{"document":{"slug":"rec-20260603-5149","title":"Motion for Leave to Answer and Limited Answer of the Indicated PJM Transmission Owners in response to certain parties' responses to the 04/24/2026 Answer","issued":"2026-06-03","accession":"20260603-5149","docket":"ER26-1479-000","group":"PJM co-location compliance","filer":"Indicated PJM Transmission Owners","kind":"answer","file":"sources/filings/text/20260603-5149_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260603-5149","tier":"record","sha256":"68ea108fbaf956be313976086facb076300f521d1971717dd69ade033973a7d6","pages":5,"tokens":1475,"emptyPages":[],"textThemes":[]},"pages":[{"page":1,"startToken":0,"endToken":512,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C.   \n \n)  \n \nDocket No. ER26-1479-000 \n \nMOTION FOR LEAVE TO ANSWER AND LIMITED ANSWER OF  \nTHE INDICATED PJM TRANSMISSION OWNERS \n \nPursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“FERC” or “Commission”), 18 C.F.R. §§ 385.212 and 385.213, the \nIndicated PJM Transmission Owners1 submit this Limited Answer in response to certain parties’ \nresponses to the PJM Transmission Owners’ April 24, 2026 answer submitted regarding PJM \nInterconnection, L.L.C.’s (“PJM”) 60-Day Compliance Filing in the above-captioned proceeding.2  \nThis answer is limited to addressing replies to the PJM Transmission Owners on the issue of PJM’s \nproposed modifications to retail Behind the Meter-Generation (“Retail BTMG”) rules, in \ncompliance with the Commission’s December 18, 2025 Order in this proceeding (“December 18 \n \n1  \nFor purposes of this filing, the Indicated PJM Transmission Owners are: American Electric Power Service \nCorporation on behalf of its affiliates, Appalachian Power Company, Indiana Michigan Power Company, Kentucky \nPower Company, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian \nTransmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc., AEP Kentucky Transmission \nCompany, Inc., AEP Ohio Transmission Company, Inc., and AEP West Virginia Transmission Company, Inc.; The \nDayton Power and Light Company d/b/a AES Ohio; Dominion Energy Services, Inc. on behalf of Virginia Electric \nand Power Company d/b/a Dominion Energy Virginia; Duke Energy Business Services, LLC for Duke Energy \nKentucky, Inc. and Duke Energy Ohio, Inc.; Duquesne Light Company; East Kentucky Power Cooperative; Exelon \nCorporation on behalf of its affiliates Atlantic City Electric Company, Baltimore Gas and Electric Company, \nCommonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light \nCompany, PECO Energy Company, and Potomac Electric Power Company; FirstEnergy Service Company, on behalf \nof its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic \nInterstate Transmission LLC, The Potomac Edison Company, Monongahela Power Company, Keystone Appalachian \nTransmission Company, and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Companies”); \nPPL Electric Utilities Corporation; Public Service Electric and Gas Company; Rockland Electric Company; and the \nSouthern Maryland Electric Cooperative (“PJM Transmission Owners”). \n2  \nTo the extent required, the PJM Transmission Owners respectfully move for leave to answer.  The \nCommission’s procedural rules generally prohibit answers to answers.  However, the Commission has the discretion \nto waive its prohibition of answers to answers for good cause shown, i.e., to assist the Commission’s understanding \nand resolution of the issues raised or to ensure a complete record.  See, e.g., Pioneer Transmission, LLC v. N. Ind. \nPub. Serv. Co., 140 FERC ¶ 61,057, at P 94 (2012); Midwest Indep. Transmission Sys. Operator, Inc., 120 FERC ¶ \n61,083, at P 23 (2007); Morgan Stanley Cap. Grp., Inc. v. N.Y. Indep. Sys. Operator, Inc., 93 FERC ¶ 61,017, at \n61,036 (2000); CNG Transmission Corp., 89 FERC ¶ 61,100, at 61,287 n.11 (1999).  This Answer is submitted to \nensure a complete and accurate record.  Accordingly, good cause exists to permit this answer."},{"page":2,"startToken":512,"endToken":808,"text":"2 \nOrder”),3 specifically the level of materiality threshold for Retail BTMG, as well as the proposed \ngrandfathering provisions to ensure that existing Retail BTMG arrangements are not unfairly \nharmed by the transition to the new Retail BTMG rules required by the December 18 Order.4  For \nthe reasons explained below, the Commission should reject arguments for a materiality threshold \ngreater than 50 MW, while ensuring that grandfathering provisions are appropriately robust to \navoid unfair impacts to existing customers that have substantially relied on PJM’s Retail BTMG \nrules. \nI. \nANSWER  \nIn their April 24 answer, the PJM Transmission Owners explained that the Commission \nshould reject arguments arguing for a Retail BTMG threshold higher than 50 MW because the 50 \nMW threshold strikes the appropriate balance between allowing continued use of Retail BTMG \nwith the appropriate limitations to ensure reliability.  In response, the Answering Parties contend \nthat 50 MW is “arbitrarily low” and would include facilities that pose no reliability risk to PJM.5  \nThese arguments broadly miss the point: the issue is less that existing Retail BTMG arrangements \ncreate substantial reliability risks on their own, but rather that the proliferation of large loads, \nincluding those that opt to utilize arrangements with on-site generation, pose an increasing risk \ndue to the fact that Retail BTMG are not fully accounted for in resource adequacy planning and \ncan shift costs onto other transmission customers contrary to cost causation principles.6   \n \n3  \nPJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at PP 179, 221-224 (2025).   \n4  \nSpecifically, the PJM Transmission Owners reply to the further answers filed by Eastman Chemical \nCompany (“Eastman”), the PJM Industrial Customer Coalition (“Industrials”), and the BTMG Parties (collectively, \n“Answering Parties”). \n5  \nEastman at 3; Industrials at 3-4. \n6  \nDecember 18 Order at P 186."},{"page":3,"startToken":808,"endToken":1116,"text":"3 \nThese were the concerns underlying the Commission’s finding that PJM’s existing Retail \nBTMG arrangements are no longer just and reasonable, with the Commission specifically agreeing \nwith PJM’s explanation that the existing BTMG rules were conceived and implemented for \nsubstantially smaller loads, and that problems could occur if large loads were allowed to use the \nexisting BTMG rules.7  Although Commission did not make a finding as to a particular just and \nreasonable materiality threshold in the December 18 Order, it did note as “points of reference” that \nPJM requires individual metering for generators above 10 MW and that the Commission’s \ndefinition of a small generator is 20 MW.8  In this light, PJM’s 50 MW threshold is entirely \nreasonable, as it is high enough to exempt substantially-sized commercial and industrial facilities, \nbut is not so high as to create ongoing reliability risks as well as shifting an unreasonable amount \nof costs to other ratepayers.  The need to avoid cost-shifting is particularly apt given concerns over \nratepayer affordability and subsidization, which will only increase as more large loads come \nonline.  For these reasons, the Commission should accept PJM’s 50 MW threshold. \nThe Commission should also reject arguments that PJM failed to comply with the \nDecember 18 Order because it proposed a Retail BTMG materiality threshold based on generation \ncapacity rather than load size.  As PJM explained, it reasonably based the threshold on generator \nsize—measured by cumulative nameplate rating—because generator capacity is static and \nadministrable, whereas load can fluctuate.9  None of the Answering Parties adequately address this \npoint, instead focusing on the reference to the “amount of load” in the December 18 Order, \nparticularly in Ordering Paragraph (F).10  However, that Ordering Paragraph made clear that PJM’s \n \n7  \nId. \n8  \nId. at P 221. \n9  \nPJM Compliance Filing at 14. \n10  \nSee BTMG Parties at 2-3."},{"page":4,"startToken":1116,"endToken":1399,"text":"4 \ncompliance obligation was “as discussed in the body” of the December 18 Order.  In discussing \npotentially appropriate thresholds in the body of the December 18 Order, the Commission did not \npreclude a generation-based threshold.  To the contrary, the Commission specifically provided two \npoints of reference based on generator size, rather than the size of load itself.  Answering Parties’ \ncontentions that PJM’s proposal conflicts with the December 18 Order are therefore without \nmerit.11 \nFinally, it is clear from Answering Parties arguments that their primary concern involves \nthe treatment of existing Retail BTMG customers, rather than new large loads.  The PJM \nTransmission Owners agree it is important that an appropriate materiality threshold rule should be \npaired with grandfathering provisions recognizing that industrial and commercial customers have \nrelied on Retail BTMG rules.  To that end, the PJM Transmission Owners indicated their support \nfor certain additions and clarifications to PJM’s grandfathering proposal suggested by Answering \nParties, and other commenters.  The PJM Transmission Owners are open to additional suggestions \nas well as the development of further detail regarding the implementation of the grandfathering \nprovisions in order to avoid substantial financial harm to existing Retail BTMG customers.  \nHowever, the need for robust grandfathering provisions is not a convincing reason to increase the \nmateriality threshold going forward.  The two mechanisms address fundamentally different \nconcerns—the grandfathering provisions are meant to protect existing customers that have relied \non existing BTMG rules, while the materiality threshold is intended to ensure that the proliferation \nof new large loads does not compromise reliability or shift costs to other PJM ratepayers.  The \nCommission should reject the attempts of the Answering Parties to conflate the two issues. \n \n \n11  \nDecember 18 Order at P 221."},{"page":5,"startToken":1399,"endToken":1475,"text":"5 \nII. \nCONCLUSION \nThe PJM Transmission Owners respectfully request that the Commission accept this \nanswer and that any subsequent Commission orders addressing these issues be consistent with the \ndiscussion herein. \n \nRespectfully Submitted, \n \n \n \n \n \n \n \n/s/ Michael Kunselman \n \n \n \n \n \n \nMichael Kunselman  \n \n \n \n \n \n \nRichard P. Sparling \n \n \n \n \n \n \n \n \n \nNicholas J. Cicale \n \n \n \n \n \n \nJonathan A. Namazi \n \n \n \n \n \n \nDavis Wright Tremaine LLP \n \n \n \n \n \n \n1301 K Street NW \n \n \n \n \n \n \nSuite 500 East \n \n \n \n \n \n \nWashington, DC 20005 \n \n \n \n \n \n \nCounsel for the FirstEnergy  \n \n \n \n \n \n \n  Companies \n \n \n \n \n \n \n \n \n \n \n \n \n \n \nOn behalf of the PJM   \n \n \n \n \n \n \n  Transmission Owners \n \n \n \n \n \n \nDated:  June 3, 2026"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":588,"startToken":0,"endToken":600},{"p":2,"at":588,"title":"I. ANSWER","method":"printed heading","endPage":5,"endAt":3,"startToken":600,"endToken":1400},{"p":5,"at":3,"title":"II. CONCLUSION","method":"printed heading","endPage":5,"endAt":735,"startToken":1400,"endToken":1475}]}