{"document":{"slug":"rec-20260720-5181","title":"Constellation Energy Generation, LLC submits Limited Request for Rehearing and Clarification of the 06/18/2026 Order","issued":"2026-07-20","accession":"20260720-5181","docket":"ER26-1479-001","group":"PJM co-location compliance","filer":"Constellation Energy Generation, LLC","kind":"rehearing request","file":"sources/filings/text/20260720-5181_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260720-5181","tier":"record","sha256":"f9bbbde036ea6e81c3b84082a19a7daeb91d9db02d75a6ec769dbec0e0b40ec9","pages":19,"tokens":6634,"emptyPages":[],"textThemes":["colo","study","flex"]},"pages":[{"page":1,"startToken":0,"endToken":200,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM Interconnection, L.L.C., et al. \n \n \n \n \nLarge Loads Co-Located at Generating Facilities \n \n \n \nConstellation Energy Generation, LLC \n \n     v. \n \nPJM Interconnection, L.L.C. \n \n \n \nPJM Interconnection, L.L.C. \n) \n) \n) \n) \n) \n \n) \n) \n) \n \n) \n) \n) \n) \n) \n) \n) \n \n) \n) \n) \n \n \n \nDocket Nos. EL25-49-002 \nEL25-49-000 \n \n \n \nDocket No. AD24-11-001 \n \n \n \nDocket No. EL25-20-001 \n(consolidated) \n \n \n \n \n \n \nDocket No. ER26-1479-000 \nLIMITED REQUEST FOR REHEARING AND CLARIFICATION \nOF CONSTELLATION ENERGY GENERATION, LLC \nConstellation submits this limited request for rehearing and clarification of the June 2026 \nCo-Location Order.1 We raise four discrete points on rehearing to reinforce the Commission’s \nobjective of establishing sufficiently clear tariff terms to allow the speedy connection and service \nto Co-Located Loads in a way that “facilitate[s] more efficient use of the existing transmission \nsystem” and “limit[s] unnecessary transmission system buildout” in PJM.2 \n \n1 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209 (2026) (“June 2026 Co-Location Order”). \n2 Id. P 579; see also PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 160 (2025) (“December 2025 Co-Location \nOrder”) (“These new transmission service options reflect a Co-Located Load’s ability to limit withdrawals from the \ntransmission system and potentially avoid costly and inefficient transmission system buildout that may not be \nnecessary.”)."},{"page":2,"startToken":200,"endToken":502,"text":"2 \nFirst, the Commission should modify the June 2026 Co-Location Order to require study \ndeadlines, which are the most critical path for the speedy interconnection of Co-Located Loads \nand would be logically consistent with the ANOPR Show Cause Order.3 \nSecond, the Commission should require PJM to spell out in its Tariff the methodology and \nprocess (including deadlines) for completing Necessary Studies. These terms belong in the Tariff, \nand not the Manuals, because they “significantly affect rates, terms, and conditions” of service and \nare “readily susceptible to specification.”4 \nThird, the Commission should modify the operational penalty for the misoperation of \ncontrol technologies and/or protections to include only a two-strike disqualification as opposed to \na 120-day suspension on top of a two-strike disqualification. A 120-day suspension has no added \nreliability benefit, is inconsistent with existing practice, and could have a chilling effect that could \nresult in costly and unnecessary Network Upgrades. \nFourth, as Constellation recommended, the Commission should mitigate Transmission \nOwners’ proposals that give them unfettered discretion over the timelines and technical \nrequirements for necessary control technologies and/or protection systems. The Commission \nshould also require all Transmission Owner standards, requirements, guidance, and practices \nrelated to necessary control technologies and/or protection schemes for Co-Location \nArrangements to be on file with the Commission.5 The Commission failed to articulate its \nreasoning for rejecting these recommendations, rendering its decision arbitrary and capricious. \n \n3 PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (2026) (“ANOPR Show Cause Order”). \n4 Energy Storage Ass’n v. PJM Interconnection, L.L.C., 162 FERC ¶ 61,296, at P 103 (2018) (citing Cal. Indep. Sys. \nOperator Corp., 122 FERC ¶ 61,271, at P 16 (2008)). \n5 Response Brief of Constellation Energy Generation, LLC, Docket Nos. EL25-49-000 et al., at 10-12 (Apr. 24, 2026) \n(“Constellation Apr. 24 Response Brief”)."},{"page":3,"startToken":502,"endToken":862,"text":"3 \nIn addition, Constellation seeks clarification, or in the alternative, rehearing on the \nCommission’s denial of Constellation’s request to modify the definition of Co-Located Load \nGenerating Facility so that only the portion of the Generating Facility serving the Co-Located Load \nbe considered the Co-Located Generating Facility. When only a portion of a Generating Facility’s \ncapacity is dedicated to serving co-located non-network load (say, a 100 MW non-network load is \nco-located with a 500 MW generator), then only that portion should be considered a Co-Located \nGenerating Facility and required to delist. Alternatively, Constellation seeks rehearing on this \nissue. Constellation also requests that the Commission clarify the filing of an Interim Network \nIntegration Transmission Service (“NITS”) application by an applicant with a pending NITS \napplication does not restart the NITS process, sending the applicant to the “back of the line.” \nSTATEMENT OF ISSUES/SPECIFICATIONS OF ERROR \nIn accordance with section 713 of the Commission’s Rules of Practice and Procedure,6 \nConstellation respectfully submits the following statement of issues and specifications of error:  \n1. The June 2026 Co-Location Order is arbitrary and capricious because it fails to \nmeaningfully address Constellation’s comments that a replacement rate for the new \ntransmission services must include study deadlines. The June 2026 Co-Location \nOrder is also arbitrary and capricious because its failure to establish study deadlines \nfor the new transmission services is inconsistent with the contemporaneously issued \nANOPR Show Cause Order requiring study deadlines for the provision of \ntransmission service for large loads, and the Commission fails to acknowledge this \ninconsistency. Each of these shortcomings renders the June 2026 Co-Location \nOrder arbitrary and capricious. See 5 U.S.C. § 706(2)(A); Motor Vehicle Mfrs. \nAss’n of U.S., Inc. v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983) (“State \nFarm”); New England Power Generators Ass’n v. FERC, 881 F.3d 202, 210-11 \n(D.C. Cir. 2018) (“NEPGA”). \n2. The June 2026 Co-Location Order is arbitrary and capricious because it fails to \nexplain why Necessary Studies provisions that determine required upgrades—and \ntherefore significantly affect the rates, terms, and conditions of service—may be \n \n6 18 C.F.R. § 385.713(c)(1)-(2)."},{"page":4,"startToken":862,"endToken":1292,"text":"4 \nrelegated to unenforceable PJM Manuals rather than included in the Tariff. See 5 \nU.S.C. § 706(2)(A); State Farm, 463 U.S. at 43. \n3. The June 2026 Co-Location Order is arbitrary and capricious because its finding \nthat suspending new transmission service for an Eligible Customer up to 120 days \nafter the first misoperation of control technologies and/or protection systems is just \nand reasonable is not adequately supported by the facts, is logically inconsistent \nwith the Commission’s finding that PJM’s one-strike proposal for failing to follow \na curtailment or load shed directive is “unnecessarily strict,” and fails to engage \nwith Constellation’s arguments that a 120-day suspension is not consistent with \nexisting practice. Each of these shortcomings render the June 2026 Co-Location \nOrder arbitrary and capricious. See 5 U.S.C. § 706(2)(A); State Farm, 463 U.S. at \n43; Burlington Truck Lines v. United States, 371 U.S. 156, 168 (1962) \n(“Burlington”); NEPGA, 881 F.3d at 210-11. \n4. The June 2026 Co-Location Order is arbitrary and capricious because it confers \nunfettered discretion upon the Transmission Owners with respect to necessary \ncontrol technologies and protection systems without consideration of comments \nadvising otherwise. Failure to consider comments raised renders the June 2026 Co-\nLocation Order arbitrary and capricious. See 5 U.S.C. § 706(2)(A); State Farm, 463 \nU.S. at 43; NEPGA, 881 F.3d at 210-11. \n5. If the Commission does not clarify the definition of Co-Located Generating \nFacility, the June 2026 Co-Location Order is arbitrary and capricious because it \nfails to provide a logical basis for denying Constellation’s request that only the \nportion of the Generating Facility serving the Co-Located Load be considered the \nCo-Located Generating Facility. Failure to consider comments raised renders the \nJune 2026 Co-Location Order arbitrary and capricious. See 5 U.S.C. § 706(2)(A); \nState Farm, 463 U.S. at 43; NEPGA, 881 F.3d at 210-11. \nREQUEST FOR REHEARING \nI. \nThe Commission Should Require Study Deadlines Binding Both PJM and the \nTransmission Owners. \nThe June 2026 Co-Location Order fails to engage with repeated requests for the \nCommission to direct PJM and the Transmission Owners to establish and comply with study \ndeadlines for the new transmission services, which are imperative for the speedy interconnection \nof large loads.7 The Commission “decline[d] to direct PJM to provide more detail in its Tariff on \n \n7 See, e.g., Constellation Apr. 24 Response Brief at 2 (“Two simple solutions can prevent discrimination and delay: \nfirst, deadlines for deliverables from the Transmission Owners, such as studies, and second, requiring standards,"},{"page":5,"startToken":1292,"endToken":1807,"text":"5 \nthe process for studying requests for Interim NITS”—but did not provide any discussion of study \ndeadlines.8 For Firm Contract Demand Service and Non-Firm Contract Demand Service, the \nCommission directed that PJM adopt more precise terms and conditions similar to “the cluster \nstudy process” and study procedures in the Non-Firm Point-to-Point Transmission Service,9 \nrespectively, but also did not require study deadlines. The lack of study deadlines and any mention \nof them is a failure to engage in reasoned decision making and bad policy. \nFirst, failure to engage with comments raised is a violation of the Administrative Procedure \nAct (“APA”).10 Summarizing comments is not sufficient.11 The Commission must take the next \nstep of providing a substantive response to the comments raised. \nSecond, the absence of binding and enforceable deadlines for the new transmission services \nis inconsistent with the June 2026 Co-Location Order itself, where the Commission acknowledged \n \npractices, and technical requirements to be clear and on file at the Commission.”); id. at 11 (“the Commission can \ndirect PJM to establish deadlines for studies and other Transmission Owner approvals or consultation requirements. \nDeadlines are commonplace in PJM’s Tariff and procedures”); Constellation Energy Generation, LLC Reply Brief, \nDocket Nos. EL25-49-000 et al., at 17-18 (Mar. 25, 2026) (“Constellation Mar. 25 Reply Brief”) (“Deadlines and \nother mechanisms must be set forth in the Tariff to prevent Transmission Owners from needlessly delaying studies \nand unreasonably denying new transmission services.”); id. at 15 (“PJM must spell out in the Tariff the studies that \nit will perform in conjunction with the Co-Located Generating Facility and the timetable for completing these \nstudies.”); id. at 23 (“[A] detailed description of the studies to be performed and the timelines they are to be \ncompleted must be on file as they are a key element of the service to be provided and will directly implicate the time \nto provide such service.”); id. at 9 (“Clarification of what additional studies need to be performed, and the timeline \nfor such studies, will streamline the process.”); Protest and Comments of Constellation Energy Generation, LLC, \nDocket No. ER26-1479-000, at 17 (Mar. 16, 2026) (“Constellation 60-Day Compliance Filing Comments”) (“To \nachieve speed to market, there must be deadlines set forth in the Tariff to prevent needless and discriminatory \ndelays.”). \n8 June 2026 Co-Location Order, 195 FERC ¶ 61,209 at P 575. \n9 Id. PP 370, 373. \n10 NEPGA, 881 F.3d at 211 (finding “that FERC did not engage in the reasoned decisionmaking required by the \nAdministrative Procedure Act” because it “failed to respond to the substantial arguments put forward by Petitioners \nand failed to square its decision with its past precedent”) (emphasis added). \n11 June 2026 Co-Location Order, 195 FERC ¶ 61,209 at P 366 (“Constellation requests that the Commission deter \ndelays and potential disputes by … establishing deadlines for studies and other transmission owner approvals or \nconsultation requirements”); id. P 368. (“Constellation contends that the Commission should … direct that … studies \nbe on file, including study deadlines.”); id. P 358 (“Vistra and Constellation … argue that PJM provides no timelines \nor deadlines for processing transmission service requests”)."},{"page":6,"startToken":1807,"endToken":2292,"text":"6 \nthat “PJM also does not address a timeline for its study process,”12 yet declined to direct PJM to \nestablish one. The lack of study deadlines is also inconsistent with the Commission’s preliminary \nfinding in the contemporaneously issued ANOPR Show Cause Order that PJM’s Tariff is unjust \nand unreasonable because it lacks “a study deadline of no more than 60-90 calendar days” for \ntransmission service requests by Eligible Customers on behalf of large loads.13 The June 2026 Co-\nLocation Order does not acknowledge this inconsistency or attempt to reconcile it. The concerns \nanimating the ANOPR Show Cause Order study deadlines are the same as those that parties have \nraised in the PJM Co-Location proceeding. Failure to square precedent is a failure to engage in \nreasoned decision-making.14 \nThird, failure to require study deadlines binding on both PJM and the Transmission Owners \nis bad policy. The delays that have plagued the Necessary Study process demonstrate this. The \nabsence of binding and enforceable deadlines has allowed Transmission Owners to refuse to \nparticipate in the Necessary Study process and delay the interconnection of large loads for years.15 \n \n12 Id. P 372. \n13 ANOPR Show Cause Order, 195 FERC ¶ 61,211 at P 63. \n14 See NEPGA, 881 F.3d at 211 (finding “that FERC did not engage in the reasoned decisionmaking required by the \nAdministrative Procedure Act” because it “failed to respond to the substantial arguments put forward by Petitioners \nand failed to square its decision with its past precedent”) (emphasis added); see also State Farm, 463 U.S. at 43 \n(“Normally, an agency rule would be arbitrary and capricious if the agency … offered an explanation for its decision \nthat runs counter to the evidence before the agency ….”); id. (“[T]he agency must examine the relevant data and \narticulate a satisfactory explanation for its action including a ‘rational connection between the facts found and the \nchoice made.’”) (quoting Burlington, 371 U.S. at 168). \n15 See, e.g., Complaint Requesting Fast Track Processing of Constellation Energy Generation, LLC, Constellation \nEnergy Generation, LLC v. PJM Interconnection, L.L.C., Docket No. EL25-20-000, at 7 (Nov. 22, 2024) (“Exelon \nis refusing to process necessary studies on these grounds, demanding expensive upgrades under their unfiled \ninterconnection procedures, delaying agreed-upon work which will force a nuclear plant to take additional outages, \nand forcing additional services to be procured.”) (“Constellation Complaint”); id. at 7-8. (“Exelon fulfilled its \nresponsibilities as an interconnection provider to review PJM’s necessary studies for one Constellation nuclear \nstation, the LaSalle Clean Energy Center (‘LaSalle’), but later refused to do so at the other two stations, insisting \nthat Constellation or its potential customer must first apply for retail service and designate what sort of wholesale \ntransmission service it will take from Exelon.”); id. at 17 (“But for Constellation’s … Limerick Clean Energy Center \n(‘Limerick’) in Pennsylvania, Exelon has refused to conduct its review of PJM’s completed necessary studies,"},{"page":7,"startToken":2292,"endToken":2866,"text":"7 \nDeadlines binding only PJM, but not the Transmission Owners, have failed to produce the timely \ncompletion of studies. Indeed, PJM’s Form of Necessary Studies Agreement provides that PJM’s \n“good faith estimate for the time of completion of Necessary Studies is within 270 days,” or just \nless than 9 months, from the date that PJM “approves the dynamic model and data submitted by \nProject Developer.”16 Yet (and aside from the inconsistency with the 60 to 90 day timing in the \nANOPR Show Cause Order), Constellation has been waiting years for Necessary Studies for \nmultiple projects, where the Transmission Owner simply refused to cooperate with PJM. New \ntransmission service requests will be subject to the same delays unless the Commission requires \nPJM to establish and enforce deadlines that bind both PJM and the Transmission Owners. \n \ninsisting that Constellation or its potential customer must first apply for retail service and designate what sort of \nwholesale transmission service it will take from Exelon.”); id. at 8 (“projects are being held hostage by a few \nmonopolies refusing to cooperate with reliability studies related to interconnection modifications”); id. at 10 n.25 \n(“Exelon refuses to review co-location reliability studies as required by the OATT and pro forma ISA”) (citing \nConstellation PDO Protest, Exhibit 1, Declaration of James R. McCoskey at ¶ 13); id. at 16 (“Proposed Fully Isolated \nCo-Located data center projects in PJM are currently being held hostage by one or two monopoly utilities’ refusal \nto cooperate … with reliability studies related to interconnection modifications.”); see also Constellation Energy \nGeneration, LLC November 21, 2025 Supporting Comments, Docket No. RM26-4-000, at 3-4 (Nov. 21, 2025) \n(“Some Transmission Owners have simply refused to participate in PJM’s studies to analyze reliability impacts; and \nsome, acting under unfiled interconnection study procedures, have changed their entire construct and timetable for \nprocessing load studies.”); Answer of Constellation Energy Generation, LLC, PJM Interconnection, L.L.C. et al., \nDocket Nos. EL25-49-000, et al., at 3 (Apr. 23, 2025) (“The Indicated Transmission Owners read the existing Tariff \nto require this one-size-fits-all limitation, and they have refused to perform studies for new load seeking a different \nconfiguration.”); id. at 14 (“What is more, regardless of what the Tariff actually says and does not say, some of the \nIndicated Transmission Owners have refused to cooperate in PJM’s ‘necessary studies’ process unless the load \nagrees to taking NITS, claiming justification under the Tariff. Some of the Indicated Transmission Owners have \nrefused to process necessary studies, demanded expensive upgrades under their unfiled interconnection procedures, \nand forced a generator seeking to serve co-located load to procure additional services not required by the Tariff.”) \n(citing Constellation Complaint at 7); Constellation Complaint at 9 (“Exelon’s also is refusing to perform work on \nLaSalle’s interconnection facilities to accommodate co-location, none of which affects the grid. Exelon’s refusal to \ncomplete previously agreed-upon work as scheduled during an upcoming planned outage will increase costs to \nConstellation by $15.3-$19 million at that site alone, just so Exelon can pursue its litigation positions.”); see also \nPJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at P 75 (2025) (“[T]here are allegations in the record that Exelon \nhas delayed work on Constellation’s requests to co-locate load with its generators at certain facilities due to Exelon’s \nconcerns that such requests are not allowed under the Tariff without arranging for wholesale transmission or retail \ndistribution service.”). \n16 PJM Tariff, Part IX, Subpart G, § 15 (Form of Necessary Studies Agreement)."},{"page":8,"startToken":2866,"endToken":3226,"text":"8 \nUsing its authority to establish a just and reasonable replacement rate,17 the Commission \nshould modify its June 2026 Co-Location Order to require PJM to establish such study deadlines. \nRequiring PJM to establish a deadline would not constrain PJM’s discretion in determining how \nbest to maintain the reliability of the transmission system. PJM would remain free to propose \nappropriate deadlines, provided those deadlines are reasonable. \nThe Commission also should require PJM to establish Necessary Study deadlines binding \nboth PJM and the Transmission Owners. While the December 2025 Co-Location Order did not \ndirect revisions to the Necessary Study process,18 the Commission has the authority to modify its \norders before the record is filed in the court of appeals.19 Here, the record demonstrates that PJM’s \nTariff is unjust and unreasonable because the Necessary Studies provisions do not support their \ntimely completion.20  \nII. \nThe Commission Should Direct PJM to Clarify its Necessary Study Process in its Tariff \nInstead of its Manual. \nIn response to our argument that PJM’s proposed tariff revisions identifying the scope of \nthe Necessary Study Process requires “additional clarity,”21 the Commission “direct[ed] PJM to \nspecify in its compliance filing what types of additional detail about the studies will be available \nin the PJM manuals.”22 Additional details should be included in the Tariff, not the Manuals.  \n \n17 16 U.S.C. § 824e. \n18 June 2026 Co-Location Order, 195 FERC ¶ 61,209 at P 281 (“While parties request that the Commission establish \ndeadlines for the Necessary Study process, we note the December Order did not include any such requirement, and \nour review of these proposed Tariff revisions is limited to whether PJM complies with the directives in the December \nOrder.”). \n19 16 U.S.C. § 825l(a) (“[T]he Commission may at any time, upon reasonable notice and in such manner as it shall \ndeem proper, modify or set aside, in whole or in part, any finding or order made or issued by it under the provisions \nof this Act.”). \n20 See supra note 15. \n21 Constellation 60-Day Compliance Filing Comments at 12. \n22 June 2026 Co-Location Order, 195 FERC ¶ 61,209 at P 280."},{"page":9,"startToken":3226,"endToken":3662,"text":"9 \nNecessary Studies, along with the methodology and process for performing them and the \nresults that methodology and process will produce, “significantly affect rates, terms, and \nconditions”23 of generator interconnection. While including high-level descriptors of the “studies” \nto be performed in the Necessary Study Process is an improvement to PJM’s current Tariff,24 PJM \nmust also include in the Tariff a description of the methodology and process for performing the \nstudies, including deadlines for completing the studies and any consultation requirements. A \nframework for how Necessary Studies will be performed and completed is not a “mere \nimplementation detail[]”25 that may remain unenforceable and subject to unilateral change without \nnotice or Commission oversight.26 How studies are performed determines whether a planned \nmodification will have a “permanent material impact on the Transmission System” and the \nupgrades to the Transmission System that are deemed “necessary.”27 And like the Tariff \nrequirements for studies performed for other interconnection and transmission requests,28 a \n \n23 Energy Storage Ass’n v. PJM Interconnection, L.L.C., 162 FERC ¶ 61,296 at P 103. \n24 Id. \n25 See Hecate Energy Greene Cnty. 3 LLC v. FERC, 72 F.4th 1307, 1312 (D.C. Cir. 2023) (“The tariff need not include \nmere implementation details.”). \n26 See RWE Clean Energy, LLC v. PJM Interconnection, L.L.C., 194 FERC ¶ 61,212, at P 38 (2026) (“The \nCommission does not review and approve PJM’s manuals, as they are not filed with the Commission. As a result, \nwe have no statutory obligation to enforce the terms of Manual 14B.”) (citations omitted). \n27 PJM Tariff, Part VII, Subpart A, § 400 (definition of (“Necessary Study”). \n28 See, e.g., id. Part VI, Attachment D (Methodology for Completion of System Impact Study); TranSource, LLC v. \nPJM Interconnection, L.L.C., 168 FERC ¶ 61,119, at P 83 (2019) (requiring that PJM include in its Tariff “high-\nlevel summaries of: (1) a definition of the models used to evaluate IARR requests, including descriptions of the \nIARR market model and the planning model; (2) a description of how the market limits or operative constraints in \nthe market model are determined; and (3) a detailed explanation of how ‘simultaneous feasibility’ is determined for \nIARR requests, including a description of how PJM conducts the ‘simultaneous feasibility test’ and determines the \n‘incremental capability required’ for IARR requests to be granted”); see also ISO New England, Inc., 187 FERC \n¶ 61,017, at P 13 (2024) (“the meter data submission deadline is a key component of metering practices for DER \nAggregators that should be included in the basic description of metering practices in the Tariff”)."},{"page":10,"startToken":3662,"endToken":3987,"text":"10 \ndescription of the Necessary Studies methodology and process, including study and consultation \ndeadlines, is “readily susceptible to specification.”29  \nThe Necessary Study Process is a leading cause of the delay of co-located load \ninterconnections. The Commission should ensure rules on the Necessary Study Process are clearly \nstated in the Tariff, so that everyone – transmission owners and market participants alike – know \nthe applicable rules, which can then be enforced by the Commission. \nIII. \nA Two-Strike Disqualification Is a Sufficient Deterrent and Alone Should Be the Just \nand Reasonable Replacement Rate. \nThe Commission failed to adequately support its finding that suspending new transmission \nservice for an Eligible Customer up to 120 days after the first misoperation of control technologies \nand/or protection systems is just and reasonable.30 While an investigation of the misoperation is \nappropriate, imposing a four-month suspension while the investigation is ongoing is not. The \nCommission should reject the 120-day suspension and approve only the two-strike disqualification \npenalty for the misoperation of control technologies and/or protection systems as the just and \nreasonable operational penalty. \nFirst, suspending service for an Eligible Customer for 120 days will have no added \ndeterrence value or reliability benefit on top of imposing a two-strike disqualification penalty.31 A \ntwo-strike disqualification penalty will sufficiently incentivize Co-Located Loads to make sure \nthey are “willing and able to limit their energy withdrawals.”32 Faced with the commercial risk \n \n29 Energy Storage Ass’n v. PJM Interconnection, L.L.C., 162 FERC ¶ 61,296 at P 103. \n30 June 2026 Co-Location Order, 195 FERC ¶ 61,209 at P 516. \n31 Id. P 524 (“We find that this replacement rate serves to deter conduct contrary to the fundamental principle around \nwhich the new transmission services created by the Commission were based, i.e., that Eligible Customers taking \nservice on behalf of Co-Located Loads are willing and able to limit their energy withdrawals from the transmission \nsystem under certain conditions.”). \n32 Id. P 524."},{"page":11,"startToken":3987,"endToken":4389,"text":"11 \n(and potential commercial penalties) of disqualification and the years-long NITS process,33 Co-\nLocated Loads will seek to ensure they do not cause or allow the misoperation of necessary control \ntechnologies and/or protections schemes. Imposing a 120-day suspension regardless of the Eligible \nFacility’s or load’s fault, will not make loads or Eligible Customers any more diligent. In fact, \ngiven the increased risk and uncertainty, loads that are otherwise willing and able to limit their \nwithdrawals could be deterred from applying for the new transmission services and, instead, elect \nNITS, leading to “unnecessary transmission system buildout.”34 \nNor do the North American Electric Reliability Corporation’s (“NERC”) reliability \nstandards require suspension of service when a protection scheme misoperates today. NERC \nreliability standards require that the misoperation be investigated and a corrective action plan \ndeveloped.35 If the Commission believes more should be required to ensure reliability, it can direct \nNERC to evaluate and establish reliability standards through the ordinary statutory process. \nSecond, the Commission’s approval of the 120-day suspension is logically inconsistent \nwith its finding that PJM’s one-strike proposal for failing to follow a curtailment or load shed \n \n33 See, e.g., Comments of Talen Energy Corp., Docket No. AD24-11-000, Analysis Group Report at 12 n.43 (Oct. 28, \n2024) (describing wait times to plan, design, site and construct a new grid connection to be as long as seven years \nfor Dominion and seven to ten years for AEP). \n34 June 2026 Co-Location Order, 195 FERC ¶ 61,209 at P 579. \n35 See Reliability Standard PRC-004-6, Protection System Misoperation and Identification, at R1 (“Each Transmission \nOwner, Generator Owner, and Distribution Provider that owns a BES interrupting device that operated under the \ncircumstances in Parts 1.1 through 1.3 shall, within 120 calendar days of the BES interrupting device operation, \nidentify whether its Protection System component(s) caused a Misoperation ….”); id. at R5 (“Each Transmission \nOwner, Generator Owner, and Distribution Provider that owns the Protection System component(s) that caused the \nMisoperation shall, within 60 calendar days of first identifying a cause of the Misoperation: … Develop a Corrective \nAction Plan (CAP) for the identified Protection System component(s), and an evaluation of the CAP’s applicability \nto the entity’s other Protection Systems including other locations” or “Explain in a declaration why corrective actions \nare beyond the entity’s control or would not improve BES reliability, and that no further corrective actions will be \ntaken.”)."},{"page":12,"startToken":4389,"endToken":4798,"text":"12 \ndirective is “unnecessarily strict.”36 A four-month loss of transmission service—that has the \npotential to be economically ruinous—effectively amounts to a one-strike proposal.37 If \ndisqualification after the first failure to follow a load shed or curtailment directive is “unnecessarily \nstrict,” so too should a four-month disqualification for the misoperation of control technologies \nand/or protection systems that may be unrelated to actions taken by the load or Eligible Customer. \nThird, the Commission’s finding failed to consider arguments Constellation raised in its \nMay 11 Answer.38 Our May 11 Answer explained that PJM’s claim its 120-day suspension was \n“consistent” with NERC requirements was incorrect, stating, “[t]he NERC Reliability Standards \nthat PJM cites—PRC-004-6 (Protection System Misoperation Identification and Correction) and \nPRC-012-2 (Remedial Action Schemes)—set forth a process for investigating whether protection \nsystems misoperated and for developing a Corrective Action Plan if appropriate” but neither \nreliability standard “call[ed] for suspension or disqualification of service while an investigation is \nongoing.”39 While the Commission summarizes our comments,40 the Commission does not \nprovide a substantive response.41 Failure to respond to comments raised is an APA violation.42 \n \n36 June 2026 Co-Location Order, 195 FERC ¶ 61,209 at P 515; see also State Farm, 463 U.S. at 43 (“Normally, an \nagency rule would be arbitrary and capricious if the agency … offered an explanation for its decision that runs \ncounter to the evidence before the agency ….”). \n37 Depending on the nature of the load, such a loss of service could have ramifications beyond just economic impacts \nfor the owner. For example, if the load is a data center running critical national security, banking, medical, \neducational or similar critical applications, the impact may be far broader than just to the owner of the load. \n38 Motion for Leave and Answer of Constellation Energy Generation, LLC (May 11, 2026) (“May 11 Answer”). \n39 Id. at 9-10. \n40 June 2026 Co-Location Order, 195 FERC ¶ 61,209 at P 514. \n41 See id. PP 523-24. \n42 See NEPGA, 881 F.3d at 211 (finding “that FERC did not engage in the reasoned decisionmaking required by the \nAdministrative Procedure Act” because it “failed to respond to the substantial arguments put forward by Petitioners \nand failed to square its decision with its past precedent”) (emphasis added); see also State Farm, 463 U.S. at 43 \n(“[T]he agency must examine the relevant data and articulate a satisfactory explanation for its action”)."},{"page":13,"startToken":4798,"endToken":5169,"text":"13 \nIf the Commission denies our request for rehearing, the Commission should clarify that an \nEligible Customer could still take transmission service on behalf of other loads during the \nsuspension period. This change is necessary to make the suspension and disqualification provisions \nconsistent. The June 2026 Co-Location Order found it not just and reasonable to “disqualify the \nEligible Customer as a whole from taking the relevant transmission service” after the two strikes \nand directed PJM to revise its Tariff to allow the Eligible Customer to “still take transmission \nservice, including Interim NITS, FCD transmission service, and NFCD transmission service, on \nbehalf of other loads through other transmission service agreements.”43 The same should apply to \nthe suspension period if the penalty is not removed. \nIV. \nTransmission Owners Should Not Have Unfettered Discretion over Necessary Control \nTechnology Configurations and Resumption of Service After a Misoperation. \nTwo findings in the June 2026 Co-Location Order are arbitrary and capricious because they \ngrant Transmission Owners unfettered discretion over necessary control technologies and \nprotection systems without addressing comments that cautioned against such unchecked \nauthority.44 First, the Commission finds that “it is reasonable” that service may resume after the \nsuspension “following PJM’s approval, as well as the relevant transmission owner’s approval of \nthe necessary control technologies and/or protection systems for consistency with the transmission \nowner’s technical standards.”45 Second, the Commission states, “the transmission owners shall \n \n43 June 2026 Co-Location Order, 195 FERC ¶ 61,209 at P 527. \n44 See Constellation Apr. 24 Response Brief at 10 (“The Commission should also act to mitigate the Transmission \nOwners’ new proposals that could give them unfettered discretion over the timelines and technical requirements, \nincluding the following Transmission Owner requests: … ‘[T]he relevant Transmission Owner’s approval must be \nincluded in the process of allowing service to be reinstated’ after service was suspended; ‘[T]echnical requirements \nshould also require an Eligible Customer to satisfy any applicable Transmission Owner-imposed technical \nrequirements;’ ‘PJM Transmission Owners request that PJM add, as a condition precedent for receiving service, that \nthe Eligible Customer satisfy any load-connection related requirements imposed by the applicable PJM \nTransmission Owner(s);’….”) (emphasis and citations omitted). \n45 June 2026 Co-Location Order, 195 FERC ¶ 61,209 at P 524 (emphasis added)."},{"page":14,"startToken":5169,"endToken":5413,"text":"14 \nhave the option to review and agree to the implementation of the Eligible Customer’s necessary \ncontrol technologies and/or protection systems as defined in the service agreement.”46 \nWhile it may be reasonable for Transmission Owners to review necessary control \ntechnologies and/or protection systems, that review should be bound by Good Utility Practice and \nclear deadlines. Simply stated, Transmission Owners do not favor Co-located Load arrangements \nand have delayed their implementation when given the opportunity to do so.47 As a result, \nTransmission Owner review of necessary control technologies and/or protections systems should \nbe consistent with Good Utility Practice, consent should not be unreasonably withheld, and \nTransmission Owner review should be completed within a reasonable time frame (no longer than \n30-60 days). \nAs Constellation previously recommended, the Commission should direct PJM to establish \ndeadlines for Transmission Owner approvals or consultation requirements and require PJM’s and \nTransmission Owners’ standards, requirements, guidance, and practices on necessary control \ntechnologies and protection schemes for Co-Location Arrangements to be on file with the \nCommission on a standalone basis or reflected in PJM’s Tariff.48 Rules for Co-Location \nArrangements must be clearly stated and available as they determine the necessary control \ntechnologies and protection systems which are a prerequisite to obtaining the new services and \ntherefore “significantly affect rates, terms, and conditions” of service and can be “readily \n \n46 Id. P 487 (emphasis added). \n47 See supra note 15. \n48 Constellation Apr. 24 Response Brief at 10-12."},{"page":15,"startToken":5413,"endToken":5737,"text":"15 \nsusceptible to specification.”49 They cannot be hidden and subject to unilateral change without any \nnotice or without any Commission oversight.50  \nCLARIFICATION \nI. \nThe Commission Should Direct PJM to Revise the Definition of Co-Located Generating \nFacility to Conform to the December 2025 Co-Location Order. \nWe seek clarification on the Commission’s denial51 of Constellation’s request to revise \nPJM’s definition of Co-Located Generating Facility to “mean the portion of an existing or planned \nGenerating Facility that the Interconnection Customer designates to serve and is physically \nconnected to a Co-Located Load.”52 Constellation proposed this revision to conform the definition \nof Co-Located Generating Facility with the December 2025 Co-Location Order that specifically \ncontemplated a “portion of the generating facility [will] be designated to serve any Co-Located \nLoad that is not receiving NITS.”53 No party opposed. Based on these facts, it is unclear why the \nCommission disagreed. The Commission should direct PJM to revise its definition on compliance. \nA more precise definition in the PJM Tariff is critical to reduce uncertainty and potential \nlitigation, expedite the interconnection of large loads, and ensure the intent of the December 2025 \nCo-Location Order is achieved. Without adding a modifier to “Generating Facility,” some could \ninterpret Co-Located Generating Facility as including the entire capacity at a generation site even \nif only a portion of the capacity is contracted to serve the Co-Located Load. For example, where a \n500-MW unit serves a 100-MW Co-Located Load, some could consider the entire 500 MW facility \n \n49 Energy Storage Ass’n v. PJM Interconnection, L.L.C., 162 FERC ¶ 61,296 at P 103. \n50 See supra note 26 (citing RWE Clean Energy, LLC v. PJM Interconnection, L.L.C., 194 FERC ¶ 61,212 at P 38). \n51 June 2026 Co-Location Order, 195 FERC ¶ 61,209 at P 312. \n52 Constellation 60-Day Compliance Filing Comments at 17 (emphasis in original).  \n53 Id. (quoting December 2025 Co-Location Order, 193 FERC ¶ 61,217 at P 230)."},{"page":16,"startToken":5737,"endToken":6019,"text":"16 \nas the Generating Facility and thus the Co-Located Generating Facility. This is because PJM \ndefines “Generating Facility” as meaning a “Project Developer’s device for the production and/or \nstorage for later injection of electricity” which “consists of one or more generating unit(s) and/or \nstorage device(s).”54 It is unclear how the June 2026 Co-Location Order’s reference to Part IX, \nSubpart A Form of Application and Studies Agreement, section 2 resolves our concern.55 \nMoreover, including the entire capacity of a Generating Facility into a Co-Located \nGenerating Facility has real and substantive consequences.56 The Commission found that existing \ngenerators that are Co-Located Generating Facilities must delist their Capacity Interconnection \nRights when serving a non-network Co-Located Load.57 The Commission should clarify that a \nhypothetical 500-MW unit serving a 100-MW Co-Located Load via contract demand service is \nnot required to delist the entire 500 MW when the load is only 100 MW. Such a requirement would \nneedlessly take megawatts out of the system and reduce the capacity available for existing PJM \ncustomers. \nIf the Commission does not grant our clarification, we request rehearing for the \nCommission’s failure to engage in reasoned decision making for failing to provide a rational \nresponse to the comments raised. \nII. \nAn Applicant with a Pending NITS Application Should Be Allowed to Request Interim \nNITS Without Restarting the NITS Process. \nConstellation proposed a transitional mechanism that would allow NITS applicants with \npending applications to also be deemed to have applied for Interim NITS. The Commission stated \n \n54 PJM Tariff, Part VIII, Subpart A, section 400, Definitions G. \n55 June 2026 Co-Location Order, 195 FERC ¶ 61,209 at P 312. \n56 Id. \n57 Id. P 159."},{"page":17,"startToken":6019,"endToken":6365,"text":"17 \nthat this is “unnecessary” because “PJM’s proposal does not prohibit any NITS applicant from \nalso applying for Interim NITS.”58 That is not responsive to Constellation’s point. To be sure, \nConstellation agrees that an applicant with a pending NITS application should be allowed to apply \nfor Interim NITS.59 But Constellation’s concern relates to pending NITS applications. Applicants \nwith NITS applications already on file should not be required to go to the back of the line if they \nwish to apply for Interim NITS service as well. \nAccordingly, Constellation requests that the Commission direct PJM to clarify that an \nInterim NITS request can be added to a pending NITS application without causing the applicant \nto restart or delay the NITS process. After all, PJM “designed the new Interim NITS to basically \nbe treated the same as regular, full NITS.”60 In this respect, the process for any pending NITS \nrequest would have been nearly identical had the initial request been for Interim NITS service. In \naddition, in some service territories, NITS applicants have been waiting nearly a decade to be \ninterconnected to the grid.61 These applicants should not have to wait any longer for service. If \nthese applicants will be forced to the “back of the line” for requesting Interim NITS, most are \nunlikely to do so even though they may be willing and able to limit their energy withdrawals. The \nCommission and PJM will have unnecessarily reduced the pool of large loads that are “critical to \n \n58 See id. P 578. \n59 Constellation Mar. 25 Reply Brief at 14 (“PJM should revise its proposal to clarify that large loads with pending \nNITS applications may apply for Interim NITS.”). \n60 Reply Brief of PJM Interconnection, L.L.C. at 1 (Apr. 24, 2026). \n61 See, e.g., Comments of Talen Energy Corp., Docket No. AD24-11-000, Analysis Group Report at 12 n.43 (Oct. 28, \n2024) (describing wait times to plan, design, site and construct a new grid connection to be as long as seven years \nfor Dominion and seven to ten years for AEP)."},{"page":18,"startToken":6365,"endToken":6556,"text":"18 \nsupporting the innovation economy, leading the global race on artificial intelligence, and reshoring \nmanufacturing jobs back to the United States.”62 \nCONCLUSION \nFor the reasons set forth above, Constellation respectfully requests that the Commission \ngrant rehearing and clarification of the June 2026 Co-Location Order. \n \n \n \n \n \n \n \n    Respectfully submitted, \n \n \n \n \n \n \n \n    /s/ Paul F. Wight \n \n \n \nJuly 20, 2026 \n \n62 See FERC, FERC Launches Aggressive Targeted Action to Speed Large Load Integration (June 18, 2026), \nhttps://ferc.gov/news-events/news/ferc-launches-aggressive-targeted-action-speed-large-load-integration. \nCarrie Hill Allen \nSr. Vice President & Deputy General Counsel \nSeth T. Lucia \nAssistant General Counsel \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \ncarrie.allen@constellation.com \nseth.lucia@constellation.com \n  \nChristopher A. Wilson \nVice President, Federal Regulatory Affairs \nConstellation Energy Generation, LLC \n250 Massachusetts Ave. NW, Suite 760 \nWashington, D.C. 20001 \n202-347-7500 \nFERCe-filings1@constellation.com \n \nPaul F. Wight \nCarolyn E. Clarkin \nDLA Piper LLP (US) \n500 Eighth Street NW \nWashington, D.C. 20004 \n703-773-4058 \npaul.wight@us.dlapiper.com  \ncarolyn.clarkin@us.dlapiper.com  \n \nSophia Browning \n4365 Executive Drive \nSuite 1100 \nSan Diego, CA 92121 \n858-677-1455 \nsophia.browning@us.dlapiper.com \n \nCounsel for Constellation Energy \nGeneration, LLC"},{"page":19,"startToken":6556,"endToken":6634,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have on this 20th day of July, 2026, caused to be served a copy of \nthe foregoing upon all parties on the service lists in these proceedings in accordance with the \nrequirement of Rule 2010 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. \n§ 385.2010 (2025). \n/s/ Sophia Browning \n \n \nSophia Browning \n4365 Executive Drive \nSuite 1100 \nSan Diego, CA 92121 \n858-677-1455 \nsophia.browning@us.dlapiper.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":4,"endAt":2014,"startToken":0,"endToken":1185},{"p":4,"at":2014,"title":"I. The Commission Should Require Study Deadlines Binding Both PJM and the","method":"printed heading","endPage":8,"endAt":944,"startToken":1185,"endToken":3009},{"p":8,"at":944,"title":"II. The Commission Should Direct PJM to Clarify its Necessary Study Process in its Tariff","method":"printed heading","endPage":13,"endAt":828,"startToken":3009,"endToken":4922},{"p":13,"at":828,"title":"IV. Transmission Owners Should Not Have Unfettered Discretion over Necessary Control","method":"printed heading","endPage":15,"endAt":168,"startToken":4922,"endToken":5437},{"p":15,"at":168,"title":"I. The Commission Should Direct PJM to Revise the Definition of Co-Located Generating","method":"printed heading","endPage":16,"endAt":1356,"startToken":5437,"endToken":5944},{"p":16,"at":1356,"title":"II. An Applicant with a Pending NITS Application Should Be Allowed to Request Interim","method":"printed heading","endPage":18,"endAt":156,"startToken":5944,"endToken":6387},{"p":18,"at":156,"title":"CONCLUSION","method":"printed heading","endPage":19,"endAt":0,"startToken":6387,"endToken":6556},{"p":19,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":19,"endAt":464,"startToken":6556,"endToken":6634}]}