{"document":{"slug":"rec-20260528-5222","title":"Motion for Leave to Answer and Answer of the Indicated PJM Transmission Owners in response to certain reply briefs filed on 04/24/2026 and the Motion for…","issued":"2026-05-28","accession":"20260528-5222","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Indicated PJM Transmission Owners","kind":"answer","file":"sources/filings/text/20260528-5222_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260528-5222","tier":"record","sha256":"ed16a8787c258f4ac6c4d988e6efe8a379ac3d5cb7464f0caa11de32b02c7b44","pages":14,"tokens":4194,"emptyPages":[],"textThemes":["colo","study","flex","cost"]},"pages":[{"page":1,"startToken":0,"endToken":339,"text":"1 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et al.\n) \nDocket No. EL25-49-000 \n) \nDocket No. EL25-49-001 \n) \nLarge Loads Co-Located at Generating Facilities \n)  \nDocket No. AD24-11-000 \n) \nConstellation Energy Generation, LLC \n) \nv. \n)  \nDocket No. EL25-20-000 \nPJM Interconnection, L.L.C.  \n)  \n(Consolidated) \nMOTION FOR LEAVE TO ANSWER AND ANSWER  \nOF \nTHE INDICATED PJM TRANSMISSION OWNERS \nI.\nINTRODUCTION AND SUMMARY \nPursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal \nEnergy Regulatory Commission (“FERC” or “Commission”), 18 C.F.R. §§ 385.212 and \n385.213 (2025), the Indicated PJM Transmission Owners (the “PJM Transmission Owners”)1\nrespectfully submit this Motion for Leave to Answer and Answer in response to certain of the \n1\nFor purposes of this answer, the PJM Transmission Owners are:  American Electric Power Service \nCorporation on behalf of its affiliates, Appalachian Power Company, Indiana Michigan Power Company, \nKentucky Power Company, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP \nAppalachian Transmission Company, Inc., AEP Indiana Michigan Transmission Company, Inc., AEP Kentucky \nTransmission Company, Inc., AEP Ohio Transmission Company, Inc., and AEP West Virginia Transmission \nCompany, Inc.; The Dayton Power and Light Company d/b/a AES Ohio; Dominion Energy Services, Inc. on behalf \nof Virginia Electric and Power Company d/b/a Dominion Energy Virginia; Duke Energy Business Services, LLC \nfor Duke Energy Kentucky, Inc. and Duke Energy Ohio, Inc.; Duquesne Light Company; East Kentucky Power \nCooperative, Inc.; Exelon Corporation on behalf of its affiliates Atlantic City Electric Company, Baltimore Gas \nand Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., \nDelmarva Power & Light Company, PECO Energy Company, and Potomac Electric Power Company; FirstEnergy \nService Company, on behalf of its affiliates American Transmission Systems, Incorporated, Jersey Central Power \n& Light Company, Mid-Atlantic Interstate Transmission LLC, The Potomac Edison Company, Monongahela \nPower Company, Keystone Appalachian Transmission Company, and Trans-Allegheny Interstate Line Company \n(collectively, the “FirstEnergy Companies”); PPL Electric Utilities Corporation; Public Service Electric and Gas \nCompany; Rockland Electric Company; and the Southern Maryland Electric Cooperative."},{"page":2,"startToken":339,"endToken":681,"text":"2 \nreply briefs filed on April 24, 20262 and the Motion For Leave and Answer of Constellation \nfiled on May 11, 2026 in these proceedings.  The April 24 reply briefs and Constellation answer \nwere filed in response to the Commission’s December 18, 2025 order in PJM Interconnection. \nL.L.C., 193 FERC ¶ 61,217, at P 193 (2025) (“Order”). \nThe Commission should reject Constellation’s attempt to subvert the clear meaning of \nthe Order through its proposal to make protection systems optional for Co-Located Load \narrangements.3  Redundant protection systems are necessary for all Co-Located Load taking \none of the new transmission services to ensure adherence to relevant contractual limits, as well \nas to secure system reliability.  The Commission should also deny Constellation’s request to \nrequire Transmission Owners to file their load integration studies with FERC.  This requirement \nwould exceed the Commission’s jurisdiction and is unnecessary given the protections afforded \nby existing transmission planning processes as well as PJM’s proposed Co-Located Load \ntransmission study process.  Finally, the Commission should reject further attempts to shift to \nother ratepayers the costs associated with the benefits Co-Located Load customers receive \nthrough continued interconnection and synchronization to the grid, as reflected in the PJM \nTransmission Owners’ proposed Grid Reliance Charge.   \nII.\nMOTION FOR LEAVE TO FILE ANSWER \nAlthough answers are not expressly permitted under the Order, the Commission has \npermitted answers when they clarify issues in dispute, provide information to assist in the \n2\nThe PJM Transmission Owners address the reply briefs and responses filed by Constellation Energy \nGeneration, LLC (“Constellation”); Eolian, L.P., Antora Energy, Inc., Calibrant Energy, Mainspring Energy, Inc., \nU.S. Energy Storage Coalition, and Verrus, LLC (collectively, the “Joint Co-Location Developers”); PJM \nIndustrial Customer Coalition, the Industrial Energy Consumers of America, the American Forest and Paper \nAssociation, and the National Railroad Passenger Corporation (collectively, the “PJM Industrial Customer \nOrganizations and Amtrak”); and Old Dominion Electric Cooperative. \n3\nCapitalized terms that are not otherwise defined shall have the meanings set forth in the PJM \nInterconnection, L.L.C. (“PJM”) Open Access Transmission Tariff (“Tariff”)."},{"page":3,"startToken":681,"endToken":1044,"text":"3 \nCommission’s decision-making process, or to ensure the record is complete and accurate.4  This \nanswer will provide the Commission with information to ensure the record is complete and \naccurate because the reply briefs and Constellation’s further pleading either misunderstand or \nmisrepresent the PJM and PJM Transmission Owners’ proposals.  This answer will clarify the \nrecord and will aid the Commission in its decision-making process.  For these reasons, the PJM \nTransmission Owners respectfully request that the Commission accept this answer. \nIII.\nANSWER   \nA.\nProtection Systems and Other Reliability Remediation Requirements are \nnot Optional. \nTwo reply briefs raise issues concerning PJM’s proposal for protection systems and \nother reliability remediation requirements.  They generally argue that reliability protections and \nremediation should be tailored to actual risk rather than imposed as default requirements.5\nThese arguments suggest that protection systems and remediation requirements are somehow \nelective.  For instance, Constellation claims that protection systems are not appropriate for \nevery situation and should not be used to mitigate contractual issues such as unauthorized \nwithdrawals.6  These arguments are inconsistent with the Order as well as fundamental \nreliability principles. \n4\nSee, e.g., Transcontinental Gas Pipeline Corp., 119 FERC ¶ 61,039, at P 15 (2007) (accepting an answer \nbecause the information assisted the Commission in its decision-making process); Mich. Elec. Transmission Co., \n106 FERC ¶ 61,064, at P 3 (2004) (accepting an answer because “it provides information that clarifies the issues \nand aids us in the decisional process.”); Duke Energy Oakland, LLC, 102 FERC ¶ 61,093, at P 10 (2003) (finding \ngood cause to accept an otherwise impermissible answer because the answer assisted the Commission in \nunderstanding and resolving the issues involved in the proceeding); Carolina Power & Light Co., 97 FERC ¶ \n61,048 at 61,278 (2001) (finding good cause to waive Rule 213 when the pleading helped to ensure a complete \nand accurate record); Morgan Stanley Capital Group, Inc. v. N.Y. Indep. Sys. Operator, Inc., 93 FERC ¶ 61,017 at \n61,036 (2000) (accepting an answer to an answer that was “helpful in the development of the record.”). \n5\nConstellation at 13-18, Ex. 1 at 3-8; Joint Co-Location Developers at 5-10, Attachment A at 10-15. \n6\nConstellation at 16."},{"page":4,"startToken":1044,"endToken":1337,"text":"4 \nIn the Order, the Commission made clear that one of the rationales for implementing \nthe three new transmission services specific to Co-Located Load was Co-Located Loads “are \nwilling and able to control their withdrawals from the transmission system” through the use of \nsystem protection facilities.7  The Commission was unambiguous on this point, stating that “in \nthese instances where the Co-Location Arrangement includes special protection schemes that \nlimit its energy withdrawals, we find that it is a just and reasonable replacement rate to allow \nan Eligible Customer taking transmission service on behalf of such load to take and be charged \nfor new types of transmission service that are alternatives, and not equivalent, to [Network \nIntegration Transmission Service].”8  In other words, in order for an Eligible Customer to take \none of the new Co-Located Load-specific transmission services it is necessary and thus just and \nreasonable to require an Eligible Customer to include appropriate protection systems.  \nTherefore, contrary to Constellation’s claim, it is not only appropriate but necessary for PJM to \nrequire that any Eligible Customer that wishes to take one of the new transmission services to \ninclude protection systems to ensure that those Eligible Customers do not exceed their \ncontractual limitations. \nMoreover, the obligations of PJM and Transmission Owners in PJM to safeguard and \nmaintain system reliability are paramount, as the Commission has established on numerous \noccasions.  Accordingly, the new transmission services required under the Order must be \nsubject to appropriate terms and conditions to ensure that the implementation of these new \nservices does not compromise system reliability.  Co-Located Loads, as well as any on-site \ngenerators used to serve those loads, are not islanded.  Rather, they are fully connected and \n7\nOrder at P 204. \n8\nId. at P 205 (emphasis added)."},{"page":5,"startToken":1337,"endToken":1648,"text":"5 \nsynchronized with the transmission system, like all other loads and generators, and thus the \ntotal on-site load and generation have the ability to adversely affect the system.  This is \nespecially true given that PJM proposes that it will not identify network upgrades to \naccommodate transmission service requests for Co-Located Load beyond those amounts that \nan Eligible Customer designates for Network Integration Transmission Service or Firm \nContract Demand Service.9  For Co-Located Loads, maintaining the continued reliability of the \nsystem will depend on the utilization of protection schemes and remediation requirements to \nensure use of the system by Co-Located Load beyond its reserved use. \nConstellation asserts that fully redundant protection systems should not be the default \nrequirement for Co-Located Load arrangements.10  Constellation acknowledges that such \nprotections may be appropriate, but argues that they are only appropriate in limited, higher-risk \nsituations.11  It adds that there is no rational basis to require protection schemes on both the \ncustomer’s and the Transmission Owner’s side of the point of interconnection.12  This claim is \nincorrect.  Special Protection Schemes (“SPS”) on both the Co-Located Load customer’s and \nthe Transmission Owner’s side of the point of interconnection should not be limited to what \nConstellation claims are higher-risk situations.  Constellation’s suggestion that financial \npenalties imposed by PJM after the fact are a sufficient deterrent to ensure curtailment in \nresponse to a transmission system event or fault within the Eligible Customer’s facility shows \na fundamental lack of understanding of power system engineering.  The Eligible Customer \n9\nSee, e.g., PJM February 23 Initial Brief, Illustrative Tariff Sheets at 710.5 (“As set forth in the Service \nAgreement for Contract Demand Transmission Service, the Eligible Customer may also be responsible for the cost \nof network upgrades from the Transmission Provider’s Transmission System to the Delivery Point.”). \n10\nConstellation at 13-18; Ex. 1 at 3-7. \n11\nId. \n12\nId."},{"page":6,"startToken":1648,"endToken":1952,"text":"6 \nmight not be a NERC-registered entity subject to its oversight.  Additionally, it is overly \noptimistic to believe that penalties alone will ensure that Eligible Customers, who have a \nfinancial interest in minimizing the costs associated with protection systems, always will install, \noperate, and maintain their SPS and Remedial Action Schemes (“RAS”) correctly over time if \nthe only consequence they may face are possible fines after an event.   \nOn every other element of the bulk electric system in PJM, there is an expectation for \nredundancy for protection systems that are primarily responsible for fault clearing.  In the case \nof Co-Located Load, the failure to curtail load or generation adequately can adversely impact \nthe transmission system just as significantly as a fault, especially if there are no limitations on \nthe size of the load and generation connected in one facility.  Without protection system \nredundancy, the transmission system and the millions of customers that rely on it are at risk.  \nAccordingly, it is not accurate to claim that lower-risk configurations can be addressed \neffectively through operating procedures, relaying, and remote tripping capability, as \nConstellation contends.13\nConstellation’s assertions that PJM should use a PJM-driven study process to determine \nwhether SPS or other types of remediation are needed, and that any remediation should be \ncommensurate with actual reliability risk rather than imposed by default,14 ignore the fact that \nPJM is not equipped to perform these studies.  Currently, PJM does not possess the relay \nsettings for Co-Located Load interconnections.  Nor is it likely that PJM could obtain the relay \nsettings or perform any meaningful analysis even if it did obtain them.  Studying the need for \nSPS and RAS is within the purview of the PJM Transmission Owners because they have the \n13\nConstellation at 13-18; Ex. 1 at 3-7. \n14\nId. at 12-18; Ex. 1 at 6-8."},{"page":7,"startToken":1952,"endToken":2276,"text":"7 \nknowledge and insight with respect to the local protection systems and operational constraints \nthat may occur due to equipment outages for routine maintenance or equipment failure.   \nAlso, the cost to implement protection systems should not be a deterrent.  The overall \ncost to implement protection systems at a given facility comes primarily from the personnel \nhours during engineering and construction, then later maintenance.  But in any event, the cost \nof protection system equipment is extremely low when compared to other costs associated with \nthe development and interconnection of Co-Located Load.  Similarly, such installations are best \nperformed when the Co-Located Load first comes on-line as it is relatively inexpensive to install \nprotection systems as part of initial construction.  It is, on the other hand, much more expensive \nand time-consuming to retrofit a Co-Located Load facility after initial construction, given that \nit likely would require a generation facility outage.   \nFinally, Constellation continues to offer unsupported accusations concerning \nTransmission Owner discrimination, asserting that the Commission should guard against \nTransmission Owner discretion that could enable discrimination or delay.15  As the PJM \nTransmission Owners discussed in their April 24 Reply Brief,16 claims that the PJM Transmission \nOwners will use their role in the study process to delay and deny co-location arrangements or \notherwise discriminate against Co-Located Load are baseless and speculative.  There simply is no \nreason to assume that any PJM Transmission Owner will seek to frustrate the intent of \nCommission-accepted tariff provisions.  Likewise, it is illogical to assume that any PJM \nTransmission Owners will have an incentive to discriminate against Co-Located Loads in studying \n15\nConstellation at 9-12.  Constellation’s list of concerns includes rejecting the proposed use of “Point of \nChange in Ownership” in the definition of Co-Located Load, imposing deadlines for studies and approvals, and \nrequiring co-location standards, requirements, guidance, and practices to be filed with the Commission or placed \nin the tariff.  Id.\n16\nIndicated PJM Transmission Owners April 24 Reply Brief at 11."},{"page":8,"startToken":2276,"endToken":2660,"text":"8 \nsuch arrangements.  As noted above, the primary concern for Transmission Owners in PJM is \nsystem reliability.  To the extent Co-Located Load arrangements present no reliability issues, there \nis no reason or evidence to suggest that the PJM Transmission Owners will not accommodate their \ninterconnections. \nB.\nTransmission Owner Load Integration Studies Should not be Subject to \nFERC Filing. \nConstellation claims that the Commission should exercise jurisdiction over load \nintegration studies conducted by Transmission Owners and direct those load integration studies to \nbe filed with the Commission.17  This suggestion is meritless.  As PJM correctly pointed out in its \nApril 24 reply brief, the Transmission Owners’ processes for studying the integration of new retail \nloads, and identifying associated upgrades, do not inherently implicate the Commission’s \njurisdiction.18  To the contrary, retail load studies have always been subject to state jurisdiction, \nand the fact that such studies will be used as one of the inputs into PJM’s process for studying \napplications for one of the new transmission services does not provide a sufficient basis for the \nCommission to assert jurisdiction over those studies.  There is a fundamental distinction between \nstudying load for purposes of providing retail distribution and energy delivery services, and the \nimplementation of FERC-jurisdictional interconnection and transmission services, a jurisdictional \nline that has long been respected by the Commission.19  Under PJM’s proposed Co-Located Load \n17\nConstellation May 11 Answer at 6-7. \n18\nPJM April 24 Reply Brief at 34. \n19\nSee Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Servs. \nby Pub. Utils.; Recovery of Stranded Costs by Pub. Utils. and Transmitting Utils., Order No. 888, FERC Stats. & \nRegs. ¶ 31,036 (1996) (cross-referenced at 75 FERC ¶ 61,080), on reh’g, Order No. 888-A, FERC Stats. & Regs. \n¶ 31,048 (cross-referenced at 78 FERC ¶ 61,220), on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), on reh’g, \nOrder No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom., Transmission Access Policy Study \nGrp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom., N.Y. v. FERC, 535 U.S. 1 (2002); Standardization \nof Generator Interconnection Agreements and Procedures, Order No. 2003, 104 FERC ¶ 61,103 (2003), order on \nreh’g, Order No. 2003-A, 106 FERC ¶ 61,220, order on reh’g, Order No. 2003-B, 109 FERC ¶ 61,287 (2004),"},{"page":9,"startToken":2660,"endToken":3028,"text":"9 \ntariff provisions, it is PJM as the Transmission Provider that will make determinations about \nwhether and to what extent one of the new transmission services can be provided to an applicant.20\nThese determinations will be transparent, as PJM is required to provide a written explanation with \nrespect to any denial of service.21\nMoreover, any FERC-jurisdictional transmission facilities needed to accommodate a load \ninterconnection, be it a Co-Located Load or otherwise, will continue to be subject to the planning \nprocedures, including the associated stakeholder review and input processes, set forth in PJM’s \nTariff and Operating Agreement, either through the Regional Transmission Expansion Planning \nprotocols, or the local planning provisions set forth in Attachment M-3.  Finally, even with respect \nto studies performed with respect to FERC-jurisdictional services, such as generator \ninterconnection and transmission services, the Commission does not require transmission \nproviders to file studies, as they are neither service agreements nor rate schedules.  To the extent \nthat a customer has a dispute with the outcome of a particular study, the customer may challenge \nthat outcome in the context of the Interconnection Agreement or Transmission Service \nAgreement process.  Similarly, if an Eligible Customer seeking to procure one or more of the \nnew Co-Located Load transmission services believes that the outcome of PJM’s study process \nis flawed, the customer can seek redress through the Commission. \norder on reh’g, Order No. 2003-C, 111 FERC ¶ 61,401 (2005), aff’d sub nom. Nat’l Ass’n of Regul. Util. Comm’rs \nv. FERC, 475 F.3d 1277 (D.C. Cir. 2007). \n20\nPJM February 23 Initial Brief, Illustrative Tariff Sheets at 710.3 (“Following completion of all studies, \nTransmission Provider will make the determination, in consultation with the affected PJM Transmission Owner(s), \nabout whether (and to what level as applicable) Firm Contract Demand Transmission Service or Non-Firm \nContract Demand Transmission Services can be reliably provided for an Application, and if so, what level of \nservice may be provided.”). \n21\nSee id. at 710.3 (“If the Transmission Provider determines that only a portion of the Non-Firm Contract \nDemand Transmission Service requested by Eligible Customer can be provided reliably, the Transmission Provider \nwill provide a written explanation of its reasons for partial denial of service.”)."},{"page":10,"startToken":3028,"endToken":3296,"text":"10 \nFor these reasons, there is no need or legal basis for FERC to assert jurisdiction over and \nrequire the filing of Transmission Owner load integration studies. \nC.\nObjections to the Proposed Grid Reliance Charge are Meritless.  \nA few reply briefs take issue with the PJM Transmission Owners’ Grid Reliance Charge \nproposal.  In general, these briefs claim that the proposed Grid Reliance Charge is unprecedented \nand inconsistent with principles of cost causation.22  These objections are misplaced for a number \nof reasons. \nThe PJM Transmission Owners developed the Grid Reliance Charge partially in response \nto Commissioner Chang’s guidance that a just and reasonable replacement rate for the new \ntransmission services should reflect “some form of minimum transmission service charge, which \nwould protect other customers against cost shifts resulting from Co-Located Loads that rely upon \nthe transmission system but do not directly or meaningfully contribute to its costs via transmission \nservice payments.”23  The PJM Transmission Owners’ proposed Grid Reliance Charge achieves \nthis goal.  As the PJM Transmission Owners explained in their April 24 Reply Brief, the proposed \nGrid Reliance Charge is designed to reflect the costs of using the transmission system to deliver \nblack start and regulation services, as well as the costs of providing the inherent benefits that all \ncustomers, including Contract Demand customers, receive as a result of their synchronization to \nand reliance on the grid.24\n22\nSee, e.g., Constellation at 8; PJM Industrial Customer Organizations and Amtrak at 11-14; Joint Co-\nLocation Developers at 3-4. \n23\nOrder, Chang Concurrence at P 9. \n24\nIndicated PJM Transmission Owners April 24 Reply Brief at 21."},{"page":11,"startToken":3296,"endToken":3630,"text":"11 \nIn its May 11, 2026 Answer, Constellation presents a handful of criticisms of the PJM \nTransmission Owners’ Grid Reliance Charge proposal.25  For example, Constellation’s witness, \nZachary Ming, asserts that the PJM Transmission Owners “fail to address the fundamental \nshortcoming of their proposal – a transmission system built only to deliver ancillary services would \nbe nowhere near as large or expensive as a transmission system built to serve peak demand.”26\nMr. Ming continues to miss the point.  The purpose of the Grid Reliance Charge is not merely to \nrecover the costs of a fictional transmission system built only to deliver ancillary services, but \nrather to ensure that Co-Located Load customers pay their fair share of the transmission system as \nit exists and the associated benefits that it provides to all interconnected customers, including \nessential reliability services, such as frequency support, inertia, voltage stability, fault current \ncapability, ride-through and protection coordination, and sufficient short-circuit capability.27  The \nPJM Transmission Owners’ proposed Grid Reliance Charge does so by calculating the portions of \nannual depreciation and operations and maintenance expenses that constitute a reasonable proxy \nfor the costs of providing those benefits.  The Grid Reliance Charge is therefore just and \nreasonable. \nIn contrast, Constellation’s proposed minimum system replacement proposal28 is not just \nand reasonable.  The minimum system method is only appropriate for and applicable to \ndistribution level service.  It is entirely inappropriate to apply the minimum system method to \n25\nConstellation May 11 Answer at 2 (“The Transmission Owners’ excessive Grid Reliance Charge has no \nbasis in principle or precedent, while Constellation has proposed a just and reasonable replacement rate the \nCommission can readily adopt.”); Id. at 11 (The “Grid Reliance Charge is arbitrary and unmoored from cost \ncausation principles.”).   \n26\nReply Testimony of Zachary Ming at 9:14-16 (“Ming Reply Testimony”). \n27\nIndicated PJM Transmission Owners April 24 Reply Brief, Exh. PTO-0005 at 31. \n28\nConstellation March 25, 2026 Reply Brief at Attachment 1; Constellation May 11 Answer at 11-13; Ming \nReply Testimony at 11-18."},{"page":12,"startToken":3630,"endToken":3931,"text":"12 \ncalculate a transmission service rate.  As Mr. Schafer explains in his further testimony included \nas Attachment A to this answer, Mr. Ming continues to fail to account for the fact that the \nminimum system approach is only designed as a mechanism to classify portions of certain \ndistribution plant accounts as either customer- or demand-related.29  It is not, however, used to \ndetermine a revenue requirement, and therefore Mr. Ming’s proposed 6.2% “minimum system” \nallocation factor is inappropriate in the context of calculating a transmission service rate.30  Mr. \nMing also continues to base his minimum system analysis on equipment, such as distribution \nwood poles, that would not be used for transmission assets, even a hypothetical “minimum” \ntransmission system that was designed solely to deliver ancillary services.31\nD.\nODEC’s Requests for Clarification are Addressed in PJM’s and the PJM \nTransmission Owners’ Paper Hearing Briefs. \nIn its April 24 reply brief, Old Dominion Electric Cooperative (“ODEC”) indicates its \ngeneral agreement with the proposals submitted by PJM and the PJM Transmission Owners, \nbut requests clarification on several items.  With respect to the PJM Transmission Owners’ \nproposal to provide billing credits for revenues associated with the Grid Reliance Charge and \nNon-Firm Contract Demand Transmission Service, ODEC requests that the Transmission \nOwners confirm the mechanism for providing these credits to customers.32  This issue is \naddressed in further detail in the PJM Transmission Owners’ April 24 reply brief, which \nincludes illustrative tariff language that provides for direct bill credits to customers from PJM \nfor such revenues.33  ODEC also requests clarification on how regulation and black start service \n29\nReply Testimony of Lance Schafer, Attachment A at 8 (“Schafer Reply Testimony”). \n30\nSchafer Reply Testimony at 8-10. \n31\nId. at 10-11. \n32\nODEC at 3. \n33\nApril 24 Reply Brief, Exh. No. PTO-0006."},{"page":13,"startToken":3931,"endToken":4115,"text":"13 \nwill be charged to Eligible Customers taking service on behalf of Co-Located Load.  Based on \nPJM’s proposal, the PJM Transmission Owners understand that those charges will be assessed \ndirectly to load-serving entities, in the same manner as they are currently for NITS customers.34\nIV.\nCONCLUSION \nFor the reasons set forth herein, the PJM Transmission Owners respectfully request that \nthe Commission accept this answer and rule in a manner consistent with the discussion above.  \nIn particular, the Commission should reject attempts to water down requirements to install \nsufficient protection systems to ensure Co-Located Load customers do exceed their contractual \ncommitments.  The Commission should also reject arguments to shift costs of Co-Located Load \ncustomers to other ratepayers and accept the PJM Transmission Owners’ proposed Grid \nReliance Charge. \nRespectfully submitted, \n/s/ Michael Kunselman \nMichael Kunselman  \nRichard P. Sparling \n \nNicholas J. Cicale \nJonathan A. Namazi \nDavis Wright Tremaine LLP \n1301 K Street NW \nSuite 500 East \nWashington, DC 20005 \nCounsel for the FirstEnergy\n  Companies \nOn behalf of the Indicated PJM   \n  Transmission Owners\nDated:  May 28, 2026 \n34\nSee PJM February 23 Initial Brief at Attachment A."},{"page":14,"startToken":4115,"endToken":4194,"text":"CERTIFICATE OF SERVICE \nUnder Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § \n385.2010 (2025), I hereby certify that I have this day served the foregoing document upon each \nperson designated on the official service lists compiled by the Secretary in these proceedings. \nDated at Washington, D.C. this 28th day of May, 2026. \n/s/ Daniel Klein \nDaniel Klein \nDavis Wright Tremaine LLP \n1301 K Street NW \nSuite 500 East \nWashington, DC 20005"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":458,"startToken":0,"endToken":60},{"p":1,"at":458,"title":"I. INTRODUCTION AND SUMMARY","method":"printed heading","endPage":2,"endAt":1409,"startToken":60,"endToken":544},{"p":2,"at":1409,"title":"II. MOTION FOR LEAVE TO FILE ANSWER","method":"printed heading","endPage":3,"endAt":555,"startToken":544,"endToken":760},{"p":3,"at":555,"title":"III. ANSWER","method":"printed heading","endPage":3,"endAt":570,"startToken":760,"endToken":762},{"p":3,"at":570,"title":"A. Protection Systems and Other Reliability Remediation Requirements are","method":"printed heading","endPage":8,"endAt":312,"startToken":762,"endToken":2321},{"p":8,"at":312,"title":"B. Transmission Owner Load Integration Studies Should not be Subject to","method":"printed heading","endPage":10,"endAt":165,"startToken":2321,"endToken":3055},{"p":10,"at":165,"title":"C. Objections to the Proposed Grid Reliance Charge are Meritless.","method":"printed heading","endPage":12,"endAt":837,"startToken":3055,"endToken":3759},{"p":12,"at":837,"title":"D. ODEC’s Requests for Clarification are Addressed in PJM’s and the PJM","method":"printed heading","endPage":13,"endAt":288,"startToken":3759,"endToken":3976},{"p":13,"at":288,"title":"IV. CONCLUSION","method":"printed heading","endPage":14,"endAt":0,"startToken":3976,"endToken":4115},{"p":14,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":14,"endAt":467,"startToken":4115,"endToken":4194}]}