{"document":{"slug":"rec-20260521-5093","title":"Motion for Leave to Answer and Answer of Geronimo Power, LLC in response to the reply briefs filed by PJM Interconnection, L.L.C. et al","issued":"2026-05-21","accession":"20260521-5093","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"GERONIMO POWER, LLC","kind":"answer","file":"sources/filings/text/20260521-5093_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260521-5093","tier":"record","sha256":"84319f705297bd568ac2a834eafbf937601ccaea34dfd41da3d023b170bc897e","pages":14,"tokens":4503,"emptyPages":[],"textThemes":["flex","colo","cost","study"]},"pages":[{"page":1,"startToken":0,"endToken":383,"text":"1 \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \nInterconnection of Large Loads to the  \nInterstate Transmission System  \nConstellation Energy Generation, LLC \nv. \nPJM Interconnection, L.L.C. \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n \nDocket Nos. EL25-49-000 \nEL25-49-001  \n \nDocket No. AD24-11-000 \n \n \nDocket No. EL25-20-000 \n \n \n(Consolidated) \nMOTION FOR LEAVE TO ANSWER AND ANSWER OF  \nGERONIMO POWER, LLC \n \nPursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s (“FERC” \nor “Commission”) Rules of Practice and Procedure,1 Geronimo Power, LLC (“Geronimo Power”) \nhereby files this answer2 in response to the reply briefs filed by PJM Interconnection, L.L.C. \n(“PJM”)3 and the PJM Transmission Owners4 in the above-captioned proceedings. \n \n1 18 C.F.R. §§ 385.212 and 385.213. \n2 Rule 213(a)(3) allows for an answer to be submitted to “any pleading, if not prohibited under paragraph \n(a)(2) of this section.”  18 C.F.R. § 385.213(a)(3).  Paragraph (a)(2) does not prohibit answers to briefs or reply briefs.  \nNevertheless, out of an abundance of caution, Geronimo Power moves for leave to file this answer.  The Commission \nhas accepted answers in the past when they have (i) assisted the Commission in understanding the issues presented, \n(ii) provided additional information for the Commission’s decision-making process, and (iii) helped ensure an accurate \nrecord.  See, e.g., PJM Interconnection, L.L.C., 181 FERC ¶ 61,162, at P 29 (2022); Canal Generating LLC, 181 \nFERC ¶ 61,157, at P 14 (2022); Equitrans, L.P., 134 FERC ¶ 61,250, at P 6 (2011); Cal. Indep. Sys. Operator Corp., \n132 FERC ¶ 61,023, at P 16 (2010).  In this proceeding, Geronimo Power’s answer will help the Commission \nunderstand the issues presented in this proceeding and provide further information to inform the Commission’s \ndecision-making process.  Geronimo Power therefore respectfully requests leave to file this answer to the extent the \nCommission deems such leave is necessary and requests that the Commission consider this answer in its deliberations \nin this proceeding. \n3 PJM Interconnection, L.L.C., et al., Docket Nos. EL25-49-000, et al., Reply Brief of PJM Interconnection, \nL.L.C. (April 24, 2026) (“PJM Reply”). \n4 PJM Interconnection, L.L.C., et al., Docket Nos. EL25-49-000, et al., Reply Brief of the Indicated PJM \nTransmission Owners (April 24, 2026) (“PJM TO Reply”)."},{"page":2,"startToken":383,"endToken":759,"text":"2 \n \nI. \nANSWER \nAt the heart of the Commission’s Show Cause Order5 lies a recognition that the current \nparadigm for serving large loads in PJM is not sufficiently flexible to accommodate the growth of \nhyperscale data centers and other large load customers that are essential for the nation’s economic \nprosperity, national security, and global competitiveness.  As the Show Cause Order explained, \nthe current framework for serving large loads within PJM requires that large loads that “are willing \nand able to limit their energy withdrawals from the transmission system” nevertheless pay for \n“costly and inefficient transmission system buildout that may not be necessary” to serve them.6  \nAnd because, as stated by Commissioner Rosner in his concurrence to the Show Cause Order, it \n“has become persistently difficult and increasingly expensive to build new grid infrastructure in \nthis country,”7 large loads are simply unable to timely obtain service even if they are willing to \npay for transmission system upgrades.  \nThe Commission sought to remedy this situation by ordering PJM to adopt three new \ntransmission services—Interim Network Integration Transmission Service (“NITS”), Firm \nContact Demand, and Non-Firm Contract Demand—that would reflect that certain large loads \nwhich co-locate with generation resources are able and willing to limit their reliance on the PJM \ntransmission system.8  But the positions taken by PJM and the PJM Transmission Owners in their \nbriefs filed in this proceeding regarding how these new transmission services will be implemented \n \n5 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“Show Cause Order”).  \n6 Show Cause Order at P 177.  See also id. at P 199 (“Requiring this could necessitate inefficient and costly \ntransmission buildout and costs paid by transmission customers that may not be necessary if Eligible Customers taking \ntransmission service on behalf of Co-Located Loads are willing to limit their energy withdrawals and take a \ntransmission service that requires fewer Network Upgrades to provide.”). \n7 Id. (Comm’r Rosner, concurring at P 3).  \n8 Id. at P 177 (“[W]e also find that PJM’s Tariff is unjust and unreasonable because it does not include \ntransmission services that reflect Eligible Customers taking service on behalf of Co-Located Loads that are willing \nand able to limit their energy withdrawals from the transmission system under certain conditions.”)."},{"page":3,"startToken":759,"endToken":1078,"text":"3 \n \nwill, if adopted, have the effect of preserving the status quo in PJM.  More specifically, certain \nrates, terms, and conditions proposed by PJM and the PJM Transmission Owners associated with \nthese new transmission services will effectively limit the ability of large load customers to take \ntransmission service that reflects their actual grid usage, disincentivize large loads from entering \ninto flexible co-location arrangements that minimize their impact on the grid, delay the timeline \nfor large loads to obtain the service they require, and lead to inefficient transmission build out.   \nGeronimo Power urges the Commission to reject any rates, terms, and conditions proposed \nby PJM or the PJM Transmission Owners that unnecessarily limit the flexibility of large loads to \nco-locate and take transmission service based on their actual use of the grid consistent with the \nShow Cause Order.  Geronimo Power files this answer to highlight the positions of PJM and the \nPJM Transmission Owners that are inconsistent with the flexibility the Show Cause Order \nenvisioned and, if adopted, would be most detrimental to the Commission’s efforts to ensure that \nlarge loads can be served efficiently, reliably, and on a timeline that ensures the U.S. does not fall \nbehind in the industries of the future. \nA. \nThe Commission Should Reject PJM’s And The PJM Transmission Owners’ \nProposals To Restrict Non-Firm Contract Demand Transmission Service To \nOutages \n \nIn its Reply, PJM doubles down on its view that Non-Firm Contract Demand transmission \nservice should be limited to when a generation facility is on “outage or temporary derate \nconditions…”9  The PJM Transmission Owners take this one step further by saying that Non-Firm \nContract Demand transmission service should only be available “when a generator is offline due \nto a breakdown or maintenance issues” and should “not cover other instances when a generator is \nnot operating, such as when intermittent generation resources are unable to produce; when a co-\n \n9 PJM Reply at 7."},{"page":4,"startToken":1078,"endToken":1380,"text":"4 \n \nlocated battery has depleted its available energy; or when a natural gas generator is unable to secure \nfuel.”10  These proposed restrictions on Non-Firm Contract Demand transmission service are \ninconsistent with the requirements of the Show Cause Order, will unnecessarily restrict the ability \nof large loads to co-locate, and should be rejected by the Commission.   \nAs an initial matter, restricting Non-Firm Contract Demand transmission service to when \na co-located generation facility is on outage is inconsistent with the requirements of the Show \nCause Order.  In the Show Cause Order, the Commission explained that “not all Co-Located Loads \nwill necessarily plan to withdraw energy from the transmission system on a regular basis” and thus \nNon-Firm Contract Demand transmission service should be available for when such loads “seek \nto withdraw energy from the transmission system from time to time when transmission capacity is \navailable and not needed by firm customers.”11  Moreover, the Commission indicated that Non-\nFirm Contract Demand transmission service should “be available only when there is available \ntransmission capacity, similar to existing non-firm transmission service options in the Tariff … for \nterms ranging from one hour to one month…”12  The Commission in no way suggested that it \nwould be appropriate to limit the availability of Non-Firm Contract Demand transmission service \nto times when co-located resources are on outage.  \nPJM’s and the PJM Transmission’s Owners’ proposals to restrict Non-Firm Contract \nDemand transmission service to when a co-located resource is on outage ignores the requirements \nfor this service outlined in the Show Cause Order.  Rather than making Non-Firm Contract \nDemand transmission service available for co-located loads at any time when transmission \ncapacity is available, PJM has proposed unnecessary restrictions that will limit co-located load \n \n10 PJM TO Reply at 6. \n11 Show Cause Order at P 214.  \n12 Id. at P 215."},{"page":5,"startToken":1380,"endToken":1683,"text":"5 \n \nfrom relying on the grid even when excess grid capacity is available to serve them.  This is not the \nflexibility that the Show Cause Order envisioned that Non-Firm Contract Demand transmission \nservice would provide.  \nThe restrictions imposed by PJM and the PJM Transmission Owners on Non-Firm Contract \nDemand transmission service would fundamentally undermine a key benefit of co-location.  \nSpecifically, a primary reason that large loads are considering co-location is so that they can reduce \ntheir impact on the grid and, in turn, obtain speed to power on a timeline that traditional utilities \nare increasingly proving unable to accommodate.  Large loads’ efforts to reduce their impact on \nthe grid through co-location may take on a variety of forms, including the use of intermittent \nresources paired with natural gas or battery energy storage or reducing their load (i.e., curtailing) \nat times of high demand when non-firm service is unavailable.   \nFor example, a solar and battery hybrid facility or natural gas generator may have the ability \nto meet the needs of co-located load in all but a limited set of hours during a year (e.g., due to \nunexpected natural gas supply interruptions).  Non-Firm Contract Demand transmission service \nwas intended to provide such a customer the option to obtain transmission service on an as-\navailable basis to meet its load during those limited instances where the onsite generation resource \nis unavailable to meet its demand (subject to an obligation to curtail if transmission service is \nunavailable).   \nYet, under PJM and the PJM Transmission Owner’s proposal, co-located load effectively \nwould have no alternative to taking NITS or Firm Contract Demand transmission service for its \nentire demand to ensure that it is able to obtain service during the limited handful of hours when \nthe generation resource is unavailable for reasons other than a “breakdown or maintenance"},{"page":6,"startToken":1683,"endToken":2112,"text":"6 \n \nissues.”13  In effect, PJM and the PJM Transmission Owners’ proposal would force a co-located \nload that is able to meet its own demand in all but a handful of hours to be studied as if it is planning \nto rely exclusively on the grid to serve its needs.  Inevitably, these studies will lead to the \nconclusion that accommodating these loads requires the construction of costly new transmission \nupgrades—upgrades that would be avoided if the customer is given the flexibility to take non-firm \nservice during the limited periods when the onsite generation is unavailable.   \nPJM and the PJM Transmission Owners’ primary rationale for imposing this restriction \nappears to be that making Non-Firm Contract Demand transmission service more broadly available \nposes reliability concerns since the PJM system has not been planned to accommodate this load.14  \nBut this misses the entire point of this service.  In the Show Cause Order the Commission made \nclear that Non-Firm Contract Demand transmission service “would be available only when there \nis available transmission capacity” and that co-located loads using such service “would not be \nconsidered for resource adequacy planning purposes.”15  When transmission capacity is not \navailable, large loads relying on Non-Firm Contract Demand transmission service will be \ncurtailed.16  PJM thus does not need to expand its transmission system or otherwise change its \noperations to accommodate this load; it merely needs to allow such load to take transmission \nservice when it is available, as PJM itself acknowledges.17  If transmission service is unavailable \n \n13 PJM TO Reply at 6.  \n14 Id. at 9-10; PJM TO Reply at 4-5 (“Limiting the use of Non-Firm Contract Demand Service is also \nnecessary to ensure the reliable operation of the PJM transmission system, especially because PJM and the PJM \nTransmission Owners will be relying on increased uses of Special Protection Schemes (‘SPS’), Remedial Action \nSchemes (‘RAS’), and other control technologies and protective systems to ensure that on-site load that is not being \nplanned from a transmission expansion or capacity standpoint can be operated reliably.”).  \n15 Show Cause Order at PP 215, 218.  \n16 Id. at P 215 (“We find that the new Non-Firm Contract Demand transmission service must be available \nduring normal operations and curtailed during emergency operations (i.e., it will be curtailed before existing firm \ntransmission services and the new Firm Contract Demand Transmission Service).”). \n17 PJM Reply at 10 (“The ability of the system to accommodate this service will depend on the system \nconditions at the time of the request and any constraints that may arise regarding energy and reliability. For energy,"},{"page":7,"startToken":2112,"endToken":2478,"text":"7 \n \nduring particular periods, then the customer will be forced to curtail.  If the system conditions that \nimpose reliability risks arise, PJM can refuse to accommodate requests for this non-firm service.  \nAnd to the extent that accommodating this service would require PJM to make changes to its \nmarkets and operations systems as PJM claims,18 that should not be a barrier to providing co-\nlocated loads the flexibility the Commission required of PJM in the Show Cause Order.     \nThe effect of PJM and PJM Transmission Owners’ proposal will be to severely limit co-\nlocation opportunities in PJM.  Large loads will either need to co-locate with a resource that can \nbe called upon at all times (other than when on outage) even when there is excess grid capacity to \nserve them or take NITS or Firm Contract Demand transmission service that will result in the same \ninefficient, timely, and costly grid build out that undermines speed to power efforts that the Show \nCause Order sought to avoid.  The Commission should not allow PJM and the PJM Transmission \nOwners to prolong the status quo in PJM by depriving large loads of the flexibility the Show Cause \nOrder was clearly intended to afford.   \nB. \nThe PJM Transmission Owners Have Not Demonstrated That Charging The \nSame Rate For Non-Firm Contract Demand Transmission Service As Firm \nTransmission Service Is Just And Reasonable \n \nNo party in this proceeding disputes that Non-Firm Contract Demand transmission service \nis a lesser service than NITS or Firm Contract Demand transmission service.  Non-Firm Contract \nDemand transmission service can be taken only on an as-available basis and is subject to \ncurtailment before NITS or Firm Contract Demand transmission service.  Yet despite the fact that \nNon-Firm Contact Demand transmission service is indisputably an inferior service, the PJM \n \nthe Co-Located Generating Facility’s outage may coincide with high demand conditions on the Transmission System \nor where system conditions otherwise (e.g., seasonal outages) may not allow such transmission service or energy to \nbe offered reliably.”).  \n18 Id. (“In Essence, Non-Firm Contract Demand Transmission Service is intended to provide whatever level \nof service the Transmission System can reliably accommodate at that snapshot in time without any advanced planning \nfor transmission or capacity.”)."},{"page":8,"startToken":2478,"endToken":2776,"text":"8 \n \nTransmission Owners have proposed to apply the same rate they charge for NITS and Firm \nContract Demand transmission service to Non-Firm Contract Demand transmission service.  The \nPJM Transmission Owners’ proposal is unjust and unreasonable, will disincentivize co-located \nloads from relying on Non-Firm Contract Demand transmission service, and lead to less efficient \nuse of the transmission system.  \nNeither the PJM Transmission Owners nor any other party to this proceeding have provided \na reasonable basis for the Commission to conclude that it is just and reasonable to apply the same \nNITS or Firm Contract Demand transmission service rate to Non-Firm Contract Demand \ntransmission service.  The PJM Transmission Owners have instead simply restated their flawed \ninitial rationales for charging the same rate for an inferior service.  For example, the PJM \nTransmission Owners explain that it would be inappropriate for them to apply the non-firm point-\nto-point transmission rate to Non-Firm Contract Demand transmission service because such \nservice is “demonstrably superior” to non-firm point-to-point transmission service.19  But as \nGeronimo Power explained in its Response,20 the question before the Commission is not whether \nthe PJM Transmission Owners should charge the non-firm point-to-point transmission rate for \nNon-Firm Contract Demand transmission service.  The question is what is a just and reasonable \nrate for Non-Firm Contract Demand transmission service.  The PJM Transmission Owners have \noffered no meaningful response to this question.   \nThe PJM Transmission Owners also reiterate that Commission policy allows them to \ncharge up to the same rate they charge for firm transmission service and that such rate is justified \nuntil they “gather data on how Non-Firm Contract Demand Service customers are utilizing the \n \n19 Id. at 19.  \n20 PJM Interconnection, L.L.C., Docket Nos. EL25-49-000, et al., Response Brief of Geronimo Power, LLC \nat 7 (Mar. 25, 2026) (“Geronimo Response”)."},{"page":9,"startToken":2776,"endToken":3149,"text":"9 \n \nservice, taking into account the intended purpose of the service, and the effect of that utilization \non the system.”21  But, as Geronimo Power noted in its Response,22 the mere fact that Commission \npolicy allows the PJM Transmission Owners to charge up to the firm rate in some cases, does not \nmean that doing so here is just and reasonable.  And the Commission itself has acknowledged that \nrates for non-firm service generally should be lower than the rates for firm service.23  The PJM \nTransmission Owners have provided no independent basis for the Commission to conclude it is \njust and reasonable to charge the same rate for Non-Firm Contract Demand transmission service \nas they charge for NITS and Firm Contract Demand transmission service.   \nMoreover, while the PJM Transmission Owners claim that “it is far from certain what \nupgrades may be required for Non-Firm Contract Demand Service customers” and thus assert that \nthey cannot yet determine the appropriate discount they should provide to Non-Firm Contract \nDemand transmission customers,24 there should be little doubt that some form of discount must be \napplied.  This is particularly true given that the Non-Firm Contract Demand transmission service \nthe Show Cause Order contemplates is required to be offered only when the PJM system is capable \nof accommodating such service.  Because Non-Firm Contract Demand transmission service is \noffered on an as-available basis the extent to which network upgrades are required for Non-Firm \nContract Demand transmission service—to the extent any are required at all—should be minimal \n(assuming that reasonable study assumptions are applied).25  \n \n21 PJM TO Reply at 20.  \n22 Geronimo Response at 7. \n23 Id. (citing Transmission Access Policy Study Group v. FERC, 225 F.3d 667, 731 (D.C. Cir. 2000); \nNortheast Utils. Serv. Co., 57 FERC ¶ 61,340, 62103 (1991) (“A non-firm rate is generally lower than a firm rate to \nreflect the nature of the interruptible wheeling service.”)).   \n24 PJM TO Reply at 20.  \n25 Geronimo Power recognizes that the extent to which Non-Firm Contract Demand transmission service may \nbe accommodated without network upgrades will likely depend on how the co-located loads taking this service are \nstudied.  For instance, there could be scenarios where overly conservative study assumptions result in network"},{"page":10,"startToken":3149,"endToken":3579,"text":"10 \n \nC. \nThe PJM Transmission Owners Have Not Demonstrated That Their Proposed \nGrid Reliance Charge Is Just And Reasonable And Consistent With Cost \nCausation Requirements \n \nGeronimo Power does not oppose the concept of a Grid Reliance Charge.  Indeed, despite \naccusations to the contrary by the PJM Transmission Owners,26 Geronimo Power made clear in its \nResponse that “it may be appropriate to impose certain charges on co-located load for \ndemonstrated costs they cause and benefits that accrue to them” but maintained that any such \ncharge must be based on co-located loads’ actual impact on the grid and the transmission services \nthey receive consistent with the Federal Power Act’s (“FPA”) cost causation requirements.27  The \nPJM Transmission Owners’ Initial Brief neither demonstrated that a Grid Reliance Charge is \nnecessary in this case nor that their proposed Grid Reliance Charge accurately reflects co-located \nloads’ actual grid impact or the transmission service they will receive.  And the PJM Transmission \nOwners’ Reply fairs no better.  The PJM Transmission Owners instead simply reiterate two of \ntheir three flawed rationales for applying a Grid Reliance Charge that would currently be 25.8% \nof a transmission owners’ annual transmission revenue requirement to all co-located load relying \non onsite generation.   \n \nupgrades being triggered to accommodate a request for Non-Firm Contract Demand transmission service.  But such \nstudy scenarios would likely be based on unnecessarily conservative study assumptions regarding the level of service \nrequested (e.g., an assumption that a co-located load would take this service 95% of the time) that do not reflect how \nthis type of service is likely to be taken nor align with the level of service directed by the Commission for Non-Firm \nContract Demand transmission service.  Such conservative study assumptions for Non-Firm Contract Demand \ntransmission service are neither required nor appropriate.  Rather, they would result in unnecessary network upgrades \nand inefficient system planning that would discourage parties from entering into flexible co-location arrangements \nthat rely on Non-Firm Contract Demand transmission service and ultimately undermine the Commission’s goal of \nproviding alternative speed to power options for large loads while mitigating grid impacts.  The Commission should \nrequire PJM and the PJM Transmission Owners to clearly articulate their approach to studying large loads requesting \nNon-Firm Contract Demand transmission service so that it can determine whether the network upgrades PJM and the \nPJM Transmission Owners claim Non-Firm Contract Demand transmission service will cause are not the mere result \nof unrealistic study assumptions. \n26 PJM TO Reply at 22 (“Vistra and Geronimo are the only two parties that suggest no Grid Reliance Charge \nis necessary.”).  \n27 Geronimo Response at 9-10."},{"page":11,"startToken":3579,"endToken":3934,"text":"11 \n \nFirst, the PJM Transmission Owners restate their position that the delivery of black start \nand regulation services justify their proposed Grid Reliance Charge because these services \n“provide no value without the ability to access the transmission system to obtain them.”28  But the \nfact that these services provide no value to load that is not interconnected to the transmission \nsystem does not mean that there is a delivery cost associated with the provision of these services.  \nIndeed, as Geronimo Power explained in its Response, neither black start nor regulation service \ninclude a delivery component and the PJM Transmission Owners have not sought to impose such \ndelivery charge on other transmission customers.29  The PJM Transmission Owners’ proposal to \nassess a charge for the delivery of black start and regulation service when other customers are not \nrequired to pay a separate delivery charge is unjust, unreasonable, and unduly discriminatory and \npreferential.  \nThe Northern Virginia Electric Cooperative, Inc. (“NOVEC”) attempts to justify the PJM \nTransmission Owners’ proposal by noting that although “the current formula for Black Start \nService does not include a delivery component,” that “simply reflects the fact that all load besides \nCo-Located Load in PJM would otherwise cover the cost of transmission service required for \nBlack Start Service.”30  NOVEC overlooks, however, that co-located loads taking Non-Firm \nContract Demand transmission service also will contribute to grid costs through the charges that \nthey pay for this service.  Additionally, PJM has proposed to assess co-located load charges for \nblack start and regulation service on a gross basis.31  It is thus unclear why co-located load should \n \n28 PJM TO Reply at 23.  \n29 Geronimo Response at 12-14.  \n30 PJM Interconnection, L.L.C. et al., Docket Nos. EL25-49-000, et al., Reply of Northern Virginia Electric \nCooperative, Inc. to Responses to Initial Brief of PJM Interconnection, L.L.C. and to Initial Brief and Joint Responses \nof the Indicated PJM Transmission Owners to Paper Hearing Questions at 18-19 (April 24, 2026). \n31 PJM Interconnection, L.L.C., et al., Docket Nos. EL25-49-000, et al., Initial Brief of PJM Interconnection, \nL.L.C. at 27 (Feb. 23, 2026)."},{"page":12,"startToken":3934,"endToken":4235,"text":"12 \n \nhave to pay for black start and regulation service as all other transmission customers do and pay a \nseparate delivery charge for these services that is not assessed to any other customers.  \nSecond, the PJM Transmission Owners also reiterate their claim that being connected to \nthe grid provides co-located load with “obvious benefits” which they explain include “frequency \nsupport, inertia, voltage stability, fault current capability, ride-through and protections \ncoordination, and providing sufficient short-circuit capability.”32  But the PJM Transmission \nOwners have not demonstrated that these benefits will accrue to the same degree for co-located \nload that is being primarily supplied by onsite generation.  And there is no evidence in this \nproceeding that these benefits alone justify applying a charge that is based on the percentage of \ntransmission depreciation and operations and maintenance expense of a transmission owner’s \nannual transmission revenue requirement (currently 25.8%) to all co-located load relying on onsite \ngeneration.33  \nApplying a Grid Reliance Charge to all co-located loads that bears no relationship to their \nimpact on the grid and the services they receive is not only inconsistent with the FPA, but will \ndiscourage co-location arrangements.  While large loads are prepared to pay their fair share of grid \ncharges and certain large loads may even be willing to pay more if it can accelerate their timeline \nto service, imposing a Grid Reliance Charge that is not reflective of the benefits co-located loads \nreceive will disincentivize co-location arrangements.  Requiring customers that make significant \ninvestments to bring their own co-located resource online to also pay a Grid Reliance Charge that \nis over a quarter of PJM transmission owners’ annual revenue requirement and for which they do \nnot receive a corresponding benefit could render the co-location calculus uneconomic for many \n \n32 PJM TO Reply at 22.  \n33 Id. at 27-28."},{"page":13,"startToken":4235,"endToken":4439,"text":"13 \n \nlarge loads.  Indeed, a charge that is divorced from the benefits co-located load receives may \nincentivize these loads to simply elect NITS or Firm Contract Demand transmission service if there \nis no cost difference between those services and the Non-Firm Contract Demand option, which, in \nturn, undermines the goal of supporting the timely interconnection of large loads and will lead to \ninefficient and unnecessary grid build out.  The Commission should decline to allow the PJM \nTransmission Owners to impose any form of Grid Reliance Charge on co-located load until they \ndemonstrate that such charge is necessary, consistent with the FPA’s cost causation requirements, \nand will not disincentivize large loads to co-locate. \nII. \nCONCLUSION \nGeronimo Power respectfully requests that the Commission issue an order consistent with \nits filings in these proceedings.  \nRespectfully submitted, \n \n/s/ Stephen J. Hug \nMatthew Morais \nSenior Director, Policy \nKurt Rempe \nAssistant General Counsel \nGERONIMO POWER, LLC \n8400 Normandale Lake Blvd., Ste. 1200 \nBloomington, MN 55437 \nmmorais@geronimopower.com  \nkrempe@geronimopowre.com  \n  \nStephen J. Hug \nBen N. Reiter \nAKIN GUMP STRAUSS HAUER & FELD LLP \n2001 K Street, N.W. \nWashington, D.C.  20006 \nTel: (202) 887-4084 \nshug@akingump.com \nbreiter@akingump.com   \nOn behalf of Geronimo Power \nDated: May 21, 2026"},{"page":14,"startToken":4439,"endToken":4503,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have caused the foregoing document to be served upon the individuals \ndesignated on the Commission’s official service list for this proceeding. \nDated at Washington, D.C., this 21st day of May 2026. \n \n \n/s/ Stephen J. Hug \n \nStephen J. Hug \nAKIN GUMP STRAUSS HAUER & FELD LLP \n2001 K Street, N.W. \nWashington, D.C.  20006 \n(202) 887-4084"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":5,"startToken":0,"endToken":384},{"p":2,"at":5,"title":"I. ANSWER","method":"printed heading","endPage":3,"endAt":1316,"startToken":384,"endToken":963},{"p":3,"at":1316,"title":"A. The Commission Should Reject PJM’s And The PJM Transmission Owners’","method":"printed heading","endPage":7,"endAt":1205,"startToken":963,"endToken":2312},{"p":7,"at":1205,"title":"B. The PJM Transmission Owners Have Not Demonstrated That Charging The","method":"printed heading","endPage":10,"endAt":6,"startToken":2312,"endToken":3150},{"p":10,"at":6,"title":"C. The PJM Transmission Owners Have Not Demonstrated That Their Proposed","method":"printed heading","endPage":13,"endAt":740,"startToken":3150,"endToken":4347},{"p":13,"at":740,"title":"II. CONCLUSION","method":"printed heading","endPage":14,"endAt":0,"startToken":4347,"endToken":4439},{"p":14,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":14,"endAt":388,"startToken":4439,"endToken":4503}]}