{"document":{"slug":"rec-20260424-5298","title":"Reply Brief of PJM Industrial Customer Coalition, et al","issued":"2026-04-24","accession":"20260424-5298","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"PJM Industrial Customer CoalitionIndustrial Energy Consumers of AmericaAmerican Forest and Paper Association, Inc. ,National Railroad Passenger Corporation (\"Amtrak\") ,","kind":"brief","file":"sources/filings/text/20260424-5298_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260424-5298","tier":"record","sha256":"fcec260e010d0651d5326172f94b22a3ae94ff44fc91d0a40b24221a2cf8d021","pages":23,"tokens":7606,"emptyPages":[],"textThemes":["retail","flex","colo","study"]},"pages":[{"page":1,"startToken":0,"endToken":238,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM Interconnection, L.L.C., et al.  \n \n \nLarge Loads Co-Located at Generating \nFacilities \n \nConstellation Energy, LLC \n        v.  \nPJM Interconnection, L.L.C.\n \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n \n \nDocket Nos. EL25-49-000 \n                     EL25-49-001 \n \n                     AD24-11-000 \n \n \n                     EL25-20-000 \n                     (Consolidated) \n  \n \nREPLY BRIEF OF \nINDUSTRIAL CUSTOMER ORGANIZATIONS AND AMTRAK \n \nPursuant to the Order on Show Cause Proceeding, Directing Compliance Filings, \nEstablishing Paper Hearing, and Granting In Part and Denying In Part Complaint (“Co-Located \nLoad Order”) in the above-captioned dockets,1 and the January 23, 2026, Notice of Extension of \nTime,2 the PJM Industrial Customer Coalition (“PJMICC”), the Industrial Energy Consumers of \nAmerica (“IECA”), the American Forest and Paper Association (“AF&PA”) (collectively, \n“Industrials”), and the National Railroad Passenger Corporation (“Amtrak”) hereby file this Reply \nBrief in response to the responsive briefs filed at the Federal Energy Regulatory Commission \n(“FERC” or “Commission”) on or around March 25, 2026, in the above-captioned dockets.  \nI. \nEXECUTIVE SUMMARY \nThe Industrials/Amtrak are part of a subset of retail customers (i.e., traditional large users) \nwith high energy consumption needs who have long contributed to the development and resiliency \n \n1 PJM Interconnection, L.L.C., et al., Order on Show Cause Proceeding, Directing Compliance Filings, Establishing \nPaper Hearing, and Granting In Part and Denying In Part Complaint, Docket Nos. EL25-49-000, EL25-49-001, AD24-\n11-000, EL25-20-000 (“Consolidated Dockets”) (Dec. 18, 2025). \n2 Notice of Extension of Time, Docket Nos. EL25-49-000, EL25-49-001, AD24-11-000, EL25-20-000 (Jan. 23, 2026)."},{"page":2,"startToken":238,"endToken":507,"text":"2 \n \nof the PJM Interconnection, L.L.C. (“PJM”), grid, including by operating retail Behind-the-Meter \nGeneration (“BTMG”), while remaining longstanding pillars of the regional and national economy \nas major employers and by providing critical goods and services to the public.  \nThese traditional large manufacturing and transportation users did not trigger the current \nresource adequacy challenges on the grid. Nor do they present the reliability risks posed by super-\nsized computational loads rapidly entering the landscape. Like residential and small commercial \nretail customers, traditional large users are facing a crisis of costs and adequacy not of their own \nmaking. Unlike their smaller retail customer counterparts, however, many traditional large users \nhave invested substantial capital into retail BTMG that is deeply integrated with their industrial \nprocesses and operations, such that the economics of the entire facility can be jeopardized by the \nCommission’s determinations on retail BTMG in this proceeding and in the BTMG Compliance \nDocket at ER26-1479-000.  \nThe decisions made in these proceedings will determine the future of much on-site \ngeneration in PJM. Even more significantly, it may mean the difference between certain energy-\nintensive businesses (e.g., manufacturers, industrials) operating or closing their operations in PJM. \nStated plainly, there are broad public policy and economic consequences to the Commission’s \ndecisions regarding retail BTMG. Consistent with burgeoning efforts by policymakers to protect \nexisting retail customers, the Commission must also protect traditional large users in accordance \nwith FERC’s statutory mandate under the Federal Power Act (“FPA”), which requires that rates \nand terms of jurisdictional service be just, reasonable, and not unduly discriminatory or \npreferential.3  \n \n3 16 U.S.C. § 824e(a)."},{"page":3,"startToken":507,"endToken":907,"text":"3 \n \nTo provide relevant and accurate information to the Commission as it establishes new rates \nand terms, the Industrials/Amtrak offer replies to several comments in the Paper Hearing, as \nsummarized as follows: \n1) A just and reasonable back-up service is missing from the new transmission \nservices structure. Back-up service provided without a default assumption that it will \nbe used during system peaks is guaranteed to Qualifying Facilities (“QF”) under the \nPublic Utility Regulatory Policies Act of 1978 (“PURPA”) and should be extended to \nother retail customers with on-site generation on a cost-causation basis, either through \nretail netting or through a firm, back-up service charged on a cost-causation basis.  \n2) The penalty regime should be developed cautiously. While the Industrials/Amtrak \nagree that the new Contract Demand Transmission Services (“CDS”), Firm CDS and \nNon-Firm CDS, must have enforcement mechanisms, harsh operational penalties are \npremature at this juncture, at least for existing customers who have long been \naccustomed to receiving NITS based on actual use.  \n \n3) The FERC can avoid stressing the PJM queue and study process and support \ninnovative state-based solutions by establishing appropriate grandfathering and \nBTMG materiality threshold (“Retail Threshold”) standards. The FERC has an \nopportunity in Docket No. ER26-1479 (“BTMG Compliance Docket”) to focus its Co-\nLocated Load reforms on the areas of highest risk, thereby avoiding extended PJM \nqueues and allowing state-based retail solutions for traditional load with on-site \ngeneration to thrive as it has for decades. \n4) Any Grid Reliance Charge for Non-Firm CDS must comport with actual use. \nRather than a fixed fee, any Grid Reliance Charge should be based on actual use of the \nservice. \n \n5) The Retail Threshold, set appropriately, can avoid significant customer confusion \nand economic harm as the FERC introduces the new suite of transmission \nservices. The outcome of PJM’s pending compliance proposal in the BTMG \nCompliance Docket, including a yet-to-be-determined Retail Threshold, directly \nimpacts the ability to achieve just and reasonable terms and conditions in the Paper \nHearing, as well as the economic viability of traditional industrial, institutional, and \ntransportation retail customers who have been successfully operating on-site generation \nfor decades.   \n \nThe Industrials/Amtrak recognize the New Transmission Services structure as a seismic \nshift in the industry. It bears repeating that, unlike grid operators, transmission owners, distribution \ncompanies, generators, and many developers, traditional industrial and institutional users are retail \ncustomers, focused on their core businesses.  Industrial, transportation, and institutional customers"},{"page":4,"startToken":907,"endToken":1220,"text":"4 \n \ndo not primarily operate in the wholesale energy industry. Any new requirements that FERC \nimplements should be narrowly tailored to address the critical issues facing the wholesale grid \nwhile avoiding unnecessarily capturing retail customers into a regulatory regime with which they \nare unfamiliar, with substantially more red tape, and adding to their costs of doing business.   \nII. \nARGUMENTS \nThe Industrials/Amtrak offer the perspective of large, established retail customers whose \nday-to-day operations are deeply interwoven with on-site energy production. Many retail \ncustomers represented in this pleading rely heavily on energy investments they have made over \nthe course of years and decades; these customers, whose retail BTMG may not survive a move to \nCo-Location Arrangement,4 arguably have the most to lose in this docket, despite being stable, \ncooperative, and constructive parts of the grid for decades. The Industrials/Amtrak offer the \nfollowing comments to address significant concerns prompted by the Order and other briefs \nsubmitted in this Paper Hearing. \nA. \nA Just and Reasonable Back-up Service Is Missing from the Suite of New \nTransmission Services.  \nThe initial briefs and responsive briefs in this Paper Hearing do not address the importance \nof back-up service for retail customers with on-site generation, a concern that may not be widely \nunderstood by other interested parties.   The New Services’ design lacks a key component: access \nto back-up power on a cost-causation basis—that is, a firm back-up service that is taken and paid \nfor based on use (“cost-based”). Back-up service is a critical component of operations for industrial \nand institutional retail customers; yet, as explained below, the New Services do not currently \naddress this need.  \n \n4 See PJM Interconnection, L.L.C., 60-Day Compliance Filing for Co-Located Load Related Revisions to Open Access \nTransmission Tariff to Comply with Commission Order in Docket No. EL25-49, et al., (“PJM Compliance Filing”) \nDocket No. ER26-1479-000, at 12-13 (Feb. 23, 2026)."},{"page":5,"startToken":1220,"endToken":1739,"text":"5 \n \nFor many retail customers, access to back-up power is essential. Back-up power \nenables a retail customer to maintain an uninterrupted power supply in the event of a disruption to \nits on-site generation. In the context of PURPA,5 back-up power is defined as “electric energy or \ncapacity supplied by an electric utility to replace energy ordinarily generated by a facility's own \ngeneration equipment during an unscheduled outage of the facility.”6 Back-up power is guaranteed \nto QFs under PURPA with certain cost-based assumptions—namely, that sales of back-up cannot \noperate with the assumption (unless grounded in factual data) that the need for back-up power will \noccur during the system peak.7 However, as explained below, the need for back-up power is not \nlimited to QFs, and the cost-causation basis for back-up power is not limited to QFs, either.  \nIn contrast to NITS, which measures cost responsibility based on the actual use of the grid \nduring times of congestion (putting aside the aspect of recent changes to the retail behind-the-\n \n5 Congress passed PURPA in 1978 to encourage cogeneration, small power production, and geothermal energy \nproduction. 16 U.S. Code § 824a-3(a). PURPA has played an important role for manufacturers and the electric grid \nfor nearly five decades, providing market access where none previously existed, taking strain off the grid, and \nsupporting American industry by enabling economic means to reduce energy costs. Under PURPA, QFs fall into two \nbroad categories: “qualifying small power production facilities,” which can be sized up to 80 MW, and “qualifying \ncogeneration facilities” (“Cogeneration QFs”), which have no size limit. 16 U.S.C. § 824a-3. Cogeneration QFs must \nachieve certain efficiency standards and are highly efficient in their use of input fuels. Cogeneration QFs, which \nproduce both electricity and heat from the same fuel source, make use of the “waste heat” in their manufacturing, \nheating, or cooling process. Cogeneration facilities can achieve efficiencies in excess of 80% by using waste heat and \navoiding electrical losses, compared to the efficiency of approximately 50% for conventional electricity generation \nwith a steam boiler. PJM Interconnection, L.L.C., et al., Responsive Brief of Industrial Customer Organizations and \nAmtrak (“Industrials/Amtrak Responsive Brief”), Docket Nos. EL25-49-000, EL25-49-001, AD24-11-000, EL25-20-\n000, Attachment 1: Affidavit of James Dauphinais (“Dauphinais Affidavit”) at P 11 (Mar. 25, 2026). \n6 18 C.F.R. § 292.101(b)(9) (emphasis added). Under long-established FERC regulations (enacted at Congress’ \ndirection), QFs are entitled to access supplementary power, back-up power, maintenance power, and interruptible \npower. 18 C.F.R. § 292.305(b). \n7 18 C.F.R. § 292.305(c) states: \nRates for sales of back-up and maintenance power. The rate for sales of back-up power or \nmaintenance power: \n(1) Shall not be based upon an assumption (unless supported by factual data) that forced outages or \nother reductions in electric output by all qualifying facilities on an electric utility's system will occur \nsimultaneously, or during the system peak, or both; and \n(2) Shall take into account the extent to which scheduled outages of the qualifying facilities can be \nusefully coordinated with scheduled outages of the utility's facilities."},{"page":6,"startToken":1739,"endToken":2064,"text":"6 \n \nmeter netting rules), the design of the Firm and Non-Firm CDS focuses on pre-defining in advance \nan amount of transmission capacity, then enforcing load limits and/or curtailment through a variety \nof mechanisms. These mechanisms include contract-based services, pre-scheduling of Non-Firm \nCDS use, curtailment prioritization, enforcement penalties, and protective schemes to physically \nprevent excessive draw from the grid.  \nUnfortunately, as currently envisioned, the New Services structure is a poor fit for many \ntraditional large users that operate critical industrial and institutional processes. Many of these \nretail customers cannot shut off immediately if their on-site generation trips suddenly. Reasons for \nthis can be operational, environmental, or health and safety issues. For example, a steel mill in the \nmiddle of a melt must handle molten metal or risk damaging the furnace if it cools too rapidly. For \nrefineries, depressurizing and cooling must occur in controlled sequences to prevent equipment \nfailures or explosions. In some manufacturing contexts that utilize gases, if shutdowns occur too \nquickly, gases must be flared, which can result in environmental compliance violations. Hospitals, \nnaturally, must constantly maintain power. Chemical plants must properly manage ongoing \nchemical reactions to avoid runaway reactions.8 \nThese are just a few examples of the operational, environmental, compliance, and safety \nimplications that prevent retail customers with on-site generation from immediately curtailing their \nload when their on-site generation trips offline due to a forced outage. These traditional large loads \nare quite different from computational load driving today’s load growth (and transmission \nchallenges). As noted by the North American Electric Reliability Corporation (“NERC”), “a data \n \n8 See, e.g., Devin Partida, What happens when manufacturing facilities lose power?, available at \nhttps://www.ishn.com/articles/113257-what-happens-when-manufacturing-facilities-lose-power (last visited Apr. 24, \n2026); Hydropower Carbon Publishing Company, Refinery Power Outage Mitigations, available at \nhttps://www.hydrocarbonpublishing.com/ReportP/power.pdf (last visited Apr. 24, 2026); Global Risk Consultants, \nIt’s Electric: Business Interruption & Property Damage Hazards, tuvsud-electric-business-interruption-and-property-\ndamage-hazards-wp-final.pdf (last visited Apr. 24, 2026)."},{"page":7,"startToken":2064,"endToken":2446,"text":"7 \n \ncenter has a very different load consumption pattern as compared to older large industrial facilities \nlike a paper or steel mill.”9 \nBack-up service closes the service gap for customers that cannot immediately curtail during \na forced outage, by seamlessly and immediately providing replacement electric power to the \ncustomer until the retail BTMG can return to service. Currently, such customers can obtain cost-\nbased back-up service via NITS, which nets out on-site generation output. However, under the \nstructure proposed by PJM in the BTMG Compliance Docket, if the nameplate rating of a retail \ncustomer’s BTMG does not fit under the Retail Threshold, and the BTMG does not qualify for any \ngrandfathering, the retail customer will not be permitted to net any of its on-site generation \noutput.10 If such a customer stays on NITS, it will be forced to pay for transmission service that \ndoes not recognize any contribution of the on-site generation from a transmission cost perspective. \nNot only does this violate cost-causation principles, but it will make some retail customers’ on-\nsite generation uneconomic.11  \nAs designed, neither Firm nor Non-Firm CDS provides back-up power at just and \nreasonable rates. In theory, a retail customer that no longer qualifies for BTMG netting treatment \ncould choose to pursue approval as a Co-Location Arrangement, assuming the retail customer \ndeemed it worthwhile to go through all necessary queues, study processes, applications, \n \n9 North American Electric Reliability Corporation, Assessment of Gaps in Existing Practices, Requirements, and \nReliability Standards for Emerging Large Loads (NERC Large Loads Working Group White Paper) (“NERC Large \nLoad Gap Assessment”), at 10, n. 36 (Mar. 2026), available at https://www.nerc.com/globalassets/our-\nwork/guidelines/reliability/white-paper---assessment-of-gaps.pdf.  \n10 Under PJM’s proposal in the BTMG Compliance Docket, qualification for BTMG treatment would depend on the \nnameplate rating of the on-site generation. If the nameplate exceeds the Retail Threshold, no portion of the generation \noutput would qualify for netting. PJM Compliance Filing, Docket No. ER26-1479-000, at 6-7. The Industrials/Amtrak \nhave protested this proposed treatment. PJM Interconnection, L.L.C., Joint Protest and Comments of Industrial \nCustomer Organizations and Amtrak (“Industrials/Amtrak Protest”), Docket No. ER26-1479-000, at 34-37 (Mar. 16, \n2026). \n11 See Dauphinais Affidavit at PP 42-44. See also PJM Compliance Filing, Docket No. ER26-1479-000, at 12-14."},{"page":8,"startToken":2446,"endToken":2896,"text":"8 \n \ninspections, and installations of protective equipment. If PJM’s approach in its Initial Brief is \nadopted by the FERC, the retail customer would (after obtaining approval) be responsible for \nsubscribing to Non-Firm CDS in the amount of the co-located generation output that is reserved \nfor the Co-Located Load, and to subscribe to Firm CDS in the amount needed from the grid.12 \nProblematically, even after all of this is set up, the retail customer will have no means of \nobtaining back-up power from the grid in the event of forced outages. As proposed, Non-Firm \nCDS cannot provide back-up power because it cannot be accessed during a BTMG generation \nfacility outage until a request for it is submitted to and approved by PJM. The retail customer \nwould be required to automatically curtail its load until it submits a Non-Firm CDS request to PJM \nand PJM approves that request.13  \nFirm CDS, unlike Non-Firm CDS, can provide back-up power—but at the full Firm CDS \nprice. Because Firm CDS implicitly assumes BTMG forced outages occur at the time of the system \npeak and all such BTMG forced outages occur simultaneously, Firm CDS, as proposed, cannot \nprovide back-up service at a cost lower than taking NITS based on gross load.14 In essence, relying \non Firm CDS for back-up service would be reserving that transmission capacity at a price designed \n \n12 PJM Interconnection, L.L.C., Initial Brief of PJM Interconnection, L.L.C. (“PJM Initial Brief”), Docket Nos. EL25-\n49-000, EL25-49-001, AD24-11-000, EL25-20-000, at 16 (Feb. 20, 2026). \n13 Non-Firm CDS would not meet PURPA’s requirements for back-up service. Dauphinais Affidavit at P 45 (“Non-\nFirm [CDS] would fall short in two respects. First, it is incapable of providing backup power for forced outages of \nQualifying Cogeneration Facilities because the actual usage Non-Firm [CDS] would have to be pre-scheduled with \nand approved by PJM in advance of its use, and forced outages cannot be known in advance. Second, the service is \nnot reliable and risky to use as it is only available on an as-available basis, subject to interruption during emergencies, \nand subject to automated interruption. It is not a product that could be used to provide safe and environmentally \ncompliant maintenance power to traditional commercial, industrial, and institutional retail customers with Qualifying \nCogeneration Facilities, never mind backup power to them.”). \n14 Dauphinais Affidavit at P 44 (“[Firm CDS] would inherently assume, in violation of FERC’s rules for backup and \nmaintenance power for Qualifying Facilities, that forced outages or other reductions in electric output by all qualifying \nfacilities on an electric utility's system will occur simultaneously, or during the system peak, or both, without any \nfactual data to support such an assumption.”)."},{"page":9,"startToken":2896,"endToken":3448,"text":"9 \n \nfor 100% use when it might be needed once a year.15 This is completely at odds with sound \neconomics and does not respect basic cost-causation principles, particularly where the history and \nrisk of the individual unit are well established or have met external standards (such as qualifying \nas a QF).16 \nCost-Causation Principles and PURPA Regulations require a back-up power option \nfor retail customers with on-site generation. As recognized by the D.C. Circuit Court of \nAppeals, the “cost-causation principle” has been recognized “for decades” by “the Commission \nand the courts.”17 Under the cost-causation principle, “costs are to be allocated to those who cause \nthe costs to be incurred and reap the resulting benefits.”18 Additionally, PURPA regulations \nexpressly recognize the need for cost-based back-up power and maintenance power for QFs to be \nable to draw from the grid, including during occasional unscheduled outages. However, this need \nis not limited to QFs. To function according to cost-causation principles and under just and \n \n15 As explained in the Industrials/Amtrak Responsive Brief, if ten 100 MW industrial loads, each with offsetting \nBTMG, individually experience unplanned outages 1% of the time, the New Services structure would require them to \ncollectively purchase 1,000 MW (1 GW) of Firm CDS, even though they would statistically never use more than a \nfraction of that amount at one time. In such a scenario, it would be unjust and unreasonable for a Transmission Owner \nto build 1 GW of transmission capacity, when only a fraction of that would ever be needed. In like fashion, it would \nbe unjust and unreasonable to charge a customer as if that transmission capacity would be needed. \n16 The New Services structure also does not reasonably accommodate maintenance power. While Non-Firm CDS is \ncapable of providing maintenance power, it is only capable of doing so on a non-firm basis, which is problematic for \nthose loads, that, due to safety, environmental compliance and/or high cost implications, are unable to immediately \ncurtail their load when PJM operationally curtails the use of Non-Firm CDS. Firm CDS, in contrast, is capable of \nproviding maintenance power on a firm basis; however, like with back-up power, it cannot do so at a cost any lower \nthan taking NITS based on gross load, which is not consistent with cost of service principles given this would \nimplicitly assume BTMG maintenance outages cannot be scheduled to avoid periods when resource adequacy and \ntransmission service availability is challenged. \n17 Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1255 (D.C. Cir. 2018). (“For decades, the Commission and the \ncourts have understood [the ‘just and reasonable’ rate requirement] to incorporate a ‘cost-causation principle’—the \nrates charged for electricity should reflect the costs of providing it.”). \n18 Nat’l Ass’n of Reg. Util. Comm’rs v. FERC, 475 F.3d 1277, 1285 (D.C. Cir. 2007). (See also K N Energy, Inc. v. \nFERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992); City of Lincoln v. FERC, 89 F. 4th 926, 930 (D.C. Cir. 2024); see also \nMidwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004) (“we evaluate compliance with \nthis unremarkable [cost causation] principle by comparing the costs assessed against a party to the burdens imposed \nor benefits drawn by that party”)."},{"page":10,"startToken":3448,"endToken":3790,"text":"10 \n \nreasonable rates, other retail loads with on-site generation also require back-up service based on \ncost causation. \nDespite the above principles, the New Services structure puts industrial retail customers \nwith BTMG and other similarly situated customers in a bind. If the FERC’s final orders in this \nproceeding and the BTMG Compliance Docket do not allow these customers to qualify for netting \nas retail BTMG, they will have zero options for cost-based back-up power. Even if they go through \nthe (likely extensive) process of PJM studies, entering the queue, qualifying as a Co-Location \nArrangement, installing protective equipment, etc., they will still not have access to cost-based \nback-up service. Consequently, for the Commission to meet: (1) PURPA regulatory requirements \n(applicable to QFs) and (2) cost-causation principles in transmission service design (applicable to \nall customers), transmission services must be developed that apply cost-causation standards to \noccasional, yet unplanned use of the transmission system that does not occur during peak hours.  \nTo that end, in the BTMG Compliance Docket, the Industrials/Amtrak proposed that: (1) \nQFs be able to continue to net output and operate under longstanding/historical retail BTMG rules \nand (2) the Retail Threshold be set at a realistic level (i.e., at least 200 MW) to permit these kinds \nof retail customers (ranging from hospitals to steel mills to pharmaceutical manufacturers to \ntransportation providers) that are not presenting resource adequacy concerns or risks to continue \nto operate under existing BTMG rules.19 As described in the Responsive Brief, the BTMG netting \nconstruct meets the requirements of PURPA’s implementing regulations that QFs be guaranteed \naccess to back-up and maintenance power with the cost-based assumptions required by the \nRegulations. (If a retail customer with BTMG is in the netting construct and it requires back-up \n \n19 Industrials/Amtrak Protest at 17-23. While allowing QFs to remain eligible for longstanding BTMG netting rules \naddresses the essential concern for QFs, many facilities operate on principles similar to those of QFs but do not have \nQF status. See Industrials/Amtrak Responsive Brief at 20-21; Dauphinais Affidavit at P 48."},{"page":11,"startToken":3790,"endToken":4191,"text":"11 \n \nservice during peak hours, it will then be charged accordingly in the following year; if, however, \nas is usually the case, back-up power is only needed on occasion and not during peak hours, the \nNITS netting structure accounts for that in its pricing by adjusting the customer’s transmission \nobligation the subsequent year.) \nThe Commission has two valid options before it to address the need for back-up power. \nFirst, it could grant the grandfathering, Retail Threshold, and QF requests of the \nIndustrials/Amtrak in the BTMG Docket, as restated above. Alternatively, the Commission could \nalso develop a back-up power service option for Co-Location Arrangements. Ideally, the \nCommission would do both, ensuring an essential, cost-based service continues in the future. \nB. \nThe Grid Reliance Charge Must Comport with Actual Use. \nIn their Initial Brief, the Transmission Owners proposed a “Grid Reliance Charge” for Non-\nFirm CDS.20 The Transmission Owners proposed an initial allocator of 25.8% to each zone’s \ntransmission revenue requirement, with periodic updates.21 This allocator is based on the portion \nof transmission operations and maintenance (“O&M”) and depreciation that is associated with \n“grid reliance” functions.  \nIn the responsive briefing stage, several parties addressed the proposed Grid Reliance \nCharge.  The Industrials/Amtrak support the comments of Vistra Corp. (“Vistra”), arguing that the \n \n20 PJM Interconnection, L.L.C., Initial Brief and Joint Responses of the Indicated PJM Transmission Owners to Paper \nHearing Questions (“Transmission Owners Initial Brief”), Docket Nos. EL25-49-000, EL25-49-001, AD24-11-000, \nEL25-20-000, at 14-15. \n21 The “PJM Transmission Owners initially propose to calculate this charge for each zone based on an average fixed \npercentage of the portion of transmission depreciation and operations and maintenance (‘O&M’) expense associated \nwith providing grid reliance services, and then applying that percentage to each PJM Transmission Owner’s \nAttachment H annual transmission revenue requirement.” Id. The fixed percentage “allocator” is “based on costs \nincluded in transmission plant and transmission O&M FERC accounts, derived from FERC Form No. 1 Reports of \nthe Transmission Owners….” The Transmission Owners propose that the allocator “be multiplied by each PJM \nTransmission Owner’s rate for NITS and Firm Contract Demand Service to arrive at an ‘unadjusted’ Grid Reliance \nCharge rate,” which will then be multiplied by a zone-based ratio “that accounts for the difference between the demand \nused to account for the NITS and Firm Contract Demand Service . . . and Co-Located Load customers’ gross load.” \nId. at 17."},{"page":12,"startToken":4191,"endToken":4609,"text":"12 \n \nGrid Reliance Charge fails to reflect how differently customers rely on the transmission system. \nUnder the Transmission Owners’ proposal, customers that take little or no energy from the grid \nwould subsidize traditional network customers, violating cost-causation principles. Vistra states in \nits Responsive Brief: \nThe Commission’s questions illustrate that customers could use Non-Firm Contract \nDemand Transmission Service in different ways. A customer might (a) never \nreserve service (in fact, it might actually commit to never reserving service),22 or \n(b) occasionally reserve a de minimis amount of service, or (c) frequently reserve \nsignificant amounts of service. The first customer in that example clearly does not \nrely on the grid to the same extent as the second or third, and the second customer \nclearly does not rely on the grid to the same extent as the third. A customer that \nnever reserves transmission service relies on the PJM grid only to transport black \nstart and regulation services, while other customers may rely on the PJM grid for \nenergy withdrawals, either for primary or back-up service, in significantly varying \namounts. Yet the PJM Transmission Owners’ proposal would impose the same grid \nreliance charge on these very different customers.23 \n \nAs Vistra noted, Non-Firm CDS may have a range of uses, both in type and amount. Yet, \nthe Grid Reliance Charge, as proposed by the Transmission Owners, does not reflect this \ndistinction at all. As stated by Vistra, the “Transmission Owners’ proposal stands in stark contrast \nto this long-standing policy [of offering and pricing individual ancillary services separately] by \ncreating a new service charge for what appears to be an undefined ancillary service (i.e., grid \nreliance), which they assert covers a ‘suite of synchronization support services.’”24 Vistra states \nthat the Transmission Owners do not explain how customers benefit from that “suite” of purported \nservices, proposing instead to bundle the services together instead of “pric[ing] the individual \n \n22 PJM Interconnection, L.L.C., Response Brief of Vistra Corp. (“Vistra Responsive Brief”), Docket Nos. EL25-49-\n000, EL25-49-001, AD24-11-000, EL25-20-000 at 19 (citing Co-Located Load Order, 193 FERC ¶ 61,217 at P 178 \nn. 380). \n23 Id. (citing Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1263 (D.C. Cir. 2018) (“FERC must make some \nreasonable effort to match costs to benefits.”); BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 268 (D.C. \nCir. 2014) (holding that the cost-causation principle is a “matter of making sure that burden is matched with benefit”). \n24 Id. at 20."},{"page":13,"startToken":4609,"endToken":4993,"text":"13 \n \n[services] separately.” Yet, as Vistra aptly notes, “the Transmission Owners then propose to \nimpose that cost on customers without regard to the extent to which customers actually rely on the \ngrid. The Transmission Owners do not justify how it is consistent with cost-causation principles \nto impose the same grid reliance charge for those very different types of grid reliance.”25  \nTo reinforce this concern, consider the following hypothetical retail customer:  \nAn industrial retail customer – a steel mill – has operated a cogeneration facility \nfor the past 50 years. The mill employs 500 workers and produces over a million \ntons of steel per year. The cogeneration configuration uses blast furnace gas and \nother sources to produce both electricity and useful steam for processing. The \nelectric generation reaches approximately 80 MW – that’s two-thirds of the total \nelectrical supply needed to operate the plant, which is 120 MW. For decades, this \nmill has been operating under NITS for transmission cost determination. Its NITS \ntag tends to be around 40 MW, because its on-site generation operates reliably and \nis deeply integrated into the mill’s production process. \n \nDepending on the outcome of the BTMG Compliance Docket, this hypothetical customer \nmay be forced off of its existing service with retail BTMG netting (due to having 80 MW of \ntransmission charges added to the mill’s transmission tag; assuming a relatively average NITS rate \nof $50,000 per MW-year, that is a $4 million annual cost increase). To avoid spending an \nadditional $4 million annually, the mill may need to seek status as a Co-Location Arrangement. \nHowever, even if (and when) the mill accomplishes that, it would (under the Transmission \nOwners’ Grid Reliance Charge proposal.26) have approximately 25% charge for the Non-Firm \nCDS—in this illustration, approximately $1 million per year. However, it is not clear what value \nthe steel mill would receive from this $1 million, because Non-Firm CDS access is only as-\navailable and cannot function as a back-up service.  \n \n25 Id.  \n26 See Transmission Owners Initial Brief at 14-15 (proposing an initial 25.8%). See also PJM Initial Brief at 16 \n(proposing that “[a]n Eligible Customer taking service on behalf of a Co-Located Load must request Non-Firm \nContract Demand Transmission Service equivalent to the MW level of the Co-Located Generating Facility dedicated \nto serving the Co-Located Load”)."},{"page":14,"startToken":4993,"endToken":5296,"text":"14 \n \nConsequently, as an as-available service, Non-Firm CDS should not be charged a “standby \nfee” such as the Grid Reliance Charge, as Non-Firm CDS does not provide any guaranteed \navailability. Regardless of the merits of an access or standby fee in the context of a firm service \noffering, it is unreasonable to charge for “access” with no guarantee of when such access will be \navailable. Rather, an actual use calculation on an hourly basis would be an appropriate way to \ncharge for Non-Firm CDS. Such an approach guarantees that retail customers pay for what they \nuse; such revenues collected by transmission owners would go toward the revenue requirement for \nthat transmission owner, ultimately lowering rates for Firm CDS and NITS customers. \nC. \nThe FERC Can Avoid Stressing the PJM Queue and Study Process and \nSupport Innovative State-Based Solutions by Establishing Appropriate \nGrandfathering and Retail Threshold Standards. \nWhile the FERC is pursuing major industry reforms in the Co-Located Load proceeding, \nthe Industrials/Amtrak respectfully request that the Commission take care to accomplish the \ndesired reforms without creating undue hardship for those impacted by the rule changes—namely, \nretail customers who have already made major investments in on-site generation or who (in the \ncase of cogeneration) require on-site generation as part of their operational process. The truism of \n“unintended consequences” remains applicable here. Striking the right balance between risk and \nregulatory burden means avoiding overly broad regulations that overregulate beyond the core \nissues intended to be remedied.  \nIn this proceeding, the FERC itself implicitly acknowledged this balance in the Order when \naddressing BTMG rule changes, stating that “[a] materiality threshold for all BTMG should reduce \nthe reliability and resource adequacy risks that large or increasing BTMG may pose to PJM, while \nalso allowing for Network Customers to reduce their transmission charges in a transparent, not"},{"page":15,"startToken":5296,"endToken":5593,"text":"15 \n \nunduly discriminatory fashion.”27 This acknowledgment by the FERC of the risk balance is on \npoint. Here, requirements should be narrowly tailored to reduce significant grid risk without \nburdening traditional retail customers with terms, conditions, or rates that are unduly \ndiscriminatory, unjust, unreasonable, or difficult to understand and follow. Rather, to the extent \nthe FERC implements sweeping regulatory change, it should focus on the challenges that are \nchanging how the grid functions—namely, the entry of super-sized computational loads that dwarf \nmost industrial, institutional, and transportation facilities. The Commission is appropriately \nconcerned with “grid-busting” growth, but this growth is driven by often massive computational \nloads, not traditional large loads that have been in place for decades.  \nThe FERC’s regulations should also be narrowly tailored to avoid jurisdictional conflicts \nwith the states, which are accustomed to working with retail customers and have a variety of tools \nto ensure fair interconnection and cost-allocation policies. Finally, to make its intended changes \nsuccessful, the FERC should not “gum up” the PJM queue and study process by avoiding putting \nlarge amounts of existing load into the queue. \nThe key to accomplishing the FERC’s goals while reducing unintended consequences \nresides in the BTMG Compliance Docket. There, the FERC should take the following actions:  \n1. Set a realistic Retail Threshold to focus new Co-Located Load rules on “grid-\nbusting” growth above 200-300 MW, not on existing industrial customers (e.g., \nconsumer goods manufacturers, steel mills, chemical manufacturers, paper mills, \nand pharmaceutical factories). \n2. Qualify all QFs for retail BTMG treatment without a date limit, consistent with \nPURPA regulations. \n3. Set clear grandfathering rules to enable existing, established users to avoid \nintensive PJM study queues, study deposits, processes, for operations that continue \nto function properly. \n \n \n27 Co-Located Load Order at P 179 (emphasis added)."},{"page":16,"startToken":5593,"endToken":5943,"text":"16 \n \nThe above steps will relieve considerable pressure on the industry, PJM, utilities, and customers \nas all stakeholders work to implement the Commission’s final order in this proceeding.  These \ninterrelated issues directly bear on the Commission’s resolution of the issues raised in this paper \nhearing. \nOne final comment on this topic: as noted by PJM in the BTMG Compliance Docket, \nexisting retail BTMG arrangements—including QFs and other BTMG arrangements with existing \ncontracts—“have been in place and netted against Network Loads within PJM without operational \nissues to date.”28 Large loads with large retail BTMG units have existed in PJM since the BTMG \nrules were established in 2004.29 That phrase bears repeating—without operational issues to date. \nThe FERC should act with extreme caution when upsetting something that has functioned so well \nfor over two decades, as a team effort between retail customers, state regulators, and local utilities.  \nD. \nThe Penalty Regime Should be Developed Cautiously. \nIn the Order, the Commission asked for comment on “[w]hat interconnection requirements \nand operational practices are necessary for special protection schemes to maintain system \nreliability . . . in the event that a Co-Located Load itself or its associated generator trips offline.”30 \n \n28 PJM Compliance Filing, Docket No. ER26-1479-000, at 10. \n29 From the beginning, large manufacturers have operated generating facilities behind-the-meter that offset their load. \nWhen BTMG rules were established in PJM over 20 years ago, large on-site generation units already existed and \nparticipated in the proceeding that approved these rules. For example, a refining company intervenor at the time \ndescribed its on-site generation as a “60 megawatt combined cycle cogeneration facility,” and an agricultural company \ndescribed its operational location as having “a combined load, net of the capabilities of [the company’s] onsite \ncogeneration, of between 200 and 300 MW,” implying a substantial presence of on-site generation. PJM \nInterconnection, L.L.C., Motion to Intervene of Valero Refining Company – New Jersey, Docket No. ER04-608-000 \n(Mar. 23, 2004); PJM Interconnection, L.L.C., Motion to Intervene of Archer-Daniels-Midland Company, Docket No. \nER04-608-000 (Mar. 22, 2004). \n30 Co-Located Load Order at P 219(6)."},{"page":17,"startToken":5943,"endToken":6277,"text":"17 \n \nIn its initial brief, PJM proposed strong operational penalties for Non-Firm CDS. In response, \nseveral parties oppose PJM’s “draconian” penalty regime, including the “one-strike” provision.31 \nThe Industrials/Amtrak urge the Commission to exercise caution regarding operational \npenalties. Specifically, the FERC should initially avoid operational penalties or limit them based \non load size and type (i.e., in accordance with grid risk). Non-Firm CDS should be designed to \nprevent cost shifts to other customers, in accordance with cost-causation principles; yet, as the \nindustry adapts, the Commission should exercise caution in overly harsh operational penalties—\nespecially for existing retail customers who may be forced to move from retail BTMG \narrangements to Co-Location Arrangements. Transitioning to the New Transmission Services will \nnot be a simple process for traditional retail customers, who have long taken service from their \nretail service provider under a NITS construct. Of particular concern is the severe consequences \nof suspending a retail customer’s access to CDS services after a single violation. \nTaking the hypothetical steel mill from Section II(B), supra, assume the mill obtains Co-\nLocation Arrangement status. If the Transmission Owners’ proposal is accepted, the mill owes a \n$1+ million annual charge for Non-Firm CDS (approximately 25% of the NITS cost) for its 80 \nMW on-site generation—but at least the mill avoids an increase of $4 million per year, which \nwould occur under a regime that the customer must pay for NITS on a gross basis. However, the \nmill—which, for decades, has occasionally drawn its full 120 MW during planned maintenance \nand rare forced outages—will now be at risk of losing access to Non-Firm CDS (a $3 million \nannual net cost, the difference between gross NITS and Non-Firm CDS) if it does the same thing \nonce more. However, as explained in Section II(A), supra, it may not be possible in some scenarios \n \n31 PJM Interconnection, L.L.C., Reply Brief of Constellation Energy Generation, L.L.C., Docket Nos. EL25-49-000, \nEL25-49-001, AD24-11-000, EL25-20-000 (Mar. 25, 2026)."},{"page":18,"startToken":6277,"endToken":6626,"text":"18 \n \nfor the mill to curtail. If the mill is in the middle of a melt and the on-site generation trips, it must \nbe able to draw the additional 80 MW from the grid to avoid safety violations or catastrophic \ndamage to its equipment. In such a case, the mill would reasonably pay financial penalties, but it \nshould not be banned from Non-Firm CDS for that lone violation.32 \nPerhaps such flexibility cannot be afforded for a 1,000 MW computational load, as 1,000 \nMW of flow may have exponentially greater implications for a transmission zone than an extra 80 \nMW. Large computational loads have a different risk profile than existing industrial and \ninstitutional loads with a known operating history. As stated in a recent White Paper by NERC, \n“recent years have witnessed significant growth in large load facilities that differ markedly from \ntraditional industrial load.”33 NERC explains that these “new types of loads are not only substantial \nin size but also predominantly consist of numerous rectifiers that supply power to the end process, \ncontrasting sharply with traditional industrial loads dominated by large induction or synchronous \nmotors.”34 As NERC’s analysis clearly demonstrates, computational load may pose substantial \nreliability challenges for the grid, challenges the industry is just beginning to broadly understand. \nIn contrast, industrial and institutional retail customers have existed with on-site generation \nfor many decades without issue.35 Consequently, while the Industrials/Amtrak believe penalties \nshould be strong enough to create economic incentives that align with the design of the New \nTransmission Services, the initial penalty regime should account for the possibility that existing \nretail customers who are not primarily in the energy industry may shift to this new construct. Retail \ncustomers like the hypothetical steel mill, who could be forced into a position where there are no \n \n32 As the contract-based services reflect the natural gas construct to some degree, it is important to note that natural \ngas generally operates under financial, not operational, penalties. \n33 NERC Large Load Gap Assessment at 29. \n34 Id. \n35 PJM Compliance Filing, Docket No. ER26-1479-000, at 10."},{"page":19,"startToken":6626,"endToken":6930,"text":"19 \n \ngood back-up power options, and yet, for health or safety reasons, could not curtail, should not be \nsuspended from Firm and Non-Firm CDS, and forced back to gross NITS after one error.  \nE. \nThe Retail Threshold, Set Appropriately, Can Avoid Significant Customer \nConfusion and Economic Harm as the FERC Introduces the New Suite of \nTransmission Services. \nThe Industrials/Amtrak fully support grid reliability and resource adequacy. However, the \nIndustrials/Amtrak respectfully urge the Commission to prevent the impact of the Commission’s \nreforms from falling most heavily on existing large retail customers, such as industrial, \ninstitutional, and transportation customers. Many of these retail customers developed and built on-\nsite generation facilities based on certain critical cost assumptions, and they have operated under \nthose assumptions for many years.   \nIn the view of the Industrials/Amtrak, the Co-Located Load Order may be \nimplemented in one of two approaches. The first approach—failing to provide a cost-based \nback-up power option for current BTMG retail customers, yet forcing them off the retail netting \napproach—would cause significant damage to the traditional large users that have helped build, \ninnovate, and strengthen the grid over decades.  \nHowever, there is an alternative approach that respects the reforms the FERC is pursuing, \nwhile ensuring American industry, institutions, and transportation providers have access to \nreliable, cost-based back-up power. By providing a pragmatic and reasonable Retail Threshold in \nthe BTMG Compliance Docket (i.e., at least 200 MW), the FERC may pursue the primary goals \nof the Co-Located Load Order while avoiding significant and direct damage to existing \nmanufacturers, universities, hospitals, and transportation systems. \nThe potential economic impacts of the FERC’s decisions in this docket and in the BTMG \nCompliance Docket are profound, during a time when retail customers are already grappling with \ncost increases, resource adequacy concerns, and other economic pressures. Despite investing"},{"page":20,"startToken":6930,"endToken":7324,"text":"20 \n \nsubstantial sums over the course of years to develop and maintain on-site generation (thus \nminimizing the load placed on the transmission system and reducing the need for more system \nupgrades) and, in many cases, to support thermal needs at their facilities, retail customers with \nBTMG are facing the potential of being forced to a “gross load” measurement for NITS or moving \nto Firm and Non-Firm CDS. However, neither structure accurately accounts for the true benefits \nand costs of a reliable on-site generating unit that occasionally needs back-up power, and both \nstructures treat that on-site generating unit as if it is nonexistent for purposes of transmission \ncharges. \nIn addition to violating cost-causation principles, failing to provide for a cost-based back-\nup service could seriously damage existing users’ economic viability by requiring customers to be \ncharged for transmission (and capacity, subject to clarification) as if their BTMG were not \noperating. The result will render some of those units uneconomic, forcing them to operate at a loss, \nclose and seek power from the grid, or shutter the plant entirely.36 As stated previously, in the \nProtest and Comments of Eastman Chemical Company (“Eastman”) in the BTMG Compliance \nDocket, Eastman explained that an arbitrarily low and unrealistic Retail Threshold (resulting in \nremoval of BTMG netting) “renders Eastman’s BTMG uneconomic after almost 28 years of \noperations.”37 These are the kinds of unintended consequences the Commission should carefully \nconsider as it weighs the significant issues before it. \n \n36 Addressing cogeneration units in particular, Mr. Dauphinais explained that if the ability to operate “in a safe and \nenvironmentally compliant manner within the bounds of what can be supported by the remaining thermal capability \nof the Cogeneration Facility at just and reasonable electric power rates” cannot be assured, “cogeneration may fail to \nbe a practical and/or economic solution to the retail customer’s needs, causing the efficiency benefits of cogeneration \nto be forgone and/or the retail customer to become economically unviable.” Dauphinais Affidavit at P 43. \n37 PJM Interconnection, L.L.C., Protest and Comments of Eastman Chemical Company, Docket No. ER26-1479-000 \n(Mar. 16, 2026). For some industrial and institutional customers, transmission and capacity cost savings are a critical \nfactor that makes it worth the investment to build and operate generation on their premises—investments these \ncustomers have already made (sometimes over decades). See Dauphinais Affidavit at P 17."},{"page":21,"startToken":7324,"endToken":7412,"text":"21 \n \nIn summary, if the FERC sets a reasonable Retail Threshold that reflects current retail \nBTMG installations, as discussed in the Industrials/Amtrak’s BTMG Protest (and in the attached \nDauphinais Affidavit), and appropriately exempts QFs without a date limit, these actions go a long \nway toward allowing FERC to address the real drivers of change on the grid through, among other \nthings, the proposed New Services without damaging the existing load that has helped build and \nsustain the grid for decades and without discouraging continued American manufacturing growth."},{"page":22,"startToken":7412,"endToken":7545,"text":"22 \n \nIII. \nCONCLUSION & REQUEST FOR RELIEF \nThe Industrials/Amtrak respectfully request that the Commission consider this Reply Brief \nin adjudicating the issues raised in this Paper Hearing. Specifically, the Industrials/Amtrak ask the \nCommission to implement the Co-Located Load Order in a measured and careful fashion that does \nnot result in adverse cost consequences to traditional large users, including manufacturers and \ntransportation customers.   \n \n \n \n \n \nRespectfully submitted, \n \nBy: \n/s/ Susan E. Bruce \n \n \n \nSusan E. Bruce \nKenneth R. Stark \nMatthew L. Garber \nMcNees Wallace & Nurick LLC  \n100 Pine Street \nHarrisburg, PA  17101 \nTel:  717-232-8000 \nE-mail: sbruce@mcneeslaw.com \nE-mail: kstark@mcneeslaw.com \nE-mail: mgarber@mcneeslaw.com \n \nCounsel to the PJM Industrial Customer Coalition, \nthe Industrial Energy Consumers of America, the \nAmerican Forest and Paper Association, and the \nNational Railroad Passenger Corporation (Amtrak) \n \nDated: April 24, 2026"},{"page":23,"startToken":7545,"endToken":7606,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served via electronic transmission the foregoing upon \neach person designated on the official service list compiled by the Secretary in this proceeding.  \nDated this 24th day of April, 2026.  \n \n \n     /s/ Matthew L. Garber \n \n \n \nMatthew L. Garber \n100 Pine Street \nHarrisburg, PA  17101 \nTel:  717-232-8000 \nFax:  717-237-5433 \nE-mail: mgarber@mcneeslaw.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":1245,"startToken":0,"endToken":150},{"p":1,"at":1245,"title":"I. EXECUTIVE SUMMARY","method":"printed heading","endPage":4,"endAt":389,"startToken":150,"endToken":964},{"p":4,"at":389,"title":"II. ARGUMENTS","method":"printed heading","endPage":11,"endAt":783,"startToken":964,"endToken":3909},{"p":11,"at":783,"title":"B. The Grid Reliance Charge Must Comport with Actual Use.","method":"printed heading","endPage":14,"endAt":755,"startToken":3909,"endToken":5114},{"p":14,"at":755,"title":"C. The FERC Can Avoid Stressing the PJM Queue and Study Process and","method":"printed heading","endPage":16,"endAt":974,"startToken":5114,"endToken":5743},{"p":16,"at":974,"title":"D. The Penalty Regime Should be Developed Cautiously.","method":"printed heading","endPage":19,"endAt":194,"startToken":5743,"endToken":6659},{"p":19,"at":194,"title":"E. The Retail Threshold, Set Appropriately, Can Avoid Significant Customer","method":"printed heading","endPage":22,"endAt":6,"startToken":6659,"endToken":7413},{"p":22,"at":6,"title":"III. CONCLUSION & REQUEST FOR RELIEF","method":"printed heading","endPage":23,"endAt":0,"startToken":7413,"endToken":7545},{"p":23,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":23,"endAt":423,"startToken":7545,"endToken":7606}]}