{"document":{"slug":"rec-20260716-4004","title":"Prefiled Statement for Panelists from PJM Interconnection, L.L.C., for the PJM Governance and Stakeholder Reforms Technical Conference","issued":"2026-07-16","accession":"20260716-4004","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"PJM INTERCONNECTION, L.L.C.","kind":"testimony","file":"sources/filings/text/20260716-4004_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260716-4004","tier":"record","sha256":"4daaea7b58fc126bbbbd7134842f6d5e3d02d060183725cf9151a41eba17c7fc","pages":14,"tokens":5885,"emptyPages":[],"textThemes":["adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":44,"text":"For Public Use \n \n \n \n \n \n \n \n \n \n \nComments from  \nPJM Interconnection, L.L.C. \nPrepared in advance of the July 23, 2026, FERC Technical Conference on PJM Governance and the Stakeholder Process, \nDocket No. AD26-7-000 for Panelists David Mills, Asim Z. Haque and David Anders \nJuly 14, 2026"},{"page":2,"startToken":44,"endToken":128,"text":"Comments from PJM Interconnection, L.L.C. \nPJM © 2026 \nwww.pjm.com | For Public Use \ni | P a g e  \nContents \nI. Introduction and Summary ...................................................................................................................................... 1 \nII. PJM's Mission and the Regional Challenge .......................................................................................................... 2 \nIII. The Stakeholder Process Works Well in Many Cases, But Matters of Significance Can Stall ......................... 3 \nIV. Governance Reform Should Strengthen PJM's Ability To Act ........................................................................... 6 \nV. Stakeholder Reform Should Preserve Participation and Improve Speed ........................................................... 8 \nVI. Enhancements to the State Role in PJM Governance ....................................................................................... 10 \nVII. Next Steps ............................................................................................................................................................ 11"},{"page":3,"startToken":128,"endToken":654,"text":"Comments From PJM Interconnection, L.L.C. \nPJM © 2026 \nwww.pjm.com | For Public Use \n1 | P a g e  \nI. Introduction and Summary  \nPJM Interconnection, L.L.C. respectfully submits these comments in advance of the Commission-led Technical \nConference on PJM Governance and Stakeholder Reforms scheduled for July 23, 2026. The Commission has posed \na practical question: What concrete reforms would improve PJM's ability to address operational and wholesale \nelectricity market needs in a timely and efficient manner?  \nFor PJM, this is not an abstract question. The PJM region is experiencing rapid load growth, tightening supply-\ndemand conditions, changed resource economics and upward pressure on consumer costs. In this environment, \ngovernance and stakeholder processes play a direct role in determining how quickly and effectively PJM can respond \nto changing system needs.  \nPJM is committed to meeting this moment, and the Commission is appropriately examining whether aspects of PJM’s \ngovernance and stakeholder processes should evolve to better enable our ability to do so. The stakeholder process \nhas important strengths. It provides a structured forum in which a broad range of stakeholders can test ideas, raise \nconcerns, evaluate risks and refine proposals before they are submitted to the Commission. This deliberative function \nis a core feature of the PJM construct, including the principle that all voices in the stakeholder process will be heard \nin a meaningful forum. It should be preserved in any consideration of reform. \nPJM governance and stakeholder processes are not fundamentally broken. In fact, PJM and its stakeholders reach \nconsensus on the majority of issues considered. However, for certain high-impact matters, the current process can \nproduce a robust record without consistently producing a timely path to action. In those instances, the region benefits \nfrom both meaningful participation and a clear and effective decision point. This tension is discussed in these \ncomments and will be supported by a statistical breakdown. \nFurther, while the PJM stakeholder process is highly structured and deliberative, it was not built for speed or \noperational agility.  \nPJM serves one of the fastest-growing and dynamic regions in the country. It must therefore be able to not only \nincorporate diverse stakeholder input, but also act with greater speed, clarity and decisiveness in bringing well-\ndeveloped proposals before this Commission. \nMany ideas will be advanced during this technical conference through testimony and written comments. It is \nimportant that the Commission evaluate these proposals in light of whether they will strengthen PJM’s ability to \nefficiently serve 67 million consumers in a region that is central to the nation’s economic growth.  \nPJM appreciates the Commission’s willingness to examine these complex and important governance and \nstakeholder issues. In these comments, PJM seeks to: \n• \nProvide background on PJM governance and statistical analysis on its stakeholder process. \n• \nDiscuss the importance of considering the benefits of PJM having unconditioned Federal Power Act (FPA) \nsection 205 rights over its core regional transmission organization functions. \n• \nExpress the need for PJM stakeholder process enhancements that will allow for PJM and its stakeholders to \nadvance issues with greater speed/efficiency. \n• \nExpress a continued desire to work with states and to provide for greater participation by the states to strengthen \nPJM’s mission and regional alignment."},{"page":4,"startToken":654,"endToken":1120,"text":"Comments From PJM Interconnection, L.L.C. \nPJM © 2026 \nwww.pjm.com | For Public Use \n2 | P a g e  \n• \nOutline potential next steps to make progress on each of these issues. \nII. PJM's Mission and the Regional Challenge  \nPJM's Operating Agreement establishes the Board's governing principles, including the safe and reliable operation of \nthe bulk electric grid in the PJM region; the creation and operation of a robust, competitive and nondiscriminatory \nelectric power market; and the principle that no Member or group of Members should have undue influence over the \noperation of the PJM region.  \nThese principles matter because they establish the independence that is essential to PJM’s role as a regional \ntransmission organization and independent system operator. This independence allows PJM to coordinate a large \nmultistate electric system without favoring any particular utility, generation owner, customer class or state policy \npreference.  \nPJM’s core mission is the safe and reliable operation of the bulk electric system. Over time, PJM has carried out that \nmission by: \n• \nOperating the regional transmission grid through changing system conditions \n• \nAdministering markets that have cost-effectively reinforced reliable grid operations \n• \nPlanning transmission expansion \n• \nFacilitating the orderly entry and exit of resources through market forces \n• \nReforming interconnection processes  \n• \nIdentifying emerging reliability risks as demand growth, resource retirements and infrastructure constraints \nconverge \n \nThe context in which PJM carries out this mission has changed. \nPJM's 2026 Long-Term Load Forecast projects summer peak load growth of 3.6% per year over the next 10 years, \nwith summer peak demand forecast to increase by 65,733 MW by 2036 and by 96,704 MW by 2046. PJM's current \nplanning materials also show a widening supply and demand challenge, with 2025 supply of 181,533 MW, 2025 \nsummer peak demand of 160,526 MW, and projected 2041 summer peak demand of approximately 241,000 MW. \nThis increase is primarily being driven by the proliferation of data centers that support artificial intelligence \nadvancement in the U.S. This month alone has produced multiple days that approach (and even exceed subject to \nverification) PJM’s all-time peak demand day. \nFrom a membership perspective, the region is more complex than it was when many of the existing stakeholder rules \nwere developed. PJM's membership has grown substantially and now includes more than 1,100 Members across five \nsectors (ISO-NE has the next most with approximately 560). As PJM and its markets have grown, so too has the \ninterest in PJM and specifically the monetization of varied technologies and business models creating heightened \nadvocacy around the organization. \nFrom a state perspective, PJM has also grown increasingly complex. PJM spans 14 jurisdictions, of which seven are \nrestructured (competitive markets based) and seven are vertically integrated. Our states’ policy priorities are not \nhomogeneous. They diverge widely, with some states advancing decarbonization efforts and others prioritizing the"},{"page":5,"startToken":1120,"endToken":1596,"text":"Comments From PJM Interconnection, L.L.C. \nPJM © 2026 \nwww.pjm.com | For Public Use \n3 | P a g e  \npreservation of base load resources, as just one example. Many of our states have evolved their objectives over \ntime, and “reliability at least cost” may no longer be the sole driver for many of our states.  \nThe growth of the footprint and the varied interests that have accompanied that growth are strengths when viewed \nfrom the lens of garnering diverse perspectives and industry knowledge. However, these varied interests can \ncertainly be a challenge when trying to meet the principles articulated above around speed/efficiency in our \nstakeholder process and meeting this moment of rapid growth.  \nDespite so much change since PJM was first created in 1927 and the first stakeholder process reform effort in the \nearly 2000s, PJM’s value proposition has remained strong. The utilization of scale and markets has resulted in many \nbillions of dollars in savings for consumers along with a secure and reliable power grid. But just as our system, \nMembers, and states are evolving, the Commission is right to ask whether our governance and stakeholder \nprocesses should also evolve. We believe they should. \nIII. The Stakeholder Process Works Well in Many Cases, But Matters of \nSignificance Can Stall  \nPJM's stakeholder process has long been a strength of the region. It allows for broad participation, technical review \nand the development of proposals. The process includes, and benefits from, many perspectives: residential \nratepayers, consumer advocates, states, utilities, generators, suppliers, developers, large customers and other \nstakeholders. That openness should be preserved. \nPJM also accomplishes much through this process. PJM's review of recent issue votes indicates that from 2023 \nthrough the first half of 2026, 66 of 75 issue votes passed, an overall pass rate of approximately 88%. Many of these \nsuccessful votes involved more straightforward or narrowly focused issues, including expedited processes like Quick \nFix and Consensus Based Issue Resolution (CBIR) Lite matters. That record shows that the process can work well \nfor many issues. \nTable 1. Recent Senior Standing Committee Votes \nYear \nTotal Issue \nVotes \nIssues \nPassed \nIssues \nFailed \nPercent \nPassed \nPercent Voted \nby \nAcclamation \nPercent Voted by \nSector-Weighted \nVote \n2023 \n23 \n21 \n2 \n91.3% \n64.8% \n35.2% \n2024 \n22 \n18 \n4 \n81.8% \n70.6% \n29.4% \n2025 \n22 \n20 \n2 \n90.9% \n55.1% \n44.9% \n2026 YTD \n8 \n7 \n1 \n87.5% \n47.3% \n52.7% \nTotal \n75 \n66 \n9 \n88.0% \n \n \n \nThe difficulty arises with matters of significance; those issues that are complex, financially significant, operationally \nsensitive or polarizing across sectors. When these issues are presented through more fulsome processes, including \nCBIR or Critical Issue Fast Path (CIFP), the process may not produce consensus. Instead, and somewhat \nexpectedly, stakeholders become more entrenched, making it difficult to move from competing positions toward a \ncompromise that can command sector-weighted support."},{"page":6,"startToken":1596,"endToken":1965,"text":"Comments From PJM Interconnection, L.L.C. \nPJM © 2026 \nwww.pjm.com | For Public Use \n4 | P a g e  \nThe table below diagrams the issues that have failed over the last few years, all of which are very relevant to PJM’s \ncore business functions. \nTable 2. Matters of Significance Failed Votes \nYear  Month  \nIssue \nFailed Issues (Nothing Passed) \n2023 \nAugust  \nCritical Issue Fast Path – Resource Adequacy (Workshop and Senior Task Force prior to CIFP) \n2023 \nOctober \nCapacity Offer Opportunities for Generation with Co-Located Load  \n2024 \nMarch  \nEvaluation of Energy Efficiency Resources for 2025/2026 BRA (Solution for 2026/2027 BRA later \npassed in August 2024)  \n2024 \nJuly  \nReserve Certainty – Reserve Requirement Revisions (Reserve Deployment issue brought at the \nsame time passed) \n2024 \nAugust  \nRe-evaluation of Financial Parameters Used in CONE for 2027/2028 BRA  \n2025 \nAugust  \nELCC Accreditation Methodology  \n2025 \nNovember  \nCritical Issue Fast Path – Large Load Additions \n2026 \nJune  \nCritical Issue Fast Path – Connect and Manage (Solution for CIFP – RBP voted separately and \npassed)   \nFailed Issues (Future Success) \n2024 \nMay  \nDemand Response Availability Window Quick Fix Solution initially failed in May (Stakeholder \nSponsored); issue later passed in August following a CBIR process  \n \nThe various sectors are broken down as follows, and each has a 1.0 vote at the Members Committee, which is the \nfinal clearinghouse for proposals that advance through PJM’s committee framework. The table below also includes \nthe total number of voting Members in each sector, and how many of these Members actually voted in the CIFP for \nlarge load additions last year. \nTable 3. Member Voting Participation: CIFP on Large Load Additions \nSector \nVoting Block \nTotal Voting Members \nNumber That Voted \nin CIFP LLA1 \nEnd-Use Customers (Consumer Advocates \nand Industrials) \n1.0 \n37 \n19–20 \nElectric Distributors (Municipals and Co-Ops) \n1.0 \n45 \n33 \nOther Suppliers (Financial Traders, Demand \nResponse Providers, “Catch All”) \n1.0 \n321 \n17–18 \nTransmission Owners \n1.0 \n12 \n9–10 \nGeneration Owners \n1.0 \n110 \n32 \n \nBased on the requirement that 3.335 out of 5.000 of a sector-weighted vote is the threshold for a proposal to advance \n \n1 There were 11 packages up for vote; the ranges noted reflect different number of voters depending on the package."},{"page":7,"startToken":1965,"endToken":2625,"text":"Comments From PJM Interconnection, L.L.C. \nPJM © 2026 \nwww.pjm.com | For Public Use \n5 | P a g e  \nthrough PJM’s committee framework, only two sectors need to say “no” to a proposal for it to fail. This occurs mainly \nin “matters of significance” as shown in the table above. It should also be noted that based on the total number of \neligible Voting Members (525) and the total number of votes for or against in the CIFP-LLA (113), that a minority of \nour Voting Members (in the case of the CIFP LLA just 22%) are actually involved and voting on major issues. \nCombine this with the fact that many of these votes are conducted by proxy, and just a few individual voices/interests \ncan control whether an effort moves forward for 67 million consumers. These are not metrics and dynamics that lend \nthemselves to PJM successfully moving with speed/efficiency to meet the moment we collectively find ourselves in. \nOn matters where sector interests diverge sharply, that structure can produce a stalemate. It is very possible this is \ndue to rooted financial interests that exist not just with asset owners and market participants, but with those whose \nfunding is dependent on continued expressions of advocacy at PJM. The result goes beyond inconvenience. In a \nperiod of rapid load growth and tightening reliability needs, such delay can result in degraded reliability, increased \ncosts, a reduction in investment certainty in our markets and, most certainly, a delay in bringing issues to the \nCommission.   \nAn example of the process’s inability to move through a technically complex, yet important issue involves PJM’s \nattempts to reform its reserve markets. The Reserve Certainty Senior Task Force (RCSTF) is a stakeholder effort \nthat was launched in October 2023, and it is targeted for a Members Committee vote in October 2026 – three years \nlater. \nThe process was initiated for PJM and its stakeholders to evaluate its reliability posture and identify opportunities for \nimprovement given the energy transition and lessons learned from Winter Storm Elliott. “Reserve certainty” is derived \nfrom the idea that having an appropriate suite of ancillary service products coupled with the confidence that these \nresources in reserve will perform when called upon are necessary attributes in reserve markets.  \nSpecifically, PJM has been experiencing poor performance of its reserves at the same time that PJM’s reserve needs \nare increasing with the system. The existing reserve margins primarily address risk associated with large unit loss. \nWhile PJM will always need to manage contingency risk, this alone is no longer sufficient given the more dynamic \nuncertainties associated with the energy transition to more renewable resources. This issue also has broader impacts \nto consumer costs, as it directly ties into the concept of “uplift” payments and whether some of the costs that should \nbe appropriately reflected in reserve pricing are instead relegated to uplift. \nAs the RCSTF phased its work, two of three early-phase issues received endorsement up through the Members \nCommittee and were filed and accepted by FERC.2 Just this month, the RCSTF endorsed a proposal to move \nforward to the Markets and Reliability Committee in August, with a 65.7% simple majority vote. \nThe RCSTF has met 42 times since initiation of this issue. As discussed in the next section, PJM may have been \nable to move this process along more quickly if it had the authority to make a filing under section 205 of the Federal \nPower Act, even absent endorsement. \nLast year’s CIFP on large load additions illustrates an additional challenge. At Stage 4, where proposals are \npresented in the presence of the PJM Board, stakeholders considered multiple proposals. No proposal reached the \nsector-weighted voting threshold required for Member approval. The fact that many proposals were considered is \n \n2 See PJM Interconnection, L.L.C., Letter Order, Docket No. ER24-2885 (Oct. 18, 2024) (regarding reserve deployment); PJM \nInterconnection, L.L.C., Letter Order, Docket No. ER24-3121 (Nov. 22, 2024) (regarding hourly notification times)."},{"page":8,"startToken":2625,"endToken":3059,"text":"Comments From PJM Interconnection, L.L.C. \nPJM © 2026 \nwww.pjm.com | For Public Use \n6 | P a g e  \nevidence of active participation. The fact that none reached the threshold for approval is evidence that participation \nalone is not always enough to produce timely action on matters of significance. \nTable 4. Voting Breakdown: CIFP on Large Load Additions \nCIFP-Large Load Additions Package Sponsor \nSector-Weighted Vote Tally (3.335 passes) \nPJM \n1.933 \nIMM \n1.994 \nJoint Stakeholder Proposal \n0.836 \nData Center Coalition, Office of PA Gov., Exelon and PPL \n1.904 \nPJM Legislator’s Collaborative and NRDC \n1.012 \nPA OCA and MD OPC \n1.123 \nEKPC \n0.574 \nDominion \n0.426 \nLS Power \n1.176 \nDR Coalition \n0.261 \nPSEG \n0.412 \nSMECO \n2.333 \nIV. Any Governance Reform Should Strengthen PJM's Ability To Act  \nPJM's ability to act depends on who has the legal authority to file proposed changes with the Commission. The \nFederal Power Act controls the burden of proof when a public utility files proposals to change rates, terms, \nconditions, rules or practices on file with the Commission. The standard of review for the Commission under section \n205 is whether the proposal is just and reasonable and not unduly discriminatory or preferential. The Commission \nmust act within 60 days of the filing, or the filing is deemed accepted. \nBy contrast, the burden of proof under a section 206 complaint or Commission-initiated proceeding requires a \nshowing that the existing rate, term or condition is unjust and unreasonable, or unduly discriminatory or preferential \nbefore a replacement rate can be ordered. This requires the Commission to assess the efficacy of PJM’s proposed \nreplacement rate as compared with all other replacement rate proposals. Further, the Commission is not under a 60-\nday time clock for 206 actions. \nHaving section 205 filing rights matters because it allows a proposal to be put before the Commission without first \nrequiring the filer to prove that the existing rule is unjust and unreasonable, and it also includes a definitive 60-day \nclock. \nPJM's current governing documents divide section 205 filing rights across different entities and subject areas. PJM \nhas section 205 rights over some areas, mainly the capacity market. But in other core areas, including the energy \nand ancillary services markets and the Regional Transmission Expansion Plan process, PJM's ability to file under \nsection 205 is conditioned on Members Committee approval. Without Members Committee approval, PJM may be \nrequired to proceed under the more restrictive requirements of section 206. That dynamic can limit the ability of \nimportant issues to reach the Commission for adjudication in a timely manner."},{"page":9,"startToken":3059,"endToken":3589,"text":"Comments From PJM Interconnection, L.L.C. \nPJM © 2026 \nwww.pjm.com | For Public Use \n7 | P a g e  \nThis division is, in many cases, an accident of history dating back to the formation of PJM as an RTO and the unique \ntiming and circumstances that were before the stakeholders at the time.  \nTable 5. Current Section 205 Filing Rights by Core Function  \nCore Area \nPrincipal Governing Document(s) \nCurrent Section 205 Filing \nAuthority \nCapacity market \nTariff and Reliability Assurance Agreement \nPJM \nEnergy and ancillary services markets \nOperating Agreement \nMembers Committee (conditioned) \nOperations – emergency procedures \nOperating Agreement \nMembers Committee (conditioned) \nOperations – transmission service \nTariff \nPJM \nPlanning – Regional Transmission \nExpansion Plan process \nOperating Agreement \nMembers Committee (conditioned) \nPlanning – interconnection process \nTariff \nPJM \n \nThis structure is especially important for the energy and ancillary services markets and transmission planning. These \nare core RTO functions that affect resource performance, dispatch, operational flexibility, transmission expansion, \nand the ability to accommodate changing load and resource patterns. PJM should be able to ask the Commission to \nreview reforms in these areas consistent with the burden of proof that other RTOs and ISOs need to meet when filing \nreforms before the Commission on these same topics. There is no reason in our view why PJM (and ultimately the \nCommission) should face a higher hurdle to propose reforms in these areas than other RTOs and ISOs.  \nIndeed, as explained above, PJM’s stakeholder process to reform its reserve markets is on pace to take three years \nto complete. Having 205 rights could have accelerated this effort, as Members would know that PJM could utilize its \n205 authority for a matter that PJM views to be critical.  \nWhile PJM has mechanisms to move more quickly, as articulated in Manual 34 [Quick Fix, Enhanced Liaison \nCommittee (ELC), CIFP], without corresponding 205 rights, there simply is not the same incentive for stakeholders to \nmove issues forward with expediency. Further, each of these mechanisms can only be used in very specific \ncircumstances and can also be highly procedural. \nThese additional 205 rights would not come at the expense of meaningful engagement and transparency of the \nexisting stakeholder process. That is, even if PJM has 205 rights, we would still create opportunities for stakeholders \nto be heard and to have open and transparent discussions about proposals. PJM does this today using formal \nstakeholder processes even when seeking reform to the capacity market where PJM has 205 rights.  \nOnce filed, stakeholders, of course, may continue to provide feedback or challenge the proposal before the \nCommission. The Commission, not stakeholder voting outcomes or PJM, is ultimately responsible for determining \nwhether a proposed Tariff change is just and reasonable under the Federal Power Act. \nThe true strength of the stakeholder process lies in the diverse perspectives and the feedback provided by our \nstakeholder body on any given proposal. Consensus is desirable but is not a panacea. Like-minded stakeholders \ncould produce a proposal that unintentionally compromises reliability. We respect our stakeholders and their \nfeedback immensely. That feedback is essential to allow for the best possible proposal to be presented to the \nCommission. But we ask the Commission to consider whether conditioned 205 rights over certain of PJM’s core"},{"page":10,"startToken":3589,"endToken":4061,"text":"Comments From PJM Interconnection, L.L.C. \nPJM © 2026 \nwww.pjm.com | For Public Use \n8 | P a g e  \nbusiness functions remain appropriate based on the challenging environment that we are collectively operating \nwithin. \nPJM is an outlier. Our peer ISOs/RTOs do not have such conditioning of their 205 rights, and it is worth examining \nwhether PJM, the largest grid operator in the nation that has a mission to serve 67 million consumers reliably, should \nhave greater autonomy than it has today to act decisively on emergent matters. Aligning PJM’s authority more closely \nwith peer RTOs would modernize governance while preserving necessary elements of meaningful engagement and \ntransparency. \nPJM respectfully submits that governance reform should strengthen the institution’s ability to identify needed reforms \nand present them to the Commission for timely review. Our objective is to align authority with accountability. To that \nend, the Commission should consider whether PJM should possess unconditioned section 205 filing rights across all \nits core operational, market and transmission planning responsibilities, subject to Board oversight and informed by \nstakeholder engagement. Such a framework would preserve stakeholder participation while ensuring that important \nissues can be presented to the Commission for resolution when consensus proves elusive.  \nV. Any Stakeholder Reform Should Preserve Participation and Improve \nSpeed \nThe Commission should support reforms that preserve the strengths of PJM's stakeholder process while improving \nspeed, focus and accountability. PJM supports stakeholder input for critical decisions; however, PJM is \nrecommending that stakeholder input be organized in a way that allows critical issues to reach a conclusion. \nPJM's stakeholder process rule book, known as Manual 34, sets the procedures by which PJM, Members, states and \nother stakeholders identify issues, develop proposals, build consensus, and vote on changes to PJM's rules and \npractices. Manual 34 and the CBIR process were developed to provide structure, transparency and broad \nparticipation. Those goals remain important.  \nBut the process was designed without a particular and special focus on speed, and several past stakeholder process \nreforms added procedural structure and did little in the way of cutting timelines. \nPJM's governance history reflects this evolution. From 1997 to 2002, there were no detailed written rules for \noperation of the stakeholder process beyond the Operating Agreement provisions governing the Members \nCommittee. The Chairman's Advisory Team produced the first Members Handbook in 2002. Later efforts, including \nthe Governance Working Group, the Governance Assessment Special Team and the Super Forum, produced \nadditional process enhancements, Manual 34, the CBIR process and a few expedited processes that, again, are \nhighly procedural. They were not solely focused on making the process faster.  \nTable 6. Selected Stakeholder Process Reform History \nReform Effort \nPrimary Driver \nPrincipal Result \nChairman's Advisory Team (2002) \nNeed for basic process structure \nMembers Handbook and stakeholder \ngroup charters \nGovernance Working Group (2004–\n2006) \nGovernance and balance-of-power \nconcerns \nMembers Handbook revisions and \nprocess enhancements"},{"page":11,"startToken":4061,"endToken":4465,"text":"Comments From PJM Interconnection, L.L.C. \nPJM © 2026 \nwww.pjm.com | For Public Use \n9 | P a g e  \nReform Effort \nPrimary Driver \nPrincipal Result \nGovernance Assessment Special Team \n(2008–2010) \nOrder 719 compliance and stakeholder \nprocess rules \nManual 34, CBIR and Enhanced \nLiaison Committee process \nSuper Forum (2018–2019) \nPrioritization and contentious issues \nCritical Issue Fast Path process \nSurvey and action plan (2020) \nStakeholder process enhancements \nPJM implemented items within its \nauthority; other items required \nstakeholder or Commission action. \n \nSpecifically, as to the reform effort in 2020, PJM interviewed our most active Members in all five sectors utilizing a \nstandardized set of questions around engagement, process, governance and overall thoughts on reform. PJM \nanalyzed the results and separated recommendations into two distinct groups: those enhancements that PJM could \nimplement on its own and those enhancements that required stakeholder or Commission action to effectuate. The \nprimary underpinning for the existence of the second category is that Manual 34 (along with the Operating \nAgreement) can only be amended by a two-thirds sector-weighted vote of the Members.   \n \nTable 7.  PJM’s Approach \nSuggestions That PJM Can Implement \nGreater scrutiny on sector selection/review \nConsider use of accelerated processes. \nSummarizing FERC orders at stakeholder meetings \nPJM positioning/assertion of independence in process \nPJM enhanced review of problem statement/issue charges \nStreamline education. \nInternal process improvements  \nEnhanced parliamentarian training \nBest practices from other ISO/RTO structures \nTargeted facilitation training \nWork with states on governance reform. \nSequence/prioritize issues in the stakeholder process. \nSuggestions Requiring Affirmative Sector-Weighted Vote \n205 rights over energy market and RTEP rules \nNOPR-like process to collect comments \nIssue gating  \nRestricting motions brought from the floor \nQuorum requirements \nSector reorganization \nRep and proxy rules \nVoting reform  \nPublish sector-weighted votes at lower committees. \nMRC sole reviewer/endorser of issue charges \nLimiting proposals from lower committees \nSector challenge timing \n \nPJM worked to advance efforts for each item in the first category and left the second category for the Members to \npursue since only they could effectuate change in these areas. \nThe next phase of reform should be focused on speed and accountability. PJM recommends that the Commission \nprovide support to the following reforms that PJM and the Members can then work to implement. \n1. Create an additional expedited process, or expand existing expedited tools, for high-priority reliability, market \nand planning issues. PJM has Quick Fix, CBIR Lite, the ELC and CIFP, but these tools apply only in specific"},{"page":12,"startToken":4465,"endToken":5032,"text":"Comments From PJM Interconnection, L.L.C. \nPJM © 2026 \nwww.pjm.com | For Public Use \n10 | P a g e  \ncircumstances and are highly procedural. PJM should have a practical pathway to obtain stakeholder input \nquickly and then proceed where necessary. \n2. Apply time gates to stakeholder processes. No critical stakeholder process should continue indefinitely. For \nissues that materially affect reliability, market performance, resource adequacy, large load integration or \ntransmission planning, etc., PJM and its stakeholder body should enforce defined timelines for issue \nidentification, options development, stakeholder comment, voting and escalation. If consensus cannot be \nreached within that timeline, PJM should be able to bring the matter to its Board and, where appropriate, to the \nCommission. \n3. Conduct more business in writing where appropriate. PJM held over 400 stakeholder meetings in 2025. PJM can \npreserve participation without requiring every issue to move through repeated meetings. Written submissions, \nposted questions and answers, recorded technical presentations, and structured comment windows can reduce \nduplication while maintaining transparency. \n4. Reduce duplicative meetings and prioritize issues. PJM and stakeholders have finite time and technical \nresources. The process should distinguish between issues that require extended stakeholder work and issues \nthat can be handled through written comment, staff recommendation or a shorter review process. \n5. Use technology to improve transparency and reduce repetition. PJM is committed to exploring meeting \nrecordings, searchable materials, posted Q&A and technology-assisted summaries, subject to appropriate legal \nand quality controls. These tools can help stakeholders who cannot attend every meeting while reducing \nrepeated discussions across committees. Commission support for this effort would be of assistance in \neffectuating technological change within PJM’s existing processes. \nThese reforms should be designed to reflect all views, including dissenting opinions. Minority positions should still be \ndocumented and presented to the Board and the Commission. The objective is to ensure that dissent is heard \nwithout acting as a veto over whether an issue can be placed before the Commission. \nVI. Enhancements to the State Role in PJM Governance \nStates play an important role in PJM’s deliberative processes. It is undisputed that states retain primary jurisdiction \nover resource adequacy, integrated resource planning, siting and permitting, retail rate design, and retail cost \nallocation. Although the exact state role may differ based on whether the state has restructured and limited its role \nover generation as opposed to states that retained traditional regulation over generation, there is no question that the \nstates play a key role that needs to be effectively incorporated into PJM decision-making. Collectively, these state-\nlevel authorities play a major role in determining whether the PJM region can meet this historic load growth while \nmaintaining reliability and addressing affordability concerns. \nPJM has long worked with the states, including through the Organization of PJM States, Inc. (OPSI). PJM supported \nthe formation of OPSI in 2005 and has maintained a structured relationship with the organization ever since. PJM \nmeets regularly with its state utility regulators, and the OPSI Board meets with the PJM Board three times per year to \ndiscuss priorities and pressing matters. That relationship has provided a useful channel for PJM to receive state \ninput. It should be noted that during the formation of PJM as an independent entity, the states chose not to be \nMembers of PJM so as to not be placed in a position to vote or otherwise opine on matters that may subsequently \ncome before them in their role as state commissioners."},{"page":13,"startToken":5032,"endToken":5596,"text":"Comments From PJM Interconnection, L.L.C. \nPJM © 2026 \nwww.pjm.com | For Public Use \n11 | P a g e  \nMore recently, the energy politics in each of the PJM states has become more complex. Within individual states, PJM \nmay hear from governors, utility commissioners, legislators, consumer advocates and other public officials who each \nhold diverging views. The range of diverse voices speaking for each of the states can make it difficult for PJM to \ndetermine how best to incorporate any given state’s view into its decision-making.  \nPJM is responsive and shows great deference to the states. As a recent example, after the 2025/2026 capacity \nauction results that expressed a major uptick in pricing appropriately reflecting challenged supply/demand conditions, \nPJM made many changes in advance of the 2026/2027 auction as requested by many of our states. Such changes \nincluded a “must-offer” requirement for all resources in the capacity market, the inclusion of Reliability Must-Run \nresources in the market and the pricing cap/floor proposal.  \nThe Commission should encourage a state engagement model that strengthens PJM as a regional institution rather \nthan fragmenting regional decision-making. States should have meaningful opportunities to communicate priorities, \nidentify concerns and inform PJM’s understanding of emerging policy developments. At the same time, any \ngovernance reforms should preserve PJM’s independence and its ability to carry out its Commission-approved \nresponsibilities on a regional basis. The objective should be to strengthen PJM as an institution, which will in turn \nenhance our mission to deliver power reliably and run markets to promote economic benefits for 67 million \nconsumers.   \nState gains in PJM governance should be coupled with responsibility and accountability in the region. States already \nexercise substantial influence over regional outcomes through decisions affecting resource adequacy – integrated \nresource planning, siting and permitting, decisions about whether and how to integrate large loads, and policies \ndriving resource entry and exit. As discussions regarding governance reform continue, it is appropriate to recognize \nboth the opportunities and responsibilities associated with that influence. \nPJM welcomes the states' views on the enhanced role they envision and how that role can be structured. PJM is \nopen to discussions around how PJM can enhance opportunities for state participation and better define roles and \nresponsibilities. But such proposals should be paired with an appropriate level of responsibility and accountability \nbased upon our states’ very important role – especially in maintaining resource adequacy for the region. Failure to \nreconcile requested gains with the states’ jurisdictional responsibilities could serve to exacerbate the region’s already \nchallenging position.  \nVII. Next Steps  \nPJM appreciates the Commission holding this Technical Conference and outlines below possible options for moving \nforward. Commission guidance on the above-identified issues, through informal statements made by Commissioners \nat the Technical Conference as well as formal Commission issuances, would be welcome. The options for next steps \nthat the Commission could pursue include: \nOption One: The Commission could provide guidance and encourage PJM and its stakeholders, including the \nstates, to work toward a resolution of identified issues through the stakeholder process and encourage PJM to bring \nforth a filing pursuant to section 205 of the Federal Power Act (and to make necessary changes to Manual 34) to \naddress the identified concerns.   \nOption Two: The Commission could initiate a proceeding pursuant to section 206 of the Federal Power Act to \naddress the 205 matter, stakeholder process improvements or even the role of states. Should the Commission"},{"page":14,"startToken":5596,"endToken":5885,"text":"Comments From PJM Interconnection, L.L.C. \nPJM © 2026 \nwww.pjm.com | For Public Use \n12 | P a g e  \ndecide to utilize this formal authority, PJM encourages the Commission to narrowly scope out the areas of concern \nwith precision so as to advance a prompt resolution. Such an initial order could institute a paper hearing briefing \nprocess and ultimately culminate in an order requiring action by PJM. Should the Commission decide to employ this \nformal process, PJM encourages the Commission to also consider utilizing Option Three and promptly sua sponte \ninitiate a settlement process, as further set forth in Option Three.   \nOption Three: The Commission could appoint a settlement judge to oversee a structured, time-bound discussion of \nspecific issues utilizing a settlement process and, importantly, the settlement privilege and confidentiality \nrequirements. This process could be deployed with or without the issuance of an order pursuant to section 206 of the \nFederal Power Act. Again, the concerns and issues should be identified with precision and the scope narrowly \ndefined. Such issues may include: \n \na. Whether the conditioning of PJM’s section 205 rights as set forth in the Operating Agreement affords PJM \nsufficient independence as required by Order 2000, particularly with respect to the schedules and section \n205 rights over the energy and ancillary service markets (as set forth in Schedule Nos. 1 and 2) and \nregional and interregional planning (as set forth in Schedule Nos. 6, 6-A and 6-B) \nb. Whether the roles and responsibilities of the states and the District of Columbia are adequately defined in \nthe PJM governing documents and whether additional opportunities for participation in PJM governance \nshould be provided for the states and the District of Columbia, as well as any attendant additional financial \nsupport"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":99,"startToken":0,"endToken":148},{"p":3,"at":99,"title":"I. Introduction and Summary","method":"printed heading","endPage":4,"endAt":174,"startToken":148,"endToken":686},{"p":4,"at":174,"title":"II. PJM's Mission and the Regional Challenge","method":"printed heading","endPage":5,"endAt":1212,"startToken":686,"endToken":1317},{"p":5,"at":1212,"title":"III. The Stakeholder Process Works Well in Many Cases, But Matters of","method":"printed heading","endPage":8,"endAt":736,"startToken":1317,"endToken":2752},{"p":8,"at":736,"title":"IV. Any Governance Reform Should Strengthen PJM's Ability To Act","method":"printed heading","endPage":10,"endAt":1371,"startToken":2752,"endToken":3790},{"p":10,"at":1371,"title":"V. Any Stakeholder Reform Should Preserve Participation and Improve","method":"printed heading","endPage":12,"endAt":2293,"startToken":3790,"endToken":4786},{"p":12,"at":2293,"title":"VI. Enhancements to the State Role in PJM Governance","method":"printed heading","endPage":13,"endAt":2880,"startToken":4786,"endToken":5449},{"p":13,"at":2880,"title":"VII. Next Steps","method":"printed heading","endPage":14,"endAt":1853,"startToken":5449,"endToken":5885}]}