{"document":{"slug":"rec-20260507-5103","title":"Motion for Leave to Answer and Answer of Enchanted Rock, LLC in response to PJM Interconnection, LLC's 04/24/2026 Reply Brief","issued":"2026-05-07","accession":"20260507-5103","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Enchanted Rock, LLC","kind":"answer","file":"sources/filings/text/20260507-5103_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260507-5103","tier":"record","sha256":"d6afed2ff23b26458cf6c80dac0202107b78daa506555288e8fda09c3523bbb4","pages":10,"tokens":3095,"emptyPages":[],"textThemes":["colo","flex","cost","study"]},"pages":[{"page":1,"startToken":0,"endToken":322,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM Interconnection, L.L.C., et al. \n) \nDocket No. EL25-49-000 \nLarge Loads Co-located at Generating \nFacilities \n) \n) \n) \n \nDocket No. AD24-11-000   \nConstellation Energy Generation, LLC \n    v.  \nPJM Interconnection, L.L.C. \n) \n) \n) \n) \n \nDocket No. EL25-20-000 \n \n(consolidated) \n \n) \nPJM Interconnection, L.L.C.  \n \n     )  \n \n \n  Docket No. ER26-1479-000 \n \nMOTION FOR LEAVE TO ANSWER AND ANSWER OF  \nENCHANTED ROCK, LLC \n \nPursuant to Rules 212 and 2131 of the Federal Energy Regulatory Commission (“FERC” \nor “Commission”)’s rules of practice and procedure, Enchanted Rock, LLC (“ERock”2) submits \nthis motion for leave to answer (“Motion”) and answer (“Answer”) in response to PJM \nInterconnection, LLC (“PJM”)’s April 24, 2026 reply brief3 in the captioned proceedings \nconcerning, inter alia, the Commission’s December 18 Order.4     \nERock submits this Answer to respond to several misleading and incorrect statements \nmade by PJM in their April 24 Reply Brief concerning PJM’s proposed implementation of \nInterim Network Integration Transmission Service (“Interim NITS” 5).  Moreover, for the \n \n1 18 C.F.R. §§ 385.212, 385.213 (2025). \n2 In April 2026, Enchanted Rock, LLC rebranded to “ERock” to reflect the evolution of the brand and its future.  \n3  Reply Brief of PJM Interconnection, L.L.C., Docket Nos. EL25-49-000, et al. (Apr. 24, 2026) (“April 24 Reply \nBrief”).  \n4 See PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“December 18 Order”); see also, 60-Day \nCompliance Filing for Co-Located Load Related Revisions to Open Access Transmission Tariff to Comply with \nCommission Order in Docket No. EL25-49, et al, Docket No. ER26-1479-000 (Feb. 23, 2026) (“PJM February 23 \nCompliance Filing”). \n5 All capitalized terms not otherwise defined herein shall have the same meaning set forth in the PJM Open Access \nTransmission Tariff (“PJM Tariff”), or the Illustrative Language For New Tariff (“Illustrative Tariff”) filed with the \nInitial Brief of PJM Interconnection, L.L.C., Docket Nos. EL25-49-000, et al. (Feb. 23, 2026) (“PJM Initial Brief”), \nas applicable."},{"page":2,"startToken":322,"endToken":699,"text":"2 \nreasons stated below, and those stated in ERock’s March 25, 2026, reply brief and protest,6 \nPJM’s proposed implementation of Interim NITS conflicts with the December 18 Order’s \ndirectives requiring PJM to establish “a new interim, non-firm transmission service.”7  \nI. \nMOTION FOR LEAVE TO ANSWER \nWhile Rule 213(a)(3) of the Commission’s rules of practice and procedure provides that \nan “answer may be made to any pleading, if not prohibited under paragraph (a)(2) of this \nsection,”8 Rule 213(a)(2) precludes, as a matter of right, an answer to a protest or answer.9  The \nCommission, however, will permit such answers for good cause shown.10  Good cause exists \nwhen the response will assist the Commission in its decision-making process, such as by helping \nto explain the relevant issues or otherwise facilitating the development of the record.11  Good \ncause exists here to allow ERock to respond to the April 24 Reply Brief in order to address \nseveral erroneous arguments made by PJM, and to facilitate the development of the record.   \nII. \nANSWER \nA. \nPJM’s Proposed Implementation of Interim NITS Is Fundamentally Flawed \nAt the heart of PJM’s proposed implementation of Interim NITS lies a fundamental \ndisconnect between what PJM is proposing and what the Commission directed PJM to \nimplement in the December 18 Order.  Notably, after finding that PJM’s existing tariff is unjust \nand unreasonable because, inter alia, “it does not include transmission services that reflect an \n \n6 Reply Brief and Protest of Enchanted Rock, LLC, Docket Nos. EL25-49-000, et al. (Mar. 25, 2026) (the “ERock \nProtest”). \n7 See December 18 Order at P 160.  \n8 18 C.F.R. § 385.213(a)(3). \n9 Id. § 385.213(a)(2). \n10 See Transcontinental Gas Pipe Line Co., 158 FERC ¶ 61,125, at P 18 (2017). \n11 See id. (“Although the Commission’s Rules of Practice and Procedure do not permit answers to protests or \nanswers to answers, we find good cause to waive our rules and accept the answers because they provide information \nthat has assisted in our decision making process”); Midcontinent Indep. Sys. Operator, Inc., 161 FERC ¶ 61,056, at P \n32 (2017) (“We will accept the answers . . . because they have provided information that assisted us in our decision \nmaking process.”)."},{"page":3,"startToken":699,"endToken":1012,"text":"3 \nEligible Customer taking service on behalf of a Co-Located Load that is willing and able to limit \nits energy withdrawals from the transmission system under certain conditions,”12 the \nCommission directed PJM to “establish three new transmission services that reflect that Eligible \nCustomers taking service on behalf of Co-Located Load are willing and able to limit their energy \nwithdrawals from the transmission system under certain conditions.”13  Relevant here, one of the \nthree new types of transmission services is intended to “allow Eligible Customers seeking to take \nNITS on behalf of Co-Located Load to, at their option, take a new interim, non-firm \ntransmission service until all Network Upgrades necessary to provide NITS are complete.”14 \nRather than proposing rules that would enable Eligible Customers to utilize this “new \ninterim, non-firm transmission service,” the April 24 Reply Brief instead doubles down on PJM’s \nflawed position that would prohibit Co-Located Load from receiving any capacity or energy \nfrom a Co-Located Generating Facility while the Co-Located Load is taking Interim NITS \n(sometimes referred to herein as the “Proposed Interim NITS Limitation”).15  PJM’s Proposed \nInterim NITS Limitation, and its statements in its April 24 Reply Brief, make clear that PJM \nseeks to treat a Co-Located Generating Facility serving a Co-Located Load taking Interim NITS \nas a Capacity Resource that is fully deliverable to the PJM wholesale market during the interim \nperiod before “all Network Upgrades necessary to provide NITS are complete”16 and before the \nCo-Located Generating Facility even has an executed Generator Interconnection Agreement \n(“GIA”).  PJM’s Proposed Interim NITS Limitation thus directly frustrates the Commission’s \nintention to allow a load taking interim, non-firm transmission service, and that is co-located \n \n12 See December 18 Order at P 159.   \n13 See id. at P 160. \n14 See id. (emphasis added).   \n15 See, e.g., ERock Protest at 2.   \n16 See December 18 Order at P 160."},{"page":4,"startToken":1012,"endToken":1314,"text":"4 \nwith a generator, to be served by such generator before both the load and generator “‘graduate’ to \nfull, front-of-meter service.”17 \nFor these reasons, and the reasons discussed further herein and in the ERock Protest, \nPJM’s proposed implementation of Interim NITS clearly runs afoul of the Commission’s \napplicable directives in the December 18 Order and should be rejected by the Commission.  \nB. \nResponses to Specific PJM Statements and Arguments in the April 24 Reply Brief \nThe fundamental disconnect between PJM’s proposed implementation of Interim NITS \nand the Commission’s applicable directives manifests in several of PJM’s statements and \npositions set forth in its April 24 Reply Brief, as addressed below.   \nFirst, PJM recognizes that the December 18 Order held that “when curtailed, Eligible \nCustomers taking [Interim NITS] on behalf of Co-Located Loads may be able to continue to take \nenergy from the Interconnection Customer with which they are co-located if PJM’s Tariff \notherwise allows.”18  Rather than explaining why its tariff would not otherwise allow a Co-\nLocated Load to take energy from a Co-Located Generating Facility (i.e., the Interconnection \nCustomer), or even proposing new tariff language that would codify such prohibition, PJM \ninstead states that it “thoroughly examined whether the Tariff should allow Interim NITS \ncustomers to directly take energy from the Co-Located Generating Facility when PJM has \ncurtailed the Eligible Customer’s access to the Transmission System” and determined that it \nshould not.19   \nPJM’s Proposed Interim NITS Limitation thus clearly departs from the Commission’s \ndirective because PJM has not identified any tariff provisions that would not “otherwise allow” a \n \n17 See December 18 Order. Commissioner Rosner, Concurring at P 11 (“Rosner Concurrence”). \n18 See April 24 Reply Brief at 16 (citing December 18 Order. at P 160 (emphasis added)).   \n19 See April 24 Reply Brief at 16-17 (emphasis added)."},{"page":5,"startToken":1314,"endToken":1742,"text":"5 \nCo-Located Load from receiving any capacity or energy from a Co-Located Generating Facility \nwhile the Co-Located Load is taking Interim NITS.  Moreover, for the reasons explained by \nERock in its Protest, PJM’s Proposed Interim NITS Limitation would need to be codified in the \nPJM Tariff (PJM’s filed rate) in order to be effectuated because it is a practice, inter alia, “that \naffect[s] rates and service significantly, that [is] reasonably susceptible of specification, and that \n[is] not so generally understood in any contractual arrangement as to render recitation \nsuperfluous.”20  Accordingly, for these reasons alone, the Commission should reject PJM’s \nProposed Interim NITS Limitation.   \n \nSecond, PJM avers that its Proposed Interim NITS Limitation is in line with the \nDecember 18 Order’s requirement that Interim NITS be designed around the principles that “(1) \nthe services are designed to serve loads that are ‘willing and able to control their withdrawals \nfrom the transmission system;’ and (2) the services are designed to allow PJM to maintain \nsystem reliability,”21 and that “Interim NITS will be curtailed when the system cannot support it \nin real time, whether with sufficient generation or transmission capacity.”22  But PJM’s argument \nmisses the mark entirely, as the ability for a Co-Located Load to take energy and capacity from a \nCo-Located Generating Facility during the interim period before “all Network Upgrades \nnecessary to provide NITS are complete,”23 enables the Co-Located Load “to control their \n \n20 See ERock Protest at 7 (citing Midcontinent Indep. Sys. Operator, Inc., 158 FERC ¶ 61,003, at P 69 & n.113 \n(2017) (citations and internal quotes omitted). See also, Sw. Power Pool, Inc., 170 FERC ¶ 61,125, at PP 35-36 & \nn.92 (2020) (noting that the filed rate doctrine “entitles customers to rely upon what is in a tariff, regardless of any \n‘one-way’ assertions made by the utility outside of Commission filings.” (citing W. Deptford Energy, LLC v. FERC, \n766 F.3d 10, 24 (D.C. Cir. 2014) (rejecting the Commission’s argument that interconnection studies provided notice \nfor financial responsibility for upgrades because the Commission provided “‘no reasoned explanation for expanding \nthe notice exception to encompass such one-way assertions, especially since generators have no apparent way to \nchallenge any costs such studies purport to assign’”)); Old Dominion Elec. Coop. v. FERC, 892 F.3d 1223, 1232 \n(D.C. Cir. 2018) (finding that a website statement at issue was not filed with the Commission, which “is required for \nall rate changes”)). \n21 See April 24 Reply Brief at 17 (citations omitted).   \n22 See id. \n23 See December 18 Order at P 160."},{"page":6,"startToken":1742,"endToken":2075,"text":"6 \nwithdrawals from the transmission system.”24  Further, as made clear in Commissioner Rosner’s \nconcurrence in the December 18 Order, the Commission knew that large load customers taking \nInterim NITS would only be “willing and able to control their withdrawals from the transmission \nsystem,” if they could rely upon their Co-Located Generating Facility during the interim period \nbefore necessary Network Upgrades are constructed.25 PJM’s Proposed Interim NITS Limitation \nthus directly contradicts the Commission’s directive for PJM to establish an interim, non-firm \ntransmission service.  \nThird, PJM appears to believe that requiring the Co-Located Generating Facility to be \nfully deliverable as a Capacity Resource during the interim period is necessary to “allow PJM to \nmaintain system reliability.”26  PJM avers that allowing a Co-Located Generating Facility to \nserve a Co-Located Load utilizing Interim NITS would “remove the co-located generator from \nserving the Transmission System as a whole during emergency or pre-emergency conditions,”27 \nand states that “to the extent the co-located generator is a committed Capacity Resource, the PJM \nRegion has first call on such resource’s energy to meet the region’s needs.”28  But PJM’s \nargument is inherently flawed because prior to the Co-Located Generating Facility completing \nPJM’s interconnection study process and receiving a GIA, it is not eligible to be a Capacity \nResource. \n \n24 See id. at P 204.   \n25 See Rosner Concurrence at P 11 (“In exchange for increased speed, these loads will bear the risk of being \ncurtailed when the grid is constrained until the transmission upgrades needed to provide service are constructed.  But \nthat doesn’t mean that the load will always have to shut down completely during peak periods.  Rather, if the co-\nlocated load is paired with a new generator, and that generator is still waiting to begin its own front-of-meter service, \nthe load can take service directly from the generator in the interim until both “graduate” to full, front-of-meter \nservice.”) (emphasis added). \n26 See April 24 Reply Brief at 18.  \n27 See id. (emphasis removed).   \n28 See id."},{"page":7,"startToken":2075,"endToken":2431,"text":"7 \nERock does not object to limiting a Co-Located Load from receiving any capacity or \nenergy from a Co-Located Generating Facility during emergency conditions once the Co-\nLocated Generating Facility has gone through the interconnection study process, has received a \nGIA, is a Capacity Resource, and the Co-Located Load receives firm service following the \ncompletion of necessary Network Upgrades.29  However, imposing such restrictions during the \ninterim period prior to the Co-Located Generating Facility receiving a GIA, and prior to such \nNetwork Upgrades being completed, would not allow PJM to in fact call on the Co-Located \nGenerating Facility as a Capacity Resource to meet any emergency.  Further, such restrictions \nwould render Interim NITS unworkable and conflict with the Commission’s directives regarding \nInterim NITS.30 \nMoreover, during the period in which the Co-Located Load operates on a non-firm basis, \nPJM can curtail the Co-Located Load during emergencies in order to maintain the reliability of \nthe overall system, while the Co-Located Generating Facility can serve the Co-Located Load so \nthat it does not go entirely offline. This arrangement enables PJM to maintain the overall \nreliability of the system while encouraging large loads to be curtailable by allowing them to rely \non their Co-Located Generating Facility until both the load and generating facility “graduate” to \nfull, front of meter service, as the Commission intended.31  This is not what PJM proposed. \nFurther, forcing the Co-Located Generating Facility to be dispatched under emergency \nconditions during the interim period before it has completed the generation interconnection study \nprocess, has a GIA and is eligible to be a Capacity Resource, would not only conflict with the \n \n29 See ERock Protest at 8 n. 29.  \n30 See, e.g., ERock Protest at 8-10; Comments of the Data Center Coalition, Docket No. ER26-1479-000, at 6 (Mar. \n16, 2026) (The Proposed Interim NITS Limitation “is unworkable because curtailment should limit use of the grid, \nnot prevent the customer from using the colocated resource it supplied, which supports Interim NITS in the first \nplace. If the customer cannot use that generation during curtailment, Interim NITS provides no practical value.”).  \n31 See Rosner Concurrence at P 11."},{"page":8,"startToken":2431,"endToken":2800,"text":"8 \nDecember 18 Order, but would also unjustly and unduly discriminate against Co-Located \nGenerating Facilities because it would impose obligations upon them that are not imposed upon \nsimilarly situated generators in PJM, i.e., generators that are in the process of being studied to be \nCapacity Resources but are not Co-Located Generating Facilities.32   \nLastly, PJM argues that it would be illogical to allow Interim NITS customers to rely on \ntheir non-firm Co-Located Generating Facilities during emergencies when full NITS customers \ncannot. PJM goes so far as to argue that it is “illogical to grant this right to the transitional, \ntemporary Interim NITS when such right is not available to full NITS customers.”33  But PJM \nhas it backwards.  Instead, it would be illogical for the Interim NITS customer not to be allowed \nto rely on its non-firm Co-located Generating Facility in order to remain online during \nemergencies when it is taking non-firm transmission service precisely because it is not taking \nfirm transmission service under NITS.34   \nFurther, it would be illogical (and not just and reasonable) to have a Co-Located Load \ntaking Interim NITS bear the full capital and development risk of bringing a Co-Located \nGenerating Facility online, only for PJM to dispatch their non-firm Co-Located Generating \nFacility for the benefit of other customers with firm NITS during emergencies – which is \nprecisely when other customers with firm NITS are being served, but the non-firm, Interim NITS \ncustomer is being curtailed.  PJM’s proposal would thus create an inequitable, unjust and \n \n32 See also, Calpine Oneta Power, L.P., 119 FERC ¶ 61,177, at P 35 (2007) (“As we found in the September 26 \nOrder and reaffirm below, AEP and Oneta are similarly situated. We also reaffirm our finding in the September 26 \nOrder that it is unduly discriminatory for the transmission provider to pay AEP for its reactive power capability and \ndeny payment to Oneta for its reactive power capability, because both entities are similarly situated.”) (citation \nomitted);  Bluegrass Generation Company, L.L.C., 118 FERC ¶ 61,214, at P33 (2007) (noting that denying \ncomparable treatment for similarly situated entities \"constitute[s] undue discrimination.\").  \n33 See April 24 Reply Brief at 21.   \n34 See Rosner Concurrence at P 11."},{"page":9,"startToken":2800,"endToken":3047,"text":"9 \nunreasonable situation where firm NITS customers would receive emergency reliability benefits \nat the direct expense of Interim NITS customers.  \nIII. \nCONCLUSION \nPJM should not be allowed to openly flout the Commission’s unequivocal directives in \nthe December 18 Order.  The Commission required PJM to establish “a new interim, non-firm \ntransmission service,”35 that will allow a load that is co-located with a generator to “take service \ndirectly from the generator in the interim until both ‘graduate’ to full, front-of-meter service” so \nthat the load will not “always have to shut down completely during peak periods.”36  Rather than \ncomplying with these and related directives, PJM’s Proposed Interim NITS Limitation undercuts \nthem.  Accordingly, for the reasons set forth herein, ERock respectfully requests that the \nCommission grant its Motion, consider this Answer and prohibit PJM from imposing its \nProposed Interim NITS Limitation.    \n \n \nJoel Yu \nSenior Vice President, Policy & External \nAffairs \nEnchanted Rock, LLC \n1113 Vine Street, Suite 101 \nHouston, TX 77002  \nJyu@enchantedrock.com \n \nJames Huang  \nDirector, Wholesale Markets Policy \nEnchanted Rock, LLC \n1113 Vine Street, Suite 101 \nHouston, TX 77002 \nJhuang@enchantedrock.com \nRespectfully submitted, \n \n/s/ Steven Shparber \n \nSteven Shparber \nOmar Bustami \nKatie Bekel \nMintz, Levin, Cohn, Ferris, Glovsky and \nPopeo, P.C. \n555 12th Street NW, Suite 1100 \nWashington, D.C. 20004 \n(202) 434-7417 \n \n \n \nSShparber@mintz.com \n \n \n \nOBustami@mintz.com \nKBekel@mintz.com  \n \n \n \n \n \n \n \nCounsel to Enchanted Rock, LLC \n \n  \n \nDated: May 7, 2026 \n \n35 See December 18 Order at P 160.   \n36 See Rosner Concurrence at P 11."},{"page":10,"startToken":3047,"endToken":3095,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day caused the foregoing to be served upon each person \ndesignated on the official service list compiled by the Secretary in the captioned proceeding.   \nDated at Washington, D.C., this 7th day of May 2026. \n/s/ Steven Shparber"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":271,"startToken":0,"endToken":363},{"p":2,"at":271,"title":"I. MOTION FOR LEAVE TO ANSWER","method":"printed heading","endPage":2,"endAt":1051,"startToken":363,"endToken":498},{"p":2,"at":1051,"title":"II. ANSWER","method":"printed heading","endPage":2,"endAt":1064,"startToken":498,"endToken":500},{"p":2,"at":1064,"title":"A. PJM’s Proposed Implementation of Interim NITS Is Fundamentally Flawed","method":"printed heading","endPage":4,"endAt":401,"startToken":500,"endToken":1074},{"p":4,"at":401,"title":"B. Responses to Specific PJM Statements and Arguments in the April 24 Reply Brief","method":"printed heading","endPage":9,"endAt":149,"startToken":1074,"endToken":2820},{"p":9,"at":149,"title":"III. CONCLUSION","method":"printed heading","endPage":10,"endAt":0,"startToken":2820,"endToken":3047},{"p":10,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":10,"endAt":285,"startToken":3047,"endToken":3095}]}