{"document":{"slug":"rec-20260512-5049","title":"Motion for Leave to Answer and Answer of Eastman Chemical Company in response to the Indicated PJM Transmission Owners' 04/24/2026 Answer","issued":"2026-05-12","accession":"20260512-5049","docket":"ER26-1479-000","group":"PJM co-location compliance","filer":"EASTMAN CHEMICAL COMPANY","kind":"answer","file":"sources/filings/text/20260512-5049_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260512-5049","tier":"record","sha256":"10d8f57732ad0cf5741af9c9e4eb387fb603897ee359eb1747148043642a423f","pages":7,"tokens":1649,"emptyPages":[],"textThemes":["colo","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":292,"text":"1 \nUNITED STATES OF AMERICA \nBEFORE THE  \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, LLC \n) \nDocket No. ER26-1479-000 \nMOTION FOR LEAVE TO ANSWER AND ANSWER OF \nEASTMAN CHEMICAL COMPANY \nPursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the \nFederal Energy Regulatory Commission (FERC or Commission), 18 C.F.R. §§ 385.212 \nand 385.213 (2026), Eastman Chemical Company (Eastman) seeks leave to answer and \nsubmits this answer to the “Motion for Leave to Answer and Answer of the Indicated \nPJM Transmission Owners [(PJM TOs)]” submitted in the above-referenced docket \non April 24, 2026 (PJM TOs Answer).1 The Commission should deny the PJM \nTOs Answer because it will not assist the Commission in its decision-making, nor \ndoes it clarify the record for the Commission. There is good cause to accept this \nanswer to the PJM TOs Answer because the PJM TOs Answer fails to address the \nspecific behind the meter generation (BTMG) issues that Eastman raised in its \nprotest,2 as set forth in further detail below. \n1 The Indicated PJM Transmission Owners are the American Electric Power \nService Corporation on behalf of its affiliates, which includes Kingsport Power \nCompany. Eastman Chemical Company connects to the grid through Kingsport Power \nCompany. \n2 18 C.F.R. § 385.213(a)(2) (2026). The Commission will allow answers to \nanswer where there is good cause and where the answer will assist the Commission in \nits decision-making. See PJM Interconnection, LLC, 185 FERC 61,025 at P 24 (2023) \n(accepting answers because they provided information to assist in decision making); \nPub. Serv. Comm’n of W. Va. v. PJM Interconnection, 186 FERC 61,163 at P 69 \n(2024); Midcontinent Indep. Sys. Operator, Inc., 191 FERC 61,154 at P 42 (2025)."},{"page":2,"startToken":292,"endToken":524,"text":"2 \nA. PJM TOs Ignore Operational Realities of Industrial BTMG Facilities\nFirst, the PJM TOs Answer inappropriately lumps together all industrial BTMG \nfacilities, ignoring explicit statement that not all loads using BTMG create the reliability \nand resource adequacy risks.3 The blanket endorsement of a 50 MW threshold4 does \nnot provide consideration for the realities of individual facilities, including the Eastman \nfacility which, despite the 194 MW BTMG capacity of its facilities, could not operate \nsolely on electrical power delivered from the grid.5 \nNameplate capacity is not inherently indicative of the actual capability of BTMG \nat a facility. As Eastman explained in its Protest, the Kingsport facility is a co-\ngeneration facility, and its electric generation is coupled with steam production which \nis necessary for Eastman’s industrial processes.6 When the facility's generators are \nconstrained, both electricity output and steam production fall, reducing the facility's \nown industrial load and with it, demand on the grid.7 The facility naturally reduces grid \ndemand precisely when its generation output is limited, the opposite dynamic from the \nlarge loads that motivated the Commission's concern.8 \n3 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 at P 107 (2025) (Order). \n4 PJM TOs’ Answer at 3. \n5 Protest of Eastman Chemical Company, Docket No. ER26-1479-000, at 6 \n(filed Mar. 16, 2026) (Protest). \n6 Id. at 5. \n7 Id. \n8 Id.; Order at P 83."},{"page":3,"startToken":524,"endToken":828,"text":"3 \nThe Commission directed PJM to propose a threshold that would “reduce the \nreliability and resource adequacy risks that large or increasing BTMG may pose,” while \nallowing Network Customers to continue netting “in a transparent, not unduly \ndiscriminatory fashion.”9 PJM has proposed an arbitrarily low threshold that will \ndetrimentally impact facilities that poses no such reliability or resource adequacy risks, \nwithout taking into account the facility’s actual use of the transmission system. \nAdditionally, it is at odds with the established principle of cost causation, which has \nbeen raised and affirmed by the Commission in previous PJM tariff filings.10 The \nCommission should reject the PJM TOs' position and recognize that BTMG facilities \nwarrant treatment that reflects their operational realities. Eastman recommends a \nminimum threshold of 200 MW.  \nB. PJM TOs Fail to Defend the PJM All-or-Nothing Netting Structure\nSecond, the Commission directed PJM to establish a threshold for the load that \nNetwork Customers may net using BTMG.11 However, PJM has created a standard that \neliminates all netting for any facility that exceeds the 50 MW threshold by a single \n9 Order at P 83. \n10 See Occidental Chemical Corp. v. PJM Interconnection, L.L.C., 102 FERC ¶ \n61,275 (2003)(finding that  “charges for the use of PJM’s transmission system should \nbe allocated to network customers based on a network customer’s actual use of PJM’s \nsystem, consistent with the principle of cost causation.”); see also PJM \nInterconnection, L.L.C., 107 FERC 61,113 at PP 27-28 (2004)(finding that the BTMG \ntariff provisions would “charges for use of PJM’s transmission system should be \nallocated to network customers based on a network customer’s actual use of PJM’s \nsystem, consistent with the principle of cost causation.”).  \n11 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115 at P 221 (2025) (Show \nCause Order)."},{"page":4,"startToken":828,"endToken":1112,"text":"4 \nmegawatt.12 Under PJM's proposed structure, a facility with 50 MW of nameplate \ncapacity retains full netting rights, while a facility with 51 MW loses all netting rights.13 \nThis binary result is not a reasonable application of the Commission’s Order. \nThe Commission's Order directed PJM to allow Network Customers to net “up to” a \nthreshold level, preserving some benefit for all BTMG facilities while limiting the scale \nof large or increasing BTMG.14 Further, the Commission Show Cause Order states that \nBTMG netting is just and reasonable because it encourages load response when \ngeneration or transmission are in short supply and prices are rising15 and that charges \nto the PJM customer should be based on actual use of the system.16 PJM's proposal \ndistorts the Commission’s directive by using the 50 MW threshold not to cap netting, \nbut to eliminate it for any facility that exceeds the cap. \nNeither the PJM TOs nor PJM offer a just and reasonable basis for this structure. \nA threshold that draws no distinction between a 51 MW passive load and a 194 MW \nindustrial cogeneration facility that actively supports the grid is neither consistent with \nthe Commission's directive nor just and reasonable.17 The Commission should reject \nPJM's all-or-nothing approach and require PJM to submit a revised compliance filing \nthat permits all BTMG facilities to net load up to the threshold level, regardless of total \nnameplate capacity.  \n12 PJM TOs’ Answer at 3; Protest at 7. \n13 Compliance Filing at 7-8. \n14 Show Cause Order at P 221; Order at P 100. \n15 Show Cause Order at P 7. \n16 PJM, 107 FERC 61,113 at PP 27-28. \n17 Order at P 100; Protest at 6-7."},{"page":5,"startToken":1112,"endToken":1390,"text":"5 \nC. The PJM TOs Justification of 50 MW Threshold is Arbitrary\nThird, the PJM TOs provide no operational justification for the 50 MW \nthreshold. The PJM TOs sole justification for the 50 MW threshold is a definition \ndeveloped in an entirely different regulatory context, which was not intended to address \nthe reliability or resource adequacy risks that the Commission raised in relation to \nBTMG netting.18 The PJM TOs provide no evidence that BTMG facilities at or above \n50 MW have historically caused the resource adequacy or reliability problems the \nCommission identified as a concern.19  \nAdditionally, PJM TOs administrability argument is unpersuasive. While a \nstatic nameplate-based threshold may be easy to administer, administrative \nconvenience does not establish that a proposal is just and reasonable, particularly where \nthe result is the arbitrary elimination of netting rights for facilities that pose no grid \nreliability or resources adequacy risk. Nameplate capacity measures the maximum \npotential output of a generator, not the actual impact that a BTMG facility has on the \ngrid. For industrial co-generation facilities like the Kingsport facility, the relevant \nmetric is not how much electricity the facility could generate, but how that generation \ninteracts with the facility's load under real operating conditions. Further, the \n18 Compliance Filing, Transmittal Letter at Part III.A.2 and Attachment A (The \nPJM Large Load Additions definition was developed in order to address the reliability \nand resource adequacy challenges posed by unprecedented demand growth from data \ncenters and other large new loads connecting to the grid and it does not address \nBTMG at any point or any considerations related to how the definition would impact \nBTMG).  \n19 Order at P 83."},{"page":6,"startToken":1390,"endToken":1564,"text":"6 \nCommission directed PJM to establish a threshold for load that customers may net using \nBTMG.20 The Commission's goal was not to eliminate BTMG netting but to address \nthe specific risks posed by large or increasing BTMG.21 An administrable threshold that \ncaptures facilities posing no such risk is not a solution, it is an over-simplified standard \nthat mischaracterizes the Commission's objective while imposing real harm on \nfacilities.  \nFor the foregoing reasons, Eastman requests that the Commission accept this \nanswer and grant the relief requested in the Protest or establish an evidentiary hearing \nwith full rights of discovery to explore the issues of material fact that are in dispute. \nRespectfully submitted, \nBy: \n/s/ Emma M. Ross \nEmma M. Ross \n(571) 842-8187\nemr@floomenergylaw.com\nJohn Paul Floom\n(571) 842-8185\njpf@floomenergylaw.com\nKaci W. Poor\n(571) 842-8189\nkwp@floomenergylaw.com\nFloom Energy Law PLLC\n3100 Clarendon Blvd., Suite 920\nArlington, VA 22201\nAttorneys for \nEastman Chemical Company \nDate: May 12, 2026 \n20 Show Cause Order at P 221. \n21 Order at P 83."},{"page":7,"startToken":1564,"endToken":1649,"text":"CERTIFICATE OF SERVICE \nPursuant to Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 \nC.F.R. § 385.2010 (2026), I hereby certify that I have this day served a copy of the\nforegoing document upon each person designated on the official service list compiled \nby the Secretary in this proceeding. \nDated at Arlington, Virginia, this 12th day of May 2026. \nBy:   /s/ Emma M. Ross \nEmma M. Ross \nFloom Energy Law PLLC \n3100 Clarendon Blvd., Suite 920 \nArlington, VA 22201 \n(571) 842-8185"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":3,"startToken":0,"endToken":293},{"p":2,"at":3,"title":"A. PJM TOs Ignore Operational Realities of Industrial BTMG Facilities","method":"printed heading","endPage":3,"endAt":870,"startToken":293,"endToken":652},{"p":3,"at":870,"title":"B. PJM TOs Fail to Defend the PJM All-or-Nothing Netting Structure","method":"printed heading","endPage":5,"endAt":3,"startToken":652,"endToken":1113},{"p":5,"at":3,"title":"C. The PJM TOs Justification of 50 MW Threshold is Arbitrary","method":"printed heading","endPage":7,"endAt":0,"startToken":1113,"endToken":1564},{"p":7,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":7,"endAt":499,"startToken":1564,"endToken":1649}]}