{"document":{"slug":"rec-20260716-4000","title":"Pre-filed Statement of Marjorie Rosenbluth Philips, Senior Vice President of Wholesale Market Policy for LS Power Development, LLC, for the PJM Governance…","issued":"2026-07-16","accession":"20260716-4000","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"LS POWER DEVELOPMENT, LLC","kind":"testimony","file":"sources/filings/text/20260716-4000_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260716-4000","tier":"record","sha256":"a587d097f5f34cbbef69aa0948d255f3b0810586c9c9b98d3f3424aae4d4f20a","pages":13,"tokens":5106,"emptyPages":[],"textThemes":["retail"]},"pages":[{"page":1,"startToken":0,"endToken":276,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \n \n \n \nPJM Governance and Stakeholder Reforms \n) \n)\n) \n \n \n Docket No. AD26-7-000  \n \n \n                                     \n \n PRE-TECHNICAL CONFERENCE COMMENTS OF MARJORIE PHILIPS, LS \nPOWER DEVELOPMENT, LLC  \nI. Introduction \nLS Power Development, LLC (“LS Power”) appreciates the opportunity to \nparticipate in this examination of the efficacy of PJM Interconnection LLC (“PJM”) \ngovernance structure.1 Founded in 1990, LS Power is a premier development, \ninvestment, and operating company focused on the North American power and \nenergy infrastructure sector, with leading platforms across generation, transmission \nand energy expansion solutions. Since inception, LS Power has developed or \nacquired 50,000 MW of power generation, including utility-scale solar, wind, hydro, \nbattery energy storage, and natural gas-fired facilities. Through its transmission \nbusiness, LS Power Grid, the company operates 7 transmission utilities, has built \n780+ miles of high-voltage transmission with another 400+ miles currently in \nconstruction or development. LS Power actively invests in and scales businesses that \nare meeting the growing needs of the energy expansion, including electric vehicle \ncharging, demand response, microgrids, renewable fuels and waste-to-energy \nplatforms. Over the years, LS Power has raised more than $85 billion in debt and \nequity capital to support North American infrastructure. LS Power has been an active \nparticipant in PJM for three decades.   \nEvery stakeholder, whether Member and non-Member has had grievances with the \nPJM governance process at one point or another, but the bottom line is that Members, \nthe Board, and the relevant regulatory bodies should be proud: PJM’s \n \n1 All terms used herein shall have the meaning set forth in the PJM Operating Agreement.  PJM, \nAmended and Restated Operating Agreement, Rate Schedule FERC No. 24, (eff. 7/14/2011) \n(“Operating Agreement”)."},{"page":2,"startToken":276,"endToken":722,"text":"LS Power Comments \nPage 2 \n \n“constitutional” documents have allowed PJM to evolve over more than thirty years \nwhile maintaining reliability through independent and competitive markets.   \nConsidering the unprecedented growth in data center demand, all market \nparticipants, including PJM, are having to reconsider how their past programs can \nbe improved to meet rapidly developing needs and stability for the future. We are all \ndoing so while trying to balance enhanced stakeholder engagement up and down the \nvalue chain. And so, we must ask here, is PJMs present need to make adjustment \none of fundamental governance reform or just another step-change aligned with the \ngovernance structures which have served the region well over time?  \nIn answering this question, we find that the unanticipated resource adequacy issue \nfacing PJM (amongst others) is not fundamentally one of governance. While record \nunanticipated load growth associated with data center development is a matter of \ncritical importance - ranging from national security to everyday personal use - \naddressing this need is more logically addressed through the lens of stable market \nrules, efficient interconnection queues, supply chain constraints and broader \npermitting regimes, rather than PJM governance.  \nWhile it is true that PJM did not have or in some cases, did not robustly follow the \nrules in place to facilitate and manage this unanticipated load growth,  it is also true \nthat no amount of governance reform today can change the physical reality that it \npresently takes roughly five years to bring a new combined-cycle plant online, and \nconsiderably longer for coal and nuclear facilities, not to mention getting \ntransmission upgrades built.  \nDriving the governance discussion is the concern policy makers have expressed: \nthey lack access to the Board, and it is not independent of stakeholder influence.  \nThis is a false narrative.  Policy makers and Members already have access to the \nBoard; policy makers through the Organization of PJM States (“OPSI”) meetings, \nand Members through the Liaison Committee.  The states are not restricted by ex \nparte rules that apply to stakeholders.  Furthermore, all these parties can participate \nin stakeholder proceedings, and any interested party can send a letter to the Board \nexpressing its opinion, which is then shared publicly.  Indeed, PJM has filed joint \nproposals with state utility commissions and representatives of governors have made \npresentations in the stakeholder process.2 \n \n2 PJM Interconnection, L.L.C., Docket No. ER25-1357-000, \"Proposal for Revised Price Cap and Price Floor for the \n2026/2027 and 2027/2028 Delivery Years, and Request for a Waiver of the 60-Days' Notice Requirement to Allow \nfor a March 31, 2025 Effective Date,\" filed February 20, 2025. See also https://www.pjm.com/-\n/media/DotCom/committees-groups/committees/mrc/2025/20250618/20250618-item-04---3-sub-annual-capacity-\nmarket---presentation.pdf"},{"page":3,"startToken":722,"endToken":1228,"text":"LS Power Comments \nPage 3 \n \nWhat PJM’s governance structure can offer in times of robust growth is a stable \nregulatory forum for decision-making, one which continues to be deeply invested in \nproviding the regulatory certainty and price-signals required to allow stakeholders \nto make multi-decade investments in U.S. wholesale power infrastructure possible. \nWith that said, opportunities exist to enhance PJM’s existing governance structure \nto ensure better transparency, policy maker input, and stakeholder alignment while \npreserving PJM’s independence and mission to ensure reliability through \ncompetitive markets. \nII. The Board and PJM’s Jurisdictional Authority \nOur comments are grounded in the jurisdictional and regulatory limits that apply to \nthe Commission, PJM, and the states. The Federal Power Act does not speak in terms \nof “affordability.” Instead, it requires FERC to judge whether a rate is “just and \nreasonable” — a standard that turns on the relationship between a seller’s costs and \nmarket position (market power), and the price that seller charges.3 “Affordability,” \nby contrast, is a qualitative judgment about the impact of a rate on the buyer, and \nturns on the relationship between a customer’s income and its retail bill. \nThis distinction is why it is critical that the PJM Board focuses on producing \nwholesale market outcomes that are just and reasonable, while the states focus on \nhow those market outcomes are then allocated — equitably or otherwise — to their \nretail constituents. Keeping these two distinct responsibilities straight and keeping \nthem with the entities who jurisdictionally manage them, is foundational to \neverything that follows.4  Addressing the present significant load growth challenge \nwill require hyperscalers, state and federal regulators, PJM, the PJM Board, \ntransmission and generation asset owners and developers, end users, transmission \ndependent utilities and consumer advocates to work cooperatively to implement \nrules and regulations in the RTO, at the federal and at the state levels to manage this \n \n3 Federal Power Act § 206(a), 16 U.S.C. § 824e(a) (2018). \n4  “We recognize that states have exclusive authority over resource planning and the generation mix within their \nboundaries. Nothing about our preliminary finding here, however, intrudes or is intended to intrude on that exclusive \nauthority.” New York Independent System Operator, Inc., 195 FERC ¶61,216, at ¶93 (2026).  \nSee also Commissioner LaCerte concurrence: To that end, and in light of our action in today’s orders, I also ask the \nstate public utility commissions—whether they have already approved large load retail tariffs, are in the process of \ncrafting large load retail tariffs, or have yet to embark on this essential tariff design process—to take a hard look and \nensure their large load retail tariff provisions insulate ratepayers from the negative impacts of data center growth. \nAdditionally, I expect PJM to design proposals in response to this show cause order that dovetail with the efforts on \nthe retail side to implement the Ratepayer Protection Pledge, protect customers, and ensure that large loads cover the \ncosts they incur to integrate with the grid. PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (2026) (LaCerte, \nComm'r, concurring at 3)."},{"page":4,"startToken":1228,"endToken":1661,"text":"LS Power Comments \nPage 4 \n \nnew grid reality while ensuring PJM fulfills its missions of maintaining reliability \nthrough competitive markets.  Our recommendations below are offered in \nrecognition of those jurisdictional realities and in the core understanding that \ncooperation and coordination is imperative to success. \nThe three pillars of PJM governance, the Open Access Transmission Tariff, the \nOperating Agreement and the Consolidated Transmission Owners Agreement \n(“CTOA”), are each foundational documents upon which PJM was approved and \nhas operated for three decades.  Section 3.1 of the Operating Agreement provides \nthat the purpose of the LLC (PJM) is “to operate in accordance with FERC \nrequirements as an Independent System Operator, comprised of the PJM Board, the \nOffice of the Interconnection, and the Members Committee, with the authorities and \nresponsibilities set forth in this Agreement.”5  The Members Committee is an \nintegral part of PJM as an Independent System Operator.  No single FERC approved \ndocument regarding PJM’s formation is more important than the other, and each \nholds equal authority in the ongoing operation and governance of PJM.  Any \nassertion to the contrary does not appropriately reflect the foundation of PJM.6   This \ndeliberately crafted allocation and balance among the parties is what has contributed \nto PJM’s success; any action that significantly tilts this balance in order to meet the \nmoment must be considered judiciously so that it does not undermine PJM’s overall \nsuccess. \nIII. Board Independence \nSection 7.7 (i) of the Operating Agreement places the duty on the PJM Board to \nensure “that a Member or group of Members shall not have undue influence over the \noperation of the PJM Region.”   \nNote that the discussion around who has 205 rights applies only to the Operating \nAgreement.  With respect to resource adequacy, PJM has exclusive 205 rights under \nthe Reliability Assurance Agreement (“RAA”).  Under the Operating Agreement, \non the other hand, for matters that pertain to the energy market and regional \ntransmission planning protocols, when the Members Committee reaches a 2/3 sector \nweighted vote, PJM is expected and indeed, required, to respect that vote and file \n \n5 Operating Agreement Section 3.1. \n6 Furthermore, the CTOA itself indicates that the Operating Agreement, which is controlled by the PJM Members \nCommittee, is foundational.  Section 3.1 of the CTOA states:  Prior to [the CTOA] becoming effective as to any \nsuch entity, each of the following events shall have occurred: i. The Operating Agreement is in full force and effect.   \nii. The Operating Agreement has been executed by the entity.  iii. [The CTOA] has been executed by the entity. iv. \nAll required regulatory approvals have been obtained."},{"page":5,"startToken":1661,"endToken":2150,"text":"LS Power Comments \nPage 5 \n \nthe passed Members Committee language with the Commission acting in an \nadministrative capacity, accordingly.7  The Operating Agreement also provides the \nPJM Board explicit powers to comment, either on its own initiative or at the request \nof a PJM User Group, on proposed Operating Agreement changes as it moves \nthrough the stakeholder process or to submit directly to the Members Committee \nproposed Operating Agreement language8. State Policy Makers, for their part, hold \nno formal voting rights, but they nonetheless exercise considerable influence over \nPJM outcomes.9 \nGiven this structure, Board independence means that when the Board reaches a \ndecision, it must weigh the full range of views expressed by these constituencies and \nthen act independently and consistently with its mandate and PJM’s governing \nagreements. PJM Board independence is not only a governance imperative for just \nand reasonable rates, but also an imperative to the long-term health of the market.  \nSome are concerned with Board independence and transparency and have proposed \nthat the Board hold open meetings.10 For the PJM Board to continue to enjoy \nindependence requires them to continue to exercise their role with the highest ability \nto conduct fulsome deliberations which can only be afforded by maintaining closed \nBoard sessions. LS Power is concerned that honest deliberation will be muted if \nBoard members believe they are being judged for the appearance of favoring a \nparticular position, and that open sessions risk becoming performative rather than \nsubstantive. The same reasoning counsels against disclosing individual votes.  \nNonetheless, we see room for meaningful improvement short of full PJM Board \ntransparency or a change in the way Section 205 rights are allocated.  LS Power’s \nrecommendations include: \n \n7 Duquesne Light Co. v. PJM Interconnection, L.L.C., 176 FERC ¶ 61,052 at PP 26-27 (2021).  The Members \nCommittee can file Section 205 Operating Agreement language changes directly with FERC today without PJM’s \nadministrative function.  PJM also acts in a purely administrative capacity when filing Section 205 filings for PJM \nTariff revisions for PJM Transmission Owners. \n8 Section 7.7(v) of the Operating Agreement explicitly provides the PJM Board with the authority to “on its own \ninitiative or at the request of a User Group as specified in this Operating Agreement, submit to the Members \nCommittee such proposed amendments to this Agreement or any Schedule herein, or proposed new Schedule, as it \nmay deem appropriate.” \n \n9 PJM Interconnection, L.L.C., Docket No. ER25-1357-000, \"Proposal for Revised Price Cap and Price Floor for the \n2026/2027 and 2027/2028 Delivery Years, and Request for a Waiver of the 60-Days' Notice Requirement to Allow \nfor a March 31, 2025 Effective Date,\" filed February 20, 2025Cite to PAPUC VRR proposal; see also \nhttps://www.pjm.com/-/media/DotCom/committees-groups/committees/mrc/2025/20250618/20250618-item-04---3-\nsub-annual-capacity-market---presentation.pdf  \n10 Kavulla, Problems in Electricity Market Governance: An Assessment,” R Street Policy Study No. 180 (Oct. \n2019), p. 11 (“Kavulla Report)."},{"page":6,"startToken":2150,"endToken":2611,"text":"LS Power Comments \nPage 6 \n \n● Require the Board to explain its reasoning.11 Companies like ours are \ninvesting billions of dollars in this market, and we need confidence that Board \ndecision-making is consistent over time. That confidence is undermined when \nthe Board takes actions inconsistent over time with no explanation.12  The \nBoard should be required to explain the basis for the given position and \nprovide sound reasoning especially when it reverses course. \n● Relax the ex parte rules that apply to Board-stakeholder interactions. Other \nRTOs build in structured, direct Board interaction with stakeholders — for \nexample, quarterly meetings with individual sectors — and PJM should \nconsider a similar approach. \n● Adopt the ISO-NE model of assigning a Board member to each state.13 That \nBoard member would be responsible for maintaining a regular outreach \nschedule with state representatives, potentially extending to the state’s utility \ncommission or the governor’s office. This would give states the level of direct \nBoard access that some have said they currently lack.  It would also provide \nthe Board with insight into interests that are particular to a given state and \nworth considering in deliberations.  That said, these interactions should not \nundermine the independence requirement of Board decisions. Having this \nunique structure in place also enhances state engagement in a way that is not \navailable to stakeholders.  \n● Create a Market Surveillance Committee along the lines of the CAISO.14 This \nCommittee would be comprised of independent individuals with expertise in \nelectricity market design (with an emphasis on independence), who advise the \nBoard on decisions.  This could help break the perceived cycle of when PJM \nproposes to modify an existing rule to ensure efficient price outcomes \nstakeholders narrowly focus on their economic interest rather than the benefit \n \n11 Kavulla Report, p. 14. \n12 See https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2024/20240919-pjm-board-\nresponse-consumer-advocates-letter-re-urgent-reforms-pjm-capacity-market-re-reliability-must-run-units.pdf and \nsubsequent change in position (issued September 19, 2024) and a subsequent reverse in position in December in a \nFERC filing PJM Interconnection, L.L.C., Docket No. ER25-682-000, \"Revisions to Reliability Pricing Model,\" \nfiled December 9, 2024 \n13 “Additionally, the Nominating and Governance Committee of the ISO-NE Board assigns two Board members to \nserve as liaisons between the Board and each state commission. The Board liaisons and the state commissions meet \nat least once per year, every six to eight months, depending on the interest of the state commission and the \navailability of the liaisons.[35] NESCOE, NECPUC, or state officials can request meetings with the Board as \nneeded.”  Governance Structure and Practices in the FERC Jurisdictional ISOs/RTOs February 2021, Prepared for \nNESCOE by: Christopher A. Parent Katherine S. Fisher, William R. Cotton, Cali C. Clar, Exeter Associates, Inc. \n(February 2021), Section 3.2.2. \n14 https://www.caiso.com/meetings-events/topics/market-surveillance-committee."},{"page":7,"startToken":2611,"endToken":3056,"text":"LS Power Comments \nPage 7 \n \nto the overall health of the market.  It would add some discipline and oversight \ninto stakeholder input and provide the Board with greater ability to understand \nand evaluate the merits of PJM and stakeholder proposals.  \nIV. Enhancing State Participation in the Stakeholder Process \nLS Power has long supported expanded Section 205 rights for PJM states related to \ncost allocation for new transmission and supports ensuring the states have a \nmeaningful way to participate in Board, PJM and stakeholder deliberations.  Given \nthat there are 13 states and the District of Columbia, there is no single policy to \nincorporate into the PJM markets, unlike single-state RTOs.  It would undermine the \nindependence of PJM and the Board to integrate a single state policy goal into the \nmarket rules of PJM.   \nThe states were intimately involved in the discussions involving the formation of \nPJM.  At that time, states did not want to be voting members because they did not \nwant to be constrained by the rules governing stakeholders.  They wanted the ability \nto interface with PJM management and the Board outside of the stakeholder process.  \nSome were also concerned that voting would give the appearance of prejudicing their \nprimary role of ensuring wholesale prices are appropriately incorporated into state \nretail tariffs.  The concern was that it could prejudice the record if they were involved \nwith the creation of these costs at the wholesale level.  They also did not want to \nparticipate directly in the RTO through a voting mechanism so that they could retain \njurisdictional distinctions between the Commission and the states.15   \nThis reasoning still stands today.  Indeed, providing the States with a formal role in \nrunning PJM would add to the policy uncertainty that exists today.  As noted early \nin these comments, making multi-billion-dollar investments with several decades of \nuseful life will require market structure durability and contract sanctity.  Both of \nthose drivers of investment can be undermined by political pressure, which runs in \nfour-year cycles and is not primarily focused on long-term market viability.   \nTo that point, PJM’s job is to run a market which in its basic terms matches supply \nto demand and produces a just and reasonable cost for the service.  The allocation of \nthat cost then becomes a rate-making issue for the states, who rightly manage \naffordability constructs.  To a great extent, the states already can control those costs: \nfor example, states control the physical siting for hyperscalers from building data \ncenters in their states limiting demand, they can develop tariffs that ensure the \nhyperscalers pay their fair share for interconnection costs and retail service, and they \n \n15 https://www.eba-net.org/wp-content/uploads/2023/02/11-185-205.pdf"},{"page":8,"startToken":3056,"endToken":3451,"text":"LS Power Comments \nPage 8 \n \ncan implement tariffs that protect other customers from costs created by the need to \nprovide hyperscalers electricity.  But all of these roles would benefit from increased \ncoordination.  Thus, LS Power strongly supports the process proposed by Chairman \nBagot of Virginia and representatives of the data centers to develop model retail \ntariffs.16 \nLS Power has examined other RTOs in the country for insight into the role of states.  \nIt is worth quoting an Energy Bar Association article that noted:  \n“As regulators began practical consideration of an advisory role in regional \nwholesale markets, it is helpful to restate, in this context, how those markets \nfit with state regulation.  These answers take slightly different shapes in states \nwith retail competition regimes and those with traditional vertically integrated \nregulatory systems”.  For example, in SPP, states have voting rights over some \nof SPP’s tariff while in MISO, the states have a purely advisory role and do \nnot vote, even on transmission related issues.17   \nIndeed, FERC itself has expressed concerns about the role of states in RTO \ngovernance as reported in a document prepared for NARUC:   \n“Overall, the Final Rule allows for flexibility as to the appropriate role of the \nstates in RTO governance and operation (after RTO development and \nformation), particularly in those few areas where the FERC does not intend to \nexercise exclusive authority under the Federal Power Act.  Stated another \nway, after RTO development and formation ... the role of the states in RTO \ngovernance and operation might tend to be mainly advisory in nature.”18 \nSome potential changes: \n• The Commission could try to create a Federal-state Joint Board but that seems \nlike a cumbersome approach at a time when fast action is demanded.   \n \n16 https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260630-va-scc-and-\ndata-center-coalition-letter-re-cifp-connect-manage-reliability-backstop-procurement.pdf \n17 “The OMS Committee has the opportunity to provide input into the transmission planning, resource adequacy, \nand transmission cost allocation approach and processes, and may report periodically to MISO’s Board.” Agreement \nOf Transmission Facilities Owners To Organize The Midcontinent Independent System Operator, Inc., A Delaware \nNon-Stock Corporation, available at https://cdn.misoenergy.org/MISO%20TOA%20(for%20posting)47071.pdf   \nAppendix F Section 6.3. \n18 Regional Transmission Organizations And The Coordination Of Regional Electricity Markets: A Review Of FERC \nOrder 2000, Costello and Burns (2000) https://pubs.naruc.org/pub/FA860A98-9F87-51CE-66CB-99061504D141 , \np.45"},{"page":9,"startToken":3451,"endToken":3852,"text":"LS Power Comments \nPage 9 \n \nSome recommendations: \n• Expand OPSI to include representatives of the governors.  PJM finds itself in \na relatively new circumstance: some governors are concerned that their state \nutility commissions cannot fully represent their states’ interests. In response, \nan additional option would be to supplement OPSI by changing the OPSI \ncomposition to include two members from each state: a representative from \nthe state’s utility commission and a representative nominated by the governor, \nwhich could be another commissioner but would not need to be.    This would \naddress governors’ concerns that they are not being fully represented by \nallowing governors to appoint their own representative to participate on the \ncommittee.   LS Power supports enhancing OPSI to bring the politics and \npolicy needs into discussions at the stakeholder level, rather than those needs \nbeing proffered in a manner that appears to be political pressure when the \nstakeholder process is complete.  OPSI would continue under its structure in \nterms of voting rules, etc.   \n• The stakeholder process would benefit by enhancing the capability of all state \nrepresentatives to more meaningfully participate in the stakeholder process.  \nMembers would provide additional funding to ensure OPSI’s staff include \nexperts on electricity design who can participate in technical discussions.19  \nStaffing an enhanced OPSI enables stakeholders to engage in substantive \ndialogue — at a minimum reaching mutual understanding of each other’s \npositions, and at best arrive at solutions that meet our shared objectives. OPSI \nwould continue to have its rights to meet with the PJM Board, attend \nstakeholder meetings and bring proposals forward when supported by some \nthreshold level of the committee (to be determined). This gives OPSI the \nopportunity to be even better positioned to provide the states’ views and \nmeaningfully contribute to influencing how Members consider issues and the \nissues that are considered. \n• Enable OPSI to vote on cost allocation for new transmission (whether rebuild \nor regional).  There is precedent from SPP to consider, and LS Power would \nsupport a stronger OPSI, with Section 205 powers for transmission cost \n \n19 LS Power considered the option of a NESCOE type organization as is used in New England, but determined there \nis no need to create yet another organization that would require separate funding, delineation of responsibilities and \nobligations between such a new organization and OPSI.  Rather, the simplest and most efficient approach is to \nenable governors to achieve direct participation in the stakeholder process is to enhance OPSI."},{"page":10,"startToken":3852,"endToken":4251,"text":"LS Power Comments \nPage 10 \n \nallocation proposals similar to the SPP Regional State Committee.20  Any such \nauthority should be subject to some threshold level of consent.   \n• Expand the Nominating Committee to include the president of OPSI to \nparticipate as a non-voting member in the deliberations.    \nV. Making the Stakeholder Process More Efficient  \nLS Power observes that the stakeholder process needs more discipline generally. LS \nPower thinks the specifics of that discipline are best left to stakeholders themselves, \nand FERC should not be distracted by delving into the details of such a process.  The \nCommission has in fact done exactly what is necessary:  issued a Show Cause Order \nunder FPA section 206 “in order to ensure that PJM’s ongoing processes generate \nreforms that are sufficiently timely and comprehensive to address the concerns we \nidentify today.”21 More direct involvement could distract the Commission from its \nprimary role as an economic regulator and create unnecessary ex parte concerns, \nactually limiting the ability to informally discuss proposed changes with the \nCommission.  The Members have imposed such discipline before — the creation of \nthe CIFP process is a good example22 — and can do it again. In fact, the focus of the \nPJM Liaison Committee meeting on July 13, 2026, was PJM governance.23 \nThere are guidelines to impose more discipline worth considering: \n• Limiting the number of educational sessions. Educational sessions should \ncontinue to be taped so that no one can claim they were unable to attend. (PJM \ndoes not currently record meetings, and we support continuing that approach \nfor non-educational meetings).  \n• At the MRC and Members Committee, attendees should arrive empowered to \nmake final decision votes, including the ability to vote even if a proposal is \namended on the floor — every time a representative must “go back” to their \norganization, that adds a month of delay to the process.  \n \n20 https://www.ferc.gov/introductory-guide-participation-southwest-power-pool-processes:  LS Power notes that \nSPP is comprised of vertically integrated utilities so comparisons are limited. \n21 Order Instituting Proceeding Under Section 206 of the Federal Power Act, 195 FERC ¶61,211 (issued June 18, \n2026) ¶31.   The OA language cited in footnote 1 (Section 1.5.3 of the PJM Operating Agreement) could be used as \nthe basis for the Show Cause order. \n22 PJM Manual 34: PJM Stakeholder Process, Section 8.6.4. \n23 https://www.pjm.com/-/media/DotCom/committees-groups/committees/lc/2026/20260713/20260713-agenda.pdf ."},{"page":11,"startToken":4251,"endToken":4632,"text":"LS Power Comments \nPage 11 \n \n• Proposals should be broken down into their individual components on which \nMembers can vote; PJM should then address the “workability” of the \ncomponents or any proposal based on them. \nWe also suggest stakeholders consider the following questions that are offered for \nfurther discussion rather than as settled recommendations:  \n• Consideration of a more explicit acknowledgement of a “jump ball” structure \nthat exists in ISO-NE24 and which is implicitly available in the Operating \nAgreement.  The backbones for such an approach already exist, while not \nchanging the current clear authority of the Members Committee:   “Nothing \nherein shall be construed as affecting in any way the right of the Members, \nacting pursuant to a vote of the Members Committee as specified in Operating \nAgreement, section 8.4, unilaterally to make an application to FERC for a \nchange in any rate, charge, classification, tariff or service, or any rule or \nregulation related thereto, under section 205 of the Federal Power Act and \npursuant to the rules and regulations promulgated by FERC thereunder, \nsubject to the right of any Member that voted against such change in any rate, \ncharge, classification, tariff or service, or any rule or regulation related \nthereto, in intervene in opposition to any such application.”25 \nIn making this right more explicit, the Members Committee of PJM would \nhave its own legal counsel, just like NEPOOL within the New England \nstakeholder process. This would help ensure that the PJM Members and PJM \nTransmission Owners, with separate 205 filing rights over some issues, are \noperating within their own appropriate roles and better help resolve \nstakeholder conflicts.   It would also ensure an independent legal review for \nthe Operating Agreement language filed at FERC, proper Members \nCommittee consultation of PJM Transmission Owner 205 Filings as required \nunder the PJM Operating Agreement today, and monitoring timing of \nstakeholder process. The counsel could provide an important check on any \nunruly Members. \n• Should voting at lower-level committees shift from affiliate-level voting to a \nsingle representative vote as is done at the senior committees? At minimum, \nwe recommend that two votes be taken at lower committee meetings.  These \nvotes are intended to help advance proposals to higher level committees, but \n \n24 NEPOOL Participants Agreement, Section 11.1.5.  \n25 PJM Operating Agreement, Section 11.5(b)"},{"page":12,"startToken":4632,"endToken":4985,"text":"LS Power Comments \nPage 12 \n \nthey also provide information with respect to likely support at higher level \ncommittees.  They can also inform the Board. \nV.  What the Commission Can Do \nLS Power commends the Commission for its proactive efforts and orders to ensure \nthat each region of the country can meet the changing electricity demands.  That \nsaid, LS Power believes that it is not just a cumbersome governance problem that \nhas caused PJM to struggle to meet these demands, but a confluence of a number of \nchallenges, including the need to revise retail tariffs, to better manage \ninterconnection and transmission upgrades, to expedite supply chains, and the need \nto have forcing mechanisms that enable bilateral contracts between hyperscalers and \nnew generation in order to obtain financing.  None of these challenges are unique to \na competitive market such as PJM.  Vertically integrated utilities cannot bypass the \nphysical realities of the current grid and supply chains, and moreover, their business \nmodel shifts the risk of cost and over-procurement back to ratepayers.  This reality \nshould not, however, impede the ability to make enhancements to PJM’s governing \nprocess, as we have suggested here. \nThe Commission also has a critical role to play: it must act under its statutory \nauthority as an economic regulator.  It, too, is an independent organization staffed \nby industry experts.26 This expertise enables the Commission to be the ultimate \nbackstop in allowing the Board and PJM to make politically unpopular decisions in \norder to carry out their mission of ensuring reliability through competitive markets.   \n \n \n \n26 “Further, it has been suggested that FERC has perhaps been too deferential to proposals coming from the RTOs \nand may not give sufficient weight to minority stakeholder concerns or market monitor comments when it assesses \ncontested filings. Interviewees suggested that instead, FERC should approach RTO proposals with sufficient \nscrutiny and not overly rely on RTO independence, particularly because RTOs themselves may be in pursuit of \nmultiple goals, including state policy targets that conflict with market efficiency.”  How the RTO Stakeholder \nProcess Affects Market Efficiency, James, Jones, Kricke & Greane, R Street Policy Study No. 112 (October 2017), \np. 18."},{"page":13,"startToken":4985,"endToken":5106,"text":"LS Power Comments \nPage 13 \n \nIn our comments, LS Power has endeavored to identify areas in the PJM’s \ngovernance structure that could be improved and provide specific recommendations \nthat can be implemented without disrupting the need to focus all our attention on \nhow we get new resources online as quickly as possible.  We look forward to \nworking with the Commission and all interested parties to take advantage of the \ntremendous opportunities afforded us all to meet the energy demands of today and \ntomorrow.   \nRespectfully submitted,  \n \n/s/ Marjorie R. Philips  \nMarjorie Rosenbluth Philips  \nSenior Vice President, Wholesale Market \nPolicy  \n1700 Broadway, 35th floor  \nNew York, NY 10019  \nOn Behalf of LS Power Development, LLC \n610-401-3612 \nmphilips@lspower.com \nDated: July 14, 2026"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":294,"startToken":0,"endToken":28},{"p":1,"at":294,"title":"I. Introduction","method":"printed heading","endPage":3,"endAt":625,"startToken":28,"endToken":807},{"p":3,"at":625,"title":"II. The Board and PJM’s Jurisdictional Authority","method":"printed heading","endPage":4,"endAt":1545,"startToken":807,"endToken":1458},{"p":4,"at":1545,"title":"III. Board Independence","method":"printed heading","endPage":7,"endAt":252,"startToken":1458,"endToken":2651},{"p":7,"at":252,"title":"IV. Enhancing State Participation in the Stakeholder Process","method":"printed heading","endPage":10,"endAt":308,"startToken":2651,"endToken":3898},{"p":10,"at":308,"title":"V. Making the Stakeholder Process More Efficient","method":"printed heading","endPage":12,"endAt":154,"startToken":3898,"endToken":4656},{"p":12,"at":154,"title":"V. What the Commission Can Do","method":"printed heading","endPage":13,"endAt":800,"startToken":4656,"endToken":5106}]}