{"document":{"slug":"rec-20260508-5207","title":"Motion for Leave to Answer and Limited Answer of PJM Industrial Customer Coalition et al. to the Indicated PJM Transmission Owners’ 04/24/2026 Motion for…","issued":"2026-05-08","accession":"20260508-5207","docket":"ER26-1479-000","group":"PJM co-location compliance","filer":"PJM Industrial Customer CoalitionIndustrial Energy Consumers of AmericaAmerican Forest and Paper Association, Inc. ,National Railroad Passenger Corporation (\"Amtrak\") ,","kind":"answer","file":"sources/filings/text/20260508-5207_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260508-5207","tier":"record","sha256":"239f1c15db8661880c4687c109268da09e78fa787653217ec181d60a7d6620f8","pages":9,"tokens":2588,"emptyPages":[],"textThemes":["colo"]},"pages":[{"page":1,"startToken":0,"endToken":299,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \nPJM Interconnection, L.L.C. \n) \n) \n) \n)\n \n \nDocket No. ER26-1479-000 \nMOTION FOR LEAVE TO ANSWER AND LIMITED ANSWER  \nOF THE INDUSTRIAL CUSTOMER ORGANIZATIONS AND AMTRAK \n \nPursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s (“FERC” \nor “Commission”) Rules of Practice and Procedure,1 the PJM Industrial Customer Coalition \n(“PJMICC”), the Industrial Energy Consumers of America (“IECA”), the American Forest and \nPaper Association (“AF&PA”) (collectively, “Industrials”), and the National Railroad Passenger \nCorporation (“Amtrak”) hereby request leave to submit this Motion for Leave to Answer and \nLimited Answer (“Limited Answer”) to the Indicated PJM Transmission Owners’ (“Transmission \nOwners”) Motion for Leave to Answer and Answer (“April 24 Motion/Answer”).2 \nI. \nMOTION FOR LEAVE TO ANSWER \nThe Industrials/Amtrak respectfully request leave to file this Limited Answer, which is \nonly being filed in response to the unauthorized April 24 Answer of the Transmission Owners. \nRule 213(a)(2) generally prohibits answers to answers unless such answers have been authorized \nby the decisional authority.3 However, the Commission exercises its discretion to grant motions \nfor leave to submit answers when doing so will clarify the issues, assist in the Commission’s \n \n1 18 C.F.R. §§ 385.212 and 385.213. \n2 Motion for Leave to Answer and Answer of the Indicated Transmission Owners, Docket No. ER26-1479-000 (Apr. \n24, 2026). The Answer was filed on April 24, 2026, in response to various protests and comments on PJM \nInterconnection, L.L.C.’s (“PJM”) 60-Day Compliance Filing in the above-captioned proceeding. 60-Day Compliance \nFiling for Co-Located Load Related Revisions to Open Access Transmission Tariff to Comply with Commission \nOrder in Docket No. EL25-49, et al, Docket No. ER26-1479-000 (Feb. 23, 2026) (“Compliance Filing”). \n3 18 C.F.R. § 385.213(a)(2)."},{"page":2,"startToken":299,"endToken":683,"text":"2 \n \ndecision-making processes, or otherwise ensure an accurate and complete record.4  \nProcedurally, the Industrials/Amtrak question the Transmission Owners’ decision to file \nthe April 24 Motion/Answer well over 30 days after protests and comments were filed and after \nthe record had already been developed.5 The Industrials/Amtrak provide this Limited Answer \nsolely in response to the late-filed April 24 Motion/Answer, to assist the Commission in its \ndecision-making process.  \nOf note, the Industrials/Amtrak are representative of the entities who will be most directly \n(sometimes existentially) affected by the FERC’s determinations in this proceeding. While many \nparties have weighed in on PJM’s proposed retail Behind-the-Meter Generation (“BTMG”) rules, \nit is the industrial and institutional sectors whose future survival and growth are at issue in this \ndocket.6 These customers serve as the backbone of American manufacturing, health care, and \ntransportation services. Therefore, if the Commission accepts the April 24 Motion/Answer, the \nIndustrials/Amtrak respectfully ask the Commission to accept this Limited Answer, as well. \nII. \nLIMITED ANSWER \nA. \nThe Transmission Owners’ discussion of the Retail Threshold fails to address \nany arguments for a Retail Threshold of 200 MW or above and fails to address \nevidence showing the damage of a too-low Retail Threshold to resource \nadequacy, economic growth, and cost-causation. \nIn the April 24 Motion/Answer, the Transmission Owners address the materiality threshold \nfor application of retail BTMG rules (“Retail Threshold”), contending that “the 50 MW threshold \n \n4 See, e.g., PJM Interconnection, L.L.C., 145 FERC ¶ 61,035, at P 32 (2013); Wisconsin Pub. Serv. Corp., 144 FERC \n¶ 61,093, at P 27 (2013); Iberdrola Renewables, Inc., 137 FERC ¶ 61,185, at P 17 (2011); Virginia Elec. and Power \nCo., 125 FERC ¶ 61,391, at P 26 (2008). \n5 18 CFR § 385.213(d). \n6 As set forth in the Joint Protest and Comments of Industrial Customer Organizations and Amtrak, Docket No. ER26-\n1479-000 (Mar. 16, 2026) (“Industrials/Amtrak Protest”) and the Affidavit of James R. Dauphinais (“Dauphinais \nAffidavit”) attached thereto, traditional customers with on-site generation are facing enormous challenges that, \ndepending on the final order in this docket, will render some of that on-site generation uneconomic. See, e.g., \nDauphinais Affidavit at P 17. PJM also recognized the danger of units closing. See Compliance Filing at 12-15."},{"page":3,"startToken":683,"endToken":983,"text":"3 \n \nstrikes the appropriate balance between allowing continued use of Retail BTMG and appropriate \nlimitations to ensure reliability.” The Transmission Owners further state:  \nPJM reasonably selected 50 MW because that threshold aligns with the PJM \nBoard’s definition of large load additions, preserves existing treatment for smaller \nand longstanding Retail BTMG arrangements, and avoids sweeping in retail \ncustomers whose grid impacts are comparatively limited.7 \n \nThe Transmission Owners fail to substantiate their newly articulated position with any \nevidence. Despite extensive information provided in the Industrials/Amtrak’s Protest and in other \nfilings in this docket as to why a Retail Threshold of 200 MW is critical, the Transmission Owners \ndo not address any of these arguments.  \nIn contrast, the Industrials/Amtrak provided an extensive affidavit demonstrating that \ntraditional customers substantially larger than 50 MW reliably operate with retail BTMG. These \nare the factories that produce paper, pharmaceuticals, and steel; and the trains that carry thousands \nof passengers every day across the PJM footprint and beyond. Many of them are qualifying \nfacilities (“QF”) under the Public Utility Regulatory Policies Act of 1978 (“PURPA”), subject to \nefficiency standards (and, for non-cogeneration QFs, size limits). Some are operationally limited \nin what they can draw from the grid. These customers’ reliable operation of BTMG supports the \ncost-causation basis for the actual use approach of BTMG. \nThe Industrials/Amtrak also demonstrated that load under 200 MW—particularly \nindustrial and institutional load—is not driving today’s reliability challenges.8 The historical \nreliance on BTMG rules is supported by the Commission’s affirmations that actual use was the \noperative principle. The Commission was and is correct. Actual use should remain the operative \nprinciple, with the caveat that certain considerations must be made for loads that create substantial \n \n7 April 24 Motion/Answer at 2. \n8 Industrials/Amtrak Protest at 14-15."},{"page":4,"startToken":983,"endToken":1403,"text":"4 \n \nreliability risk. As the Commission stated, BTMG rules should (and will) be maintained; the \nquestion is to what extent. The Industrials/Amtrak Protest provided concrete, sound reasons why \nPJM’s proposed 50 MW is too low; they also provided information on the harm that will result if \n50 MW is selected, including loss of generation resources, which would heighten existing resource \nadequacy challenges.9 However, these facts have not been addressed (let alone refuted) by the \nTransmission Owners, who simply opine that 50 MW “strikes the appropriate balance.” In \ncontrast, the Industrials/Amtrak have presented compelling evidence that a 200 MW or greater \nRetail Threshold aligns with the Commission’s directive in the December 18, 2025, Order.10 \nB. \nThe Retail Threshold should be based on load, not generator size.   \nThe April 24 Motion/Answer also endorses PJM’s proposal that the Retail Threshold be \nbased on generator nameplate rating, stating: “The Order expressly directed PJM to propose a new \nMW threshold for Retail BTMG and explained that such a threshold should reduce the reliability \n \n9 In their Protest, the Industrials/Amtrak explained why PJM’s alternative Retail Threshold of at least 200 MW is \nsuperior to the main proposal of 50 MW, including: \n(1) A 200 MW Retail Threshold maintains incentives that bolster resource adequacy and grid \nefficiency, thereby avoiding inefficient transmission investment. \n(2) A 200 MW Retail Threshold preserves the focus on reliability challenges caused by super-\nsized load, while avoiding economically devastating outcomes for manufacturing, \ninstitutional and transportation facilities. \n(3) A 200 MW Retail Threshold avoids major administrative disincentives to operate on-site \ngeneration by avoiding the need to force existing retail customers into new and unfamiliar \nregulation, requiring them to become FERC-regulated public utilities, secure PJM membership, \nand undertake related credit and risk requirements.   \n(4) A 200 MW Retail Threshold aligns with regulatory logic that identifies various “tiers” of \nlarge load.  \n(5) A 200 MW Retail Threshold avoids burdening PJM with a significant number of studies \nfor existing generators (for generator deactivations or for BTMG that becomes Co-Located \nGeneration). \n(6) A 200 MW Retail Threshold de-emphasizes grandfathering and emphasizes stable rules for \ncustomers, a more durable approach. \n(7) A 200 MW Retail Threshold respects the importance of onshoring manufacturing, \nconsistent with federal and state economic development goals.  \nIndustrials/Amtrak Protest at 25; see also id. at 23-33. \n10 Order on Show Cause Proceeding, Directing Compliance Filings, Establishing Paper Hearing, and Granting In Part \nand Denying In Part Complaint, Docket Nos. EL25-49-000, EL25-49-001, AD24-11-000, EL25-20-000 \n(“Consolidated Dockets”) (Dec. 18, 2025) (“Order”)."},{"page":5,"startToken":1403,"endToken":1756,"text":"5 \n \nand resource adequacy risks posed by large Retail BTMG, while allowing smaller customers to \ncontinue netting in a transparent and not unduly discriminatory manner.”11 \nHowever, this argument misstates the Commission’s directive, as the Commission did not \npropose a generation-based threshold and did not limit netting to a particular customer type (e.g., \n“smaller customers”). Rather, the December 18, 2026, Order directs PJM to “propose a new MW \nthreshold for the amount of load at a particular electrical location that Network Customers may \nnet by using BTMG.”12 The language of the Order indicates that retail netting should continue at \nall retail electrical locations but only up to the Retail Threshold that the Commission ultimately \napproves.13 Unfortunately, PJM’s proposal is based on generation size, meaning that if generation \nis sized above the Retail Threshold, the electrical location would be entirely disqualified from \nnetting; it also incorporates an “all-or-nothing” design.  \nAs explained in the Industrials/Amtrak’s Protest, PJM’s design choice is contrary to a plain \nreading of the Order, creates an unfortunate economic “cliff” effect, and marks an unjustified shift \nfrom the current definition of BTMG (despite the Order directing that BTMG rules be \nmaintained).14 PJM’s proposal would produce radically different results for an entity just below \nthe threshold versus one just above, creating a paralysis of investment for growing American \ncompanies. In contrast, the Commission’s original directive is reasonable because it avoids an “all-\nor-nothing” design that disincentivizes growth and investment.   \n \n11 April 24 Motion/Answer at 2-3. \n12 Order at P 221 (emphasis added). See also Order at P 179 (“we direct PJM to maintain the current BTMG rules for \ncustomers that fall below a new MW materiality threshold for the amount of load at a particular electrical location that \nNetwork Customers may net using BTMG”). \n13 Paragraph 221 of the Order places no limiting language on which Network Customers or electrical locations may \n“reduce their transmission charges in a transparent, not unduly discriminatory fashion.”   \n14 See Order at P 221. The Dauphinais Affidavit provides additional reasons why a generation-based Retail Threshold \nis inappropriate. Dauphinais Affidavit at PP 55-60."},{"page":6,"startToken":1756,"endToken":2088,"text":"6 \n \nOn a related note, while the Industrials/Amtrak offered substantial explanation and \narguments concerning the unique role of QFs in the regulatory framework, the April 24 \nMotion/Answer does not address these issues or offer any insight into how PURPA regulations \nshould apply in the context of retail BTMG rules, despite the fact that many QFs, particularly \ncogeneration QFs, produce above 50 MW. The Industrials/Amtrak continue to urge the \nCommission to ensure QFs have access to back-up power as required by law.15 \nC. \nRegulatory certainty and legally durable rules are essential for investment. \nWhile grandfathering rules should be broad to avoid unnecessary economic \nharm, they should be complemented by a Retail Threshold that provides \ncertainty for future growth. \nThe Industrials/Amtrak appreciate the Transmission Owners’ recognition of the \nimportance of robust grandfathering to protect existing retail customers who would be financially \nharmed by the elimination of the BTMG operations.16 In particular, the Industrials/Amtrak agree \nthat the “existing contract” exception should be construed broadly and, when in doubt, the \ngrandfathering provision should be applied favorably to the existing customer.17 New or expanded \nfacility operations that have made material progress should be included in applicable \ngrandfathering provisions. \nWhile the Industrials/Amtrak appreciate the Transmission Owners’ robust support for \ngrandfathering provisions, reliance solely on grandfathering provisions adds complexity and \nuncertainty—two enemies of investment. For example: \n Does a factory remain grandfathered if it needs to add one new production line in \nthe future, increasing its demand by 1 MW? Can it make that investment without \n \n15 18 C.F.R. § 292.305(b)-(c). Subsection (c) states, in relevant part, “The rate for sales of back-up power or \nmaintenance power … [s]hall not be based upon an assumption (unless supported by factual data) that forced outages \nor other reductions in electric output by all qualifying facilities on an electric utility's system will occur simultaneously, \nor during the system peak, or both.”  \n16 Answer at 3-4. \n17 Id. at 3."},{"page":7,"startToken":2088,"endToken":2406,"text":"7 \n \ntriggering a transition to Co-Located Load status, with all the protective equipment \nrequirements and other operational requirements? \n \n If a large hospital system operating combined heat and power (“CHP”) is sold to a \ndifferent parent company or completes a merger, does grandfathering remain \nintact? \n \n Do facilities adding a new resource type lose grandfathering status? For example, \ndoes a facility seeking to complement its on-site resources with battery storage lose \nits grandfathering status altogether? \n \n When do large industrial companies who are making deliberate, methodical long-\nterm plans (e.g., 5, 10, 15, or 20 years) for electrification have to abandon their \nBTMG status and begin the involved process of becoming Co-Located Load? \n \nWhile the Commission may be able to address some of these scenarios, they create a \nregulatory minefield for industrial and institutional retail customers who may be making energy-\nefficient investments. Some manufacturers in the PJM region intend to expand through a \nmethodical, well-thought-out process (and without the speed-to-market demands that many data \ncenters now present). Over-reliance on grandfathering rules will make this process more daunting \nfor decision makers who must be accountable to their shareholders and stakeholders. \nUnfortunately, the risk that a facility may not be grandfathered will chill and disincentivize \ninvestment.  \nMost industrial and institutional entities providing critical goods and services must work \nvigilantly to remain viable in a competitive global economy. Investments are made deliberately \nand with care. These customers must have a reasonable degree of certainty about their investments, \nincluding regulatory certainty. While grandfathering helps to avoid short-term closure of BTMG \nunits (and potentially closure of some factories), it does not offer a roadmap for growth for existing \ncustomers who wish to expand and invest. Robust grandfathering rules should be complemented \nby a reasonable Retail Threshold of at least 200 MW of load, including all QFs who have rights to \ncost-based back-up power (which retail BTMG status provides) under PURPA and its \nimplementing regulations."},{"page":8,"startToken":2406,"endToken":2527,"text":"8 \n \nIII. \nCONCLUSION & REQUEST FOR RELIEF \nThe Industrials/Amtrak respectfully request that the Commission accept their Limited \nAnswer above; reject PJM’s Compliance Filing, consistent with their Protest and Comments filed \non March 16, 2026; and direct PJM to file a new compliance filing, consistent with the \nIndustrials/Amtrak’s Protest and Comments. \n \n \n \n \n \nRespectfully submitted, \n \nBy: \n/s/ Susan E. Bruce \n \n \n \nSusan E. Bruce \nKenneth R. Stark \nMatthew L. Garber \nMcNees Wallace & Nurick LLC  \n100 Pine Street \nHarrisburg, PA  17101 \nTel:  717-232-8000 \nE-mail: sbruce@mcneeslaw.com \nE-mail: kstark@mcneeslaw.com \nE-mail: mgarber@mcneeslaw.com \n \nCounsel to the PJM Industrial Customer Coalition, \nthe Industrial Energy Consumers of America, the \nAmerican Forest and Paper Association, and the \nNational Railroad Passenger Corporation (Amtrak) \n \nDated:  May 8, 2026"},{"page":9,"startToken":2527,"endToken":2588,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served via electronic transmission the foregoing upon \neach person designated on the official service list compiled by the Secretary in this proceeding.  \nDated this 8th day of May, 2026.  \n \n \n     /s/ Matthew L. Garber \n \nMatthew L. Garber \n100 Pine Street \nHarrisburg, PA  17101 \nTel:  717-232-8000 \nFax:  717-237-5433 \nE-mail: mgarber@mcneeslaw.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":876,"startToken":0,"endToken":120},{"p":1,"at":876,"title":"I. MOTION FOR LEAVE TO ANSWER","method":"printed heading","endPage":2,"endAt":1150,"startToken":120,"endToken":467},{"p":2,"at":1150,"title":"II. LIMITED ANSWER","method":"printed heading","endPage":2,"endAt":1171,"startToken":467,"endToken":470},{"p":2,"at":1171,"title":"A. The Transmission Owners’ discussion of the Retail Threshold fails to address","method":"printed heading","endPage":4,"endAt":760,"startToken":470,"endToken":1100},{"p":4,"at":760,"title":"B. The Retail Threshold should be based on load, not generator size.","method":"printed heading","endPage":6,"endAt":527,"startToken":1100,"endToken":1841},{"p":6,"at":527,"title":"C. Regulatory certainty and legally durable rules are essential for investment.","method":"printed heading","endPage":8,"endAt":5,"startToken":1841,"endToken":2407},{"p":8,"at":5,"title":"III. CONCLUSION & REQUEST FOR RELIEF","method":"printed heading","endPage":9,"endAt":0,"startToken":2407,"endToken":2527},{"p":9,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":9,"endAt":416,"startToken":2527,"endToken":2588}]}