{"document":{"slug":"rec-20260716-4001","title":"Pre-filed Statement of Mason Emnett, Senior Vice President for Public Policy for Constellation Energy Generation, LLC, for the PJM Governance and…","issued":"2026-07-16","accession":"20260716-4001","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"CONSTELLATION ENERGY GENERATION, LLC","kind":"testimony","file":"sources/filings/text/20260716-4001_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260716-4001","tier":"record","sha256":"d34367bddc12d45c13dbbb0318541f31245203d50e356785423d4e09fbe9c291","pages":18,"tokens":5845,"emptyPages":[],"textThemes":["adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":323,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n) \n \nPJM Governance and Stakeholder Reforms \n) \n) \nDocket No. AD26-7-000 \n \n \n \n \nPRE-CONFERENCE STATEMENT OF MASON EMNETT \nON BEHALF OF CONSTELLATION ENERGY GENERATION, LLC \n \n \nPursuant to the Commission’s July 2, 2026 notice in the above-captioned proceeding,1 and \non behalf of Constellation Energy Generation, LLC (Constellation), Mason Emnett submits this \npre-conference statement addressing potential PJM Interconnection, L.L.C. (PJM) stakeholder and \ngovernance reforms in advance of the Commissioner-led technical conference to be held on \nJuly 23, 2026.  \nI. \nCOMMENTS \nPolicymakers and stakeholders have been discussing potential improvements to PJM’s \nstakeholder process and governance structure for years.2  The intensity of this debate has ebbed \nand flowed over time but appears to be reaching a high point, with particular focus on how states \ncan more effectively participate in PJM’s decision-making and whether PJM is organizationally \n \n1 PJM Governance and Stakeholder Reforms, Second Supplemental Notice of Commission-Led Technical \nConference, Docket No. AD26-7-000 (July 2, 2026).  \n2 See, e.g., Members Committee, Stakeholder Process Super Forum, PJM Interconnection, L.L.C. (Aug. 22, 2019), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/committees/mc/20190926/20190926-item-01-\nstakeholder-process-super-forum-presentation.ashx (a concentrated effort to make adjustments to the stakeholder \nprocess to help address prioritization and transparency); Stakeholder Process Forum, PJM Interconnection, L.L.C., \nhttps://www.pjm.com/committees-and-groups/forums/stakeholder-process-forum (PJM has a regular, monthly \n“check-in” to address issues that come up in the stakeholder process, the Stakeholder Process Forum, where all \nstakeholders, including representatives of state commissions and agencies, are welcome to participate); Open Letter \nto the PJM Board of Managers from Nine Governors re: Board Vacancies (July 16, 2025), https://www.pjm.com/-\n/media/DotCom/about-pjm/who-we-are/public-disclosures/2025/20250717-nine-governors-letter-regarding-board-\nvacancies.pdf; ICYMI: In Philadelphia, Governor Shapiro Convenes Historic PJM Summit to Push for Reform, \nLower Energy Costs, and Protect Grid Reliability, Commonwealth of Pennsylvania (Sept. 23, 2025), \nhttps://www.pa.gov/governor/newsroom/2025-press-releases/icymi--in-philadelphia--governor-shapiro-convenes-\nhistoric-pjm-s."},{"page":2,"startToken":323,"endToken":699,"text":"2 \n \ncapable of quickly responding to emerging resource adequacy challenges.  In response, the \nCommission initiated this proceeding to “focus on identifying and evaluating actionable reforms \nto improve PJM’s ability to address system needs in a timely and efficient manner.”3  An effective \nstakeholder process is critical in PJM and, as elaborated below, changes can and should be made \nto ensure transparency and an opportunity for all voices to be heard.  However, these or any other \nchanges considered must preserve PJM’s independence as a regional transmission organization \n(RTO) and maintain consistency with the Federal Power Act (FPA).   \nIt is also critical that the Commission, PJM, the states, and stakeholders identify with \nprecision the problems (from their respective perspective) that need to be solved so that we can \ncollectively debate solutions that actually address each issue.  For example, some suggest that \nPJM’s lack of section 205 filing rights results in gridlock when PJM’s Members cannot find \nconsensus on a complicated issue.  Yet most of the unrest in PJM over the last decade has involved \nissues related to resource adequacy, generator retirements and replacements, and capacity market \nrules changes—matters over which PJM already has section 205 filing rights and is able to take \naction under section 205 even when the Membership disagrees.  When PJM has delayed action, it \nhas been because its leadership has decided not to proceed, not because of any lack of authority.  \nIn the same vein, PJM’s lack of section 205 rights over energy market issues has not deterred \nPJM’s action under section 206 when its leadership decided to proceed without Membership \nendorsement.4  PJM has sufficient authority under its existing decisional structure to take action \nwhen its leadership concludes that action is necessary.  Strong and decisive leadership by PJM, \n \n3 PJM Governance and Stakeholder Reforms, Notice of Commission-Led Technical Conference, Docket No. AD26-\n7-000 (May 12, 2026). \n4 See, e.g., Facilitating PJM Independent 205 Filing Rights Over Transmission Planning of PJM Interconnection, \nL.L.C., Docket No. EL24-119-000, at 9-11 (June 21, 2024) (filing by PJM under section 206 of the FPA); Enhanced \nPrice Formation in Reserve Markets of PJM Interconnection, L.L.C., Docket No. EL19-58-000, at 1 & n.1 (Mar. 29, \n2019) (filing by PJM under section 206 of the FPA)."},{"page":3,"startToken":699,"endToken":1065,"text":"3 \n \nwhether proceeding under section 205 or section 206, is what matters, and the Commission, states, \nand stakeholders should be focused on improvements to the stakeholder process or governance \nmechanics that reinforce (rather than undermine) PJM’s leadership.  \nA. The Role of States: Existing Participation and Additional Opportunities \nMuch of the current debate regarding the effectiveness of the PJM stakeholder process and \nrelated governance mechanics appears to be driven by concerns from some states that they do not \nhave sufficient opportunity to be heard by PJM or otherwise participate in PJM processes and \ndecision-making.  Notwithstanding these concerns, state representatives have a long history of \nactive participation in PJM’s stakeholder processes, both individually and collectively.  For \nexample, state representatives can and routinely do: \n• Submit issues charges for PJM and its Members to consider;5   \n• Participate directly in the stakeholder process, such as by submitting proposals and \nweighing in on others’ proposals6 (and, in fact, state-supported proposals have been \n \n5 See, e.g., Issue Charge, PJM Interconnection, L.L.C. (July 16, 2025), https://www.pjm.com/-\n/media/DotCom/committees-groups/committees/mrc/2025/20250723/20250723-item-05---3-revised-sub-annual-\nauction-issue-charge---clean.pdf (sub-annual issue charge brought by Governor Josh Shapiro, on behalf of the \nCommonwealth of Pennsylvania, which led to the creation of the Sub-Annual Capacity Market Senior Task Force, \nhttps://www.pjm.com/committees-and-groups/task-forces/sacmstf); Clean Attribute Procurement Senior Task Force, \nPJM Interconnection, L.L.C., https://www.pjm.com/committees-and-groups/closed-groups/capstf (this now-closed \ngroup was established by an issue charge to coordinate the PJM markets with state clean energy attributes).   \n6 See, e.g., Appendix 1, attached below (compiling written submissions by PJM state entities in two recent PJM \nCritical Issues Fast Path stakeholder processes); Letter from Maryland Delegate Lorig Charkoudian on behalf of the \nNational Caucus of Environmental Legislators (NCEL), to President Mills & the PJM Board (June 23, 2026), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-written-comments---\nmaryland-delegate-lorig-charkoudian-on-behalf-of-ncel.pdf; Agenda for Critical Issue Fast Path (CIFP) - Reliability \nBackstop Procurement (RBP) / Connect & Manage (C&M), PJM Interconnection, L.L.C., (June 30, 2026), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-agenda.pdf \n(Maryland State Senator Katie Fry Hester allotted time for comments)."},{"page":4,"startToken":1065,"endToken":1490,"text":"4 \n \nselected by PJM and its stakeholders—and accepted by the Commission—as the \npath forward7); \n• Submit letters to the PJM Board expressing their views directly to the PJM Board;8 \nand \n• Participate in state-specific task forces, user groups, and committees.9 \nStates are nevertheless expressing increasing concern that participation has been difficult \nand ineffective. To enhance the ability of states to participate consistently in PJM processes, OPSI \nhas begun expanding its capabilities so it can more effectively coordinate and represent state \ninterests.  The Commission, PJM, and its Members should support this right-sizing of OPSI \nresources to ensure that the organization is sufficiently staffed and supported (including by lawyers \nand consultants) and capable of enabling a robust and effective state/PJM relationship, particularly \nas states seek to address the resource adequacy challenges that have been the focus of recent state \nconcern. \n \n7 See 2025 Periodic Review of Variable Resource Requirement Curve Shape and Key Parameters of PJM \nInterconnection, L.L.C., Docket No. ER26-455-000, at 7-8 (Nov. 7, 2025) (describing the Joint PJM/PA Public \nUtility Commission, Vice Chair Barrow proposal that received super-majority support from stakeholders and was \nadopted by the PJM Board without modification), accepted by PJM Interconnection, L.L.C., 194 FERC ¶ 61,049, on \nreh’g, 196 FERC ¶ 61,007 (2026). \n8 In just the past year-and-a-half, the PJM states, in some capacity, have submitted over fifty letters to the PJM \nBoard on a variety of issues.  See Appendix 2, attached below.  In addition, the Organization of PJM States, Inc. \n(OPSI) can meet with the PJM Board multiple times annually. \n9 See, e.g., Independent State Agencies Committee, PJM Interconnection, L.L.C., https://www.pjm.com/committees-\nand-groups/state-commissions/isac (focused primarily on transmission matters); Affordability and Reliability for \nResidential Consumers User Group, PJM Interconnection, L.L.C., https://www.pjm.com/committees-and-\ngroups/user-groups/arrcug (includes state-appointed consumer advocates of several restructured states within the \nPJM service area); Public Interest & Environmental Organizations User Group, PJM Interconnection, L.L.C., \nhttps://www.pjm.com/committees-and-groups/user-groups/pieoug (includes representatives of Consumer Advocates, \nas well as public interest and environmental organizations, and holds an annual meeting with the PJM Board); Clean \nAttribute Procurement Senior Task Force, PJM Interconnection, L.L.C., https://www.pjm.com/committees-and-\ngroups/closed-groups/capstf (this now-closed group was set up to “coordinate a comprehensive discussion” between \nOPSI, PJM stakeholders, and staff “around enhancements to enable states and other willing buyers to procure clean \nresource attributes, on a voluntary basis, through a regional and centralized procurement or market.”)."},{"page":5,"startToken":1490,"endToken":1826,"text":"5 \n \nPJM also could facilitate more effective engagement by the states by being explicit \nregarding the input that it seeks from states and the forum(s) in which that input is to be provided.  \nWhether accurate or not, there is a general perception that PJM leadership does not take input from \nthe states seriously.  PJM can correct that perception by identifying in a structured way the specific \ninput that it desires from states, where and when that input is to be provided, and then \ncommunicating back to the states how that information was considered by PJM to reach decisions.  \nConstellation recommends that PJM do this for the following topics at a minimum: \n• Proposed changes to market rules and planning processes; \n• Jurisdictional authority of PJM relative to the states; \n• Load forecasting, including obtaining input from state retail regulatory authorities \non what large load requests are sufficiently real to be included in PJM’s capacity \nprocurement and transmission planning; \n• Resource adequacy preferences, including whether the state intends to rely on PJM \nmarkets for capacity procurement or to establish its own planning and procurement \nmechanism(s) and whether the state prefers certain capacity types and, if so, how \nthose resources should be procured;10 and \n• Views on the relative importance of rule or process changes so PJM can factor that \ninto its workload prioritization.  \n \n10 See Transcript of Technical Video Conference at 225, Technical Conference Regarding Resource Adequacy in the \nEvolving Electricity Sector, Docket No. AD21-10-000 (Mar. 23, 2021) (Jason Stanek, Chairman, Maryland Public \nService Commission: “So [FRR] would allow us to reclaim resource adequacy. But at the same time we’ve been \nrelatively content in the capacity markets up until the Calpine decision, and we’d like to stay if possible.”); \nTranscript of Technical Conference at 179-247 (Panel 3), Meeting the Challenge of Resource Adequacy in Regional \nTransmission Organization and Independent System Operator Regions, Docket No. AD25-7-000 (June 4, 2025), \n(roundtable discussion with state public utility commissioners and other state representatives about the role of states \nin resource adequacy in PJM)."},{"page":6,"startToken":1826,"endToken":2089,"text":"6 \n \nThis increased collaboration also should go both ways.  There are a number of market and \nresource adequacy-related matters governed by state laws and regulations that are impacted by \nPJM decisions or otherwise interact with the wholesale markets and planning functions overseen \nby PJM.  PJM should work with the states to identify the areas of support they need to fulfill their \nown duties.  This could include matters ranging from the siting and permitting of transmission, \ngeneration, and gas pipeline infrastructure necessary to bring PJM-planned resources online, to \nopportunities to increase the use of bilateral contracting and hedging structures to protect \nconsumers from wholesale market volatility.   \nAs noted above, effective coordination with the states will require both PJM and the states \nto be specific as to the information or input to be provided and the forum(s) in which that \ninformation and input is to be provided.  To ensure that OPSI can provide meaningful and \ncoordinated support to the states in meeting those expectations, PJM should: \n• Establish protocols and schedules for meeting regularly with state commissions and \ntheir staff, both individually and collectively, to seek input regarding important \nmarket and transmission issues, rule changes, and other areas of concern, including \nboth staff-to-staff and leadership-to-leadership meetings;  \n• Establish a process for states, both individually and collectively, to request and \nreceive technical information and support on matters related to wholesale markets \nand/or infrastructure planning and their interactions with state regulation and retail \nrates; and \n• Develop (with Commission and state guidance) options for additional hedging \ntools, such as a state purchasing authority (or buyers’ cooperative), to facilitate"},{"page":7,"startToken":2089,"endToken":2469,"text":"7 \n \nbilateral contracting11 and manage consumer risks associated with wholesale price \nvolatility.12 \nFinally, PJM also should discuss with OPSI and the PJM Governors Collaborative whether \nthey desire to establish an organization, either separate from or integrated with OPSI, to facilitate \nparticipation by state elected officials in PJM processes.  Elected officials do not currently have a \nforum similar to OPSI to support their engagement in PJM matters and may lack the technical \nresources needed to engage effectively.  Additional funding for such an organization, whether \nseparate from or integrated with OPSI, could be provided through the PJM Tariff to ensure \nsufficient staffing and support (including by lawyers and consultants).  This could be accomplished \nthrough an amendment to Schedule 9 of the PJM Tariff, which already provides funding for both \nOPSI as well as the Consumer Advocates of PJM States, Inc. (CAPS). \nB. The Commission’s Role: Ensuring PJM Processes Are Effective \nIn situations where the Commission desires to see prompt action on a particular matter, or \nthe Commission is concerned that a lack of stakeholder consensus is leading to inaction by PJM, \nthe Commission can spur action by using its convening authority, both informal and formal.  For \nexample, the Commission could hold conferences/workshops on enhancing bilateral transactions \nor other steps that PJM could take in coordination with states to protect consumers from price \nvolatility in the wholesale market.  Despite the best efforts of PJM and its stakeholders, \n \n11 Bilateral contracting is generally beneficial as it supports competitive investment to meet resource adequacy goals \nand provides risk mitigation for supply and demand-side market participants. See Meeting the Challenge of Resource \nAdequacy in Regional Transmission Organization and Independent System Operator Regions, Post-Technical \nConference Comments of Constellation Energy Generation, LLC, Docket No. AD25-7-000, at 5-9 (July 7, 2025).  \n12 In its recent whitepaper on the future of its markets, PJM stressed the importance of bilateral contracting for retail \nratepayer loads through their Load Serving Entities (LSEs) and Electric Distribution Companies (EDCs).  PJM \nsuggested this could be done either through an individual LSE hedging requirement or through a PJM-administered, \nlong-term procurement, such as a tiered, multi-year capacity market.  See Powering Reliability Through Market \nDesign, PJM Interconnection, L.L.C. (May 6, 2026), https://www.pjm.com/-/media/DotCom/library/reports-\nnotices/special-reports/2026/20260506-powering-reliability-through-market-design.pdf."},{"page":8,"startToken":2469,"endToken":2820,"text":"8 \n \ncomplicated matters sometimes cannot be resolved and formal proceedings are initiated at the \nCommission.  In addition to working through these disputes itself, based on the record submitted \nby the parties (as it typically does), the Commission should be more expansive in its use of \nsettlement proceedings, providing guidance as to what it would find (un)acceptable, imposing tight \ndeadlines on discussions (which can motivate parties to compromise), and encouraging settlement \njudges to actively engage in the process and discussions.13  This has worked well in the past.  The \noriginal Reliability Pricing Model mechanism was developed as part of a Commission settlement \nprocess that was initiated and shaped by a prior Commission “guidance” order.14  Cost allocation \nissues in the wake of the GreenHat default also were resolved by settlement,15 and numerous PJM-\nrelated complaints filed in the wake of Winter Storm Elliott were resolved through a Commission-\nordered expedited settlement process.16 \nThe Commission also should consider more frequent use of designating non-decisional \nCommission staff on contentious policy matters.  Non-decisional Commission staff can help PJM, \nthe states and stakeholders to better understand Commission policy guidance and increase the \nlikelihood that the resolution of conflicts or rule changes are ultimately found by the Commission \nto be just and reasonable.  For instance, non-decisional staff played a key role in supporting PJM \nstakeholders when responding to Commission directed changes to PJM’s capacity market (i.e., \nMinimum Offer Price Rule).17  \n \n13 A Commission Policy Statement could lay out how the Commission will make use of such mechanism, including if \nrequested by the parties. \n14 See PJM Interconnection, L.L.C., 115 FERC ¶ 61,079, at P 176 (2006) (Initial Order on Reliability Pricing \nModel).   \n15 See PJM Interconnection, L.L.C., 167 FERC ¶ 61,209, at PP 28-29 (2019). \n16 See Essential Power OPP, LLC, 183 FERC ¶ 61,163, at P 17 (2023). \n17 See Calpine Corp. v. PJM Interconnection, L.L.C., Notice of Designation of Commission Staff as Non-Decisional, \nDocket Nos. EL16-49-000, et al. (July 17, 2018); Calpine Corp. v. PJM Interconnection, L.L.C., 163 FERC ¶ 61,236 \n(2018)."},{"page":9,"startToken":2820,"endToken":3207,"text":"9 \n \nC. PJM’s Role: Using its Stakeholder Processes and Governance Mechanisms to \nAddress System Needs in a Timely and Efficient Manner \nIn Constellation’s experience, many of the complaints about PJM’s stakeholder process \nand its governance mechanisms are, in actuality, disagreements with PJM about its decisions to \ntake, defer, or decline a particular action combined with a perception that competing views have \nnot been adequately considered.  The Commission’s goal cannot be for PJM to always agree or \ntake unwavering direction from a particular entity or group of entities.  That would be inconsistent \nwith the core independence principle of Order No. 2000, which the Commission enforces in order \nto ensure that each RTO has “a decisionmaking process that is independent of control by any \nmarket participant or class of participants.”18  The same is true of states, which should participate \nextensively in RTO processes and, as discussed above, have the resources and organizational \nstructures to do so.  While improvements are needed in PJM to ensure that the views of states (as \nwell as other stakeholders) are fully considered, it does not follow that states need or should be \ngiven filing rights under section 205 of the FPA or decisional control over PJM leadership.   \n1. PJM Leadership Matters Most \nWhether an issue is raised for consideration by a stakeholder or PJM, PJM sets the agenda \nfor its standing committees and task forces, where most of the substantive work is done.  It is \nPJM’s responsibility, then, to use its stakeholder process to drive to decisions instead of delay. \nStakeholders look to PJM to determine when an issue has been fully vetted, opportunities for \ncollaboration or compromise have been exhausted, and it is time for PJM or stakeholders to move \n \n18 Regional Transmission Organizations, Order No. 2000, 89 FERC ¶ 61,285, at slip op. 194 (1999), order on reh’g, \nOrder No. 2000-A, 90 FERC ¶ 61,201 (2000), petitions for review dismissed sub nom. Pub. Util. Dist. No. 1 v. \nFERC, 272 F.3d 607 (D.C. Cir. 2001); see Duquesne Light Co., 189 FERC ¶ 61,181, at PP 24-25, 43-47 (2024), \norder on reh’g, 192 FERC ¶ 61,051, at PP 36-40 (2025) (Commission reiterating the importance of PJM \nindependence), aff’d sub nom. PJM Transmission Owners v. FERC, Nos. 25-1064, 25-1100, 2026 U.S. App. LEXIS \n16255 (D.C. Cir. June 5, 2026)."},{"page":10,"startToken":3207,"endToken":3550,"text":"10 \n \nforward with a decision.  Undoubtedly, PJM has a difficult job balancing competing interests with \nrespect to prioritization, timing, information, transparency, and direction, and there will always be \nstakeholders who would like additional time to discuss an issue or additional information before \nmaking a decision, sometimes with the intent of delaying a resolution of an issue rather than \nreaching consensus.  PJM’s leadership can reduce gridlock by making decisions on a timely basis, \ncommunicating its decisions clearly, explaining its views of alternative positions, and sticking with \nits decisions through execution and over time.   \nWhen PJM strikes the balance right, working collaboratively with stakeholders, it can \nsuccessfully and timely address some of the system’s most pressing needs.  For example, the \nInterconnection Process Reform Task Force was able, in the span of roughly one year, to develop \nboth significant reforms to the PJM interconnection process and a transition mechanism to address \nthe backlog of existing interconnection requests.  Guided by clear goals and timeframes from PJM, \nstakeholders were able to consider a range of PJM and stakeholder proposed solutions, agree on a \npackage of reforms, and file that package at the Commission.19  This is how the stakeholder process \nshould work. \nWithout clear guidance from PJM, the stakeholder process can instead flounder. For \nexample, the Reserve Certainty Senior Task Force began its work in 2023 with a dauntingly long \nproject plan timeline, has had numerous restarts as PJM has revised its deliverables, has failed to \nfile one set of reforms that PJM deemed necessary, and is stumbling toward the finish line where \nit is unclear that any proposal will receive sector-weighted majority support.  Even initiatives \ndesigned to be accelerated can, without PJM leadership, fail to meet their intended goals.  Such \n \n19 See Tariff Revisions for Interconnection Process Reform of PJM Interconnection, L.L.C., Docket No. ER22-2110-\n000, at 2, 13 (June 14, 2022), accepted by PJM Interconnection, L.L.C., 181 FERC ¶ 61,162 (2022), order on reh’g, \n184 FERC ¶ 61,006 (2023), aff’d sub nom. Hecate Energy LLC v. FERC, 126 F.4th 660 (2025)."},{"page":11,"startToken":3550,"endToken":3852,"text":"11 \n \nwas the case with last year’s Critical Issue Fast Path (CIFP)-Large Load Addition stakeholder \nprocess which, after months of deliberation, led to a second CIFP process instead of a decision on \nissues that had been vetted fully. \n2. Who Has Section 205 Filing Rights Is a Red Herring \nSome nevertheless argue that PJM’s section 205 rights should be expanded, pointing to a \nlack of Member endorsement leading to gridlock.  As discussed above, PJM already has section \n205 filing rights over resource adequacy, generator retirements and replacements, and capacity \nmarket rule changes which have been the most contentious issues in PJM particularly for the states.  \nDissatisfaction over PJM’s actions and inactions on these issues has more to do with how PJM is \naddressing (or not) feedback received than who has the right to propose a rule change under \nsection 205.  And while it is true that PJM needs Member endorsement to file an energy market \nrule change under section 205, the lack of stakeholder approval has not stopped PJM in the past \nfrom proceeding with filings under section 206 when its leadership concluded that a change was \nnecessary despite stakeholders not reaching the consensus necessary for PJM to file under section \n205.20 \nOthers argue that states should be given section 205 filing rights, but that would be \ninconsistent with the very structure of the Federal Power Act.  Utilities providing jurisdictional \nservice have filing rights, and the Commission reviews proposed changes to ensure they are just \nand reasonable.  The same is true for state regulation of utilities.  If either the Commission or a \nstate commission desires to change a tariff or market rule, it can initiate its own proceeding to \ninvestigate if that change is needed.  It would be unreasonable to give states more authority over \n \n20 See supra note 4."},{"page":12,"startToken":3852,"endToken":4262,"text":"12 \n \nfilings made by Commission-jurisdictional RTOs than the Commission itself has, or more than \nstates have over their own utilities.21   \nIf the Commission nonetheless believes that something has changed that now renders \nPJM’s existing filing rights over market rules unjust, unreasonable and unduly preferential, then it \nis generators who should receive additional authority to expedite section 205 filings proposing \nchanges to those rules.  Generators are the only entities providing capacity, energy, and related \njurisdictional services under the FPA.  To the extent generators ceded any of their rights under \nsection 205 in agreeing to participate in PJM, they cannot be forced to further cede those rights \nthrough other changes to the filing rights structure in PJM.22   \n3. Board Member Selection Must Remain Independent \nFinally, it is essential that PJM’s Board member selection process remain independent of \nundue influence from any particular interest.23  PJM’s existing selection process is consistent with \nCommission precedent and welcomes input, including potential nominees, from all interested \nparties.24  This is a healthy process that is fair to all Members and is consistent with approaches \nused in other regions.  \n \n21 Some incorrectly point to “jump ball” rights in New England as an example of states having section 205 filing \nrights.  In reality, those “jump ball” rights are held by the New England Power Pool, which is an association of \nrepresentatives from six sectors of the electricity industry: generators, suppliers, transmission owners or utilities, end \nusers, publicly owned entities, and alternative resources. See Corporate Governance, ISO New England Inc., \nhttps://www.iso-ne.com/about/corporate-governance. In MISO and SPP, states have limited rights to require or \notherwise request the RTO to submit section 205 filings addressing resource adequacy and transmission cost \nallocation.  That authority is tailored to the particular regulatory structures of those regions, which are dominated by \nvertically integrated utilities with states engaging regularly in integrated resource planning. \n22 With respect to substantive capacity market matters, PJM only has authority to make filings under section 205 to \nthe extent such authority has been contracted to it.  But as noted, PJM cannot force those providing jurisdictional \nservices to provide PJM with even more of their section 205 rights. \n23 See supra note 19. \n24 PJM Nominating Committee offers the opportunity for any interested person to submit candidates directly to an \nindependent consultant (currently, Korn Ferry International).  See Nominating Committee, PJM Interconnection, \nL.L.C., https://www.pjm.com/committees-and-groups/committees/nc; Operating Agreement §§ 7.1-7.2."},{"page":13,"startToken":4262,"endToken":4536,"text":"13 \n \nSome states in PJM have requested a more formal role in Board member selections.  Giving \nany group, whether states or anyone else, an outsized role in Board member selection could \nundermine the independence of the Board and PJM as an organization.  Instead, states can and \nshould make their views known about potential Board members by taking advantage of existing \nopportunities to engage.  This could include coordinating efforts by developing a list of suggested \nnominees, perhaps through OPSI or through the formation of nomination advisory group \nconsisting of state-designated representatives.   \nRelatedly, it is important that the Board is immune from political pressure and has all the \ninformation it needs in making decisions.  To ensure Board independence is maintained, PJM \nstakeholders and the Commission should evaluate whether Board terms should be lengthened, and \nwhether substantive criteria should be adopted for removing Board members, to promote well-\ninformed Board decisions that are immune from political influence.  In addition, to support the \nBoard’s consideration of complicated policy decisions, the Board should be given access to input \nfrom third-party market experts when complex technical matters are being considered.25 \nII. \nCONCLUSION \nThank you for the opportunity to address the Commission regarding potential PJM \ngovernance reforms.  Constellation looks forward to working with the Commission, PJM, its \nstakeholders, and that states as we evaluate and implement improvements to existing processes to \nmake participation more effective while supporting PJM’s leadership and independence.   \n \nJuly 14, 2026 \n \n25 Improvements could also include returning the Liaison Committee meetings to being entirely in-person and \nseparate from the Annual Meeting and/or adding networking receptions at each Board meeting where there isn’t a \nLiaison Committee meeting."},{"page":14,"startToken":4536,"endToken":4700,"text":"APPENDIX 1 \nState Entity Involvement in a Sampling of Recent CIFP Proceedings \n \nCritical Issue Fast Path - Reliability Backstop Procurement / Connect & Manage \n \n1 \nWritten Comments - Delaware Public Service Commission    \n7.2.2026 \n2 \nWritten Comments - VA SCC and Data Center Coalition   \n6.30.2026 \n3 \nWritten Comments - West Virginia Public Service Commission \n6.30.2026 \n4 \nWritten Comments - Virginia Chief Energy Officer  \n6.30.2026 \n5 \nWritten Comments - DC DOEE    \n6.30.2026 \n6 \nWritten Comments - PJM Governors Collaborative   \n6.25.2026 \n7 \nWritten Comments - Maryland Delegate Lorig Charkoudian on behalf of \nNCEL \n6.23.2026 \n8 \nItem 02C - Joint Consumer Advocates - C&M and RBP - Executive Summary \n6.23.2026 \n9 \nItem 03I - Joint Consumer Advocates Presentation   \n6.5.2026 \n11 \nItem 02K - Joint Consumer Advocates Presentation    \n5.1.2026 \n12 \nOPSI Reliability Backstop Procurement Feedback  \n4.27.2026 \n \nCritical Issue Fast Path - Reliability Backstop Procurement / Connect & Manage, PJM \nInterconnection, L.L.C., https://www.pjm.com/committees-and-groups/cifp-rbp (last visited July \n13, 2026)."},{"page":15,"startToken":4700,"endToken":4929,"text":"2 \n \nCritical Issue Fast Path - Large Load Additions \n \n1 \nItem 02E - PJM Legislators and NRDC Package - Executive Summary \n11.18.2025 \n2 \nItem 02F - Joint Consumer Advocates Package - Executive Summary  \n11.17.2025 \n3 \nItem 02D - Data Center Coalition Governors Exelon and PPL Package \n- Executive Summary \n11.14.2025 \n4 \nItem 03A - Pennsylvania OCA Proposal  \n11.7.2025 \n5 \nItem 03B - State Legislators Collaborative Proposal - Updated  \n11.7.2025 \n6 \nItem 04H - Joint DCC Governors and Exelon Proposal - Updated  \n11.6.2025 \n7 \nItem 04H - Joint DCC and Governors Proposal \n11.3.2025 \n8 \nItem 04D - Maryland OPC Proposal  \n11.3.2025 \n9 \nItem 03B - State Legislators Collaborative Proposal  \n11.3.2025 \n10 \nItem 03H - Maryland Office of Peoples Counsel Proposed Options \n10.13.2025 \n11 \nPA, NJ, MD, & IL Governors Letter  \n8.29.2025 \n12 \nPennsylvania Office of Consumer Advocate Comments \n8.29.2025 \n13 \nDelaware Public Service Commission Comments \n8.29.2025 \n14 \nNew Jersey Division of Rate Counsel Comments \n8.29.2025 \n15 \nMaryland Office of People’s Counsel Comments \n8.29.2025 \n16 \nIllinois Office of the Attorney General Comments  \n8.29.2025 \n17 \nPennsylvania Public Utility Commission Comments \n8.29.2025 \n18 \nDelaware Division of the Public Advocate Comments \n8.29.2025 \n \nCritical Issue Fast Path - Large Load Additions, PJM Interconnection, L.L.C., \nhttps://www.pjm.com/committees-and-groups/cifp-lla (last visited July 13, 2026)."},{"page":16,"startToken":4929,"endToken":5222,"text":"APPENDIX 2 \nState Entities Letters to the PJM Board from 2025 and 2026 \n \n \n2026 \nDate \n1 \nPublic Utilities Commission of Ohio Letter Regarding CIFP Stage 4 \nConnect and Manage PDF \n7.8.2026 \n2 \nVA SCC and Data Center Coalition Letter Regarding CIFP – Connect \n& Manage / Reliability Backstop Procurement PDF \n6.30.2026 \n3 \nWV PSC Letter Regarding Connect & Manage Proposal PDF \n6.30.2026 \n4 \nDC Department of Energy and Environment Letter Regarding PJM’s \nCIFP-C&M / RBP Proposal PDF \n6.25.2026 \n5 \nPJM ICC, PA OCA, IL CUB Letter Regarding Positioning States for \nSuccess in Retail Cost Allocation  PDF \n6.23.2026 \n6 \nVirginia Chamber of Commerce Letter Regarding Valley Link \nProject PDF \n6.19.2026 \n7 \nPJM Legislators’ Collaborative Letter Regarding Reliability Backstop \nProcurement and Connect & Manage Proposals PDF \n6.15.2026 \n8 \nPA State Senator Yaw Letter Regarding PJM’s Powering Reliability \nThrough Market Design Paper PDF \n5.26.2026 \n9 \nPJM Governors’ Collaborative Letter Regarding Reliability Backstop \nProcurement Objectives PDF \n4.14.2026 \n10 \nWV State Senator Rose Letter Regarding Reliability Backstop \nProcurement PDF \n4.14.2026 \n11 \nWV Delegate Bell Letter Regarding Reliability Backstop \nProcurement PDF \n4.7.2026 \n12 \nNJBPU Letter Regarding Connect and Manage Issue Charge PDF \n4.1.2026 \n13 \nIN Governor Letter Regarding Fixed Resource Requirement PDF \n3.20.2026 \n14 \nPJM State Legislators Collaborative Letter Regarding Reliability \nBackstop Procurement PDF \n3.19.2026 \n15 \nKY Governor Letter Regarding PJM Governance and Fixed Resource \nRequirement PDF \n3.17.2026 \n16 \nOH Governor Letter Regarding Ensuring an Abundant, Affordable, \nand Reliable Energy Supply PDF \n2.18.2026 \n17 \nIL, NJ Governors’ Letter Regarding the Expedited Interconnection \nTrack Proposal PDF \n2.17.2026 \n18 \nPA Governor Shapiro Letter Regarding BRA Price Collar \nExtension PDF \n2.11.2026"},{"page":17,"startToken":5222,"endToken":5540,"text":"2 \n \n19 \nNECL Letter Regarding Prioritization of Issues in the PJM Board’s \nDecisional Letter on Critical Issue Fast Path (CIFP) - Large Load \nAdditions PDF \n2.11.2026 \n20 \nLetters Regarding the Price Collar: OPSI PDF \n2.3.2026 \n21 \nPAPUC Letter Regarding 2025 RTEP Window 1 MAAC Regional \nCluster Competitive Solution 2025-W1-237 PDF \n1.27.2026 \n22 \nPA OCA Letter Regarding RTEP Project 237 PDF \n1.21.2026 \n23 \nIL, NJ Governors’ Letter Regarding National Energy Dominance \nCouncil and 13 Governors’ Statement of Principles PDF \n1.21.2026 \n24 \nCAPS Letter Regarding Consumer Advocate Voting on the SMECO \nproposal in CIFP-Large Load Addition PDF \n1.5.2026 \n \n2025 \n \n25 \nSeveral Governors' Letter Regarding Critical Issue Fast Path – Large \nLoad Additions  PDF \n12.3.2025 \n26 \nIllinois Governor Pritzker Letter Regarding Critical Issue Fast Path – \nLarge Load Additions PDF \n11.19.2025 \n27 \nPJM Legislators’ Collaborative Letter Regarding Critical Issue Fast \nPath – Large Load Additions PDF \n11.18.2025 \n28 \nNJBPU Staff Regarding Critical Issue Fast Path – Large Load \nAdditions PDF \n11.18.2025 \n29 \nCongressional Letter Regarding Critical Issue Fast Path – Large Load \nAdditions PDF \n11.6.2025 \n30 \nIL Legislative Letter Regarding Critical Issue Fast Path – Large Load \nAdditions PDF \n11.6.2025 \n31 \nVA Delegate Sullivan Letter Regarding Data Center Heat Re-\nUse PDF \n10.31.2025 \n32 \nSelect PA Senate Members Letter Regarding Supporting Resource \nAdequacy and Affordability in the PJM Region PDF \n10.15.2025 \n33 \nMD Office of Peoples’ Counsel Regarding Large Load Adjustments \nfor the 2026 Load Forecast PDF \n10.15.2025 \n34 \nSenator Fetterman Letter Regarding the Large Load Addition Critical \nIssues Fast Path (CIFP) Process PDF \n10.13.2025 \n35 \nPJM Governors’ Collaborative Joint Statement of Intent PDF \n9.25.2025 \n36 \nGovernors of PJM Member States Letter to the PJM Board Related to \nthe Nomination Committees Decision Regarding Open Seats on the \nBoard of Managers PDF \n9.11.2025"},{"page":18,"startToken":5540,"endToken":5845,"text":"3 \n \n37 \nOPSI Letter to the Board Regarding FPR and IRM Values PDF \n9.8.2025 \n38 \nOPSI Letter Regarding Consultant Review of ELCC \nMethodology PDF \n8.28.2025 \n39 \nOH Stakeholders’ Letter Regarding Board Vacancies PDF \n8.15.2025 \n40 \nPA, VA Governors’ Letter Regarding Board Candidates PDF \n8.11.2025 \n41 \nMultiple Parties’ Letter Regarding Future Priorities PDF \n7.24.2025 \n42 \nConsumer Advocates’ Letter Regarding Board Elections PDF \n7.23.2025 \n43 \nOH Governor DeWine Letter Regarding Board Vacancies PDF \n7.21.2025 \n44 \nNine Governors’ Letter Regarding Board Vacancies PDF \n7.17.2025 \n45 \nPA, VA Governors’ Letter to the Nominating Committee Regarding \nPJM Board Nominations PDF \n6.25.2025 \n46 \nFive Governors’ Letter Regarding FERC Order 1920 PDF \n5.28.2025 \n47 \nNJ Congressional Delegation Letter Regarding Electricity Prices in \nNew Jersey PDF \n5.5.2025 \n48 \nNJ Legislature Senate Select and Assembly Telecommunications and \nUtilities Committees’ Letter Regarding PJM’s March 28, 2025 \nTestimony PDF \n4.22.2025 \n49 \nNJBPU President Guhl-Sadovy Letter Regarding Capacity Market \nAdjustments PDF \n3.26.2025 \n50 \nMD OPC Letter Regarding Request for FPA 202(c) Order for \nContinued Operation of Brandon Shores and Wagner PDF \n2.28.2025 \n51 \nNJ Division of Rate Counsel Letter Regarding NJ Basic Generation \nService (BGS) Auction PDF \n2.13.2025 \n52 \nPA Representative Kauffman Letter Regarding the Transource Project \n9-A PDF \n1.29.2025 \n53 \nMD Governor Moore Letter Regarding Capacity Market Price \nCap PDF \n1.21.2025 \n54 \nNJ Governor Murphy Letter Regarding Capacity Market Price \nCap PDF \n1.21.2025 \n55 \nCAPS Letter Regarding IMM Contract Renewal PDF \n1.15.2025 \n56 \nPA Governor Shapiro Letter Regarding Capacity Market Price \nCap PDF \n1.13.2025 \n \nBoard Communications, PJM Interconnection, L.L.C., https://www.pjm.com/about-pjm/who-we-\nare/pjm-board/public-disclosures (last visited July 13, 2026)."}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":647,"startToken":0,"endToken":84},{"p":1,"at":647,"title":"I. COMMENTS","method":"printed heading","endPage":3,"endAt":266,"startToken":84,"endToken":736},{"p":3,"at":266,"title":"A. The Role of States: Existing Participation and Additional Opportunities","method":"printed heading","endPage":7,"endAt":940,"startToken":736,"endToken":2229},{"p":7,"at":940,"title":"B. The Commission’s Role: Ensuring PJM Processes Are Effective","method":"printed heading","endPage":9,"endAt":5,"startToken":2229,"endToken":2821},{"p":9,"at":5,"title":"C. PJM’s Role: Using its Stakeholder Processes and Governance Mechanisms to","method":"printed heading","endPage":13,"endAt":1268,"startToken":2821,"endToken":4447},{"p":13,"at":1268,"title":"II. CONCLUSION","method":"printed heading","endPage":18,"endAt":1904,"startToken":4447,"endToken":5845}]}