{"document":{"slug":"rec-20260720-5180","title":"Exelon Corporation and FirstEnergy Service Company submit Request for Rehearing of the 06/18/2026 Order","issued":"2026-07-20","accession":"20260720-5180","docket":"ER26-1479-001","group":"PJM co-location compliance","filer":"Exelon CorporationThe FirstEnergy Transmission Companies","kind":"rehearing request","file":"sources/filings/text/20260720-5180_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260720-5180","tier":"record","sha256":"d5fec07de81e3c826a5153ca6285f2f403d46686e0a884ad80f962fd1932ad57","pages":43,"tokens":15731,"emptyPages":[],"textThemes":["colo","study","cost","flex"]},"pages":[{"page":1,"startToken":0,"endToken":264,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C., et al. \n \n) \nDocket No. EL25-49-002 \nDocket No. EL25-49-000 \n \nLarge Loads Co-Located at Generating \nFacilities \n) \nDocket No. AD24-11-001 \nConstellation Energy Generation, LLC \n \nv. \n \nPJM Interconnection, L.L.C. \n \nPJM Interconnection, L.L.C. \n) \n \n) \n \n) \n \n) \nDocket No. EL25-20-001 \n(consolidated) \n \n \n \n \nDocket No. ER26-1479-000 \n \n \nREQUEST FOR REHEARING OF EXELON CORPORATION AND  \nFIRSTENERGY SERVICE COMPANY \n \nPursuant to Federal Power Act (“FPA”) section 3131 and Rule 7132 of the Rules of Practice \nand Procedure of the Federal Energy Regulatory Commission (“FERC” or “Commission”),  \nExelon Corporation3 and FirstEnergy Service Company4 (together “Exelon and FirstEnergy”) \nrequest rehearing of the Commission’s ruling that extends the new forms of transmission service \nthat were ordered for Co-Located Load to also be made available to load served by Behind-the-\nMeter Generation (“BTMG”).5 The Commission’s June 18, 2026 Order determination that new \n \n1  \n16 U.S.C. § 825l(a). \n2  \nSee 18 C.F.R. § 385.713. \n3  \nExelon Corporation submits this rehearing request on behalf of its affiliates Atlantic City Electric Company, \nBaltimore Gas and Electric Company, Commonwealth Edison Company (“ComEd”), Commonwealth Edison \nCompany of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and Potomac Electric \nPower Company \n4  \nFirstEnergy Service Company submits this rehearing request as agent for its affiliates American Transmission \nSystems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, \nKeystone Appalachian Transmission Company, The Potomac Edison Company, Monongahela Power Company \nand Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Transmission Companies”). \n5  \nPJM Interconnection, L.L.C., 195 FERC ¶ 61,209 (2026) (“June 18, 2026 Order”)."},{"page":2,"startToken":264,"endToken":588,"text":"2 \n \ntransmission service options must be provided for load served by BTMG are arbitrary and \ncapricious and not based upon reasoned decision making.  \nThe June 18, 2026 Order addressed rehearing requests relating to the Commission’s \nDecember 18, 2025 Order6 in this proceeding, concerning the Commission’s determination that \nthe existing Network Service in the PJM Tariff is unjust and unreasonable for service to Co-\nLocated Load and requiring that three new forms of service be made available for Co-Located \nLoad: Firm Contract Demand Network Service (“FCD”); Non-Firm Contract Demand Network \nService (“NFCD”); and Interim Network Service. Exelon and FirstEnergy sought rehearing of that \norder on January 16, 2026, which rehearing request was denied by operation of law when the \nCommission did not rule by February 17, 2026. Exelon and FirstEnergy have submitted Petitions \nfor Review in the Third Circuit Court of Appeals on the issues where their rehearing was rejected.7 \nThe June 18, 2026 Order does not alter the Commission’s finding on the issues pending in Exelon \nand FirstEnergy’s submitted petitions for review; Exelon and FirstEnergy are not addressing those \nissues further here, and the issues are instead before the Third Circuit.  \nIn addition to rejecting Exelon and FirstEnergy’s rehearings of the December 18, 2025 \nOrder, the June 18, 2026 Order made certain new findings relating to BTMG. In the June 18, 2026 \nOrder, the Commission erroneously extended the availability of its new FCD, NFDC, and Interim \nNetwork Service offerings to loads served by BTMG. This rehearing addresses only the extension \nof the new service options to load served by BTMG.  \nIn addition to addressing rehearings, the June 18, 2026 Order also addressed filings that \nwere made in compliance with the December 18, 2025 Order in order to implement the new forms \n \n6  \nPJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025) (“December 18, 2025 Order”). \n7  \nExelon Corp., Case No. 26-1901 (3rd Cir.); American Transmission Systems, Inc., Case No. 26-2494 (3rd Cir.)."},{"page":3,"startToken":588,"endToken":927,"text":"3 \n \nof transmission service. This rehearing does not address the compliance issues in the June 18, \n2026 Order which Exelon and FirstEnergy are instead addressing in other pleadings.  \nTo be clear, the purported purpose of the Commission’s rulings at issue here is to improve \nthe availability of service to new BTMG-served customers and ensure that service to such \ncustomers does not impose unnecessary costs on existing customers. But the creation of these new \nforms of transmission service will not hasten or improve service and instead merely reduces \ntransmission charges for BTMG-served customers at the expense of other customers. The \nCommission’s order does not resolve any actual inadequacy in the PJM Tariff and instead is merely \nan unreasonable and unduly preferential gift to a favored class. \n \nI. \nStatement of Issues/Specification of Error. \nIn accordance with 18 C.F.R. § 385.713(c)(1) and (2), Exelon and FirstEnergy provide the \nfollowing specification of errors and statement of issues, including citations to representative \nCommission and judicial precedent. \n1. The Burden Under FPA Section 206 Has Not Been Met: The Existing Rate Has \nNot Been Shown to Be Unjust and Unreasonable. See 16 U.S.C. § 824e(a); Pub. \nCitizen, Inc. v. FERC, 7 F.4th 1177, 1183 (D.C. Cir. 2021) (explaining that “[t]he \nburden of proving” that a rate is unjust or unreasonably is placed on “the party that \ninitiated the proceeding”). \na. There is No Evidence In the Record That Loads Served by BTMG Are \nUnable to Obtain Reliable, Timely, and Reasonably Priced Service \nUsing the Existing Network Service Construct. Therefore, the \nCommission \nFails \nTo \nSatisfy \nthe \nRequirement \nUnder \nthe \nAdministrative Procedure Act That Its Decision Be Supported With \nSubstantial Evidence. \ni. The Administrative Procedure Act (“APA”) requires the \nCommission to “examine the relevant data and articulate a \nsatisfactory explanation for its action including a ‘rational \nconnection between the facts found and the choice made,’” and \nto base its decision on substantial evidence; because FERC has \nfailed to do so, its decision is arbitrary and capricious. Motor"},{"page":4,"startToken":927,"endToken":1337,"text":"4 \n \nVehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co. (“State \nFarm”), 463 U.S. 29, 43 (1983) (citation omitted); see Fla. Gas \nTransmission Co. v. FERC (“Florida Gas”), 604 F.3d 636, 639 \n(D.C. Cir. 2010) (“[T]he Commission ‘must be able to demonstrate \nthat it has made a reasoned decision based upon substantial evidence \nin the record.’”) (citation omitted); Consol. Edison Co. of N.Y. v. \nNLRB, 305 U.S. 197, 229 (1938) (explaining that substantial \nevidence means “more than a mere scintilla”); see also 5 U.S.C. \n§ 706. \nii. The PJM Tariff provides two transmission service options \n(Network Integration Transmission Service and Point-to-Point \nTransmission Service) and includes provisions to explain how \nthose services work and how Network Customers will be Served. \nSee PJM Tariff at §§ 31.1, 31.2, 31.3, 31.6 and 32; see also generally \nPJM Tariff , OATT Definitions. \niii. To the extent that parties have argued they are unable to \ninterconnect or are experiencing delays, that is false and any \ndelay is of their own making. See, e.g., Exelon Dec. 8, 2025 \nComments at 3-4; Complaint Requesting Fast Track Processing of \nConstellation Energy Generation, LLC, Docket No. EL25-20, at Ex. \n5 Attach 1 (providing Exelon’s Nov. 12, 2024 Letter). FERC \narbitrarily and capriciously disregarded evidence in the record \nthat Network Service under the current tariff is feasible and has \nbeen used for co-location arrangements. Compare PJM \nInterconnection, L.L.C., 189 FERC ¶ 61,078 (2024) and PJM \nInterconnection, L.L.C., Docket No. ER24-2172-000, Application \nAttach. A, Amended ISA, at Schedule F, Part F.4 (June 1, 2024), \nwith Press Release, Talen Energy, Talen Energy Expands Nuclear \nEnergy \nRelationship \nwith \nAmazon \n(June \n11, \n2025), \nhttps://ir.talenenergy.com/news-releases/news-release-\ndetails/talen-energy-expands-nuclear-energy-relationship-amazon. \nSee also Exelon Dec. 8, 2025 Comments at 6. \niv. Ignoring data in the record regarding the ability of large loads \nto interconnect to the transmission system violates the APA and \nrenders FERC’s decision arbitrary and capricious. See State \nFarm, 463 U.S. at 43. \nv. There is no evidence in the record that the cost of Network \nService adversely impacts loads served by BTMG. Nor is there \nevidence to support that existing Network Service imposes \nunnecessary upgrades on all customers. Nor is there evidence \nthat new forms of transmission service will allow for faster \ninterconnection. See Florida Gas, 604 F.3d at 639 (“[T]he \nCommission ‘must be able to demonstrate that it has made a"},{"page":5,"startToken":1337,"endToken":1808,"text":"5 \n \nreasoned decision based upon substantial evidence in the record.’”) \n(citation omitted); Consol. Edison Co. of N.Y., 305 U.S. at 229 \n(explaining that substantial evidence means “more than a mere \nscintilla”); see also 5 U.S.C. § 706. \nvi. The Commission has not met its burden under FPA section 206 \nbecause it acknowledges that the existing transmission services \nremain just and reasonable options. See June 18, 2026 Order, 195 \nFERC ¶ 61,209 at P 195 (finding Network Service charged on a \ngross demand basis to be “one just and reasonable transmission \nservice option”). \nb. The Commission Did Not Engage in Reasoned Decision Making \nBecause It Did Not Explain its Departure from FERC Precedent \nRegarding the Reasonableness of the Existing Network Service. See \nF.C.C. v. Fox Television Stations, Inc., 556 U.S. 502, 515 (2009) (“[T]he \nrequirement that an agency provide reasoned explanation for its action \nwould ordinarily demand that it display awareness that it is changing \nposition. An agency may not, for example, depart from a prior policy sub \nsilentio or simply disregard rules that are still on the books.”); New England \nPower Generators Ass’n v. FERC, 881 F.3d 202, 211 (D.C. Cir. 2018) \n(“Although case-by-case adjudication sometimes results in decisions that \nseem at odds but can be distinguished on their facts, it is the agency’s \nresponsibility to provide a reasoned explanation of why those facts \nmatter.”); W. Deptford Energy, LLC v. FERC, 766 F.3d 10, 20 (D.C. Cir. \n2014) (“It is textbook administrative law that an agency must ‘provide[ ] a \nreasoned explanation for departing from precedent or treating similar \nsituations differently,’ and Commission cases are no exception.”) (citations \nomitted); Cal. Pub. Utils. Comm’n v. FERC, 879 F.3d 966, 977 (9th Cir. \n2018) (“FERC departed from this policy without acknowledgment or \nexplanation. This departure was arbitrary and capricious.”); Sw. Airlines \nCo. v. FERC, 926 F.3d 851, 856 (D.C. Cir. 2019) (“‘A full and rational \nexplanation’ becomes ‘especially important’ when, as here, an agency \nelects to ‘shift [its] policy’ or ‘depart[ ] from its typical manner of’ \nadministering a program. . . . [FERC] must at least ‘acknowledge’ its \nseemingly inconsistent precedents and either offer a reason ‘to distinguish \nthem’ or ‘explain its apparent rejection of their approach’ . . . . But however \nthe agency justifies its new position, what it may not do is ‘gloss[ ] over or \nswerve[ ] from prior precedents without discussion.’”) (most alterations in \noriginal) (citations omitted); see also 16 U.S.C. § 824d(b) (prohibiting a \npublic utility from making or granting an “undue preference or advantage” \nor from maintaining “any unreasonable difference in rates, charges, service, \nfacilities, or in any other respect, . . . as between classes of service”); \nTransCanada Power Mktg. Ltd. v. FERC, 811 F.3d 1, 12–13 (D.C. Cir. \n2015) (remanding because FERC did not adequately explain its position)."},{"page":6,"startToken":1808,"endToken":2289,"text":"6 \n \ni. The Commission has a long-standing policy of rejecting \nattempts by network transmission customers to avoid paying \ntheir load ratio share of system cost. See, e.g., Nat’l R.R. \nPassenger Corp. v. PPL Elec. Utils. Corp., 171 FERC ¶ 61,237 at \nPP 40–41, denying clarification & addressing arguments raised on \nreh’g, 173 FERC ¶ 61,043 at PP 13–14 (2020); see Promoting \nWholesale Competition Through Open Access Non-Discriminatory \nTransmission Services by Public Utilities; Recovery of Stranded \nCosts by Public Utilities and Transmitting Utilities, Order No. 888-\nA, FERC Stats. & Regs. ¶ 31,048, 62 Fed. Reg. 12,274, 12,324 \n(Mar. 14, 1997), order on reh’g, Order No. 888-B, 81 FERC ¶ \n61,248 (1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 \n(1998), aff’d in relevant part sub nom. Transmission Access Pol’y \nStudy Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom. \nNew York v. FERC, 535 U.S. 1 (2002); see also, e.g., Fla. Mun. \nPower Auth. v. FERC, 411 F.3d 287 (D.C. Cir. 2005); Fla. Power \n& Light Co., 113 FERC ¶ 61,290 (2005), aff’d on rehearing, 116 \nFERC ¶ 61,012 (2006), aff’d on appeal sub nom. Fla. Mun. Power \nAgency v. FERC, 264 F. App’x 4 (D.C. Cir. 2008) (per curiam); \nIdaho Power Co., 106 FERC ¶ 61,329 (2004); Ameren Servs. Co. v. \nPrairieland Energy Inc., 131 FERC ¶ 61,125 (2010); Ariz. Pub. \nServ. Co., 151 FERC ¶ 61,191 (2015); Preventing Undue \nDiscrimination and Preference in Transmission Service, Order No. \n890, 119 FERC ¶ 61,119 (“Order No. 890”), order on reh’g, Order \nNo. 890-A, 121 FERC ¶ 61,297 (2007), order on reh’g, Order No. \n890-B, 123 FERC ¶ 61,299 (2008), order on reh’g, Order No. 890-\nC, 126 FERC ¶ 61,228, order on clarification, Order No. 890-D, \n129 FERC ¶ 61,126 (2009). \nc. The Loads Rely Upon the Entire Embedded Transmission System to \nServe Their Full Gross Load. Therefore, FERC’s Decision is Arbitrary \nand Capricious Because the Embedded Transmission System Costs \nShould Be Charged For Those Transmission Services. See Decl. of \nDavid Weaver, PE, Attachment 1 to Exelon Comments, Docket No. EL25-\n20 (Dec. 12, 2024); see also PJM Interconnection, L.L.C., Docket \nNo. EL25-20-000, Indicated TOs June 3, 2025 Answer, Declaration of \nDanielle S. Powers, at P 29. \ni. The Commission’s failure to consider the benefits of grid \ninterconnection makes the June 18, 2026 Order arbitrary and \ncapricious. See State Farm, 463 U.S. at 43. \n2. The Burden Has Not Been Met Under FPA Section 206: FERC’s Replacement \nRate is Not Just and Reasonable. See 16 U.S.C. § 824e(a); Advanced Energy \nMgmt. All. v. FERC, 860 F.3d 656, 663 (D.C. Cir. 2017) (“If the Commission finds \nthat a rate is ‘unjust, unreasonable, unduly discriminatory or preferential, the \nCommission shall determine the just and reasonable rate ... and shall fix the same"},{"page":7,"startToken":2289,"endToken":2717,"text":"7 \n \nby order,’” and “[i]t is the Commission’s job—not the petitioner’s—to find a just \nand reasonable rate.”) (alterations in original) (citation omitted); Emera Maine v. \nFERC, 854 F.3d 9, 21 (D.C. Cir. 2017); Atl. City Elec. Co. v. FERC, 295 F.3d 1, \n10 (D.C. Cir. 2002). The June 18, 2026 Order failed to address the fact that \nreliability is relevant to the inquiry of whether a rate is just and reasonable. \nSee Constellation Mystic Power, LLC v. FERC, 45 F.4th 1028, 1035 (D.C. Cir. \n2022) (“The reasonableness of a rate is assessed in light of the FPA’s goals of \npromoting reliable service at reasonable rates and developing plentiful energy \nsupplies.”); NAACP v. FPC, 425 U.S. 662, 669–70 (1976) (“[T]he principal \npurpose of [the FPA is] to encourage the orderly development of plentiful supplies \nof electricity . . . at reasonable prices.”). \na. Allowing Special Treatment For These Loads Violates the FPA’s \nRequirement That There Be No Undue Preference Or Unreasonable \nDifference In Rates Between Classes of Service. See 16 U.S.C. § 824d(b). \ni. To the extent that the Commission suggests that the \ntransmission provider may move forward with interconnection \nbefore studies are completed, such course of action would \njeopardize reliability and would be in tension with NERC \nreliability standards. See, e.g., See NERC, FAC-002-4 – Facility \nInterconnection \nStudies \n(2022), https://www.nerc.com/globalassets/standards/reliability-\nstandards/fac/fac-002-4.pdf; NERC, 181 FERC ¶ 61,126 (2022) \n(approving FAC-002-4). \nii. There is no lawful basis to require tariff changes to impose new \nforms of service that give certain customers a reduced share of \nembedded costs compared to all other users when they receive \nthe same benefits. See Coal. of MISO Transmission Customers v. \nFERC, 45 F.4th 1004, 1009 (D.C. Cir. 2022). \nb. The Commission’s Emphasis on Protective Systems Is In Tension With \nthe Commission’s Open Access Policies and Therefore Is Arbitrary and \nCapricious. The Commission Also Erred In Minimizing the Fact that \nProtective Systems Can and Have Failed. See NERC, Characteristics and \nRisks of Emerging Large Loads: Large Loads Task Force White Paper, at \n13 (July 2025), https://www.nerc.com/globalassets/who-we-are/standing-\ncommittees/rstc/whitepaper-characteristics-and-risks-of-emerging-large-\nloads.pdf. \ni. The Commission erred in adopting a policy in tension with its \nopen access policies. See Promoting Wholesale Competition \nThrough Open Access Non-Discriminatory Transmission Services \nby Public Utilities; Recovery of Stranded Costs by Public Utilities \nand Transmitting Utilities, Order No. 888-A, FERC Stats. & Regs. \n¶ 31,048, 62 Fed. Reg. 12,274 (Mar. 14, 1997), order on reh’g,"},{"page":8,"startToken":2717,"endToken":3184,"text":"8 \n \nOrder No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh’g, Order \nNo. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub \nnom. Transmission Access Pol’y Study Grp. v. FERC, 225 F.3d 667 \n(D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 \n(2002). \nc. The June 18, 2026 Order is Arbitrary and Capricious in Abandoning \nthe Main Construct of Service to Load, Which is That Customers Share \nIn the Embedded Costs of the System. The Commission Also Erred in \nAdopting a Generator Funding Model for The Funding of Network \nUpgrades for Co-Located Load with No Supporting Evidence. See \nFlorida Gas, 604 F.3d at 639 (“[T]he Commission ‘must be able to \ndemonstrate that it has made a reasoned decision based upon substantial \nevidence in the record.’”) (citation omitted); Consol. Edison Co. of N.Y., \n305 U.S. at 229 (explaining that substantial evidence means “more than a \nmere scintilla”); see also 5 U.S.C. § 706. \ni. FERC’s order is arbitrary and capricious in abandoning the \nmain construct of service to load, which is that customers share \nin the embedded costs of the system. See State Farm, 463 U.S. at \n43; Coal. of MISO Transmission Customers, 45 F.4th at 1009 \n(quoting S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 53 (D.C. Cir. \n2014) (per curiam)). \nii. The Commission’s proposal that such load must self-fund any \nneeded transmission upgrades is arbitrary and capricious \nbecause FERC has not explained its decision to depart from \nprior precedent. See F.C.C. v. Fox Television Stations, Inc., 556 \nU.S. at 515 (“[T]he requirement that an agency provide reasoned \nexplanation for its action would ordinarily demand that it display \nawareness that it is changing position. An agency may not, for \nexample, depart from a prior policy sub silentio or simply disregard \nrules that are still on the books.”); New England Power Generators \nAss’n, 881 F.3d at 211 (“Although case-by-case adjudication \nsometimes results in decisions that seem at odds but can be \ndistinguished on their facts, it is the agency’s responsibility to \nprovide a reasoned explanation of why those facts matter.”); W. \nDeptford Energy, LLC, 766 F.3d at 20 (“It is textbook administrative \nlaw that an agency must ‘provide[ ] a reasoned explanation for \ndeparting from precedent or treating similar situations differently,’ \nand Commission cases are no exception.”) (citations omitted); Cal. \nPub. Utils. Comm’n, 879 F.3d at 977 (“FERC departed from this \npolicy without acknowledgment or explanation. This departure was \narbitrary and capricious.”); Sw. Airlines Co., 926 F.3d at 856 (“‘A \nfull and rational explanation’ becomes ‘especially important’ when, \nas here, an agency elects to ‘shift [its] policy’ or ‘depart[ ] from its \ntypical manner of’ administering a program. . . . [FERC] must at"},{"page":9,"startToken":3184,"endToken":3604,"text":"9 \n \nleast ‘acknowledge’ its seemingly inconsistent precedents and either \noffer a reason ‘to distinguish them’ or ‘explain its apparent rejection \nof their approach’ . . . . But however the agency justifies its new \nposition, what it may not do is ‘gloss[ ] over or swerve[ ] from prior \nprecedents without discussion.’”) (most alterations in original) \n(citations omitted); see also 16 U.S.C. § 824d(b) (prohibiting a \npublic utility from making or granting an “undue preference or \nadvantage” or from maintaining “any unreasonable difference in \nrates, charges, service, facilities, or in any other respect, . . . as \nbetween classes of service”); TransCanada Power Mktg. Ltd., 811 \nF.3d at 12–13 (remanding because FERC did not adequately explain \nits position). \niii. The June 18, 2026 Order departs from traditional cost causation \nprinciples and fails to explain or justify its departure. See, e.g., \nNat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp., 173 FERC ¶ \n61,043, at PP 13–14 (2020); see also Fox Television Stations, Inc., \n556 U.S. at 515 (“[T]he requirement that an agency provide \nreasoned explanation for its action would ordinarily demand that it \ndisplay awareness that it is changing position. An agency may not, \nfor example, depart from a prior policy sub silentio or simply \ndisregard rules that are still on the books.”) (citation omitted). \niv. The Commission provides no record evidence nor a reasoned \nexplanation for why this load should not be charged like other \nload, i.e., with the upgrade cost recovered as part of the \ntransmission rates charged to all customers. Transmission \nowners are permitted to earn a reasonable return on the \ninvestments necessary to construct, operate, and maintain \ntransmission facilities, including those network upgrades \nrequired to serve co-located load. See, e.g., Fed. Power Comm’n \nv. Hope Nat. Gas Co., 320 U.S. 591 (1944); Bluefield Water Works \n& Improvement Co. v. Pub. Service Comm’n of W. Va., 262 U.S. \n679 (1923). \nd. The Commission is Wrong in Suggesting That the New Service Will \nPromote Efficiency or Change Siting. \ni. The Commission’s decision to require options for CD Service \ndoes not change how the study process or the regional planning \nprocess should work. See PJM Tariff §§ 31.1-31.3, 31.6, 32. \ne. The \nCommission’s \nDisregard \nof \nReliability \nConsiderations \nUnderscores that the Replacement Rate is Not Just and Reasonable. See \nConstellation Mystic Power, LLC, 45 F.4th at 1035 (“The reasonableness \nof a rate is assessed in light of the FPA’s goals of promoting reliable service \nat reasonable rates and developing plentiful energy supplies.”); NAACP v."},{"page":10,"startToken":3604,"endToken":4076,"text":"10 \n \nFPC, 425 U.S. at 669–70 (“[T]he principal purpose of [the FPA is] to \nencourage the orderly development of plentiful supplies of electricity . . . at \nreasonable prices.”). \n3. FERC Exceeded Its Jurisdiction. See 16 U.S.C. § 824(b). \na. FERC’s Replacement Rate Violates the Major Questions Doctrine. See \nWest Virginia v. EPA, 597 U.S. 697, 723 (2022); Whitman v. Am. Trucking \nAss’ns, 531 U.S. 457, 468 (2001) (“Congress, we have held, does not alter \nthe fundamental details of a regulatory scheme in vague terms or ancillary \nprovisions—it does not, one might say, hide elephants in mouseholes.”); see \nalso Midship Pipeline Co., v. FERC, 45 F.4th 867, 877 (5th Cir. 2022) \n(vacating part of the Commission’s order and remanding the remainder \nbecause “[t]he FERC’s interpretation of the NGA to give the agency power \nto determine ‘the reasonable cost’ of remediation efforts ‘change[d] the plot \nline’ of its enabling legislation, and was therefore erroneous” and “[t]he \nFERC lacks such authority under the NGA, and it likewise lacked authority \nto order an ALJ to make such a determination indirectly”) (quoting West \nVirginia v. EPA, 597 U.S. at 723); see Atl. City Elec. Co. v. FERC, 295 F.3d \n1, 8 (D.C. Cir. 2002) (As a federal agency, “FERC is a ‘creature of statute,’ \nhaving ‘no constitutional or common law existence or authority, but only \nthose authorities conferred upon it by Congress. Thus, if there is no statute \nconferring authority, FERC has none.”) (citation omitted).’ \n \nb. The Commission’s New Approach Infringes on State Retail Authority. \ni. The Commission’s new approach infringes on state jurisdiction \nand is distinguishable from wholesale demand response \nprograms. See 16 U.S.C. § 824(b); see also FERC v. Elec. Power \nSupply Ass’n, 577 U.S. 260, 270, 278–79 (2016); FERC, Energy \nPrimer: A Handbook for Energy Market Basics, at 41 (Jan. 17, \n2024), \nhttps://www.ferc.gov/news-events/news/ferc-staff-issues-\n2024-energy-primer-handbook-energy-market-basics. \nii. The Commission is unable to do indirectly what it cannot do \ndirectly. Cf. Nat’l Fuel Gas Supply Corp. v. FERC, 909 \nF.2d 1519, 1522 (D.C. Cir. 1990) (“once want of power to do this \ndirectly were established, the existence of power to achieve the same \nend indirectly through the conditioning power might well be \ndoubted” (quoting Sunray Mid-Continent Oil Co. v. FPC, 364 \nU.S. 137, 152 (1960) and citing Richmond Power & Light v. \nFERC, 574 F.2d 610, 620 (D.C. Cir. 1978) (the Commission may \nnot achieve indirectly through conditioning power of Federal Power \nAct what it is otherwise prohibited from achieving directly)); Am. \nGas Ass’n v. FERC, 912 F.2d 1496, 1510 (D.C. Cir. 1990) (“[T]he \nCommission may not use its § 7 conditioning power to do \nindirectly . . . things that it cannot do at all.”); see also FERC v. Elec."},{"page":11,"startToken":4076,"endToken":4414,"text":"11 \n \nPower Supply Ass’n, 577 U.S. at 288 (“The FPA ‘leaves no room \neither for direct state regulation of the prices of interstate \nwholesales’ or for regulation that ‘would indirectly achieve the same \nresult.’”) (citation omitted). \nII. \nThe Burden Under FPA Section 206 Has Not Been Met: The Existing Rate \nHas Not Been Shown To Be Unjust And Unreasonable. \n \nThe FPA requires that the rates and charges of a public utility “in connection with the \ntransmission or sale of electric energy subject to the jurisdiction of the Commission, and all rules \nand regulations affecting or pertaining to such rates or charges shall be just and reasonable.”8 \n“[A]ny such rate or charge that is not just and reasonable is . . . unlawful.”9 Under FPA section \n206, the Commission may, by its own motion or upon complaint from a third party, remedy any \n“rate [or] charge” or “any rule, regulation, practice, or contract affecting such rate [or] charge” \nfound to be “unjust [or] unreasonable.”10 “The burden of proving an unjust or unreasonable rate \nrests with the party that initiated the proceeding—that is, the Commission or the third-party \ncomplainant.”11 In other words, a respondent to a FPA section 206 complaint is not required to \nmake an affirmative showing that its existing rate is still just and reasonable.  \nFor the reasons below, neither the complainants in the above-captioned dockets nor any \nother party have met their burden of demonstrating that PJM’s current rate is unjust and \nunreasonable so as to require new forms of transmission service for load served by BTMG.  \nA. There is No Evidence In The Record That Loads Served by BTMG Are \nUnable to Obtain Reliable, Timely, And Reasonably Priced Service Using \nThe Existing Network Service Construct. Therefore, the Commission Fails To \nSatisfy The Requirement Under The APA That Its Decision Be Supported \nWith Substantial Evidence. \n \n8  \n16 U.S.C. § 824d(a). \n9  \nId. \n10  Id. § 824e(a). \n11  Pub. Citizen, Inc. v. FERC, 7 F.4th 1177, 1183 (D.C. Cir. 2021)."},{"page":12,"startToken":4414,"endToken":4766,"text":"12 \n \n \nUnder the APA, the Commission “must examine the relevant data and articulate a \nsatisfactory explanation for its action including a ‘rational connection between the facts found and \nthe choice made’”12 and must base its decision on substantial evidence in the record.13 Substantial \nevidence means “more than a mere scintilla,” that is, “such relevant evidence as a reasonable mind \nmight accept as adequate to support a conclusion.”14 The Commission’s June 18, 2026 Order does \nnot satisfy this requirement. \nThe totality of the Commission’s reasoning for requiring that new forms of transmission \nservice be offered to loads served by BTMG is in Paragraph 91 of the Order, which states:  \nthe Tariff is unjust and unreasonable because it does not \ninclude transmission services that reflect that Eligible \nCustomers taking transmission service on behalf of load with \nBTMG are willing and able to limit their energy withdrawals \nfrom the transmission system under certain conditions. \nRequiring Eligible Customers taking transmission service on \nbehalf of load with BTMG to take NITS, without the option to \ninstead take such alternative transmission services that reflect \ntheir willingness and ability to limit their energy withdrawals, \nwould be unjust and unreasonable for the same reasons we \nmade the same finding with respect to Eligible Customers \ntaking transmission service on behalf of Co-Located Load.15 \n \nThis finding with respect to load served by BTMG is unsupported by evidence that the \ncurrent tariff service options are inadequate. Under the current PJM Tariff, there are two \ntransmission service options: (1) Network Integration Transmission Service (“NITS” or “Network \n \n12  State Farm, 463 U.S. at 43 (citation omitted). \n13  See, e.g., Fla. Gas Transmission Co. v. FERC, 604 F.3d 636, 639 (D.C. Cir. 2010) (“[T]he Commission ‘must be \nable to demonstrate that it has made a reasoned decision based upon substantial evidence in the record.’” (quoting \nPac. Gas & Elec. Co. v. FERC, 373 F.3d 1315, 1319 (D.C. Cir. 2004))); see also 5 U.S.C. § 706.  \n14  Consol. Edison Co. of N.Y., 305 U.S. at 229. \n15  June 18, 2026 Order at P 91."},{"page":13,"startToken":4766,"endToken":5202,"text":"13 \n \nService”);16 and (2) Point-to-Point Transmission Service.17 There is no inability to determine how \nto serve load in PJM; the PJM Tariff already has provisions explaining how Network Service works \nand how loads of Network Customers will be served. The starting point is Section 31.1 of the PJM \nTariff, which (mirroring the Commission’s own pro forma Open Access Transmission Tariff \n(“OATT”)) requires that Network Loads are to be specified in the Service Agreement. The PJM \nTariff sets forth in Sections 31.2 and 31.3 the procedures for identifying new Network Loads that \nwill be served by the Network Customer. If, and to the extent that, study is required of the request, \nthe requirements of that study are spelled out in Section 32 of the PJM Tariff. And, in recognition \nof the fact that loads change after commencement of service, Section 31.6 provides the process by \nwhich to report on changing loads. Further, there are application procedures for studying any new \nservice in Section 29 of the PJM Tariff, which require specification of all aspects of the requested \nservice, including capabilities and operating restrictions on all proposed network resources. These \ntariff provisions have been in place for decades, and already require that service requests should \nbe assessed and analyzed based on their particular features; thus they already provide mechanisms \nfor factoring in and assessing the individualized characteristics of the proposed service. The June \n18, 2026 Order does not even begin to explain how the existing Network Service construct and \nexisting PJM Tariff rules and precedent fail to provide a mechanism for loads of all sorts, including \nloads served by BTMG with specific resource limitations and restrictions.  \n \n16  Under the PJM Tariff, “Network Transmission Service” “mean[s] transmission service provided pursuant to the \nrates, terms and conditions set forth in Tariff, Part III, or transmission service comparable to such service that is \nprovided to a Load Serving Entity that is also a Transmission Owner.”  PJM Tariff, OATT Definitions – L – M – \nN, at 13-14.  The PJM Tariff defines “Network Integration Transmission Service” as “the transmission service \nprovided under Tariff, Part III.  There are two types of firm Network Integration Transmission Service:  Regional \nNetwork Integration Transmission Service and firm Cross-Border Network Integration Transmission Service.  \nNon-firm Network Integration Transmission Service includes Secondary Service.”  Id. at 12–13. \n17  Under the PJM Tariff, “Point-To-Point Transmission Service” “mean[s] the reservation and transmission of \ncapacity and energy on either a firm or non-firm basis from the Point(s) of Receipt to the Point(s) of Delivery \nunder Tariff, Part II.”  Id., OATT Definitions – O – P – Q, at 10."},{"page":14,"startToken":5202,"endToken":5598,"text":"14 \n \nThe Commission’s reasoning on load served by BTMG relies on its analysis with respect \nto Co-Located Load, but there too there is no evidence that the existing rules are inadequate. There \nare certainly statements that there is a lack of “clarity”, such as in Paragraph 56-58 of the June 18, \n2026 Order, but there is no evidence to back that up. For example, the Commission states in \nParagraph 58 that there is no clarity that an Eligible Customer must be designated to take \ntransmission service, but the existing PJM Tariff already defines “Transmission Customer” and \nspecifies that it must be an “Eligible Customer”.18 While it is certainly true that certain parties in \nthese proceedings, such as Constellation, have sought transmission service without designation of \nan Eligible Customer, 19 there has never been a credible case that there is a lack of clarity on the \nissue. The Commission continues to use the Constellation example as a demonstration that there \nis a lack of “clarity” requiring new forms of transmission service,20 but this is a logical tautology. \nThat is, the fact that Constellation attempted to circumvent the rules, causing delays in its service \nrequest, does not prove that the existing rules were inadequate.  \nAt Para 65 of the June 18, 2026 Order, the Commission cites to the Susquehanna ISA \nProceeding, in fn. 136, as evidence that there is continued reason for concern.  In Docket Nos. \nER24-2172-000 and ER24-2172-001 (“Susquehanna ISA Proceeding”),21 there was a proposal to \nallow co-located load to avoid purchasing Network Service through the use of a behind-the-meter \n \n18  PJM Tariff, Definition of Transmission Customer, Section 1. \n19  See Complaint Requesting Fast Track Processing of Constellation Energy Generation, LLC, at Ex. 5 Attach. 1, \nDeclaration of James R. McCoskey (filed Nov. 22, 2024).   That attachment is a November 12, 2024, letter from \nComEd to Constellation concerning interconnection requests at the LaSalle and Byron nuclear facilities.  In that \nletter, ComEd details certain design issues with Constellation’s proposal and then explains that the “end use load \nis retail load under both Illinois and federal law and cannot be interconnected solely through amendments to the \nLaSalle or Byron [interconnection service agreements].”  In other words, Constellation was seeking transmission \nservice without an Eligible Customer. \n20  See June 18, 2026 Order at fn. 114, citing the Constellation situation. \n21  See Susquehanna ISA Order, 189 FERC ¶ 61,078."},{"page":15,"startToken":5598,"endToken":5911,"text":"15 \n \narrangement.22 The Commission correctly rejected the proposed interconnection service \nagreement (“ISA”) in the Susquehanna ISA Proceeding. 23 Talen subsequently announced that \n“[t]he existing Susquehanna co-located load arrangement between Talen and Amazon will \ntransition to a ‘front-of-the-meter’ arrangement after the completion of transmission \nreconfigurations expected in the Spring of 2026, concurrent with Susquehanna’s refueling \noutage.”24 Talen effectively conceded that PJM Network Service works, which is to say that \nNetwork Service under the existing PJM Tariff provides for timely service, and is a service upon \nwhich all customers may rely. There is simply no evidence suggesting otherwise. \nThe Commission’s findings relating to the existing tariff promoting “economic \ninefficiency”25 are likewise devoid of evidence. That is, the existing PJM Tariff provides for a \nfulsome study process based on the proposed operating characteristics of the loads and resources. \nSee PJM Tariff at Sections 29 and 31. No evidence is offered in the order of any circumstance in \nwhich the current transmission rate service offerings in the PJM Tariff impacted study results. To \nthe contrary, study results are based on the physics and engineering of the system – not on whether \nthe rates are based on the customer’s gross load or net load. Customers with BTMG have been \nserved under open access tariffs for decades and there is simply no evidence offered in the order \nthat such customers are forced to operate inefficiently on account of the existing OATT \ntransmission service offerings.  Indeed, as discussed below, the Commission has consistently \n \n22  See PJM Interconnection, L.L.C., Docket No. ER24-2172-000, Application Attach. A, Amended ISA, at Schedule \nF, Part F.4 (June 3, 2024). \n23  Susquehanna ISA Order, 189 FERC ¶ 61,078. \n24  Press Release, Talen Energy, Talen Energy Expands Nuclear Energy Relationship with Amazon (June 11, \n2025), https://ir.talenenergy.com/news-releases/news-release-details/talen-energy-expands-nuclear-energy-\nrelationship-amazon. \n25  June 18, 2026 Order at P 65."},{"page":16,"startToken":5911,"endToken":6264,"text":"16 \n \nrejected arguments that different ratemaking should be applied even where there are limits to the \namount of transmission system use.26 \nFurther, the Commission’s December 18, 2025 Order held that Network Service remains \njust and reasonable. The Commission states that, \nit continues to be just and reasonable for an Eligible Customer \ntaking transmission service on behalf of Co-Located Load to elect, \nas one of the required transmission services from which the Eligible \nCustomer must choose, to take NITS. . . . NITS provides significant \nbenefits because a NITS customer gains the right to be served from \nthe transmission system at any time, and PJM and the transmission \nowners incorporate NITS load into their transmission planning.27  \n \nIn the June 18, 2026 Order, the Commission holds fast to that determination but holds that  \ncertain customers (which now includes load served by BTMG) are entitled to more new options.28 \nThe Commission (in fn 156) then cites back to the December 18, 2025 Order and its finding \nwithout evidence that inefficiencies result if new options are not available. In total, there are \nassertions of inefficiency, but no evidence to support the conclusion that the existing service \noptions fail to address the needs of any loads, including loads served by BTMG. That is not a \npermissible basis to take action under FPA section 206.  \nB. The Commission Did Not Engage in Reasoned Decision Making Because It \nDid Not Explain its Departure from FERC Precedent or Refute that, Because \nthe Existing PJM Tariff Provides Service on the Same Basis for All \nCustomers, the Existing PJM Tariff Does Not Grant an Undue Preference.  \n \nAs an initial matter, picking and choosing customers to receive preferential rate treatment \nruns contrary to the FPA’s requirement that “[n]o public utility shall, with respect to any \n \n26  See Fla. Power & Light Co., 113 FERC ¶ 61,290 (2005), aff’d on rehearing, 116 FERC ¶ 61,012 (2006), aff’d on \nappeal sub nom. Fla. Mun. Power Agency v. FERC, 264 F. App’x 4 (D.C. Cir. 2008) (per curiam). \n27  December 18, 2025 Order, at  P 195 (footnote omitted). \n28  June 18, 2026 Order at P 68."},{"page":17,"startToken":6264,"endToken":6622,"text":"17 \n \ntransmission or sale subject to [FERC’s] jurisdiction . . . (1) make or grant any undue preference \nor advantage to any person or subject any person to any undue prejudice or disadvantage, or (2) \nmaintain any unreasonable difference in rates, charges, service, facilities, or in any other respect, \neither as between localities or as between classes of service.”29  \nThe Commission has a long-standing policy of rejecting attempts by network transmission \ncustomers to avoid paying their load ratio share of system cost. As the Commission recognized in \nthe June 18, 2025 Order, citing the Amtrak case, the Commission “has rejected cost causation \narguments made by network customers that sought to lower their load ratio share based on actual \nuse of the transmission system.”30 This policy has long persisted for very good reason. The \n“assessment of [Network Integration Transmission Service] is not based on actual use over a \nparticular transmission path, but rather based on the network customer’s right to use the entire \nsystem” and its effects on that system.31  \nThe Amtrak case, which rejected an attempt by a network customer in PJM to pay for less \nthan its full gross load, was not an outlier, but instead reflected decades of Commission precedent, \nrejecting challenges to uniform application of the rule that Network Service would be based on the \nentire gross load of the network customer, regardless of arguments (such as those advanced by \nAmtrak) that the customer could purportedly limit use of the system. For example, this exact issue \nwas addressed in Order No. 888-A and resulting appeals. In Order No. 888-A, the Commission \n \n29  16 U.S.C. § 824d(b). \n30  June 18, 2026 Order, 193 FERC ¶ 61,217 at P 196 & n.412 (citing Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. \nCorp, 171 FERC ¶ 61,237, at P 41 (2020), denying clarification and addressing reh’g, Nat’l R.R. Passenger Corp. \nv. PPL Elec. Utils. Corp., 173 FERC ¶ 61,043 (2020) (“Amtrak”); PJM Interconnection, L.L.C., 169 FERC ¶ \n61,041, at P 60 (2019)). \n31  Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp., 173 FERC ¶ 61,043, at PP 13–14 (2020)."},{"page":18,"startToken":6622,"endToken":7027,"text":"18 \n \nheld that customers cannot “split” their load at a delivery point—if some of the load takes Network \nService, all of the load must be designated for Network Service: \nThe concept of allowing a “split system” or splitting a discrete load \nis antithetical to the concept of network service. A request for \nnetwork service is a request for the integration of a customer’s \nresources and loads. Quite simply, a load at a discrete point of \ndelivery cannot be partially integrated—it is either fully integrated \nor not integrated. Furthermore, such a split system creates the \npotential for a customer to “game the system” thereby evading some \nor all of its load-ratio cost responsibility for network services.32 \nThat ruling was expressly upheld on appeal by the U.S Court of Appeals for the District of \nColumbia Circuit (“D.C. Circuit”), which accepted the Commission’s reasoning, finding that \nobjections were “not well-taken.”33  \nIn the June 18, 2026 Order, the Commission argues that it is not violating Order No. 888-\nA, because the load is not “split” but is instead limited by contract demand.34 This is sophistry – \ncharging network service for a portion of the load, and not for other portions of the load at the \nsame delivery point, is the exact type of load-splitting proposal that the Commission rejected in \nOrder No. 888-A. Further, because the Commission has recognized that these customers use the \ntransmission system for some services for their whole load (such as load following and black start), \nthe notion that the customer can use the system for those services but not others, again reflects a \nsplitting of responsibility for the load that flies in the face of the Commission’s Order 888-A ruling.  \nThe Commission suggests that specification of a fixed contract demand avoids opportunities for \n \n32  Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public \nUtilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888-A, 78 FERC \n¶ 61,220 (1997), order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), order on reh’g, Order No. 888-C, \n82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission Access Pol’y Study Grp. v. FERC, 225 \nF.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002). \n33  Transmission Access Pol’y Study Grp., 225 F.3d at 726. \n34  June 18, 2026 Order at P 112."},{"page":19,"startToken":7027,"endToken":7439,"text":"19 \n \n“gaming” eliminating at least one of the concerns of Order No. 888-A,35 but the gaming \nopportunity here is in the designation of contract demand, which pretends that the load is only \npartially using the transmission system, even though the transmission system is following the \nentirety of the load.  \nThe issue was likewise addressed in a long series of cases involving Florida Municipal \nPower Agency (“FMPA”) and transmission service it was taking from Florida Power and Light. \nAs recounted by the D.C. Circuit in 2005, years of litigation in that case involved the attempt by \nFMPA to avoid paying for Network Service based on its overall gross load, with the Commission \nconsistently rejecting all arguments by FMPA against such load splitting.36 In the 2005 decision, \nthe court remanded one argument by FMPA, which is that physical constraints on the transmission \nsystem made it physically impossible for its entire load to be served by the FPL system.37 On \nremand, the Commission found that even in the case of physical impossibility of serving the entire \nload, the gross load construct was most appropriate, rejecting arguments that a network customer \nshould pay for any less than its entire system load.38 \nThe Commission has consistently followed this precedent.39 For example, in Idaho Power, \nthe Commission rejected Bonneville Power Administration’s (“BPA”) attempt to remove certain \n \n35  Id. \n36  Fla. Mun. Power Auth. v. FERC, 411 F.3d 287 (D.C. Cir. 2005) (describing history of case back to 1993). \n37  Id. at 292 (remanding because “FERC . . . failed to explain why network customers should be charged by the \ntransmission provider for network service that the provider is physically constrained from offering and, relatedly, \nwhy physical impossibility should not be recognized as an exception to the general rule against permitting partial \nload ratio pricing for network customers”). \n38  Fla. Power & Light, 113 FERC  ¶ 61,290 (2005), aff’d on rehearing, 116 FERC ¶ 61,012 (2006), aff’d on appeal, \n264 F. App’x 4 (D.C. Cir. 2008). \n39  See, e.g., Idaho Power Co., 106 FERC ¶ 61,329 (2004) (“Idaho Power”); Ameren Servs. Co. v. Prairieland Energy \nInc., 131 FERC ¶ 61,125 (2010) (finding that network customer failed to comply with the tariff by not designating \nits total load as network load); Ariz. Pub. Serv. Co., 151 FERC ¶ 61,191 (2015) (finding that a network customer's \nrequest to designate less than its entire load as network load violated both the transmission provider’s OATT and \n(cont'd)"},{"page":20,"startToken":7439,"endToken":7861,"text":"20 \n \nof its load from its load ratio share.40 The Commission explained that, contrary to Order No. 888, \n“BPA’s proposal would essentially leave the behind the meter loads . . . as part of BPA’s network \nload served by Idaho Power’s transmission service, but eliminate the requirement that such loads \nbe metered, i.e., included in BPA’s load ratio share, because Idaho Power’s transmission service \nmay only be needed in rare instances.”41 Similarly, in Order No. 890,42 commenters complained \nthat assigning transmission-related costs to customers that reduce their use of the transmission \nprovider’s system to serve load is inconsistent with the Commission’s cost-causation principles. \nThe Commission rejected such arguments, stating that its existing policy already provides \ncustomers with the opportunity to reduce network service costs to the extent a customer is not \nrelying on the transmission system to meet its energy needs (i.e., by taking point-to-point \ntransmission service instead of network service).43 \nIn the June 18, 2026 Order, the Commission in its ruling on BTMG now has departed from \nthese decades of precedent and, contrary to the APA, has failed adequately to explain its \ndeparture.44 The Commission’s prior determinations of the fairness of load ratio allocation (based \n \nlong standing Commission policy, which require network customers to designate their entire load as network load \nto receive network service). \n40  Idaho Power, 106 FERC ¶ 61,329 at P 14. \n41  Id. \n42  Preventing Undue Discrimination and Preference in Transmission Service, Order No. 890, 119 FERC ¶ 61,119 \n(“Order No. 890”), order on reh'g, Order No. 890-A, 121 FERC ¶ 61,297 (2007), order on reh'g, Order No. 890-\nB, 123 FERC ¶ 61,299 (2008), order on reh'g, Order No. 890-C, 126 FERC ¶ 61,228, order on clarification, \nOrder No. 890-D, 129 FERC ¶ 61,126 (2009). \n43  See Order No. 890, 119 FERC ¶ 61,119.. \n44  See  Fox Television Stations, Inc., 556 U.S. at 515 (“the requirement that an agency provide reasoned explanation \nfor its action would ordinarily demand that it display awareness that it is changing position. An agency may not, \nfor example, depart from a prior policy sub silentio or simply disregard rules that are still on the books.”).  At \nparagraph 211 of the June 18, 2026 Order, the Commission says that the current load-splitting proposal is different \nfrom prior situations because PJM need only plan for the specified contract demand rather than the full load, but \nthis argument is not a difference from prior cases at all, such as the FPL case where there was no contention that \n(cont'd)"},{"page":21,"startToken":7861,"endToken":8251,"text":"21 \n \non gross load—even in the case of purported physical impossibility of service to full load) of \nembedded costs hold true. There is no reasoned basis for these distinctions. \nThe Declaration of Danielle S. Powers (“Powers Declaration”), submitted by Exelon and \nFirstEnergy, explains why the assessment of Network Service is not based on actual use over \nspecific transmission paths.45 All customers have different usage of the grid. Many customers’ \nreliance upon the grid varies during different times of the year and can be distinguished from other \ncustomers’ uses. These customers may have distinct load shapes or load factors, but they pay the \nsame rate for Network Service as do high load factor customers. Such customers pay the full \nNetwork Service rate, but because Network Service charges are allocated based on contribution to \nthe system coincident peak, some customer charges may be lower on average than others if their \noperations occur disproportionately outside of the peak hours. No additional rate discount is \nnecessary or given. Up until now, the Commission has consistently applied this approach of not \ncarving out special rates for different customer classes for good reason—every customer can \nattempt to make arguments why their usage should result in a decrease of their share of the \nembedded costs of the transmission system. Utilities have an obligation to serve load and that load \nneeds to be able to call on service regardless of whether they actually utilize the system to the \nmaximum allowable extent since weather and other factors are unpredictable. Hence, actual usage \ndoes not reflect the benefit. Entertaining such arguments would frustrate the rate design that the \nCommission has applied across the board and that was put in place following Order No. 888.46 \n \nFPL was redesigning its system to serve the full load of FMPA, or the Amtrak case where the entire premise of \nthe argument was that Amtrak made only rare and limited use of the system. \n45  See PJM Interconnection, L.L.C., Docket No. EL25-20-000, Indicated TOs June 3, 2025 Answer, Declaration of \nDanielle S. Powers at P 29. \n46  See, e.g., Recovery of Stranded Costs by Pub. Utils. and Transmitting Utils., Order No. 888, 75 FERC ¶ 61,080 \n(1996), order on reh’g, Order No. 888-A, 78 FERC ¶ 61,220, order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 \n(cont'd)"},{"page":22,"startToken":8251,"endToken":8829,"text":"22 \n \nThe existing PJM Tariff effectuates the principle that those that benefit from the \ntransmission system should contribute on a load ratio basis to the embedded costs of the system \nand is consistent with the pro forma OATT in providing for Network Service and Point-to-Point \nService, an important component of Order No. 888.47 Under the APA, the Commission must \nexplain why circumstances have changed such that this proceeding requires departure from past \nefforts by customers to pay for less than gross load.48 The Commission made no serious attempt \nto do so. Nor has the Commission distinguished why other existing customers will not qualify for \ndiscounts—many of whom can argue that they impose lesser demand on the grid by some measure. \nThat failure to provide explanation renders FERC’s decision arbitrary and capricious and violates \nthe APA.49 Ultimately, this is not reasoned decision making and will create a nightmare as other \ncustomers in PJM and beyond raise a host of similar arguments that their transmission rates should \n \n(1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission \nAccess Pol’y Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000) (TAPS), aff’d sub nom. New York v. FERC, 535 \nU.S. 1 (2002). \n47  See, e.g., id. \n48  See Fox Television Stations, Inc., 556 U.S. at 515 (“the requirement that an agency provide reasoned explanation \nfor its action would ordinarily demand that it display awareness that it is changing position.  An agency may not, \nfor example, depart from a prior policy sub silentio or simply disregard rules that are still on the books.”); see \nalso Constellation Mystic Power, LLC 45 F.4th at 1057 (finding the Commission’s decision to be arbitrary and \ncapricious and that “the Commission’s ‘failure to provide an intelligible explanation . . . amounts to a failure to \nengage in reasoned decisionmaking’”) (citation omitted); New England Power Generators Ass’n, Inc. v. FERC, \n881 F.3d 202, 211 (D.C. Cir. 2018) (“Although case-by-case adjudication sometimes results in decisions that \nseem at odds but can be distinguished on their facts, it is the agency’s responsibility to provide a reasoned \nexplanation of why those facts matter.” (citing BP Energy Co. v. FERC, 828 F.3d 959, 968 (D.C. Cir. 2016) \n(vacating finding of no undue discrimination where Commission identified differences between two natural-gas \ncompanies but failed to adequately explain why they provide a rational basis for the difference in treatment))); \nW. Deptford Energy, LLC v. FERC, 766 F.3d 10, 20 (D.C. Cir. 2014) (“It is textbook administrative law that an \nagency must ‘provide[ ] a reasoned explanation for departing from precedent or treating similar situations \ndifferently,’ . . . and Commission cases are no exception . . . .”) (alteration in original) (citations omitted). \n49  See, e.g., Cal. Pub. Utils. Comm’n, 879 F.3d at 977 (“FERC departed from this policy without acknowledgment \nor explanation. This departure was arbitrary and capricious.”); Sw. Airlines Co., 926 F.3d at 856 (“‘A full and \nrational explanation’ becomes ‘especially important’ when, as here, an agency elects to ‘shift [its] policy’ or \n‘depart[ ] from its typical manner of’ administering a program. . . .  [FERC] must at least ‘acknowledge’ its \nseemingly inconsistent precedents and either offer a reason ‘to distinguish them’ or ‘explain its apparent rejection \nof their approach’ . . . But however the agency justifies its new position, what it may not do is ‘gloss[ ] over or \nswerve[ ] from prior precedents without discussion.’”) (alterations in original) (citation omitted)."},{"page":23,"startToken":8829,"endToken":9143,"text":"23 \n \nbe modified based on their allegedly different use of the system, which is a reason why the \nCommission never mandated this in the past.  \nC. The Loads Rely Upon The Entire Embedded Transmission System To Serve \nTheir Full Gross Load. Therefore, FERC’s Decision is Arbitrary and \nCapricious Because The Embedded Transmission System Costs Should Be \nCharged For Those Transmission Services. \nNotwithstanding well-established Commission policy and judicial precedent to the \ncontrary, the June 18, 2026 Order establishes a new preferential transmission rate available for \nloads served by BTMG. Not only is this new rate unduly discriminatory (as discussed herein), but \nit is based on a false premise that the combination of transmission system burdens and user benefits \nto loads served by BTMG are so insignificant as to justify the establishment of a lower, preferential \nrate. The Commission is wrong, with respect to both the actual burdens on the system and the \nbenefits to load served by BTMG of being interconnected to the grid. \nAs for benefits, the Commission has recognized that co-located loads benefit from black \nstart and load following service,50 and that such service properly should be charged based on gross \nload. The Commission did not discuss the issue for load served by BTMG, but such load likewise \nis reliant on black start and load following. Load following services are supplied from a diverse \nrange of the interconnected generation facilities located throughout the system. These services \ncannot be provided without use of all the transmission system’s resources and personnel. \nMoreover, because it is a universal rule that generators cannot operate every hour of every year \nand that unexpected outages can and do occur, transmission interconnections provide an avenue \nfor such loads to readily acquire back-up power when co-located generation facilities are not \navailable.  \n \n50  See June 18, 2026 OrderJune 18, 2026 Order, 193 FERC ¶ 61,217 at PP 209, 219 (3), (4)."},{"page":24,"startToken":9143,"endToken":9495,"text":"24 \n \nIn addition, in assessing load served by BTMG, the Commission fails to consider the many \nadvantages to such loads when they connect to the transmission system. These advantages become \napparent when one compares islanded projects to similar projects that are interconnected to the \ntransmission grid. Islanded projects require extensive back-up generation to assure reliable sources \nof power. It is very difficult and expensive to supply islanded generation with black start \ncapabilities or instantaneous load following. All back-up generation on an islanded project will sit \nidle when not needed to serve the islanded load, thereby forgoing significant revenues from selling \nthe surplus power into the wholesale market. These lost opportunity sales revenues alone could \nlikely cover the fully embedded costs of Network Service. Ultimately, islanded generation projects \nare more risky and therefore more difficult to finance. Grid interconnection is valuable, which is \nwhy the BTMG-served customers do not just create isolated islands. In determining that traditional \nNetwork Service without the option of additional services is unjust and unreasonable for load \nserved by BTMG, the Commission considered none of these benefits of grid interconnection to \nsuch loads. Failure to consider the benefits of grid interconnection makes the June 18, 2026 Order \narbitrary and capricious and unreasoned.51 \nIII. \nThe Burden Has Not Been Met Under FPA Section 206: FERC’S Replacement \nRate is Not Just and Reasonable. \n \nUnder FPA section 206,52 there are two steps: only after the Commission finds a rate to be \nunjust and unreasonable, may it set a replacement rate.53 No one has met the burden at either step \nin ordering that new forms of transmission service be provided to load served by BTMG.  \n \n51  See State Farm, 463 U.S. at 43. \n52  16 U.S.C. § 824e(a).  \n53  See id; see also Advanced Energy Mgmt. All., 860 F.3d at 663 (“If the Commission finds that a rate is ‘unjust, \nunreasonable, unduly discriminatory or preferential, the Commission shall determine the just and reasonable \nrate … and shall fix the same by order,’” and “[i]t is the Commission’s job—not the petitioner’s—to find a just \n(cont'd)"},{"page":25,"startToken":9495,"endToken":9827,"text":"25 \n \nA. Allowing Special Treatment For Load Served by BTMG Violates The FPA’s \nRequirement That There Be No Undue Preference Or Unreasonable \nDifference In Rates Between Classes Of Service.  \nAs explained above, FPA section 205 prohibits any public utility charging transmission \nrates from “mak[ing] or grant[ing] any undue preference or advantage to any person or subject any \nperson to any undue prejudice or disadvantage” or “maintain[ing] any unreasonable difference in \nrates, charges, service, facilities, or in any other respect, either as between localities or as between \nclasses of service.”54 The Commission, by requiring new forms of service for load served by \nBTMG, would establish rates that grant an undue preference or advantage to such loads.  \nThere already exist mechanisms (such as demand response at the state and federal levels) \nto address when customers can scale back their load or bring other generation to bear in order to \nreduce their withdrawals when called upon. If loads served by BTMG would like to be \ncompensated for being interruptible, then they should rely upon PJM’s demand response rules, or \nretail rules in the various states, and the June 18, 2026 Order fails to explain why those rules are \ninadequate here. The point of FPA section 206 is not for the Commission to declare what it thinks \nwould be better tariff options—it is to ensure that the tariff on file is just and reasonable. Similarly, \nthe PJM Tariff already has in place provisions to provide compensation to those that can ease \ntransmission congestion – to the extent that a basis for the Commission’s orders is that some uses \nof the system reduce grid usage thus easing congestion, the mechanisms are already there.  The \nCommission does not consider those existing tariff provisions, and thus fails to develop just and \nreasonable rate mechanisms. \n \nand reasonable rate.”) (alterations in original) (citation omitted); Emera Maine, 854 F.3d at 21; Atl. City Elec. \nCo., 295 F.3d at 10. \n54  16 U.S.C. § 824d(b)."},{"page":26,"startToken":9827,"endToken":10171,"text":"26 \n \nFor the new Interim Service, there is no basis for the Commission to require this new form \nof service prior to the completion of necessary network upgrades and studies to ensure reliability \nof the system. The Commission has effectively conceded it has not yet done adequate analysis on \nthis point – ruling in Paragraphs 125 and 131 of the June 18, 2026 Order that it is “premature” to \ndetermine the extent, if any, that the new forms of service promote efficiency or impact reliability. \nThe Commission cannot have it both ways – if it is premature to consider if the new services \npromote efficiency, or adequately protect reliability, the Commission cannot rely on purported \nefficiency gains, to justify imposition of the new services, and cannot claim to have done so in a \nway that is protective of reliability.  \nSecond, the only issue that CD Services resolve is ratel levels for embedded costs allocated to \nthese load. The form of service does not dictate what studies should be conducted, or what \nupgrades might be necessary for the system. Whether or not a customer seeks CD Service, studies \nshould consider the actual circumstances of the proposed interconnection, which will be dictated \nby engineering and physics, and not by the rate level charged to the customer. The notion that CD \nService impacts issues such as where a customer interconnects depend on a fallacy that system \nstudies consider rate levels rather than the details of the proposed interconnection. \nInterconnecting to the grid burdens the system by adding new loads and operating \ncontingencies that must be addressed by system operators. Grid interconnections also bring \nsignificant project benefits such as the ability to sell on-site back-up generation into the wholesale \nmarkets when it otherwise would sit idle, and the ability to receive load following service from \noff-site generation. The totality of these burdens and benefits—benefits which no doubt exceed \nthe cost of Network Service based on gross load—easily justify charging these loads the same rate \nas all other transmission customers. To allow for preferential rate treatment would allow those"},{"page":27,"startToken":10171,"endToken":10647,"text":"27 \n \ncustomers to rely upon the grid and its benefits at a price that is subsidized by all other customers. \nThat cannot be said to be just and or reasonable.55 Such a decision is not grounded in reasoned \ndecision making and is not supported by substantial evidence.56  \nB. The Commission’s Emphasis On Protective Systems Is In Tension With The \nCommission’s Open Access Policies And Therefore Is Arbitrary And \nCapricious. The Commission Also Erred In Minimizing The Fact That \nProtective Systems Can And Have Failed. \n \nAs Exelon and FirstEnergy have explained, protective systems can provide value, but they \nare no panacea. They can protect against net withdrawals from the grid (where the load exceeds \nthe co-located generation), but do not protect the grid from real impacts that occur even when there \nis consumption by a co-located customer but no net withdrawal, such as the impacts of load and \nvoltage spikes and oscillations.57 Further, the emphasis on protective systems to prevent backflows \nignores an important issue: other providers may want to compete to serve these customers. The \ngenerators have an interest in designing captive arrangements where the customers cannot access \nalternative supply, but that is not something the Commission should endorse. To the contrary, it \nflouts the core proposition behind Order No. 888,58 where the Commission established its open \n \n55  See Coal. of MISO Transmission Customers, 45 F.4th at, 1009 (alterations in original) (quoting S.C. Pub. Serv. \nAuth. v. FERC, 762 F.3d 41, 53 (D.C. Cir. 2014) (per curiam)) (“The cost-causation principle requires that \n‘[t]he cost of transmission facilities . . . be allocated to those within the transmission planning region that \nbenefit from those facilities in a manner that is at least roughly commensurate with estimated benefits.’”). \n56  See Florida Gas, 604 F.3d at 639 (“[T]he Commission ‘must be able to demonstrate that it has made a reasoned \ndecision based upon substantial evidence in the record.’”) (citation omitted); Consol. Edison Co. of N.Y., 305 \nU.S. at 229 (explaining that substantial evidence means “more than a mere scintilla”); see also 5 U.S.C. § 706. \n57  This follows directly from the Commission’s acknowledgement that these arrangements need load following for \nthe entire gross load, regardless of the absence of net withdrawals. \n58  See Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by \nPublic Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888-A, \nFERC Stats. & Regs. ¶ 31,048, 62 Fed. Reg. 12,274, 12,323 (Mar. 14, 1997), order on reh’g, Order No. 888-B, \n81 FERC ¶ 61,248 (1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub \nnom. Transmission Access Pol’y Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. \nFERC, 535 U.S. 1 (2002)."},{"page":28,"startToken":10647,"endToken":10950,"text":"28 \n \naccess policies. Transmission asset owners cannot create barriers that inhibit the ability of other \ngeneration on the grid to compete to serve load. As the Supreme Court recognized, a key \nmotivation behind the open access requirements is that owners’ “control of transmission facilities \ngives them the power either to refuse to deliver energy produced by competitors or to deliver \ncompetitors’ power on terms and conditions less favorable than those they apply to their own \ntransmissions.”59 But that is exactly what generators propose and the Commission now endorses. \nBy design, the protective systems are intended to prevent ready access to competing suppliers. In \naddition to its other flaws, that proposal should be rejected because it is an illegal effort to stifle \ncompetition. \nMoreover, the Commission puts too much faith in protective systems operating \ninstantaneously and without failure. BTMG loads are like co-located loads which “can pose \nreliability risks if their generation unexpectedly trips off-line and appropriate protection or ride-\nthrough systems are not in place [because] [t]he operational visibility and controllability of \n[behind-the-meter] loads are limited, making it more challenging to predict system impacts, \nespecially during uncontrolled transitions between on-site generation and grid supply that may \narise due to protection system failures.”60 If, after BTMG generation fails, the load unexpectedly \nshifts to drawing supply from the grid, for even a moment, the transmission system sees a rapid \ndemand spike, which may stress and harm the system.61 Moreover, as the Commission \nacknowledged, “PJM maintains that it is always possible that any protection system in an isolated \n \n59  New York v. FERC, 535 U.S. 1, 8–9 (2002).  \n60  NERC, Characteristics and Risks of Emerging Large Loads: Large Loads Task Force White Paper, at 13 (July \n2025), \nhttps://www.nerc.com/globalassets/who-we-are/standing-committees/rstc/whitepaper-characteristics-\nand-risks-of-emerging-large-loads.pdf. \n61  Id."},{"page":29,"startToken":10950,"endToken":11258,"text":"29 \n \n(but not islanded) Co-Location Arrangement could mis-operate, be disabled, or degrade, and that, \nin the few instances where such schemes exist on the PJM system, PJM has observed these \nschemes fail, and the load has taken grid service.”62  \nAs the Commission recognizes from PJM’s comments, “if the protection system fails, the \nlarge load would instantly take significant energy from the system” and “though a few such \nconfigurations may seem tolerable, the risk increases with large quantities of such \nconfigurations.”63 To address this risk, the Commission “direct[s] PJM to apply a penalty rate.”64 \nAssessing penalties, however, only addresses the issue after the fact and does not remediate the \nreliability implications of faulty protective systems.  \nAs previously discussed, because the Commission has not addressed these issues, it has not \nengaged in reasoned decision making and fails to satisfy the APA requirements. \nC. The June 18, 2026 Order is Arbitrary And Capricious To the Extent it Adopts \na Generator Funding Model for Network Upgrades Required for Service to \nLoads Served by BTMG \n \nIn the December 18, 2025 Order, as upheld in the June 18, 2026 Order, FERC adopted a \npolicy that Network Upgrades associated with the new forms of transmission service would be \npaid for using the Generator Funding Model, in which Generators are responsible for the Upgrade \nCosts.65 We presume that this ruling now extends to loads served by BTMG. This is a departure \nfrom the existing model for transmission service charges – in which loads simply pay a load ratio \nshare of the entire transmission system. 66 To be clear, the Commission has a different model for \n \n62  December 18, 2025 Order, 193 FERC ¶ 61,217 at P 44. \n63  Id. P 17. \n64  Id. P 212. \n65  June 18, 2026 Order at P 166. \n66  See, e.g. PJM Tariff P 34.1."},{"page":30,"startToken":11258,"endToken":11593,"text":"30 \n \nupgrade costs required to interconnect a generator – in which the generator may be required to pay \nthose costs – but that is a different situation because the generator is not a load, and absent those \npayments does not pay for transmission system costs at all.  The June 18, 2026 order conflates the \nfunding model applicable to upgrades required to serve load and the funding model applicable to \nupgrades required for generation. In the long run the Commission’s approach that has some \ncategories of load paying only incremental costs will lead to one set of loads paying far less than \nother loads for use of the same transmission system – that is, in the long run, payment of embedded \ncost rates on a load ratio basis will generally exceed a one-time assessment of incremental costs.  \n(Again, the situation is just different for generation – which does not owe anything in the long run \nunder load ratio mechanisms.) The Commission has not provided reasoned findings that the \nexisting approach for charging load leads to unreasonable results, nor has it provided reasoned \nanalysis in support of the new model.  \nAs explained above, the Commission’s policy for decades has been that the embedded costs \nof the transmission system are shared by all customers. To that end the costs of network upgrades \nare shared by all customers. This makes sense because “[t]he cost-causation principle requires that \n‘[t]he cost of transmission facilities . . . be allocated to those within the transmission planning \nregion that benefit from those facilities in a manner that is at least roughly commensurate with \nestimated benefits.’”67 \nAgain, under the PJM Tariff, as provided in Section 34.1, load pays all transmission costs. \nThe only exception is when the transmission system requires upgrades to accommodate requests \nby generators (not load) to interconnect. Charging load for the embedded costs of the system, \n \n67  Coal. of MISO Transmission Customers, 45 F.4th at 1009 (second and third alterations in original) (quoting S.C. \nPub. Serv. Auth., 762 F.3d at 53)."},{"page":31,"startToken":11593,"endToken":11986,"text":"31 \n \nincluding upgrades, makes sense because all loads benefit from the transmission network. The \nCommission provides no record evidence nor a reasoned explanation for why load served by \nBTMG should not be charged like other load, i.e., with the upgrade cost recovered as part of the \ntransmission rates charged to all customers.68  \nThe new approach to incremental costs – using a Generation Funding model that has not \npreviously been used for charges to load -- differs from the approach taken in the PJM Tariff, and \nthe Commission’s own OATT, which assign cost responsibility among all load by charging all \nnetwork customers (based on their respective load ratio shares) for incremental investments needed \nto reliably serve load expansion (in addition to making all network loads responsible for their share \nof pre-existing embedded system costs).69 The June 18, 2026 Order’s shifting of cost responsibility \nfrom the Load Model to the Generation Funding Model departs from traditional cost causation \nprinciples and is randomly applied only to certain cases where the added load is purportedly served \nthrough an existing generator interconnection facility. The simultaneous existence of conflicting \nfunding models is discriminatory, internally inconsistent with the June 18, 2026 Order’s retention \nof Network Service, and contrary to FERC’s cost-causation principles. The June 18, 2026 Order \n \n68  See State Farm, 463 U.S. at 43.  Of course, transmission owners are permitted to earn a reasonable return on the \ninvestments necessary to construct, operate, and maintain transmission facilities, including those network \nupgrades required to serve co-located load.  See, e.g., Fed. Power Comm’n., 320 U.S. 591; Bluefield Water Works \n& Improvement Co., 262 U.S. 679.  For decades, the Commission has recognized this principle by rolling the \ncosts of load-driven network upgrades into transmission rates.  The June 18, 2026 OrderJune 18, 2026 Order, \nhowever, departs from this longstanding approach without substantial record evidence or justification.  \nEliminating this opportunity for capital recovery with a reasonable rate of return not only creates regulatory \nuncertainty that undermines investor confidence, but further discourages investment in the transmission system \nat a time when such investment is critical.  Since the 2003 blackout, the electric industry has faced persistent \nchallenges in attracting private capital.  Abrupt policy shifts—such as narrowing rolled-in rate treatment—\nexacerbate these challenges, weaken financial performance, and deter investors who rely on stable, predictable \nreturns. \n \n69  See generally PJM Tariff Section 34.1."},{"page":32,"startToken":11986,"endToken":12306,"text":"32 \n \nfails to explain or justify this departure and therefore is arbitrary and capricious and not the product \nof reasoned decision making.70 \nThe Commission has failed to consider numerous issues arising from this disparate \ntreatment:  \nFirst, in some (if not most) cases, it will be a benefit to other customers to include new \nloads in the pool of payers for the existing transmission network rather than setting them apart and \nassigning them only the incremental cost for specific upgrades. By spreading the revenue \nrequirement for the transmission system generally over an increasing number of billing units— \na.k.a. “increasing the denominator”—it reduces what other customers pay for transmission.\n The \nundeniable fact is that large loads—not only because of their size, but also their high load factors, \nimpose significantly upon the overall transmission (and distribution) revenue requirement needs \nnow, and new co-located loads would do the same. By contributing to paying the cost of overall \nsystem on which they depend, these customers, like other customers, equitably, could help address \noverall concerns about affordability as the national energy grid transforms. But, if they are required \nto pay only for incremental investment, they avoid paying for the broader system upon which they \ndepend and that public benefit is lost. The more some loads are carved out to pay separately for \ncertain transmission infrastructure, the less they will pay for the overall grid and the more other \ncustomers will pay as a forced subsidy. \nOver the long term the calculus of requiring some loads to fund upgrades but not pay \notherwise for their use of the existing system, can play out in just one way: it is worse for other \ncustomers while it significantly and unduly benefits the select customers who get to enjoy the \nincremental-only pricing model. Once a load has fulfilled its responsibility (whether immediately \n \n70  See New England Power Generators Ass’n, Inc., 881 F.3d at 211."},{"page":33,"startToken":12306,"endToken":12588,"text":"33 \n \nor over time) for funding certain upgrades, such customers taking minimalistic contract demand \nservice will pay essentially no embedded costs. But the transmission system is not a one-and-done \ninvestment. The system evolves and requires maintenance to ensure reliability, resilience, and \nquality of service, all of which comes at a cost. Over time, the existing load ratio allocation scheme \nimposes more costs on the large loads. (Which is why the large loads do not like the model and \npropose alternatives.) Allowing a model where initial investment absolves some loads from \nfinancial contributions associated with the ongoing use of the system leaves other customers \nholding the bag. \nSecond, such an approach creates challenging dynamics like those we have seen in the \ngenerator interconnection space. For example, this approach likely benefits earlier loads that \nidentify favorable interconnection points, only for later customers to trigger significant upgrades, \nwhich once completed may lower costs for future load interconnection requests. Furthermore, \ntransmission system upgrade needs can be very sensitive to other large loads modifying their \nrequests or withdrawing, as well as overlapping issues with other aspects of transmission planning. \nNot only do these dynamics threaten to create inequities, they create incentives for speculative \nbehavior and point of interconnection “shopping,” with associated unpredictable requests and \nwithdrawals. This is precisely the kind of behavior that became so problematic, resource-intensive, \nand delay-inducing in the generator interconnection queue.  \nThird, not all large loads are as financially strong as data center owners. Allocating \ntransmission system upgrade costs up-front to those customers runs counter to the policy objective \nof promoting economic development by imposing too many near-term financial hurdles. While \nsome loads may have substantial access to capital, significant up-front requirements could hinder"},{"page":34,"startToken":12588,"endToken":12953,"text":"34 \n \neconomic development, particularly for many commercial and industrial customers that find \nthemselves included in a new paradigm designed to support AI data center interconnections.  \nIt also bears emphasis that large loads, co-located or otherwise, will not always trigger \nsignificant transmission upgrades. The expectation is that large new loads will make every effort \nto choose sites where the upgrades will be minor, and the harmful impact of their future exemption \nfrom transmission costs on other customers will not be offset at all. In short, it should not be \nassumed that large loads will trigger system upgrades with costs in excess of what they would \notherwise contribute to the system if they paid traditional network rates based on their load-share \nratio, and the June 18, 2026 Order erred in adopting a funding model around such a false premise.71  \n \nD. The Commission Is Wrong In Suggesting That CD Service Will Promote \nEfficiency Or Change Siting. \nTo be clear, under any circumstance, project development teams for new load, whether that \nload is co-located or not, already have a strong incentive to site their facilities on the grid at a \nlocation that minimizes the need for transmission upgrades. Project developers understand that \nadditional work can add cost, increase complexity, risk project delay, and result in lost opportunity. \nIn addition, and as discussed above, wise siting decisions will minimize the need for system \nupgrades, which will hasten interconnection. That benefit is real. But it has nothing to do with the \nproposed CD Service. This is because the impacts to the grid are based on physics and engineering. \n \n71  The Commission also lacked evidence to eliminate rolled-in rate treatment as an option for network upgrades.  \nHere again, the Commission failed to satisfy its burden under the APA.  By replacing rolled‑in rate treatment with \ndirect assignment to the co-located generator, without at least providing customers the option to select rolled-in \nrate treatment, the June 18, 2026 Order is arbitrary and capricious.  In the June 18, 2026 Order, the Commission \nfailed to (a) address material comments demonstrating system-wide benefits of transmission upgrades required \nby exiting generation, or (b) consider the alternative of permitting both rolled‑in rate treatment and direct \nassignment."},{"page":35,"startToken":12953,"endToken":13261,"text":"35 \n \nWhether the service paid for is based on net load or gross load does not change that planning and \nsiting depend on the physics and engineering of the grid.  \nThe Commission’s decision to require options for CD Service does not change how the \nstudy process should work. Regardless of cost-allocation, ensuring there is a reliable grid is \nessential and understanding what load amount the system needs to support is necessary. If \ntransmission providers are forced to pretend a 500 MW load is only 50 MW, or even that it is zero, \nand pretend away the physics and engineering impacts, it will threaten reliability and resource \nadequacy and therefore cannot be said to be just and reasonable. \nWhile protective systems can be beneficial, any suggestion that regional planning needs \nare automatically reduced by the establishment of CD Service is also not supported by evidence. \nNo loads should be taken out of the broader planning process—to do so would only threaten \nreliability of the system. Grid operators must plan for such eventualities to ensure system \nreliability.72  \nThe Commission finds in the December 18, 2025 Order that the BTMG “rules in PJM’s \nTariff are no longer just and reasonable because loads with BTMG are not fully accounted for in \nresource adequacy planning and shift costs onto other transmission customers contrary to the \nCommission’s cost causation principles.”73 In other words, the netting of BTMG against load for \ncalculating network cost responsibilities effectively shifts transmission costs. This ruling was \nupheld in the June 18, 2026 Order.74 Therefore, in the context of BTMG, FERC determined that \nBTMG, above a certain materiality threshold, should be considered to ensure resource adequacy \n \n72  See PJM Tariff §§ 31.1-31.3, 31.6, 32. \n73  December 18, 2025 Order, 193 FERC ¶ 61,217 at P 2. \n74  June 18, 2026 Order at P 145."},{"page":36,"startToken":13261,"endToken":13573,"text":"36 \n \nand that such BTMG output should not be netted against load. The Commission’s decision against \nthe netting of BTMG above a materiality threshold and the stated reasons for that decision cannot \nbe logically reconciled with the structure it proposed for the new transmission services. The very \nreasons that the Commission made this BTMG change are the same reasons that the new \ntransmission services are not just and reasonable – that is, loads served by BTMG impose demands \non the system (such as the need for reserves and capacity) that must be accounted for, and the new \nservices ignore those demands on the system. On this basis, the requirement for PJM to offer these \nservices cannot be said to be reasoned decision making and the Commission’s decision is arbitrary \nand capricious.75 \nE. The Commission’s Disregard of Reliability Considerations Underscores That \nThe Replacement Rate Is Not Just and Reasonable. \nThe new transmission service options reflect that the Commission overlooked important \nreliability concerns. The Commission’s ruling in the June 18, 2026 Order that the issue is \npremature highlights the fact that the Commission has not yet dealt with this issue.76 Further, the \nJune 18, 2026 Order continues to fail to address the fact that loads impact the system even when \nthere is no net power draw on the system. The Commission acknowledges as much when it finds \nthat the loads use the grid for load following based on gross load, not net load.77 Protective systems, \neven when fully functioning, are intended to keep net load at zero or below, but as the Commission \nhas held, it is the gross load that is being followed by resources elsewhere on the grid every minute \n \n75  See State Farm, 463 U.S. at 43. \n76 June 18, 2026 Order at P 131. \n77  See December 18, 2025 Order, 193 FERC ¶ 61,217 at P 209."},{"page":37,"startToken":13573,"endToken":13888,"text":"37 \n \nof the day, and thus using and impacting the system every minute of the day.78 The suggestion that \nprotective systems that only address net load obviate reliability concerns ignores physical reality.  \nFurther, the Commission in the June 18, 2026 Order does not squarely address flaws in that \nreasoning even though they were directly raised in the record regarding risks associated with \nprotective system failures or removal. Even if protective systems operated perfectly (and they do \nnot necessarily work perfectly) and penalties addressed any residual risk (again, they do not, \nespecially, and indeed, because the penalties are currently unknown), large loads may have an \nincentive to exceed their contract limitations for transmission service in some circumstances. The \nCommission has not explained how reliability planning may proceed in the face of that prospect. \nThe Commission’s decision to direct Interim Service be offered to load served by BTMG \nuntil all Network Upgrades necessary to provide the requested Network Service are completed \noverlooks potential resource adequacy risks. This service is, by definition, offered before needed \ntransmission upgrades are completed and it is unclear from the June 18, 2026 Order how it will be \ndetermined whether the load may be reliably served. The purpose of this interim service is “more \nrapid interconnection and operation of Co-Located Loads” and the only reliability check is a \ndetermination by PJM that it can provide “some level of interim service reliably.”79 The \nCommission’s decision is arbitrary and capricious. Among other things, we still do not know how \nPJM will determine whether it can provide “some level of interim service reliably” which is an \nissue that has been left for later compliance filings.80 Because “[t]he reasonableness of a rate is \nassessed in light of the FPA’s goals of promoting reliable service at reasonable rates and \n \n78  See id. \n79  Id. P 200.  \n80     June 18, 2026 Order at P 575."},{"page":38,"startToken":13888,"endToken":14386,"text":"38 \n \ndeveloping plentiful energy supplies,”81 and given that it is still unknown how one could \nreasonably determine what level of service can be provided before studies are conducted, it cannot \nbe said that these transmission service options are just and reasonable.82 The Commission has \nfailed to seriously take into account reliability implications in setting a replacement rate, and its \ndecision is therefore not reasoned decision making and is arbitrary and capricious. \nIV. \nFERC Exceeded Its Jurisdiction. \nA. FERC’s Replacement Rate Violates the Major Questions Doctrine. \nThere is no basis to change the PJM Tariff under FPA section 206 when the purpose of the \nchange is to provide preferential treatment or a preferred service to a certain category of customers. \nSuch action would violate the major questions doctrine. If Congress wanted to give the \nCommission authority to direct its preferred transmission service to benefit certain categories of \ncustomers, it could have done so.83 It did not do so. FERC, like all agencies, “ha[s] only those \npowers given to [it] by Congress, and ‘enabling legislation’ is generally not an ‘open book to which \n \n81  Constellation Mystic Power, LLC, 45 F.4th at 1035. \n82  Cf. Ameren Servs. Co. v. FERC, 880 F.3d 571, 580–81 (D.C. Cir. 2018) (finding that FERC “ma[de] no real \nattempt to holistically assess all of the various risks and benefits to the transmission owner caused by the addition \nof the upgrade facilities,” that “FERC inadequately considered [the] argument that all costs, and risks, are not \nbaked in—that, in fact, shareholders are forced to accept incremental exposure to loss with no corresponding \nbenefit” and therefore, that FERC’s “failure to meaningfully respond to it makes FERC’s decision arbitrary and \ncapricious”) (footnote omitted); Advanced Energy Mgmt. All., 860 F.3d at 664–65 (explaining the Commission’s \nrationales that “support[ed] the Commission’s finding that the energy market rules were unjust and unreasonable,” \nwhich included a rationale that “existing generator outage provisions ‘impede PJM’s ability to ensure reliability’ \nbecause they do not give PJM the authority to rescind approval for a planned outage when there is an emergency”) \n(citation omitted); Cent. Hudson Gas & Elec. Corp. v. FERC, 783 F.3d 92, 111 (2d Cir. 2015) (explaining that \nFERC, in creating the Lower Hudson Zone, considered long-term benefits that would follow accurate price \nsignals, including that it would “alleviate the risk of reliability problems in the long run”). \n83  Cf. Whitman v. Am. Trucking Ass’ns, 531 U.S. 457, 468 (2001) (“Congress, we have held, does not alter the \nfundamental details of a regulatory scheme in vague terms or ancillary provisions—it does not, one might say, \nhide elephants in mouseholes.”); see Atl. City Elec. Co., 295 F.3d at 8 (As a federal agency, “FERC is a ‘creature \nof statute,’ having ‘no constitutional or common law existence or authority, but only those authorities conferred \nupon it by Congress. Thus, if there is no statute conferring authority, FERC has none.”) (citation omitted)."},{"page":39,"startToken":14386,"endToken":14729,"text":"39 \n \nthe agency [may] add pages and change the plot line.”84 The Commission lacks authority under \nthe FPA to order a new type of transmission service with the sole purpose to benefit some \ncategories of load and to treat it differently from other loads that have similar system impacts and \nusage. Accordingly, the replacement rate directed by FERC—because it favors a narrow category \nof customers (i.e., load served by BTMG) without reasoned explanation—violates the requirement \nin the FPA that no rate by a public utility grants an undue preference or advantage or unreasonable \ndifference in rates.85  \nB.  The Commission’s New Approach Infringes On State Retail Authority.  \n \nThe states, not the Commission, have jurisdiction to decide when and in what \ncircumstances retail load will be curtailed, and how utilities should charge and treat retail \ncustomers in those circumstances. The Commission has jurisdiction over “the transmission of \nelectric energy in interstate commerce and to the sale of electric energy at wholesale in interstate \ncommerce,” and over “all facilities for such transmission or sale of electric energy.”86 Except as \notherwise provided in the FPA, the states retain jurisdiction over “any other sale of electric energy” \nand “over facilities used for the generation of electric energy or over facilities used in local \n \n \n84  \nWest Virginia v. EPA, 597 U.S. 697, 723 (2022) (third alteration in original) (citation omitted); see also Midship \nPipeline Co. v. FERC, 45 F.4th 867, 877 (5th Cir. 2022) (vacating part of the Commission’s order and remanding \nthe remainder because “[t]he FERC’s interpretation of the NGA to give the agency power to determine ‘the \nreasonable cost’ of remediation efforts ‘change[d] the plot line’ of its enabling legislation, and was therefore \nerroneous” and “[t]he FERC lacks such authority under the NGA, and it likewise lacked authority to order an ALJ \nto make such a determination indirectly”) (second alteration in original) (quoting West Virginia v. EPA, 597 U.S. \nat 723). \n85  16 U.S.C. § 824d(b). \n86  16 U.S.C. § 824(b)."},{"page":40,"startToken":14729,"endToken":15062,"text":"40 \n \ndistribution or only for the transmission of electric energy in intrastate commerce, or over facilities \nfor the transmission of electric energy consumed wholly by the transmitter.”87  \nStates decide how the retail obligation to serve should be met. For example, states might \nrequire the provision of backup service to retail customers who lose supply from their contracted \nsupplier (even if that supplier is BTMG), would regulate the distribution system costs associated \nwith such service that would be charged to the retail customer (even if the customer’s primary \nservice is provided by BTMG), and would regulate the costs and terms of the backup service. \nRather than honoring the states’ freedom and flexibility to exercise their jurisdiction over such \nquestions, the Commission’s new rule appears to create a new federal construct that defines the \nextent and terms of service in such situations. That is, the Commission’s new rules leave it entirely \nup to the customer to specify a contract demand service level that it will purportedly not exceed, \neven if state law mandates that the local utility provide the customer with backup service in the \nevent of an outage. The Commission’s conclusion that the customer will not take additional service \nlies in direct conflict with the states’ backup service mandates. The Commission does not have \nauthority under the FPA to dictate the terms of retail service in that fashion.  \nUnlike wholesale demand response programs, which “allow[] any state regulatory body to \nprohibit consumers in its retail market from taking part in wholesale demand response programs,” \nthereby “not requir[ing] any “‘action[ ] that would violate State laws or regulations,’” the \nCommission’s new forms of transmission services provide no such limitation.88 As the Supreme \nCourt has explained, however, “if indirect or tangential impacts on wholesale electricity rates \nsufficed, FERC could regulate now in one industry, now in another, changing a vast array of rules \n \n87  Id. \n88  FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 275 (2016) (third alteration in original) (citation omitted)."},{"page":41,"startToken":15062,"endToken":15479,"text":"41 \n \nand practices to implement its vision of reasonableness and justice,” a result that the Court could \nnot “imagine . . . was what Congress had in mind.”89 That is the problem here with FERC’s \nreplacement rate. \nAs the Supreme Court explained, the FPA \n“limit[s] FERC’s sale jurisdiction to that at wholesale,” reserving \nregulatory authority over retail sales (as well as intrastate wholesale \nsales) to the States. FERC cannot take an action transgressing that \nlimit no matter how direct, or dramatic, its impact on wholesale \nrates. Suppose, to take a far-fetched example, that the Commission \nissued a regulation compelling every consumer to buy a certain \namount of electricity on the retail market. Such a rule would \nnecessarily determine the load purchased on the wholesale market \ntoo, and thus would alter wholesale prices. But even given that \nineluctable consequence, the regulation would exceed FERC’s \nauthority, as defined in § 824(b), because it specifies terms of sale \nat retail—which is a job for the States alone.90 \nFERC’s CD Services similarly interfere with States’ regulation of the terms of sale at retail, \ndictating the terms and circumstances of service to end use customers who lose their contracted \nretail power supplier—an area that is directly within the States’ domain. The Commission is unable \nto do indirectly what it cannot do directly, which is what it does when it intrudes on state regulatory \nauthority over retail service in this fashion.91 \n \n89  Id. at 278. \n90  Id. at 279–80 (alteration in original) (citations omitted). \n91  Cf. Nat’l Fuel Gas Supply Corp. v. FERC, 909 F.2d 1519, 1522 (D.C. Cir. 1990) (“once want of power to do this \ndirectly were established, the existence of power to achieve the same end indirectly through the conditioning \npower might well be doubted”) (quoting Sunray Mid-Continent Oil Co. v. FPC, 364 U.S. 137, 152 (1960) and \nciting Richmond Power & Light v. FERC, 574 F.2d 610, 620 (D.C. Cir. 1978) (the Commission may not achieve \nindirectly through conditioning power of Federal Power Act what it is otherwise prohibited from achieving \ndirectly)); Am. Gas Ass’n, 912 F.2d at 1510 (“[T]he Commission may not use its § 7 conditioning power to do \nindirectly . . . things that it cannot do at all.”); see also FERC v. Elec. Power Supply Ass’n, 577 U.S. at 288 (“The \nFPA ‘leaves no room either for direct state regulation of the prices of interstate wholesales’ or for regulation that \n‘would indirectly achieve the same result.’”) (citation omitted)."},{"page":42,"startToken":15479,"endToken":15684,"text":"42 \n \nThe Commission should leave retail service questions to the retail regulator. The \nimposition of CD Service rates to usurp these questions exceeds the Commission’s lawful \nauthority. \nV. \nConclusion \nBecause neither the Commission nor any other complainant have satisfied their burden \nunder FPA section 206 and the Commission has not engaged in reasoned decision making in the \nJune 18, 2026 Order, the Commission should grant rehearing, revoke its directives June 18, 2026 \nOrder to establish new transmission service offerings for load served by BTMG, and instead, take \nno action pursuant to section 206 and find that the existing PJM Tariff is just and reasonable.  \n \nRespectfully submitted, \n \n/s/ William Sauer \nWilliam Sauer \nVice President, Federal Regulatory \nAffairs  \nExelon Corporation  \n701 Ninth St. N.W.  \nWashington, DC 20001  \nTelephone: 202-868-7499  \nEmail: william.sauer@exeloncorp.com  \n/s/ Bradley R. Perkins  \nBradley R. Perkins \nVice President and Deputy General Counsel \nExelon Corporation \nChase Building \n10 S. Dearborn, 52nd Floor \nChicago, IL 60603 \n(312)394-2632 \nTelephone: 312-394-2632 \nEmail: bradley.perkins@exeloncorp.com \n \n \nOn behalf of Exelon Corporation \n \n \n/s/ Amanda P. Parker \nAmanda P. Parker \nCorporate Counsel \nFirstEnergy Service Company \n341 White Pond Drive \nAkron, OH 44320 \nTelephone: (330) 384-4592 \nEmail: aparker@firstenergycorp.com  \n \n \n \nOn behalf of The FirstEnergy \nTransmission Companies"},{"page":43,"startToken":15684,"endToken":15731,"text":"43 \n \n \nCERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list in the above captioned dockets. \n \nDated at Chicago, IL this 20th day of July, 2026. \n \n \n/s/ Geneva Kennedy  \n  \nGeneva Kennedy  \nExelon Corporation"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":813,"startToken":0,"endToken":713},{"p":3,"at":813,"title":"I. Statement of Issues/Specification of Error.","method":"printed heading","endPage":11,"endAt":236,"startToken":713,"endToken":4113},{"p":11,"at":236,"title":"II. The Burden Under FPA Section 206 Has Not Been Met: The Existing Rate","method":"printed heading","endPage":11,"endAt":1586,"startToken":4113,"endToken":4338},{"p":11,"at":1586,"title":"A. There is No Evidence In The Record That Loads Served by BTMG Are","method":"printed heading","endPage":16,"endAt":1383,"startToken":4338,"endToken":6130},{"p":16,"at":1383,"title":"B. The Commission Did Not Engage in Reasoned Decision Making Because It","method":"printed heading","endPage":23,"endAt":145,"startToken":6130,"endToken":8854},{"p":23,"at":145,"title":"C. The Loads Rely Upon The Entire Embedded Transmission System To Serve","method":"printed heading","endPage":24,"endAt":1415,"startToken":8854,"endToken":9349},{"p":24,"at":1415,"title":"III. The Burden Has Not Been Met Under FPA Section 206: FERC’S Replacement","method":"printed heading","endPage":25,"endAt":6,"startToken":9349,"endToken":9496},{"p":25,"at":6,"title":"A. Allowing Special Treatment For Load Served by BTMG Violates The FPA’s","method":"printed heading","endPage":27,"endAt":273,"startToken":9496,"endToken":10220},{"p":27,"at":273,"title":"B. The Commission’s Emphasis On Protective Systems Is In Tension With The","method":"printed heading","endPage":29,"endAt":941,"startToken":10220,"endToken":11094},{"p":29,"at":941,"title":"C. The June 18, 2026 Order is Arbitrary And Capricious To the Extent it Adopts","method":"printed heading","endPage":34,"endAt":878,"startToken":11094,"endToken":12726},{"p":34,"at":878,"title":"D. The Commission Is Wrong In Suggesting That CD Service Will Promote","method":"printed heading","endPage":36,"endAt":802,"startToken":12726,"endToken":13392},{"p":36,"at":802,"title":"E. The Commission’s Disregard of Reliability Considerations Underscores That","method":"printed heading","endPage":38,"endAt":480,"startToken":13392,"endToken":13961},{"p":38,"at":480,"title":"IV. FERC Exceeded Its Jurisdiction.","method":"printed heading","endPage":38,"endAt":518,"startToken":13961,"endToken":13966},{"p":38,"at":518,"title":"A. FERC’s Replacement Rate Violates the Major Questions Doctrine.","method":"printed heading","endPage":39,"endAt":610,"startToken":13966,"endToken":14487},{"p":39,"at":610,"title":"B. The Commission’s New Approach Infringes On State Retail Authority.","method":"printed heading","endPage":42,"endAt":190,"startToken":14487,"endToken":15506},{"p":42,"at":190,"title":"V. Conclusion","method":"printed heading","endPage":43,"endAt":8,"startToken":15506,"endToken":15685},{"p":43,"at":8,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":43,"endAt":309,"startToken":15685,"endToken":15731}]}