{"document":{"slug":"rec-20260424-5278","title":"Reply Protest of Maryland Office of People's Counsel to PJM Interconnection, L.L.C. initial brief and responsive pleadings","issued":"2026-04-24","accession":"20260424-5278","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Maryland Office of People's Counsel","kind":"protest","file":"sources/filings/text/20260424-5278_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260424-5278","tier":"record","sha256":"633fb5fbd822c868f5a92908a3fafce8a7125111bd497e64f7ec042aa4cc958d","pages":14,"tokens":2880,"emptyPages":[],"textThemes":["colo","adequacy","cost"]},"pages":[{"page":1,"startToken":0,"endToken":61,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM INTERCONNECTION, L.L.C.  \nDOCKET NOS. EL25-49-000 \n                          EL25-49-001 \n \n \n \nREPLY PROTEST OF THE MARYLAND OFFICE OF PEOPLE’S COUNSEL ON  \nPJM’S PROPOSED TERMS AND CONDITIONS \n \nApril 24, 2026 \nDAVID S. LAPP \nPEOPLE’S COUNSEL \n \nWilliam F. Fields \nDeputy People’s Counsel \n \nPhilip L. Sussler  \nSenior Assistant People’s Counsel \n \nMark S. Byrd \nAssistant People’s Counsel"},{"page":2,"startToken":61,"endToken":288,"text":"1 \nPursuant to the Commission’s December 18, 2025 order setting an April 17, 2026 \ndeadline for replies,1 which was extended one week by notice issued January 23, 2026, \nthe Maryland Office of People’s Counsel (“MPC”) respectfully submits the following \nreply regarding PJM Interconnection, L.L.C.’s (“PJM”) initial brief (hereinafter, “PJM \nInitial Brief”) and responsive pleadings submitted in the above captioned proceeding. \nINTRODUCTION \nPJM’s co-location proposals in this docket have major implications for Maryland’s \nresidential ratepayers due to the potential impact on capacity market prices. The impact \non existing customers depends on whether and how co-located arrangements between \nnew large loads and existing generation effects supply in the Base Residual Auction \n(“BRA”) or effects procurement targets in PJM’s planned reliability backstop \nprocurement (“RBP”). This distinction is substantial considering the BRA will allocate \ncosts across the system, whereas the RBP, as currently under consideration in the PJM \nstakeholder process, may allocate costs to individual electric distribution companies \n(“EDCs”) and/or load serving entities (“LSEs”) on a pro rata or other basis.2 As described \nby PJM’s Independent Market Monitor, co-locating data center loads with existing \n \n1 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“Show Cause Order”). \n2  See Reliability Backstop Procurement Design, PJM Staff (April 2026) at 9, https://www.pjm.com/-\n/media/DotCom/committees-groups/cifp-rbp/2026/20260416/20260416-item-05---pjm-reliability-\nbackstop-procurement-design---pjm-presentation.pdf."},{"page":3,"startToken":288,"endToken":571,"text":"2 \ngeneration reduces the supply of capacity to the BRA, thereby increasing capacity \nprices.3 \nAdditionally, PJM’s co-location proposals with respect to existing generation are \ninconsistent between this docket and the compliance filing in Docket No. ER26-1479-\n000. Whereas PJM’s compliance filing in Docket No. ER26-1479-000 proposes tariff \nrevisions that would facilitate new large loads co-locating with existing generators, PJM’s \nfiling in this docket suggests that only new generation is eligible for the new transmission \nservices.4 These inconsistencies render it impossible to determine the effect of these \nproposals on ratepayers. The Commission should therefore require PJM to clarify \nwhether these co-location rules are intended to apply to co-location arrangements \nundertaken with existing baseload generation so the effect of these transmission services \non ratepayers can be determined and, if so, how adverse impacts on existing (particularly \nresidential) customers can be mitigated. \nThe Commission should not accept co-location rules that facilitate the \ninterconnection of large load data centers to the detriment of residential ratepayers. Such \nan outcome would be at direct odds with the statement of principles signed by the \nNational Energy Dominance Council within the White House and thirteen governors of \n \n3 See Comments to the Maryland PSC Senate Bill 1 Co-location Study Administrative Docket PC 61 (Sep. \n24, 2024) at 1, \nhttps://www.monitoringanalytics.com/filings/2024/IMM_Comments_MDPSC_PC61_20240924.pdf. \n4 Compare PJM, Proposed Tariff Revisions, Docket No. ER26-1479-000 (Feb. 23, 2026) (defining “Co-\nLocated Generating Facility” as “an existing or planned Generating Facility that is physically connected \nto a Co-Located Load…”) with PJM Initial Brief at 79 (explaining that it is unlikely that generation \nintended to serve Co-Located Load will be constructed and operational before June 1, 2029)."},{"page":4,"startToken":571,"endToken":820,"text":"3 \nstates within PJM5 stating that PJM’s tariff revisions should reflect how costs are \nallocated to data centers to protect residential customers. It would also contradict the \nWhite House’s ratepayer protection pledge that companies will build, bring, or buy the \nnew generation resources and electricity needed to satisfy their new energy demands, \npaying the full cost of those resources whether by building, or buying from, new or \notherwise additive power plants.6 \nBACKGROUND \n1. Show Cause Order: \nOn December 18, 2025, the Commission determined that PJM’s tariff is unjust and \nunreasonable, explaining generally that the tariff: \ndoes not contain provisions addressing with sufficient clarity or consistency \nthe rates, terms, and conditions of service that apply to Interconnection \nCustomers serving Co-Located Load, including generators serving Co-\nLocated Load in a configuration with special protection schemes to prevent \nthe Co-Located Load from taking energy from the transmission system.7  \n \nThe Commission directed PJM to revise its tariff to provide clarity regarding the \nresponsibilities of existing interconnection customers seeking to serve co-located load \nusing their generating facilities.8 The Commission also directed PJM to file tariff changes \nspecifying that an interconnection customer seeking to serve co-located load using an \n \n5 See Statement of Principles Regarding PJM, White House and 13 State Governors (Jan. 16, 2026), \nhttps://www.energy.gov/documents/statement-principles-regarding-pjm. _  \n6 See Donald J. Trump, Ratepayer Protection Pledge Proclamation, \nhttps://www.whitehouse.gov/presidential-actions/2026/03/ratepayer-protection-pledge-proclamation/ \n(Mar. 4, 2026). \n7 Show Cause Order at P 249.  \n8 Id. P 225."},{"page":5,"startToken":820,"endToken":1057,"text":"4 \nexisting generating facility must bear the costs of all network upgrades that PJM finds are \nnecessary to preserve transmission system reliability for existing transmission \ncustomers.9  \nFurthermore, the Show Cause Order also required that PJM define “Co-Located \nLoad” as a “configuration [that] refers to end-use customer load that is physically \nconnected to the facilities of an existing or planned Customer Facility on the \nInterconnection Customer’s side of the Point of Interconnection to the PJM Transmission \nSystem.”10 The Commission clarified that an existing generating facility may not begin \nserving Co-Located Load that is not Network Load until it has delisted its Capacity \nInterconnection Rights for the portion of the generating facility to be designated to serve \nany Co-Located Load that is not receiving network integration transmission service \n(“NITS”).11 \nThe Commission’s Show Cause Order in this proceeding also directed PJM to \nrevise its tariff to allow eligible customers seeking to take NITS on behalf of co-located \nload to take a new interim, non-firm transmission service until all Network Upgrades \nnecessary to provide NITS are complete. The Commission also directed PJM to offer two \nother new transmission services—a firm contract demand transmission service and a non-\nfirm contract demand transmission service—that an eligible customer can choose to take \non behalf of a co-located load instead of taking NITS.”12  \n \n9 Id. P 176. \n10 Id. P 164. \n11 Id. P 230. \n12 Id. P 160."},{"page":6,"startToken":1057,"endToken":1317,"text":"5 \n2. White House and PJM Governors Statement of Principles and White House \nPledge \n \nOn January 15, 2026, the National Energy Dominance Council within the White \nHouse and thirteen governors of states within PJM signed the Statement of Principles \nurging PJM to expeditiously file proposed tariff revisions with the Commission that \nreflect a set of principles for how generation capacity for data centers should be procured, \nand how costs should be allocated to data centers to protect residential customers.13 \nSpecifically, under these principles, PJM should hold a procurement for capacity through \nthe conduct of at least one reliability backstop auction (“RBA”) to procure new capacity \nresources, with the costs of such new capacity going primarily to load serving entities \nwith new data centers that have not self-procured new capacity or agreed to be \ncurtailable.14  \nOn March 4, 2026, the White House issued the Ratepayer Protection Pledge that \ncompanies will build, bring, or buy the new generation resources and electricity needed \nto satisfy their new energy demands, paying the full cost of those resources whether by \nbuilding, or buying from new or otherwise additive power plants.15 The pledge also \nprovides that where possible, these companies will also add more capacity that serves the \nbroader public by increasing supply.16 \n \n13 See Statement of Principles Regarding PJM, White House and 13 State Governors (Jan. 16, 2026),  \nhttps://www.energy.gov/documents/statement-principles-regarding-pjm. \n14 Id. at 1. \n15 See Donald J. Trump, Ratepayer Protection Pledge Proclamation, \nhttps://www.whitehouse.gov/presidential-actions/2026/03/ratepayer-protection-pledge-proclamation/ \n(Mar. 4, 2026). \n16 See id."},{"page":7,"startToken":1317,"endToken":1550,"text":"6 \n \n3. PJM Board Letter \n \nOn January 16, 2026, the PJM Board of Managers (“Board”) issued a decisional \nletter expressing that PJM’s system is at higher risk than ever due to the PJM’s capacity \nmarket clearing short of its reliability requirement for the first time in history in the \n2027/2028 BRA.17 The Board determined that this outcome is unacceptable and warrants \ncorrective action through initiation of a reliability backstop procurement and a holistic \nreview of investment incentives in PJM’s markets in 2026, among other initiatives.  \n4. PJM Compliance Filing in Docket No. ER26-1479-000 \nPJM’s February 23 Compliance Filing in Docket No. ER26-1479-000 generally \nsets forth the relative obligations of project developers seeking to serve co-located load, \nand PJM. The proposal defines “Co-Located Generating Facility” as “an existing or \nplanned Generating Facility that is physically connected to a Co-Located Load,” and \n“Co-Located Load” as “a configuration that refers to end-use customer load that is \nphysically connected to the facilities of an existing or planned Generating Facility on the \nProject Developer’s side of the Point of Change in Ownership to the Transmission \nProvider’s Transmission System.”18 Importantly, these definitions appear to \naccommodate not only new generators, but existing generators seeking to serve co-\nlocated load. \n \n17 Board Letter at 1 https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-\ndisclosures/2026/20260116-pjm-board-letter-re-results-of-the-cifp-process-large-load-additions.pdf.  \n18 Proposed Tariff Revisions, Part I, Definition of Co-Located Load."},{"page":8,"startToken":1550,"endToken":1806,"text":"7 \nAdditionally, the February 23 Compliance Filing in Docket No. ER26-1479-000 \nproposes tariff revisions requiring that “[a] Project Developer whose planned \nmodifications include Co-Located Load configuration shall be required to enter into a \nNecessary Studies Agreement with Transmission Provider in the form set forth in Tariff, \nPart IX, Subpart G.”19 The proposed tariff revisions would require a Project Developer to \nprovide the Transmission Provider with “the amount of reduction to Capacity \nInterconnection Rights to facilitate the Co-Located Load configuration.”20 The proposed \nrevisions also provide that:  \nProject Developer shall be responsible for the costs of any modifications or \nNetwork Upgrades identified by Transmission Provider, as applicable, as a \nresult of the change to the Interconnection Service Agreement or \nGeneration Interconnection Agreement to serve Co-Located Load, \nincluding to reflect any reduction in Capacity Interconnection Rights.21 \n \n“Capacity Interconnection Rights” (“CIRs”) are previously defined in PJM’s tariff as “the \nrights to input generation as a Generation Capacity Resource into the Transmission \nSystem at the Point of Interconnection where the generating facilities connect to the \nTransmission System.”22 Thus, the proposed revisions appear to accommodate new \ngenerators seeking to serve co-located load, as well as existing generators seeking to \nserve co-located load by reducing their CIRs, and, thus, their ability to input generation \nonto PJM’s transmission system. \n \n \n19 Id. Part VIII, Subpart A, section 401.H.3.b. \n20 Id. Section 401.H.3.b.i.c. \n21 Id. Section 401.H.3.b.iii. \n22 PJM, Intra-PJM Tariffs, OATT, § I.1 Definitions - C - D (40.1.1)."},{"page":9,"startToken":1806,"endToken":2033,"text":"8 \n5. PJM’s Initial Brief \nPJM’s Initial Brief proposes non-rate terms and conditions for the new \ntransmission services required by the Show Cause Order (Interim NITS and the two \nContract Demand Transmission Services). PJM states that Interim NITS “will \nsignificantly affect the PJM Load Forecast and expected demand.”23 PJM seeks an \neffective date of June 1, 2029, for tariff revisions implementing the three new \ntransmission services. In support of this effective date, PJM explains that it is unlikely \nthat generation intended to serve Co-Located Load will be constructed and operational \nbefore June 1, 2029, which suggests that PJM does not intend for existing load to be \neligible for these Co-Located Load transmission services.24 \nPROTEST \nAs explained by the Commission in the Show Cause Order, PJM’s tariff is unjust \nand unreasonable because it does not contain provisions addressing with sufficient clarity \nor consistency the rates, terms, and conditions of service that apply to generators serving \nCo-Located Load and Eligible Customers taking transmission service on behalf of Co-\nLocated Load.25 However, in light of the recent issuance of Statement of Principles issued \njointly by the White House and thirteen governors of states within PJM, the Ratepayer \nProtection Pledge, and PJM’s proposed Reliability Backstop Procurement applicable to \n \n23 PJM Initial Brief at 79. \n24 PJM Initial Brief at 79. \n25 See Show Cause Order at P 2."},{"page":10,"startToken":2033,"endToken":2313,"text":"9 \nnew capacity resources, PJM’s proposed terms and conditions remain without sufficient \nclarity and consistency.  \nThe Statement of Principles directed PJM to hold a reliability backstop auction to \nprocure new capacity resources, which PJM has proposed to implement in two phases—\nthe first in September 2026 and the second in March 2027.26 The Statement of Principles \nfurther urges that costs of such new capacity should go primarily to load serving entities \nwith new data centers that have not self-procured new capacity or agreed to be \ncurtailable.27 The Ratepayer Protection Pledge also commits the major data center \ndevelopers to procure new capacity resources to serve their needs. Thus, the thrust of the \nStatement of Principles and the Ratepayer Protection Pledge is that generally new data \ncenters should pay for new capacity.  \nUnder this framework, new data centers that are not served by self-procured new \nco-located generation could be subject to higher costs from the load serving entity as \nresult of the reliability backstop auction. But PJM’s proposed terms and conditions do not \nexplain how existing capacity resources that shift to co-located arrangements with new \ndata centers would be treated relative to the PJM’s proposed RBP. For example, it is \nunclear whether capacity from existing generators that remove themselves from the \ncapacity market and enter co-location arrangements with new data center load would \nneed to be replaced with new capacity through the RBP or in the regular BRA to serve \n \n26 See Statement of Principles at 1; See Reliability Backstop Procurement Design, PJM Staff (April 2026) \nat 2, https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260416/20260416-item-\n05---pjm-reliability-backstop-procurement-design---pjm-presentation.pdf. \n27 See Statement of Principles at 1."},{"page":11,"startToken":2313,"endToken":2588,"text":"10 \nexisting load. Additionally, it is unclear whether new data center load that co-locates with \nan existing generator will be included in the cost allocation of the reliability backstop \nprocurement. \nIf the capacity of existing generation that shifts to serve new co-located data center \nload is added to the BRA, ratepayers would be saddled with enormous costs that should \nbe assigned to the co-located load, in contravention of the Statement of Principles and the \nRatepayer Protection Pledge. For example, analysis by PJM’s Independent Market \nMonitor concluded that if 1,000 UCAP MW of nuclear capacity in Maryland was \nremoved—due to shifting to serving a co-located load for example—total market \nrevenues for the 2025/2026 BRA would increase by more than $3.6 billion.28 Yet PJM’s \ncompliance filing provides no explanation as to how such costs would be paid by new co-\nlocated data center load rather than being shifted to existing ratepayers. \nPJM’s proposed terms and conditions thus leave significant and fundamental \nquestions unanswered with respect to how existing generation can serve new co-located \ndata center load. Without providing more details regarding how the proposal will align \nwith PJM’s plans for the RBA, PJM’s proposal remains unclear and inconsistent with the \nStatement of Principles underpinning the RBA. This lack of clarity and consistency \ncauses PJM’s proposed terms and conditions to remain unjust and unreasonable. At a \nminimum, the Commission should require PJM’s proposal to be consistent across the co-\n \n28 See Comments to the Maryland PSC Senate Bill 1 Co-location Study Administrative Docket PC 61 \n(Sep. 24, 2024) at 3, \nhttps://www.monitoringanalytics.com/filings/2024/IMM_Comments_MDPSC_PC61_20240924.pdf."},{"page":12,"startToken":2588,"endToken":2795,"text":"11 \nlocation compliance dockets so the effect on ratepayers may be understood and \ndemonstrate how its proposal meets the ratepayer protection standards set forth in the \nStatement of Principles and Ratepayer Protection Pledge.  \nCONCLUSION \nThe issuance of the Statement of Principles by the White House and thirteen \ngovernors of states within PJM calling for an RBA to serve new data center load and the \nRatepayer Protection Pledge are salient intervening events that have occurred since the \nShow Cause Order issued. However, despite the significance of PJM’s work toward \nimplementing an RBP, fundamental issues surrounding how existing generators that shift \nto serve Co-Located Load under PJM’s proposed tariff revisions will be treated relative to \nthe RBP remain unaddressed. As a result, PJM’s proposed revisions do not provide the \nclarity and consistency required by the Show Cause Order. PJM’s proposed terms and \nconditions thus are unjust and unreasonable without a complete picture of how they will \ninteract with PJM’s planned RBP. The Commission should clarify how its proposal meets \nthe ratepayer protection standards set forth in the Statement of Principles and Ratepayer \nProtection Pledge and defer action on the proposed revisions until after PJM proposes \ntariff revisions to implement its planned RBP.  \n \nRespectfully submitted, \n \nDAVID S. LAPP \nPEOPLE’S COUNSEL"},{"page":13,"startToken":2795,"endToken":2832,"text":"12 \nWilliam F. Fields \nDeputy People’s Counsel \n \nPhilip L. Sussler \nSenior Assistant People’s Counsel \n \n/electronic signature/ \nMark S. Byrd \nAssistant People’s Counsel \n \nOffice of People’s Counsel \n6 St. Paul Street, Suite 2102 \nBaltimore, Maryland 21202 \n(410) 767-3908"},{"page":14,"startToken":2832,"endToken":2880,"text":"13 \nCERTIFICATE OF SERVICE \nI hereby certify that I have this day caused the foregoing pleading to be served upon each \nperson designated on the official service list compiled by the Secretary in this proceeding. \nDated this 24th day of April, 2026. \n/s/ electronic signature----_____ \nMark S. Byrd"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":429,"startToken":0,"endToken":125},{"p":2,"at":429,"title":"INTRODUCTION","method":"printed heading","endPage":4,"endAt":472,"startToken":125,"endToken":643},{"p":4,"at":472,"title":"BACKGROUND","method":"printed heading","endPage":12,"endAt":230,"startToken":643,"endToken":2621},{"p":12,"at":230,"title":"CONCLUSION","method":"printed heading","endPage":14,"endAt":4,"startToken":2621,"endToken":2833},{"p":14,"at":4,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":14,"endAt":298,"startToken":2833,"endToken":2880}]}