{"document":{"slug":"rec-20260424-5312","title":"Reply Brief of the Indicated PJM Transmission Owners","issued":"2026-04-24","accession":"20260424-5312","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Indicated PJM Transmission Owners","kind":"brief","file":"sources/filings/text/20260424-5312_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260424-5312","tier":"record","sha256":"a74519a63be4a119028b416c08013e40ec3ef798a655235a30b2dbbc3fe561a5","pages":34,"tokens":10234,"emptyPages":[],"textThemes":["colo","flex","study","cost"]},"pages":[{"page":1,"startToken":0,"endToken":340,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et al.  \n )  \nDocket No. EL25-49-000 \n )  \nDocket No. EL25-49-001 \n ) \nLarge Loads Co-Located at Generating Facilities ) \nDocket No. AD24-11-000 \n ) \nConstellation Energy Generation, LLC  \n \n )  \nDocket No. EL25-20-000 \nv.  \n \n ) \nPJM Interconnection, L.L.C.  \n )  \n(Consolidated) \nREPLY BRIEF OF  \nTHE INDICATED PJM TRANSMISSION OWNERS \nPursuant to the Commission’s December 18, 2025 order in PJM Interconnection, L.L.C., \n193 FERC ¶ 61,217, at P 193 (2025) (“Order”), the Indicated PJM Transmission Owners \n(collectively, the “PJM Transmission Owners”)1 submit this reply brief to parties’ responses to the \ninitial briefs filed by PJM Interconnection, L.L.C. (“PJM Initial Brief”) and the PJM Transmission \nOwners (“PJM Transmission Owners Initial Brief”) on February 23, 2026 in the above-captioned \nproceedings. \n1\nFor the purpose of this filing, the Indicated PJM Transmission Owners are: American Electric Power Service \nCorporation on behalf of its affiliates, Appalachian Power Company, Indiana Michigan Power Company, Kentucky \nPower Company, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian \nTransmission Company, AEP Indiana Michigan Transmission Company, AEP Kentucky Transmission Company, \nAEP Ohio Transmission Company, and AEP West Virginia Transmission Company; The Dayton Power and Light \nCompany d/b/a AES Ohio; Dominion Energy Services, Inc. on behalf of Virginia Electric and Power Company d/b/a \nDominion Energy Virginia; Duke Energy Business Services, LLC for Duke Energy Kentucky, Inc. and Duke Energy \nOhio, Inc.; Duquesne Light Company; East Kentucky Power Cooperative; Exelon Corporation on behalf of its \naffiliates Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, \nCommonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and \nPotomac Electric Power Company; FirstEnergy Service Company, on behalf of its affiliates American Transmission \nSystems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, The \nPotomac Edison Company, Monongahela Power Company, Keystone Appalachian Transmission Company, and \nTrans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Companies”); PPL Electric Utilities \nCorporation; Public Service Electric and Gas Company; Rockland Electric Company; and the Southern Maryland \nElectric Cooperative."},{"page":2,"startToken":340,"endToken":673,"text":"2 \nI.\nINTRODUCTION \nThe PJM Transmission Owners’ proposals in this proceeding are grounded in two main \nprinciples: (1) rates for the new services must be consistent with longstanding cost allocation \nprinciples, and (2) the new services must be implemented in a manner that does not compromise \nsystem reliability.  Co-Located Load2 customers must pay their fair share of transmission system \ncosts, including those related to the benefits of being connected and synchronized with the \nextensive PJM Transmission System.  Otherwise, other ratepayers will be forced to subsidize Co-\nLocated Load customers.  Additionally, reliability must be a key consideration of these new \nservices, not a secondary issue or afterthought.  Co-Located Loads will be fully connected and \nsynchronized with the transmission system, and can have serious impacts on the system.  The \nlaudable goals of promoting speed to power and economic efficiency for data centers and other \nlarge load customers will not be well-served by implementing new transmission services in a \nmanner that results in significant risks and uncertainty around the ongoing reliability of the system.  \nMoreover, such a result risks undermining continued reliable service to existing customers.   \nIn this reply brief, the PJM Transmission Owners respond to a number of issues raised with \nrespect to PJM’s proposed non-rate terms and conditions for the three new transmission services \nand their rate proposals for the new transmission services.  The PJM Transmission Owners express \nsupport for PJM’s proposed scope of the new transmission services, on the basis that they provide \nreasonable flexibility to Co-Located Load customers while recognizing the need to implement \nthese new services in a reliable fashion.  They also respond to criticisms of PJM’s proposed study \nprocess, pointing out the important role that PJM Transmission Owners will continue to play with \nrespect to conducting load-related studies, and explaining why allegations of potential PJM \n2\nAll capitalized terms that are not otherwise defined herein shall have the meaning set forth in the PJM Open \nAccess Transmission Tariff or Amended and Restated Operating Agreement of PJM Interconnection, L.L.C."},{"page":3,"startToken":673,"endToken":965,"text":"3 \nTransmission Owner discrimination are without merit.  The PJM Transmission Owners emphasize \nthe importance of PJM’s strong operational penalties given the potential for large amounts of load \nto be secured from causing adverse system impacts based on the correct operation of control \ntechnologies and protection systems and provide further detail on their proposal for \ncomplementary financial penalties. \nThe PJM Transmission Owners also address criticisms of their rate proposals for the new \ntransmission services.  Specifically, the PJM Transmission Owners rebut claims that their proposal \nto set the maximum rate for Non-Firm Contract Demand Service at the rate for Firm Contract \nDemand Service is unjust and unreasonable, explaining the superiority of this service relative to \nthe existing Non-Firm Point-to-Point product and the need for further analysis prior to offering \nany rate discounts.  The PJM Transmission Owners further explain why their proposal for a Grid \nReliance Charge is just and reasonable and consistent with cost allocation principles, given the \nbenefits that the ongoing safe operation of the transmission system will provide to all Co-Located \nLoad, regardless of on-site generation.    \nII.\nRESPONSE TO COMMENTS RELATED TO PJM’S PROPOSED TERMS AND \nCONDITIONS FOR THE NEW TRANSMISSION SERVICES \nA.\nPJM has Appropriately Defined the Scope of Contract Demand and Interim \nNetwork Integration Transmission Services \nThe PJM Transmission Owners support PJM’s proposals regarding the scope of Firm and \nNon-Firm Contract Demand Services and Interim Network Integration Transmission Service \n(“NITS”), including PJM’s proposal to restrict the use of Non-Firm Contract Demand Service to \nperiods when on-site generation is on outage.3  In particular, the PJM Transmission Owners agree \nwith PJM that Non-Firm Contract Demand Service is intended by the Commission to be a limited \n3\nPJM Initial Brief, Docket Nos. EL25-49, et al., Attachment B at P 17 (“Abdulsalam Affidavit”)."},{"page":4,"startToken":965,"endToken":1323,"text":"4 \nservice and is not a substitute for Firm Contract Demand Service or NITS for the portion of on-\nsite load that will not be served by on-site generation. \nContrary to commenters’ assertions, there simply is no compelling reason for PJM not to \nrestrict Non-Firm Contract Demand Service to periods where a Co-Located generating facility is \non outage merely because the Commission did not limit the usage of Non-Firm Contract Demand \nService to outages.4  Nor do commenters provide a compelling basis for Non-Firm Contract \nDemand Service to be available during non-outage conditions.  In the Order, the Commission \nexplained that Non-Firm Contract Demand Service is intended to be an option for Eligible \nCustomers seeking to use the transmission system on behalf of Co-Located Load in a more limited \nmanner when on-site generation is not available to serve load.5\nLimiting the use of Non-Firm Contract Demand Service is also necessary to ensure the \nreliable operation of the PJM transmission system, especially because PJM and the PJM \nTransmission Owners will be relying on increased uses of Special Protection Schemes (“SPS”), \nRemedial Action Schemes (“RAS”), and other control technologies and protective systems to \nensure that on-site load that is not being planned from a transmission expansion or capacity \nstandpoint can be operated reliably.  As PJM witness Dr. Sami Abdulsalam explains in his affidavit \naccompanying PJM’s Initial Brief, there are numerous operational and planning challenges \nassociated with implementing Non-Firm Contract Demand Service.6  For instance, transmission \n4\nReply Brief of Constellation Energy Generation, LLC, Docket Nos. EL25-49, et al., at 10-12 (filed Mar. 25, \n2026) (“Constellation”); Reply Brief of Advanced Energy United and the Solar Energy Industries Association, Docket \nNos. EL25-49, et al., at 3, 5-10 (filed Mar. 25, 2026); Reply Comments of Vistra Corp., Docket Nos. EL25-49, et al., \nat 25-26 (filed Mar. 25, 2026); Reply Brief of Eolian, L.P.; Antora Energy, Inc.; Calibrant Energy; Convergent Energy \nand Power; Mainspring Energy, Inc.; U.S. Energy Storage Coalition; and Verrus, LLC, Docket Nos. EL25-49, et al., \nat 6-7 (filed Mar. 25, 2026) (collectively, the “Joint Developers”).   \n5\nOrder at P 214. \n6\nPJM Initial Brief, Abdulsalam Affidavit at PP 9-12."},{"page":5,"startToken":1323,"endToken":1623,"text":"5 \nfacilities serving large loads will likely have multiple feeders serving load, which will require \nprotection systems with multiple measurements, logics and significant flexibility, adding \ncomplexity and reducing the reliability and overall security of the system.7  PJM witness Matthew \nWharton provides further details regarding the operational complexities associated with \nimplementing RASs.8  As Mr. Wharton explains, there is the possibility of interactions between \nRAS in a tightly coupled network such as PJM, increasing the possibility of misoperations.9  Mr. \nWharton’s testimony details an incident where a failed lighting arrestor on a 230 kV transmission \nsystem led to the loss of 1,500 MW within the PJM region at multiple substations, which highlights \nthe risk of having multiple RASs within a single area.10\nGiven these risks and challenges, Non-Firm Contract Demand Service cannot become a \ngeneral substitute for firm service types such as NITS or Firm Contract Demand Service for load \nthat is not intended or designed to be served from on-site generation under normal (i.e., non-\noutage) operating conditions.  Instead, Non-Firm Contract Demand Service should be limited to a \nsupplemental service intended to provide as-available transmission capacity when such on-site \ngeneration is on outage.  This approach will properly balance flexibility for Co-Located Load \ncustomers to obtain needed firm or non-firm service depending on their mix of on-site load and \ngeneration, with the obligation to ensure that the system can continue to be operated reliably for \nthe benefit of all customers. \nIn its Initial Brief and illustrative tariff records (“Illustrative Tariff”), PJM refers generally \nto “outages” and being “on outage” without further explanation.  PJM should clarify in any \n7\nId. at P 11. \n8\nPJM Initial Brief, Attachment C at PP 15-26 (“Wharton Affidavit”). \n9\nPJM Initial Brief, Wharton Affidavit at PP 20-22. \n10\nId. at P 21."},{"page":6,"startToken":1623,"endToken":1930,"text":"6 \neffective tariff records that, for purposes of obtaining Non-Firm Contract Demand Service, an \n“outage” is limited to periods where a generator is offline due to a breakdown or maintenance \nissues, and does not cover other instances when a generator is not operating, such as when \nintermittent generation resources are unable to produce; when a co-located battery has depleted its \navailable energy; or when a natural gas generator is unable to secure fuel. \nB.\nPJM Appropriately did not Propose Changes to the Definition of Eligible \nCustomer \nIn their comments, Invenergy Renewables LLC and Invenergy Thermal LLC (together, \n“Invenergy”) request clarification on how the Commission and PJM view the definition of Eligible \nCustomer in the PJM Open Access Transmission Tariff (“Tariff”) when applied to the co-located \ngenerator and co-located load.11  Specifically, whether a co-located generator would qualify as an \nEligible Customer on behalf of a Co-Located Load, and whether a co-located generator’s status as \nan Eligible Customer depends on whether the co-location arrangement is in a jurisdiction that has \nmandated retail choice.12\nIn its Initial Brief, PJM appropriately proposed no changes to the definition of Eligible \nCustomer.  PJM’s definition of Eligible Customer is essentially identical to the definition \ncontained in the Commission’s pro forma Open Access Transmission Tariff.  Under that definition, \nan Eligible Customer can be an electric utility, a federal power marketing agency, or any person \ngenerating electric energy for sale for resale (i.e., making wholesale sales), as well as a retail \ncustomer taking unbundled transmission service pursuant to a state unbundling requirement.13  The \n11\nComments of Invenergy Renewables LLC and Invenergy Thermal LLC, Docket Nos. EL25-49, et al., at 5-\n6 (filed Mar. 16, 2026). \n12\nId. at 5-6. \n13\nSee FERC Pro Forma Open Access Transmission Tariff, definition of “Eligible Customer”; see also PJM \nTariff, Section 1, definition of ”Eligible Customer.”"},{"page":7,"startToken":1930,"endToken":2347,"text":"7 \nanswer to Invenergy’s questions would presumably depend on an individual co-located generator’s \nspecific factual circumstances.  However, it seems unlikely that a co-located generator (as opposed \nto the load) would meet the definition of an Eligible Customer for purposes of obtaining Contract \nDemand Service.  The generator likely would not be seeking to procure transmission service in \norder for it to serve the on-site load, and instead would be selling its output directly to the on-site \nload at retail (or to its state licensed supplier).14  The ability of a Co-Located Load, or an entity \nrepresenting the load, to qualify as an Eligible Customer would necessarily depend on whether the \njurisdiction in which it is located has adopted retail choice, and the related criteria adopted by the \nstate.  This is because the Commission does not assert jurisdiction over bundled sales and under \nSection 212(h), the Commission cannot mandate retail wheeling.15\nC.\nThe Commission Should not Mandate a Combined Interconnection and \nTransmission Study Process for Co-Located Loads and Generation \nInvenergy argues that the Commission and PJM should clarify how transmission and \ngenerator interconnection study processes can work in tandem.16  In Invenergy’s view, developers \nand lenders will be reluctant to commit to projects without both sets of study results showing that \nthe project is viable and identifying expected upgrade costs, and coordinated studies would better \n14\nEven if a co-located generator did qualify as an Eligible Customer, the PJM Transmission Owners caution \nthe Commission not to create incentives for existing generators to exit the system in order to exclusively serve large \nloads.  The solution to capacity shortfall situations such as currently exists in PJM cannot be to simply to move the \noutput of existing resources to serve new large loads at the expense of existing loads.    \n15\nSee 16 U.S.C. § 824k(h); see also Promoting Wholesale Competition Through Open Access Non-\nDiscriminatory Transmission Servs. by Pub. Utils.; Recovery of Stranded Costs by Pub. Utils. and Transmitting Utils., \nOrder No. 888, FERC Stats. & Regs. ¶ 31,036 (1996) (cross-referenced at 75 FERC ¶ 61,080), on reh’g, Order No. \n888-A, FERC Stats. & Regs. ¶ 31,048 (cross-referenced at 78 FERC ¶ 61,220), on reh’g, Order No. 888-B, 81 FERC \n¶ 61,248 (1997), on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom., Transmission \nAccess Pol’y Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom., N.Y. v. FERC, 535 U.S. 1 (2002). \n16\nInvenergy at 2-5."},{"page":8,"startToken":2347,"endToken":2642,"text":"8 \nalign generation and load, improve efficiency, reduce system costs, and provide the certainty \nneeded for co-location projects to be financed and developed at scale.17\nIt is unclear what Invenergy is asking for here, but to the extent it is requesting a combined \ntransmission and interconnection study process for Co-Located Load and generation, the \nCommission should decline.  PJM’s Initial Brief already sets forth a coordinated load and \ngeneration study process, with the PJM Transmission Owners conducting load integration studies \nand PJM performing generator interconnection and transmission service studies, when necessary.  \nAs the PJM Transmission Owners explain in their March 25, 2026, joint response to PJM’s Initial \nBrief, they are fully committed to continuing to work closely and collaboratively with PJM, as \nthey do today on numerous matters, to ensure that large loads can be quickly and efficiently \ninterconnected.18  In addition, the study process will be maximally efficient if the PJM \nTransmission Owners conduct load integrating studies first to ensure that the load additions can \nbe reliably interconnected to the grid, which would then inform PJM’s generator interconnection \nand transmission service studies.19  Conducting load integration studies first will help avoid \npotential duplication of effort and expenses between PJM and the PJM Transmission Owners.20\nFurthermore, requiring PJM to adopt a single study process goes well beyond the issues set \nfor hearing by the Commission in the Order.  PJM and the PJM Transmission Owners have \nproposed a just and reasonable process for conducting the appropriate studies and ensuring they \nare completed quickly and efficiently, consistent with the Commission’s directives in the Order.  \n17\nId. at 4. \n18\nSee Joint Response of the PJM Transmission Owners, Docket Nos. EL25-49, et al., at 6 (filed Mar. 25, 2026). \n19\nId. at 6-7. \n20\nId. at 7."},{"page":9,"startToken":2642,"endToken":2933,"text":"9 \nThere is no reason for the Commission to entertain proposals that go beyond those directives, such \nas requiring a single study process for Co-Located Loads. \nMoreover, regardless of the study process ultimately adopted by PJM, it cannot be ignored \nor sidestepped that end-use load is still retail load and governed by existing load interconnection \nrules set forth in state jurisdictional tariffs and agreements.  There is no need for the Commission \nto entangle itself in questions regarding the division between its jurisdiction over interstate \ntransmission matters and state jurisdiction over retail service in this proceeding.  The coordinated \nstudy approach proposed by PJM will provide a just and reasonable opportunity for Co-Located \nLoad to interconnect and assess the appropriate type and level of transmission service that the \ncustomer wishes to obtain.  The PJM Transmission Owners commit to continue working closely \nwith PJM to ensure the study process remains efficient and identifying any process improvements \nneeded to do so. \nD.\nPJM’s Study Proposal Does not Promote Discrimination Against Co-Located \nLoad Customers \nCertain commenters assert that PJM’s study procedures for the new transmission services \nare too broad, lack detail, and do not address the terms and conditions for these new services with \nsufficient detail, clarity or consistency.21  The same commenters contend that the study procedures \nallow PJM and the PJM Transmission Owners too much discretion, which could result in delays \nand undue discrimination.22\nWhile more detail regarding the study process for new transmission services, such as the \nrelevant steps in the process, associated timelines for studies, and study fees, may be helpful, \ncommenters’ concerns are overstated.  This is particularly true with respect to accusations that the \n21\nConstellation at 14-15; Vistra at 32, 37-38. \n22\nConstellation at 15-18; Vistra at 32-36, 38."},{"page":10,"startToken":2933,"endToken":3310,"text":"10 \nPJM Transmission Owners will use the study process to discriminate against Co-Located Load or \nto deny co-location arrangements, or that references PJM Transmission Owner criteria as being \ninsufficient.23\nPJM’s Illustrative Tariff language appropriately provides that Transmission Owners will \nplay a key role in this study process.  Transmission Owners will continue to have the responsibility \nfor performing load integration studies related to the interconnection of any new or modified Co-\nLocated Loads.24  Moreover, the design of any control technologies and protection systems will \nneed to be closely coordinated with Transmission Owners in order to ensure they meet both PJM \nand PJM Transmission Owner criteria, as well as North American Electric Reliability Corporation \n(“NERC”) requirements.25  Given these considerations, it is appropriate and sufficient only to \nreference the need to incorporate each Transmission Owner’s related technical requirements in the \nTariff.  Consistent with the Commission’s rule of reason,26 the Tariff need not include details of \neach Transmission Owner’s requirements.  The reference to studies conducted by the Transmission \nOwners that PJM will consider inherently must refer to the studies Transmission Owners will \nconduct in order to integrate load facilities.  The PJM Transmission Owners do not, however, \noppose making this explicit in the Tariff. \n23\nFor instance, Vistra notes that for Firm Contract Demand Service, PJM and the Transmission Owner “shall \ncoordinate to study the effects” of providing service on the Transmission Owner’s system “pursuant to the applicable \naffected Transmission Owner requirements,” but states it is unclear what those requirements would be or where they \nare located.  Vistra at 33. \n24\nPJM Initial Brief, Attachment A at Section 710.3. \n25\nPJM Initial Brief at 60; see also infra Section II.E & n. 31. \n26\nSee, e.g., City of Cleveland v. FERC, 773 F.2d 1368, 1376 (D.C. Cir. 1985) (explaining that the rule of reason \nrequires that tariffs include practices that “affect rates and services significantly,” “are realistically susceptible of \nspecification,” and “are not so generally understood in any contractual arrangement as to render recitation \nsuperfluous”); Hectate Energy Greene Cnty. 3 LLC v. FERC, 72 F.4th 1307, 1314 (D.C. Cir. 2023) (“[E]ven \nspecifiable practices that significantly affect rates need not be included if they are clearly implied by the tariff’s express \nterms.”)."},{"page":11,"startToken":3310,"endToken":3599,"text":"11 \nClaims that the PJM Transmission Owners will use their role in the study process and \n“natural monopoly market power” to delay and deny co-location arrangements or otherwise \ndiscriminate against Co-Located Load27 are baseless and speculative.  Contrary to Constellation’s \nassertions, there is no basis to simply assume that any PJM Transmission Owner would work to \nfrustrate the intent of Commission-accepted tariff provisions.  Likewise, it is illogical that PJM \nTransmission Owners would have an incentive, financial or otherwise, to discriminate against Co-\nLocated Loads in studying such arrangements, as any delay in implementing new Co-Located \nLoads will simply mean fewer retail and transmission customers on the system to be served by \nTransmission Owners.  Likewise, it makes no sense that the PJM Transmission Owners would \neschew available tools, such as Co-Located Load arrangements, to the extent those arrangements \nsupport their obligation to ensure grid reliability. \nE.\nThe PJM Transmission Owners’ Proposed Criteria Relating to Special \nProtection Schemes and Remedial Action Schemes are Just and Reasonable \nIn their initial brief, the PJM Transmission Owners proposed criteria to help address the \npotential adverse reliability impacts associated with a potentially substantial increase in reliance \non SPS/RAS and other protection systems resulting from implementation of the new transmission \nservices.28\nIn its reply brief, Constellation states that it agrees with the PJM Transmission Owners that \nall SPS and RAS should be fully redundant, as long as such redundancy is consistent with a two \ncircuit breaker in a series example that it provides in its reply brief.29  The PJM Transmission \nOwners agree that the customer and Transmission Owner may own the circuit breaker(s) and \n27\nConstellation at 14; Vistra at 32. \n28\nPJM Transmission Owners Initial Brief at 23-25. \n29\nConstellation at 22."},{"page":12,"startToken":3599,"endToken":3929,"text":"12 \nprotection systems at their respective facilities.  However, the meaning of Constellation’s caveat \nis unclear because typical substation construction does not necessarily mean that there will ever \nonly be two breakers in a series.  The terminals formed by the circuit breakers on each end of the \nconductors between a Transmission Owner’s and a customer’s facilities may be composed of one \nor more than one circuit breaker.  Regardless, it does not change the nature and design of the \nprotection systems used to accomplish SPS and RAS.  The number of breakers will be determined \nby the Transmission Owner’s and customer’s design practices and budget, and the Transmission \nOwner’s technical criteria. \nConstellation also states that it “agrees in principle with the fourth recommendation” \nasserted in the PJM TOs’ initial paper hearing brief,30 that “[a]ll SPS and RAS must fully meet \nPJM and PJM Transmission Owner technical criteria.”31  As Constellation acknowledges, PJM \nManual 3 governs PJM’s procedures for reviewing RASs.32  Where Constellation and the PJM \nTransmission Owners diverge is Constellation’s assertion that “[n]ew technical criteria [in Manual \n3] should not be established solely for Co-Located Loads.”33  Revisions or additions to Manual 3 \nto account for Co-Located Loads may be unavoidable due to technical characteristics of Co-\nLocated Load.  However, to the extent new technical criteria in Manual 3, or any other manual, \nmake sense to apply more broadly to participants other than Co-Located Load, the PJM \nTransmission Owners are amenable to that possibility.  But PJM and the PJM Transmission \nOwners should not be restricted from developing and implementing criteria applicable to Co-\nLocated Load as a class, if those criteria are based on reasonable technical differences between \n30\nId. at 23 (emphasis added). \n31\nId. at 23 (citing PJM Transmission Owners Initial Brief at 23). \n32\nId. at 23-24.  See PJM, PJM Manual 03: Transmission Operations (Mar. 4, 2026), https://www.pjm.com/-\n/media/DotCom/documents/manuals/m03.pdf (last visited Apr. 24, 2026). \n33\nConstellation at 24."},{"page":13,"startToken":3929,"endToken":4281,"text":"13 \nCo-Located Loads and other facilities.  In particular, Manual 3 does not contemplate a potentially \nsignificantly expanded use of SPS/RAS to enable load to take transmission service without \nbuilding transmission upgrades otherwise necessary to serve Co-Located Load.  To the extent Co-\nLocated Load arrangements impose additional and distinct reliability challenges, there is no \njustification for limiting PJM’s and the PJM Transmission Owners’ ability to address those \nchallenges through additional criteria, including those specific to Co-Located Load, through \nrevisions to Manual 3 or otherwise. \nAdditionally, Constellation’s request that the Commission reject the PJM Transmission \nOwners’ remaining recommendations is without merit.34 Constellation claims that these \nrecommendations would treat Co-Located Loads differently without any legitimate basis.  \nConstellation is wrong.  For instance, some PJM Transmission Owners already require protection \non their facilities to ensure that existing customers with on-site generation do not backfeed the \ntransmission system.  This also arises with respect to certain legacy networked distribution systems \nwhere the PJM Transmission Owner maintains a tripping scheme to ensure that power does not \nflow back onto the transmission system.  And both the PJM Transmission Owners and PJM have \nprovided ample evidence explaining how the use of SPS and RAS in the context of Co-Located \nLoad presents new and different challenges on the PJM system.35  No commenter, including \nConstellation, rebuts this evidence.  Moreover, the measures proposed by the PJM Transmission \n34\nId. at 24-25.  These recommendations consist of (i) permitting Transmission Owners the option of requiring \nSPS or RAS on their side of the point of interconnection and permitting recovery of the associated costs; (ii) allowing \nTransmission Owners the option (which may or may not be exercised) of owning, operating and maintaining an SPS \nor RAS installed on the customer side of the point of interconnection; (iii) limiting the amount of load that can be \ncovered by SPSs or RASs, and (iv) more frequent testing of SPS and RAS than is currently mandated by NERC \nreliability standards.  See PJM Transmission Owners Initial Brief at 23-24. \n35\nSee PJM Transmission Owners Initial Brief at 22-25; see also PJM Initial Brief, Wharton Affidavit at PP 20-\n26."},{"page":14,"startToken":4281,"endToken":4652,"text":"14 \nOwners could be applicable to other customers—in addition to Co-Located Load—to the extent \nthat the proliferation of SPS and RAS requires PJM-wide revisions to the relevant criteria.   \nRelatedly, Vistra provides no convincing reason for the Commission to reject the PJM \nTransmission Owners’ recommendation that reasonable limits be imposed on the amount of load \nin specific geographic areas covered by SPS/RAS.36  As both PJM and the PJM Transmission \nOwners have explained, a heavy concentration of these protection systems in specific areas \nincreases reliability risks based on potential failures on the system and the resulting potential for \ncascading outages.37  Vistra fails even to address, much less rebut, these explanations.  \nNevertheless, the PJM Transmission Owners recognize that to implement such limitations \nappropriately, further details and guidelines need to be developed, and welcome further \nengagement with stakeholders to assist PJM in doing so. \nF.\nThe PJM Transmission Owners Support PJM’s Proposed Operational \nPenalties, and Provide Additional Details on Proposed Financial Penalties \n1.\nPJM’s Operational Penalties are Just and Reasonable \nThe PJM Transmission Owners support the operational consequences and penalties \nproposed by PJM that will apply to failures to follow load shedding/curtailment instructions and \ncontrol technology and protection system misoperation.38  Robust operational penalty provisions \nare a necessary component of the new services because network upgrades are planned and built \nonly to accommodate load covered by Firm Contract Demand Service or NITS.  Thus, it is crucial \n36\nVistra at 27-28. \n37\nPJM Transmission Owners Initial Brief at 23; PJM Initial Brief, Wharton Affidavit at PP 21-22. \n38\nSee PJM Initial Brief at 40-51.  PJM proposes penalties “applicable to Eligible Customers taking transmission \nservice on behalf of a Co-Located Load using: (i) Firm Contract Demand Transmission Service; (ii) Non-Firm \nContract Demand Transmission Service; and (iii) Interim NITS prior to automatically transitioning to NITS on behalf \nof a Co-Located Load.  PJM supports three different penalties applicable where such Eligible Customers:  (i) fail to \nfollow established Load Shedding and Curtailment procedures; (ii) rely on necessary control technologies or \nprotection systems in accordance with the PJM Manuals, which may include a RAS, that fail (i.e., misoperate) more \nthan once; and (iii) makes unreserved use of the PJM Transmission System.”  Id. at 40."},{"page":15,"startToken":4652,"endToken":5018,"text":"15 \nthat Co-Located Loads respect their contractual limits.  This concern is particularly acute because \nthese Co-Located Load arrangements likely will involve substantial amounts of load—hundreds, \nif not thousands of MW—being served by on-site generation but still connected to the grid.39  If \nthese limits are not respected, the reliability consequences to the system—and to existing \ncustomers that depend on the reliable operation of that system—could be severe.40  Therefore, \noperational penalties must be structured to meaningfully deter load customers that exceed reserved \nservice amounts.  PJM’s proposal appropriately achieves this purpose.  \nConstellation argues that PJM should simply adopt Southwest Power Pool, Inc.’s (“SPP”) \nHigh Impact Large Load (“HILL”) process, which imposes only financial penalties.41  This \nargument is without merit.  First, SPP’s HILL proposal differs in a several pertinent respects from \nPJM’s proposal.  For example, unlike SPP’s HILL proposal, under PJM’s proposal Co-Located \nLoad customers may be in the position of installing and operating their own control technologies \nand protection systems.42  Under such circumstances, it is appropriate and necessary that PJM have \nin place strong measures to ensure reliability and to incentivize customers to operate accordingly.  \nMoreover, PJM and SPP are two different regions with different characteristics, including \ntopology and proliferation of large loads.43  Financial penalties are proper but insufficient \nsafeguards against adverse operational consequences of the sort proposed by PJM. \n39\nJoint Rebuttal Testimony of Peter Blazunas, Lance Schafer, and Hanhan Hammer, Exhibit No. PTO-0005 \nat 4 (“Blazunas, Schafer, and Hammer Rebuttal Testimony”) . \n40\nId. at 4. \n41\nConstellation at 19-21.  \n42\nPJM Initial Brief at 43, 56; PJM Initial Brief, Attachment A at Sections 702.4, 705.5, 708(c), 710.4, 713.6. \n43\nSee generally North American Electric Reliability Corporation, Long-Term Reliability Assessment (Jan. \n2026), https://www.nerc.com/globalassets/our-work/assessments/nerc_ltra_2025.pdf; PJM, PJM Load Forecast \nReport (Jan. 14, 2026), https://www.pjm.com/-/media/DotCom/library/reports-notices/load-forecast/2026-load-\nreport.pdf; Southwest Power Pool, 2025 Integrated Transmission Planning Assessment Report (Nov. 25, 2025), \nhttps://www.spp.org/media/2429/2025-itp-report-v10.pdf.  In addition, the level of retail competition and prevalence \nof independent generators in SPP differ substantially from those in PJM."},{"page":16,"startToken":5018,"endToken":5315,"text":"16 \nThe concerns raised regarding the liability of Co-Located Load customers for penalties \nassociated with control technologies and protection systems operated by other parties, such as \nTransmission Owners44 miss the point.  The installation of redundant protection facilities by \nTransmission Owners on their own system should not serve as an excuse for customers to fail to \nproperly maintain and operate their own equipment.  The failure to do so should be subject to the \npenalties proposed by PJM, regardless of whatever additional protection systems a Transmission \nOwner or other entity may install.  \n2.\nAdditional Detail Regarding PJM Transmission Owners’ Financial \nPenalty Proposal \nAs set forth in their March 25 joint response, the PJM Transmission Owners are proposing \nfinancial penalties that will operate in a complementary fashion with PJM’s proposed operational \npenalties.45  The PJM Transmission Owners provide more detail on this proposal in the \naccompanying Blazunas, Schafer, and Hammer Rebuttal Testimony, as well as the accompanying \nIllustrative Tariff sheets.  As explained in the Blazunas, Schafer, and Hammer Rebuttal Testimony, \nthe PJM Transmission Owners propose a financial penalty charge structure with two components: \n(1) a base penalty charge, which applies to each individual hour in which the reserved transmission \nservice limit is exceeded, and (2) a penalty ratchet, which applies when such exceedances occur \nrepeatedly.46  When a Co-Located Load exceeds its reserved transmission service limit, which will \ninclude any reductions based on curtailments directed by PJM, the base penalty charge will be \nassessed for any hour in which at least one five-minute interval occurs during which a customer’s \n44\nSee Response of the Data Center Coalition, Docket Nos. EL25-49, et al., at 8 (Mar. 25, 2026); Vistra at 30-\n31. \n45\nJoint Response of the PJM Transmission Owners at 11-13.  \n46\nBlazunas, Schafer, and Hammer Rebuttal Testimony at 6."},{"page":17,"startToken":5315,"endToken":5558,"text":"17 \nmetered load at the point of delivery exceeds its reserved transmission service.47  Such a five-\nminute interval is defined as an Exceedance Interval, and such an hour is defined as an Exceedance \nHour.48  The base penalty charge will apply to each Exceedance Hour.49\nThe penalty rachet applies when multiple Exceedance Hours occur during a particular time \nperiod.50  It is designed to discourage recurring reliance on unreserved transmission capacity.51\nUnder the penalty rachet framework, the penalty charges escalate as the frequency of unreserved \ntransmission use increases.52  Specifically, if more than one Exceedance Hour occurs on the same \ncalendar day, an additional daily penalty applies.53  If exceedances occur on multiple calendar days \nwithin the same calendar week, an additional weekly penalty applies; likewise, if exceedances \noccur in multiple calendar weeks within the same calendar month, an additional monthly penalty \napplies.54  By progressively increasing the economic consequences of repeated penalties, the \npenalty ratchet reinforces the expectation that Co-Located Load customers manage their load in a \nmanner consistent with their reserved transmission service limits.55\nIII.\nRESPONSE TO COMMENTS ON THE PJM TRANSMISSION OWNERS’ RATE \nPROPOSALS \nAs required by the Commission, the PJM Transmission Owners have proposed rates for \nInterim NITS, Firm Contract Demand Service, Non-Firm Contract Demand Service, and a Grid \n47\nId. at 7. \n48\nId. at 7. \n49\nId. at 7. \n50\nId. at 7. \n51\nId. \n52\nId. \n53\nId.\n54\nId.\n55\nId."},{"page":18,"startToken":5558,"endToken":5875,"text":"18 \nReliance Charge.  Some parties support the PJM Transmission Owners rate proposals,56 while \nothers raised issues regarding certain aspects of those proposals.  As discussed in their initial brief \nand below, the PJM Transmission Owners’ rate proposals are just and reasonable, and none of the \ncriticisms in the March 25 filings support significant modifications to the proposed rates.   \nIn addition, the PJM Transmission Owners are including with this filing Illustrative Tariff \nsheets to provide additional detail regarding the implementation of their rate proposals.57\nTestimony supporting these tariff revisions, as well as the PJM Transmission Owners’ responses \nto commenters, is included as Exhibit No. PTO-0005 to this reply brief. \nA.\nThe Proposed Contract Demand Rate Design is Just and Reasonable \nThe Firm Contract Demand Service rate will be calculated in a manner essentially identical \nto the existing NITS rates.58  Constellation notes that a number of PJM Transmission Owners do \nnot use a single coincident peak to calculate their NITS rates.59  Constellation requests clarification \nthat the Firm Contract Demand Service rate will be equal to the applicable Transmission Owner’s \nNITS rate calculated using that Transmission Owner’s methodology.60  The PJM Transmission \nOwners clarify that the zonal Firm Contract Demand rate will be calculated using that \nTransmission Owner’s specific methodology applicable to NITS customers. \nVistra incorrectly alleges that the PJM Transmission Owners fail to grapple with the \nquestion of whether it may be just and reasonable to apply the current zonal Non-Firm Point-to-\n56\nSee Response of Northern Virginia Electric Cooperative, Inc., Docket Nos. EL25-49, et al., at 6-10 (filed \nMar. 25, 2026); Reply Brief of Old Dominion Electric Cooperative, Docket Nos. EL25-49, et al., at 5, 8-10 (filed Mar. \n25, 2026). \n57\nSee Exhibit No. PTO-0006. \n58\nPJM Transmission Owners Initial Brief, Exhibit No. PTO-0001, Direct Joint Testimony of Peter Blazunas, \nLance Schafer, and Hanhan Hammer at 6. \n59\nConstellation at 31. \n60\nId. at 31."},{"page":19,"startToken":5875,"endToken":6181,"text":"19 \nPoint (“PTP”) Service rates to Non-Firm Contract Demand Service, including whether Non-Firm \nContract Demand Service is superior to Non-Firm PTP Service.61  In their Initial Brief, the PJM \nTransmission Owners explained why it would be unreasonable to simply apply the existing Non-\nFirm PTP rates to Non-Firm Contract Demand Service.62  That is, for many years in PJM, \ntransmission customers have used Non-Firm PTP service exclusively to facilitate the delivery of \nspecific generation to the PJM border, not for internal use.  The existing discounted Non-Firm PTP \nService rate reflects historical use, and was certainly not intended, and is not appropriate, for Non-\nFirm Contract Demand Service, which (a) is intended to be a limited, supplemental service within \nPJM and (b) does not facilitate the delivery of specific generation to specific load over a contract \npath.63  In addition, Non-Firm Contract Demand Service is demonstrably superior to Non-Firm \nPTP service.  As discussed in the PJM Transmission Owners Initial Brief, Non-Firm Contract \nDemand Service has a superior curtailment priority relative to Non-Firm PTP.64\nA few parties contend that the PJM Transmission Owners’ proposal to initially establish \nrates for Non-Firm Contract Demand Service based on the rates determined for Firm Contract \nDemand Service is inconsistent with principles of cost causation.65  The Joint Developers, for \ninstance, argue that the PJM Transmission Owners should discount Non-Firm Contract Demand \nService because Non-Firm Contract Demand customers will impose “lesser costs” on the grid.66\nHowever, as noted in the Initial Brief, before determining whether a discount is appropriate for \n61\nVistra at 16-17. \n62\nPJM Transmission Owners Initial Brief at 11-12. \n63\nId. at 11 n. 30. \n64\nId. at 12. \n65\nJoint Developers at 3, 20-23; Response Brief of Geronimo Power, LLC, Docket Nos. EL25-49, et al. at 6 \n(filed Mar. 25, 2026) (“Geronimo”).   \n66\nJoint Developers at 20."},{"page":20,"startToken":6181,"endToken":6510,"text":"20 \nNon-Firm Contract Demand Service, and if so, at what level the discount should be set, the PJM \nTransmission Owners need to gather data on how Non-Firm Contract Demand Service customers \nare utilizing the service, taking into account the intended purpose of the service, and the effect of \nthat utilization on the system.67  Thus, the PJM Transmission Owners will consider on a going-\nforward basis whether a discount is appropriate for Non-Firm Contract Demand Service based on \nsystem conditions and use patterns and, if so, the criteria and limits under which PJM will apply \nthe discount.68  In short, the PJM Transmission Owners are preserving the ability to offer discounts, \nwhich is sufficient at this time to address the Joint Developers’ concerns.69\nThe Joint Developers argue that no further study or data gathering is necessary before \noffering a discount because the PJM Transmission Owners can have confidence that customers \nusing Non-Firm Contract Demand Service will require fewer upgrades.70  However, it is far from \ncertain what upgrades may be required for Non-Firm Contract Demand Service customers.  Indeed, \nit is possible that most or all Co-Located Load customers will take significant Firm Contract \nDemand Service, with only limited non-firm service.  This supports the PJM Transmission \nOwners’ explanation in their initial brief that further analysis is needed to determine whether a \ndiscount is appropriate for Non-Firm Contract Demand Service and, if so, what level of discount \nshould be adopted, taking into account how customers are utilizing the service and the effect of \nthat utilization on the system.71\n67\nPJM Transmission Owners Initial Brief at 13. \n68\nId. at 13.  Any rate discount offered for Non-Firm Contract Demand Service would be offered by PJM based \non rules and criteria established by the PJM Transmission Owners designed to incentivize the efficient use of Non-\nFirm Contract Demand Service and the transmission system.  Id.\n69\nJoint Developers at 20-23. \n70\nId. at 21. \n71\nPJM Transmission Owners Initial Brief at 13."},{"page":21,"startToken":6510,"endToken":6817,"text":"21 \nFinally, the Joint Developers’ concerns that the Non-Firm Contract Demand Service rate \nwill discourage industrial development72 are exaggerated and misplaced.73  As the Commission \nhas recognized, Non-Firm Contract Demand Service is intended as a limited service to cover \nperiods when on-site generation is on outage, not a substitute for Firm Contract Demand Service \nor NITS.74  To the extent that Co-Located Load intends to rely on delivery of energy from the \ntransmission system, rather than on-site generation, that load should be required to obtain firm \nservice, either in the form of Firm Contract Demand Service or NITS.75\nB.\nThe Proposed Grid Reliance Charge Rate Design is Just and Reasonable \nIn their initial brief, the PJM Transmission Owners proposed a Grid Reliance Charge \ndesigned to reflect the costs of using the transmission system to deliver black start and regulation \nservices.76  The Grid Reliance Charge also reflects the costs of providing the inherent benefits that \nall customers, including Contract Demand customers, receive as a result of their connection and \nsynchronization to the grid.77  The PJM Transmission Owners proposed a methodology based on \nthe portions of annual depreciation and operations and maintenance expenses that best capture the \nportions of a transmission owner’s revenue requirements relating to the ongoing reliable operation \nof the grid.78  Although nearly all of the commenters acknowledge that some Grid Reliance Charge \nis appropriate, a few parties contend that the PJM Transmission Owners’ proposed methodology \n72\nJoint Developers at 22-23. \n73\nId. at 22-23 (“For example, . . . thermal energy storage resources must be able to take power when low-cost \nsupply is available . . . at prices that reflect the lower cost of electricity and transmission service during such \nconditions.”). \n74\nOrder at P 214. \n75\nId. at P 160. \n76\nPJM Transmission Owners Initial Brief at 14-18. \n77\nId. at 14. \n78\nId. at 15-16."},{"page":22,"startToken":6817,"endToken":7100,"text":"22 \nfor determining the Grid Reliance Charge is unjust and unreasonable.  These claims are without \nmerit.   \nVistra and Geronimo are the only two parties that suggest no Grid Reliance Charge is \nnecessary.  Geronimo claims that “not being islanded from the grid is not a benefit in and of \nitself”79 and argues that the PJM Transmission Owners did not provide any detail on what sort of \n“inherent benefits” will flow from the service associated with the Grid Reliance Charge.80  This \nclaim is incorrect.  Being connected to the grid provides obvious benefits in terms of the ability to \naccess resources that are not co-located with load if necessary, backing up co-located generation, \nand providing critical ancillary services to Co-Located Load, such as regulation and black start.  \nThese grid benefits also include delivering ancillary services and essential reliability services, such \nas frequency support, inertia, voltage stability, fault current capability, ride-through and \nprotections coordination, and providing sufficient short-circuit capability.81  The PJM \nTransmission Owners are not aware of any existing or proposed Co-Located Load customers that \nare choosing to island their load and on-site generation.  Indeed, the Order directs PJM to provide \nthree transmission-service pathways for Co-Located Loads, allowing those loads to take \ntransmission service from the grid rather than requiring a fully islanded arrangement.  It follows \nthat Co-Located Loads should share in the basic costs of operating and maintaining the grid upon \nwhich they rely. \nLikewise, Geronimo incorrectly asserts that there are no costs associated with delivering \nblack start and regulation services.82  In the Order, the Commission expressly recognized that rates \n79\nGeronimo at 11. \n80\nId. at 11-12. \n81\nRebuttal Testimony of Blazunas, Schafer, and Hammer at 16. \n82\nGeronimo at 12-14."},{"page":23,"startToken":7100,"endToken":7439,"text":"23 \nmay need to include an additional charge for delivering these services, in addition to the costs of \nthe services themselves.83  This additional charge is appropriate because ancillary services such as \nblack start and regulation provide no value without the ability to access the transmission system to \nobtain them.   \nConstellation contends that the proposed Grid Reliance Charge is not grounded in sound \nratemaking and cost-causation principles based on the Grid Reliance Charge excluding and \nincluding certain cost categories.84  Namely, Constellation argues that the Grid Reliance Charge \nexcludes reasonable costs, such as rate of return and taxes, while including unreasonable costs, \nsuch as the full costs of depreciation for facilities sized to meet PJM peak demand.85  Constellation \nis mistaken.  The PJM Transmission Owners’ proposed Grid Reliance Charge methodology is \ngrounded in sound ratemaking and cost causation principles.  It represents an appropriate balance \nbetween fairly estimating the grid reliance benefits to Co-Located Load and the need to ensure the \nrate can be practically implemented.86  Practicality concerns are particularly pertinent here given \nthe Commission’s desire to expedite the interconnection of data center loads.  This approach is \nalso fully consistent with longstanding Commission and court precedent holding that cost \nallocation rules do not require exacting precision as long as they represent a comparison of the \ncosts assessed to a party against the burdens imposed or benefits drawn.87  The PJM Transmission \nOwner’s Grid Reliance Charge proposal meets this standard. \n83\nOrder at P 160. \n84\nConstellation at 25-27. \n85\nId. at 25-27. \n86\nRebuttal Testimony of Blazunas, Schafer, and Hammer at 16. \n87\nSee, e.g., Ill. Commerce Comm’n v. FERC, 576 F.3d 470, 477 (7th Cir. 2009); Transmission Plan. & Cost \nAllocation by Transmission Owning & Operating Pub. Utils., Order No. 1000, 136 FERC ¶ 61,051, at P 504 and nn. \n393, 435, 453 (2011) (citing to Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361 at 1369, 1371 (D.C. Cir. \n2004) (explaining that cost causation “does not require exacting precision in a ratemaking agency’s allocation \ndecisions.”))."},{"page":24,"startToken":7439,"endToken":7754,"text":"24 \n Attempting to determine the proportion of rate of return and taxes to include in the Grid \nReliance Charge, as Constellation suggests,88 would necessarily entail the need to determine \nrelated proportions for all components (and all relevant FERC accounts in those components) of \nthe Transmission Owner’s revenue requirement.  Such determinations would be extremely difficult \nto produce and would potentially result in a spurious level of precision because they would depend \nlargely on subjective determinations including judgments based on the unique facts of each Co-\nLocated Load arrangement.  Such determinations would be extremely challenging to implement \non an ex ante basis and highly susceptible to disputes and challenges.  Moreover, although the base \ncomponents included in the proposed Grid Reliance Charge calculation are limited to transmission \ndepreciation and a percentage of transmission operations and maintenance expenses, the \ncalculation also includes accounts related to day-to-day operational costs of the provision of grid \nreliance while maintaining a high level of transparency.  By excluding rate of return and taxes, the \nmethodology produces a more conservative result focused on recovery of the costs necessary to \nsupport the ongoing reliable operation of the grid, rather than a return on investment. \nConstellation further challenges the PJM Transmission Owners’ proposal to include 100% \nof transmission depreciation expense in the calculation of the Grid Reliance Charge.89\nConstellation witness Zachary Ming argues that it is inappropriate to include the “full depreciation \ncosts for a variety of transmission components . . . that are sized to meet the actual peak demand \nrequirements of the PJM system, even though customers paying the [Grid Reliance Charge], by \ndefinition, do not impose any demand or withdraw any energy from the PJM system . . . .”90  As \nthe PJM Transmission Owners explain in the Initial Brief and related testimony, the Grid Reliance \n88\nConstellation at 11-12. \n89\nId. at 26-27. \n90\nId. at 27 (quoting Testimony of Zachary Ming at 12:5-10 (“Ming Testimony”))."},{"page":25,"startToken":7754,"endToken":8095,"text":"25 \nCharge includes 100% of the transmission depreciation expenses included in FERC Accounts 350-\n359.91  This proposal is reasonable when considered in the overall context of the rate design \nmethodology.  Although the transmission system is built to meet peak demand, the proposed Grid \nReliance Charge rate design does not include the full revenue requirement associated with the \ntransmission infrastructure put in place to meet peak demand, meaning that the full cost of that \ninfrastructure is not recovered in the Grid Reliance Charge.  But even if a particular customer is \nnot making use of the transmission system to deliver energy during the peak period(s), that \ncustomer still relies on the grid based on its on-site demand.  The PJM Transmission Owners’ \nproposed Grid Reliance Charge appropriately reflects that fact by including only costs associated \nwith the continued operation of the transmission system. \nInstead of the methodology proposed by the PJM Transmission Owners, Constellation’s \nwitness Zachary Ming proposes a “minimum system” approach to calculating the Grid Reliance \nCharge.92  Under this proposal, the Grid Reliance Charge would be calculated using the “minimum \nsystem” method that some, but far from all, utilities use to determine customer-driven components \nof their distribution rates.  This approach would be based on determining the costs associated with \nthe minimum size of all system components that could be used to recreate its system and connect \neach customer to the grid.93  Constellation’s proposal is unreasonable in the context of a Grid \nReliance Charge, and if adopted, would end up shifting to other users of the system costs that are \nappropriately borne by Co-Located Load customers that will continue to rely on their \ninterconnection to the transmission system. \n91\nPJM Transmission Owners Initial Brief, Exhibit No. PTO-0001, Direct Joint Testimony of Peter Blazunas, \nLance Schafer, and Hanhan Hammer at 21-22. \n92\nConstellation at 26-28; Ming Testimony at 14:2-15:2. \n93\nMr. Ming addresses this proposal in greater detail and estimates a value between 2 and 10 percent of total \nsystem costs.  Constellation at 27-28; Ming Testimony at 21:17-20."},{"page":26,"startToken":8095,"endToken":8414,"text":"26 \n  \n \nAs Mr. Ming acknowledges, although the “minimum system” method is sometimes used94\nas a component of class cost of service studies for distribution systems, it is not used in \ntransmission studies.95  As Mr. Schafer explains in the Blazunas, Schafer, and Hammer Rebuttal \nTestimony, the minimum system method is not used at the transmission level because the \nfoundational premise of the method—that a definable portion of the system is built solely to \nconnect customers largely independent of load—does not exist in transmission systems, which are \nplanned and operated to serve bulk power flows and meet system-wide reliability criteria.96  In \ndistribution studies, the minimum system study results are allocated to customer classes based on \nthe count of customers, not on rate-class demand.97  Yet Mr. Ming nevertheless proposes to apply \nthe results of the minimum system study to develop a demand-related charge – the Grid Reliance \nCharge.  Such an application is inconsistent with the methodology because the minimum system \nstudy develops a customer-related cost that is not intended to be billed on demand.98\nMr. Ming further proposes the minimum system methodology without concern for what \nthe Grid Reliance Charge is designed to accomplish.  He states that “[w]ithin the context of \nelectricity system ratemaking, [the minimum system] methodology [is] designed to calculate \nprecisely the costs of constructing wires to connect all customers, i.e., customer-driven costs.”99\nMr. Ming adds that “[a] ‘minimum system’ is a theoretical electricity system designed only to \n94\nIndeed, the minimum system approach is not uniformly used even in distribution ratemaking. \n95\nMing Testimony at 21:9-11 (“As discussed above, there is little to no precedent for applying the minimum \nsystem method to the transmission system, so there is relatively little available data upon which to benchmark \nresults.”). \n96\nBlazunas, Schafer, and Hammer Rebuttal Testimony at 20. \n97\nId. at 23. \n98\nId. at 25. \n99\nMing Testimony at 14:14-17."},{"page":27,"startToken":8414,"endToken":8726,"text":"27 \nconnect each customer and deliver a de minimis amount of power.”100  However, the simple goal \nof “connecting all customers” is quite different from recovering costs associated with delivery of \nblack start, regulation and other ancillary services, which must be available under any system \ncondition, along with the costs associated with a Co-Located Load’s continued reliance on the \nreliable operation of the transmission system.  Mr. Ming does not demonstrate that there is any \ncorrelation between the mere electrical connection of customers and the benefits a Co-Located \nLoad receives from an on ongoing grid connection in proportion to its on-site load.  Without some \nlink between the two, there is no justification for using a minimum system method to calculate the \nGrid Reliance Charge.  Further, the quoted portions above again highlight that the minimum \nsystem method is related to customer costs, not costs that should be recovered through demand \ncharges.101  The minimum system method is simply not appropriate for use in developing the \ndemand-based Grid Reliance Charge.  This contrasts with the PJM Transmission Owners’ \nproposal, which identifies the specific depreciation and operations and maintenance expense \ncategory that best captures the portions of a Transmission Owner’s revenue requirements relating \nto the ongoing reliable operation of the grid, and therefore the benefits that all customers \ninterconnected with the system receive as a result.102\nMr. Ming’s position is that because no utilities use the “minimum system” method for \ntransmission, the Commission must assume that the minimum system value is close to 0% for the \ntransmission system, and therefore conclude that the PJM Transmission Owners’ proposed fixed \n100\nMing Testimony at 14:19-20. \n101\nBlazunas, Schafer, and Hammer Rebuttal Testimony at 28. \n102\nSee PJM Transmission Owners Initial Brief, Exhibit No. PTO-0001, Direct Joint Testimony of Peter \nBlazunas, Lance Schafer, and Hanhan Hammer at 20-21; see also Blazunas, Schafer, and Hammer Rebuttal Testimony \nat 26-27."},{"page":28,"startToken":8726,"endToken":9089,"text":"28 \npercentage should be much less than the proposed 25.8%.103  This reasoning is nonsensical.  The \nrational conclusion to draw here is that if no utilities use the “minimum system” method for \ntransmission, then that method is irrelevant to this proceeding and it cannot be the basis for any \ninferences or conclusions with respect to the PJM Transmission Owners’ proposed Grid Reliance \nCharge methodology.104  The fact that the PJM Transmission Owner’s proposal resulted in a fixed \npercentage allocator higher than Constellation would prefer does not cause the underlying \nmethodology to be unjust and unreasonable. \nMr. Ming further presents what he claims are the results of a minimum system study \napproach to the Grid Reliance Charge,105 but even if such an approach were theoretically \nlegitimate, his implementation is fundamentally flawed.  This is evident from his selection of \nminimum system components.  For example, when choosing the minimum system component for \ntransmission poles and transmission towers, Mr. Ming indicates the use of “distribution wood \npole[s].”106  In other words, Mr. Ming’s minimum system study assumes that a minimum \ntransmission system could be built with wood poles used for distribution system facilities.  This \nassumption disregards the engineering reality of the transmission system.  A distribution wood \npole cannot perform the function of a transmission structure in that it cannot support required \nvoltages, cannot meet clearance requirements, and cannot handle mechanical loads (e.g., span \nlength, conductor weight).107\n103\nMr. Ming admits that “no utilities that I am aware of classify any transmission costs to the customer cost \ndriver,” and, based on this fact he assumes utilities are implicitly assuming “a minimum system value of 0% for the \ntransmission system.”  Consequently, Mr. Ming concludes that “it is reasonable to assume that a proper minimum \nsystem study when applied to the transmission system would yield a value significantly lower than [the] 25.8%” that \nthe PJM Transmission Owners propose for the initial fixed percentage.  See Ming Testimony at 18:11-15. \n104\nBlazunas, Schafer, and Hammer Rebuttal Testimony at 22-23. \n105\nMing Testimony at 20:1 (Table 1). \n106\nId. at 20:1, n.26 (Table 1). \n107\nBlazunas, Schafer, and Hammer Rebuttal Testimony at 19."},{"page":29,"startToken":9089,"endToken":9397,"text":"29 \nVistra also argues that the Grid Reliance Charge is unjust, unreasonable and unduly \ndiscriminatory, raising a number of claims.108  None of Vistra’s claims have any merit.  First, the \nPJM Transmission Owners’ proposal does not conflict with Order No. 888’s requirement to \nunbundle ancillary services from transmission service.109  Contrary to Vistra’s claim that the PJM \nTransmission Owners are proposing a new “undefined ancillary service,”110 the Grid Reliance \nCharge is not a new ancillary service.  Rather, it is a charge contemplated in the Order that is \nnecessary to account for and recognize the benefits that Co-Located Load receives through its \ninterconnection with the transmission grid and the delivery of black start and regulation services.  \nAs such, it is appropriately designed and recovered as a transmission service charge.111\nSecond, Vistra’s proposed alternative to the Grid Reliance Charge methodology also is \nwithout merit.  Vistra argues that, because only 0.5% of “PJM’s monthly billings” are related to \nblack start and regulation charges, 0.5% is a reasonable proxy for the Grid Reliance Charge fixed \npercentage.112  This argument assumes that the 0.5% can be employed as the Grid Reliance Charge \nfixed percentage without considering the relationship between the percentage of billed revenue for \nblack start and regulation and the costs of the transmission system used to deliver those ancillary \nservices when needed, as well as to provide the benefits associated with an ongoing grid \ninterconnection.113  In fact, there is no connection between the two metrics, making a comparison \nof the billings for black start and regulation service to the costs required to deliver those services \n108\nVistra at 18-23. \n109\nId. at 19-20. \n110\nId. at 20. \n111\nOrder, Chang Concurrence at P 9. \n112\nVistra at 22 (quoting Affidavit of Rebecca Stadelmeyer at 11:12-14). \n113\nBlazunas, Schafer, and Hammer Rebuttal Testimony at 29."},{"page":30,"startToken":9397,"endToken":9702,"text":"30 \nmisleading at best.114  The fixed percentage is a function of the facilities and expenses related to \nthe delivery of ancillary services; it is not associated with PJM’s billings for the actual ancillary \nservices.115  Moreover, the purpose of the Grid Reliance Charge is not confined to recovering the \ncosts associated with delivery of black start and regulation services, but rather, encompasses the \nfull range of benefits that a Co-Located Load received by virtue of its continued interconnection \nto the grid.116\nThird, Vistra is incorrect in its assertion that the PJM Transmission Owners’ proposal fails \nto account for Co-Located Load customers that take different levels of service.117  Under the PJM \nTransmission Owners’ rate proposal, customers taking some form of transmission delivery service \n(NITS, Firm or Non-Firm Contract Demand Service) will be charged only for that service, while \ncustomers that take no such transmission service will not be subject to such charges.  However, \neven if a customer never “pulls energy from the grid,” and only relies on black start and regulation \nservice,118 and receives the inherent benefits that come with grid interconnection, providing these \nbenefits still requires transmission infrastructure, which requires investment and expense.  The \nGrid Reliance Charge appropriately captures, with reasonable precision, the costs of the \ntransmission necessary for the delivery of ancillary services to co-located loads, as the \nCommission recognized in the Order.119\n114\nId. at 29. \n115\nId. \n116\nId. at 31. \n117\nVistra at 21-22. \n118\nId. at 21 (“[A] customer that is relying on the grid solely for regulation and black start service is demonstrably \nrelying very little on the grid.”). \n119\nOrder at P 183.  As with some other parties, if Vistra disagrees with this Commission finding, its path is to \nseek rehearing of the Order, not to challenge the PJM Transmission Owners’ proposed compliance."},{"page":31,"startToken":9702,"endToken":9962,"text":"31 \nC.\nThe PJM Transmission Owners’ Crediting Proposal Will not Create a Cost \nShift Among Customers \nVistra claims that the PJM Transmission Owners’ proposal to credit the revenues \nassociated with the Grid Reliance Charge and Non-Firm Contract Demand Service to customers \ntaking NITS and Firm Contract Demand Service will create unjustified cost shifts among customer \nclasses.120  Vistra is incorrect.  First, the proposed credits relating to Non-Firm Contract Demand \nService revenues are not subsidies but instead represent offsets that reduce the amount paid by \nfirm service customers for the firm transmission service they receive.121  This is entirely \nappropriate as transmission rates are designed to recover the fixed costs of building and \nmaintaining the system so as to provide service to firm customers.122  Therefore, the revenues \nreceived from Non-Firm Contract Demand Service are appropriately applied as a credit to offset \nthose fixed costs.123  Absent such a credit, transmission owners would over-recover their revenue \nrequirements.  Similarly, it is appropriate to provide firm service customers with credits \nrepresenting the revenues received from the Grid Reliance Charge.  Those customers will be \npaying a rate that reflects the full embedded cost of the transmission system.124  Absent receiving \na credit associated with the Grid Reliance Charge, those customers would be effectively double-\ncharged for those services, which are already fully included in their firm service charge.  \nImportantly, the crediting mechanism is fully consistent with previously approved crediting \n120\nVistra at 23-25. \n121\nBlazunas, Schafer, and Hammer Rebuttal Testimony at 30. \n122\nId. at 30. \n123\nId. at 30. \n124\nId. at 31."},{"page":32,"startToken":9962,"endToken":10060,"text":"32 \nmechanisms in PJM’s Tariff, such as Section 27A, which credits Non-Firm PTP transmission \nservice revenue to Network and Firm PTP transmission service customers.125\nFinally, Vistra’s statement regarding the manner in which a PJM Transmission Owner or \nits affiliate passes along any bill credits it receives by virtue of its role as a transmission customer \nis irrelevant.126  Issues regarding the allocation of bill credits to retail customers are matters of \nstate retail ratemaking, and beyond the scope of this specific proceeding and the Commission’s \njurisdiction generally. \n125\nSee PJM Tariff, Section 27A. \n126\nVistra at 24-25."},{"page":33,"startToken":10060,"endToken":10155,"text":"33 \nIV.\nCONCLUSION \nThe PJM Transmission Owners appreciate the opportunity to submit this reply brief to \nparties’ responses to the PJM and PJM Transmission Owners Initial Briefs.  The PJM Transmission \nOwners respectfully request that any subsequent Commission orders addressing these issues adopt \nthe proposals and recommendations set forth herein. \nRespectfully submitted, \n/s/ Michael Kunselman \nMichael Kunselman  \nRichard P. Sparling \n \nNicholas J. Cicale \nJonathan A. Namazi \nDavis Wright Tremaine LLP \n1301 K Street NW \nSuite 500 East \nWashington, DC 20005 \nCounsel for the FirstEnergy\n  Companies \nOn behalf of the PJM   \n  Transmission Owners\nDated:  April 24, 2026"},{"page":34,"startToken":10155,"endToken":10234,"text":"CERTIFICATE OF SERVICE \nUnder Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § \n385.2010 (2025), I hereby certify that I have this day served the foregoing document upon each \nperson designated on the official service lists compiled by the Secretary in these proceedings. \nDated at Washington, D.C., this 24th day of April 2026. \n/s/ Daniel Klein \nDaniel Klein \nDavis Wright Tremaine LLP \n1301 K Street NW \nSuite 500 East \nWashington, DC 20005"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":3,"startToken":0,"endToken":341},{"p":2,"at":3,"title":"I. INTRODUCTION","method":"printed heading","endPage":3,"endAt":1227,"startToken":341,"endToken":849},{"p":3,"at":1227,"title":"II. RESPONSE TO COMMENTS RELATED TO PJM’S PROPOSED TERMS AND","method":"printed heading","endPage":3,"endAt":1335,"startToken":849,"endToken":865},{"p":3,"at":1335,"title":"A. PJM has Appropriately Defined the Scope of Contract Demand and Interim","method":"printed heading","endPage":6,"endAt":463,"startToken":865,"endToken":1696},{"p":6,"at":463,"title":"B. PJM Appropriately did not Propose Changes to the Definition of Eligible","method":"printed heading","endPage":7,"endAt":969,"startToken":1696,"endToken":2081},{"p":7,"at":969,"title":"C. The Commission Should not Mandate a Combined Interconnection and","method":"printed heading","endPage":9,"endAt":1053,"startToken":2081,"endToken":2799},{"p":9,"at":1053,"title":"D. PJM’s Study Proposal Does not Promote Discrimination Against Co-Located","method":"printed heading","endPage":11,"endAt":993,"startToken":2799,"endToken":3453},{"p":11,"at":993,"title":"E. The PJM Transmission Owners’ Proposed Criteria Relating to Special","method":"printed heading","endPage":14,"endAt":980,"startToken":3453,"endToken":4426},{"p":14,"at":980,"title":"F. The PJM Transmission Owners Support PJM’s Proposed Operational","method":"printed heading","endPage":17,"endAt":1209,"startToken":4426,"endToken":5495},{"p":17,"at":1209,"title":"III. RESPONSE TO COMMENTS ON THE PJM TRANSMISSION OWNERS’ RATE","method":"printed heading","endPage":18,"endAt":747,"startToken":5495,"endToken":5667},{"p":18,"at":747,"title":"A. The Proposed Contract Demand Rate Design is Just and Reasonable","method":"printed heading","endPage":21,"endAt":639,"startToken":5667,"endToken":6609},{"p":21,"at":639,"title":"B. The Proposed Grid Reliance Charge Rate Design is Just and Reasonable","method":"printed heading","endPage":31,"endAt":4,"startToken":6609,"endToken":9703},{"p":31,"at":4,"title":"C. The PJM Transmission Owners’ Crediting Proposal Will not Create a Cost","method":"printed heading","endPage":33,"endAt":4,"startToken":9703,"endToken":10061},{"p":33,"at":4,"title":"IV. CONCLUSION","method":"printed heading","endPage":34,"endAt":0,"startToken":10061,"endToken":10155},{"p":34,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":34,"endAt":469,"startToken":10155,"endToken":10234}]}