{"document":{"slug":"rec-20260715-4009","title":"Pre-filed Statement of Kent Chandler, Non-Resident Senior Fellow of Energy and Environmental Policy at R Street Institute, for the PJM Governance and…","issued":"2026-07-15","accession":"20260715-4009","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"R STREET INSTITUTE","kind":"testimony","file":"sources/filings/text/20260715-4009_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260715-4009","tier":"record","sha256":"0402cdec7e389e193aaa060a77868ffb23760930ed7bfe72e125dcd48c086733","pages":6,"tokens":2936,"emptyPages":[],"textThemes":["adequacy","retail","study"]},"pages":[{"page":1,"startToken":0,"endToken":32,"text":"SUBMITTED STATEMENT OF \nKENT CHANDLER \nSENIOR FELLOW, ENERGY AND ENVIRONMENTAL POLICY  \nR STREET INSTITUTE \n \n \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nCOMMISSIONER-LED TECHNICAL CONFERENCE REGARDING PJM \nGOVERNANCE AND STAKEHOLDER REFORMS   \n \n \nJULY 14, 2026"},{"page":2,"startToken":32,"endToken":610,"text":"2 \n \nFERC TECHNICAL CONFERENCE REGARDING PJM GOVERNANCE AND \nSTAKEHOLDER REFORMS   \n \n \nChairman Swett and Commissioners Rosner, See, Chang, and LaCerte, \n \nThank you for holding this Commissioner-led technical conference, and for inviting me to \nparticipate in it. My name is Kent Chandler, and I am a Non-Resident Senior Fellow at the R Street \nInstitute, a nonprofit, nonpartisan think tank in Washington, D.C. Immediately before joining R \nStreet, I was a Commissioner and Chairman of the Kentucky Public Service Commission \n(Kentucky PSC), President of the Organization of PJM States, Inc. (OPSI), President of the Mid-\nAtlantic Conference of Regulatory Utilities Commissioners, and a member of the National \nAssociation of Regulatory Utility Commissioners’ Board of Directors and Executive Committee. \nDuring my time as a commissioner with the Kentucky PSC, I also served as a member of the board \nof the Organization of MISO States (OMS). Before being appointed to the Kentucky PSC, I served \nas a wholesale market advisor to the Kentucky commissioners, which included staffing the \nKentucky representative on the OMS and OPSI boards, including then-OPSI President, Kentucky \ncommissioner Talina Mathews. Prior to my time at the Kentucky PSC, I served as an assistant \nattorney general in the Kentucky Office of the Attorney General, which included representing \nKentucky consumers in the PJM stakeholder process as a Member.1  \n \nPJM’s governance process is broken, but not irreparably so.2 As opposed to other RTO regions, \nstates are on the outside-looking-in in PJM when it comes to major issues that ultimately affect \nretail electric rates and states’ economies. States have long sought a meaningful seat at the table in \nthe decision-making process at PJM, particularly on issues that jointly fall within the ambit of \nfederal and state jurisdiction, like wholesale transmission costs and resource adequacy.3 While \nmost states do not have an interest in becoming Members of PJM4, there is broad agreement \namongst states in the region that their current “soft” power is insufficient to represent their interests \nand to benefit their constituents. Merely conveying the positions of the states via letters to or \ndiscussions with the PJM Board of Managers is insufficient to effectuate outcomes sought by the \nstates, and serves to frustrate the states in a way that undermines PJM’s prime objectives. For \ninstance, if PJM is determined to file a capacity market proposal without state support, or the \nTransmission Owners are seeking a cost allocation opposed by OPSI, if either are approved by \nFERC, the states possess the ability to affect siting of generation or transmission through use of \ntheir police powers in response. This eye-for-an-eye process undermines the interests of PJM, its \nMembers and the states. PJM and the states need each other to succeed in order for them to succeed \nthemselves. \n \n \n1 “Member” refers to the definition of “Member” as found in the PJM Operating Agreement. \n2 Ethan Howland, “PJM may be ‘too big to function’: FERC Chairman Swett,” Utility Dive, May 13, 2026. \nhttps://www.utilitydive.com/news/pjm-ferc-swett-capacity-governance-data-center/820085/.   \n3 Ethan Howland, “States threaten to leave PJM without expanded role in grid operator,” Utility Dive, Sept. 25, 2025. \nhttps://www.utilitydive.com/news/governors-states-pjm-governance-conference-capacity/760842/; Ann McCabe, David \nA. Svanda, Betty Ann Kane, “Making Markets Work for PJM States, State Engagement Possibilities with PJM.” \nhttps://opsi.us/wp-content/uploads/2019/10/Making-Markets-Work-for-PJM-States-10-14-19-1.pdf, Oct. 2019.  \n4 Ethan Howland, “FERC reject West Virginia PSC, market monitor complaints seeking access to PJM committee,” \nUtility Dive, Mar. 4, 2024. https://www.utilitydive.com/news/ferc-west-virginia-psc-market-monitor-complaints-pjm-\nliaison-committee/709144/."},{"page":3,"startToken":610,"endToken":1253,"text":"3 \n \nDamage aside, what ails PJM can be fixed without the need for the Commission’s intervention. In \nfact, many of PJM’s substantive issues over the years stem from overly-intrusive FERC \nengagement.5 Furthermore, the Commission’s ability to dictate many specific governance reforms \nis limited given current legal precedent.6 Instead, the PJM Board of Managers, Members and the \nstates should get serious about ensuring the region’s electricity market works for its consumers. \nWhile there is certainly a role for the Commission, particularly as a convenor like it is in this \nproceeding, there is no legal impediment to the region’s stakeholders from agreeing on a changed \nframework that sets a new, more sustainable course. For instance, there is nothing keeping utilities \nfrom giving state commissions a formal role in proposing regional cost allocation methodologies \nto the Commission (beyond that limited role required in Order 1920-A) other than the utilities’ \nown preferences.7 The PJM Board of Managers could choose to share their FPA Section 205 filing \nrights over resource adequacy with the states. A few years ago state commissions supported the \nconcept of the PJM Board of Managers, not the Members Committee, having FPA Section 205 \nfiling rights over the regional’s transmission planning protocols. While the Members refused to \ngive up those rights because of the method employed by PJM and the regions’ utilities, and FERC \nrejected PJM and the utilities’ proposals to transfer those rights to the Board of Managers because \nadditional superfluous changes to governing documents would have undermined the RTO’s \nindependence, there has since been no effort to effectuate that change via a different path. I mention \nthese examples, not to relitigate issues from the past, but instead to note that a number of positive \nchanges – changes that would improve reliability, ensure just and reasonable rates, and reduce \ncomplaints to the commission, both oral and those filed under Section 206 of the FPA – can and \nshould be instituted by agreement from the PJM stakeholders. Many of the types of agreements I \nmentioned above might need to come back to the Commission, but only for its stamp of approval.  \n \nThe following are considerations for any governance change in PJM: \n \nTransparency  \n \nMembers, states and other stakeholders often gripe about not understanding the basis or rationale \nfor the Board of Managers’ decisions. The decisions I’ve heard these complaints regarding range \nfrom contract matters with the region’s independent market monitor to the eventual contents of a \nFPA Section 206 complaint after Members failed to advance a proposal through the stakeholder \nprocess. The Board of Managers should consider material changes to its own decision-making \nprocess that improve the transparency and messaging of its determinations. Some changes the \nBoard of Managers should consider are: open board meetings, where the public can observe; better \nmeeting minutes that convey the discussion of board members and a roll-call vote on each voting \nitem; or decisional orders that indicate the reasons for decisions, including what evidence or \narguments the Board of Managers considered in making its decision. Giving Members and the \npublic more information regarding the Board’s decision-making improves the durability of those \ndecisions. In a 2019 analysis of RTO governance, Travis Kavulla noted the following: \n \n \n5 See Robert Walton, “ FERC rejects PJM capacity market reform proposals, seeks quick resolution,” Utility Dive, June \n30, 2018. https://www.utilitydive.com/news/ferc-rejects-pjm-capacity-market-reform-proposals-seeks-quick-\nresolution/526903/; Ethan Howland, “FERC orders PJM to change reserve market rules, delay capacity auctions,” Utility \nDive, Dec. 23, 2021. https://www.utilitydive.com/news/ferc-orders-pjm-to-change-reserve-market-rules-delay-capacity-\nauctions/616556/; Iulia Gheorghiu, “FERC orders PJM to postpone capacity auction,” Utility Dive, July 26, 2019. \nhttps://www.utilitydive.com/news/ferc-orders-pjm-to-postpone-capacity-auction/559610/. \n6 See CAISO v. FERC, 372 F.3d 395 (D.C. Cir. 2004), and Atlantic City Elec. Co. v. FERC, 295 F.3d 1 (D.C. Cir. 2002). \n7 Similar to the OMS’s and SPP RSC’s FPA Section 205 filing rights."},{"page":4,"startToken":1253,"endToken":1815,"text":"4 \n \nSimply put, members of the public—both financially interested \nparties and other stakeholders alike—should have a right to \nunderstand clearly what information the RTO’s decision-makers are \nrelying on and the reasons they have for making important \ndecisions. Either holding open, deliberative meetings can \naccomplish this, or the RTO may accomplish it by documenting its \nreasoning. These hallmarks of good decision-making on matters of \nintense public concern echo the familiar requirement to which utility \ncommissions are subject, which is to make decisions that are not \n“arbitrary and capricious.”8  \n \nIf Members and states understand the “why” of PJM Board decision-making, development of \nproposals prior to PJM Board engagement is likely to improve. Although the engagement that \nMembers and states have with the PJM Board at Member Committee, Liaison Committee, and \nBoard-to-Board meetings is helpful in understanding perspectives, those opportunities are limited. \nUnderstanding how and why the Board of Managers made specific decisions in written form is \nhelpful to stakeholders for the same reason Commission orders are helpful to understand where \nregulators stand on issues: so that proposals improve going forward.  \n \nDurability \n \nWhile the Commission maintains jurisdiction over PJM and its governing documents, it must \nensure it balances hearing out entities affected by the PJM processes and giving the stakeholder \nprocess the deference its rules provide. FERC, and to a certain extent, the PJM Board of Managers, \nhas too often been responsive to the loudest and most aggressive detractors to a particular outcome. \nThis often results in a “squeaky wheel gets the grease” paradigm. Market rules shouldn’t be \ndictated by which actors can be the squeakiest wheel. FERC and the PJM Board must ensure that \nwhen hearing out the concerns of disaffected stakeholders they don’t unduly or unreasonably \nundermine the rules created by current processes. Where the outcome of a process, or the process \nitself, is unjust and unreasonable as understood under the Federal Power Act, then the Commission \nshould of course find as much. However, Members that merely didn’t get their way in stakeholder \nprocesses shouldn’t be able to undermine the success and durability of rules and concepts that \notherwise successfully moved through that process. Allowing “sore losers” to undermine the \nprocess after-the-fact, especially stakeholder outcomes that contribute to market efficiency, limits \nengagement in that same process going forward, and sends a signal to Members to lobby \ndecisionmakers rather than participate in votes and seek consensus.  \n \nFurthermore, while the PJM capacity market drives a minority of costs in PJM9, it has been the \nprimary point of contention in the region for the last decade. Given the overlapping nature of the \ncapacity market’s focus on resource adequacy and the role and jurisdiction of states in siting, \npermitting, and in some instances authorizing or certificating generation, state skepticism and \ndisagreement on market rules runs the risk of undermining the purpose of the capacity auctions. \n \n8 Travis Kavulla, “Problems in Electricity Market Governance: An Assessment,” R Street Policy Study No. 180, Aug. 30, \n2019. https://www.rstreet.org/research/problems-in-electricity-market-governance-an-assessment/.  \n9 In 2025, the PJM capacity market drove 15.8% of total costs in the market. In 2024, capacity represented 6.5% of total \ncosts in the PJM. Monitoring Analytics, LLC, Independent Market Monitor for PJM, “2025 State of the Market Report \nfor PJM, Volume I,” Mar. 12, 2026, at 17. \nhttps://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2025/2025-som-pjm-vol1.pdf."},{"page":5,"startToken":1815,"endToken":2441,"text":"5 \n \nAs such, the region must involve the states in the formulation of rules that ensure resource \nadequacy. In furtherance of that objective, the PJM Board of Managers should consider amending \ntheir pre-filing process for capacity auction rule changes anticipated to be made under Section 205 \nof the Federal Power Act in a way that drives state participation early in the process and gives \nthem a meaningful role over proposed rule changes. One suggestion for how this reform could \nlook would be for the PJM Board of Managers, after informing stakeholders on the content of their \nto-be-filed Section 205 proposal, to commit to filing an alternative state proposal alongside theirs \nat the Commission as a “jump ball.” Assuming the PJM Board of Managers requires the states’ \nfiling to be holistic and complete, and cover the issues addressed by the Board’s own filing, I find \nit likely that a competing state proposal will be rare. However, in order for 1) the Board of \nManagers to ensure they don’t have a competing state proposal, and 2) the states to have their ideas \nincorporated in PJM’s submission, rather than create and submit their own, this governance reform \nwill likely drive greater engagement early on in the policy formation process between states, PJM \nand the Members. Having state buy-in on market reforms and reducing litigation risk for ultimate \nfilings is a material benefit to the durability and effectiveness of the region’s rule set. I’ve seen \nfirsthand in MISO that having real opportunities for state engagement in the stakeholder process \n(and a role in formulating a FERC proposal, if it comes to that) drives more serious engagement \nfrom the states.  \n \nPrioritization  \n \nOver the past few years, PJM has struggled to sufficiently prioritize pressing issues, or when the \nRTO does prioritize something, they myopically focus on that issue to the detriment of other \nimportant considerations. PJM and its Members must reform the stakeholder process to ensure \nappropriate prioritization and work flows that accommodate pressing issues while ensuring other \nimportant problems are not ignored. This could include an annual publication by PJM of their \npriorities, either by the PJM Board of Managers, or jointly between the Board and PJM’s Members \nand states. While any prioritization will need to be inherently flexible to accommodate imminent \nand unforeseeable issues, publicly noting or agreement to policy issues to be addressed and on \nwhat timeline, gives Members and the public confidence in the direction of policy formation and \nmarket rules. This type of prioritization also allows stakeholders, particularly those without captive \ncustomers and retail rate recovery of the costs of RTO membership, to identify and prioritize \nresources for engagement at PJM.10 Allowing Members and states to understand what issues, in \nwhat order and at what speed are to be expected will allow them to prioritize internal and external \nresources and more meaningfully contribute to the stakeholder process. This would also allow \nMembers to seek out their own education and ideas on issues that are in the queue to be discussed, \nreducing the need to spend as much time and effort in the formal stakeholder process for education. \nFinally, publication of priorities will inform state and federal stakeholders so that they can hold \nthe RTO accountable for whether it is meeting its own expectations.  \n \nIndependence  \n \nFERC, through its more expansive jurisdiction over RTOs than other utilities, must ensure its \nengagement, regulation and intervention in market and governance issues doesn’t further add to \nthe chasm between utility experiences within and outside of RTOs. Today, the reality is that \nutilities outside of RTOs have it much easier than those within. I’ve seen firsthand non-RTO \n \n10 Travis Kavulla, “Problems in Electricity Market Governance: An Assessment,” R Street Policy Study No. 180, Aug. \n30, 2019. https://www.rstreet.org/research/problems-in-electricity-market-governance-an-assessment/."},{"page":6,"startToken":2441,"endToken":2936,"text":"6 \n \nutilities fight to stay out of an RTO, and I’ve seen utilities inside RTOs use their voluntary \nmembership, and the purported headache dealing with FERC and market issues that comes with \nit, as leverage to get what they want from PJM. This tactic increased with the creation of SEEM, \nand was most recently floated by the country’s largest wires company, AEP, ostensibly to \neffectuate the governance changes it would like to see and will advocate for in forums like this.11 \nPrevious analysis by R Street on the impact on governance and outcomes of voluntary RTO \nmembership is instructive on this point. \n \nRTOs are beholden to transmission owners as a practical matter, \nrespondents suggested, because the consent of these utilities gave \nrise to RTOs in the first place. As long as transmission owners’ \nmembership in RTOs is voluntary, as FERC has long agreed it to be, \nthe transmission owners always have the threat of withdrawal at \ntheir disposal. The matter is not merely theoretical. Transmission \nowners have previously decided to leave one RTO and join another \nfor reasons that presumably concern their bottom line. (In certain \nRTOs, large exit fees or the requirements of state policy for \ntransmission owners to belong to an RTO may reduce the \nimportance of this dynamic.) This dynamic leads to a “built-in \nconflict of interest” where RTO management is always looking over \nits shoulder to appease transmission owners at the expense of other \nparties, including consumers.12 \n \nFERC should be cognizant of creating a bifurcated regulatory regime for utilities within and outside \nof RTOs. Further, PJM should be empowered, both by Board of Managers and FERC action, to \nbolster its independence from Members. This could include raising the bar for FERC consideration \nof a utility request to leave an RTO, the process by which PJM staff engages Members, or by \namendment to PJM governing documents.  \n \nConclusion \n \nOver the years, Commission actions have served to make the PJM Board of Managers’ task more \ndifficult, often times unintentionally.13 The Commission should take efforts to ensure any \ngovernance amendments, formal or suggestive, that arise from this technical conference serve to \nenhance RTO decision-making and market efficiency, rather than diminish them. Consumers \ndeserve as much.  \n \n \n \n11 Ethan Howland, “AEP eyes exit from PJM, SPP over slow generation interconnection,” Utility Dive, May 6, 2026. \nhttps://www.utilitydive.com/news/aep-pjm-spp-data-centers-earnings/819419/.  \n12 Travis Kavulla, “Problems in Electricity Market Governance: An Assessment,” R Street Policy Study No. 180, Aug. \n30, 2019. https://www.rstreet.org/research/problems-in-electricity-market-governance-an-assessment/, (internal citations \nomitted). \n13 See Robert Walton, “ FERC rejects PJM capacity market reform proposals, seeks quick resolution,” Utility Dive, June \n30, 2018. https://www.utilitydive.com/news/ferc-rejects-pjm-capacity-market-reform-proposals-seeks-quick-\nresolution/526903/; Ethan Howland, “FERC orders PJM to change reserve market rules, delay capacity auctions,” Utility \nDive, Dec. 23, 2021. https://www.utilitydive.com/news/ferc-orders-pjm-to-change-reserve-market-rules-delay-capacity-\nauctions/616556/; Iulia Gheorghiu, “FERC orders PJM to postpone capacity auction,” Utility Dive, July 26, 2019. \nhttps://www.utilitydive.com/news/ferc-orders-pjm-to-postpone-capacity-auction/559610/."}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":3445,"startToken":0,"endToken":554},{"p":2,"at":3445,"title":"A. Svanda, Betty Ann Kane, “Making Markets Work for PJM States, State Engagement Possibilities with PJM.”","method":"printed heading","endPage":6,"endAt":1928,"startToken":554,"endToken":2752},{"p":6,"at":1928,"title":"Conclusion","method":"printed heading","endPage":6,"endAt":3440,"startToken":2752,"endToken":2936}]}