{"document":{"slug":"rec-20260720-5170","title":"Vistra Corp. submits Request for Clarification or, in the Alternative, Rehearing of the 06/18/2026 Order","issued":"2026-07-20","accession":"20260720-5170","docket":"ER26-1479-001","group":"PJM co-location compliance","filer":"Vistra Corp.","kind":"rehearing request","file":"sources/filings/text/20260720-5170_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260720-5170","tier":"record","sha256":"0e013dcedf25ea1e80d2023588e07373caad46a4ce4c4e135aa09bae94114e4b","pages":19,"tokens":5682,"emptyPages":[],"textThemes":["colo","flex","adequacy","study"]},"pages":[{"page":1,"startToken":0,"endToken":292,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et al. \nLarge Loads Co-Located at Generating Facilities \nConstellation Energy Generation, LLC \nv. \nPJM Interconnection, L.L.C. \nPJM Interconnection, L.L.C. \n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\nDocket Nos. EL25-49-002 \n                     EL25-49-000 \nDocket No. AD24-11-001 \nDocket No. EL25-20-001 \n                  (consolidated) \nDocket No. ER26-1479-000 \nREQUEST FOR CLARIFICATION OR, IN THE ALTERNATIVE, REHEARING  \nOF VISTRA CORP. \nPursuant to Section 313 of the Federal Power Act (“FPA”)1 and Rules 212 and 713 of the \nRules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission” or \n“FERC”),2 Vistra Corp. (“Vistra”) requests clarification, or in the alternative, rehearing, of the \norder issued by the Commission on June 18, 2026, in the above-captioned dockets (“June 2026 \nOrder”).3  The Commission should clarify one narrow issue:  when a secondary generator4 in a \nCo-Location Arrangement will continue to be available to PJM as a capacity resource and comply \nwith its Day-Ahead Market offer requirement, that unit should not be required to delist its Capacity \n1 16 U.S.C. § 825l(a). \n2 18 C.F.R. §§ 385.212, 385.713. \n3 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209 (2026) (“June 2026 Order”). \n4 In this context, a “secondary generator” refers to a generation unit that will serve the Co-Located Load only if \nthe unit dedicated to providing primary service to the Co-Located Load is on an outage and only if the secondary \ngenerator is not committed in PJM’s energy market.  However, Vistra notes that the same principles apply where the \nservice to the Co-Located Load does not come entirely from a single unit, but instead comes from portions of each \ngeneration unit with the remaining MW from each unit being offered in PJM’s energy market."},{"page":2,"startToken":292,"endToken":835,"text":"-2- \nInterconnection Rights (“CIRs”).  This clarification is necessary because the Commission’s June \n2026 Order’s findings on CIR treatment did not address the circumstance in which the secondary \ngenerator complies with the Day-Ahead Market offer requirement.  To the extent this clarification \nis denied, we seek rehearing. \nSPECIFICATION OF ERRORS & STATEMENT OF ISSUES \n1. The PJM tariff is ambiguous as to whether an Interconnection Customer must delist the CIRs \nof a secondary, interruptible unit that serves a Co-Located Load only when not committed in \nthe PJM market.  The Commission should clarify that the PJM tariff does not require an \nInterconnection Customer to delist the CIRs of a unit of a capacity resource that is capable of \nmeeting both the emergency performance and the Day-Ahead Market must-offer requirements \napplicable to capacity resources, if the unit provides secondary, interruptible service to a Co-\nLocated Load only when the unit is not committed in PJM’s energy market.  Without \nclarification, the PJM tariff violates the FPA requirement that rates, terms, and conditions of \nCommission-jurisdictional service be just and reasonable and not unduly discriminatory or \npreferential.  See 16 U.S.C. §§ 824d(a), 824d(b), 824e. \n2. If the Commission declines to provide the clarification requested above, the June 2026 Order \nis arbitrary and capricious, in violation of the Administrative Procedure Act, because the \nCommission failed to engage in reasoned decisionmaking by failing to respond to Vistra’s \nobjections to PJM’s proposal and failing to consider the important issues that Vistra raised.  \nSee 5 U.S.C. § 706(2)(A); Motor Vehicle Mfrs. Ass’n v. State Farm Mutual Automobile Ins. \nCo., 463 U.S. 29 (1983) (“State Farm”); Michigan v. EPA, 576 U.S. 743 (2015); Del. Div. of \nPub. Advoc. v. FERC, 3 F.4th 461 (D.C. Cir. 2021); New England Power Generators Ass’n v. \nFERC, 881 F.3d 202 (D.C. Cir. 2018); TransCanada Power Mktg. Ltd. v. FERC, 811 F.3d 1 \n(D.C. Cir. 2015); Pub. Serv. Comm’n of Ky. v. FERC, 397 F.3d 1004 (D.C. Cir. 2005); \nCanadian Ass’n of Petroleum Producers v. FERC, 254 F.3d 289, 299 (D.C. Cir. 2001). \n3. If the Commission declines to provide the clarification requested above, the June 2026 Order \nis arbitrary and capricious, in violation of the Administrative Procedure Act, because the \nCommission accepted tariff provisions that did not comply with its directive to clarify its \ninterconnection procedures and agreements to increase certainty and consistency.  See 5 U.S.C. \n§ 706(2)(A); State Farm, 463 U.S. 29; FCC v. Fox Television Stations, Inc., 556 U.S. 502 \n(2009); PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 159 (2025). \n4. If the Commission declines to provide the clarification requested above, the June 2026 Order \nis arbitrary and capricious, in violation of the Administrative Procedure Act and the Federal \nPower Act, to the extent the Commission accepted unjust, unreasonable, and unduly \ndiscriminatory tariff provisions that require a secondary, interruptible unit serving Co-Located \nLoad only when not committed in PJM’s market (and only when the primary unit is not serving \nthe Co-Located Load) to delist its CIRs to implement a Co-Location Arrangement.  See \n5 U.S.C. § 706(2)(A); 16 U.S.C. §§ 824d, 824e; State Farm, 463 U.S. 29."},{"page":3,"startToken":835,"endToken":1155,"text":"-3- \nI.\nBackground \nLast December, the Commission found that the PJM tariff is unjust and unreasonable \nbecause it lacks sufficient clarity and consistency regarding how interconnection customers can \nserve Co-Located Load using existing generating facilities.5  The Commission directed PJM to \npropose tariff revisions to clarify that existing generators can use the necessary study process to \nmodify their interconnection to reflect the addition of new Co-Located Loads.6  In connection with \nthe addition of those Co-Located Loads, the Commission explained that “an existing generating \nfacility may not begin serving Co-Located Load that is not Network Load until it has delisted its \nCIRs for the portion of the generating facility to be designated to serve any Co-Located Load that \nis not receiving [Network Integration Transmission Service (“NITS”)].”7\nPJM proposed, on compliance, to require existing generators that seek to serve Co-Located \nLoad to submit to PJM “the amount of reduction to [CIRs] to facilitate the Co-Located Load \nconfiguration.”8  PJM would then “assess the impact of the reduction in [CIRs]” in the necessary \nstudy process.9\nVistra filed a protest to PJM’s compliance filing, expressing concern that this tariff \nlanguage remained ambiguous and therefore did not address the Commission’s directive to \n“clarify” its interconnection procedures to ensure that it is clear to existing generators how to \n5 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 225 (2025) (“December 2025 Order”). \n6 Id. P 226. \n7 Id. P 230 (emphasis added). \n8 PJM Interconnection, L.L.C., Transmittal Letter, Docket No. ER26-1479-000, at 26 (filed Feb. 23, 2026) (“PJM \nTransmittal Letter”); PJM, Open Access Transmission Tariff, pt. VIII, subpt. A, § 401 (Applications for Cycle Process \nIntroduction) (5.0.0), § H(3)(b)(i)(c); id., pt. IX, subpt. G (Form of Necessary Studies Agreement) (3.0.0), attach. 1 \n(Planned Modifications). \n9 PJM, Open Access Transmission Tariff, pt. VIII, subpt. A, § 401 (5.0.0), § H(3)(b)(ii)."},{"page":4,"startToken":1155,"endToken":1418,"text":"-4- \ninterconnect in a Co-Location Arrangement.10  Specifically, Vistra explained, PJM’s proposed \ntariff language was ambiguous with regards to how a generator should calculate the amount by \nwhich its CIRs should be reduced.  Vistra expressed concern that the tariff could be read to require \ngenerators to delist CIRs associated with any facility that would ever provide power to Co-Located \nLoad, not just the portion of the facility designated to serve the Co-Located Load.  Under this \nbroad reading, an existing, two-unit generator with one 50 MW unit serving Co-Located Load on \na firm basis and one 50 MW unit serving Co-Located Load on an interruptible, secondary basis \nonly when the unit is not committed in PJM’s energy market would need to delist 100 MWs of \nCIRs.  In other words, the generator would need to delist more CIRs than the portion the facility \ndesignated to serve the Co-Located Load on a firm basis.11\nVistra explained that this overly broad reading would be unduly discriminatory.  There is \nno principled basis to treat a secondary unit in a Co-Location Arrangement differently from a \ngenerator with a non-firm or recallable commitment to sell power outside of PJM where both types \nof generators comply with all capacity resource obligations, including the Day-Ahead Market \nmust-offer requirement.12  And as a matter of policy, there is no reason to ignore the valuable \ncontribution secondary units can make to resource adequacy.  Doing so would unnecessarily \ndeprive the PJM region of available capacity.13\n10 Vistra Protest at 9-11. \n11 Id. at 9-10. \n12 Id. at 11-12. \n13 Id. at 10, 12."},{"page":5,"startToken":1418,"endToken":1819,"text":"-5- \nIn the June 2026 Order, the Commission summarized some of Vistra’s arguments14 but did \nnot meaningfully respond to them.  It simply “disagree[d] with Vistra and Constellation that \ncapacity resources should not have to reduce their CIRs to serve Co-Located Load.”15  Its sole \nsupport for this conclusion was a cross-reference to its reasoning in an earlier section of the June \n2026 Order, where it had addressed Constellation’s argument—which was distinct from any of \nVistra’s arguments in critical ways.  Specifically, Constellation argued that a generator serving \nCo-Located Load should retain its CIRs if “PJM can verify that the Co-Located Load has no \ncontractual right to energy from the generator during a capacity emergency and that the Co-\nLocated Load has the ability either to curtail or draw on back-up power.”16  In that earlier section \nof the June 2026 Order, the Commission rejected Constellation’s argument, explaining that under \nthe scenario Constellation laid out, “the Co-Located Generator would not be capable of meeting \nits entire capacity requirement,” which includes the requirement to offer its energy into the Day-\nAhead Market throughout the delivery year.  It found that Constellation’s proposal would allow \nthe capacity resource to violate the must-offer requirement and thus provide an inferior capacity \nproduct for the same payment.17\n14 June 2026 Order, 195 FERC ¶ 61,209 at P 278 (“Vistra claims that PJM’s proposal would require existing \ngenerators to provide PJM with the amount of reduction to CIRs to facilitate the Co-Located Load configuration, \nwhich Vistra argues is vague and potentially overbroad because it could be read to require that generators include in \ntheir CIR reduction any portion of a facility that will ever provide power to a Co-Located Load.  Vistra and DCC \nexpress concern that PJM’s proposal could require generators to delist more CIRs than necessary.  Vistra further \ncontends that allowing secondary units to provide occasional, interruptible service to Co-Located Load and to retain \ntheir CIRs would be consistent with the Tariff.  Vistra and Constellation argue that capacity resources that serve Co-\nLocated Load on an interruptible basis should not be required to delist CIRs.” (internal citations omitted)).\n15 Id. P 288 (citing id. PP 159-162); see also id. P 279 (accepting PJM’s proposed revisions to its Necessary Study \nprocess in part).  The Commission rejected PJM’s proposed Form of Necessary Studies Agreement on different \ngrounds.  Id. P 288. \n16 Id. P 157.  \n17 Id. P 161."},{"page":6,"startToken":1819,"endToken":2125,"text":"-6- \nII.\nRequest for Clarification \nClarification of the June 2026 Order is necessary because it accepted unclear tariff \nlanguage and failed to explain how that tariff language applies to the issue Vistra raised in its \nprotest.  Specifically, the December 2025 Order found that existing generators need only delist \nCIRs “for the portion of the generating facility to be designated to serve any Co-Located Load that \nis not receiving NITS.”18  PJM’s compliance filing failed to account for this specific Commission \ndirective, instead generally leaving it to generators to submit “the amount of reduction to [CIRs] \nto facilitate the Co-Located Load configuration,”19 without specifying how that CIR reduction \nshould be calculated.  Rather than direct PJM to remedy that ambiguity in a manner consistent \nwith the December 2025 Order, the Commission accepted PJM’s vague language and did not \nrespond to the nuances of how that language should apply.  \nPJM’s tariff revisions—and the Commission order accepting them—are ambiguous on the \ncritical point of how customers should calculate the reduction in CIRs.  PJM’s tariff language risks \nbeing interpreted far too broadly, to require an Interconnection Customer to delist the CIRs for a \ncapacity resource that is capable of meeting both the emergency performance and the Day-Ahead \nMarket must-offer requirements, and that provides secondary, interruptible service to a Co-\nLocated Load only when the unit is not committed in PJM’s energy market.  Vistra respectfully \nrequests that the Commission clarify that PJM’s tariff revisions should not be read in that manner.  \nThe Commission should clarify that an Interconnection Customer is not required to delist the \n18 December 2025 Order, 193 FERC ¶ 61,217 at P 230 (emphasis added). \n19 PJM Transmittal Letter at 26; PJM, Open Access Transmission Tariff, pt. VIII, subpt. A, § 401 (5.0.0), \n§ H(3)(b)(i)(c); id. pt. IX, subpt. G, attach. 1."},{"page":7,"startToken":2125,"endToken":2401,"text":"-7- \nportion of the CIRs that meet the specifications described above when implementing a Co-\nLocation Arrangement.   \nAs discussed below, Vistra’s requested interpretation is consistent with the December 2025 \nOrder.  It is also consistent with the rest of the PJM tariff.  Moreover, allowing this ambiguity to \npersist (or adopting a contrary interpretation) would be unjust and unreasonable and unduly \ndiscriminatory or preferential.  \nA. Vistra’s Requested Clarification Is Consistent With the December 2025 Order \nand the Reasoning in the June 2026 Order  \nThe Commission’s December 2025 Order set a clear standard: an existing generator must \ndelist CIRs “for the portion of the generating facility to be designated to serve any Co-Located \nLoad that is not receiving NITS.”20  PJM’s compliance proposal did not clearly implement that \nstandard.   \nTo “designate” something is “to indicate and set [it] apart for a specific purpose, office, or \nduty.”21  In the configuration Vistra described in its protest, a portion of the generating facility is \nclearly “set apart for [the] specific purpose” of serving the Co-Located Load.  The remainder of \nthe facility is not.  The facility will continue offering the remaining generation into the Day-Ahead \nMarket and injecting power onto the PJM grid when it receives a Day-Ahead Market award.  \nAccordingly, the remaining capacity is not “designated” to serve the Co-Located Load, which \nmeans that under the December 2025 Order, it need not delist its CIRs. \n20 December 2025 Order, 193 FERC ¶ 61,217 at P 230 (emphasis added). \n21 Designate, Merriam-Webster, https://www.merriam-webster.com/dictionary/designate (last visited July 20, \n2026); accord Designate, Black’s Law Dictionary (12th ed. 2024) (“To choose (someone or something) for a particular \njob or purpose.”)."},{"page":8,"startToken":2401,"endToken":2680,"text":"-8- \nThe Commission’s June 2026 Order did not address this issue.  Rather, it addressed \nConstellation’s (different) argument that a capacity resource serving Co-Located Load that can \nsupply power to the grid during emergencies should not be required to delist its CIRs.  The \nCommission’s reason for rejecting Constellation’s argument was that such a resource would be \nincapable of meeting its Day-Ahead Market must-offer obligation.22  That reasoning simply does \nnot apply to the scenario Vistra presented, where the secondary, interruptible unit would meet its \nDay-Ahead Market must-offer obligation and would only serve Co-Located Load if doing so did \nnot conflict with its commitment in PJM’s market (and would only do so as backup to the primary \nunit which is designated to serve the Co-Located Load).  The Commission should clarify that these \ntypes of secondary units—that meet Day-Ahead Market must-offer requirements—should retain \ntheir CIRs. \nB. Clarification Will Ensure that the PJM Tariff Is Just and Reasonable and Not \nUnduly Discriminatory or Preferential \nVistra’s requested clarification will ensure compliance with the FPA.  As Vistra explained \nin its protest, requiring a secondary, interruptible unit that serves Co-Located Load only when it is \nnot committed in PJM’s market (and only when the primary unit is not serving the Co-Located \nLoad) to delist its CIRs would be unjust and unreasonable and unduly discriminatory or \npreferential.23\nPJM already permits a class of resources with non-firm, non-network commitments to \nparticipate as capacity resources: generators with a non-firm or recallable commitments to external \nsales of capacity.  While the tariff excuses capacity resources with firm commitments to external \n22 See June 2026 Order, 195 FERC ¶ 61,209 at P 161. \n23 16 U.S.C. § 824"},{"page":9,"startToken":2680,"endToken":3042,"text":"-9- \nsales of their capacity from the capacity market must-offer requirement,24 it does not excuse \ncapacity resources with non-firm or recallable commitments to external sales from that \nrequirement.25  The tariff thus recognizes that firm external sales pose unique concerns for meeting \ncapacity market commitments, while non-firm or recallable external sales do not: generators with \nnon-firm or recallable external sale commitments can be expected to perform normally in the \ncapacity market.  The same distinction applies here.  Primary units that provide firm energy to a \nCo-Located Load clearly cannot also meet the obligations of PJM capacity resources, but \nsecondary units that provide interruptible, backup energy to a Co-Located Load can.  \nThere is no principled basis to treat a secondary, interruptible unit in a Co-Location \nArrangement differently from an external resource with a non-firm capacity commitment.  Like \ngenerators with non-firm or recallable external sale commitments, secondary interruptible units \ncan fulfill capacity resource obligations.26  Accordingly, the two classes of generators are similarly \nsituated with respect to their ability to serve as capacity resources.  Subjecting the two categories \nto different rules—specifically, allowing one to maintain CIRs while requiring the other to delist \nthem—would amount to undue discrimination.  \nFurther, it would be unjust and unreasonable to require a secondary, interruptible unit \nserving Co-Located Load only when not committed in PJM’s market (and only when the primary \nunit is not serving the Co-Located Load) to delist its CIRs to implement a Co-Location \n24 See Vistra Protest at 10 (citing PJM, Open Access Transmission Tariff, attach. DD.6, § 6.6 (Offer Requirement \nfor Capacity Resources) (3.0.0), §§ 6.6(a), (g); PJM Interconnection L.L.C., Constellation Request for Clarification \nor, in the Alternative, Rehearing, Docket Nos. EL25-49-000, et al., at 4 (filed Jan. 20, 2026)). \n25 See id. at 10-11 (citing PJM Interconnection, L.L.C., Mot. for Leave to Answer & Answer of PJM, Docket No. \nEL25-49-000, at 6 (filed Mar. 9, 2026)). \n26 See also PJM Interconnection, L.L.C., 190 FERC ¶ 61,088, at P 47 (2025) (accepting PJM proposal to account \nfor reliability must-run resources as capacity resources because they “can reasonably be expected to perform, similar \nto capacity resources”)."},{"page":10,"startToken":3042,"endToken":3317,"text":"-10- \nArrangement.  Just like resources with non-firm external capacity commitments, this type of \nsecondary unit would be fully capable of meeting PJM’s capacity commitment requirements—\nincluding both the emergency performance requirement and the Day-Ahead Market must-offer \nobligation.   \nRequiring that secondary, interruptible unit to delist its CIRs would deprive the PJM \ncapacity market of available capacity for no conceivable reason.27  For the vast majority of hours, \nthe secondary, interruptible unit could offer into the Day-Ahead Market and provide energy when \neconomic.  In the remaining hours, the secondary, interruptible unit could offer into the Day-Ahead \nMarket with an offer that reasonably reflects its non-firm commitment to the Co-Located Load \nsuch that the unit would be available to the system during emergencies.  Such a resource has all \nthe hallmarks of a capacity resource.  It is patently unjust and unreasonable to deprive the capacity \nmarket of such a resource at a time when capacity market supply is tight, demand is rising, and \nPJM and the Commission face unprecedented pressure to address rising prices.28\nIn addition, forcing the secondary unit to delist its CIRs would disincentivize the Co-\nLocated Load from providing demand response to the grid.  Because the Co-Located Load would \nhave to pay for the secondary unit’s capacity, there would be no reason for the Co-Located Load \nto choose to switch to its own back-up generator and make the secondary unit’s capacity available \nto the grid. \n* * * \n27 See PJM Interconnection, L.L.C., 190 FERC ¶ 61,088 at P 47 (finding that including reliability must-run \nresources in the capacity market supply stack would “reflect the actual availability of resources in the PJM Region”). \n28 See id."},{"page":11,"startToken":3317,"endToken":3596,"text":"-11- \nThe Commission should grant clarification that secondary, interruptible units in the \nscenario Vistra has outlined are not required to delist their CIRs.  This clarification would comport \nwith the December 2025 Order, and it would ensure that the PJM tariff remains just and reasonable \nand not unduly discriminatory or preferential. \nIII.\nAlternative Request for Rehearing \nTo the extent the Commission denies the clarification Vistra seeks above, Vistra requests \nrehearing of the June 2026 Order.  In the absence of Vistra’s requested clarification, the \nCommission’s decision in the June 2026 Order was arbitrary, capricious, and otherwise not in \naccordance with law for three reasons.29  First, the Commission failed to respond to any of the \nobjections Vistra raised on this issue in its protest.  Second, the Commission erred in accepting a \nproposal that failed to comply with the Commission’s directive to “clarify” procedures for entering \nCo-Location Arrangements.  Third, the Commission erred in accepting PJM’s proposal because it \nis unjust and unreasonable and unduly discriminatory or preferential in violation of the Federal \nPower Act to the extent it requires secondary, interruptible units to delist their CIRs.  For those \nreasons, the Commission’s acceptance of PJM’s proposal violated its obligation to engage in \nreasoned decisionmaking and its duty under the FPA to ensure that the rates, terms, and conditions \nof transmission service are just and reasonable and not unduly discriminatory.  To remedy these \nflaws, the Commission should grant rehearing and direct PJM to revise its tariff to specify that a \nsecondary, interruptible unit serving a Co-Located Load only when not committed in PJM’s \nmarkets is not required to delist its CIRs to implement a Co-Location Arrangement. \n29 5 U.S.C. § 706(2)(A)."},{"page":12,"startToken":3596,"endToken":4000,"text":"-12- \nA. The Commission’s Failure to Respond to Vistra’s Objections Was Arbitrary and \nCapricious \nThe June 2026 Order does not reflect the type of reasoned decisionmaking required by the \nAdministrative Procedure Act.30  “It is well established” that the Administrative Procedure Act’s \nreasoned decisionmaking standard means that the “Commission must respond meaningfully to the \narguments raised before it.”31  In responding to those arguments, the Commission may not “fail[] \nto consider an important aspect of the problem” it addresses.32  The June 2026 Order summarily \ndismissed Vistra’s arguments, without responding to them, by citing an inapposite discussion \nabout an entirely distinct argument.  That is squarely in the zone of arbitrary and capricious \naction.33\nAs detailed above,34 Vistra’s protest raised four distinct arguments about PJM’s proposal \nregarding reduction of CIRs.  First, Vistra argued that PJM’s vague tariff language did not meet \nthe directive in the December 2025 Order to “clarify” its interconnection procedures and \nagreements to ensure that existing generators know how to enter a Co-Location Arrangement.35\nRather than provide clarity, PJM’s proposal introduced ambiguity as to how CIR reductions should \n30 See Motor Vehicle Mfrs. Ass’n v. State Farm Mutual Automobile Ins. Co., 463 U.S. 29, 43-44 (1983) (“State \nFarm”); Michigan v. EPA, 576 U.S. 743, 750 (2015). \n31 New England Power Generators Ass’n v. FERC, 881 F.3d 202, 210 (D.C. Cir. 2018) (cleaned up) (citing \nTransCanada Power Mktg. Ltd. v. FERC, 811 F.3d 1, 12 (D.C. Cir. 2015); Pub. Serv. Comm’n of Ky. v. FERC, 397 \nF.3d 1004, 1008 (D.C. Cir. 2005)); Canadian Ass’n of Petroleum Producers v. FERC, 254 F.3d 289, 299 (D.C. Cir. \n2001) (“Unless the Commission answers objections that on their face seem legitimate, its decision can hardly be \nclassified as reasoned.”). \n32 Del. Div. of Pub. Advoc. v. FERC, 3 F.4th 461, 469 (D.C. Cir. 2021) (citing State Farm, 463 U.S. at 43).  \n33 See New England Power Generators Ass’n, 881 F.3d at 211 (“FERC’s responses to Petitioners' arguments \nbelow amounted to conclusory statements that dismissed Petitioners’ concerns without providing reasoned analysis.”); \nTransCanada Power Mktg., 811 F.3d at 12 (finding that Commission order that “simply never addressed the matter” \nraised by a party, and instead provided a “perplexing response” that did not actually address the party’s concern, was \narbitrary and capricious).\n34 See supra Part I. \n35 Vistra Protest at 9-11."},{"page":13,"startToken":4000,"endToken":4311,"text":"-13- \nbe calculated.  Second, Vistra argued that requiring secondary, interruptible units that can meet the \nDay-Ahead Market must-offer requirement to delist their CIRs would be unduly discriminatory, \ntreating those units differently from similarly situated capacity resources with non-firm or \nrecallable commitments to sell power outside of PJM.36  Third, Vistra argued that allowing such \nsecondary, interruptible units to maintain their CIRs is consistent with provisions of the PJM tariff \ndistinguishing between generators with firm versus non-firm external capacity commitments for \npurposes of capacity market must-offer obligations.37  Fourth, Vistra argued that requiring \nsecondary, interruptible units that can meet the Day-Ahead Market must-offer requirement to delist \ntheir CIRs would deprive ratepayers of generation that is generally available and could increase \ncapacity prices.38\nThe Commission did not respond to a single one of these objections.  It simply stated that \nit “disagree[d] with Vistra and Constellation that capacity resources should not have to reduce their \nCIRs to serve Co-Located Load.”39  As a threshold matter, Vistra did not argue in its protest that \ncapacity resources, writ large, should not have to reduce their CIRs to serve Co-Located Load.40\nThe Commission’s only support for this “conclusory statement”41 was its cross-reference \nto an irrelevant discussion addressing Constellation’s request for rehearing of the December 2025 \nOrder.  In that irrelevant discussion, the Commission found that a resource that “would not be \ncapable of meeting its entire capacity requirement,” including both its emergency performance \n36 Vistra Protest at 11-12. \n37 Id. at 10-11. \n38 Id. at 10, 12. \n39 June 2026 Order, 195 FERC ¶ 61,209 at P 288. \n40 See TransCanada Power Mktg., 811 F.3d at 12 (finding that a Commission order was arbitrary and capricious \nwhere it did not actually address the concern raised in a comment it claimed to address). \n41 New England Power Generators Ass’n, 881 F.3d at 211."},{"page":14,"startToken":4311,"endToken":4589,"text":"-14- \nrequirement and its Day-Ahead Market must-offer requirement, must delist its CIRs to serve Co-\nLocated Load.42  The Commission’s reasoning there does not address Vistra’s protest because \nVistra raised the issue with regards to a capacity resource that can meet both the emergency and \nits Day-Ahead Market obligations.   \nBy declining to engage with or respond to Vistra’s objections, and by instead citing \nreasoning addressing a distinct issue, the Commission failed to “respond meaningfully to the \narguments raised before it.”43  And in doing so, the Commission also entirely failed to consider \nseveral important aspects of the issues the June 2026 Order addressed.44\nB. PJM’s Tariff Revisions Do Not Satisfy the Directive to “Clarify” its \nInterconnection Procedures \nIn accepting PJM’s tariff revisions, the Commission departed from its directive in the \nDecember 2025 Order to “clarify” its interconnection procedures.  The Commission must \nacknowledge and provide a reasoned explanation for a change in position.45  Because the \nCommission failed to do so here, it erred in accepting PJM’s proposal. \nThe fundamental problem that the Commission ordered PJM to remedy in the December \n2025 Order was the tariff’s failure to address “with sufficient clarity or consistency” the rates, \nterms, and conditions of service applicable to interconnection customers serving Co-Located Load.  \nThese defects left customers “unable to determine what steps they must take to effectuate Co-\nLocation Arrangements,” leading to “uncertainty,” “disparate treatment,” and “no consistent \n42 June 2026 Order, 195 FERC ¶ 61,209 at P 161. \n43 New England Power Generators Ass’n, 881 F.3d at 210. \n44 See State Farm, 463 U.S. at 43. \n45 See FCC v. Fox Television Stations, Inc., 556 U.S. 502, 515-16 (2009)."},{"page":15,"startToken":4589,"endToken":4865,"text":"-15- \nunderstanding” of customers’ responsibilities.46  The Commission thus directed PJM to “clarify its \ninterconnection procedures and agreements to ensure that it is clear to both new and existing \nInterconnection Customers how to interconnect in a Co-Location Arrangement.”47\nAs discussed above, PJM’s tariff language governing reduction of CIRs does not satisfy \nthis directive.48  It continues to leave customers in the dark about how to calculate the CIR \nreduction necessary to effectuate Co-Location Arrangements.  Indeed, this vague language risks \nbeing read far too broadly, to require generators to include in their CIR reduction calculation even \nthe CIRs associated with a secondary, interruptible unit, an unjust and unreasonable and unduly \ndiscriminatory result.49  In other words, the lack of clarity in the tariff will lead to precisely the \ntypes of problems the December 2025 Order told PJM to fix: uncertainty, disparate treatment, and \ninconsistent understandings of customers’ responsibilities.   \nElsewhere in the June 2026 Order, the Commission rejected PJM’s proposed tariff \nprovisions when they contained insufficient detail to provide clarity to customers to ensure that \nrates would be just and reasonable and not unduly discriminatory or preferential.50  But PJM’s \ntariff provisions addressing CIR reductions suffer from the same defect.  The Commission \ntherefore erred in not directing PJM to address that defect with respect to CIRs.51\n46 December 2025 Order, 193 FERC ¶ 61,217 at P 159. \n47 December 2025 Order, 193 FERC ¶ 61,217 at P 161. \n48 See supra section II.A.  \n49 See supra section II. \n50 See June 2026 Order, 195 FERC ¶ 61,209 at PP 283, 370; cf. id. P 280. \n51 See Fox Television Stations, 556 U.S. at 515-16."},{"page":16,"startToken":4865,"endToken":5176,"text":"-16- \nC. It Is Unjust and Unreasonable and Unduly Discriminatory to Require a \nSecondary, Interruptible Unit to Delist its CIRs \nThe FPA requires the Commission to ensure that rates, terms, and conditions for \njurisdictional services are just and reasonable and not unduly discriminatory or preferential.52  The \nCommission erred when it accepted PJM’s proposed tariff provisions because they violate that \nfoundational standard.  \nAs Vistra has explained, requiring a secondary, interruptible unit serving Co-Located Load \nonly when not committed in PJM’s market (and only when the primary unit is not serving the Co-\nLocated Load) to delist its CIRs to implement a Co-Location Arrangement is unjust and \nunreasonable and unduly discriminatory or preferential, in violation of the FPA.  \nFirst, as explained above,53 it is unduly discriminatory for PJM to require secondary, \ninterruptible units to delist their CIRs.  The PJM tariff permits generators with non-firm, recallable \nexternal sale commitments to serve as capacity resources.54  There is no principled distinction \nbetween those resources and secondary, interruptible units that would justify prohibiting \nsecondary, interruptible units from also serving as capacity resources.  Both types of generators \nare similarly situated with respect to their ability to fulfill all capacity resource obligations and \ntheir ability to perform when needed.55  Subjecting them to different rules—specifically, allowing \none to maintain CIRs but requiring the other to delist them—is impermissible undue \ndiscrimination. \n52 16 U.S.C. §§ 824d(a), 824d(b), 824e(a). \n53 See supra section II.B. \n54 See Vistra Protest at 10-11 (citing PJM Interconnection, L.L.C., Mot. for Leave to Answer & Answer of PJM, \nDocket No. EL25-49-000, at 6 (filed Mar. 9, 2026)). \n55 See PJM Interconnection, L.L.C., 190 FERC ¶ 61,088 at P 47 (accepting PJM proposal to account for reliability \nmust-run resources as capacity resources because they “can reasonably be expected to perform, similar to capacity \nresources”)."},{"page":17,"startToken":5176,"endToken":5442,"text":"-17- \nSecond, as explained above,56 it is unjust and unreasonable to require a secondary, \ninterruptible unit serving Co-Located Load only when not committed in PJM’s market (and only \nwhen the primary unit is not serving the Co-Located Load) to delist its CIRs to implement a Co-\nLocation Arrangement.  This unit would be fully capable of meeting all of the performance \nrequirements applicable to a capacity resource—including both the emergency performance \nrequirement and the Day-Ahead Market must-offer obligation.  Requiring it to delist its CIRs \nwould deprive the PJM capacity market of available capacity at a time when PJM has no capacity \nto spare.  Doing so would deprive the generation resource owner of its ability to provide capacity \nto PJM—and harm resource adequacy in PJM—for no conceivable reason, resulting in unjust and \nunreasonable rates.\nIV.\nConclusion \nAt a time when PJM’s capacity market is increasingly tight on supply, demand is rising \nrapidly, and PJM and the Commission face an affordability imperative, there is no reason to ignore \nthe valuable contributions that secondary, interruptible units can make to resource adequacy and \nto affordability.  Prohibiting these resources from supplying capacity to the PJM grid, when there \nis no technical or commercial limit on their ability to do so, will force PJM to procure unnecessary \ncapacity.  \nThe Commission can readily prevent that outcome by granting clarification on the narrow \nissue Vistra presents.  Thus, the Commission can and should grant clarification that PJM’s tariff \nshould not be read to require an Interconnection Customer to delist the CIRs of a unit that provides \n56 See supra section II.B."},{"page":18,"startToken":5442,"endToken":5625,"text":"-18- \nsecondary, interruptible service to a Co-Located Load only when it is not committed in PJM’s \nenergy market. \nIn the alternative, the Commission should grant rehearing of its acceptance of PJM’s tariff \nrevisions regarding CIR reductions in the June 2026 Order.  For the reasons discussed above, \nrequiring such a unit to delist its CIRs would be unjust and unreasonable and unduly \ndiscriminatory.  Accordingly, the Commission should grant rehearing and direct PJM to revise its \ntariff to specify that a secondary, interruptible unit serving a Co-Located Load only when not \ncommitted in PJM’s markets is not required to delist its CIRs to implement a Co-Location \nArrangement. \nRespectfully submitted, \n/s/ J. Arnold Quinn\nJ. Arnold Quinn\nSVP of Regulatory Policy \nAndrew Weinstein\nVice President, FERC Market Policy\nVistra Corp.\n325 7th Street NW\nSuite 520\nWashington, DC 20004\narnie.quinn@vistracorp.com \nandrew.weinstein@vistracorp.com\n________________\nNicholas M. Gladd\nSarah Greenberg\nRachel Neuburger\nWilson Sonsini Goodrich & Rosati\n1700 K Street NW\nFifth Floor\nWashington, DC 20006\n(617) 598-7871\nngladd@wsgr.com\nsgreenberg@wsgr.com\nrneuburger@wsgr.com\nCounsel for Vistra Corp.\nDated:  July 20, 2026"},{"page":19,"startToken":5625,"endToken":5682,"text":"CERTIFICATE OF SERVICE\nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service lists compiled by the Secretary of the Commission in these \nproceedings. \nDated:  July 20, 2026 \nWashington, D.C. \n/s/ Rachel Neuburger \nWilson Sonsini Goodrich & Rosati \n1700 K Street NW \nFifth Floor \nWashington, DC 20006"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":5,"startToken":0,"endToken":836},{"p":3,"at":5,"title":"I. Background","method":"printed heading","endPage":6,"endAt":5,"startToken":836,"endToken":1820},{"p":6,"at":5,"title":"II. Request for Clarification","method":"printed heading","endPage":7,"endAt":440,"startToken":1820,"endToken":2187},{"p":7,"at":440,"title":"A. Vistra’s Requested Clarification Is Consistent With the December 2025 Order","method":"printed heading","endPage":8,"endAt":961,"startToken":2187,"endToken":2545},{"p":8,"at":961,"title":"B. Clarification Will Ensure that the PJM Tariff Is Just and Reasonable and Not","method":"printed heading","endPage":11,"endAt":342,"startToken":2545,"endToken":3367},{"p":11,"at":342,"title":"III. Alternative Request for Rehearing","method":"printed heading","endPage":12,"endAt":6,"startToken":3367,"endToken":3597},{"p":12,"at":6,"title":"A. The Commission’s Failure to Respond to Vistra’s Objections Was Arbitrary and","method":"printed heading","endPage":14,"endAt":680,"startToken":3597,"endToken":4415},{"p":14,"at":680,"title":"B. PJM’s Tariff Revisions Do Not Satisfy the Directive to “Clarify” its","method":"printed heading","endPage":16,"endAt":6,"startToken":4415,"endToken":4866},{"p":16,"at":6,"title":"C. It Is Unjust and Unreasonable and Unduly Discriminatory to Require a","method":"printed heading","endPage":17,"endAt":864,"startToken":4866,"endToken":5312},{"p":17,"at":864,"title":"IV. Conclusion","method":"printed heading","endPage":19,"endAt":0,"startToken":5312,"endToken":5625},{"p":19,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":19,"endAt":366,"startToken":5625,"endToken":5682}]}