{"document":{"slug":"rec-20260608-5078","title":"Comments of Persistence Analytics Group LLC/ United Grid related to the Commission-Led Technical Conference re PJM Governance and Stakeholder Reforms","issued":"2026-06-08","accession":"20260608-5078","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"PERSISTENCE ANALYTICS GROUP LLC, UNITED GRID","kind":"comments","file":"sources/filings/text/20260608-5078_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260608-5078","tier":"record","sha256":"343791c6626421465b801a2e97e15f2ca4f0ed7e521f6dc4f3ed787a411d97f8","pages":4,"tokens":1012,"emptyPages":[],"textThemes":["flex"]},"pages":[{"page":1,"startToken":0,"endToken":348,"text":"Comments of Persistence Analytics Group LLC / United Grid - Docket No. AD26-7-000\nPage 1\nUNITED STATES OF AMERICA\nBEFORE THE\nFEDERAL ENERGY REGULATORY COMMISSION\nPJM Governance and Stakeholder Reforms\nDocket No. AD26-7-000\nCOMMENTS OF PERSISTENCE ANALYTICS GROUP LLC / UNITED GRID\nPersistence Analytics Group LLC / United Grid respectfully submits these written comments in\nconnection with the Commission-led technical conference on PJM Governance and Stakeholder\nReforms in Docket No. AD26-7-000.\nPersistence Analytics Group is a New Jersey-based infrastructure risk analytics firm focused on demand\ndurability, grid stress, load integrity, public-cost exposure, and decision-grade evidence for long-duration\ninfrastructure and energy decisions.\nThese comments are offered as general policy input. They do not address the merits of any specific\npending contested proceeding.\nI. The Governance Question Is Also an Evidence Question\nThe agenda for Panel 1 asks how PJM governance mechanics may impede PJM's ability to address\noperational and market needs, and what concrete, actionable solutions could better equip PJM's Board\nand PJM to tackle immediate and future challenges.\nThat question is timely. PJM is facing simultaneous pressure from large-load growth, AI and data-center\ndemand, interconnection delays, capacity-market stress, state-policy conflict, transmission constraints,\nstorage deployment, resource adequacy concerns, affordability pressure, and public-cost exposure.\nPJM governance reform should not be viewed only as a question of voting mechanics, sector\nrepresentation, filing rights, or document architecture. Those issues matter. But the larger governance\nquestion is whether PJM can act quickly and credibly when operational reality changes faster than the\nstakeholder process.\nA faster process alone will not be sufficient if the process continues to rely on weak or incomplete\nassumptions. Governance reform should also improve the evidence standard that informs PJM\nplanning, market design, interconnection, cost allocation, and reliability decisions.\nProjected demand is not the same as durable demand.\nII. Large Loads Require Better Classification Before Assumptions Harden\nAs large loads scale across the PJM region, including data centers, AI campuses, hydrogen\nelectrolyzers, heavy-duty charging depots, and industrial electrification projects, PJM's governance\nstructure should help distinguish among different categories of load before those assumptions become\nembedded in planning, market, reliability, or cost-allocation outcomes.\n• announced load;"},{"page":2,"startToken":348,"endToken":625,"text":"Comments of Persistence Analytics Group LLC / United Grid - Docket No. AD26-7-000\nPage 2\n• speculative load;\n• contracted load;\n• energized load;\n• durable load;\n• flexible load;\n• controllable load; and\n• verified operating load.\nThose categories should not be treated as interchangeable. A large load that is announced but not\nfinanced, contracted but not staged, energized but not flexible, or forecast but not durable can create\nvery different planning, market, reliability, and cost-allocation implications.\nPJM governance should support a stronger evidence standard around the following questions:\n• Is the load real?\n• Is the load durable?\n• Is the load staged?\n• Is the load flexible or interruptible?\n• Is the load controllable under grid stress?\n• Is the power deliverable?\n• What upgrades are actually caused by the load?\n• Who pays if the operating profile changes?\n• How are existing customers protected if the forecast fails?\n• What evidence is sufficient before assumptions harden into planning, market, or cost-allocation\noutcomes?\nWithout a stronger evidence standard, the region risks treating projected growth as if it were verified\nsystem need. That can distort planning, increase public-cost exposure, weaken ratepayer protection,\nand create stranded infrastructure risk if load forecasts, project timelines, financing conditions, or\noperating behavior change.\nPJM governance reform should therefore include an explicit focus on large-load validation and verified\ngrid integration.\nIII. Concrete, Actionable Reform Areas\nThe Commission asked for concrete, actionable solutions. Persistence Analytics Group / United Grid\nrespectfully suggests that PJM governance reform should consider mechanisms that strengthen both\nprocess responsiveness and evidence quality.\n1. Time-bound governance pathways. Establish a time-bound governance pathway for urgent\nreliability, large-load, capacity, interconnection, and cost-allocation issues.\n2. Standardized large-load evidence classification. Require a standardized framework\ndistinguishing announced, contracted, energized, durable, flexible, controllable, and verified"},{"page":3,"startToken":625,"endToken":954,"text":"Comments of Persistence Analytics Group LLC / United Grid - Docket No. AD26-7-000\nPage 3\noperating load.\n3. Cost-causation evidence. Require stronger cost-causation evidence before major infrastructure\ncosts are assigned to existing customers or socialized across broader zones.\n4. Assumption sensitivity review. Require large-load-related planning assumptions to include\nsensitivity analysis for delay, cancellation, utilization shortfall, operational flexibility, and demand\nnon-persistence.\n5. State, utility, and stakeholder coordination. Improve coordination among PJM, states, utilities,\nlarge-load customers, and public stakeholders before load assumptions are embedded into market\nand planning outcomes.\n6. Governance performance review. Periodically assess whether PJM's stakeholder process can act\nfast enough when load, capacity, interconnection, or reliability conditions change materially.\n7. Verified grid-integration review. Consider a verified grid-integration review process for large loads\nthat may materially affect reliability, capacity pricing, transmission needs, state policy, or public-cost\nexposure.\nIV. Dependable Demand Is Now a Reliability Issue\nReliability is no longer only about dependable supply. It is also about dependable demand.\nPJM governance must be capable of verifying both sides of the system: generation performance and\nload behavior. This is especially important as large-load development, storage deployment, capacity\nmarket outcomes, and public affordability concerns converge across the region.\nThe next phase of grid governance should be built around a practical standard:\n• Verify the load.\n• Verify the power.\n• Verify cost causation.\n• Verify flexibility.\n• Verify public benefit.\n• Protect the grid and the public.\nPJM does not simply need more process. It needs governance capable of supporting verified execution.\nV. Conclusion\nPersistence Analytics Group LLC / United Grid respectfully encourages the Commission to consider\nPJM governance reforms that improve not only speed and accountability, but also the quality of\nevidence used to make planning, market, reliability, interconnection, and cost-allocation decisions.\nThe region's operational and market challenges are increasingly tied to the durability, flexibility, and\ndeliverability of large-load assumptions. PJM governance reform should help the region distinguish\nprojected demand from durable demand before costs, reliability obligations, and public exposure harden\naround assumptions that may not persist.\nRespectfully submitted,"},{"page":4,"startToken":954,"endToken":1012,"text":"Comments of Persistence Analytics Group LLC / United Grid - Docket No. AD26-7-000\nPage 4\nNeil P. Osnato\nFounder\nPersistence Analytics Group LLC / United Grid\nNational Security & Infrastructure Risk Analytics\nDemand Durability, Grid Stress & Load Integrity\nNew Jersey, USA\n609-464-9055\nneil@persistenceanalyticsgroup.com\nhttps://persistenceanalyticsgroup.com/\nSAM.gov Registered Vendor\nUEI: D3VYU39H6DX9 | CAGE: 19T34\nD-U-N-S: 142849930\nDated: June 8, 2026"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":876,"startToken":0,"endToken":117},{"p":1,"at":876,"title":"I. The Governance Question Is Also an Evidence Question","method":"printed heading","endPage":1,"endAt":2130,"startToken":117,"endToken":292},{"p":1,"at":2130,"title":"II. Large Loads Require Better Classification Before Assumptions Harden","method":"printed heading","endPage":2,"endAt":1503,"startToken":292,"endToken":555},{"p":2,"at":1503,"title":"III. Concrete, Actionable Reform Areas","method":"printed heading","endPage":3,"endAt":1125,"startToken":555,"endToken":760},{"p":3,"at":1125,"title":"IV. Dependable Demand Is Now a Reliability Issue","method":"printed heading","endPage":3,"endAt":1867,"startToken":760,"endToken":867},{"p":3,"at":1867,"title":"V. Conclusion","method":"printed heading","endPage":4,"endAt":455,"startToken":867,"endToken":1012}]}