{"document":{"slug":"rec-20260424-5295","title":"Second Reply Brief of Eolian, L.P., et al","issued":"2026-04-24","accession":"20260424-5295","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Eolian, L.P.Antora Energy LLCCalibrant Energy ,Mainspring Energy ,U.S. Energy Storage Coalition ,Verrus LLC ,","kind":"brief","file":"sources/filings/text/20260424-5295_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260424-5295","tier":"record","sha256":"3a7f5980cf41ddded3dd813bdc4679f77f22559170832193570bf59e87a37578","pages":30,"tokens":9486,"emptyPages":[],"textThemes":["flex","colo","study"]},"pages":[{"page":1,"startToken":0,"endToken":258,"text":"1 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C., et al. \n) \nDocket Nos. EL25-49-000 \n) \n \n \n         EL25-49-001 \n) \nLarge Loads Co-Located at Generating Facilities  \n)  \n \n \n         AD24-11-000 \n) \nConstellation Energy Generation, LLC  \n \n)  \n \n \n         EL25-20-000 \nv.  \n \n \n \n \n \n \n) \n \n \n         (Consolidated) \nPJM Interconnection, L.L.C.   \n \n \n)  \n \n \n \n \nSECOND REPLY BRIEF OF JOINT CO-LOCATION DEVELOPERS \n \nPursuant to the Federal Energy Regulatory Commission’s (Commission) December 18, \n2025 order (Co-Location Order),1 Eolian, L.P. (Eolian), Antora Energy, Inc., Calibrant Energy \n(Calibrant), Mainspring Energy, Inc. (Mainspring), U.S. Energy Storage Coalition, and Verrus, \nLLC (Verrus) (collectively, the Joint Co-Location Developers) submit this reply to the response \nbriefs filed in the captioned dockets on March 25, 2026. The brief draws upon the affidavit of \nAndrew Levitt and Aniruddh Mohan of the Brattle Group on behalf of Eolian, at Attachment A.2 \nAs highlighted in the Independent Market Monitor (IMM)’s response brief, PJM is proposing to \nrestrict the availability of non-firm contract demand service on the basis of vague reliability \nconcerns that are neither supported nor explained. But as the affidavit demonstrates, workable \nnon-firm service offerings that are broadly available are fully consistent with reliable system \noperation, as demonstrated in other regions that are rapidly moving to implement non-firm \ntransmission service offerings.  \nThe Commission should not bow to the IMM’s and PJM’s thinly-supported attempts to \nundermine the Co-Location Order. PJM’s proposal, if adopted, would fall short of the \n \n1 PJM Interconnection, LLC, 193 FERC ¶ 61,217 (2025) (Co-Location Order). \n2 Attach. A, Supplemental Affidavit of Andrew Levitt & Aniruddh Mohan on Behalf of Eolian, L.P. (Levitt & Mohan \nAff.)."},{"page":2,"startToken":258,"endToken":526,"text":"2 \nCommission’s goal of “ensuring that all Americans (and all American businesses) have access to \naffordable, reliable, and secure electricity.”3 As other regions are demonstrating, non-firm \ntransmission service holds significant potential to address the speed-to-power challenge while \nmaintaining a reliable electricity system. We therefore reiterate our request for the Commission \nto require PJM to establish workable Non-Firm Contract Demand Service (Non-Firm CDS) rules \nfree from arbitrary and punitive terms that discourage their use, and Interim Network Integration \nTransmission Service (Interim NITS) rules that allow load to rely on co-located supply if it is not \noffering into the capacity market. By following through on the pathbreaking Co-Location Order, \nthe Commission can achieve its goals of ensuring that all loads can connect to the transmission \nsystem in a timely, orderly, and non-discriminatory manner.  \nI. \nARGUMENT \nA. \nA broad range of stakeholders support full implementation of the Co-\nLocation Order.  \n \nA broad range of stakeholders, representing the parties aiming to engage in co-location \narrangements as both load and generation, support robust implementation of the Co-Location \nOrder. Their support demonstrates that a broad range of developers stand ready to achieve the \nCommission’s goals in the Co-Location Order of efficient and cost-effective load and generation \ndevelopment should the Commission require PJM to enable a workable, fair, and reliable service \npathway. Specifically, these parties share our concerns that PJM and the PJM Transmission \nOwners’ proposals contravene the letter and spirit of the Co-Location Order and the \nCommission’s other requirements by:  \n \n3 Interconnection of Large Loads to the Interstate Transmission System, 195 FERC ¶ 61,045, Order Regarding Intent \nto Act at P 4 (2026)."},{"page":3,"startToken":526,"endToken":944,"text":"3 \n• limiting the availability of Non-Firm CDS to generator outages;4  \n• limiting the ability of Interim NITS customers to serve their load from co-located \ngenerators during curtailment conditions;5 \n• setting the Non-Firm CDS rate at the same level as the higher-quality Firm Contract \nDemand Service (Firm CDS) rate;6 \n• threatening inadvertent misoperation with draconian penalties;7 and \n• delaying implementation, without justifying why such delay is necessary.8 \nThe Commission should address these concerns in adopting a replacement rate, directing PJM to \nestablish new transmission services that are commercially workable and therefore will result in \ntheir widespread use. \nB. \nThe Commission must adopt a Grid Reliance Charge that is cost justified. \nIn addition to these concerns, we also agree with Constellation, Vistra, and Geronimo \nPower that the proposed Grid Reliance Charge “is derived from an unsound methodology that \nviolates cost causation principles”9—a point that we did not raise in our initial brief. The \ntestimony of Zachary Ming on behalf of Constellation explains that the PJM “Transmission \nOwners attribute the full depreciation costs for a variety of transmission components (i.e. towers \nand fixtures, poles and fixtures, overhead conductors, etc.) that are sized to meet the actual peak \n \n4 See Advanced Energy United & Solar Energy Industries Association March 25, 2026 Reply Brief at 5-10; \nConstellation March 25, 2026 Reply Brief at 10-12; Data Center Coalition March 25, 2026 Response Brief at 4-6; \nVistra March 25, 2026 Response Brief at 25. \n5 See Advanced Energy United & Solar Energy Industries Association March 25, 2026 Reply Brief at 19-21, Data \nCenter Coalition March 25, 2026 Response Brief at 4-6; Enchanted Rock March 25, 2026 Reply Brief and Protest at \n8-10. Note that such a limit is not proposed in the tariff language, but PJM stated to stakeholders that it plans to \nimpose such a limit. See, e.g., Enchanted Rock March 25, 2026 Reply Brief and Protest at 2, 6-7. \n6 Geronimo Power March 25, 2026 Response Brief at 4-9; Vistra March 25, 2026 Response Brief at 16-18. \n7 Constellation March 25, 2026 Reply Brief at 18-21; Data Center Coalition March 25, 2026 Response Brief at 7-8; \nVistra March 25, 2026 Response Brief at 29-30. \n8 Constellation March 25, 2026 Reply Brief at 6-9; Data Center Coalition March 25, 2026 Response Brief at 9; \nVistra March 25, 2026 Response Brief at 5-12. \n9 Constellation March 25, 2026 Reply Brief at 25; see also Geronimo Power March 25, 2026 Response Brief at 9-\n15; Vistra March 25, 2026 Response Brief at 18-23."},{"page":4,"startToken":944,"endToken":1388,"text":"4 \ndemand requirements of the PJM system, even though customers paying the GRC, by definition, \ndo not impose any demand or withdraw any energy from the PJM system.”10  \nThe Joint Co-Location Developers stand ready and willing to pay our fair share of \ntransmission system costs. But part of the point of the new service framework is to reduce the \nneed for new transmission infrastructure. Rates for the new services should not be premised on \ncosts of infrastructure that is not needed to serve customers of these new services. Zachary Ming \nproposes an alternate cost calculation framework that follows the Commission’s cost causation \nprinciples.11 The Commission should direct the PJM Transmission Owners to adopt a Grid \nReliance Charge based on that methodology. \nC. \nThe Commission should not allow unsubstantiated reliability concerns to \ndefeat implementation of the Non-Firm CDS product required by the Co-Location \nOrder. \n \nThe IMM leans heavily on PJM’s testimony to argue that PJM cannot reliably offer the \ntransmission services required by the Co-Location Order.12 PJM asserts that Non-Firm CDS must \nbe offered only “as a standby product” available “only ‘under limited circumstances.’”13 Its \nposition appears to rest on the unexplained premise that offering non-firm transmission service \nunder normal conditions involves widespread reliance on Remedial Action Schemes to control \nwithdrawals. Reliance on Remedial Action Schemes, PJM contends, will create “complexity”14 \n \n10 Constellation March 25, 2026 Reply Brief, Attachment 1, Testimony of Zachary Ming (Ming Test.) at 12. \n11 Id. at 14-15. \n12 See IMM March 25, 2026 Reply Brief at 6 (arguing that, based on PJM’s statements, “there can be no such service \nas non-firm CDS that is fully consistent with maintaining a reliable PJM transmission system” and “the system \nwould become unmanageable if all or a significant part of the data center users wanted to use non-firm CDS,” and \nfurther asserting that “[i]t is clear from PJM’s filing that Interim NITS . . . is not consistent with PJM’s normal \ntransmission planning process and imposes potentially significant risks on the PJM system.”); see also id. at 2 \n(“some of the Commission’s defined transmission services cannot work”; “non-firm CDS and Interim NITS create \nsignificant reliability risks for the transmission system”; “the December 18th Order represents a set of dramatic \nchanges in the nature of transmission service in PJM, not all of which are workable consistent with maintaining the \nreliable operation of the PJM system.”).  \n13 PJM Initial Brief at 10 (citing Attach. B, Affidavit of Dr. Sami Abdulsalam (Abdulsalam Aff.) ¶ 14). \n14 Id. at 34-35 (“The control technologies and protection systems necessary to provide Non-Firm Contract Demand \nTransmission Service (and Interim NITS) is emblematic of the complexity associated with Non-Firm Contract"},{"page":5,"startToken":1388,"endToken":1723,"text":"5 \nthat “introduces significant risks,”15 including that “unintended protection system misoperation . \n. . could lead to cascading events.”16  \nPJM’s and the IMM’s claims are based on the mistaken assumption that increasing the \nnumber of customers taking non-firm transmission service will proportionally increase system \nreliance on Remedial Action Schemes. Rather, in the attached testimony, Levitt and Mohan \ndemonstrate that customers taking non-firm transmission service will not implicate widespread \nreliance on Remedial Action Schemes because customers can instead generally rely on simpler \nwithdrawal-limiting protection systems internal to facilities to comply with curtailment \nrequirements.17 Further, Levitt and Mohan explain that PJM’s proposal to limit Non-Firm CDS \navailability does not follow logically from its concerns with the reliability of Remedial Action \nSchemes because PJM’s limitations will increase the time during which loads must rely on \nfacility-level protection systems and Remedial Action Schemes. Last, Levitt and Mohan show \nthat experience from other regions confirms that non-firm transmission service can be provided \nwithout the limitations PJM seeks to impose. Specifically, Southwest Power Pool (SPP) and the \nElectric Reliability Council of Texas (ERCOT) are each developing non-firm services like those \nenvisioned in the Co-Location Order—and on a much faster timeline than that proposed by \nPJM—without raising the purported reliability concerns that PJM and the IMM point to.18 \n1. \nPJM and the IMM’s claims about Remedial Action Schemes do not \njustify limiting the availability of Non-Firm CDS. \n \n \nDemand Transmission Service from an operations and planning perspective”); id. at 10 (“the complexities associated \nwith the provision of Non-Firm Contract Demand Transmission Service call for relying on such service as a standby \nproduct only ‘under limited circumstances.’” (quoting Abdulsalam Aff. ¶ 14) (emphasis added)); id. at 60 (“the \ncomplexity introduced by the necessary control technology and protection systems (e.g., RAS) introduces significant \nrisks, including possible failure to communicate material information about such protective technology or system” \n(citation omitted)). \n15 Id. at 60. \n16 Id. at 10 (citing Abdulsalam Aff. ¶ 12). \n17 Levitt & Mohan Aff. at 9, 11-13. \n18 Id. at 5-8."},{"page":6,"startToken":1723,"endToken":2025,"text":"6 \n \nPJM contends that Non-Firm CDS should be offered only during a limited number of \nhours due to reliability risks from over-reliance on Remedial Action Schemes.19 This argument is \nflawed for several reasons.  \nFirst, the IMM and PJM elide a distinction between simple withdrawal-limiting \nprotection systems that are required by PJM for sites taking non-firm transmission service, and \nstandard Remedial Action Schemes. Levitt and Mohan emphasize that there is an important \ndifference between the two.20 Unlike standard Remedial Action Schemes, which monitor and \ncontrol components across the grid, simple withdrawal-limiting protection systems monitor and \ncontrol only facility-internal components, monitoring flows, adjusting consumption or generation \nat the site level, and disconnecting from the grid if necessary. In this way, while both systems are \ndesigned to prevent unauthorized withdrawals from the grid, they operate at different levels of \nthe electrical grid. A facility-level protection scheme operates on a level comparable to a home’s \nmain circuit breaker. A standard Remedial Action Scheme is more like fast-acting air traffic \ncontrol—it reacts to events in one area to manage the flow across a different part of the system to \nprevent overloads. \nThis means that simple withdrawal-limiting protection systems can be relied upon much \nmore extensively than standard Remedial Action Schemes without creating the same \ncomplexities and interdependencies.21 And in fact, reliance on simple withdrawal-limiting \nprotection systems under PJM’s proposal will extend beyond Non-Firm CDS customers: \ncustomers taking Firm CDS while self-supplying a portion of their load will also rely on simple \n \n19 See PJM Initial Brief at 10 (citing Abdulsalam Aff. ¶ 14). \n20 Levitt & Mohan Aff. at 11-13. \n21 Id. at 13 (“Because of its simplicity and localized scope, it would appear on first principles that extensive \ninstallation of withdrawal-limiting protection systems would not introduce the complexity that is associated with \nstandard RASs.”)."},{"page":7,"startToken":2025,"endToken":2412,"text":"7 \nwithdrawal-limiting protection systems to prevent withdrawals above their contracted level.22 \nNevertheless, PJM does not impose limits on when a Firm CDS customer may self-supply a \nportion of their load, nor does it voice concerns about the ability to serve Firm CDS customers \nreliably. \nSecond, PJM and the IMM ignore the redundancy built into the proposed service \nconstruct. The co-location arrangements contemplated by the Co-Location Order entail \nredundancy in the required protection systems.23 This redundancy is designed to protect against \nfailure and renders misoperation, already unlikely, even more improbable. \nThird, limiting the scope of Non-Firm CDS scheduling to generator outages, as PJM \nproposes, will increase reliance on simple withdrawal-limiting protection systems rather than \ndecrease it. This is because withdrawal-limiting protection systems are only active when the \ncustomer cannot withdraw, i.e., because no transmission service has been scheduled. By limiting \nNon-Firm CDS to periods of generator outage, PJM’s proposal increases the frequency with \nwhich a customer will not be authorized to withdraw, thereby increasing the time for which such \nmechanisms must be relied upon. As Levitt and Mohan explain, “[i]t therefore follows that \nnarrowing eligibility for N[on] F[irm] CDS scheduling does not decrease complexity.”24  \nFourth, to the extent that PJM is concerned about managing the potential for interactions \namong standard Remedial Action Schemes that are monitoring and controlling elements on the \nbulk transmission system (as distinct from simple withdrawal-limiting protection systems), it \n \n22 Id. at 13-14. There is also no need for protection systems of this nature, which exist simply to limit withdrawals \nconsistent with transmission service limits, to be temporary as PJM claims. See id. at 13 (citing Abdulsalam Aff. ¶ \n10 (“The temporary nature of such a protection system for this type of firm service is necessary to ensure the \nintegrity and reliable operation of the transmission system as a whole since protection systems are designed based on \nsystem conditions anticipated at that time and will continue to change as system conditions evolve.”)). Levitt and \nMohan note that “it is unclear why such a simple system would need to evolve with system conditions.” Id.  \n23 The PJM Transmission Owners recommend, and we agree, that “[a]ll [Special Protection Schemes] and [Remedial \nAction Schemes] should be fully redundant.” PJM Transmission Owners Initial Brief at 23. \n24 Levitt & Mohan Aff. at 14."},{"page":8,"startToken":2412,"endToken":2728,"text":"8 \nshould limit the arming of such Remedial Action Schemes, or avoid installing them in the first \nplace, and instead maximize use of pre-contingency Non-Firm CDS curtailment through \nscheduling.25 Reliance on pre-contingency curtailment is similar to how SPP and ERCOT \nenvision curtailment under the non-firm transmission services that they are developing, described \nin further detail below.  \nFor these reasons, PJM’s and the IMM’s concerns do not “call for relying on” Non-Firm \nCDS “as a standby product” only.26 The Commission should instead require PJM to establish a \nNon-Firm CDS product consistent with the requirements of the Co-Location Order.  \n2. \nNon-firm transmission services proposed by SPP and ERCOT show \nthat non-firm transmission service can be offered reliably. \n \nOther grid operators are developing non-firm transmission service options without the \nlimitations that PJM and the IMM claim are needed.27 Specifically, SPP and ERCOT are \ndeveloping non-firm services similar to those proposed in the Co-Location Order, showing that \nnon-firm service can be offered reliably on an as-available basis and implemented quickly. \nLevitt and Mohan explain that SPP recently filed tariff revisions in Docket No. ER26-\n1323 to offer a new non-firm Conditional High Impact Large Load Service (CHILLS) that would \nallow non-firm transmission service that is curtailable in the face of insufficient transmission \ncapacity.28 Unlike PJM’s Non-Firm CDS product, however, SPP plans to make CHILLS broadly \navailable during all non-constrained hours, rather than limit use to periods when an associated \n \n25 Id. at 14-15. \n26 See PJM Initial Brief at 10. \n27 See IMM March 25, 2026 Reply Brief at 2 (“some of the Commission’s defined transmission services cannot \nwork”); PJM Initial Brief at 10 (“the complexities associated with the provision of Non-Firm Contract Demand \nTransmission Service call for relying on such service as a standby product only ‘under limited circumstances.’”). \n28 Levitt & Mohan Aff. at 5-6 (referencing SPP, Filing, Docket No. ER26-1323-000 (filed Feb. 10, 2026))."},{"page":9,"startToken":2728,"endToken":3128,"text":"9 \ngeneration resource is on outage.29 In addition, unlike PJM’s proposal for Interim NITS,30 SPP \ndoes not restrict customers taking CHILLS from relying on co-located capacity or energy.31 \nMoreover, the SPP Transmission Owner Group supports CHILLS, explaining that “CHILLS has \nnumerous guardrails, including curtailability, that would ensure SPP’s continued ability to \nmaintain grid reliability.”32 The SPP Market Monitoring Unit also supports acceptance of SPP’s \nCHILLS proposal “as a just and reasonable way to effectuate SPP’s goals.”33 \nLevitt and Mohan also explain that ERCOT staff have developed a proposal by which a \nProvisional Controllable Load Resource (P-CLR) can withdraw power from the transmission \nnetwork on a non-firm basis and subject to curtailment as part of ERCOT’s ongoing “Batch \nZero” reforms to interconnect large loads.34 According to Levitt and Mohan, ERCOT’s existing \nControllable Load Resource (CLR) construct enables curtailment of loads on a nodal basis in \nsecurity-constrained economic dispatch (SCED) for resolving constraints.35 The P-CLR proposal \nbuilds on the CLR construct by allowing loads to accelerate interconnection if they choose to use \nthe transmission system on an as-available basis and curtail to resolve constraints as necessary.36 \nImportantly, Levitt and Mohan note that PJM’s Non-Firm CDS would include more reliability \n \n29 Id. at 6. \n30 Enchanted Rock March 25, 2026 Reply Brief and Protest at 6-7 (“PJM has clearly indicated to its stakeholders \nthat when it actually implements Interim NITS, it intends to ensure that ‘Co-located load taking Interim NITS \nservice will not have rights to the capacity/energy from any specific co-located generation,’ and that ([sic]‘[i]f \ncurtailed, [Eligible Customer] cannot take energy from co-located generator.’” (citations omitted)). \n31 Levitt & Mohan Aff. at 6. \n32 Southwest Power Pool Transmission Owner Group, Comments, Docket No. ER26-1323-000, at 2 (filed Mar. 3, \n2026). \n33 Southwest Power Pool Market Monitoring Unit, Comments, Docket No. ER26-1323-000, at 6 (filed Mar. 3, \n2026). \n34 Levitt & Mohan Aff. at 7-8 (citing ERCOT, Item 9.1: Batch Study Update, at 4 (April 20-21, 2026), \nhttps://www.ercot.com/files/docs/2026/04/13/9.1-Batch-Study-Update.pdf). The proposal is in final stages, and \nERCOT is targeting a June 1, 2026 Board vote to finalize the design. Id. at 7. \n35 Id. at 7. \n36 Id. (citing ERCOT, Item 9.1: Batch Study Update, at 4 (April 20-21, 2026), \nhttps://www.ercot.com/files/docs/2026/04/13/9.1-Batch-Study-Update.pdf)."},{"page":10,"startToken":3128,"endToken":3405,"text":"10 \nscreening than ERCOT’s proposed P-CLR program because PJM proposes to screen non-firm \nreservations in advance.37  \nSPP’s and ERCOT’s proposed non-firm transmission service offerings show that \ntransmission service can be provided on a non-firm and as-available basis. PJM’s own proposed \nimplementation of Interim NITS also demonstrates that non-firm transmission service need not \nbe limited to periods of outage for the co-located generator as PJM has proposed for Non-Firm \nCDS. While PJM’s Interim NITS proposal suffers from other flaws, PJM has proposed to make it \nbroadly available during normal operating conditions, and has not claimed that doing so will \ncompromise reliability.    \nSPP and ERCOT have also shown that non-firm transmission service can be implemented \nquickly. Unlike PJM’s requested 2029 effective date, SPP requested a July 1, 2026 effective date \nfor CHILLS,38 while ERCOT hopes to implement P-CLRs as soon as 2027.39 Neither PJM nor \nthe IMM has described any PJM-specific conditions that would prevent PJM from promptly \noffering non-firm transmission service available during normal conditions in a similar manner to \nSPP or ERCOT.  \n3. \nThe Commission must enforce the requirements of the Co-Location \nOrder. \nThe Co-Location Order proposed a commonsense solution to a critical and pressing \nproblem. The Commission must not allow unsubstantiated reliability concerns to dilute or delay \nthe Co-Location Order’s promise. Instead, the Commission must reject PJM’s attempt to limit \n \n37 Id. \n38 SPP, Filing, Docket No. ER26-1323-000, at 1-2 (filed Feb. 10, 2026). \n39 Levitt & Mohan Aff. at 8 (citing ERCOT, Large Load Interconnection Batch Study Workshop #7, at 25 (April 9, \n2026), https://protect.checkpoint.com/v2/r01/___https://www.ercot.com/files/docs/2026/04/09/ERCOT-Large-Load-\nBatch-Study-Workshop7-20260409_v03.pptx)."},{"page":11,"startToken":3405,"endToken":3528,"text":"11 \nthe availability of Non-Firm CDS and require PJM to establish a Non-Firm CDS product \navailable during normal system conditions as required in the Co-Location Order.  \n \n \n \nRespectfully submitted, \n/s/ Eric Stoutenburg  \nEric Stoutenburg \n \nChief Development Officer  \nEolian L.P. \n \n988 Howard Ave. Suite 200   \nBurlingame, CA 94010 \n \neric.stoutenburg@eolianenergy.com  \n/s/ Noah Long  \nNoah Long  \nDirector, State and Regulatory Affairs  \nAntora Energy, Inc.  \n200 West De Vargas St  \nSanta Fe, NM 87501  \nnoah.long@antora.com   \n \n/s/ Matt Barnes \nMatt Barnes \nChief Commercial Officer \nCalibrant Energy \n4830 W. Kennedy Blvd, Suite 600 \nTampa, Florida 33609 \nmatthew.barnes@calibrantenergy.com \n \n/s/ Brian Kauffman \nBrian Kauffman \nDirector, Wholesale Market Development \nMainspring Energy, Inc. \n3601 Haven Ave. \nMenlo Park, CA 94025 \nbrian.kauffman@mainspringenergy.com"},{"page":12,"startToken":3528,"endToken":3573,"text":"12 \n/s/ Noah Roberts \nNoah Roberts \nExecutive Director \nU.S. Energy Storage Coalition \n1299 Pennsylvania Ave NW \nWashington, D.C. 20004 \nnoah@energystorage.org \n \n/s/ Jeff Bladen \nJeff Bladen  \nHead of Energy  \nVerrus, LLC  \n918 N Rengstorff Ave.  \n \n  \nMountain View, CA 94043 \n \n \nbladen@verrusdata.com"},{"page":13,"startToken":3573,"endToken":3635,"text":"13 \nCERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary of the Commission in this \nproceeding. \n \nDated: April 24, 2026 \n/s/ Eric Stoutenburg  \nEric Stoutenburg \n \nChief Development Officer  \nEolian L.P. \n \n988 Howard Ave. Suite 200   \nBurlingame, CA 94010 \n \neric.stoutenburg@eolianenergy.com"},{"page":14,"startToken":3635,"endToken":3637,"text":"Attachment A"},{"page":15,"startToken":3637,"endToken":3692,"text":"Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan \nDocket No. EL25-49-000 et al. | Page 1 of 16 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nLarge Loads Co-Located at Generating \nFacilities \nDocket No. EL25-49-000 et al. \nSUPPLEMENTAL AFFIDAVIT OF \nANDREW LEVITT AND ANIRUDDH MOHAN \nON BEHALF OF \nEOLIAN, L.P. \nApril 24, 2026"},{"page":16,"startToken":3692,"endToken":3977,"text":"Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan \nDocket No. EL25-49-000 et al. | Page 2 of 16 \nI. \nQUALIFICATIONS \n1 \nOur names are Andrew Levitt and Aniruddh Mohan. We have previously submitted the Affidavit \n2 \ndated March 25, 2026, in this Docket EL25-49-000 et al. \n3 \nII. \nASSIGNMENT \n4 \nWe were asked by Eolian, L.P. to supplement our Affidavit dated March 25, 2026, to offer \n5 \nadditional perspectives on the reliability and timeline implications of the proposed new \n6 \ntransmission services in PJM’s Initial Brief in Docket No. EL25-49-000 et al. \n7 \nIII. \nBACKGROUND \n8 \nAs part of its compliance filing to FERC in Docket EL25-49-000, in February 2026, in an \n9 \naccompanying Initial Brief, PJM set out illustrative tariff language and supporting positions for \n10 \nthree new service categories for generators serving co-located load: Non-Firm Contract Demand \n11 \nTransmission Service (“Non-Firm CDS” or “NFCDS”), Interim Network Integration \n12 \nTransmission Service (“Interim NITS”), and Firm Contract Demand Service (“Firm CDS”).1 \n13 \nPJM also submitted supporting affidavits addressing planning, operations, market design, and \n14 \nimplementation timing.  \n15 \nSince then, a number of stakeholders have submitted responses to PJM’s Initial Brief. We submit \n16 \nthis Supplemental Affidavit in response to the timing and transmission reliability issues PJM and \n17 \nother stakeholders have raised before the Commission regarding the impact of non-firm services.  \n18 \nIV. \nSUMMARY \n19 \nSince PJM has taken steps in its Initial Brief and compliance filing to create new transmission \n20 \nservices for co-located loads, a minority of stakeholders have raised concerns that provision of \n21 \nthese new transmission services would be inconsistent with the safe and reliable operation of the \n22 \n \n1  \nPJM Interconnection, LLC, 193 FERC ¶ 61,217 (2025) (Co-Location Order)."},{"page":17,"startToken":3977,"endToken":4471,"text":"Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan \nDocket No. EL25-49-000 et al. | Page 3 of 16 \ntransmission system.2 In this Supplemental Affidavit, we find that the concerns raised do not \n1 \nprovide evidence that provision of NFCDS or Interim NITS would be inconsistent with reliable \n2 \nsystem operations. To the contrary, we point to similar non-firm services developed in other \n3 \nregional transmission organizations (“RTOs”) as evidence that such services can be offered and \n4 \nimplemented reliably. We also note that non-firm services being developed in other RTOs have \n5 \nmany of the enhancements we previously proposed to PJM in our prior Affidavit dated March \n6 \n25, 2026. We then note that these services in other RTOs are being implemented on a faster \n7 \ntimeline than that proposed by PJM. Moreover, PJM has long provided non-firm point-to-point \n8 \ntransmission service without causing the reliability concerns voiced by these stakeholders. \n9 \nWe also find that PJM’s Initial Brief and its Supporting Affidavits have made unclear and often \n10 \nconceptually inconsistent arguments regarding the reliability implications of Interim NITS and \n11 \nNFCDS that have led to comments citing potential risks from provision of non-firm service.3 \n12 \nPJM suggests that its requirement to use protection systems to limit withdrawals at facilities \n13 \ntaking CDS implies complexity that warrants narrow limitations on scheduling of NFCDS. The \n14 \nPJM Independent Market Monitor has asserted that, due to complexity, extensive deployment of \n15 \nNFCDS could become “unmanageable.”4 However, we show that PJM’s argumentation is \n16 \nflawed, that NFCDS scheduling therefore could be allowed at any time without increasing \n17 \ncomplexity from protection systems (and potentially reducing it), and that the use of the required \n18 \nprotection systems does not imply any reliability issues due to widescale adoption of CDS.  \n19 \nIn particular, PJM’s Initial Brief does not sufficiently distinguish between types of protection \n20 \nsystems. For facilities taking CDS, the protection system required by PJM monitors and controls \n21 \nconditions internal to those facilities in order to limit withdrawals at all times. By contrast, a \n22 \nstandard Remedial Action Scheme (RAS) monitors and controls disparate parts of the bulk \n23 \ntransmission system to avoid overloads there. Even though standard RAS is not required for a \n24 \n \n2  \nPJM Independent Market Monitor (“IMM”) Reply Brief at p.2 claims the December 18th Order represents a set \nof dramatic changes in the nature of transmission service in PJM, not all of which are workable consistent with \nmaintaining the reliable operation of the PJM system.” \n3  \nPJM IMM Reply Brief at p.6 claims “Interim NITS is not a preferred path forward because it is not consistent \nwith PJM’s normal transmission planning process and imposes potentially significant risks on the PJM \nsystem.” As evidence, it cites PJM’s Initial Brief at p. 60, stating that “the complexity introduced by the \nnecessary control technology and protection systems (e.g. RAS) introduces significant risks.”  \n4  \nPJM IMM, Reply Brief at p.6."},{"page":18,"startToken":4471,"endToken":4832,"text":"Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan \nDocket No. EL25-49-000 et al. | Page 4 of 16 \nfacility taking non-firm transmission, PJM repeatedly cites limitations on the feasible scale of \n1 \nRAS installations as a rationale to limit the scope of NFCDS and to justify the interim nature of \n2 \nInterim NITS.5 We address these conceptual issues as they relate to reliability risk to provide \n3 \nclarity to the Commission in the implementation of its order in Dockets EL25-49-000 et al. \n4 \nV. \nASSESSMENT OF RELIABILITY IMPLICATIONS AND \n5 \nIMPLEMENTATION TIMELINE OF PJM’S PROPOSED NEW \n6 \nTRANSMISSION SERVICES  \n7 \nPJM’s Independent Market Monitor (“IMM”) claims that the “Commission’s defined \n8 \ntransmission services cannot work given the potentially very large load additions that could \n9 \nrequest service, given the critical importance of maintaining a reliable transmission grid….”6 \n10 \nThey also claim that the Commission’s “December 18th Order represents a set of dramatic \n11 \nchanges in the nature of transmission service in PJM, not all of which are workable consistent \n12 \nwith maintaining the reliable operation of the PJM system. In particular, non-firm CDS and \n13 \nInterim NITS create significant reliability risks for the transmission system.”7  \n14 \nWe assess these claims and find no evidence that new transmission services ordered by the \n15 \nCommission and proposed by PJM, especially non-firm transmission services, are unworkable \n16 \nand create significant reliability concerns. We also find further evidence to support the assertion \n17 \nin our prior affidavit that NFCDS scheduling eligibility can be extended to all hours.  \n18 \n \n5  \nFor example, PJM’s Initial Brief, pp. 10–11 says that NFCDS should be a standby product only used “under \nlimited circumstances.” As evidence for this it cites the complexity associated with provisions of NFCDS due to \npermanent protection systems such as a RAS on the PJM transmission system. PJM’s Initial Brief, pp. 34–35 \nsays: “The control technologies and protection systems necessary to provide Non-Firm Contract Demand \nTransmission Service (and Interim NITS) is emblematic of the complexity associated with Non-Firm Contract \nDemand Transmission Service from an operations and planning perspective.” \n6  \nPJM IMM Reply Brief, p.2. \n7  \nPJM IMM Reply Brief, p.2."},{"page":19,"startToken":4832,"endToken":5289,"text":"Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan \nDocket No. EL25-49-000 et al. | Page 5 of 16 \nV.A. \nSPP CHILLS shows non-firm service is workable and does not \n1 \ncreate significant reliability concerns  \n2 \nSouthwest Power Pool (“SPP”) recently filed with FERC, in Docket No. ER26-1323-000, tariff \n3 \nrevisions to offer a new non-firm transmission service called Conditional High Impact Large \n4 \nLoad Service (“CHILLS”).8 Similar to PJM’s proposed NFCDS and Interim NITS, load that is \n5 \nserved under CHILLS does not have firm access to the transmission system, and SPP has no \n6 \nobligation to serve the load if insufficient transmission capacity exists. In SPP’s filing to FERC, \n7 \nPart VII § 44.4 states that: “The Transmission Provider and Transmission Owners undertake no \n8 \nobligation under the Tariff to plan the Transmission System in order to have sufficient capacity \n9 \nfor CHILLS”;9 CHILLS “is subject to availability and to Curtailment or Interruption”; “[t]he \n10 \nTransmission Customer or the Network Customer must not withdraw energy from the \n11 \nTransmission System at the CHILL delivery point that exceeds its CHILLS Reserved Capacity”; \n12 \nand “The Transmission Customer or the Network Customer must fully respond to a load shed or \n13 \ncurtailment for the CHILL delivery point directive by the Transmission Provider.”10 In both grid \n14 \nplanning and operations this is broadly similar to PJM’s proposed design of NFCDS and Interim \n15 \nNITS: for example PJM states in its illustrative tariff that both NFCDS and Interim NITS are \n16 \n“non-firm” and “interruptible.”11 In a supporting affidavit, Dr. Abdulsalam notes that the \n17 \ntransmission system is not planned for NFCDS: “this load is neither planned for (i.e., PJM’s \n18 \ntransmission planning does not consider this load and so the system is not designed to \n19 \naccommodate it)” showing consistency with SPP’s CHILLS.12 \n20 \n \n8  \nSPP, Submission of Tariff Revisions to Add Conditional High Impact Large Load Service, Docket No. ER26-\n1323-000, Part VII § 44.4 (filed Feb. 10, 2026). (“SPP CHILLS Filing”). \n9  \nNote that, to be eligible for CHILLS, the customer must request a firm transmission service, and a CHILLS \ncustomer must transition to firm transmission service within seven years. \n10  SPP CHILLS Filing, Part VII § 44.4. \n11  PJM Attachment A, Illustrative Language for New Tariff, Part XI § 709.2(b). PJM says “Non-Firm Contract \nDemand Transmission Service is a transmission service that allows an Eligible Customer taking service on \nbehalf of Co-Located Loads to obtain non-firm, interruptible transmission service...” On Interim NITS, Part XI, \n§ 701.1 says Interim NITS lets an Eligible Customer “receive transmission service on behalf of a Co-Located \nLoad on a non-firm, interruptible basis.” \n12  PJM Initial Brief, Attachment B (Affidavit of Dr. Sami Abdulsalam), ¶ 12."},{"page":20,"startToken":5289,"endToken":5718,"text":"Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan \nDocket No. EL25-49-000 et al. | Page 6 of 16 \nThe SPP market monitor has assessed CHILLS as just and reasonable.13 The Transmission \n1 \nOwners Group has asserted that “CHILLS has numerous guardrails, including curtailability, that \n2 \nwould ensure SPP’s continued ability to maintain grid reliability.”14 The imminent implementation \n3 \nof CHILLS in SPP directly contradicts the PJM IMM’s claim that implementation of non-firm \n4 \nservice would be unworkable and create significant reliability risks. The PJM IMM does not \n5 \npoint to specific planning or operational reasons why PJM offering NFCDS and Interim NITS, as \n6 \ndirected by the Commission’s Co-Location Order, would create reliability concerns, even though \n7 \nSPP can reliably implement such a service.15  \n8 \nWe also note that SPP does not limit the reservation of CHILLS to periods in which an \n9 \nassociated generation resource is on outage, unlike PJM’s proposed implementation of NFCDS. \n10 \nRather, SPP plans to make CHILLS broadly available during all hours. In addition, in contrast to \n11 \nPJM’s description of its Interim NITS offering to stakeholders,16 SPP does not restrict customers \n12 \ntaking CHILLS from relying on co-located capacity or energy during periods of system tightness \n13 \nand supply adequacy shortfalls.17 All of this suggests that PJM’s Interim NITS and NFCDS \n14 \nservice is not only workable and able to be reliably implemented, but can in fact be further \n15 \nenhanced for broader uptake and commercial viability. We detail these enhancements in our \n16 \nprevious Affidavit in this docket, dated March 25, 2026.18 \n17 \n \n13  Southwest Power Pool Market Monitoring Unit, Comments of the Southwest Power Pool Market Monitoring \nUnit, Docket No. ER26-1323-000, at p.1 (filed Mar. 3, 2026). \n14  Southwest Power Pool Transmission Owner Group (“SPP TO Group”), Comments of the Southwest Power \nPool Transmission Owner Group, Docket No. ER26-1323-000, at p.2 (filed Mar. 3, 2026)  \n15  PJM IMM, Reply Brief \n16  See, e.g. Reply Brief and Protest of Enchanted Rock, at p. 2 (March 25, 2026) (“[A]s described by PJM to \nstakeholders—but not set forth in its Initial Brief, Illustrative Tariff or the February 23 Compliance Filing—\nPJM intends to prohibit Co-Located Load from receiving any capacity or energy from a Co-Located \nGenerating Facility while the Co-Located Load is taking Interim NITS”.) \n17  SPP CHILLS Filing, p.26 (“In general, the co-located generation may be used by the customer to displace its \nCHILL amount, including compliance with any Curtailment directives.”).  \n18  Affidavit of Andrew Levitt & Aniruddh Mohan (filed March 25, 2026)."},{"page":21,"startToken":5718,"endToken":6078,"text":"Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan \nDocket No. EL25-49-000 et al. | Page 7 of 16 \nV.B. \nERCOT’s Provisional Controllable Load Resource proposal shows \n1 \nnon-firm service is workable, does not create significant reliability \n2 \nconcerns, and can be implemented quickly \n3 \nSimilar to SPP, developments at the Electric Reliability Council of Texas (“ERCOT”) evince the \n4 \nworkability of non-firm transmission services. As part of their ongoing “Batch Zero” reforms to \n5 \ninterconnect large loads, ERCOT staff have developed a proposal by which a Provisional \n6 \nControllable Load Resource (“P-CLR”) can withdraw power from the transmission network on a \n7 \nnon-firm basis by being subject to curtailment.19 The proposal is in final stages, and ERCOT is \n8 \ntargeting a June 1, 2026, Board vote to finalize the design.  \n9 \nERCOT’s existing CLR construct enables curtailment of loads on a nodal basis via security \n10 \nconstrained economic dispatch (“SCED”) for resolving constraints. The P-CLR proposal builds \n11 \non this construct with new offer rules, and by using CLR curtailment capability as a tool to \n12 \naccelerate connection to the transmission grid for new large loads. That is, a load signing up as \n13 \nP-CLR can use the transmission system on an as-available basis and curtail to resolve constraints \n14 \nas necessary.20 \n15 \nV.B.1. ERCOT’s proposed P-CLR shows non-firm service is \n16 \nworkable and does not create significant reliability \n17 \nconcerns, even without the additional reliability \n18 \nscreening of NFCDS  \n19 \nAs with SPP’s CHILLS and PJM’s proposed non-firm services, ERCOT under its proposed \n20 \nconstruct has no obligation to serve a P-CLR load, which is obligated to comply with dispatch \n21 \ninstructions and is prohibited from withdrawing more than its authorized amount, with the non-\n22 \nfirm amount managed through SCED.21  \n23 \nOperationally, curtailing P-CLR load in ERCOT’s SCED is similar to what PJM has envisaged \n24 \nfor NFCDS and Interim NITS, except that PJM’s NFCDS would have an added step of screening \n25 \n \n19  ERCOT, Batch Study Update, Board of Directors Meeting (April 20–21, 2026) at p.4.  \n20  ERCOT, Batch Study Update, p.4. \n21  ERCOT, Batch Study Update, p.4."},{"page":22,"startToken":6078,"endToken":6502,"text":"Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan \nDocket No. EL25-49-000 et al. | Page 8 of 16 \nnon-firm reservations ahead of time (unlike both ERCOT’s CLRs and PJM’s Interim NITS). As \n1 \nPJM notes, NFCDS reservation requests would be evaluated and “requests for non-firm service \n2 \nshall only be granted when PJM has determined there is available transmission capacity.”22 \n3 \nCompared with ERCOT’s P-CLR construct, the need to reserve PJM’s NFCDS on a forward \n4 \nbasis provides yet another opportunity to ensure that NFCDS can be provided reliably. Similar to \n5 \nSPP’s CHILLS detailed above, ERCOT’s P-CLR product once again runs contrary to the claim \n6 \nfrom PJM’s IMM that non-firm service is unworkable and inconsistent with reliable operations. \n7 \nWe also note again that unlike PJM’s proposed NFCDS product which restricts NFCDS \n8 \nreservations to hours where the co-located resource is on outage, ERCOT’s P-CLR allows loads \n9 \nto take service during all hours, subject to SCED curtailment.23 \n10 \nV.B.2. SCED curtailment of ERCOT P-CLRs will be \n11 \ndeveloped by 2027 showing that faster \n12 \nimplementation than PJM’s 2029 proposal is feasible \n13 \nPJM has proposed implementation of its new transmission services by 2029. The affidavit of \n14 \nPJM’s Timothy Horger says that changes to SCED for dispatching load in market operations will \n15 \nrequire significant updates that necessitate delaying implementation until 2029.24 However, it is \n16 \nunclear why this must be delayed until 2029 given that ERCOT has committed to \n17 \nimplementation of P-CLRs in its Batch Zero process, proposed for implementation as soon as \n18 \n2027.25 While building out such tools warrants careful design and rigorous testing, PJM has \n19 \nprovided no reasons why PJM’s system uniquely requires a longer implementation process \n20 \ncompared to other RTOs. Further, as pointed out in our previous affidavit, PJM is well placed to \n21 \nimplement changes to SCED given the existing capability of its nodal Price Responsive Demand \n22 \n(“PRD”) implementation in SCED. The PRD construct, similar to CLR, allows nodal, real-time \n23 \ncurtailment of loads via SCED. PJM can directly use or build on its PRD tools in SCED to \n24 \nexecute needed reliability-related curtailments of non-firm transmission services in order to \n25 \nmaintain transmission security in real-time in response to changing system conditions. \n26 \n \n22  PJM Initial Brief, pp. 32–33. \n23  ERCOT, Batch Study Update, p.4 \n24  PJM Initial Brief, Attachment D (Affidavit of Timothy Horger), pp. 4–5. \n25  ERCOT, Large Load Interconnection Batch Study Workshop #7 (April 9, 2026) at p.25."},{"page":23,"startToken":6502,"endToken":6861,"text":"Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan \nDocket No. EL25-49-000 et al. | Page 9 of 16 \nV.C. \nNon-firm transmission service is workable at scale even when \n1 \nenhanced with simple protection systems  \n2 \nCiting complexity associated with over-reliance on RAS, the IMM suggests that NFCDS cannot \n3 \nscale, while PJM proposes that NFCDS may only be scheduled during a very limited number of \n4 \nhours. Below, we describe what a RAS is and why offering NFCDS during all normal operating \n5 \nconditions would not cause an over-reliance on RAS. In summary, our position rests on the \n6 \nfollowing points:  \n7 \n1. There is an important distinction between standard RAS and the simple withdrawal-limiting \n8 \nprotection systems PJM proposes to require. Unlike standard RASs, which monitor and \n9 \ncontrol components across the broader transmission grid, withdrawal-limiting protection \n10 \nsystems monitor and control only facility-internal components. Because these systems are far \n11 \nnarrower in scope and operationally simpler, they can be relied upon more extensively \n12 \nwithout creating the same system complexities and interdependencies associated with \n13 \nstandard RAS.  \n14 \n2. That simplicity is reinforced by the PJM Transmission Owners’(“TOs'”) proposal to \n15 \nimplement protection systems in a redundant manner that guards against the possibility of \n16 \nprotection system failure.26  \n17 \n3. Allowing NFCDS to be scheduled more frequently rather than limiting it to periods of \n18 \ngenerator outage reduces reliance on withdrawal-limiting protection systems, because when \n19 \nNFCDS is scheduled, that protection system is disabled to allow those scheduled withdrawals \n20 \nthat are not curtailed by SCED. PJM’s proposal to reduce the extent to which NFCDS can be \n21 \nused will therefore tend to increase the extent to which withdrawal-limiting protection \n22 \nsystems are relied upon. \n23 \n4. Standard RASs can provide important system benefits but also have recognized limits. Even \n24 \nso, a customer need not install a standard RAS in order to take non-firm transmission service, \n25 \neven if PJM requires a withdrawal-limiting protection system for that customer’s facility. \n26 \n \n26  The PJM TOs recommend, and we agree, that “All SPS and RAS should be fully redundant.” PJM TOs Initial \nBrief at p.23."},{"page":24,"startToken":6861,"endToken":7247,"text":"Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan \nDocket No. EL25-49-000 et al. | Page 10 of 16 \nV.C.1. IMM and PJM are concerned with the complexity of \n1 \nnon-firm service due to protection systems and RASs \n2 \nThe IMM in its comments asserts that “[g]iven the scale of potential data center users of non-firm \n3 \nCDS, the system would become unmanageable if all or a significant part of the data center users \n4 \nwanted to use non-firm CDS…,”27 and, commenting on its reliability concerns with non-firm \n5 \nservices generally, cites to PJM’s statement that “the complexity introduced by the necessary \n6 \ncontrol technology and protection systems (e.g., RAS) introduces significant risks.”28 We expand and \n7 \ncomment on the nature of that complexity to help clarify where scale may or may not introduce \n8 \nissues.  \n9 \nIn the following statements, PJM explains the complexity associated with protection systems, and \n10 \nthat it warrants limiting scheduling eligibility for NFCDS to a very narrow window: \n11 \n…PJM will offer and manage pre-scheduled Non-Firm Contract Demand \n12 \nTransmission Service “‘operationally’ and ensure that permanent monitoring and \n13 \naggressive, fast-acting protections are in place if conditions arise that may \n14 \ncompromise reliable system operations.” This approach, as Dr. Abdulsalam explains, \n15 \n“allows for more reliable system operation, reduces the number of permanent \n16 \nprotection systems on the system,” such as a RAS, on the PJM Transmission System, \n17 \nand thus “reduc[es] the likelihood of unintended protection system misoperation that \n18 \ncould lead to cascading events.” \n19 \nIn addition, as explained further below, and by Dr. Abdulsalam, from an operations \n20 \nand planning perspective, the complexities associated with the provision of Non-Firm \n21 \nContract Demand Transmission Service call for relying on such service as a standby \n22 \nproduct only “under limited circumstances.”29 [emphasis added] \n23 \nIn the relevant section “further below,” PJM goes on to state that: \n24 \nThe control technologies and protection systems necessary to provide Non-\n25 \nFirm Contract Demand Transmission Service (and Interim NITS) is \n26 \nemblematic of the complexity associated with Non-Firm Contract Demand \n27 \nTransmission Service from an operations and planning perspective.30 \n28 \n \n27  PJM IMM Reply Brief, p.6. \n28  PJM Initial Brief, p.60. \n29  PJM Initial Brief, p.10 \n30  PJM Initial Brief, pp. 34-35."},{"page":25,"startToken":7247,"endToken":7771,"text":"Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan \nDocket No. EL25-49-000 et al. | Page 11 of 16 \nThe IMM reasons that NFCDS cannot be installed at scale and cites these complexity concerns \n1 \nraised by PJM. According to PJM, those concerns arise because complex control technologies \n2 \nand protection systems are necessary for providing NFCDS, the protection systems may \n3 \nmisoperate and lead to cascading events, and therefore NFCDS can only be relied on as a \n4 \nstandby product (i.e., when a co-located generator at a CDS facility is on outage). In the \n5 \nfollowing sections, we show that this reasoning is flawed.  \n6 \nV.C.2. Simple withdrawal-limiting protection systems are \n7 \ndistinct from standard RAS \n8 \nPJM describes a protection system at a co-located facility that disconnects a co-located load \n9 \nwhen there is a sudden failure of one of its co-located generation units, and states that all co-\n10 \nlocated facilities will have such a protection system.31 PJM describes this type of protection \n11 \nsystem as “overwhelmingly beneficial.”32 PJM states that the protection system will be “set to \n12 \nensure such load does not withdraw energy in excess of the megawatt level permitted under its \n13 \neffective service agreement.”33 In order to prevent withdrawals from exceeding the permissible \n14 \nlevel, such a protection system: monitors flows into the co-located facility; monitors the status of \n15 \ncomponents internal to the facility; and takes action to either adjust consumption or generation of \n16 \ncomponents in the facility, or to disconnect the facility from the grid. Therefore, all of the \n17 \nmonitoring and control of this type of protection system is internal to the co-located facility. We \n18 \ncall this a “withdrawal-limiting protection system.”34  \n19 \n \n31   PJM Initial Brief, Attachment C (Affidavit of Matthew Wharton), ¶ 25, and Abdulsalam Affidavit, ¶ 9. \nFollowing Dr. Abdulsalam’s naming convention, we refer to this device broadly as a protection system, noting \nthat Mr. Wharton has classified it as a RAS. We further note that, in the ERCOT Batch Zero process, a device \nwith the equivalent functionality that is required for a Self-Limited Facility is not referred to as a RAS but \nrather as a “reverse power relay or equivalent protection.” See ERCOT, Large Load Batch Study Update, \npresented to PUCT Open Meeting, April 2, 2026, p.7. \n32  PJM Initial Brief, Attachment C (Affidavit of Matthew Wharton), ¶ 25. \n33  PJM Initial Brief, Attachment B (Affidavit of Dr. Sami Abdulsalam), ¶ 9. \n34  It does not appear to be necessary to have a withdrawal-limiting protection system in order to enable non-firm \ntransmission service, and indeed such systems are not required for conventional point-to-point non-firm service, \nnor are they proposed for use in SPP CHILLS nor ERCOT P-CLR (both of which are suitable for load-only \nsites that would not make sense with a withdrawal limiter). However, we concur with PJM that a withdrawal-\nlimiting protection system is beneficial and therefore expect efficiencies in PJM’s proposal to install them \nwidely, noting that some customers may prefer not to use them and instead curtail as necessary to ensure \nreliable operations in case of a contingency internal to their facility."},{"page":26,"startToken":7771,"endToken":8250,"text":"Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan \nDocket No. EL25-49-000 et al. | Page 12 of 16 \nUnlike a withdrawal-limiting protection system (which monitors and controls only facility-\n1 \ninternal components), a standard RAS monitors and controls components across the grid. When \n2 \nit detects a triggering condition on one element on the transmission system, it takes action to \n3 \ncontrol or disconnect a distinct, often remote element on the transmission system.35  \n4 \nBoth a withdrawal-limiting protection system and a standard RAS are beneficial because they \n5 \nallow a non-firm large load to withdraw power from a constrained transmission network with \n6 \nless (or no) curtailment relative to the constraint, as follows. With the higher consumption, a \n7 \ncontingency would ordinarily overload the constrained element. However, the protection system \n8 \nmonitors for the contingency and, if it occurs, reacts immediately (e.g., by curtailing load) to \n9 \nprotect the constrained element.36 This allows curtailment after a contingency happens, rather \n10 \nthan proactively curtailing before the contingency (which is the ordinary practice in absence of a \n11 \nwithdrawal-limiting protection system or RAS). \n12 \nHowever, a standard RAS is not necessary to accommodate a non-firm load, precisely because \n13 \nthe alternative (pre-contingency curtailment) is always an option due to the non-firm nature of \n14 \nthe load. As we have pointed out, the extent of standard RAS installation must be carefully \n15 \nconsidered, and a standard RAS is not suitable in all applications due to complexity. As Dr. \n16 \nAbdulsalam notes, with increasing adoption, RAS may interact under abnormal operating \n17 \nconditions, leading to unintended consequences and potential cascading failures.37 This \n18 \ninteraction is indeed a hallmark of standard RAS, since the facilities they monitor and control are \n19 \n“apparently unrelated” and can span across a wide area that overlaps with other standard RASs.38  \n20 \n \n35  PJM Initial Brief, Attachment C (Affidavit of Matthew Wharton), ¶ 15. \n36  A withdrawal-limiting protection system directly or indirectly monitors loss of a generation unit internal to the \nco-located facility, while a standard RAS would monitor one or more transmission elements or generation units \nelsewhere on the bulk electric system.  \n37  PJM Initial Brief, Attachment B (Affidavit of Dr. Sami Abdulsalam), ¶ 10. \n38  PJM Initial Brief, Attachment C (Affidavit of Matthew Wharton), ¶ 15; CAISO, Planning Guide, p. 11 (“With \nthe increased transmission system utilization that comes with application of RAS, there can be increased \nexposure to not meeting system performance criteria if the RAS fails or inadvertently operates…If there are a \nlarge number of RAS, it may become difficult to assess the interdependency of these various schemes on system \nreliability. In addition, as RAS has become progressively increasing in complexity, it is necessary to consider \nthe level of logic complexity through combining multiple features that were acceptable individually but that \ncould compound to a level that cannot be integrated into market operation.”)"},{"page":27,"startToken":8250,"endToken":8668,"text":"Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan \nDocket No. EL25-49-000 et al. | Page 13 of 16 \nHowever, PJM has not explained how a simple withdrawal-limiting protection system, which is \n1 \nrestricted to monitoring and controlling elements internal to a single facility, would exhibit the \n2 \ninterdependencies and complexities that characterize typical RAS. Because of its simplicity and \n3 \nlocalized scope, it would appear on first principles that extensive installation of withdrawal-\n4 \nlimiting protection systems would not introduce the complexity that is associated with standard \n5 \nRASs.  \n6 \nFurther, PJM has asserted that a protection system must be temporary because it will need to \n7 \nadapt to changing system conditions.39 However, if the nature of the protection system is simply \n8 \nto limit withdrawals consistent with transmission service limits, it is unclear why such a simple \n9 \nsystem would need to evolve with system conditions.  \n10 \nFinally, the robustness associated with the simplicity of withdrawal-limiting protection systems \n11 \nis reinforced by the PJM TOs’ proposal to implement protection systems in a redundant manner \n12 \nthat guards against the possibility of protection system failure.40  \n13 \nV.C.3. Narrow eligibility for scheduling NFCDS does not \n14 \nreduce any complexity from withdrawal-limiting \n15 \nprotection systems \n16 \nAccording to PJM, any facility taking Contract Demand Service must have a withdrawal-limiting \n17 \nprotection system.41 When there is zero or partial NFCDS scheduled, this protection system \n18 \nserves to ensure there are no withdrawals above the authorized Firm CDS level. When NFCDS \n19 \nmay be reliably scheduled, the protection system obviously must be adjusted or disabled in order \n20 \nto allow the corresponding higher withdrawals. That is: under PJM’s proposal, all co-located \n21 \nfacilities will have a withdrawal-limiting protection system active at all times they are taking \n22 \n \n39  PJM Initial Brief, Attachment B (Affidavit of Dr. Sami Abdulsalam), ¶ 10 (“The temporary nature of such a \nprotection system for this type of firm service is necessary to ensure the integrity and reliable operation of the \ntransmission system as a whole since protection systems are designed based on system conditions anticipated at \nthat time and will continue to change as system conditions evolve.”) \n40  PJM TOs Initial Brief at p.23. \n41  PJM Initial Brief at p.34 (“PJM is requiring Eligible Customers taking Non-Firm Contract Demand \nTransmission Service to work with PJM and affected Transmission Owners to ‘establish necessary control \ntechnologies and protection systems, . . . which may include a [RAS], for each Service Agreement for Non-Firm \nContract Demand Transmission Service.”)"},{"page":28,"startToken":8668,"endToken":9067,"text":"Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan \nDocket No. EL25-49-000 et al. | Page 14 of 16 \nFirm + Non-Firm CDS for less than their load level. It therefore follows that narrowing \n1 \neligibility for NFCDS scheduling does not decrease complexity associated with such protection \n2 \nsystems. And, to the extent that the withdrawal-limiting protection system is disabled due to the \n3 \nscheduling of Firm + Non-Firm CDS to cover the full load, any corresponding complexity is \n4 \nremoved. Thus, PJM has not effectively demonstrated that its proposal to limit NFCDS \n5 \nscheduling eligibility to generator outage periods is reasonable for maintaining reliability, since \n6 \nNFCDS scheduling does not exacerbate complexity due to protection systems, and in many cases \n7 \nmitigates it. \n8 \nV.C.4. NFCDS can be scaled reliably, notwithstanding limits \n9 \nto installation of standard RAS \n10 \nIn addition to a withdrawal-limiting protection system, a standard RAS that monitors \n11 \ntransmission system elements and controls the co-located facility in response can be beneficial \n12 \nfor further accelerating load interconnections ahead of or instead of transmission upgrades. A \n13 \nstandard RAS allows non-firm large loads to be curtailed instantaneously after a grid \n14 \ncontingency (such as loss of a nearby transmission line) to prevent overload of a constrained \n15 \nelement, rather than pre-curtailing it before the contingency (which would be the typical \n16 \noperating practice in absence of a RAS). The result is that, with a standard RAS, such a load \n17 \nwould face curtailment due to that constraint with far lower frequency—possibly never—\n18 \ncompared to the alternative of pre-contingency curtailment. Standard RAS can and should \n19 \ntherefore be installed at as many facilities as practical within the limits that PJM has identified. \n20 \nThat said, notwithstanding its benefits, the complexity of standard RAS means there will likely \n21 \nbe a limit on the number of load facilities at which it can be installed, even if that limit is beyond \n22 \nthe current usage of standard RAS in PJM. \n23 \nThe IMM has asserted that, due to complexity, extensive deployment of NFCDS could become \n24 \n“unmanageable.”42 However, it would be incorrect to conclude that scale constraints due to \n25 \ncomplexity of standard RAS mean widescale installation of NFCDS is “unmanageable.” This is \n26 \nbecause standard RAS is not required for NFCDS, even if PJM requires a withdrawal-limiting \n27 \n \n42  PJM IMM Reply Brief at p.6."},{"page":29,"startToken":9067,"endToken":9377,"text":"Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan \nDocket No. EL25-49-000 et al. | Page 15 of 16 \nprotection system at each site. Instead of standard RAS, NFCDS can be curtailed pre-\n1 \ncontingency. PJM can and should only install standard RAS for NFCDS facilities to the extent it \n2 \nis manageable. Beyond that threshold, PJM can instead rely on pre-contingency curtailment of \n3 \nNFCDS without installing standard RAS, similar to how ERCOT and SPP envisage curtailment \n4 \nof non-firm load under the proposed P-CLR and CHILLS constructs. In this way, PJM avoids \n5 \nsuffering a reliability degradation from too much standard RAS while granting NFCDS service \n6 \nat scale. The non-firm nature of NFCDS provides this operational flexibility—precisely because \n7 \npre-contingency curtailment is always an option for non-firm load. \n8 \nV.D. \nNFCDS is consistent with a reliable and efficient PJM transmission \n9 \nsystem \n10 \nThe IMM asserts that “there can be no such service as non-firm CDS that is fully consistent with \n11 \nmaintaining a reliable PJM transmission system.”43 As we point out in our prior affidavit, the CDS \n12 \nconstruct (including NFCDS scheduled whenever it is available and desired) provides the unique \n13 \nbenefit of a reliable system that can permanently avoid the need for high-cost and unnecessary \n14 \ntransmission upgrades and allow for efficient exchanges with the grid when the transmission network \n15 \nis available to support them. By taking advantage of flexibility in grid withdrawals inherent in a site \n16 \nand PJM’s direct control of how much a facility withdraws via SCED, depending on system \n17 \nconditions, a large load customer can be connected reliably more quickly and at lower cost. As we \n18 \npoint out above, neither IMM nor PJM have shown any cause for reliability concern associated with \n19 \nthe CDS construct.  \n20 \n \n \n21 \n \n43  PJM IMM Reply Brief at p.6."},{"page":30,"startToken":9377,"endToken":9486,"text":"Supplemental Affidavit of Andrew Levitt and Aniruddh Mohan \nDocket No. EL25-49-000 et al. | Page 16 of 16 \nAffidavit of Andrew Levitt  \n \nI, Andrew Levitt, do hereby swear that I have co-authored this Supplemental \nAffidavit of Andrew Levitt and Aniruddh Mohan and the statements contained therein are true \nand accurate to the best of my knowledge and belief.  \nAndrew Levitt  \n \n \nDate: April 24, 2026 \nAffidavit of Aniruddh Mohan \n \nI, Aniruddh Mohan, do hereby swear that I have co-authored this Supplemental \nAffidavit of Andrew Levitt and Aniruddh Mohan and the statements contained therein are true \nand accurate to the best of my knowledge and belief.  \nAniruddh Mohan \n \n \nDate: April 24, 2026"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":934,"startToken":0,"endToken":390},{"p":2,"at":934,"title":"I. ARGUMENT","method":"printed heading","endPage":3,"endAt":686,"startToken":390,"endToken":623},{"p":3,"at":686,"title":"B. The Commission must adopt a Grid Reliance Charge that is cost justified.","method":"printed heading","endPage":4,"endAt":771,"startToken":623,"endToken":1067},{"p":4,"at":771,"title":"C. The Commission should not allow unsubstantiated reliability concerns to","method":"printed heading","endPage":13,"endAt":4,"startToken":1067,"endToken":3574},{"p":13,"at":4,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":14,"endAt":0,"startToken":3574,"endToken":3635},{"p":14,"at":0,"title":"Attachment A","method":"printed heading","endPage":16,"endAt":106,"startToken":3635,"endToken":3709},{"p":16,"at":106,"title":"I. QUALIFICATIONS","method":"printed heading","endPage":16,"endAt":284,"startToken":3709,"endToken":3738},{"p":16,"at":284,"title":"II. ASSIGNMENT","method":"printed heading","endPage":16,"endAt":572,"startToken":3738,"endToken":3785},{"p":16,"at":572,"title":"III. BACKGROUND","method":"printed heading","endPage":16,"endAt":1495,"startToken":3785,"endToken":3915},{"p":16,"at":1495,"title":"IV. SUMMARY","method":"printed heading","endPage":18,"endAt":504,"startToken":3915,"endToken":4554},{"p":18,"at":504,"title":"V. ASSESSMENT OF RELIABILITY IMPLICATIONS AND","method":"printed heading","endPage":30,"endAt":702,"startToken":4554,"endToken":9486}]}