{"document":{"slug":"rec-20260424-5312-3","title":"Exhibit No. PTO-0006 – Illustrative Tariff Sheets","issued":"2026-04-24","accession":"20260424-5312","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Indicated PJM Transmission Owners","kind":"attachment","file":"sources/filings/text/20260424-5312_003.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260424-5312","tier":"record","parent":"rec-20260424-5312","sha256":"fe1371184ebb96899d469e86d260bf5b3b5d6dca86469a06bedb2f70fc0cb647","pages":17,"tokens":4826,"emptyPages":[],"textThemes":["flex","colo","cost"]},"pages":[{"page":1,"startToken":0,"endToken":246,"text":"Exhibit No. PTO-0006 \nPage 1 of 17 \nILLUSTRATIVE TARIFF SHEETS FOR  \nINTERIM NITS, FIRM CONTRACT DEMAND  \nAND NON-FIRM CONTRACT DEMAND \nTRANSMISSION SERVICE RATES\nRedlines to PJM Illustrative Tariff Records from February 23, 2026 \nInitial Brief \nTariff, Part XI. Transmission Services Available for Eligible Customers Taking Service on \nBehalf of Co-Located Loads \nSubpart A – Interim Network Integration Transmission Service \n*** \n706 Rates and Charges \nEligible Customers taking Interim Network Integration Transmission Service shall pay the charges \nset forth in this Section 706. \n706.1 Monthly Demand Charge \n[Reserved] \nEligible Customer shall pay a monthly Demand Charge for Zone Network Load and Non-Zone \nNetwork Load, which shall be determined as follows:  Eligible Customer’s measured demand \namount (in MWs) multiplied by the applicable zonal Network Integration Transmission Service \nrate established pursuant to Section 34.1. \nRevenue Crediting.  Each month, revenue credits will be applied to the gross Monthly Demand \nCharge to determine the actual charge to the Transmission Customer.  Revenue credits shall be \ncalculated based on the sum of a Zone’s share of revenues collected during the month from:  (i) \nthe Grid Reliance Charge under Schedule [GRC]; and (ii) the Non-Firm Contract Demand Charge \nunder Schedule [NFCD].  The sum of these revenues will appear as a reduction to the gross \nmonthly rate stated above on a Transmission Customer’s bill in that month for service under this \nschedule.   \n706.2 Redispatch Charge \nThe Eligible Customer and each Transmission Owner shall pay any redispatch costs as set forth in \nTariff, Attachment K."},{"page":2,"startToken":246,"endToken":374,"text":"Exhibit No. PTO-0006 \nPage 2 of 17 \n706.3 Stranded Cost Recovery \nAny Transmission Owner may seek to recover stranded costs from the Eligible Customer pursuant \nto this Tariff in accordance with the terms, conditions and procedures set forth in FERC Order No. \n888.  However, the Transmission Owner must separately file any proposal to recover stranded \ncosts under section 205 of the Federal Power Act. \n706.4 Other Charges \nEligible Customer shall pay administrative services charges under Tariff, Schedule 1A; Tariff, \nSchedule 9; and Tariff, Schedule 10, consistent with the charges assessed to loads taking Network \nIntegration Transmission Service. \nEligible Customer shall pay Ancillary Services charges in accordance with Tariff, Part I, section \n3. \nEligible Customer shall pay Black Start Service charges in accordance with Tariff, Schedule 6A."},{"page":3,"startToken":374,"endToken":675,"text":"Exhibit No. PTO-0006 \nPage 3 of 17 \n714 Rates and Charges for Firm Contract Demand Transmission Service \nEligible Customers taking Firm Contract Demand Transmission Service shall pay the charges set \nforth in this Section 714. \n714.1 Monthly Demand Charge \n[Reserved] \nEligible Customer shall pay a Monthly Demand Charge based on the Firm Contract Demand \nTransmission Service amount (MW), as specified in Eligible Customer’s Service Agreement, in \naccordance with Tariff, Schedule [FCD]. \n714.2 Network Upgrade Charge \n[Reserved] \n714.3 Redispatch Charge \nThe Eligible Customer and each Transmission Owner shall pay any redispatch costs as set forth in \nTariff, Attachment K. \n714.4 Stranded Cost Recovery \nAny Transmission Owner may seek to recover stranded costs from the Eligible Customer pursuant \nto this Tariff in accordance with the terms, conditions and procedures set forth in FERC Order No. \n888.  However, the Transmission Owner must separately file any proposal to recover stranded \ncosts under section 205 of the Federal Power Act. \n714.5 Other Charges \nEligible Customer shall pay administrative services charges under Tariff, Schedule 1A; Tariff, \nSchedule 9; and Tariff, Schedule 10 based on the total quantity of MWHs of energy delivered \nusing Firm Contract Demand Transmission Service, except in the case of any capacity-related \ncharges under these schedules, which shall be based on the Eligible Customer’s Unforced Capacity \nObligation. \nEligible Customer shall pay Ancillary Services charges, except for Regulation, based on the total \nquantity in MWhs of energy delivered to the Co-Located Load using Firm Contract Demand \nTransmission Service in accordance with Tariff, Part I, section 3. \nEligible Customer shall pay Black Start Service charges based on the gross demand Co-Located \nGross Demand of the Co-Located Load in accordance with Tariff, Schedule 6A. \nEligible Customer shall pay Regulation charges based on the gross demand Co-Located Gross \nDemand of the Co-Located Load."},{"page":4,"startToken":675,"endToken":740,"text":"Exhibit No. PTO-0006 \nPage 4 of 17 \nEligible Customer shall pay a Grid Reliance Charge based on the Co-Located Gross Demand in \nexcess of the Eligible Customer’s Firm Contract Demand Transmission Service amount, in \naccordance with Tariff, Schedule [GRC].  Eligible Customer’s Co-Located Gross Demand and \nFirm Contract Demand Transmission Service amount shall be those contained in Eligible \nCustomer’s Service Agreement for Contract Demand Transmission Service."},{"page":5,"startToken":740,"endToken":1063,"text":"Exhibit No. PTO-0006 \nPage 5 of 17 \n715 Rates and Charges for Non-Firm Contract Demand Transmission Service \nEligible Customers taking Non-Firm Contract Demand Transmission Service shall pay the charges \nset forth in this Section 715. \n715.1 Monthly Demand Charge \n[Reserved] \nEligible Customer shall pay a maximum Monthly Demand Charge based on its Non-Firm Contract \nDemand Transmission Service amount (MW), as specified in Eligible Customer’s Service \nAgreement, in accordance with Tariff, Schedule [NFCD]. \n715.2 Redispatch Charge \nThe Eligible Customer and each Transmission Owner shall pay any redispatch costs as set forth in \nTariff, Attachment K. \n715.3 Stranded Cost Recovery \nAny Transmission Owner may seek to recover stranded costs from the Eligible Customer pursuant \nto this Tariff in accordance with the terms, conditions and procedures set forth in FERC Order No. \n888.  However, the Transmission Owner must separately file any proposal to recover stranded \ncosts under section 205 of the Federal Power Act. \n715.4 Other Charges \nEligible Customer shall pay administrative services charges under Tariff, Schedule 1A; Tariff, \nSchedule 9; and Tariff, Schedule 10 based on the total quantity of MWhs of energy delivered using \nNon-Firm Contract Demand Transmission Service, except any capacity-related charges under \nthese schedules will not apply. \nEligible Customer shall pay Ancillary Services charges, except for Regulation, based on the total \nquantity in MWhs of energy delivered to the Co-Located Load using Non-Firm Contract Demand \nTransmission Service in accordance with Tariff, Part I, section 3. \nTo the extent the Eligible Customer does not have an effective Service Agreement for Firm \nContract Demand Transmission Service, Eligible Customer shall pay Black Start Service charges \nbased on the its Co-Located Gross Demand gross demand of the Co-Located Loadin accordance \nwith Tariff, Schedule 6A. \nTo the extent the Eligible Customer does not have an effective Service Agreement for Firm \nContract Demand Transmission Service, Eligible Customer shall pay Regulation charges based on \nits Co-Located Gross Demand a gross demand of the Co-Located Load."},{"page":6,"startToken":1063,"endToken":1467,"text":"Exhibit No. PTO-0006 \nPage 6 of 17 \nNew Proposed Rate Schedules\nSCHEDULE [FCD] \nFirm Contract Demand Transmission Service \nFor Co-Located Load \n1) \nEligible Customer taking Firm Contract Demand Transmission Service in a Zone in which \nNetwork Integration Transmission Service rates are determined based on formula rates set forth in \nAttachment H shall pay a Monthly Demand Charge based on the Firm Contract Demand \nTransmission Service Amount (MW), as specified in Eligible Customer’s Service Agreement, \nwhich shall be determined as follows: \nMDC = FCDTSA X RTZ/12 \nWhere: \nMDC is the monthly demand charge \nFCDTSA is the Firm Contract Demand Transmission Service Amount (MW), as specified \nin Eligible Customer’s Service Agreement  \nRTZ is the rate for Network Integration Transmission Service from Attachment H for the \nZone in which the Eligible Customer’s Co-Located Load is located, stated in dollars per \nmegawatt per year.  For purposes of establishing the RTZ component in the relevant \nAttachment H, the annual peak of the Zone shall be based on the sum of Network Customer \nLoads in the Zone and Firm Contract Demand Transmission Service Amounts for all \nEligible Customers taking Firm Contract Demand Transmission Service in the Zone for \nthe applicable peak period. \n2) \nEligible Customers taking Firm Contract Demand Transmission Service in a Zone in which \nNetwork Integration Transmission Service rates are not established based on formula rates shall \npay a Monthly Demand Charge based on the Firm Contract Demand Transmission Service Amount \n(MW), as specified in Eligible Customer’s Service Agreement, multiplied by a Zonal-specific Firm \nContract Demand Transmission Service rate filed with FERC pursuant to Section 205 of the \nFederal Power Act.  Those rates will be posted on Transmission Provider’s website. \n3) \nRevenue Crediting.  Each month, credits will be applied to the Eligible Customer’s gross \nMonthly Demand Charge stated above associated with revenue collected from: (i) Grid Reliance \nCharges in accordance with Schedule [GRC]; and (ii) Non-Firm Contract Demand Transmission \nService Charges in accordance with Schedule [NFCD], based on each  Eligible Customer’s pro \nrata share of the Zone’s annual peak load, from the most recent 12-month period ending October \n31.  The Eligible Customer’s pro rata share shall be based on the ratio of its Firm Contract Demand \nTransmission Service Amount during the peak period to the sum of Network Customer Loads in \nthe Zone and Firm Contract Demand Transmission Service Amounts for all Eligible Customers \ntaking Firm Contract Demand Transmission Service in the Zone for the applicable peak period."},{"page":7,"startToken":1467,"endToken":1898,"text":"Exhibit No. PTO-0006 \nPage 7 of 17 \nThe sum of these revenue credits will appear as a reduction to the gross monthly rate stated above \non a Eligible Customer’s bill in that month for service under this schedule.   \n4) \nTransmission Enhancement Charges.  In addition to the rates set forth in section (1) of \nthis Schedule and any other applicable charges, the Eligible Customer shall also pay any \nTransmission Enhancement Charges for which it is designated as a Responsible Customer \nunder Schedule 12 appended to the Tariff. \n5)  \nDetermination of Monthly Charges for ComEd Zone.  On a monthly basis, revenue \ncredits shall be calculated based on the sum of ComEd's share of revenues collected during the \nmonth from: (i) the PJM Border Rate under Schedule 7; (ii) Network Integration Transmission \nService to Non-Zone \nNetwork \nLoad under Attachment \nH-A; \n(iii) \nSeams \nElimination \nCharge/Cost Adjustment/Assignment (“SECA”) revenues allocable to ComEd under the Tariff; \nand (iv) any Point-To-Point Transmission Service where the Point of Receipt and the Point of \nDelivery are both internal to the ComEd Zone.  On this basis, the sum of these revenues will appear \nas a reduction to the gross monthly rate stated above on a Transmission Customer’s1 bill in that \nmonth for service under this schedule. \n6)  \nDetermination of Monthly Charges for AEP Zone.  On a monthly basis, revenue credits \nshall be calculated based on the sum of AEP’s share of revenues collected during the month from: \n(i) the PJM Border Rate under Schedule 7; (ii) Network Integration Transmission Service to Non-\nZone Network Load under Attachment H-A; and (iii) Firm Point-To-Point Transmission \nService where the Point of Delivery is internal to the AEP Zone.  The sum of these revenue credits \nwill appear as an adjustment (reduction) to the gross monthly rate stated above on a Eligible \nCustomer's bill in that month for service under this schedule. \n7)  \nOther Supporting Facilities and Taxes.  In addition to the charges set forth in section (1) \nof this schedule, the Eligible Customer shall pay charges determined on a case-by-case basis for \nfacilities necessary to provide Transmission Service at voltages lower than those shown \nin Attachment H for the applicable Zone(s) and any amounts necessary to reimburse \nthe Transmission Provider for any amounts payable as sales, excise, \"Btu,\" carbon, value-added \nor similar taxes (other than taxes based upon or measured by net income) with respect to the \namounts payable pursuant to the Tariff.  \n1/ Transmission Customer is defined as an Eligible Customer that executes a Service Agreement, \nor requests PJM file an unexecuted Service Agreement, to receive transmission service under the \nTariff."},{"page":8,"startToken":1898,"endToken":2264,"text":"Exhibit No. PTO-0006 \nPage 8 of 17 \nSCHEDULE [NFCD] \nNon-Firm Contract Demand Service \nFor Co-Located Load \n1)\nEligible Customer taking Non-Firm Contract Demand Transmission Service in a Zone in \nwhich Network Integration Transmission Service rates are determined based on formula rates set \nforth in Attachment H shall pay for such service based on the amount of Non-Firm Contract \nDemand Transmission Service reserved by the Eligible Customer in MW, multiplied by the \nfollowing rates based on the reservation term: \nMonthly Rate ($/MW): Maximum of the Zonal Firm Contract Demand Transmission Rate (RTZ) \nas calculated pursuant to Schedule [FCD], divided by 12. \nWeekly Rate ($/MW): Maximum of the Zonal Firm Contract Demand Transmission Rate (RTZ) \nas calculated pursuant to Schedule [FCD], divided by 52. \nDaily On-Peak Rate1 ($/MW): Weekly Rate divided by 5. \nDaily Off-Peak Rate2 ($/MW): Weekly Rate divided by 7. \nHourly On-Peak Rate3 ($/MWh): Maximum of the Zonal Firm Contract Demand Transmission \nRate (RTZ) as calculated pursuant to Schedule [FCD], divided by 4160. \nHourly Off-Peak Rate4 ($/MWh): Maximum of the Zonal Firm Contract Demand Transmission \nRate (RTZ) as calculated pursuant to Schedule [FCD], divided by 8760. \n1/ Monday–Friday except the following holidays: New Years Day, Memorial Day, Independence \nDay, Labor Day, Thanksgiving Day, and Christmas Day. \n2/ Saturday and Sunday and the following holidays: New Years Day, Memorial Day, \nIndependence Day, Labor Day, Thanksgiving Day, and Christmas Day. \n3/ 7:00 a.m. up to the hour ending 11:00 p.m. \n4/ 11:00 p.m. up to the hour ending 7:00 a.m. \nThe Grid Reliance Charge charged to the Eligible Customer pursuant to Schedule [GRC] will be \nsubtracted from the Eligible Customer’s Non-Firm Contract Demand Transmission Service \nCharge on a MWh basis for each MWh of Non-Firm Contract Demand Service included in Eligible \nCustomer’s transmission service reservation. \n2) \nEligible Customers taking Non-Firm Contract Demand Transmission Service in a Zone in \nwhich Network Integration Transmission Service rates are not established based on formula rates \nshall pay for Non-Firm Contract Demand Transmission Service based on the amount of Non-Firm \nContract Demand Transmission Service reserved by the Eligible Customer in MW, multiplied by \nZonal-specific Non-Firm Contract Demand Transmission Service rates filed with FERC pursuant"},{"page":9,"startToken":2264,"endToken":2703,"text":"Exhibit No. PTO-0006 \nPage 9 of 17 \nto Section 205 of the Federal Power Act.  Those rates will be posted on Transmission Provider’s \nwebsite. \n3) \nDiscounts.  Three principal requirements apply to discounts for Non-Firm Contract \nDemand Transmission Service as follows: (1) any offer of a discount made by the Transmission \nProvider must be announced to all Eligible Customers solely by posting on the OASIS, (2) any \ncustomer-initiated requests for discounts (including requests for use by one’s wholesale merchant \nor an Affiliate’s use) must occur solely by posting on OASIS, and (3) once a discount is negotiated, \ndetails must be immediately posted on the OASIS.  For any discount agreed to by  Transmission \nProvider, Transmission Provider must offer the same discounted transmission service rate for the \nsame time period to all Eligible Customers taking Non-Firm Contract Demand Transmission \nService. \n4) \nTransmission Enhancement Charges.  In addition to the rates set forth in section (1) of \nthis Schedule and any other applicable charges, the Eligible Customer shall also pay any \nTransmission Enhancement Charges for which it is designated as a Responsible Customer \nunder Schedule 12 appended to the Tariff based on the Non-Firm Contract Demand Transmission \nService reserved by the Eligible Customer in MW. \n5) \nRevenue Crediting.  Revenues collected from Non-Firm Contract Demand Transmission \nService Charges shall be credited to Eligible Customers taking Network Integration Transmission \nService, Firm Contract Demand Transmission Service, and Firm Point-to-Point Transmission \nService based on each Eligible Customer’s pro rata share of the Zone’s annual peak load based on \nthe most recent 12-month period ending October 31.  The Eligible Customer’s pro rata share shall \nbe based on the ratio of its Zone Network Load or Firm Contract Demand Transmission Service \nAmount to the sum of Network Customer Loads in the Zone and Firm Contract Demand \nTransmission Service Amounts for all Eligible Customers taking Firm Contract Demand \nTransmission Service in the Zone, for the applicable peak period.  The sum of these revenue credits \nwill appear as a reduction to the gross monthly rate for Firm Contract Demand Transmission \nService on a Eligible Customer’s bill in that month. \n6) \nOther Supporting Facilities and Taxes.  In addition to the charges set forth in section (1) \nof this schedule, the Eligible Customer shall pay charges determined on a case-by-case basis for \nfacilities necessary to provide Transmission Service at voltages lower than those shown \nin Attachment H for the applicable Zone(s) and any amounts necessary to reimburse \nthe Transmission Provider for any amounts payable as sales, excise, “Btu,” carbon, value-added \nor similar taxes (other than taxes based upon or measured by net income) with respect to the \namounts payable pursuant to the Tariff."},{"page":10,"startToken":2703,"endToken":3090,"text":"Exhibit No. PTO-0006 \nPage 10 of 17 \nSCHEDULE [GRC] \nGrid Reliance Charge for  \nFirm and Non-Firm Contract Demand Service \nFor Co-Located Load \nEligible Customers taking Firm Contract Demand Transmission Service and Non-Firm Contract \nDemand Transmission Service shall pay the Grid Reliance Charge for the Zone in which the Point \nof Delivery for the Eligible Customer’s Co-Located Load is located. \n1)  \nFor Zones in which Transmission Owners in which the Network Integrated Transmission \nService charge is set pursuant to a formula rate, the Grid Reliance Charge shall be an annual charge \nequal to the Zonal Grid Reliance Rate multiplied by the difference between the Eligible \nCustomer’s Co-Located Gross Demand and its Firm Contract Demand Transmission Service \nAmount, both as specified in its service agreement for Firm Contract Demand Service.  For those \nZones that include multiple Transmission Owners or Transmission Owners with multiple formula \nrate revenue requirements that comprise the total Zonal Rate, the inputs from each relevant formula \nrate revenue requirement and components thereof will be aggregated to determine the \nTransmission Owners relevant expenses and costs used as inputs to the Zonal Grid Reliance Rate, \nas set forth below. \nFor each such Zone, the Zonal Grid Reliance Rate shall be calculated as: \n(The Zonal Network Integration Transmission Service Rate X the Grid Reliance Fixed Percentage \nAllocator) X the Zonal Grid Reliance Demand Adjustment Ratio. \nWhere: \nThe Zonal Network Integration Transmission Service Rate shall equal the rate for Network \nIntegration Transmission Service set forth in Attachment H for the Zone with which the Co-\nLocated Load is interconnected, stated in dollars per megawatt per year. \nThe Grid Reliance Charge Fixed Percentage Allocator shall be calculated as follows: \nThe Grid Reliance Charge Fixed Percentage Allocator shall be a percentage value \ncalculated as the average of all TO GRC Revenue Requirement Percentages \nTO GRC Revenue Requirement Percentage = TO GRC Revenue Requirement / TO Net \nRevenue Requirement \nTO GRC Revenue Requirement = [TO GRC Transmission O&M Percentage X TO \nTransmission O&M Expense] + [TO GRC Depreciation Expense] \nThe TO GRC Transmission O&M Percentage shall be determined for each Transmission \nOwner in PJM for which FERC Form No. 1 account-level data is publicly available, and \nshall be equal to the amounts in FERC accounts 561-564 and 570-572 set forth in the \nTransmission Owner’s most recently published FERC Form No. 1, divided by the"},{"page":11,"startToken":3090,"endToken":3570,"text":"Exhibit No. PTO-0006 \nPage 11 of 17 \nTransmission Owner’s transmission operations and maintenance amount contained in its \nmost recently published FERC Form No. 1. \nThe TO GRC Transmission O&M Expense shall be determined for each Transmission \nOwner in PJM, and is equal to the transmission operations and maintenance expense \nportion of the Transmission Owner’s revenue requirement determined based on its \nAttachment H formula rate template, as published in its most recent annual update. \nThe TO GRC Depreciation Expense shall be determined for each Transmission Owner in \nPJM and shall be equal to the transmission depreciation expense portion of the \nTransmission Owner’s revenue requirement determined based on its Attachment H formula \nrate template, as published in its most recent annual update. \nThe TO GRC Revenue Requirement Percentage shall be determined for each Transmission \nOwner in PJM and shall be equal to the Transmission Owner’s GRC Revenue Requirement \ndivided by the Transmission Owner’s net transmission revenue requirement determined \nbased on its Attachment H formula rate template, as published in its most recent annual \nupdate. \nThe Grid Reliance Fixed Percentage Allocator shall initially be calculated as of the effective date \nof this Schedule, and will be published on the Transmission Provider’s website.   \nThe Grid Reliance Fixed Percentage Allocator will be updated by the Transmission Provider \nbeginning with the first January 1 falling after the fifth anniversary of the effective date and every \nsubsequent fifth anniversary of the most recent update thereafter.  No later than November 1 prior \nto the update effective date, each Transmission Owner will provide to the Transmission Provider \nthe information required to determine the Grid Reliance Fixed Percentage Allocator.  No later than \nthe following December 1, the Transmission Provider shall post on its website and in an \ninformation filing with FERC, the updated Grid Reliance Fixed Percentage Allocator including \nthe information used to determine the Grid Reliance Fixed Percentage Allocator.  The updated \nGrid Reliance Charge for each Transmission Owner will become effective on the same date that \nits Network Integrated Transmission Service Charge is updated in the year following the update \nof the Grid Reliance Fixed Percentage Allocator.  \nThe Zonal Grid Reliance Demand Adjustment Ratio shall be calculated as the ratio of the Zonal \ndemand used to determine Network Integration Transmission Service and Firm Contract Demand \nTransmission Service rates to the sum of this Zonal demand amount plus the Co-Located Gross \nDemand in excess of Firm Contract Demand for all Co-Located Load being served by Firm \nContract Demand Transmission Service in the Zone. \n2)  \nFor Zones in which Transmission Owners charge for Network Integrated Transmission \nService is not based on a formula rate, the Grid Reliance Charge shall be specified in a separate \nrate schedule to be filed by the Zonal Transmission Owner and to be effective on the same date as \nthis Schedule [GRC] and updated each time such Transmission Owner updates its Network \nIntegrated Transmission Service charge."},{"page":12,"startToken":3570,"endToken":3654,"text":"Exhibit No. PTO-0006 \nPage 12 of 17 \n3) \nRevenues collected from Grid Reliance Charges shall be credited to Eligible Customers \ntaking Network Integration Transmission Service, Firm Contract Demand Transmission Service, \nand Firm Point-to-Point Transmission Service, based on each Eligible Customer’s pro rata share \nof the Zone’s annual peak load from the most recent 12-month period ending October 31.  The \nsum of these revenue credits will appear as a reduction to the gross monthly rate for service on an \nEligible Customer’s bill in that month."},{"page":13,"startToken":3654,"endToken":4002,"text":"Exhibit No. PTO-0006 \nPage 13 of 17 \nSCHEDULE [FP] \nFinancial Penalty Charge for  \nUnreserved Use by Co-Located Load \nAn Eligible Customer taking Firm Contract Demand Transmission Service, Non-Firm Contract \nDemand Transmission Service, or Interim Network Integration Transmission Service on behalf of \nCo-Located Load shall be subject to financial penalties for its unreserved use of the transmission \nsystem. \nThe financial penalty charge for unreserved use shall include two components: (1) a base penalty \ncharge, which applies to each individual hour in which the reserved transmission service limit is \nexceeded, and (2) a penalty ratchet, which applies when such exceedances occur repeatedly. \nBase Penalty Charge \nWhen an Eligible Customer taking service on behalf of Co-Located Load exceeds its reserved \ntransmission service limit, a base penalty charge shall be assessed for any hour in which at least \none five-minute interval occurs during which the Eligible Customer’s telemetered load at the Point \nof Delivery exceeds its reserved transmission service limit.  This five-minute interval is defined as \nan Exceedance Interval, and such an hour is defined as an Exceedance Hour.  The base penalty \ncharge shall apply to each Exceedance Hour.   \nFor an Eligible Customer taking only Firm Contract Demand Transmission Service, the \nreserved transmission service limit shall equal the Firm Contract Demand Transmission \nService minus any curtailed MW.   \nFor an Eligible Customer taking only Non-Firm Contract Demand Transmission Service, \nthe reserved transmission service limit shall equal the approved Non-Firm Contract \nDemand Transmission Service minus any curtailed MW.   \nFor an Eligible Customer taking Firm Contract Demand and Non-Firm Contract Demand \nTransmission Services, the reserved transmission service limit shall equal the Firm \nContract Demand Transmission Service plus the approved Non-Firm Contract Demand \nTransmission Service minus any curtailed MW.   \nFor an Eligible Customer taking Interim Network Integration Transmission Service, the \nreserved transmission service limit shall equal the Interim Network Integration \nTransmission Service demand minus any curtailed MW. \nEach five-minute interval beginning with the first minute of each hour shall constitute a \nseparate interval and each hour from 0100 through 2400 shall constitute a separate hour for \npurposes of determining whether one or more exceedances have occurred."},{"page":14,"startToken":4002,"endToken":4305,"text":"Exhibit No. PTO-0006 \nPage 14 of 17 \nThe base penalty charge shall be applied to each Exceedance Hour and shall be calculated as: \nHourly Exceedance MW × Equivalent Hourly Firm Contract Demand (“FCD”) rate × \nnumber of Exceedance Intervals within the hour \nWhere: \nHourly Exceedance MW = Maximum telemetered load during the hour – Reserved \nTransmission Service Limit for the hour \nEquivalent Hourly FCD rate = FCD rate / 8,760 hours \nPenalty Ratchet \nA penalty rachet shall apply when multiple Exceedance Hours occur during a particular time period \nin order to escalate the penalty charges as the frequency of unreserved transmission use increases.   \nIf more than one Exceedance Hour occurs on the same calendar day, an additional daily \npenalty shall apply.   \nIf exceedances occur on multiple calendar days within the same calendar week, an \nadditional weekly penalty shall apply.  \nIf exceedances occur in multiple calendar weeks within the same calendar month, an \nadditional monthly penalty shall apply. \nIf exceedances occur in multiple calendar months within the same calendar year, an \nadditional yearly penalty shall apply.   \nThe penalty ratchet shall be based on an Eligible Customer’s exceedance pattern and applies \nescalating FCD-equivalent rates as the frequency of unreserved transmission use increases.  \nDepending on whether exceedances occur within the same calendar day, calendar week, calendar \nmonth, or calendar year, the penalty ratchet shall apply daily, weekly, monthly, or annual penalty \ncharges, respectively, as follows:  \nExceedance Pattern \n \nPenalty Rate Applied \nMultiple Exceedance Hours in a single calendar day  \nDaily FCD-Equivalent Rate \nMultiple Exceedance Days within a calendar week  \nWeekly FCD-Equivalent Rate \nMultiple Exceedance Weeks within a calendar month \nMonthly FCD-Equivalent Rate \nMultiple Exceedance Months within a calendar year  \nFCD Annual Rate \nDaily Penalty Charge \nThe Daily Penalty Charge is calculated as: \nMaximum Hourly Exceedance MW during the calendar day \n× Daily FCD Equivalent Rate \n× Number of Exceedance Hours in the calendar day"},{"page":15,"startToken":4305,"endToken":4550,"text":"Exhibit No. PTO-0006 \nPage 15 of 17 \nWeekly Penalty Charge \nThe Weekly Penalty Charge is calculated as: \nMaximum Hourly Exceedance MW during the calendar week \n× Weekly FCD Equivalent Rate \n× Number of Exceedance Days in the calendar week \nMonthly Penalty Charge \nThe Monthly Penalty Charge is calculated as: \nMaximum Hourly Exceedance MW during the calendar month \n× Monthly FCD Equivalent Rate \n× Number of Exceedance Weeks in the calendar month \nAnnual Penalty Charge \nThe Annual Penalty Charge is calculated as: \nMaximum Hourly Exceedance MW during the calendar year \n× Annual FCD Rate \n× Number of Exceedance Months in the calendar year \nRevenues collected from Financial Penalty Charges shall be credited to Eligible Customers taking \nNetwork Integration Transmission Service and Firm Contract Demand Transmission Service.  The \nTransmission Provider shall return revenues collected from Financial Penalty Charges on a \nmonthly and annual basis as bill credits to Eligible Customers taking Network Integration \nTransmission Service and Firm Contact Demand Service, who were not assessed Financial Penalty \nCharges during the year based on each Eligible Customer’s pro rata share of the Zone’s annual \npeak load based on the most recent 12-month period ending October 31.  The Eligible Customer’s \npro rata share shall be based on the ratio of its Zone Network Load or Firm Contract Demand \nTransmission Service Amount to the sum of Network Customer Loads in the Zone and Firm \nContract Demand Transmission Service Amounts for all Eligible Customers taking Firm Contract \nDemand Transmission Service in the Zone, for the applicable peak period."},{"page":16,"startToken":4550,"endToken":4726,"text":"Exhibit No. PTO-0006 \nPage 16 of 17 \nRedlines to PJM OATT, Schedule 12\nSCHEDULE 12 \nTransmission Enhancement Charges \n*** \n(viii) FERC Filing. Within 30 days of the approval of each Regional Transmission \nExpansion Plan or an addition to such plan by the PJM Board pursuant to Operating Agreement, \nSchedule 6, section 1.6, the Transmission Provider shall designate in the Tariff, Schedule 12-\nAppendix A and in a report filed with the FERC the Responsible Customers customers using Point-\nto-Point Transmission Service and/or Network Integration Transmission Service and Merchant \nTransmission Facility owners that will be subject to each such Transmission Enhancement Charge \n(“Responsible Customers”) based on the cost responsibility assignments determined pursuant to \nthis Schedule 12. Those customers designated by the Transmission Provider as Responsible \nCustomers shall have 30 days from the date the filing is made with the FERC to seek review of \nsuch designation. Such cost responsibility designations shall be the same as those made for the \nrelevant Regional Facility, Necessary Lower Voltage Facility, or Lower Voltage Facility in the \nRegional Transmission Expansion Plan."},{"page":17,"startToken":4726,"endToken":4826,"text":"Exhibit No. PTO-0006 \nPage 17 of 17 \nRedlines to PJM OATT, Part I, Section 1 (Definitions)\nResponsible Customer: \n“Responsible Customer” shall mean customers using Interim Network Integration Transmission \nService, Firm Contract Demand Transmission Service, Non-Firm Contract Demand Transmission \nService, Point-to-Point Transmission Service and/or Network Integration Transmission Service \nand Merchant Transmission Facility owners, which are assigned cost responsibility for \nTransmission Enhancement Charges as determined pursuant to Tariff, Schedule 12. \nCo-Located Gross Demand: \n“Co-Located Gross Demand” consists of the gross demand for a Co-Located Load facility, as \nspecified in the applicable Service Agreement Contract Demand Transmission Service for Co-\nLocated Load."}],"sections":[{"p":1,"at":0,"title":"Pages 1 to 4","method":"page range","endPage":5,"endAt":0,"startToken":0,"endToken":740},{"p":5,"at":0,"title":"Pages 5 to 8","method":"page range","endPage":9,"endAt":0,"startToken":740,"endToken":2264},{"p":9,"at":0,"title":"Pages 9 to 12","method":"page range","endPage":13,"endAt":0,"startToken":2264,"endToken":3654},{"p":13,"at":0,"title":"Pages 13 to 16","method":"page range","endPage":17,"endAt":0,"startToken":3654,"endToken":4726},{"p":17,"at":0,"title":"Page 17","method":"page range","endPage":17,"endAt":780,"startToken":4726,"endToken":4826}]}