{"document":{"slug":"rec-20260715-4001","title":"Pre-filed Statement of Steven Lieberman, Vice President of Transmission & Regulatory Affairs for American Municipal Power, Inc., for Panel 2 for the PJM…","issued":"2026-07-15","accession":"20260715-4001","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"AMERICAN MUNICIPAL POWER INC","kind":"testimony","file":"sources/filings/text/20260715-4001_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260715-4001","tier":"record","sha256":"656cbd0d1be44ea67dd9a1589dc4c2e3252fe6967362d4cdf8a7cd1f1b29495b","pages":16,"tokens":4245,"emptyPages":[],"textThemes":[]},"pages":[{"page":1,"startToken":0,"endToken":212,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Governance and Stakeholder Reforms \n) \nDocket No. AD26-7-000\n \nPRE-TECHNICAL CONFERENCE STATEMENT OF  \nSTEVEN LIEBERMAN ON BEHALF OF  \nAMERICAN MUNICIPAL POWER, INC. \n \nI appreciate the opportunity to participate in the upcoming Federal Energy \nRegulatory Commission (“Commission” or “FERC”) technical conference scheduled for \nJuly 23, 2026, as a panelist on Panel 2, titled “PJM Stakeholder Process – Design, \nTransparency, and Decision-Making.” This pre-technical conference statement, \npresented on behalf of American Municipal Power, Inc. (“AMP”), focuses on the subject \nmatter of that panel discussion, as described in the Commission’s notice.1 \nAs Vice President of Transmission & Regulatory Affairs, I provide oversight and \ntake responsibility for AMP’s advocacy in the Midcontinent Independent System Operator, \nInc. (“MISO”) and PJM Interconnection, L.L.C. (“PJM”) RTO stakeholder processes, along \nwith AMP’s participation in the North American Electric Reliability Corporation (“NERC”) \nstandards development process. I hold a Bachelor of Arts degree in Environmental \nScience from Boston University. \nI. \nINTRODUCTION \nThese comments share the perspective of AMP as a non-profit public power \nwholesale supplier of electricity for 135 public power communities located across nine \nstates, including seven PJM states. AMP’s member systems serve approximately \n \n1  See Second Supplemental Notice of Commission-Led Technical Conference, Docket No. AD26-7-000, \nat 4-6 (July 2, 2026)."},{"page":2,"startToken":212,"endToken":455,"text":"2 \n650,000 meters, and while AMP represents many of the larger public power systems in \nPJM, the average AMP member community is less than 5,000 meters and rural. Our \nmember officials are keenly aware of the impact of PJM policies and governance on their \nlocal operations and costs for their customers. But AMP’s advocacy is not biased towards \npricing outcomes. Said differently, AMP does not advocate for rules that are motivated to \nintentionally raise prices or lower prices. Instead, AMP advocates for sustainable, \ncommonsense rules that will protect end-use customers from degraded reliability, while \nensuring affordability. \nPJM’s existing governance framework generally works well and does not require \nmajor structural reform. The current sector-weighted voting process appropriately \nbalances consensus-building with timely decision-making and ensures that significant \nproposals receive broad stakeholder support before advancing. \nAMP’s primary recommendation is to improve coordination and consistency \nbetween voting at senior committees and voting at lower-level committees, where voting \nresults often determine which proposals move forward. AMP believes coordination \nbetween voting results at lower-level committees and votes taken by senior committees \nwould strengthen stakeholder confidence, improve consensus-building, and make \ndecision-making more efficient. \nStakeholder representation and committee structure are not the source of delays. \nStates and other interested parties appropriately have multiple opportunities to participate \nin PJM processes, and the speed of decision-making is largely determined by PJM’s \nprioritization of issues and meeting schedules. Accordingly, better issue prioritization is \nneeded, rather than changes to stakeholder representation or governance."},{"page":3,"startToken":455,"endToken":703,"text":"3 \nPJM’s most significant challenge remains resource adequacy and reliability, but \nthe existing governance framework, with the adjustments proposed below, is sufficient to \naddress those concerns and there is no basis for weakening stakeholder processes or \nreducing stakeholder input. Expanded use of expedited stakeholder procedures may \nresult in compressed timelines that hinder stakeholder collaboration, reduce opportunities \nto build consensus, and create greater regulatory uncertainty. Better outcomes result \nwhen stakeholders have adequate time to develop and refine proposals. \nFinally, PJM should enhance transparency at the Board level. Adopting practices \nsimilar to those used by other regional transmission organizations, such as providing \ngreater public access to Board meetings, agendas, and materials, would improve \naccountability and stakeholder confidence. Overall, AMP supports targeted transparency \nimprovements while preserving the consensus-based processes that have historically \npromoted reliable and affordable electric service. \nII. \nCOMMENTS \nQuestion 1: Sector-weighted Voting  \n \nDo sector-weighted voting and existing voting thresholds strike the right balance \nbetween achieving consensus and taking timely action? \n \nSector weighted voting (SWV) is used for votes of the Members Committee (MC) \nand the Markets and Reliability Committee (MRC) (i.e., the Senior Standing Committees). \nSWV and the related voting thresholds for issues to be deemed approved (or endorsed) \nachieves a reasonable balance between developing consensus and timely action. The \nthreshold is two-thirds support from the five sectors, in which each sector provides 1.000 \nvotes towards the total. Thus the threshold for an issue to be deemed approved or passed \nvia SWV is 3.334 (rounding up)."},{"page":4,"startToken":703,"endToken":971,"text":"4 \nPJM facilitates nearly all stakeholder meetings except for the MC and the Liaison \nCommittee (LC). There is no voting at the LC, thus there is only one instance in which a \nPJM Member facilitates a committee in which voting occurs (the MC). In terms of timely \naction, the committee or task force facilitator or a stakeholder can “call the question” on \nan agenda item to ensure timely action. \nAchieving consensus does not mean unanimous support. In some instances, \nconsensus is a simple majority threshold and in others it is a super-majority. While it may \nseem difficult to achieve a super-majority threshold, particularly on contentious issues, \nwhen it is attained, it signals to FERC that the proposal before it is supported by a broad \nrange of PJM Members. \nQuestion 2. Transparency Reforms \n \nWhat transparency reforms would improve the quality of PJM’s stakeholder \nprocess and increase stakeholder confidence in its decision-making?  \n \nTransparency reforms are desperately needed, particularly for matters of \nsignificance that come before the PJM Board following stakeholder consideration and that \nresult in FERC filings. There is substantial opaqueness in the PJM Board’s deliberations \non such matters. One aspect that PJM should consider adopting from SPP is that “[a]ll \nSPP Board meetings that are not in executive session are open to the public. All meeting \nmaterials, agendas, and minutes are publicly posted on the SPP website.”2 Transparency \nis key, recognizing that certain issues necessarily lend themselves to being discussed in \nexecutive session. \n \n2  See FERC, An Introductory Guide for Participation in Southwest Power Pool Processes (“Q. How is \nSPP Governed?”), https://www.ferc.gov/introductory-guide-participation-southwest-power-pool-\nprocesses."},{"page":5,"startToken":971,"endToken":1242,"text":"5 \nMISO’s similarly open approach is also instructive. The MISO Board holds an open \nmeeting each quarter. The committees of the Board hold open meetings at least each \nquarter. Stakeholders and the public are allowed to listen to these meetings. The Board \nand its committees cover general materials in open session, but do have executive \nsessions for material related to confidential business (personnel matters, legal matters, \ncontract issues, etc.).  The committees publish and review a work plan for the year \nshowing when they have open meetings and executive sessions with a general overview \nof the topics to be covered in the meetings.   \nAt the end of their meetings the MISO Board and its committees allow an \nopportunity for public comment. During MISO’s Board week, when the Board holds an \nopen meeting, the Board joins the MISO Advisory Committee (AC)—the stakeholder \ncommittee with representatives from all of the stakeholder sectors—to hold a discussion \non a topic decided prior to the meeting. The discussion for June 2026 was “Maintaining \nResource Adequacy in a Time of Transition.” The MISO Board and the AC receive reports \nfrom the chairs of various MISO stakeholder groups.  After each report on the topics of \ninterest being discussed at the stakeholder committees, the MISO Board and the AC have \nan opportunity to ask the chair of each group questions about the work of the committee. \nAdditional opportunities for the PJM Board to interact with stakeholders and for \nstakeholders to hear PJM Board deliberations and understand the basis for decision-\nmaking, more like other RTOs, could increase stakeholder confidence in, or at least \nunderstanding of, PJM Board decisions."},{"page":6,"startToken":1242,"endToken":1527,"text":"6 \nQuestion 3. State Participation  \n \nAre there structured opportunities in the stakeholder process for state \nparticipation (e.g., defined consultation windows, joint technical sessions) to \nprovide input on topics that are of interest to the states? \n \nYes, state participation is possible, and states (some perhaps more than others) \ndo participate in stakeholder meetings, including by presenting proposals for \nconsideration. Per Manual 34, Section 4: Roles and Responsibilities, “[t]here are several \ntypes of participants in the PJM stakeholder process, including the Members, PJM (the \nOffice of the Interconnection, or Staff), the Independent Market Monitor (IMM) and the \nOrganization of PJM States, Inc. and its member regulatory agencies. Additionally from \ntime to time other parties may participate in the PJM stakeholder process.”3  \nSection 4.1 Members and Other Participants, explains that “[i]t is the responsibility \nof each participant in the PJM stakeholder process to represent its interests in \ncooperation with all other stakeholders to ensure the reliability of the PJM system and \nimplementation of efficient, fair and transparent markets.” Specifically, participant \nresponsibility includes five stated items: \n• \nArticulating their interests, concerns, ideas and their basis of support for a \nparticular approach or proposal; \n• \nRaising objections and concerns, and the responsibility to provide an alternative \nif they are not able to agree with a proposal or option; \n• \nAlerting the stakeholder meeting facilitator to specific sensitive concerns related \nto the process or subject matter; \n• \nProviding all materials in a timely manner for website posting and notification; \nand \n \n3  Additional information about the roles and responsibilities of the Organization of PJM States, Inc. (OPSI) \nand State Regulators is provided in PJM, Manual 34, Section 4.4, at 23, https://www.pjm.com/-\n/media/DotCom/documents/manuals/m34.pdf."},{"page":7,"startToken":1527,"endToken":1808,"text":"7 \n• \nAdhering to the Stakeholder Group’s Charter and work plan, and seeking to \ncomplete it in a timely and efficient manner that meets any regulatory or other \ndeadlines. \nMoreover, PJM’s stakeholder process allows for the formation of a “user group.” \nRecently, the consumer advocates created a user group, the Affordability and Reliability \nfor Residential Consumers User Group. The consumer advocates also joined with \nenvironmental interests to form the Public Interest & Environmental Organizations User \nGroup. There is also the Independent State Agencies Committee (ISAC), which is a \nvoluntary, stand-alone committee that consists of members from regulatory and other \nstate agencies representing all of the states within the service territory of PJM and the \nDistrict of Columbia. “The ISAC is an independent committee that shall not be controlled \nor directed by PJM or the PJM Board of Managers.”4 The ISAC provides “PJM with input \nto inform the assumptions, scenarios, and studies developed as part of PJM’s Regional \nTransmission Expansion Planning Protocol as well as to discuss alternative sensitivity \nstudies, modeling assumptions, and scenario analyses.”5 The ISAC may also address \n“items described in section 1.5 of Schedule 6 of the PJM Operating Agreement,”6 i.e., the \nprocedures for developing the PJM Regional Transmission Expansion Plan. \nFinally, one of the most direct ways any stakeholder may communicate its position \nis to send a letter to PJM’s President and CEO, and to PJM’s Board of Managers. States, \npublic utility commissions, concerned citizens, and Members from every sector all avail \nthemselves of this opportunity, which typically results in a timely response from the Board \n \n4  OPSI, ISAC Charter at 1, https://opsi.us/wp-content/uploads/2023/05/ISAC-Charter.pdf. \n5  Id.  \n6  Id."},{"page":8,"startToken":1808,"endToken":2071,"text":"8 \nChair. A list of communications submitted to PJM and the responses from PJM are \npublicly posted on PJM.com here. \nQuestion 4. Governing Documents \n \nDo existing governing document provisions (e.g., Operating Agreement, Manuals) \nimpede stakeholder decision-making and what changes could be made to \naddress them? \n \nAlthough the current PJM governance framework remains generally sound, there \nare targeted reforms that could be made to improve the efficiency of the stakeholder \nprocess. Existing provisions of Manual 34 (PJM Stakeholder Process) impede \nstakeholder decision-making and a key example is the impact of voting that occurs at the \n“lower level” committees in determining which proposals may be voted on in the senior \ncommittees. The lower-level committees should play a critical role in screening and \ndeveloping the proposals that are ultimately considered by the senior committees. For \nproposals to be viable, their ultimate approval at the Members Committee should be \nreasonably foreseeable by the lower-level committees. In order to efficiently build \nproposals that may achieve consensus at the critical Members Committee, it is imperative \nto ensure that the voting structure at the lower level Standing Committees adequately \ncaptures the views of stakeholders represented in MC voting. Under the existing rules, it \ndoes not. \nThe current process impedes stakeholder decision-making because at the lower-\nlevel committees, all PJM Members receive one vote, including Affiliates, but at the senior \ncommittees, each corporate family receives only one vote.  As a result, Members with \nmore Affiliates control the flow of proposals from the lower-level committees to the senior \ncommittees, meaning that proposals that are not viable at the senior-level committees"},{"page":9,"startToken":2071,"endToken":2374,"text":"9 \nbecause there was not buy-in across the stakeholder sectors in the lower-level \ncommittees are sometimes moved forward, and potentially viable proposals are left \nbehind. \nIn this regard, the code of conduct included in Manual 34 explains that: \nthe stakeholder process has been designed intentionally so \nthat the decision-making authority is exclusively vested with \nthe Senior Standing Committees consistent with Operating \nAgreement, section 8.4. Votes at the \"lower\" Standing \nCommittees (e.g. the Operating Committee, Planning \nCommittee, Market Implementation Committee, and Risk \nManagement \nCommittee) \nand \ntheir \nsubordinate \nsubcommittees and task forces have no such weight or finality \nin their votes. Votes at the lower level Standing Committees \nmerely set the order of voting on various proposals that were \nconsidered in the lower Committee for consideration at the \nSenior Standing Committees and afford Members an \nopportunity to understand general stakeholder sentiment \nhelpful in fostering further consensus building activities. See \ngenerally, Section 3: Purpose of the Stakeholder Process as \nwell as Section 8: Consensus Based Issue Resolution at the \nStanding Committee Level. A PJM Members Committee vote \nis singularly the vote that fulfills their Operating Agreement \nresponsibilities. All other Member votes and stakeholder polls \nare only indicative of a Members' preference or interest as \nsolutions are explored.7 \nAt the two senior committees, the MRC and the MC, only Members are able to \nvote (i.e., no Affiliates and no non-Members). For all other committees and senior task \nforces, each Member gets one vote. The standard process for a Member seeking action \non an item by the MRC and MC requires that the proposal first receive simple majority \nsupport at the subordinate, lower level committees and task forces. If multiple proposals \nachieve simple majority support, the proposal with the greatest level of support is deemed \n \n7  PJM, Manual 34, Section 4.5, at 23."},{"page":10,"startToken":2374,"endToken":2684,"text":"10 \nthe “main motion” and the others are “alternates.” If the main motion passes at the MRC \nand MC, there is no vote on the alternates.  \nThus the disparity in voting participants at the lower level compared to the senior \nlevel committees may and often does greatly impact the voting outcome at the MRC and \nMC. This is because a Member with multiple Affiliates has an outsized opportunity to \ninfluence the order of voting, and therefore the proposals that are voted on, at the senior \nlevel. The largest numbers of Affiliates belong to Members in the Generation Owner (260), \nOther Supplier (228), and Transmission Owner (39) sectors.8 Members in sectors \ntypically viewed as aligned with consumer interests have few, if any, Affiliates; sector \ntotals are: Electric Distributors (9); End Use Customers (4). \nManual 34 explains that voting at the Standing Committees includes both Members \nand Affiliates, and that if a simple majority prefers a proposal over the status quo the \nproposal with the greatest level of support will become the Main Motion for consideration \nat the MRC, while other proposals will be Alternate Motions. If the Main Motion passes, \nno vote is taken on Alternate Motions.  \nThe status quo voting paradigm that allows Affiliates to vote at Standing \nCommittees favors Members with registered Affiliates. The more Affiliates a Member has, \nand the more Affiliates a sector has, the greater the influence that Member and that sector \nhave on Senior Standing Committees such as the MRC and MC, where voting is \nMembers-only. Members who have substantial numbers of Affiliates are positioned to act \nas a veto on proposals that would otherwise be brought to the MRC for a vote by only \nMembers (i.e., no Affiliates) since there are more Affiliate members in PJM (540) than \n \n8  PJM, Member List (July 10, 2026), https://www.pjm.com/about-pjm/member-services/member-list."},{"page":11,"startToken":2684,"endToken":2984,"text":"11 \nvoting Members (517).9 Due to their combined size, Members with their Affiliates may \nhave a voting block with substantial sway over the voting results at the lower committees \nand, by implication, at the Senior Standing Committee level. As noted above, there are \nthree sectors that have the overwhelming majority of total Affiliates in PJM and these \nthree sectors, or a combination of any two of the three sectors, are able to determine \nwhich, if any, proposals may be voted on at the MRC by all five sectors. \nOne simple way to fix this would be to modify the lower-level committee voting \nstructure to match the senior committees. This would allow voting Members to better \nunderstand whether a proposal that is supported at a lower-level committee has sufficient \nsector weighted support to potentially pass an MC vote, and if not, to identify the sticking \npoints so they can be addressed. \nAlternatively, in order to ensure that all Members of the MRC have the ability to act \non any proposal voted on at the Standing Committee in an equal manner to the Main \nMotion, not just those preferred by two or three sectors with the vast majority of Affiliates, \nPJM should analyze the voting results of the Standing Committee. If a proposal has \nreceived support from at least one voting Member from four of the five sectors it should \nbe viewed as a potentially viable proposal for consideration by the MRC. Voting on this \nadditional proposal along with the proposal that received the greatest level of support \nabove the simple-majority threshold would occur in a non-truncated manner, allowing \nboth proposals to be voted on at the MRC simultaneously. If multiple proposals receive \nsupport from at least four of the five sectors, the proposal with the greatest number of \n \n9  Id."},{"page":12,"startToken":2984,"endToken":3243,"text":"12 \ncombined votes would be moved for consideration to the MRC along with the status quo \n“Main Motion” proposal.  \nA proposal that receives support from at least one Member in four sectors would \nbe deemed a viable proposal for the MRC to consider as it could pass the MRC even if \none entire sector opposes it. This sensible change to the voting methodology for \nproposals considered by the MRC would mitigate any perceived veto power at either the \nStanding Committee level or the Senior Standing Committee level. \nQuestion 5. Stakeholder Process Reforms \n \nWhat reforms to the stakeholder process could ensure PJM can meet the region’s \nchallenges? \n \nThe single biggest challenge PJM continually faces is how to conduct a capacity \nauction to ensure sufficient quantities of capacity are available to meet anticipated \ndemand plus adequate reserves to maintain a 1-in-10 level of reliability, consistent with \nthe FERC-approved Reliability Pricing Model (RPM) capacity construct rules. RPM’s \nstructure is contained within PJM’s Open Access Transmission Tariff (OATT or Tariff). \nPJM has Federal Power Act section 205 filing rights over the OATT.10 No changes are \nneeded to the stakeholder process to ensure PJM can meet the region’s resource \nadequacy challenges, given the section 205 filing rights that PJM currently enjoys over \nthe terms and conditions of RPM. Rather than reforming the stakeholder process, \nsignificant reforms to how PJM prioritizes and schedules meetings to address the \nchallenges should be made.  PJM already has the ability to do so but has not.   \n \n10  With the exception of certain rights reserved by the Transmission Owners."},{"page":13,"startToken":3243,"endToken":3588,"text":"13 \nPJM’s Manual 34 offers a useful high-level description of the interplay between the \nPJM stakeholder process and filing rights under Federal Power Act sections 205 and 206, \nas follows: \nSections 205 and 206 of the Federal Power Act set forth the \nrequirements that must be met to obtain FERC approval of a \nproposed revision to a governing document and are germane \nto the governing documents of PJM (the Operating \nAgreement, the Open Access Transmission Tariff (Tariff) and \nthe Reliability Assurance Agreements (RAA)), and to the \noperation of the PJM stakeholder process. Sections 205 and \n206 establish the standards for demonstrating why a \nproposed revision to a governing document should be \napproved by the FERC. Section 205 requires that the \nproposer of a revision demonstrate the proposed revision is \n“just and reasonable.” Section 206 requires a potentially \nhigher hurdle in that the proposer of a revision to the \ngoverning documents must demonstrate that the then current \nprovisions are “unjust and unreasonable,” and that the \nproposed revisions are “just and reasonable.” Within the PJM \nstakeholder process it is recognized that the Members \nCommittee maintains Section 205 authority over the \nOperating Agreement, and that the Board of Managers \nmaintains Section 205 authority over the Open Access \nTransmission Tariff (Tariff) (with the exception of certain Tariff \nprovisions that are under the exclusive control of the \nTransmission Owners) and the Reliability Assurance \nAgreements. Any party not possessing 205 authority over one \nof the governing documents may propose a revision to the \ndocument to the FERC under Section 206. It is also \nrecognized that the Members provide input into the Regional \nTransmission Expansion Plan (“Plan”), and that the Plan is \napproved by the Board.11 \nManual 34 also describes the consultation process that PJM uses when making \nFPA section 205 filings. PJM is required under the Tariff to consult with the Transmission \nOwners and the MC at least seven days prior to filing. However, “neither the Transmission \nOwners, except as provided for in [Tariff] section 9.3, nor the PJM Members Committee \n \n11  PJM, Manual 34, Section 3, at 18."},{"page":14,"startToken":3588,"endToken":3849,"text":"14 \nshall have any right to veto or delay any such Section 205 filing.”12 Further, “PJM may file \nwith less than a full 7 day advance consultation in circumstances where imminent harm \nto system reliability or imminent severe economic harm to electric consumers requires a \nprompt Section 205 filing . . . .”13 \nQuestion 6. Near-term Reforms \n \nWhat near-term reforms to stakeholder representation could PJM and its \nMembers take to improve speed in decision-making while preserving stakeholder \ninput? \n \nPJM needs to focus on issues related to reliability and resource adequacy above \nother issues. Stakeholders work on issues that require rapid development based on \nPJM’s meeting schedules. PJM sets the cadence for the stakeholder process through the \ncalendar. PJM sets the priority of issues when it develops the calendar. If there is a \nconcern about the speed of decision-making, that is not cause for reforming stakeholder \nrepresentation. Instead, it only requires PJM to prioritize and schedule stakeholder \nmeetings so key discussions can occur more quickly.  \nQuestion 7. Committee Structure \n \nAre there elements of PJM’s committee structure that routinely contribute to \ndelays?  Are there stakeholder processes or issues that could be expedited or \nchanged to provide greater focus on key issues and allow faster or more \nunilateral action on others? \n \nAs noted above, PJM controls the calendar, which sets the pace and prioritizes the \nissues; the committee structure is not the concern. Significantly, per Manual 34, “[t]he \nSecretary of the Members Committee has ultimate meeting prioritization decision.”14 \n \n12  Id., Section 11.14, at 87. \n13  Id. \n14  Id., Section 11.4, at 80."},{"page":15,"startToken":3849,"endToken":4113,"text":"15 \nMoreover, while the MC chair and vice chair are representatives of Members, the MC \nSecretary is a PJM staff member15 “appointed by the President of PJM,” who administers \nthe stakeholder process procedures.16 The current MC Secretary is PJM’s Senior Director \nof Stakeholder Affairs.17 \nQuestion 8. Expedited Action \n \nShould PJM increase the use of fast-path or time-bound review procedures to \nexpedite committee action on high-importance topics?  \n \nSimply scheduling additional meetings closer together to address mission-critical \ntopics may be more effective than invoking truncated procedures. As we saw in the just \ncompleted CIFP-RBP/Connect & Manage process, when PJM attempts to use fast-path \nor time-bound review procedures to expedite action, PJM may trip itself up, resulting in \nwholesale changes to its own proposal. Similarly, stakeholders do not have sufficient time \nto work amongst themselves to consolidate their approaches, resulting in an unwieldy \nnumber of alternative proposals that often fail to consolidate into a clear consensus \nposition. Further, expediting discussions in Valley Forge at the expense of consensus in \nthe stakeholder process only serves to increase regulatory uncertainty. \nQuestion 9. Regional Differences \n \nRecognizing regional differences, are there lessons from other RTO/ISO \nstakeholder processes that PJM could reasonably adopt to improve speed in \nvoting processes and stakeholder representation? \n \nWhen PJM’s stakeholders have time to thoroughly discuss an issue, understand \none another’s opinions, and develop proposals that align with the theory of mutual gains \n \n15  See PJM, Members Committee, https://www.pjm.com/committees-and-groups/committees/mc. \n16  PJM, Manual 34, Definitions (Secretary), at 16. \n17  See PJM, Members Committee, https://www.pjm.com/committees-and-groups/committees/mc."},{"page":16,"startToken":4113,"endToken":4245,"text":"16 \n(the backbone of PJM’s Consensus Based Issues Resolution structure), the volume of \nproposals presented to the Members Committee is often greatly reduced, which in turn \nimproves the speed at which the stakeholder process proceeds to a vote. While PJM’s \nstakeholder process is open to all interested parties, PJM’s stakeholders, including its \nMembers, have very limited access to the PJM Board and essentially no insight into Board \ndecisions on matters passed on by the Board that lead to a FERC filing (FPA sections \n205 or 206) until that decision is finalized, filed, and communicated via email to the \nstakeholders. The transparency improvements discussed supra in response to Question \n2 draw on MISO and SPP governance examples that suggest the PJM Board should \nprovide more transparency regarding these matters. \n \nDated: July 14, 2026"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":1198,"startToken":0,"endToken":159},{"p":1,"at":1198,"title":"I. INTRODUCTION","method":"printed heading","endPage":3,"endAt":1063,"startToken":159,"endToken":590},{"p":3,"at":1063,"title":"II. COMMENTS","method":"printed heading","endPage":16,"endAt":850,"startToken":590,"endToken":4245}]}