{"document":{"slug":"rec-20260511-5167","title":"Motion for Leave to Answer and Answer of Constellation Energy Generation, LLC in response to PJM Interconnection, LLC's 04/24/2026 Reply Brief","issued":"2026-05-11","accession":"20260511-5167","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Constellation Energy Generation, LLC","kind":"answer","file":"sources/filings/text/20260511-5167_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260511-5167","tier":"record","sha256":"05c08452d157c1d819ddf08db1ec42fa8ae4af91875fd2a12708c9a7ffe85670","pages":39,"tokens":9651,"emptyPages":[],"textThemes":["study","colo","flex","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":340,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et al.\nLarge Loads Co-Located at Generating Facilities\nConstellation Energy Generation, LLC\n     v.\nPJM Interconnection, L.L.C.\n)\n)\n)\n)\n)\n)\n)\n)\nDocket No. EL25-49-000\nDocket No. EL25-49-001\nDocket No. AD24-11-000\nDocket No. EL25-20-000\n(Consolidated)\nMOTION FOR LEAVE AND ANSWER OF  \nCONSTELLATION ENERGY GENERATION, LLC \nConstellation moves for leave and submits this answer1 to reject four arguments made by \nPJM and the Indicated PJM Transmission Owners in their response briefs.2 First, just and \nreasonable rules for large load interconnection cannot be delayed until the end of the decade and \nclaims that such delays are “required”3 are belied both by PJM’s rush to adopt its own preferred \n“Connect and Manage” alternative and by the fact that other regions are managing to develop rules \nfor interruptibility much more quickly. Second, the Federal Power Act (“FPA”) requires study \nrequirements to be clearly written in the PJM Tariff because these study timelines and \nmethodologies significantly affect the provision of the new transmission services—and a lack of \n1 Constellation Energy Generation, LLC (“Constellation”) submits this answer and motion for leave pursuant to \nRules 212 and 213 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. §§ 385.212 and 385.213. \nConstellation respectfully submits there is good cause for the Commission to accept this answer as it is intended to \naid the Commission in its decision-making. Unless otherwise defined, all capitalized terms have the same meaning \nas in PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“December 18th Order”). \n2 Reply Brief of PJM Interconnection, L.L.C. at 57 (Apr. 24, 2026) (“PJM Apr. 24 Response”); Reply Brief of the \nIndicated PJM Transmission Owners (Apr. 24, 2026) (“Indicated TO Apr. 24 Response”). The Indicated PJM \nTransmission Owners (“Transmission Owners”) that filed the Indicated TO Apr. 24 Response are the same subset \nof Transmission Owners in PJM that filed the February 23, 2026 Initial Brief and March 25, 2026 Reply. \n3 PJM Apr. 24 Response at 57."},{"page":2,"startToken":340,"endToken":665,"text":"2 \nclarity and resulting protracted delays (including delays due to refusals to study) are what \ninstigated this proceeding in the first place. Third, draconian rules imposing disqualifications, \nsuspensions and other unnecessary restrictions on the Commission’s new transmission services do \nnot address any genuine “risks to reliability and resource adequacy”4 but instead merely limit \naccess to, frustrate, and otherwise discriminate against these landmark services. Fourth, the \nTransmission Owners’ excessive Grid Reliance Charge has no basis in principle or precedent, \nwhile Constellation has proposed a just and reasonable replacement rate the Commission can \nreadily adopt. In addition, there are several other areas in PJM’s response brief and revised \nIllustrative Tariff where clarification is needed or appropriate. \nI.\nThree Years Is Not “Required” to Replace an Unlawful Rate \nPJM claims “[a] June 1, 2029 effective date is required for the provision of these new, \ncurtailable services.”5 At the same time, PJM is expediting its Connect and Manage \ninterconnection framework to commence June 1, 2027, which would allow the interconnection of \nnon-capacity backed loads that are potentially interruptible during capacity shortages, unless the \nload brings its own (new) generation.6 This, ironically, is a rebranded Option 7 from PJM’s show-\ncause filing, which the Commission rejected in favor of Interim Network Integration Transmission \nService (“Interim NITS”).7 PJM did not seek rehearing on this point, yet PJM is nonetheless fast-\ntracking the version of interruptibility that the Commission rejected, while slow-boating the \n4 Id. at 45. \n5 Id. at 57. \n6 PJM, Connect & Manage Exemption and Reliability Backstop Process Impacts, Connect and Manage Senior Task \nForce, at 2 (Apr. 28, 2026), 20260428-item-03---connect--manage-exemption-and-reliability-backstop-process-\nimpacts-education---presentation.pdf (“Connect & Manage Presentation”). \n7 December 18th Order, 193 FERC ¶ 61,217 at P 200 (“we direct PJM to submit, within 60 days of the date of issuance \nof this order, a compliance filing to create a new interim, non-firm transmission service similar, but not identical, to \nPJM’s proposed option 7.”)."},{"page":3,"startToken":665,"endToken":950,"text":"3 \nversion of interruptibility that the Commission required. That is unacceptable. It is simply not \ncredible that PJM will take more than three years to implement Interim NITS allegedly due to \n“significant changes to PJM’s core Markets and Operations systems”8 but less than one year to \ncommence Connect and Manage, a framework not clearly defined let alone demonstrated to be \njust and reasonable.  \nAccordingly, the Commission should promptly approve the rates and terms for Interim \nNITS, with Constellation’s focused modifications,9 and make them effective no later than \nOctober 1, 2026, so that service can begin no later than June 1, 2027, the same date that PJM plans \nto commence Connect and Manage. Adopting Interim NITS as soon as possible—for pending and \nfuture NITS applicants—should not be difficult. PJM “designed the new Interim NITS to basically \nbe treated the same as regular, full NITS.”10\nII.\nStudy Procedures and Deadlines Must Be in the Tariff \nThe study procedures for the new transmission services must be identified clearly and \nspelled out in the tariff. Indeed, additional studies may not be needed at all to implement Interim \nNITS. As PJM states, it could determine that “the NITS study already conclusively answers the \nquestion of whether and how much Interim NITS may be provided” and grant Interim NITS \n“immediately.”11 PJM nevertheless argues, first, that its Illustrative Tariff properly details how \n8 PJM Apr. 24 Response at 57. \n9 Response Brief of Constellation Energy Generation, LLC at 7 (Apr. 24, 2026) (“Constellation Apr. 24 Response”); \nsee also Reply Brief of Constellation Energy Generation, LLC at 14-25, 29 (Mar. 25, 2026) (“Constellation Mar. 25 \nReply”). \n10 PJM Apr. 24 Response at 1. \n11 Id. at 27."},{"page":4,"startToken":950,"endToken":1271,"text":"4 \nPJM will study requests for new transmission services.12 Second, PJM claims that load integration \nstudies are outside the scope of the Commission’s jurisdiction.13 Neither argument has merit. \nA. The Commission Should Require Clear and Detailed Study Requirements to \nbe on File \nThe Illustrative Tariff does not contain any clear statement of what studies will be required \nfor the new transmission services. Rather, it states merely that PJM will determine “whether \nadditional studies are needed”14 for Interim NITS and “will coordinate with the affected \nTransmission Owner(s) to complete studies, including load integration studies”15 for Contract \nDemand Services. Contrary to PJM’s assertions, these vague statements do not come close to \n“appropriately detail[ing] PJM’s process, role, and standards for studying requests for these new \ntransmission services.”16 Indeed, the only “detail” that can be gleaned from the Illustrative Tariff \nis that studies may be conducted. There is no indication of what type of studies will be conducted—\nother than the Transmission Owners’ load integration studies—or the methodologies PJM will use \nto assess whether the transmission system can “reliably” provide the new transmission services.  \nThese are not mere “implementation” details that are missing from the Illustrative Tariff. \nThese terms directly affect eligibility for Interim NITS and Contract Demand Services, which \nclearly is a core requirement of the service.17 Requirements establishing the type of studies \nperformed and methodologies used to assess whether PJM can provide the new transmission \n12 Id. at 22. \n13 Id. at 34. \n14 Illustrative Tariff, Part XI, § 704.1. \n15 Id. at § 710.3. \n16 PJM Apr. 24 Response at 22. \n17 December 18th Order, 193 FERC ¶ 61,217 at P 200 (“Moreover, this new service would be optional for an Eligible \nCustomer seeking NITS on behalf of a Co-Located Load and would only be available to the extent PJM determines \nthat it can provide some level of interim service reliably.”) (emphasis added)."},{"page":5,"startToken":1271,"endToken":1767,"text":"5 \nservices reliably are “practices that affect rates and service significantly, that are realistically \nsusceptible of specification, and that are not so generally understood in any contractual \narrangement as to render recitation superfluous.”18 PJM has a “statutory obligation to file \nsignificant changes to its rates and ‘practices … affecting such rates.’”19 It is irrelevant whether \nstakeholders have the “fulsome opportunity to participate”20 in the development of PJM’s Manuals \nbecause including this material is part of PJM’s compliance obligation.21 \nAccordingly, the Commission should direct PJM to set forth clear and specific study \nrequirements in the Tariff. At a minimum, PJM should specify in its Tariff the violations that will \nbe studied and the studies to be conducted for each, the deadline for completing each study and \nsteps taken if study deadlines are not met, and defined remediation for specific violations found. \nThe record in this long proceeding underscores that it is critical for these study rules and deadlines \nto be on file to effectuate the Commission’s and the Trump Administration’s commitment to \nproviding prompt service to large loads.22\n18 City of Cleveland v. FERC, 773 F.2d 1368, 1376 (D.C. Cir. 1985) (emphasis in original). \n19 Keyspan-Ravenswood, LLC v. FERC, 474 F.3d 804, 811 (D.C. Cir. 2007) (internal quotations omitted). \n20 PJM Apr. 24 Response at 33. \n21 See December 18th Order, 193 FERC ¶ 61,217 at P 219 (requesting briefing on rates, terms, and conditions for the \nnew transmission services); see also Keyspan-Ravenswood, LLC v. FERC, 474 F.3d at 811 (“[T]he Commission \nprovides no reason to believe that Ravenswood’s participation in such a stakeholder process relieved NYISO of its \nstatutory obligation to file significant changes to its rates and ‘practices … affecting such rates.’”). \n22 See, e.g., Constellation Complaint at 7 (“Exelon is refusing to process necessary studies on these grounds, \ndemanding expensive upgrades under their unfiled interconnection procedures, delaying agreed-upon work which \nwill force a nuclear plant to take additional outages, and forcing additional services to be procured.”); id. at 7-8. \n(“Exelon fulfilled its responsibilities as an interconnection provider to review PJM’s necessary studies for one \nConstellation nuclear station, the LaSalle Clean Energy Center (‘LaSalle’), but later refused to do so at the other two \nstations, insisting that Constellation or its potential customer must first apply for retail service and designate what \nsort of wholesale transmission service it will take from Exelon.”); id. at 17 (“But for Constellation’s … Limerick \nClean Energy Center (‘Limerick’) in Pennsylvania, Exelon has refused to conduct its review of PJM’s completed \nnecessary studies, insisting that Constellation or its potential customer must first apply for retail service and \ndesignate what sort of wholesale transmission service it will take from Exelon.”); id. at 8 (“projects are being held \nhostage by a few monopolies refusing to cooperate with reliability studies related to interconnection modifications”); \nid. at 10 n.25 (“Exelon refuses to review co-location reliability studies as required by the OATT and pro forma ISA”)"},{"page":6,"startToken":1767,"endToken":2403,"text":"6 \nB. Transmission Owner Load Integration Study Requirements are Unwritten \nand Undisclosed Policies that Significantly Affect the Commission’s \nLandmark Transmission Services \nThe Commission has jurisdiction to regulate load integration studies in connection with \njurisdictional transmission service. PJM is wrong to assert that “any ‘lack of detail’” regarding \nthose studies is justified for jurisdictional reasons.23 The Commission has jurisdiction over all \ntransmissions, including transmissions to end users.24 The courts have long held the Commission \ncan regulate practices affecting rates within its jurisdiction, even if the Commission’s regulation \ntouches upon state authority.25 Load integration studies, which determine “whether (and to what \n(citing Constellation PDO Protest, Exhibit 1, Declaration of James R. McCoskey at ¶ 13); id. at 16 (“Proposed Fully \nIsolated Co-Located data center projects in PJM are currently being held hostage by one or two monopoly utilities’ \nrefusal to cooperate … with reliability studies related to interconnection modifications.”); see also Constellation \nEnergy Generation, LLC November 21, 2025 Supporting Comments, Docket No. RM26-4-000 at 3-4 (Nov. 21, \n2025) (“Some Transmission Owners have simply refused to participate in PJM’s studies to analyze reliability \nimpacts; and some, acting under unfiled interconnection study procedures, have changed their entire construct and \ntimetable for processing load studies.”); Answer of Constellation Energy Generation, LLC, PJM Interconnection, \nL.L.C. et al., Docket Nos. EL25-49-000, et al., at 3 (Apr. 23, 2025) (“The Indicated Transmission Owners read the \nexisting Tariff to require this one-size-fits-all limitation, and they have refused to perform studies for new load \nseeking a different configuration.”) (“Constellation Apr. 23, 2025 Answer”); id. at 14 (“What is more, regardless of \nwhat the Tariff actually says and does not say, some of the Indicated Transmission Owners have refused to cooperate \nin PJM’s ‘necessary studies’ process unless the load agrees to taking NITS, claiming justification under the Tariff. \nSome of the Indicated Transmission Owners have refused to process necessary studies, demanded expensive \nupgrades under their unfiled interconnection procedures, and forced a generator seeking to serve co-located load to \nprocure additional services not required by the Tariff.”) (citing Constellation Complaint at 7); Constellation \nComplaint at 9 (“Exelon’s also is refusing to perform work on LaSalle’s interconnection facilities to accommodate \nco-location, none of which affects the grid. Exelon’s refusal to complete previously agreed-upon work as scheduled \nduring an upcoming planned outage will increase costs to Constellation by $15.3-$19 million at that site alone, just \nso Exelon can pursue its litigation positions.”); see also PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at P 75 \n(2025) (“[T]here are allegations in the record that Exelon has delayed work on Constellation’s requests to co-locate \nload with its generators at certain facilities due to Exelon’s concerns that such requests are not allowed under the \nTariff without arranging for wholesale transmission or retail distribution service.”). \n23 PJM Apr. 24 Response at 34 (“at root, … Constellation’s complaints regarding the level of detail in PJM’s study \nprocedures generally concern the Transmission Owner’s load integration studies”). \n24 16 U.S.C. § 824(a); New York v. FERC, 535 U.S. 1, 20 (2002) (“[T]he FPA authorizes FERC’s jurisdiction over \ninterstate transmissions, without regard to whether the transmissions are sold to a reseller or directly to a \nconsumer.”); December 18th Order, 193 FERC ¶ 61,217 at PP 170, 173-74. \n25 See, e.g., New Eng. Power Generators Ass’n v. FERC, 757 F.3d 283, 290-91 (D.C. Cir. 2014) (upholding the \nCommission’s mitigation of buyer-side market power as to out-of-market entrants as not “improperly regulating \n‘facilities used for the generation of electric energy”); id. at 290 (“We have previously held that the Commission has \njurisdiction to regulate certain parameters of the capacity market related to the price of capacity, even if those \ndeterminations touch on states’ authority.”); Conn. Dep’t of Pub. Util Control v. FERC, 569 F.3d 477, 481-83"},{"page":7,"startToken":2403,"endToken":2863,"text":"7 \nlevel)” the new transmission services can be reliably provided (that is, whether the new \ntransmission services are provided at all), easily fall within that scope.26\nOn rehearing, and on its own accord,27 the Commission should exercise its jurisdiction over \nthe load integration studies needed to provide jurisdictional transmission service and direct those \nload integration studies to be on file.28 At a minimum, the PJM Tariff should specify the violations \nthat will be studied and the studies to be conducted for each, the deadline for completing each \nstudy and steps taken if study deadlines are not met, and define remediation for specific violations \nfound. Otherwise, the Commission risks neutering its December 18th Order by allowing \nrecalcitrant Transmission Owners an avenue to delay or disfavor the Commission’s new \ntransmission services.29\nIII.\nThe Commission Should Reject Certain Proposed Strictures on the New Transmission \nServices \nPJM claims that its draconian disqualification and suspension scheme is necessary to \naddress “unique reliability and resource adequacy risks” of integrating large loads into PJM’s \n(upholding Commission’s authority to regulate the Installed Capacity Requirement, even if the requirement could \nnecessitate the construction of facilities, a matter traditionally within the state’s jurisdiction); Municipalities of \nGroton v. FERC, 587 F.2d 1296, 1303 (D.C. Cir. 1978) (finding the Commission’s capacity deficiency charge does \nnot encroach on state jurisdiction, even though it may “motivate [utilities] to develop sufficient capacity to meet \ntheir load requirements”). \n26 Illustrative Tariff, Part XI, § 710.3 (“Transmission Provider will coordinate with the affected Transmission \nOwner(s) to complete studies, including load integration studies, which will provide data relevant to the \ndetermination of whether (and to what level as applicable) (i) Firm Contract Demand Transmission Service can be \nreliably provided and identify any necessary enhancements to the Transmission System to accommodate the \nrequested level of service, and/or (ii) Non-Firm Contract Demand Transmission Services can be reliably provided.”)  \n27 16 U.S.C. § 825l(a) (upon a request for rehearing, “the Commission shall have power to grant or deny rehearing or \nto abrogate or modify its order without further hearing”). \n28 16 U.S.C. § 824d(c) (“[E]very public utility shall file with the Commission … all rates and charges for any \ntransmission or sale subject to the jurisdiction of the Commission, and the classifications, practices, and regulations \naffecting such rates and charges, together with all contracts which in any manner affect or relate to such rates, \ncharges, classifications, and services.”); Fla. Mun. Power Agency v. Duke Energy Fla., LLC, 167 FERC ¶ 61,138, \nat P 43 (2019) (finding an “unwritten policy constitutes a practice that significantly affects the terms and conditions \nof transmission service … and, therefore, should have been filed with the Commission for Commission review.”). \n29 See supra note 22."},{"page":8,"startToken":2863,"endToken":3106,"text":"8 \nTransmission System.30 Similarly, PJM claims that limiting Non-Firm Contract Demand Service \nto times when the Co-Located Generating Facility is on outage is “appropriate” because of \nunidentified “reliability and operational issues inherent in providing this service.”31 The \nCommission should reject both. \nA. PJM’s Proposed Disqualification and Suspension Scheme is Not a Just, \nReasonable and Non-Discriminatory Replacement Rate \nPJM fails to demonstrate that “unique reliability and resource adequacy risks” justify the \nextreme and unprecedented penalties PJM proposes with respect to the Commission’s new \ntransmission services.  \nFirst, existing practice shows that PJM’s proposal is unwarranted. PJM Transmission \nCustomers taking Non-Firm Point-To-Point Transmission Service are not subject to suspension or \ndisqualification for unreserved use of the transmission system.32 PJM provides no reason why \ncustomers taking the new non-firm transmission services should be treated any differently. \nNotably, SPP proposes no suspension or disqualification of interruptible loads as part of its \nConditional High Impact Large Loads Service (“CHILLS”).33 If SPP can manage interruptible \nloads without such draconian penalties, PJM should similarly be capable of doing so.  \nSecond, the one reliability incident that PJM highlights to defend its proposal—when \n“approximately 1,500 MW of data centers disconnected simultaneously and unexpectedly from \nthe [Bulk Electric System] due to a transmission line fault in 2024”34—involved traditional grid \n30 PJM Apr. 24 Response at 45. \n31 Id. at 6. \n32 Constellation Mar. 25 Reply at 19-20. \n33 Id.\n34 PJM Apr. 24 Response at 41-42."},{"page":9,"startToken":3106,"endToken":3435,"text":"9 \nconnected load, not a Co-Located Load.35 In fact, this incident illustrates how co-locating load \nwith generation can provide benefits to the grid as compared to direct grid connections. As former \nPJM Chief Operating Officer Michael Kormos previously explained, “had those data centers been \nco-located with a generator (especially a nuclear generator), it is possible that the load would not \nhave dropped offline as a result of the load being closer to the voltage source.”36\nThird, PJM fails to explain how its resource adequacy concerns justify its disqualification \nand suspension scheme. To the extent PJM’s resource adequacy concerns stem from Interim NITS \nand Non-Firm Contract Demand Service being non-capacity backed,37 then PJM should have the \nsame concern regarding the non-capacity backed loads that could be interconnected under its \nConnect and Manage framework and would be required to curtail during capacity shortfalls. But \nPJM has proposed no such penalties under the Connect and Manage framework, showing that \nPJM’s real agenda here is to discourage use of the transmission services it disfavors.38\nFourth, a four-month suspension is not “consistent” with NERC requirements as PJM \nclaims.39 The NERC Reliability Standards that PJM cites—PRC-004-6 (Protection System \nMisoperation Identification and Correction) and PRC-012-2 (Remedial Action Schemes)—set \nforth a process for investigating whether protection systems misoperated and for developing a \nCorrective Action Plan if appropriate.40 Neither Reliability Standard, however, calls for suspension \n35 Constellation Apr. 23, 2025 Answer, Exhibit 5, at ¶ 7 (Kormos Affidavit). \n36 Id.\n37 See infra pp. 13-14 (explaining the Commission rejected the previously proposed Option 7 that provided non-\ncapacity backed loads would have been interconnected on the condition they would be curtailed before all other load \nduring capacity shortfalls).  \n38 See generally Connect & Manage Presentation. \n39 PJM Apr. 24 Response at 40. \n40 See, e.g., Reliability Standard PRC-004-6, Protection System Misoperation and Identification, at R1 (“Each \nTransmission Owner, Generator Owner, and Distribution Provider that owns a BES interrupting device that operated"},{"page":10,"startToken":3435,"endToken":3848,"text":"10 \nor disqualification of service while an investigation is ongoing. Indeed, such a suspension would \nbe fundamentally unjust and unreasonable, as it would deny the load a service to which it is \nentitled—potentially with ruinous economic consequences—without any finding of fault. \nB. Limiting Non-Firm Contract Demand Service to Temporary Derates or \nOutages Is Non-Compliant and Unreasonable \nPJM claims it must limit Non-Firm Contract Demand Service to temporary derates or \noutages because of “the inherent risks to the Transmission System and operational complexities \nassociated with providing this service on a continuous basis.”41 Based on this logic, PJM should \nalso limit Non-Firm Point-to-Point Transmission Service. PJM does not. Indeed, if the customer \ntaking Non-Firm Point-to-Point Transmission Service is willing to pay through congestion, under \nthe Transmission Loading Relief Procedure, PJM only curtails the service after all other measures \nhave failed to maintain system reliability.42\nThe Transmission Owners’ attempt to support PJM’s limitation on Non-Firm Contract \nDemand Service fares no better. Citing several of PJM’s unsubstantiated claims, Transmission \nOwners state, “facilities serving large loads will likely have multiple feeders serving load” that \nunder the circumstances in Parts 1.1 through 1.3 shall, within 120 calendar days of the BES interrupting device \noperation, identify whether its Protection System component(s) caused a Misoperation ….”); id. at R5 (“Each \nTransmission Owner, Generator Owner, and Distribution Provider that owns the Protection System component(s) \nthat caused the Misoperation shall, within 60 calendar days of first identifying a cause of the Misoperation: … \nDevelop a Corrective Action Plan (CAP) for the identified Protection System component(s), and an evaluation of \nthe CAP’s applicability to the entity’s other Protection Systems including other locations” or “Explain in a \ndeclaration why corrective actions are beyond the entity’s control or would not improve BES reliability, and that no \nfurther corrective actions will be taken.”); Reliability Standard PRC-012-2, Remedial Action Schemes, at R5 (“Each \nRAS-entity, within 120 full calendar days of a RAS operation or a failure of its RAS to operate when expected, or \non a mutually agreed upon schedule with its reviewing Reliability Coordinator(s), shall” “Participate in analyzing \nthe RAS operational performance to determine whether” the “System events and/or conditions appropriately \ntriggered the RAS,” the “RAS responded as designed,” the “RAS was effective in mitigating BES performance \nissues it was designed to address,” or the “RAS operation resulted in any unintended or adverse BES response.”). \n41 PJM Apr. 24 Response at 7. \n42 PJM Manual 13, § 5.6."},{"page":11,"startToken":3848,"endToken":4125,"text":"11 \nwill “add[] complexity and reduc[e] the reliability and overall security of the system.”43 PJM and \nTransmission Owners continue to provide no justification or explanation for requiring multiple \nfeeders.44\nTransmission Owners also claim “there is the possibility of interactions between RAS in a \ntightly coupled network such as PJM, increasing the possibility of misoperations.”45 This \ncircumstance is possible but unlikely. Multiple RAS in an area is a sign the transmission \ninfrastructure is inadequate and the area has increased reliability risks. As Mr. Kormos explained, \n“[g]iven the increased reliability risks … most Co-Location Arrangements with new generation \nare unlikely to locate in areas without robust transmission.”46\nIV.\nThe Transmission Owners’ Grid Reliance Charge is Based Neither on Principle Nor \nPrecedent \nThe Commission should reject the Transmission Owners’ Grid Reliance Charge and adopt \nthe minimum system method as recommended by electricity market expert Zachary Ming.47 The \nTransmission Owners’ Grid Reliance Charge is arbitrary and unmoored from cost causation \nprinciples. As Mr. Ming explains in his Reply Testimony in Attachment 1, the Transmission \nOwners’ proposal is “an improvised approach lacking any theoretical foundation and disconnected \nfrom any cost-causation principle, designed to produce an outcome that ‘feels right’ to the \nTransmission Owners.”48 Their proposal includes all the depreciation costs for the full cost of \n43 Indicated TO Apr. 24 Response at 4-5. \n44 Constellation Mar. 25 Reply at 30. \n45 Indicated TO Apr. 24 Response at 5. \n46 Constellation Apr. 24 Response, Exhibit 1, at ¶ 11 (“Second Affidavit of Michael Kormos”). \n47 Constellation Mar. 25 Reply, Attachment 1 (“Ming Initial Testimony”). \n48 See Reply Testimony of Zachary Ming at 10:18-20 (“Ming Reply Testimony”)."},{"page":12,"startToken":4125,"endToken":4418,"text":"12 \nsizing the transmission system components to serve peak load.49 This would force customers that \ndo not impose demand on the grid to pay for transmission components that are sized to serve peak \nload.50 The Transmission Owners’ proposal also arbitrarily excludes costs related to rate of return \nand taxes.51\nConstellation’s proposal leverages the minimum system method, a principled methodology \ngrounded in precedent, to produce a just and reasonable rate that ensures Co-Located Loads pay \ntheir fair share of the transmission system based on how they actually use it—which is to receive \nancillary services, not to draw power from the grid. The minimum system method is a “well-\naccepted framework for applying cost-causation principles.”52 It is not “extremely challenging to \nimplement.”53 Numerous jurisdictions across North America have applied the minimum system \nmethod at the distribution level for decades.54 And as Mr. Ming explains, “[t]here is no reason that \nit cannot similarly be applied in the context of the transmission system—there has just not \npreviously been any need to do so.”55\nIn his initial testimony, using publicly available data, Mr. Ming estimated that a minimum \nsystem yielding between 2% and 10% of actual system costs is reasonable, and he recommended \na minimum transmission system of 6%.56 The Commission can adopt a Grid Reliance Charge \nbased on 6%, or up to 10%, of the NITS rate as a reasonable rate that can be practically \n49 Id. at 10:6-8. \n50 Id. at 14:1-5. \n51 Id. at 8:7-12. \n52 Id. at 10:8-15. \n53 Indicated TO Apr. 24 Response at 24. \n54 Ming Reply Testimony at 18:7-11. \n55 Id. at 14:12-14. \n56 Ming Initial Testimony at 19:3-5; id. at 21:17-20."},{"page":13,"startToken":4418,"endToken":4743,"text":"13 \nimplemented. If the Commission believes there should be additional consideration of what \nconstitutes a minimum system, the Commission can direct PJM to conduct a minimum system \nstudy. But the Commission should reject the Transmission Owners’ unsupported and inflated \nproposal. \nV.\nRequested Clarifications of PJM’s Response Brief and Modifications to Revised \nIllustrative Tariff \nThere are five areas in PJM’s response brief and revised Illustrative Tariff where \nclarification is needed or appropriate. \nFirst, PJM’s statement that an “Interim NITS customer would only be curtailed … if the \nsystem is in an unreliable state due to transmission system violations or capacity/reserve \nshortages”57 improperly conflates Interim NITS and the rejected Option 7.58 Under the rejected \nOption 7, non-capacity backed loads would have been interconnected on the condition they would \nbe curtailed before all other load during capacity shortfalls.59 The Commission found this option \n“too broad and not sufficiently detailed to direct as a replacement rate.”60 No party, including PJM, \nsought rehearing challenging the Commission’s rejection. PJM now attempts to reinstate the \n“capacity/reserve shortage” curtailment criterion. But PJM failed to seek rehearing of this issue \nand cannot bypass the Federal Power Act’s rehearing requirements.61 The Commission should \nreject this attempt62 and direct PJM to revise Part XI, Section 705.2 of its Illustrative Tariff to \n57 PJM Apr. 24 Response at 20 (emphasis added); see also id. 18 (“Interim NITS must be designed to allow PJM to \nmaintain system reliability—both from a transmission and capacity perspective.”). \n58 December 18th Order, 193 FERC ¶ 61,217 at P 202. \n59 PJM Answer to February 2025 Show Cause at 18-19 (March 24, 2025). \n60 December 18th Order, 193 FERC ¶ 61,217 at P 202. \n61 16 U.S.C. § 825l(a). \n62 See PJM Interconnection, L.L.C., 195 FERC ¶ 61,030, at P 27 (2026) (rejecting PJM attempt to change a \nCommission-directed definition through its compliance filing because, among other things, “no party, including"},{"page":14,"startToken":4743,"endToken":5034,"text":"14 \nspecify that Interim NITS shall only be curtailed before Firm Contract Demand Service and NITS \nif the system is in an unreliable state due to transmission system violations. During capacity/reserve \nshortages, like all other loads, Co-Located Loads taking Interim NITS should only be curtailed \nafter PJM has taken all real-time emergency procedure steps and still cannot provide adequate \ncapacity to meet PJM’s load. \nSecond, Constellation supports PJM’s statement that “Eligible Customers serving Co-\nLocated Loads with pending NITS applications would be able to apply for Interim NITS.”63 PJM \nshould revise its Illustrative Tariff accordingly to clarify that large loads with currently pending \nNITS applications shall be studied for Interim NITS at the request of the load without the need to \nmake a new or separate application, as long as such loads with pending NITS applications are Co-\nLocated Loads that will be served by an Eligible Customer. PJM should add such language to \nSection 702.2 (Application Procedures) of Part XI of its Illustrative Tariff. \nThird, PJM should add to the “Conditions Precedent for Receiving Service” in Part XI, \nSubpart A, Section 702.1 and Part XI, Subpart B, Section 710.1 the requirement that the Eligible \nCustomer identify the Co-Located Arrangement, including the Customer Facilities that will be \nassociated with the Co-Located Load for which the Eligible Customer is taking the service. If the \nCustomer Facilities include an existing generator, certification that the existing generator supports \nthe request should also be required. This clarification will ensure the Co-Located Load “is \nPJM, sought rehearing or clarification of this directive”); see also, e.g., Ne. Utils. Serv. Co., 74 FERC ¶ 61,355, at \nn.10 (1996). \n63 PJM Apr. 24 Response at 56; Constellation Mar. 25 Reply at 14."},{"page":15,"startToken":5034,"endToken":5300,"text":"15 \nphysically connected to the facilities of an existing or planned Customer Facility,” consistent with \nthe definition of Co-Located Load.64\nFourth, PJM should remove Part XI, Section 710.1(vi) of the Illustrative Tariff requiring \nan Eligible Customer to “submit to the Transmission Provider an authorization or certification \nfrom its Relevant Electric Retail Regulatory Authority which affirms that the Eligible Customer is \nauthorized to provide energy to the Co-Located Load.”65 This requirement is unworkable in \nexisting state regulatory frameworks. It would be nonsensical for a generator to obtain special \napproval from a state commission in a retail competition state, and other non-competitive states \nhave no procedures in place to seek approval.66 This provision would only serve to obstruct Co-\nLocated Load Arrangements. \nFifth, Constellation supports PJM’s proposed revision to Part III, Section 29.2(x) of its \nTariff. We propose one minor change to match the proposed intent. \nFor Eligible Customers taking service on behalf of Co-Located \nLoad: (1) a demonstration that the Co-Located Load on behalf of \nwhich the Eligible Customer is seeking taking to obtain service and \nthe Co-Located Generating Facility are located on the same side of \nthe Delivery Point to the Transmission Provider’s Transmission \nSystem as the Co-Located Load . . . . \n64 December 18th Order, 193 FERC ¶ 61,217 at P 164; see also PJM Interconnection, L.L.C., 195 FERC ¶ 61,030 at \nP 27 (affirming the Commission’s mandated definition of Co-Located Load). \n65 Illustrative Tariff, Part XI, § 710.1(vi). \n66 See Constellation Mar. 25 Reply at 29; Old Dominion Electric Cooperative Reply Brief at 7 (Mar. 25, 2026)."},{"page":16,"startToken":5300,"endToken":5464,"text":"16 \nCONCLUSION \nFor the reasons stated above, Constellation respectfully requests that the Commission \naccept this Answer and promptly approve the terms for Interim NITS, with Constellation’s focused \nmodifications, effective October 1, 2026, with customers commencing service by June 1, 2027. \n    Respectfully submitted, \n/s/ Paul F. Wight \n \nMay 11, 2026 \nCarrie Hill Allen \nSr. Vice President & Deputy General Counsel \nSeth T. Lucia \nAssistant General Counsel \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \ncarrie.allen@constellation.com\nseth.lucia@constellation.com\nChristopher A. Wilson \nManaging Director, Federal Regulatory Affairs \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \n202-347-7500 \nFERCe-filings1@constellation.com\nPaul F. Wight \nCarolyn E. Clarkin \nDLA Piper LLP (US) \n500 Eighth Street NW \nWashington, D.C. 20004 \n703-773-4058 \npaul.wight@us.dlapiper.com\ncarolyn.clarkin@us.dlapiper.com\nSophia Browning \n4365 Executive Drive \nSuite 1100 \nSan Diego, CA 92121 \n858-677-1455 \nsophia.browning@us.dlapiper.com\nCounsel for Constellation Energy \nGeneration, LLC"},{"page":17,"startToken":5464,"endToken":5542,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have on this 11th day of May, 2026, caused to be served a copy of \nthe foregoing upon all parties on the service lists in these proceedings in accordance with the \nrequirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. \n§ 385.2010 (2025). \n/s/ Sophia Browning \n \nSophia Browning \n4365 Executive Drive \nSuite 1100 \nSan Diego, CA 92121 \n858-677-1455 \nsophia.browning@us.dlapiper.com"},{"page":18,"startToken":5542,"endToken":5549,"text":"ATTACHMENT 1\nREPLY TESTIMONY OF ZACHARY MING"},{"page":19,"startToken":5549,"endToken":5618,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION\nPJM Interconnection, L.L.C., et al. \nLarge Loads Co-Located at Generating \nFacilities \nConstellation Energy Generation, LLC \nv. \nPJM Interconnection, L.L.C. \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \nDocket No. EL25-49-000 \nDocket No. EL25-49-001 \nDocket No. AD24-11-000 \nDocket No. EL25-20-000 \n(Consolidated) \nReply Testimony of Zachary Ming \nPartner \nEnergy and Environmental Economics, Inc. (“E3”) \nOn behalf of \nConstellation Energy Generation, LLC (“Constellation”) \nMay 11, 2026"},{"page":20,"startToken":5618,"endToken":5647,"text":"2 \nTable of Contents \n1\nIntroduction .............................................................................................. 3\n2\nBackground ............................................................................................... 6\n3\nEvaluation of Transmission Owners’ New Claims .................................. 9\n4\nResponse to Criticisms of E3 Proposal .................................................. 11\n5\nSummary ................................................................................................. 19"},{"page":21,"startToken":5647,"endToken":5836,"text":"3 \nConstellation \n1 \n2 \nTransmission Tariffs for Co-Located Load – Grid Reliance Charge \n3 \n4 \n5 \nReply Testimony of Zachary Ming, Partner, Energy and Environmental Economics, \n6 \nInc. (“E3”) \n7 \n1\nIntroduction\n8 \nQ1.\nPLEASE STATE YOUR NAME, OCCUPATION, AND BUSINESS \n9 \nADDRESS. \n10 \nA1.\nMy name is Zachary Ming. My current position is Partner at Energy and \n11 \nEnvironmental Economics (“E3”). My business address is 44 Montgomery Street \n12 \nSuite 1250, San Francisco, California 94104. \n13 \nQ2.\nPLEASE STATE ON WHOSE BEHALF YOU ARE FILING TESTIMONY. \n14 \nA2.\nI am filing this testimony as an independent expert, and it represents my own \n15 \npositions \nand \nperspectives. \nConstellation \nEnergy \nGeneration, \nLLC \n16 \n(“Constellation”) compensated for my testimony, but my compensation did not \n17 \ndepend on my conclusions. \n18 \nQ3.\nHAVE YOU PREVIOUSLY SUBMITTED TESTIMONY IN THIS \n19 \nDOCKET? \n20 \nA3.\nYes. I previously submitted testimony in this docket regarding the appropriate rate \n21 \ndesigns that should be applied to different configurations of Co-Located Load.1 I \n22 \n1 Testimony of Zachary Ming, on behalf of Constellation Energy Generation, LLC, Docket Nos. EL25-49-\n000, AD24-11-000, and EL25-20-000 (filed Apr. 23, 2025)."},{"page":22,"startToken":5836,"endToken":6117,"text":"4 \nalso submitted testimony regarding the Transmission Owners’ proposal for \n1 \ndeveloping the Grid Reliance Charge at the outset of this paper hearing.2\n2 \nQ4.\nARE YOUR QUALIFICATIONS THE SAME AS THOSE SET FORTH IN \n3 \nYOUR PRIOR TESTIMONY IN THIS DOCKET? \n4 \nA4.\nMy qualifications are the same as those set forth in my prior testimony in this docket \n5 \nand include testimony before the Federal Energy Regulatory Commission \n6 \n(“FERC”) and multiple state and provincial utility commissions. \n7 \nQ5.\nPLEASE PROVIDE A SUMMARY OF YOUR TESTIMONY. \n8 \nA5.\nThis testimony responds to the Reply Brief of the Indicated PJM Transmission \n9 \nOwners (“Transmission Owners”), 3  including specifically the Joint Rebuttal \n10 \nTestimony of Concentric Energy Advisors, Inc. (“Concentric”).4\n11 \nFirst, I provide a brief review of both the Transmission Owners’ and my \n12 \npositions and arguments regarding the proposed Grid Reliance Charge. Second, I \n13 \ndemonstrate that despite new arguments, the Transmission Owners’ proposal for \n14 \nthe Grid Reliance Charge is still unjust and unreasonable because it violates the \n15 \nprinciples of cost causation adopted by FERC by charging Co-Located Load \n16 \ncustomers for costs they do not impose on the system. Third, I respond to specific \n17 \ncriticisms of the Transmission Owners regarding my proposed Grid Reliance \n18 \nCharge. In several cases, I demonstrate that the Transmission Owners’ criticisms \n19 \n2 Testimony of Zachary Ming, on behalf of Constellation Energy Generation, LLC, Docket Nos. EL25-49-\n000, EL25-49-001, AD24-11-000, and EL25-20-000 (filed Mar. 25, 2026). \n3 Reply Brief of the Indicated PJM Transmission Owners (Apr. 24, 2026) (“Indicated TO Apr. 24 \nResponse”). \n4 Exhibit No. PTO-0005 (Joint Rebuttal Testimony of Peter Blazunas, Lance Schafer and Hanhan \nHammer)."},{"page":23,"startToken":6117,"endToken":6156,"text":"5 \nare more applicable to their own proposal than mine. I conclude by reiterating that \n1 \nthe Transmission Owners’ Grid Reliance Charge is unjust and unreasonable and \n2 \nthat my proposed Grid Reliance Charge is just and reasonable.  \n3"},{"page":24,"startToken":6156,"endToken":6373,"text":"6 \n2\nBackground\n1 \nQ6.\nWHAT WAS THE SUBJECT OF YOUR PRIOR TESTIMONY IN THIS \n2 \nPROCEEDING? \n3 \nA6.\nThe subject of my prior testimony in this proceeding related to the Transmission \n4 \nOwners’ proposed new “Grid Reliance Charge” for Co-Located Load customers in \n5 \nPJM. The Transmission Owners developed this charge in response to \n6 \nCommissioner Chang’s guidance that “a just and reasonable replacement rate for \n7 \nthe new transmission services should reflect some form of minimum transmission \n8 \nservice charge, which would protect other customers against cost shifts resulting \n9 \nfrom Co-Located Loads that rely upon the transmission system but do not directly \n10 \nor meaningfully contribute to its costs via transmission service payments.”5\n11 \nQ7.\nDO YOU SUPPORT A GRID RELIANCE CHARGE? \n12 \nA7.\nYes. I am aligned with the Transmission Owners that the concept of a Grid Reliance \n13 \nCharge is appropriate to ensure that Co-Located Load customers that consume \n14 \nancillary services make a contribution to the cost of the wires that deliver these \n15 \nservices. However, I disagree with the Transmission Owners as to the method for \n16 \ndetermining that charge and reach different conclusions about the amount of a \n17 \nreasonable charge. \n18 \n5 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (Chang, Comm’r, concurring at P 9).."},{"page":25,"startToken":6373,"endToken":6668,"text":"7 \nQ8.\nPLEASE EXPLAIN HOW YOU AND THE TRANSMISSION OWNERS \n1 \nDIFFER REGARDING HOW THE GRID RELIANCE CHARGE SHOULD \n2 \nBE CALCULATED. \n3 \nA8.\nBoth the Transmission Owners and I seek to quantify the “the costs of delivering \n4 \nancillary services, including the delivery of black start and regulation.” 6  To \n5 \naccomplish this, both the Transmission Owners and I seek to identify the percentage \n6 \nof system costs required to deliver ancillary services. However, the Transmission \n7 \nOwners and I are not aligned on 1) the methodology to determine this percentage \n8 \nof system costs or 2) a reasonable value for this percentage.  \n9 \nWith regard to methodology, the Transmission Owners use FERC Form 1 \n10 \ndata to identify cost accounts that they assert “support grid reliance.” In doing so, \n11 \nthe Transmission Owners include certain costs related to depreciation and \n12 \nOperation and Maintenance expenses (“O&M”) while excluding costs related to \n13 \nreturn on rate base and taxes. Notably, the Transmission Owners include “100 \n14 \npercent of the transmission depreciation category.”7 I explain the flaws of this \n15 \nassumption below. The Transmission Owners then divide the sum of their included \n16 \ncosts by the total transmission revenue requirement to produce a result of 25.8%. \n17 \nIn contrast, my proposed methodology to calculate the Grid Reliance \n18 \nCharge leverages the established “minimum system” method to identify the portion \n19 \nof costs that would be required to deliver ancillary services while excluding costs \n20 \nthat are incurred to size the system to serve peak demand. Dividing the cost of the \n21 \nminimum system by the costs of a system sized to peak demand yields 6.2%. \n22 \n6 Exhibit No. PTO-0001 at 17:12-13. \n7 Id. at 21:11 to 22:1."},{"page":26,"startToken":6668,"endToken":6865,"text":"8 \nQ9.\nPLEASE \nSUMMARIZE \nTHE \nARGUMENTS \nIN \nYOUR \nPRIOR \n1 \nTESTIMONY IN THIS PROCEEDING. \n2 \nA9.\nMy prior testimony outlined that while the concept of a Grid Reliance Charge is \n3 \nappropriate, the Transmission Owners’ proposed implementation of the Grid \n4 \nReliance Charge is unjust and unreasonable because it violates the principles of cost \n5 \ncausation by charging Co-Located Load customers for costs they do not impose on \n6 \nthe system. Specifically, because Co-Located Load customers that pay the Grid \n7 \nReliance Charge do not withdraw energy from the system, they do not contribute \n8 \nto the sizing of transmission system components such as wires, towers, and \n9 \ntransformers to serve peak load. From a cost causation perspective, they should \n10 \ntherefore not be responsible for 100% of depreciation costs that include the full cost \n11 \nof sizing transmission system components to serve peak load. Instead, the minimum \n12 \nsystem method is a just and reasonable approach, because it provides a principled, \n13 \ncost-causation basis for determining the portion of the system that is necessary to \n14 \nprovide ancillary services to Co-Located Load customers while excluding costs \n15 \nrelated to sizing equipment to serve peak load.  \n16"},{"page":27,"startToken":6865,"endToken":7097,"text":"9 \n3\nEvaluation of Transmission Owners’ New Claims\n1 \nQ10.\nWHAT NEW ASSERTIONS DO THE TRANSMISSION OWNERS MAKE \n2 \nREGARDING THEIR PROPOSED METHODOLOGY? \n3 \nA10.\nThe Transmission Owners assert that their proposed rate of 25.8% “represents an \n4 \nappropriate balance between fairly estimating the grid reliance benefits to Co-\n5 \nLocated Load with the need to ensure the rate can be practically implemented.”8\n6 \nThey additionally state that their methodology is designed to produce a \n7 \n“conservative result focused on recovery of the costs necessary to support the \n8 \nongoing reliable operation of the grid, rather than a return on investment.”9 Finally, \n9 \nthey justify their approach as one that can be “practically implemented” without \n10 \n“exacting precision.”10\n11 \nQ11.\nDO THE TRANSMISSION OWNERS’ ASSERTIONS SUPPORT THEIR \n12 \nPROPOSAL BEING JUST AND REASONABLE? \n13 \nA11.\nNo. They fail to address the fundamental shortcoming of their proposal – a \n14 \ntransmission system built only to deliver ancillary services would be nowhere \n15 \nnear as large or expensive as a transmission system built to serve peak demand. \n16 \nCustomers that do not withdraw energy from the transmission system should not \n17 \nbe responsible for sharing 100% of depreciation costs when they are not causally \n18 \nresponsible for all of those costs. \n19 \n8 Exhibit No. PTO-0005 at 16:8-10. \n9 Indicated TO Apr. 24 Response at 24. \n10 Id. at 23."},{"page":28,"startToken":7097,"endToken":7382,"text":"10 \nThe Transmission Owners implicitly acknowledge this point when they \n1 \nstate that “although the transmission system is built to meet peak demand, the \n2 \nproposed Grid Reliance Charge rate design does not include the full revenue \n3 \nrequirement associated with the transmission infrastructure put in place to meet \n4 \npeak demand.”11 However, they do not follow through on the implications of that \n5 \nposition. Instead, they propose Grid Reliance Charge customers to share in 100% \n6 \nof depreciation costs for the “transmission infrastructure put in place to meet peak \n7 \ndemand,” and arbitrarily exclude costs related to rate of return and taxes.   \n8 \nThat approach is entirely unmoored from a cost-causation analysis. After \n9 \nall, whatever investments the Transmission Owners would need to make to deliver \n10 \nancillary services would necessarily incur costs associated with both rate of return \n11 \nand taxes. Over a century of regulatory precedent confirms this point.12 Further, \n12 \nthere is no precedent by any utility in any proceeding that I am aware of that \n13 \ndistinguishes between depreciation on one hand and rate of return and taxes on the \n14 \nother when it comes to the cost of delivering ancillary services.   \n15 \nIn sum, the Transmission Owners’ proposal to include all depreciation costs \n16 \nfor transmission infrastructure, and then arbitrarily exclude the rate of return and \n17 \ntax related to those costs, reveals what the proposal really is: an improvised \n18 \napproach lacking any theoretical foundation and disconnected from any cost-\n19 \ncausation principle, designed to produce an outcome that “feels right” to the \n20 \nTransmission Owners.    \n21 \n11 Id. at 25. \n12 Bluefield Water Works & Improvement Co. v. Public Service Commission, 262 U.S. 679 (1923)."},{"page":29,"startToken":7382,"endToken":7625,"text":"11 \n4\nResponse to Criticisms of E3 Proposal\n1 \nQ12.\nDO THE TRANSMISSION OWNERS PROVIDE CRITICISMS OF YOUR \n2 \nPROPOSED \nMINIMUM \nSYSTEM \nMETHODOLOGY \nFOR \n3 \nDETERMINING THE GRID RELIANCE CHARGE? \n4 \nA12.\nYes. The Transmission Owners provide numerous criticisms of my proposal that I \n5 \nrespond to below.  \n6 \nQ13.\nPLEASE RESPOND TO THE CRITICISM THAT THE MINIMUM \n7 \nSYSTEM METHOD IS TOO COMPLEX. \n8 \nA13.\nThe Transmission Owners claim that a minimum system method “would be \n9 \nextremely difficult to produce and would potentially result in a spurious level of \n10 \nprecision because they would depend largely on subjective determinations.”13 This \n11 \nassertion is unconvincing for two reasons. First, I have already produced an \n12 \nestimate of 6.2% in my initial testimony. FERC could order PJM to use this \n13 \npercentage as a reasonable rate that can be practically implemented. Second, my \n14 \nproposal to use the minimum system method does not seek to apply more precision \n15 \nthan the Transmission Owners’ proposal but rather seeks to apply principles to \n16 \ndetermining the costs associated with the delivery of ancillary services. If the \n17 \nTransmission Owners or the Commission has concerns about how I reached the \n18 \n6.2% estimate, then the right approach is to direct PJM to come up with its own \n19 \nminimum system estimate—not discard the approach in favor of the Transmission \n20 \nOwners’ arbitrary proposal. \n21 \n13 Indicated TO Apr. 24 Response at 24."},{"page":30,"startToken":7625,"endToken":7905,"text":"12 \nQ14.\nPLEASE RESPOND TO THE TRANSMISSION OWNERS’ CRITICISM \n1 \nTHAT THE MINIMUM SYSTEM METHOD IS INAPPROPRIATE IN THE \n2 \nCONTEXT OF A GRID RELIANCE CHARGE. \n3 \nA14.\nThe Transmission Owners broadly assert that the minimum system method is \n4 \ninappropriate to apply within the context of the Grid Reliance Charge.  \n5 \nFor example, they state that I “propose[] the minimum system methodology \n6 \nwithout concern for what the Grid Reliance Charge is designed to accomplish.”14\n7 \nHowever, I am using the minimum system method for exactly what the Grid \n8 \nReliance Charge is trying to accomplish – to isolate the portion of system costs that \n9 \nCo-Located Load customers should contribute to as the foundation for a just and \n10 \nreasonable rate. This is the same objective that the Transmission Owners purport to \n11 \nshare, although I am using a principled approach to determine these costs. \n12 \nThey also assert that I “[d]o not demonstrate that there is any correlation \n13 \nbetween the mere electrical connection of customers and the benefits a Co-Located \n14 \nLoad receives from an … ongoing grid connection.”15 That is unfounded for two \n15 \nreasons. First, these customers are not drawing power from the grid. Therefore, by \n16 \ndefinition, they do not contribute to system components that are sized above \n17 \nminimum levels. Second, while it is true that all customers derive “benefits” from \n18 \nthe grid, standard cost-of-service ratemaking does not attempt to charge customers \n19 \nbased on the benefits they receive but rather on the costs of providing service. This \n20 \nis exactly what the minimum system framework does – it establishes a clear \n21 \n14 Id. at 26. \n15 Id. at 27."},{"page":31,"startToken":7905,"endToken":8174,"text":"13 \n“correlation between the mere electrical connection of customers” and the costs of \n1 \nserving a Co-Located Load customer. \n2 \nThe Transmission Owners also contend that I am “advocating for a \n3 \nreclassification of a portion of PJM transmission costs as customer-related even \n4 \nthough this reclassification is not only inappropriate but contradicts standard \n5 \nindustry literature.”16 This is likewise unfounded. Nowhere do I advocate for any \n6 \nreclassification of costs or changes to existing cost allocation methods already used \n7 \nin PJM. I am simply proposing a method to quantify the cost of delivering ancillary \n8 \nservices.  \n9 \nQ15.\nPLEASE RESPOND TO THE TRANSMISSION OWNERS’ CRITICISM \n10 \nTHAT YOUR PROPOSAL “WOULD END UP SHIFTING TO OTHER \n11 \nUSERS OF THE SYSTEM COSTS THAT ARE APPROPRIATELY BORNE \n12 \nBY CO-LOCATED LOAD CUSTOMERS.”17\n13 \nA15.\nThis criticism not only is misplaced, but in fact the Transmission Owners’ proposal \n14 \nis the one that inappropriately shifts costs—from other users of the system to Co-\n15 \nLocated Load customers. In the context of the electricity system, cost-shifting can \n16 \noccur when certain customers do not pay their fair share of system costs, causing \n17 \nthose costs to be borne by other customers. The Transmission Owners’ claim of \n18 \ncost-shifting relies on the assumption that their calculated rate is the appropriate \n19 \nfair share that Co-Located Loads should pay, when it is in fact not the appropriate \n20 \nfair share because it forces customers that do not impose demand on the grid to pay \n21 \n16 Exhibit No. PTO-0005 at 18:2-4. \n17 Indicated TO Apr. 24 Response at 25."},{"page":32,"startToken":8174,"endToken":8463,"text":"14 \nfor transmission components that are sized to serve peak demand. Instead, it would \n1 \nbe correct to say that the Transmission Owners’ proposal would shift costs to Co-\n2 \nLocated Load customers by forcing Co-Located Load customers to pay costs \n3 \nassociated with sizing up the grid to deliver energy, when Co-Located Load \n4 \ncustomers do not cause those costs at all.  \n5 \nQ16.\nPLEASE RESPOND TO THE TRANSMISSION OWNERS’ CRITICISM \n6 \nTHAT THERE IS NOT PRECEDENT FOR APPLYING THE MINIMUM \n7 \nSYSTEM METHOD IN THE CONTEXT OF THE TRANSMISSION \n8 \nSYSTEM. \n9 \nA16.\nThe Transmission Owners acknowledge the minimum system method has \n10 \nprecedent in the context of the distribution system. 18  It is a well-accepted \n11 \nframework for applying cost-causation principles. There is no reason that it cannot \n12 \nsimilarly be applied in the context of the transmission system—there has just not \n13 \npreviously been any need to do so. After all, this proceeding was designed to \n14 \naddress the emerging and somewhat novel challenge of interconnecting co-located \n15 \nnew large loads to the transmission system, which have grown rapidly in recent \n16 \nyears.19 To address this new problem, it is logical to use a minimum system method \n17 \nthat is well-accepted in an analogous context. \n18 \nBy contrast, the Transmission Owners’ proposal has no precedent that I am \n19 \naware of in any portion of the electricity sector (including distribution), by any \n20 \nutility, in any geography. My approach has far greater precedential support than \n21 \n18 Id. at 25. \n19 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at P 65 (2025). (“the surge of interest in co-location \narrangements in PJM has put before the Commission several significant and novel issues”)."},{"page":33,"startToken":8463,"endToken":8706,"text":"15 \ntheirs. It is better to rely on principles and methods that have been used in other \n1 \napplications rather than an arbitrary method with no precedent at all.    \n2 \nQ17.\nPLEASE RESPOND TO THE TRANSMISSION OWNERS’ CRITICISM \n3 \nTHAT YOUR ASSUMPTIONS IN DEVELOPING THE MINIMUM \n4 \nSYSTEM RESULT “VIOLATE[S] THE ENGINEERING REALITY OF \n5 \nTHE TRANSMISSION SYSTEM.”20\n6 \nA17.\nThe Transmission Owners posit that my “selection of minimum system components \n7 \n… violates the engineering reality of the transmission system.”21 For example, they \n8 \nstate that “a distribution wood pole cannot perform the function of a transmission \n9 \nstructure in that it cannot support required voltages, cannot meet clearance \n10 \nrequirements, and cannot handle mechanical loads (e.g., span length, conductor \n11 \nweight).”22\n12 \nThis criticism is not valid because a minimum system is a theoretical system \n13 \ndesigned to deliver a de minimis amount of electricity as opposed to a system \n14 \ndesigned to serve peak demand. As a result, everything is smaller in a minimum \n15 \nsystem. Voltages are lower, conductors are lighter, etc. Therefore, transmission \n16 \nstructures do not need to be sized with the same clearance or to handle the \n17 \nmechanical loads of today’s actual transmission system. Therefore, my \n18 \nassumptions are entirely consistent with the engineering reality of a minimum\n19 \nsystem.  \n20 \n20 Exhibit No. PTO-0005 at 19:17. \n21 Id. at 19:12-17. \n22 Indicated TO Apr. 24 Response at 28."},{"page":34,"startToken":8706,"endToken":8945,"text":"16 \nIf anything, my assumptions are conservatively high because they assume \n1 \nthe same number of conductor miles, structures, and substations as the current PJM \n2 \nsystem. The existence of many of these components themselves are driven by \n3 \nredundancies for contingencies associated with serving peak demand, so it is \n4 \nactually possible that a minimum system would not only have smaller components \n5 \nbut also fewer components. Because my analysis does not assume fewer \n6 \ncomponents, it is conservatively high. \n7 \nIn any event, if the Transmission Owners disagree with what components \n8 \nmake up a minimum system, then they can provide an alternative proposal for the \n9 \ncomponents that should be considered under this methodology. Instead, they reject \n10 \nthe framework altogether. And if the Commission believes there should be further \n11 \nconsideration of what constitutes a minimum system, then (as my direct testimony \n12 \nrecommends) the Commission can order PJM to conduct a minimum system study. \n13 \nPJM may have additional data that is not publicly available, and PJM may find it \n14 \nappropriate to use different assumptions. While I calculated a 6.2% result, my direct \n15 \ntestimony acknowledges that a result as high as 10% may be reasonable. \n16 \nQ18.\nPLEASE RESPOND TO THE TRANSMISSION OWNERS’ CRITICISM \n17 \nTHAT THE RESULTS OF THE MINIMUM SYSTEM METHOD ARE \n18 \n“BASED ENTIRELY ON REPLACEMENT COST” AND “[DO] NOT \n19 \nINCORPORATE \nRATE OF RETURN, \nTAXES, \nDEPRECIATION, \n20"},{"page":35,"startToken":8945,"endToken":9211,"text":"17 \nOPERATIONS AND MAINTENANCE, OR ANY OTHER ELEMENT OF \n1 \nTHE REVENUE REQUIREMENT.”23\n2 \nA18.\nThese assertions reflect a misunderstanding of the minimum system method and \n3 \nhow its results should be used. The “replacement cost” that I use in my study is \n4 \nequivalent to the “book cost” that seminal industry literature recommends.24 The \n5 \nminimum system uses the ratio of replacement costs for both the minimum system \n6 \nand actual system to identify what portion of the entire revenue requirement is \n7 \nattributable to the minimum system. It does not omit any element of the revenue \n8 \nrequirement. Nonetheless, I appreciate the Transmission Owners highlighting the \n9 \nimportance of incorporating all elements of the revenue requirement, which their \n10 \nmethod explicitly does not do. The Transmission Owners’ criticism would \n11 \ntherefore be more appropriately applied to their own proposal.  \n12 \nQ19.\nPLEASE RESPOND TO THE TRANSMISSION OWNERS’ CRITICISM \n13 \nTHAT IT NOT APPROPRIATE TO USE THE RESULTS OF THE \n14 \nMINIMUM SYSTEM METHOD TO DEVELOP A DEMAND CHARGE \n15 \nAND THAT APPLYING THE RESULTS OF THE MINIMUM SYSTEM \n16 \nMETHOD DIRECTLY TO THE NITS RATE “VIOLAT[ES] COST \n17 \nCAUSATION PRINCIPLES.”25\n18 \nA19.\nThe Transmission Owners’ criticism here appears to be largely based on the fact \n19 \nthat the minimum system method is typically used to identify customer-driven \n20 \ncosts. The fact that the results of a minimum system study can be used in this way \n21 \n23 Exhibit No. PTO-0005 at 26:8-13. \n24 NARUC, Electric Utility Cost Allocation Manual at 90-91 (1992). \n25 Exhibit No. PTO-0005 at 24:11."},{"page":36,"startToken":9211,"endToken":9382,"text":"18 \ndoes not mean that it can only be used in this way. As I have outlined extensively \n1 \nabove, the minimum system method provides a principled basis for isolating the \n2 \ncosts required to deliver ancillary services consistent with cost-causation principles. \n3 \nQ20.\nPLEASE RESPOND TO THE TRANSMISSION OWNERS' CRITICISM \n4 \nTHAT YOUR PROPOSED METHODOLOGY WOULD BE “EXTREMELY \n5 \nCHALLENGING TO IMPLEMENT.”26\n6 \nA20.\nThe Transmission Owners’ criticism is inconsistent with the minimum system \n7 \nmethod's established track record. The method has been applied at the distribution \n8 \nlevel across numerous jurisdictions across North America for decades, where \n9 \nregulators have repeatedly found it to be both workable and sufficiently precise for \n10 \nratemaking purposes. Further, I have already developed a reasonable estimate of \n11 \nthe minimum system percentage outlined in my direct testimony. A methodology \n12 \nwith significant precedent for which a reasonable study has already been completed \n13 \nshould not be characterized as “extremely challenging to implement.” \n14 \n15 \n26 Indicated TO Apr. 24 Response at 24."},{"page":37,"startToken":9382,"endToken":9606,"text":"19 \n5\nSummary\n1 \nQ21.\nPLEASE SUMMARIZE YOUR TESTIMONY. \n2 \nA21.\nYes. The key takeaways of my testimony are: \n3 \n\nThe concept of a Grid Reliance Charge is reasonable to ensure that Co-Located \n4 \nLoad customers contribute to the cost of delivering ancillary services; \n5 \n\nThe Transmission Owners’ proposed Grid Reliance Charge is unjust and \n6 \nunreasonable because it violates cost causation principles by charging Co-\n7 \nLocated Load customers for costs they do not impose on the system, namely \n8 \n100% of depreciation costs that include the cost of sizing transmission system \n9 \ncomponents to serve peak load when Co-Located Load customers by definition \n10 \ndo not impose any load on the system; \n11 \n\nThe Transmission Owners’ proposal to compensate for this overcharging by \n12 \nundercharging for rate of return and taxes is not “practical”, it is arbitrary and \n13 \nunrelated to the cost of delivering ancillary services; \n14 \n\nThe Transmission Owners’ criticisms of my proposal to use the minimum \n15 \nsystem method are without merit, and in several cases their criticisms are more \n16 \napplicable to their own proposal than to mine; and \n17 \n\nThe minimum system method is a just and reasonable approach for calculating \n18 \nthe Grid Reliance Charge, because it provides a principled, cost-causation basis \n19 \nfor isolating the portion of the system necessary to deliver ancillary services. \n20"},{"page":38,"startToken":9606,"endToken":9617,"text":"20 \nQ22.\nDOES THIS CONCLUDE YOUR TESTIMONY? \n1 \nA22.\nYes \n2"},{"page":39,"startToken":9617,"endToken":9651,"text":"VERIFICATION \nI declare under penalty of perjury that the foregoing Reply Testimony is true and correct to \nthe best of my knowledge, information, and belief.  \nExecuted this 11th day of May, 2026.\n________________________ \nZachary Ming"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":831,"startToken":0,"endToken":455},{"p":2,"at":831,"title":"I. Three Years Is Not “Required” to Replace an Unlawful Rate","method":"printed heading","endPage":3,"endAt":914,"startToken":455,"endToken":813},{"p":3,"at":914,"title":"II. Study Procedures and Deadlines Must Be in the Tariff","method":"printed heading","endPage":4,"endAt":197,"startToken":813,"endToken":980},{"p":4,"at":197,"title":"A. The Commission Should Require Clear and Detailed Study Requirements to","method":"printed heading","endPage":6,"endAt":3,"startToken":980,"endToken":1768},{"p":6,"at":3,"title":"B. Transmission Owner Load Integration Study Requirements are Unwritten","method":"printed heading","endPage":7,"endAt":862,"startToken":1768,"endToken":2536},{"p":7,"at":862,"title":"III. The Commission Should Reject Certain Proposed Strictures on the New Transmission","method":"printed heading","endPage":8,"endAt":312,"startToken":2536,"endToken":2906},{"p":8,"at":312,"title":"A. PJM’s Proposed Disqualification and Suspension Scheme is Not a Just,","method":"printed heading","endPage":10,"endAt":284,"startToken":2906,"endToken":3478},{"p":10,"at":284,"title":"B. Limiting Non-Firm Contract Demand Service to Temporary Derates or","method":"printed heading","endPage":11,"endAt":743,"startToken":3478,"endToken":3958},{"p":11,"at":743,"title":"IV. The Transmission Owners’ Grid Reliance Charge is Based Neither on Principle Nor","method":"printed heading","endPage":13,"endAt":285,"startToken":3958,"endToken":4458},{"p":13,"at":285,"title":"V. Requested Clarifications of PJM’s Response Brief and Modifications to Revised","method":"printed heading","endPage":16,"endAt":4,"startToken":4458,"endToken":5301},{"p":16,"at":4,"title":"CONCLUSION","method":"printed heading","endPage":17,"endAt":0,"startToken":5301,"endToken":5464},{"p":17,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":20,"endAt":3,"startToken":5464,"endToken":5619},{"p":20,"at":3,"title":"Table of Contents","method":"printed heading","endPage":21,"endAt":198,"startToken":5619,"endToken":5677},{"p":21,"at":198,"title":"Introduction","method":"printed heading","endPage":24,"endAt":5,"startToken":5677,"endToken":6158},{"p":24,"at":5,"title":"Background","method":"printed heading","endPage":37,"endAt":6,"startToken":6158,"endToken":9384},{"p":37,"at":6,"title":"Summary","method":"printed heading","endPage":39,"endAt":236,"startToken":9384,"endToken":9651}]}