{"document":{"slug":"rec-20260508-5176","title":"Motion for Leave to Answer and Answer of Calibrant Energy et al. in response to the 04/24/2026 Answer of the Indicated PJM Transmission Owners","issued":"2026-05-08","accession":"20260508-5176","docket":"ER26-1479-000","group":"PJM co-location compliance","filer":"Calibrant EnergyAntora Energy LLCConvergent Energy and Power LP ,Eolian, LP ,Mainspring Energy ,Verrus LLC ,","kind":"answer","file":"sources/filings/text/20260508-5176_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260508-5176","tier":"record","sha256":"9ccdde3e51b138afeabb1e83912df3e105e50e826cd5368a7872c289f13ae3ce","pages":11,"tokens":2999,"emptyPages":[],"textThemes":["colo","flex"]},"pages":[{"page":1,"startToken":0,"endToken":313,"text":"1 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n) \nPJM Interconnection, LLC \n) \nDocket No. ER26-1479-000 \n) \n \nMOTION FOR LEAVE TO ANSWER AND ANSWER OF THE BTMG PARTIES \n \nPursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal \nEnergy Regulatory Commission (Commission), 18 C.F.R. §§ 385.212 and 385.213, Calibrant \nEnergy (Calibrant), Antora Energy, Inc. (Antora), Convergent Energy and Power (Convergent), \nEolian L.P. (Eolian), Mainspring Energy, Inc. (Mainspring), and Verrus, LLC (Verrus) (together, \nBTMG Parties) hereby move to answer and submit this Answer in response to the Answer of the \nIndicated PJM Transmission Owners (PJM TOs) filed on April 24, 2026, in the above-captioned \nproceeding. \nI. \nMOTION FOR LEAVE TO ANSWER \n \nAlthough the Commission’s procedural rules generally do not allow answers to answers, \nthe Commission may permit them for good cause.1 The Commission frequently accepts answers \nthat clarify the issues before the Commission, ensure a complete record, or otherwise assist the \nCommission in its decision-making.2 BTMG Parties respectfully request that the Commission \naccept this answer to clarify certain issues and assist the Commission with its decision-making. \n \n1 See 18 C.F.R. § 385.213. \n2 See, e.g., PJM Interconnection, L.L.C., 182 FERC ¶ 61,073, at P 13 (2023) (accepting answers to answers that \n“provided information that assisted us in our decision-making process”); New Fortress Energy LLC, 174 FERC ¶ \n61,207, at P 7 (2021) (accepting answers because they provided information that assisted the Commission’s \ndecision-making process); Alaska Gasline Dev. Corp., 171 FERC ¶ 61,134, at P 7 (2020) (accepting answers that \n“clarify the concerns raised and provide information that has assisted in our decision making”); Saltville Gas \nStorage Co., L.L.C., 164 FERC ¶ 61,212, at P 2 n.6 (2018) (accepting answers that “assist the Commission in \nunderstanding the issues raised, and will ensure a complete record”)."},{"page":2,"startToken":313,"endToken":612,"text":"2 \nII. \nARGUMENT \nA. \nBTMG Parties and PJM TOs Agree That Workable and Broadly Construed \nGrandfathering Provisions Are Necessary to Avoid Substantial Harm due to \nReasonable Reliance on Retail Behind-the-Meter-Generation (BTMG) Rules. \n \nThe PJM TOs support PJM’s 50 MW threshold but advocate that “this threshold be paired \nwith grandfathering provisions that appropriately recognize that industrial and commercial \ncustomers have relied on Retail BTMG rules and that eliminating the ability to continue relying \non those provisions could cause them substantial financial harm.”3 While the BTMG Parties \ncontest PJM TOs’ mischaracterization of the BTMG Parties’ protest, they agree with PJM TOs \non a critical point: the limits on BTMG arrangements must be paired with workable \ngrandfathering for projects that “would have been eligible for Retail BTMG treatment” but for \nimposition of the materiality threshold and “have made substantial progress toward completion” \nin order to protect the reasonable investment-backed expectations of PJM customers (and the \nBTMG developers) and to ensure just and reasonable rates. \n1. \nPJM TOs Mischaracterize BTMG Parties’ Position on the Materiality \nThreshold. \nAs an initial matter, PJM TOs do not accurately state the position of the BTMG Parties. \nPJM TOs claim that “[s]everal commentors argue that a nameplate-based threshold is \ninappropriate and urge the Commission to adopt a materially higher threshold, such as 200 \nMW.”4 PJM TOs do not address the substance of the BTMG Parties’ argument: BTMG Parties \nprotested PJM’s proposed netting threshold because it did not comply with the directive in the \nCommission’s order directing PJM’s compliance in this proceeding (Co-Location Order).5 PJM \nTOs do not demonstrate that PJM’s proposal imposes a “MW threshold for the amount of load \n \n3 PJM TOs Answer at 3. \n4 Id. at 2. \n5 See PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (Co-Location Order)."},{"page":3,"startToken":612,"endToken":926,"text":"3 \nthat Network Customers may net by using BTMG” as directed in ordering paragraph (F) of the \nCo-Location Order, and therefore is non-responsive to BTMG Parties’ argument.6 Instead, PJM \nTOs argue that a different threshold based on nameplate capacity would also be a just and \nreasonable replacement rate.7 But the question before the Commission in this compliance docket \nis not whether a nameplate-based threshold could be just and reasonable, nor whether the \nCommission should have imposed a nameplate-based threshold replacement rate in the Co-\nLocation Order (a matter to be contested only via a request for rehearing); rather the sole legal \nquestion before the Commission is whether PJM complied with the directives in Co-Location \nOrder. Because PJM did not, that is the end of the matter.   \n2. \nBTMG Parties and the PJM TOs Agree that Workable \nGrandfathering Provisions Are Essential to Ensure Just and Reasonable \nRates. \nIn any event, the BTMG Parties and the PJM TOs agree on a critical point regarding \nPJM’s proposed tariff revisions: the grandfathering provisions must be implemented so as to \navoid substantial harm to the investment-backed expectations of customers who relied on the \nexisting BTMG provisions, as the Commission required in its Co-Location Order. BTMG Parties \nagree with PJM TOs that: \n• Grandfathering treatment should extend to projects that are not yet in service and would \nhave been eligible for Retail BTMG treatment, but have made substantial progress \ntowards completion.  \n \n• The “existing contract” exception to the application of the new Retail BTMG rules \nshould be construed broadly to cover a wide range of contracts and recognition of \nrenewal rights in those contracts.  \n \n \n6 BTMG Parties Protest at 1 (citing Co-Location Order at Ordering P (F) & PP 179, 221). \n7 PJM TOs Answer at 2-3 (“PJM reasonably based the threshold on generator size—measured by cumulative \nnameplate rating—because generator capacity is static and administrable, whereas load can fluctuate”)."},{"page":4,"startToken":926,"endToken":1245,"text":"4 \n• Grandfathering treatment should be extended to existing Retail BTMG arrangements that \nhave been physically in service and operating for a significant period of time to avoid \ndisrupting these long-standing arrangements.8  \nAs the BTMG Parties explained in their protest, developing BTMG resources takes years and \nmillions of dollars in investment. Failure to grandfather projects that would have been eligible \nfor Retail BTMG treatment and that have made substantial progress towards completion and/or \nhave committed significant financial investments towards their development pursuant to \ncontractual arrangements would be unjust and unreasonable.9 As PJM TOs explain, “eliminating \nthe ability to continue relying on [previously applicable Retail BTMG rules] could cause \n[customers] substantial financial harm.”10 In their protest, BTMG Parties offered multiple ways \nto avoid this unjust and unreasonable outcome, including: extending the starting point from \nwhich grandfathering occurs (effectively providing more advance notice and opportunity to be \neligible for grandfathering)11 to customers already developing projects that would have been \neligible for Retail BTMG treatment; and/or increasing the size of the materiality threshold to 200 \nMW if the Commission elects to accept a materiality threshold based on nameplate capacity \n(effectively providing PJM customers more opportunity to realize the commercial benefit of their \npreexisting investment into BTMG projects).12 BTMG Parties agree with the PJM TOs’ proposal \nto ensure grandfathering of any projects that (1) “have made substantial progress towards \ncompletion”; (2) have an “existing contract,” within a broadly construed meaning of that phrase; \nor (3) are physically in service because such grandfathering is necessary to appropriately \n \n8 Id. at 3-4. \n9 BTMG Parties Protest at 13-15 (narrow grandfathering provisions “could leave retail customers who have been \ndeveloping projects for several years and have invested millions in infrastructure to serve loads wholly ineligible to \nnet, upsetting commercial expectations and threatening project viability”). \n10 PJM TOs Answer at 3. \n11 BTMG Parties Protest at 13-16. \n12 Id. at 12-13."},{"page":5,"startToken":1245,"endToken":1499,"text":"5 \nrecognize the years and substantial financial investments of PJM customers based on Retail \nBTMG rules. \nB. \nThe Record Supports Expanding Transmission Services Eligibility to \nSimilarly Situated Customers that Do Not Have Generation with a PJM \nInterconnection Agreement. \nPJM TOs urge the Commission to “reject the Joint Parties’ request that it reject or defer \naction on PJM’s proposal to limit the new transmission service options to Co-Located Load.”13 \nThey argue that “there is absolutely no evidence in the record to suggest that load-only customers \nshould be entitled to utilize these transmission services”14 and that “the new services are tied to \ngenerator-specific attributes that ordinary load-only customers do not share, including an \nassociated generator, separate metering from that generator, and the ability and willingness to \nprevent or limit withdrawals through the co-location configuration itself.”15 But the PJM TOs are \nwrong on both points:  \n(1) There is robust evidence in the record that load-only customers should be entitled to \nutilize these transmission services. The Commission’s core findings draw from \npleadings that demonstrate why load-only customers should be allowed to access the \nnew transmission services. \n(2) The new services are not tied to generator-specific attributes. Even if they were, that \nwould not justify denying service to co-location configurations where the generator \ndoes not inject into the PJM system.  \nRobust record evidence supports extending the new transmission services to load-only \ncustomers, including customers with BTMG. The evidence the Commission relied on in ordering \n \n13 PJM TOs Answer at 6. \n14 Id. \n15 Id. at 7."},{"page":6,"startToken":1499,"endToken":1905,"text":"6 \nPJM to develop the new transmission services applies both to co-location configurations \ninvolving PJM-interconnected generation, as well as BTMG or inherently flexible load that \nenables the same capabilities to limit grid withdrawals. Specifically, the Antora comments the \nCommission relied upon16 explained that Antora’s thermal battery technology provides for an \ninherently flexible, low-load factor load, whether or not co-located with generation.17 As Antora \nexplained with regard to these flexible loads, “[w]here a customer could have instead taken \ncurtailable transmission service that allows PJM and/or the [Electric Distribution Company] to \ncurtail its load if that service were offered, the failure to provide a service option that \nincorporates load flexibility will directly lead to costs for the interconnecting customer that do \nnot appropriately reflect its flexibility and resulting ability to avoid using high value energy or \ngrid capacity.”18  \nFurther, the Co-Location Order makes clear that PJM should take measures “to \nminimize the impact of [the BTMG rule] transition on existing BTMG customers,”19 and \nemphasizes that these BTMG rule revisions apply broadly beyond the context of Co-Located \nLoad.20 PJM is required to put forth a replacement rate for BTMG that is just and reasonable and \nnot unduly discriminatory. The record demonstrates that customers with behind-the-meter \ngeneration, like those with front-of-meter arrangements, can limit the amount of transmission \n \n16 See Co-Location Order at P199 n. 423 (citing Antora, April 23 Reply Comments, Docket Nos. EL25-49 et al., at \n11-12 (filed April 23, 2025)). \n17 Antora, April 23 Reply Comments, Docket Nos. EL25-49 et al., at 4 (April 23, 2025) (“Like electro-chemical \nbatteries, a significant portion of Antora’s thermal battery value comes from flexibility.  The battery is charged \nduring periods of high energy production and low demand, thereby helping reduce curtailment of renewable \nresources and allowing the thermal battery to absorb low value/negatively priced electricity.  Because thermal \nstorage can provide 24/7 heat over a multi-day period by charging only roughly 1/3 of the time, it can fully avoid \nperiods of high demand, high-capacity utilization and high electricity pricing.”). Id. at 6 (“PJM’s existing tariff is \nunjust, unreasonable, and unduly discriminatory because it does not offer any study process or form of transmission \nservice that properly accounts for highly flexible and low load factor loads such as Antora’s thermal energy \nstorage.”). \n18 Id. at 11-12 (cited by the Commission at n. 423).  \n19 Co-Location Order at P 222. \n20 Id. at P 186."},{"page":7,"startToken":1905,"endToken":2224,"text":"7 \nthey need, such that it would be not just and reasonable and unduly discriminatory to set forth a \nBTMG replacement rate that fails to offer the new transmission services opportunities to these \ncustomers. For example, PJM Industrial Customer Coalition explained that customers with \nBTMG may have an “identical impact to the transmission grid” as customers with PJM-\ninterconnected generation, arguing that the Commission should provide a transmission service \n“methodology that does not discriminate between or among classes of transmission customers” \nand that focuses on actual use of the transmission system.21 Other comments similarly argued \nthat transmission costs should follow the Commission’s cost causation principles, including \naccounting for where a facility is able to limit its use of the transmission system,22 and pointed \nout that “multiple viable configurations of co-located load and generation exist today, including \nboth front-of-meter and behind-the-meter designs.”23 In addition, Joint Parties in this docket \nexplained that “loads connected to behind-the-meter generation without interconnection rights” \nmay demonstrate the same capabilities as Co-Located Loads to “limit their energy withdrawals \nfrom the transmission system.”24  \nPJM and the PJM TOs may reasonably seek assurance that the relevant load is in fact \ncapable and obligated to limit its withdrawals. But the Commission can provide for such \nassurance in the relevant tariff provisions setting forth the new transmission service options \nrather than categorically excluding a class of market participants willing and able to limit \n \n21 PJM Industrial Customer Coalition & Industrial Energy Consumers of America, April 23 Reply Comments, \nDocket Nos. EL25-49 et al., at 9-10 (filed April 23, 2025) (emphasis in original).   \n22 Co-Location Order, 193 FERC ¶ 61,217 at P 63 (referencing Electricity Consumers Resource Council, April 23 \nReply Comments, Docket Nos. EL25-49 et al., at 7 (filed April 23, 2025)). \n23 Data Center Coalition, April 23 Reply Comments, Docket Nos. EL25-49 et al., at 7 (filed April 23, 2025) \n24 Joint Parties Protest at 10."},{"page":8,"startToken":2224,"endToken":2619,"text":"8 \nwithdrawals. The Commission has ample record to assess the technical requirements necessary to \nensure that any customer taking such service can appropriately limit withdrawals.25 \n \nAccordingly, the record of this compliance proceeding and the underlying show cause \nproceeding contains ample evidence to support extending new transmission service eligibility to \nall customers willing and able to limit withdrawals from the grid, including load-only customers \nserved by BTMG or otherwise able to consume flexibly. \nContrary to PJM TOs’ claims, nothing about such willingness and ability to limit \nwithdrawals is “tied to generator-specific attributes that ordinary load-only customers do not \nshare, including an associated generator, separate metering from that generator, and the ability \nand willingness to prevent or limit withdrawals through the co-location configuration itself.”26 \nRather than accepting PJM’s proposed restrictions, the Commission should require PJM to tailor \nnew transmission service eligibility more closely to the Commission’s justification in issuing the \nCo-Location Order: the willingness and ability to limit withdrawals from the transmission system \nunder specified circumstances. As noted above, loads beyond those co-located with generation \nwith injection rights are also able to limit withdrawals and may be interested in subscribing to the \nnew transmission services. These include loads served by BTMG as well as flexible loads like \nthose identified by Antora, among others. PJM TOs do not specify what generator-specific \nattributes these loads lack that would prohibit them from complying with any curtailment \n \n25 See, e.g., PJM, Initial Brief, Docket Nos. EL25-49 et al., Attachment A Illustrative Language for New Tariff, Part \nXI; Attachments F-3A and F-4; and Other Illustrative Tariff Revisions, §§710.4 & 710.5 (filed Feb. 23, 2026) \n(proposing technical and facilities installation requirements that Co-Located Loads must comply with before \ncommencing contract demand transmission service).  \n26 PJM TOs Answer at 7. Further, to the extent the Commission were to determine that any generator located at the \nsame point of interconnection must be separately metered in order for the customer to qualify for the new \ntransmission services, generation currently classified as BTMG could install the necessary equipment to meet the \nrequirement. But the framework put forth by Commission goes significantly further by requiring interconnection, \nleaving any generation that falls above the netting threshold stranded. Such customers would find themselves not \nonly exposed to transmission charges for the first time, but unable to appropriately leverage their existing generation \nto reduce transmission service requirements."},{"page":9,"startToken":2619,"endToken":2846,"text":"9 \nrequirements or instructions. And they cannot, because the ability to inject to the grid is not \nrequired to enable a load to limit withdrawals from the transmission system.  \nEven if PJM TOs were correct that something about the new transmission services \nnecessitated the presence of an associated generator or other attributes that such a generator \ncould provide, that would support, rather than preclude, extending new service eligibility at least \nto loads served by BTMG. These loads are associated with generation behind the point of \ninterconnection. The fact that they lack interconnection agreements and attendant rights to inject \nis immaterial to their ability to allow loads to limit withdrawals from the transmission system.  \n \nIf a load is able to meet technology-neutral technical requirements to demonstrate reliable \ncurtailment eligibility, it should be allowed to enroll in the new transmission services. \n \n \nRespectfully submitted, \n/s/ Matt Barnes \n \n \n \n/s/ Kim Smaczniak \nMatt Barnes \n  \n \n \n \nKim Smaczniak \nChief Commercial Officer \n \n \nMiles Farmer \nCalibrant Energy \n \n \n \nNathan Lobel \n4830 W. Kennedy Blvd, Suite 600 \n  \nRoselle LLP \nTampa, Florida 33609  \n \n \n300 New Jersey Ave. NW, Suite 300 \nmatthew.barnes@calibrantenergy.com  \nWashington, DC 20001 \n \n \n \n \n \n \nkim.smaczniak@rosellellp.com \n/s/ Noah Long  \n \n \n \nmiles.farmer@rosellellp.com \nNoah Long  \n \n \n \n \nnathan.lobel@rosellellp.com \nDirector, State and Regulatory Affairs  \n \nAntora Energy, Inc.   \n \n \nCounsel for Calibrant Energy \n200 West De Vargas St  \nSanta Fe, NM 87501  \nnoah.long@antora.com"},{"page":10,"startToken":2846,"endToken":2939,"text":"10 \n/s/ Katie Guerry \nKatie Guerry \nSVP Regulatory and Government Affairs \nConvergent Energy and Power \n7 Time Square, Suite 3504 \nNY, NY 10036 \nkguerry@convergentep.com \n \n/s/ Eric Stoutenburg  \n \n \n \nEric Stoutenburg \n  \n \n \n \nChief Development Officer  \n \n \nEolian L.P. \n  \n \n \n \n \n988 Howard Ave. Suite 200   \n \n \nBurlingame, CA 94010 \n  \n \n \neric.stoutenburg@eolianenergy.com   \n \n/s/ Brian Kauffman \nBrian Kauffman \nDirect, Wholesale Market Development \nMainspring Energy, Inc. \n3601 Haven Ave. \nMenlo Park, CA 94025 \nbrian.kauffman@mainspringenergy.com \n \n/s/ Jeff Bladen \nJeff Bladen  \nHead of Energy  \nVerrus, LLC  \n918 N Rengstorff Ave.  \n \n  \nMountain View, CA 94043 \n \n  \nbladen@verrusdata.com"},{"page":11,"startToken":2939,"endToken":2999,"text":"11 \nCERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary of the Commission in this \nproceeding. \n \nDated: May 8, 2026 \n/s/ Nathan Lobel \nNathan Lobel \nRoselle LLP \n300 New Jersey Ave. NW, Suite 300 \nWashington, DC 20001 \nnathan.lobel@rosellellp.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":767,"startToken":0,"endToken":114},{"p":1,"at":767,"title":"I. MOTION FOR LEAVE TO ANSWER","method":"printed heading","endPage":2,"endAt":3,"startToken":114,"endToken":314},{"p":2,"at":3,"title":"II. ARGUMENT","method":"printed heading","endPage":2,"endAt":18,"startToken":314,"endToken":316},{"p":2,"at":18,"title":"A. BTMG Parties and PJM TOs Agree That Workable and Broadly Construed","method":"printed heading","endPage":5,"endAt":108,"startToken":316,"endToken":1261},{"p":5,"at":108,"title":"B. The Record Supports Expanding Transmission Services Eligibility to","method":"printed heading","endPage":11,"endAt":4,"startToken":1261,"endToken":2940},{"p":11,"at":4,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":11,"endAt":373,"startToken":2940,"endToken":2999}]}