{"document":{"slug":"rec-20260715-4006","title":"Pre-filed Statement of Brian D. George, Senior Lead of U.S. Energy Markets for Google LLC, for the PJM Governance and Stakeholder Reforms Technical Conference","issued":"2026-07-15","accession":"20260715-4006","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"GOOGLE LLC","kind":"testimony","file":"sources/filings/text/20260715-4006_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260715-4006","tier":"record","sha256":"a61e86e11f16bfa1795e081953ba123c070840d90e413e4c258be23d38dc2ad1","pages":6,"tokens":2376,"emptyPages":[],"textThemes":["registry"]},"pages":[{"page":1,"startToken":0,"endToken":310,"text":"UNITED STATES OF AMERICA \nFEDERAL ENERGY REGULATORY COMMISSION  \n \n \nPJM Governance and Stakeholder Reforms​ ​\n)​\n​\n        Docket No. AD26-7-000 \n \n \nPRE-FILED STATEMENT OF BRIAN D. GEORGE ON BEHALF OF  \nGOOGLE LLC \n \n \n \nChairman Swett and Commissioners Rosner, See, Chang, and LaCerte; \n \nThank you for convening this Chairman and Commissioner-led Technical Conference in the \nabove-captioned proceeding to discuss PJM Interconnection, L.L.C.’s (“PJM”) governance and \nstakeholder processes, with a particular focus on identifying and evaluating concrete, actionable \nreforms to improve PJM’s ability to address operations and market needs in a timely and efficient \nmanner.1 My name is Brian George and I serve as Sr. Lead, U.S. Energy Markets at Google, LLC \n(“Google”). My job responsibilities include establishing and executing Google’s energy strategy \nacross the RTO and ISO regions, including PJM, and at the Federal Energy Regulatory \nCommission (“FERC”), to ensure access to adequate power supply and infrastructure required to \nserve our data centers in the United States. I welcome this Commission’s proactive leadership on \ngovernance and stakeholder reforms in PJM, and appreciate the opportunity to submit this \npre-filed statement and participate in the Technical Conference. \n \nI offer these comments, observations, and recommendations in the interest of improving \ncollaboration, fostering innovative thinking, and ultimately producing tangible results that lead to \na more reliable and efficient grid that can simultaneously accommodate the integration of new \nlarge loads while also protecting residential consumers from unintended reliability or \naffordability issues. These pre-filed comments address the questions raised by the Commission \nin the Second Supplemental Notice of Commission-Led Technical Conference for Panel 2: PJM \nStakeholder Process – Design, Transparency, and Decision-Making, and are informed primarily \nby my experience participating in the recent Critical Issue Fast Path (“CIFP”) process on behalf \nof Google and as a member of the Data Center Coalition (“DCC”).  \n \n1 See Second Supplemental Notice of Commission-Led Technical Conference, Docket No. AD26-7-000 (July 2, \n2026).  \n1"},{"page":2,"startToken":310,"endToken":782,"text":"I.​\nPJM’s Stakeholder Process is a Robust, Open Forum, But Cannot Succeed Without \nConsistent, Active, and Transparent Leadership From PJM Executive Staff and \nBoard of Managers.  \n \nThe PJM stakeholder process is a public forum, and with limited exceptions, open to \nparticipation from any individual or organization, including member states. In general, any \nperson, including non-members, can participate in meetings, ask questions to PJM staff or other \nstakeholders regarding their respective packages, propose new packages or changes to existing \npackages, lobby other stakeholders, and build coalitions. Over the last year, during the course of \nPJM’s two CIFP stakeholder process to address Large Load Additions (“CIFP-LLA”) and the \nReliability Backstop Procurement and Connect-and-Manage reforms (“CIFP-RBP/C&M”), \nseveral members of the PJM Board of Managers (“Board”) were present, providing all \nparticipants with the opportunity to directly appeal to the members of the Board.  \n \nGoogle is not a PJM member, and we do not have voting rights in the PJM stakeholder process. \nHowever, Google was deeply engaged in both CIFP processes. We participated in nearly every \nmeeting, including in-person, when offered by PJM. In August 2025, at the outset of the \nCIFP-LLA, Google offered detailed public feedback to PJM and the Board, including proposed \nreforms of PJM’s large load forecasting process, PJM’s demand response rules to better align \nwith Google’s demand response capabilities, and a Bring Your Own New Generation \n(“BYONG”) proposal to provide large loads a pathway to bilaterally contract to offset new load \nwith new generation.2 In September, Google worked with a cross-sector coalition to develop, \nrefine, and advance a multi-issue package that contained reforms of PJM’s load forecasting \nprocess, demand response rules and emergency procedures designed to protect residential \nconsumers from blackouts in an emergency, and a proposed reliability backstop auction to \naddress PJM’s supply shortfall.3 Google was also proud to help lead, and join, via the DCC, a \nmulti-sector package that included four bipartisan governors and two major transmission owners \nin PJM.4  \n \nAs a result of our efforts, and many others within, and outside of, the traditional stakeholder \nbody, PJM and the Board had several strong options to address and manage large load additions. \nWhile many viewed the outcome of the CIFP-LLA as a failure because all twelve packages \npresented to the Board failed to receive the required sector-weighted approval, most the twelve \n4 Executive Summary of Joint Proposal by Governors, DCC, Exelon, PPL. Nov. 19, 2025.  \nhttps://www.pjm.com/-/media/DotCom/committees-groups/cifp-lla/2025/20251119/20251119-item-02d---data-cente\nr-coalition-governors-exelon-and-ppl-package---executive-summary.pdf  \n3 Joint Stakeholder Options, PJM CIFP – Large Load Additions. October 14, 2025.  \nhttps://www.pjm.com/-/media/DotCom/committees-groups/cifp-lla/2025/20251014/20251014-item-03k---amazon-c\nalpine-constellation-google-microsoft-talen---joint-stakeholder-proposed-options---updated.pdf  \n2 Critical Issues Fast Path – Large Load Additions, Stakeholder Comments, pp. 150-175. Aug 28, 2025.  \nhttps://www.pjm.com/-/media/DotCom/committees-groups/cifp-lla/postings/20250828-stakeholder-comments-cifp-l\nla.pdf \n2"},{"page":3,"startToken":782,"endToken":1310,"text":"packages were not all that dissimilar conceptually, indicating general stakeholder agreement on \nkey components and principles.5 In general, packages focused on reforms to load forecasting, \ndemand response and emergency procedures, and mechanisms to incentivize large loads to \nBYONG to offset new load or face curtailment risk if PJM’s resource adequacy picture failed to \nimprove. All things considered, the CIFP-LLA process worked quite well in identifying core \nissues and proposing conceptual reforms. It is not unreasonable to posit that with a narrowed and \ntargeted focus, additional efforts to build consensus, including, critically, from PJM leadership, \nand transparency from the Board regarding their desired outcomes from the stakeholder body, \nand a little more time, consensus could have been achieved. Even if consensus could not have \nbeen achieved, the Board certainly would have had clear options for potential reforms.  \n \nPJM has a tremendous, diverse, and intellectually engaged stakeholder body, comprised of \nsubject matter experts, process veterans, and the wonkiest of energy policy wonks, advocating \nfor a broad range of perspectives and interests. However, if asked to solve basic arithmetic, such \nas “what is the answer to one plus one?,” the PJM stakeholder body would undoubtedly spend a \nsignificant amount of time to produce multiple answers. Given the open nature of PJM’s \nstakeholder process, on top of over 1,100 formal PJM members, it can easily become unwieldy \nto manage and balance these naturally conflicting interests; this only becomes more difficult as \nthe complexity of the issues facing the stakeholder body increases. Left to their own devices, \nstakeholders cannot and will not achieve consensus, particularly on foundational market and \noperational issues. This is not a criticism of PJM stakeholders, but a reality of a large and diverse \nstakeholder body. At the end of the day, market administration and operation is PJM’s \nresponsibility; actions or changes have to be justified by PJM and approved by this Commission. \nTherefore, active, consistent, and transparent engagement and leadership from PJM, including \nthe Board, is essential to producing tangible outcomes in the stakeholder process.  \n \nThroughout the CIFP-LLA process, however, PJM’s position on the various packages or \nconceptual reforms was not consistently known, nor was there a visible public effort focused on \nstakeholder alignment on key reforms, or direction from PJM on acceptable (or unacceptable) \npathways forward. As an example, in response to 197 pages of stakeholder feedback on the \nCIFP-LLA scope in August 2025, PJM offered only a high-level 19 page presentation (including \nno acknowledgement or feedback on Google’s BYONG comments or questions).6 Given the \nstrict time boundaries of the CIFP process, and the volume of proposals on the table, stakeholder \nmeetings felt rushed and disjointed, rather than focused attempts to identify and build consensus. \nThe process was simultaneously substantively open-ended and bound by a rigid timeline, so the \noutcome was not unexpected. This outcome could have been avoided by the Board and/or PJM \n6 Large Load Additions, Stakeholder Feedback. Sept. 15, 2025. \nhttps://www.pjm.com/-/media/DotCom/committees-groups/cifp-lla/2025/20250915/20250915-item-04---stakeholder\n-feedback-on-large-load-additions---pjm-presentation.pdf  \n5 Ethan Howland, “PJM stakeholders fail to agree on data center interconnection rules,” Utility Dive, Nov. 20, 2025.  \n https://www.utilitydive.com/news/pjm-stakeholders-data-center-interconnection-cifp/806009/  \n3"},{"page":4,"startToken":1310,"endToken":1803,"text":"Staff more clearly articulating the problem statement, placing more explicit boundaries on scope, \nand exercising better time management to ensure only those packages most consistent with the \nscope received adequate stakeholder discussion and vetting. These are relatively \neasy-to-implement changes that require more affirmative and vocal stances from PJM leadership \nand the Board, if necessary.  \n \nThe subsequent CIFP process focused on the RBP and C&M benefitted from more affirmative \nPJM engagement and detailed proposals, yet suffered a lack of transparency into PJM’s \ndecision-making process, which resulted in last-minute, often significant changes in PJM’s \nproposals. For example, PJM’s initial RBP proposal included a six-month window for large loads \nto bilaterally contract for new capacity, a position supported by an overwhelming majority of \nstakeholders. As Google articulated extensively, BYONG is the best pathway to ensure the costs \nand risks of new generation required to serve large loads are appropriately borne by the large \nload, and not passed on to residential consumers, consistent with the principles of the Ratepayer \nProtection Pledge that Google and six other leading technology companies signed in March \n2026. Despite overwhelming support for PJM’s position, in May, PJM abruptly shifted to a \nSeptember RBP, forgoing the six-month window essential to allow loads to fully explore the \nBYONG alternative.  \n \nAs another example, consider PJM’s C&M proposal. Despite significant implementation and \njurisdictional questions, which were raised early and often in the CIFP process, PJM pressed \nforward on a C&M approach that did not provide sufficient detail or clarity. Basic questions, \nsuch as the definition of “new load” and how PJM’s proposal would respect existing, executed \nfirm service power contracts negotiated years ago, were either avoided, defined but then \nchanged, or provided with insufficient details. In response, in late June, PJM opted to move away \nfrom its C&M proposal in favor of a voluntary, registry-based concept administered largely by \nthe states. While the questions and concerns that ultimately supported PJM’s move had been \nraised since January, the late shift in position sparked, for good reason, concern among \nstakeholders, including the states, about implementation roles and responsibilities. It is not clear \nwhy PJM waited until so late in the process to adopt such a significant change; concerns could \nhave been avoided or mitigated had PJM shifted stance on C&M earlier in the process, allowing \nentities appropriate time to respond.  \n \nThese two examples raise two important points. First, we cannot be simultaneously frustrated \nwith a “broken” stakeholder process and also frustrated with the positions developed in that \nprocess when the process is put to work. If PJM had no intent to adopt stakeholders’ positions, \nparticularly on the RBP, it would have been easier and far less time consuming to simply move \nforward with a preferred approach. Second, significant changes to proposals have significant \ncommercial ramifications. In the case of C&M, an evolving definition of “new load” created \ncontinuous uncertainty regarding the amount of capacity new large loads would be expected to \n4"},{"page":5,"startToken":1803,"endToken":2273,"text":"procure to avoid curtailment; changing that date meant constantly recalibrating procurement \nefforts. Stakeholders dedicate a significant amount of time preparing for, and engaging in, PJM \nstakeholder processes, and informing their respective leadership of the nature of the various \nproposals to inform commercial activity (e.g., bilateral contracting for new generation). Sudden \nchanges in direction, even if well supported, require time to reevaluate the commercial landscape \nand adapt commercial activity.  \n \nPJM’s stakeholder process is unique, and as evidenced above, certainly not free from challenges. \nHowever, like any task, in order for it to be successful, it must be armed with clear directives and \na level of confidence that outcomes will be respected, or, in the alternative, the rationale for any \ndeviation by PJM should be clearly articulated and conveyed with sufficient time for the market \nto respond accordingly. Finally, while every stakeholder wants their position to win the day, that \nis an unreasonable expectation. The stakeholder process is premised on compromise, and \noutcomes will undoubtedly leave stakeholders with mixed emotions. However, fear of this \nshould not stand in the way of decisive action.   \n \nII.​\nAny Governance Reforms Should Be Clear About the Problems They Are Intended \nto Address, and How the Proposed Reforms Will Resolve Those Problems.  \n \nPJM is understandably facing an unprecedented amount of pressure, including from the President \nof the United States and the governors of the PJM states. We are in the midst of a period of rapid \nload growth following decades of stagnation. Extreme weather events are increasing in \nfrequency, and in early July, PJM was one emergency procedure away from deploying backup \ngenerators at data center facilities to preserve reliability while serving a record demand of over \n168,000 MW.7 The problems facing PJM are real, and they are here now.  \n \nGiven this, it is even more important that any changes to PJM’s governance structure clearly \narticulate how those changes will lead to better outcomes for the PJM region. The PJM \nstakeholder process would, without question, benefit from more consistent engagement from all \nof the PJM states, including the state commissioners, executives, and legislators. Google is proud \nto partner with state officials, including in the first CIFP process where the DCC joined a \ncoalition that included the governors of Pennsylvania, Maryland, New Jersey, and Virginia. \nIndeed, nothing within PJM’s current rules prevents states from engaging and influencing the \nprocess today. However, if changes are contemplated that would give states more authority (e.g., \nFederal Power Act Sec. 205 filing rights or a more formal role in selecting PJM Board \nmembers), those changes need to be explicit regarding their ability to address and resolve the \nidentified problems.  \n \n7 June Hot Weather Operations June 29 - July 5. July 9, 2026. \nhttps://www.pjm.com/-/media/DotCom/committees-groups/committees/oc/2026/20260709/20260709-item-04---hot-\nweather-update---presentation.pdf  \n5"},{"page":6,"startToken":2273,"endToken":2376,"text":"III.​\nConclusion  \n \nGoogle welcomes the Commission’s dialogue on governance and stakeholder process reforms in \nPJM, and we appreciate your leadership in resolving the most pressing challenges facing the \nregion, and our nation. We look forward to the robust dialogue during and following this \ntechnical conference, and welcome the opportunity to collaborate with PJM, the PJM states, and \nall stakeholders as we seek common-sense reforms to meaningfully address and resolve \nchallenging problems. Thank you for the opportunity to provide these remarks and my \nperspectives.  \n \nSincerely, \n \n \nBrian D. George \nSr. Lead, U.S. Energy Markets \nGoogle LLC \nbriangeorge@google.com \n \n \n \n \n \n \n \nDated: July 14, 2026 \n6"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":6,"endAt":6,"startToken":0,"endToken":2274},{"p":6,"at":6,"title":"Conclusion","method":"printed heading","endPage":6,"endAt":718,"startToken":2274,"endToken":2376}]}