nTo the extent the Eligible Customer does not have an effective Service Agreement for Firm \nContract Demand Transmission Service, Eligible Customer shall pay Regulation charges based on \na gross demand of the Co-Located Load. \n \n \n716 Operating Agreement \n716.1 Operating Agreement \nThe Eligible Customer shall plan, construct, operate and maintain its facilities in accordance with \nGood Utility Practice and in conformance with the Operating Agreement.   \nThe terms and conditions under which the Eligible Customer shall operate its facilities and the \ntechnical and operational matters associated with the implementation of Tariff, Part XI shall be \nspecified in the Operating Agreement.   \nThe Operating Agreement shall provide for the Eligible Customer and Transmission Provider  to \n(i) operate and maintain equipment necessary for integrating the Eligible Customer within the \nTransmission Provider’s Transmission System (including, but not limited to, remote terminal units, \nmetering, communications equipment and relaying equipment); (ii) transfer data between the \nTransmission Provider and the Eligible Customer (including, but not limited to, heat rates and \noperational characteristics of Network Resources, generation schedules for units outside the \nTransmission Provider’s Transmission System, interchange schedules, unit outputs for required \nredispatch, voltage schedules, loss factors and other real time data); (iii) use software programs \nrequired for data links and constraint dispatching; (iv) exchange data on forecasted loads and \nresources necessary for long-term planning; and (v) address any other technical and operational \nconsiderations required for implementation of Tariff, Part XI, including scheduling protocols."},{"page":94,"startToken":32104,"endToken":32435,"text":"23 \nService Agreement No. [Insert] \n \nATTACHMENT F-3A \n \nService Agreement For \nRegional Network Integration Transmission Service \nAnd/or \nInterim Network Integration Transmission Service  \n(For Co-Located Load) \n \n1.0 \nThis Service Agreement, dated as of the date the last party executes this agreement, is \nentered into, by and between the Office of the Interconnection of PJM Interconnection, \nL.L.C. (the Transmission Provider) as the administrator of the Tariff, PJMSettlement Inc. \n(“Counterparty”) as the counterparty, and ____________ (“Network Customer”). [If \napplicable: This Service Agreement supersedes the Service Agreement among \nTransmission Provider, Counterparty, and [insert prior Network Customer’s entity name], \n[insert Service Agreement Number], effective date [insert], which was filed with the \nCommission in Docket No. [insert].] \n \n2.0 \n[Instructions:  Choose one of the following] \n \n[The Network Customer has been determined by the Transmission Provider to have a valid \nrequest for Network Transmission Service under the Tariff and to have satisfied the \nconditions for service imposed by the Tariff.] \n \n \n[or] \n \n[The Network Customer, which is an Eligible Customer taking transmission service on \nbehalf of Co-Located Load, has been determined by the Transmission Provider to have a \nvalid request for Network Transmission Service under the Tariff and to have satisfied the \nconditions for service imposed by the Tariff, except for the condition that the following \nfacilities must be completed and placed into service: \n \n[If applicable, list facilities to be completed and placed into service.] \n \nUntil the facilities listed above are completed, the Transmission Owner provides a Notice \nof Completion to PJM, and the facilities listed above are in service, the Eligible Customer \nmay not only receive Interim Regional Network Integration Transmission Service subject \nto the conditions of Part XI of the Tariff. \n \n3.0 \nRegional Network Integration Transmission Service under this agreement shall commence \non the later of: (l) the requested service commencement date of ___________________, or \n(2) the date on which construction of any Direct Assignment Facilities and/or Network \nUpgrades are completed, or (3) such other date as it is permitted to become effective by"},{"page":95,"startToken":32435,"endToken":32873,"text":"24 \nthe Commission.  Network Customer taking Regional Network Integration Transmission \nService shall take such service on terms that do not expire.  \n \nRegional Network Integration Transmission Service shall terminate consistent with Tariff, \nPart I, section 2.5.  Specifically, Regional Network Integration Transmission Service may \nbe terminated where: (1) an incumbent Network Customer will be replaced by a successor \nNetwork Customer, in which case the incumbent’s service shall only terminate if the \nsuccessor agrees to commence the taking of the service, the appropriate service agreement \nis executed, and all other applicable terms and conditions of the PJM Governing \nAgreements are satisfied; (2) an incumbent Network Customer seeks to terminate its \nservice and no successor Network Customer exists, in which case the incumbent must \nprovide PJM with forty-two (42) months’ notice prior to the commencement of a Delivery \nYear, subject to receiving all necessary regulatory approvals for such termination, if any; \nor (3) on such other date mutually agreed upon by the Parties. \n \n \n[If applicable]  [Interim Network Integration Transmission Service under this agreement \nshall commence on the later of: (l) the requested service commencement date of \n___________________, or (2) such other date as it is permitted to become effective by the \nCommission.  On the date on which construction of any Direct Assignment Facilities \nand/or Network Upgrades are completed, Interim Network Integration Transmission \nService shall terminate consistent with Tariff, Part XI, and Regional Network Integration \nTransmission Service shall begin.] \n \n4.0 \nThe Transmission Provider agrees to provide and the Network Customer agrees to take and \npay for Regional Network Integration Transmission Service, when applicable, and Interim \nRegional Network Integration Transmission Service, when applicable, in accordance with \nthe provisions of the Tariff, including the Operating Agreement (which is incorporated \nherein by reference), and this Service Agreement as they may be amended from time to \ntime.  Failure to timely inform the Transmission Provider of a material change in (i) the \ndemand characteristics of the Co-Located Load or (ii) the supply characteristics of the Co-\nLocated Generating Facility may constitute a breach of the Eligible Customer’s Service \nAgreement and this Service Agreement may be terminated pursuant to Tariff, Part XI, \nSubpart B, section 710.7. \n \n \n[If applicable] [The Eligible Customer will comply with the necessary control technologies \nand protection systems provisions in Tariff, Part XI, prior to the Service Commencement \nDate.] \n \n5.0 \nThe Eligible Customer certifies it is willing and able to limit its usage of the Transmission \nSystem when requested by the Transmission Provider. \n \n6.0   \nAny notice or request made to or by either Party regarding this Service Agreement shall be \nmade to the representative of the other Party as indicated below."},{"page":96,"startToken":32873,"endToken":32925,"text":"25 \nTransmission Provider (on behalf of Transmission Provider and Counterparty): \n \n \nPJM Interconnection, L.L.C.  \n \n2750 Monroe Blvd. \n \nAudubon, PA 19403 \n \nNetwork Customer: \n \n \n_____________________________________ \n \n \n_____________________________________ \n \n \n_____________________________________ \n \n7.0 \nThe Tariff for Network Integration Transmission Service, Tariff, Part III, and Interim \nNetwork Integration Transmission Service, Tariff, Part XI, is incorporated herein and made \na part hereof."},{"page":97,"startToken":32925,"endToken":32963,"text":"26 \nIN WITNESS WHEREOF, the Parties have caused this Service Agreement to be executed by their \nrespective authorized officials. \n \nOffice of the Interconnection: \n \nBy: \n______________________ _______________ \n______________ \n \nName                       \n \nTitle   \n    \nDate \n \nCounterparty: \n \nBy: \n______________________ _______________ \n______________ \n \nName  \n \n \nTitle \n \n \nDate \n \nNetwork Customer: \n \nBy: \n______________________ _______________ \n______________ \n \nName                       \n \nTitle   \n    \nDate"},{"page":98,"startToken":32963,"endToken":33019,"text":"27 \nCERTIFICATION \n \n \nI, ___________________________, certify that I am a duly authorized officer of \n___________________________________ (Network Customer) and that \n___________________________________ (Network Customer) will not request service under \nthis Service Agreement to assist an Eligible Customer to avoid the reciprocity provision of this \nOpen-Access Transmission Tariff. \n \n_____________________________ \n(Name) \n \n_____________________________ \n(Title) \n \n \n \nSubscribed and sworn before me this _____ day of _____________, _______. \n \n_____________________________ \n \n(Notary Public) \n \nMy Commission expires:_____________________"},{"page":99,"startToken":33019,"endToken":33128,"text":"28 \nSPECIFICATIONS FOR \nREGIONAL NETWORK INTEGRATION TRANSMISSION SERVICE \n \n1.0 \nRegional Network Integration Transmission Service Amount (MW):  \n   ______MW \n \n2.0 \nDescription of Co-Located Generating Facility:________________________________ \n \n \n \n \n \n \n \n________________________________________ \n \n \n \n \n \n \n \n________________________________________ \n \n \nMaximum Facility Output of  Co-Located Generating Facility: \n \n_______MW \n \n3.0 \nDescription of Co-Located Load: \n________________________________________ \n \n \n \n \n \n \n \n________________________________________ \n \n \n \n \n \n \n \n________________________________________ \n \n \nGross Demand of Co-Located Load:  \n \n \n \n \n______MW \n \n4.0 \nService under this Agreement may be subject to some combination of the charges detailed \nbelow.  (The appropriate charges for individual transactions will be determined in \naccordance with the terms and conditions of the Tariff.) \n \n \n4.1 \nEmbedded Cost Transmission Charge:_______________________ \n \n \n \n______________________________________________________ \n \n \n4.2 \nFacilities Study Charge:__________________________________ \n \n \n \n______________________________________________________ \n \n \n4.3 \nDirect Assignment Facilities Charge:________________________ \n \n \n \n______________________________________________________ \n \n \n4.4 \nAncillary Services Charge:________________________________ \n \n \n \n______________________________________________________ \n \n \n4.5 \nOther Supporting Facilities Charge:_________________________ \n \n \n \n______________________________________________________"},{"page":100,"startToken":33128,"endToken":33241,"text":"29 \n{If applicable}  SPECIFICATIONS FOR \nINTERIM REGIONAL NETWORK INTEGRATION TRANSMISSION SERVICE \n \n1.0 \nInterim Regional Network Integration Transmission Service Amount (MW): ______MW \n \n2.0 \nDescription of Co-Located Generating Facility:________________________________ \n \n \n \n \n \n \n \n________________________________________ \n \n \n \n \n \n \n \n________________________________________ \n \n \nMaximum Facility Output of  Co-Located Generating Facility: \n \n_______MW \n \n \n \n3.0 \nDescription of Co-Located Load: \n________________________________________ \n \n \n \n \n \n \n \n________________________________________ \n \n \n \n \n \n \n \n________________________________________ \n \n \nGross Demand of Co-Located Load:  \n \n \n \n \n______MW \n \n4.0 \nService under this Agreement may be subject to some combination of the charges detailed \nbelow.  (The appropriate charges for individual transactions will be determined in \naccordance with the terms and conditions of the Tariff.) \n \n \n4.1 \nEmbedded Cost Transmission Charge:_______________________ \n \n \n \n______________________________________________________ \n \n \n4.2 \nFacilities Study Charge:__________________________________ \n \n \n \n______________________________________________________ \n \n \n4.3 \nDirect Assignment Facilities Charge:________________________ \n \n \n \n______________________________________________________ \n \n \n4.4 \nAncillary Services Charge:________________________________ \n \n \n \n______________________________________________________ \n \n \n4.5 \nOther Supporting Facilities Charge:_________________________ \n \n \n \n______________________________________________________"},{"page":101,"startToken":33241,"endToken":33591,"text":"30 \nService Agreement No. [Insert] \n \nATTACHMENT F-4 \n \nService Agreement For \nContract Demand Transmission Service \n(For Co-Located Load) \n \n1.0 \nThis Service Agreement, dated as of the date the last party executes this agreement, is \nentered into, by and between the Office of the Interconnection of PJM Interconnection, \nL.L.C. (the Transmission Provider) as the administrator of the Tariff, PJMSettlement Inc. \n(“Counterparty”) as the counterparty, and ____________ (“Eligible Customer”). [If \napplicable: This Service Agreement supersedes the Service Agreement among \nTransmission Provider, Counterparty, and [insert prior Eligible Customer’s entity name], \n[insert Service Agreement Number], effective date [insert], which was filed with the \nCommission in Docket No. [insert].] \n \n2.0 \n[Instructions:  Choose one of the following depending on whether facilities upgrades are \nneeded.] \n \n[If facilities upgrades are not needed or if Eligible Customer is seeking solely Non-Firm \nContract Demand Transmission Service] The Eligible Customer, who is taking \ntransmission service on behalf of Co-Located Load, has been determined by the \nTransmission Provider to have a valid request for [Firm Contract Demand Transmission \nService and/or Non-Firm Contract Demand Transmission Service] under the Tariff and to \nhave satisfied the conditions for service imposed by the Tariff. \n \n \n[or] \n \n[If facilities upgrades are needed, assuming Eligible Customer is seeking at least a portion \nof Firm Contract Demand Transmission Service] [The Eligible Customer, who is taking \ntransmission service on behalf of Co-Located Load, has been determined by the \nTransmission Provider to have a valid request for Firm Contract Demand Transmission \nService under the Tariff and to have satisfied the conditions for service imposed by the \nTariff, except for the condition that the following facilities must be completed and placed \ninto service:] \n \n[If applicable, list facilities to be completed and placed into service.] \n \nUntil the facilities listed above are completed, the Transmission Owner provides a Notice \nof Completion to PJM, and the facilities listed above are in service, the Eligible Customer \nmay not receive Firm Contract Demand Transmission Service under Tariff, Part XI. \n \n3.0 \nContract Demand Transmission Service under this agreement shall commence on the later \nof: (l) the requested service commencement date of ___________________, or (2) the date"},{"page":102,"startToken":33591,"endToken":33874,"text":"31 \non which construction of any Direct Assignment Facilities and/or Network Upgrades are \ncompleted, or (3) such other date as it is permitted to become effective by the Commission.   \n \nContract Demand Transmission Service shall terminate consistent with Tariff, Part XI, \nsection 710.7.   \n \n4.0 \nThe Transmission Provider agrees to provide and the Eligible Customer agrees to take and \npay for Contract Demand Transmission Service in accordance with the provisions of the \nTariff, including the Operating Agreement (which is incorporated herein by reference), and \nthis Service Agreement, as they may be amended from time to time.  Failure to timely \ninform the Transmission Provider of a material change in (i) the demand characteristics of \nthe Co-Located Load or (ii) the supply characteristics of the Co-Located Generating \nFacility may constitute a breach of the Eligible Customer’s Service Agreement and this \nService Agreement may be terminated pursuant to Tariff, Part XI, Subpart B, section 710.7. \n \n5.0  \nThe Eligible Customer will comply with the necessary control technologies and protection \nsystems provisions in Tariff, Part XI, prior to the Service Commencement Date.   \n \n6.0 \nThe Eligible Customer certifies it is willing and able to limit its usage of the Transmission \nSystem when requested by the Transmission Provider. \n \n7.0   \nAny notice or request made to or by either Party regarding this Service Agreement shall be \nmade to the representative of the other Party as indicated below.   \n \nTransmission Provider (on behalf of Transmission Provider and Counterparty): \n \n \nPJM Interconnection, L.L.C.  \n \n2750 Monroe Blvd. \n \nAudubon, PA 19403 \n \nEligible Customer: \n \n \n_____________________________________ \n \n \n_____________________________________ \n \n \n_____________________________________ \n \n8.0 \nTariff, Part XI, for Contract Demand Transmission Services, as it may be revised from time \nto time, is incorporated herein and made a part hereof."},{"page":103,"startToken":33874,"endToken":33912,"text":"32 \nIN WITNESS WHEREOF, the Parties have caused this Service Agreement to be executed by their \nrespective authorized officials. \n \nOffice of the Interconnection: \n \nBy: \n______________________ _______________ \n______________ \n \nName                       \n \nTitle   \n    \nDate \n \nCounterparty: \n \nBy: \n______________________ _______________ \n______________ \n \nName  \n \n \nTitle \n \n \nDate \n \nEligible Customer: \n \nBy: \n______________________ _______________ \n______________ \n \nName                       \n \nTitle   \n    \nDate"},{"page":104,"startToken":33912,"endToken":33968,"text":"33 \nCERTIFICATION \n \n \nI, ___________________________, certify that I am a duly authorized officer of \n___________________________________ (Eligible Customer) and that \n___________________________________ (Eligible Customer) will not request service under \nthis Service Agreement to assist an Eligible Customer to avoid the reciprocity provision of this \nOpen-Access Transmission Tariff. \n \n_____________________________ \n(Name) \n \n_____________________________ \n(Title) \n \n \n \nSubscribed and sworn before me this _____ day of _____________, _______. \n \n_____________________________ \n \n(Notary Public) \n \nMy Commission expires:_____________________"},{"page":105,"startToken":33968,"endToken":34102,"text":"34 \nSPECIFICATIONS FOR \nCONTRACT DEMAND TRANSMISSION SERVICE \n \n1.0 \nFirm Contract Demand Transmission Service Amount (MW):  \n \n______MW \n \nNon- Firm Contract Demand Transmission Service Amount (MW):  \n______MW \n \n \n2.0 \nDescription of Co-Located Generating Facility:________________________________ \n \n \n \n \n \n \n \n________________________________________ \n \n \n \n \n \n \n \n________________________________________ \n \n \nMaximum Facility Output of  Co-Located Generating Facility: \n \n_______MW \n \n \nMW of Co-Located Generating Facility dedicated to Co-Located Load:  \n_______MW \n \n3.0 \nDescription of Co-Located Load: \n________________________________________ \n \n \n \n \n \n \n \n________________________________________ \n \n \n \n \n \n \n \n________________________________________ \n \n \nGross Demand of Co-Located Load:  \n \n \n \n \n______MW \n \n4.0 \nService under this Agreement may be subject to charges specified in the Tariff, which may \nchange from time to time, plus some combination of the charges detailed below.  (The \nappropriate charges for individual transactions will be determined in accordance with the \nterms and conditions of the Tariff.) \n \n \n4.1 \nEmbedded Cost Transmission Charge:_______________________ \n \n \n \n______________________________________________________ \n \n \n4.2 \nFacilities Study Charge:__________________________________ \n \n \n \n______________________________________________________ \n \n \n4.3 \nDirect Assignment Facilities Charge:________________________ \n \n \n \n______________________________________________________ \n \n \n4.4 \nAncillary Services Charge:________________________________ \n \n \n \n______________________________________________________"},{"page":106,"startToken":34102,"endToken":34109,"text":"35 \n \n \n4.5 \nOther Supporting Facilities Charge:_________________________ \n \n \n \n______________________________________________________"},{"page":107,"startToken":34109,"endToken":34115,"text":"36 \nSchedule A \n \nSingle Line Diagram"},{"page":108,"startToken":34115,"endToken":34240,"text":"37 \nPart III Network Integration Transmission Service \n \n29 \nInitiating Service \n. . .  \n29.2 \nApplication Procedures: \n. . .  \n(x) For Eligible Customers taking service on behalf of Co-Located Load: (1) a demonstration \nthat  the Co-Located Load on behalf of which the Eligible Customer is seekingtaking to obtain \nservice and the Co-Located Generating Facility are located on the same side of the Delivery \nPoint to the Transmission Provider’s Transmission System as the Co-Located Load; (2) \ndescription of the supply characteristics of the Co-Located Generating Facility, including the \ngeneration profile and other technical specifications as may be requested by the Transmission \nProvider; and (3) a description of the demand characteristics of the Co-Located Load above, \nincluding the demand profile and other technical specifications as may be requested by the \nTransmission Provider. \n \n. . ."},{"page":109,"startToken":34240,"endToken":34746,"text":"38 \nOperating Agreement, Schedule 1 \n \n7.4 \nAllocation of Auction Revenues. \n \n. . .  \n \n7.4.2 Auction Revenue Rights. \n \n. . .  \n(d) \nIn stage 2 of the allocation process, the Office of the Interconnection shall conduct an \niterative allocation process that consists of two rounds with up to one half of the remaining \nsystem Auction Revenue Rights capability allocated in each round.  Each round of this allocation \nprocess will be conducted sequentially with Network Service Users and Transmission Customers \nand Eligible Customers taking Firm Contract Demand Transmission Service being given the \nopportunity to view results of each allocation round prior to submission of Auction Revenue \nRight requests into the subsequent round.  In each round, each Network Service User shall \ndesignate a subset of buses from which Auction Revenue Rights will source and sink.  Valid \nAuction Revenue Rights source buses include only Zones, generators, hubs and external \nInterface Pricing Points.  Valid Auction Revenue Rights sink buses include only Zones, \ngenerators, hubs and external Interface Pricing Points.  The Network Service User shall specify \nthe amount of Auction Revenue Rights requested from each source bus to each sink bus. Prior to \nthe 2015/2016 Planning Period, each Auction Revenue Right shall sink to the  Energy Settlement \nArea of the Network Service User as described in Section 31.7 of Part III of the Tariff.  \nCommencing with the 2015/2016 Planning Period, each Auction Revenue Right shall sink to the \nEnergy Settlement Area of the Network Service User as described in Section 31.7 of Part III of \nthe Tariff, unless the Network Service User’s Energy Settlement Area represents the Residual \nMetered Load of an electric distribution company’s fully metered franchise area(s) or service \nterritory(ies) and the Network Service User elects to have its Auction Revenue Rights sink at the \naggregate load buses in a Zone.  The sum of each Network Service User’s Auction Revenue \nRights requests in each stage 2 allocation round for each Zone must be equal to or less than one \nhalf of the difference between the Network Service User’s peak load for that Zone as determined \npursuant to Section 7.4.2(b) and the sum of its Auction Revenue Right Allocation from stages \n1A and 1B of the allocation process for that Zone.  The stage 2 allocation to Transmission \nCustomers shall be as set forth in subsection (f). \n \n. . .  \n(l)  \nAn Eligible Customer taking Firm Contract Demand Transmission Service may request \nAuction Revenue Rights in stage 2 of the allocation process.  In each round, each Eligible \nCustomer taking Firm Contract Demand Transmission Service shall designate a subset of buses \nfrom which Auction Revenue Rights will source and sink. Valid Auction Revenue Rights source \nbuses include only Zones, generators, hubs and external Interface Pricing Points.  Valid Auction \nRevenue Rights sink buses include only Zones, generators, hubs and external Interface Pricing \nPoints. The Eligible Customers taking Firm Contract Demand Transmission Service shall specify \nthe amount of Auction Revenue Rights requested from each source to each sink.  The Auction \nRevenue Rights that such an Eligible Customer taking Firm Contract Demand Transmission"},{"page":110,"startToken":34746,"endToken":34786,"text":"39 \nService may request in each round of stage 2 of the allocation process must be equal to or less \nthan one half of the number of megawatts equal to the megawatts of Firm Contract Demand \nTransmission Service being provided."},{"page":111,"startToken":34786,"endToken":34853,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each \nperson designated on the official service list compiled by the Secretary in this proceeding.  \n \nDated at Washington, D.C., this 24th day of April 2026. \n \n \n \n \n \n \n \n \n/s/ Ruth M. Porter \n \n \n \n \n \n \n \nRuth M. Porter \n \n \n \n \n \n \n \nWright & Talisman, P.C. \n \n \n \n \n \n \n \n1200 G Street, NW, Suite 600 \n \n \n \n \n \n \n \nWashington, DC  20005 \n \n \n \n \n \n \n \n(202) 393-1200 \n \n \n \n \n \n \n \nporter@wrightlaw.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":0,"startToken":0,"endToken":362},{"p":3,"at":0,"title":"TABLE OF CONTENTS","method":"printed heading","endPage":3,"endAt":540,"startToken":362,"endToken":410},{"p":3,"at":540,"title":"B. Interim NITS Customers Should Not Be Allowed Access to Co-Located","method":"printed heading","endPage":3,"endAt":699,"startToken":410,"endToken":429},{"p":3,"at":699,"title":"C. The Illustrative Tariff Properly Details How PJM Will Study Requests for","method":"printed heading","endPage":3,"endAt":1896,"startToken":429,"endToken":550},{"p":3,"at":1896,"title":"D. Non-Monetary Penalties Are Just and Reasonable and Necessary to Support","method":"printed heading","endPage":4,"endAt":2024,"startToken":550,"endToken":826},{"p":4,"at":2024,"title":"IV. ADDITIONAL ILLUSTRATIVE TARIFF LANGUAGE TO INTEGRATE NEW","method":"printed heading","endPage":7,"endAt":1306,"startToken":826,"endToken":1884},{"p":7,"at":1306,"title":"I. INTRODUCTION","method":"printed heading","endPage":10,"endAt":3,"startToken":1884,"endToken":2670},{"p":10,"at":3,"title":"II. RESPONSE TO ISSUES RAISED IN REPLY BRIEFS","method":"printed heading","endPage":10,"endAt":52,"startToken":2670,"endToken":2678},{"p":10,"at":52,"title":"A. Contract Demand Transmission Service","method":"printed heading","endPage":20,"endAt":854,"startToken":2678,"endToken":6010},{"p":20,"at":854,"title":"B. Interim NITS Customers Should Not Be Allowed Access to Co-Located","method":"printed heading","endPage":26,"endAt":4,"startToken":6010,"endToken":8057},{"p":26,"at":4,"title":"C. The Illustrative Tariff Properly Details How PJM Will Study Requests for","method":"printed heading","endPage":43,"endAt":4,"startToken":8057,"endToken":13624},{"p":43,"at":4,"title":"D. Non-Monetary Penalties Are Just and Reasonable and Necessary to","method":"printed heading","endPage":59,"endAt":4,"startToken":13624,"endToken":18532},{"p":59,"at":4,"title":"E. Effective Date","method":"printed heading","endPage":62,"endAt":4,"startToken":18532,"endToken":19460},{"p":62,"at":4,"title":"F. Issues Beyond the Scope of This Proceeding","method":"printed heading","endPage":64,"endAt":4,"startToken":19460,"endToken":20113},{"p":64,"at":4,"title":"III. REVISIONS TO ILLUSTRATIVE TARIFF FILED WITH INITIAL BRIEF","method":"printed heading","endPage":68,"endAt":1012,"startToken":20113,"endToken":21899},{"p":68,"at":1012,"title":"IV. ADDITIONAL ILLUSTRATIVE TARIFF LANGUAGE TO INTEGRATE","method":"printed heading","endPage":70,"endAt":103,"startToken":21899,"endToken":22400},{"p":70,"at":103,"title":"V. DOCUMENT ENCLOSED","method":"printed heading","endPage":70,"endAt":195,"startToken":22400,"endToken":22414},{"p":70,"at":195,"title":"Attachment A: Redlines on Reply Brief to Illustrative Language for New","method":"printed heading","endPage":70,"endAt":352,"startToken":22414,"endToken":22437},{"p":70,"at":352,"title":"VI. CONCLUSION","method":"printed heading","endPage":71,"endAt":0,"startToken":22437,"endToken":22589},{"p":71,"at":0,"title":"Attachment A","method":"printed heading","endPage":72,"endAt":625,"startToken":22589,"endToken":22695},{"p":72,"at":625,"title":"Attachment F-3A. PJMSettlement shall be the Counterparty to the Interim Network Integration","method":"printed heading","endPage":72,"endAt":2125,"startToken":22695,"endToken":22906},{"p":72,"at":2125,"title":"Attachment F-3A, the transmission service provided to the Eligible Customer will automatically","method":"printed heading","endPage":73,"endAt":2006,"startToken":22906,"endToken":23300},{"p":73,"at":2006,"title":"Attachment F-3A, or requests in writing that the Transmission Provider file a","method":"printed heading","endPage":82,"endAt":2169,"startToken":23300,"endToken":27224},{"p":82,"at":2169,"title":"Attachment F-4, or requests in writing that the Transmission Provider file a","method":"printed heading","endPage":85,"endAt":968,"startToken":27224,"endToken":28475},{"p":85,"at":968,"title":"Attachment F-4, consistent with Good Utility Practice and any additional requirements reasonably","method":"printed heading","endPage":94,"endAt":38,"startToken":28475,"endToken":32109},{"p":94,"at":38,"title":"ATTACHMENT F-3A","method":"printed heading","endPage":101,"endAt":38,"startToken":32109,"endToken":33246},{"p":101,"at":38,"title":"ATTACHMENT F-4","method":"printed heading","endPage":111,"endAt":0,"startToken":33246,"endToken":34786},{"p":111,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":111,"endAt":509,"startToken":34786,"endToken":34853}]}