{"document":{"slug":"rec-20260720-5199","title":"Eolian, L.P., et. al. submit Request for Clarification or, in the Alternative, Rehearing of the 06/18/2026 Order","issued":"2026-07-20","accession":"20260720-5199","docket":"ER26-1479-001","group":"PJM co-location compliance","filer":"Eolian, L.P.Calibrant EnergyVerrus LLC ,","kind":"rehearing request","file":"sources/filings/text/20260720-5199_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260720-5199","tier":"record","sha256":"783b97ea229f28e449306981d15563db2176e2658741a45c5cc7db883bcd6cd2","pages":32,"tokens":9651,"emptyPages":[],"textThemes":["flex","colo","adequacy","proximate"]},"pages":[{"page":1,"startToken":0,"endToken":196,"text":"1 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C., et al., \n \nDocket Nos. EL25-49-000 \n                      EL25-49-002 \nLarge Loads Co-Located at \nGenerating Facilities \n                      AD24-11-001 \nConstellation Energy Generation \nL.L.C. \nv. \nPJM Interconnection, L.L.C. \n                      EL25-20-001 \n                      (consolidated) \n \n \nPJM Interconnection, L.L.C. \n                      ER26-1479-000 \n \nREQUEST FOR CLARIFICATION OR, IN THE ALTERNATIVE, REHEARING \nOF EOLIAN, L.P., CALIBRANT ENERGY HOLDINGS, LLC, AND VERRUS, LLC  \nPursuant to section 313(a) of the Federal Power Act (“FPA”), 16 U.S.C. § 825l (2024), \nand Rule 713 of the Rules of Practice and Procedure of the Federal Energy Regulatory \nCommission (“Commission” or “FERC”),1 Eolian, L.P. (“Eolian”), Calibrant Energy Holdings, \nLLC (“Calibrant”), and Verrus, LLC request clarification, and the in alterative rehearing of the \nCommission’s June 18 Order in the above-captioned proceeding (Order). In brief, we seek \nclarification of two aspects of the Order concerning the new Interim Network Integration \nTransmission Service (“Interim NITS”). First, the Commission should clarify that PJM's tariff \nmust generally describe the reliability principles and circumstances under which these services \nmay be curtailed, and not merely their relative curtailment priority. Second, the Commission \n \n1 18 C.F.R. § 385.713."},{"page":2,"startToken":196,"endToken":455,"text":"2 \nshould clarify that a transmission customer taking Interim NITS may rely on any resource whose \ncapacity is not committed to be delivered to PJM or another entity during curtailment events.  \nLIST OF ERRORS/STATEMENT OF ISSUES \nWe seek clarification or rehearing on two issues:  \n1. \nThe Commission should clarify that, in providing details on the curtailment \npriority of Interim NITS, non-firm and firm contract demand service vis-à-vis \nexisting transmission services, PJM must specify at least the general reliability \ncircumstances under which curtailment may occur.  \na. \nFailure to provide clarity on these service terms fails to adequately specify \ntariff terms as required by the Federal Power Act. See 16 U.S.C. § \n824d(c); City of Cleveland v. FERC, 773 F.2d 1368, 1376 (D.C. Cir. \n1985); Hecate Energy Greene County 3 LLC v. FERC, 72 F.4th 1307, 1314 \n(D.C. Cir. 2023). \nb. \nLack of specificity in curtailment terms is unjust and unreasonable \nbecause it will make use of these services commercially unworkable and \ntherefore will not adequately enable the avoidance of costly and inefficient \ntransmission system buildout that may not be necessary. See 16 U.S.C. § \n824d(a); PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025).  \nc. \nLack of specificity in curtailment terms risks undue discrimination as \nbetween transmission customers in application. See 16 U.S.C § 824d(a); \nE.ON Climate & Renewables N. Am., LLC, 137 FERC ¶ 61,076, at P 38 \n(2011); Standardization of Generator Interconnection Agreements and \nProcedures, Order No. 2003, 104 FERC ¶ 61,103, at P 11 (2003)."},{"page":3,"startToken":455,"endToken":835,"text":"3 \n2. \nThe Commission should clarify that any resource that has not committed its \ncapacity to PJM or another entity may be relied upon by a transmission customer \ntaking Interim NITS during curtailment events to the extent it is capable of \ndelivering capacity to the customer.  \na. \nProhibiting such resources from offering their services to Interim NITS \ncustomers during curtailment events would not be just and reasonable \nbecause it would prevent efficient use of Interim NITS and unreasonably \ndeny resources the opportunity to sell their services. See 16 U.S.C. § \n824d(a); PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025); \nElectric Storage Participation in Markets Operated by Regional \nTransmission Organizations and Independent System Operators, Order \nNo. 841, 162 FERC ¶ 61,127 (2018). \nb. \nProhibiting such resources from offering their services to Interim NITS \ncustomers during curtailment events would be unduly discriminatory \nbecause all resources whose services are not committed to PJM or another \nentity are similarly situated to the two specific classes of resources the \nCommission requires PJM to allow Interim NITS customers to rely upon. \nSee 16 U.S.C. § 824d(b); Associated Gas Distributors v. FERC, 824 F.2d \n981, 998 (D.C. Cir. 1987); Consol. Edison Co. of N.Y. v. FERC, 45 F.4th \n265, 281 (D.C. Cir. 2022); El Paso Natural Gas Co. Aera Energy, L.L.C., \n104 FERC ¶ 61,045, at P 115 (2003); N.Y. Indep. Sys. Operator, Inc., 162 \nFERC ¶ 61,124, at P 10 (2018). \nTo the extent that the requested clarifications are denied, we respectfully request \nrehearing. \nII. \nThe Commission Should Clarify that PJM Must Describe the General Reliability \nCircumstances Pursuant to Which Interim NITS, Non-Firm and Firm Contract \nDemand Services May Each Be Curtailed. \nThe June 18 Order “disagree[s] with commenters that PJM must provide specific details \nin its Tariff, such as the trigger and procedures for curtailment of Interim NITS and FCD or \nNFCD transmission services, or how PJM will enforce its curtailment procedures.”2 It finds that \n“requiring PJM to specify the curtailment priority of [the] new transmission services in its Tariff, \nwhile leaving specific implementation details in its manuals and individual service agreements, \nprovides transmission customers sufficient certainty as to their priority relative to other \n \n2 Order at P 552."},{"page":4,"startToken":835,"endToken":1136,"text":"4 \ntransmission services and ensures that PJM has sufficient flexibility to preserve system reliability \nin varying operating conditions.”3  \nAs a general matter, Eolian believes that a unified, specific approach to reliability triggers \nfor non-firm service adopted across grid operators and based on existing reliability frameworks \nwould provide clear and consistent rules of the road to developers of load and generation \nresources, thereby reducing transaction costs, and facilitating the scale-up of efficient, cost-\neffective business models for the development of load and supply designed to take advantage of \nnon-firm service. And by basing such triggers on transparent, actionable, and already-established \nreliability criteria—such as limiting resource adequacy-based curtailment to NERC energy \nemergency alert thresholds of EOP-011, and limiting transmission security-based curtailment \nbased on market-based dispatch of a dispatchable load bidding at the cap—a clear and consistent \ntrigger across regions would provide grid operators controls within the existing reliability \nframework and procedures that ensure adequate system reliability.4 And by basing such triggers \non the existing reliability framework and procedures, regions can avoid needless disputes about \napplication of business practices. While we urge the Commission to consider providing all \nregions with direction or other encouragement to adopt such criteria, we recognize that this \nproceeding may not be the appropriate place for the Commission to establish such a specific, \nnationwide rule.  \n \n3 Id. \n4 See Attachment A, Affidavit of Andrew Levitt on Behalf of Eolian, L.P. (July 17, 2026) (“Levitt \nAffidavit”) (explaining the benefits of a clear standard, and reasons to set the curtailment trigger \nfor resource adequacy events at EEA2 and for transmission security events based on market-\nbased dispatch of a dispatchable load as a suitable trigger for transmission security, with a cap on \nbid prices (e.g., $3,700/MWh, as for certain demand response in PJM today))."},{"page":5,"startToken":1136,"endToken":1424,"text":"5 \nNonetheless, we request clarification, or in the alternative, rehearing, of the \nCommission’s findings because while “specific details” regarding the curtailment trigger may be \nappropriately included in the business practices manuals, Commission precedent and case law \ninterpreting the Federal Power Act make clear that the tariff must at least describe generally \nwhen curtailment will occur. Moreover, including such general circumstances in the tariff will \nhelp avoid commercial uncertainty that risks undermining the Commission’s objectives in \nrequiring PJM to establish these new transmission services in the first place. \nPJM must at minimum provide tariff language that not only specifies curtailment priority \norder but also explains the reliability circumstances when curtailment may occur. PJM’s proposal \nhas not cleared that low bar. The Commission should provide further guidance to PJM, which \nwould set the stage for PJM to follow up with manual language establishing workable specific \nimplementation details that enable commercial investments while ensuring reliable system \noperations.5 Providing the general boundaries for curtailment would be consistent with PJM’s \ntariff terms for other types of transmission service.6 Far from compromising system operations, \nproviding more guidance on curtailment triggers will ameliorate potential challenges to dispatch \ncoordination.7 PJM’s far more detailed tariff provisions on curtailment for products such as \ndemand response help support investments into such resources, which enhances system \nreliability.8 More specificity regarding when transmission services may be curtailed would do the \nsame. \n \n5 As Andrew Levitt describes in affidavit attached hereto as Attachment A, a reasonable \nstandard—though not necessarily the only reasonable standard—would establish that non-firm \nNITS and non-firm contract demand service may be curtailed when specific resource adequacy \nor transmission security triggers occur. Levitt Affidavit at 7-11. \n6 Id. at 5-6. \n7 Id. \n8 Id."},{"page":6,"startToken":1424,"endToken":1785,"text":"6 \nAs described in the attached affidavit of Andrew Levitt, PJM’s proposal does not set any \nlimit on the circumstances in which it may curtail customers taking the new transmission \nservices, because while it provides that such customers will be curtailed before pre-emergency \ndemand response, it provides no condition after which such curtailment will be called.9 As \nexplained in the Joint Co-Location Developers Reply Brief, “[t]his open-ended process . . . \ntheoretically allows PJM to curtail such services at any time.”10 Without any boundary limiting \nthe conditions under which curtailment may occur (e.g. limiting curtailment to certain defined \nreliability circumstances), the tariff proposal fails to provide adequate notice of its service terms. \nThe Commission’s Order requires PJM to provide greater specificity insofar as PJM must amend \nits proposal to provide for the relative curtailment priority of these new transmission services and \nPJM’s existing services. Depending on how PJM responds, however, this may not necessarily \nguarantee that PJM will book-end its proposal to provide a clear boundary beyond which \ncurtailment will not occur. For example, if PJM provides that curtailment of non-firm contract \ndemand service may occur prior to curtailment of other services, then the outer boundary of \nwhen curtailment may occur would remain entirely undefined. In particular, to the extent that \nPJM indicates that the new services may be curtailed prior to non-firm point-to-point service, or \nin circumstances that differ from point-to-point service, then such a response to the \nCommission’s directive would fail to provide market participants with any clear limits on or \nability to forecast when curtailment may be called. It is not clear that the Commission \n \n9 Id. at 4. PJM’s proposed tariff provisions specified that PJM “may curtail Interim Network \nIntegration Transmission Service prior to dispatching the Pre-Emergency Load Response \nProgram as further set forth in the PJM Manuals, or in response to a transfer capability shortage \nas a result of system reliability conditions.” PJM Initial Brief, Illustrative Tariff, Part XI, Subpart \nB, § 705.2 & Subpart C, § 713.4. \n10 Reply Brief of Joint Co-location Developers and Motion to Intervene Out-of-time of Calibrant, \nConvergent, U.S. Energy Storage Coalition, and Verrus, at 17 (filed Mar. 25, 2026)."},{"page":7,"startToken":1785,"endToken":2177,"text":"7 \ncontemplated this circumstance and intended such open-ended levels of curtailment. As such, the \nCommission should clarify its order by directing PJM to include general principles and \nconditions where curtailment may occur when using Interim NITS. PJM could then provide \nadditional specificity in its manuals.  \nUnder City of Cleveland v. FERC and the Commission’s “rule of reason” precedent, a \ntariff must include “practices that affect rates and service significantly, that are realistically \nsusceptible of specification, and that are not so generally understood in any contractual \narrangement as to render recitation superfluous.”11 While it is true that tariffs “need not include \nmere implementation details,”12 the general circumstances when curtailment may occur are core \nto the definition of the new transmission services. As Levitt states, the “curtailment trigger is not \na minor feature of the new FERC-required transmission services, but one of the key attributes \nthat determines the value of the service and the associated impacts of the new large load on the \nbalance of transmission customers.”13 Decisions whether to take such services hinge on the \nability to estimate the depth and length of potential curtailments, and to plan for such \ncurtailments, such as assessing the extent to which investments in on-site resources or other \nmeasures would allow the load to withstand such curtailments.14 As developers of generation, \n \n11 773 F.2d 1368, 1376 (D.C. Cir. 1985) (emphasis in original).  \n12 Hecate Energy Greene County 3 LLC v. FERC, 72 F.4th 1307, 1312 (D.C. Cir. 2023) \n13 Levitt Affidavit at 4. \n14 See id. (“The difference between a service curtailed only during defined emergency conditions \nand one curtailed based on broad operational discretion is not small, and will directly impact the \ninvestment feasibility, characteristics, and impact of each of these services.”). For example, in \nassessing the potential for energy storage resources located at the point of interconnection to \nsupport a transmission customer’s ability to take one of the new transmission services, a \ndeveloper may assess whether a 6-hour storage resource sized to the nameplate load is likely to \nbe sufficient to guard against curtailment risk to the level required by the load customer. Is a \nbattery double or quadruple that size required? The answers to these questions cannot be known \nor even estimated without at least general guidance on the circumstances under which \ncurtailment will be triggered."},{"page":8,"startToken":2177,"endToken":2496,"text":"8 \nstorage, and load resources, our development choices depend heavily on the level of curtailment \nrisk predicted by the transmission services tariff terms. As Levitt explains, “a financial model \nsupporting a co-location investment would need assumptions regarding expected curtailment \nhours, maximum event duration, seasonal concentration, event time, and whether curtailment is \ntied to conditions affecting the specific delivery path or to broader PJM system conditions.”15 \nWhile developers do not need certainty with respect to each of these variables, they need \nsufficient, general parameters of a service to make reasonable assumptions and assign informed \nprobabilities. The vague curtailment language set forth by PJM in its proposed Tariff is so open-\nended that it does not provide a basis for any particular assumptions, and so is not adequate to \nsupport investment in co-located generation, energy storage, demand response, and other \nresources to support transmission customers. The Commission’s directive to PJM to indicate \nrelative curtailment order is helpful, but it does not ensure that PJM will bound curtailment in a \nmanner necessary to ameliorate the open-ended commercial risk that its original tariff proposal \nwould establish. While PJM asserts in its reply brief dated April 24, 2026, that  “...all generating \nresource that are available ...will be utilized to serve the Interim NITS customer,” that \ncommitment does not appear in its Tariff language. \nAnd while it is true that “even specifiable practices that significantly affect rates need not \nbe included if they are clearly implied by the tariff’s express terms,”16 in this case neither PJM \nnor the Commission has pointed to any express tariff terms that imply when and how curtailment \nmay occur. The Commission’s Order appropriately requires PJM to spell out curtailment priority \nof both new and existing transmission services. But if curtailment priority of the new services is \n \n15 Id. at 4-5. \n16 Hecate Energy Greene County 3 LLC v. FERC, 72 F.4th 1307, 1314 (D.C. Cir. 2023)."},{"page":9,"startToken":2496,"endToken":2762,"text":"9 \nnot equal to existing services or nested within them, the tariff may not even imply the \ncircumstances when curtailment may occur. The Commission’s should therefore clarify that, in \naddition to providing curtailment order, PJM’s tariff must at minimum set forth general reliability \nprinciples and circumstances when curtailment may occur so that it can implement these \nprinciples and provide greater detail on the circumstances in its manuals. \nAs Levitt persuasively argues, the most efficient approach would be to provide a clear \nand precise curtailment directive in the tariff.17 But even general tariff language providing \nguidance to be implemented more precisely in a manual would be a significant improvement \nupon the manifestly open-ended approach taken by PJM. Such a directive would be consistent \nwith the level of specificity set forth for non-firm point-to-point transmission service, where the \ntariff provides the following general direction regarding when curtailments for reliability or \neconomic reasons may occur:  \nThe Transmission Provider reserves the right to Curtail, in whole or in part, Non-\nFirm Point-To-Point Transmission Service provided under the Tariff for reliability \nreasons when an emergency or other unforeseen condition threatens to impair or \ndegrade the reliability of the Transmission System or the systems directly and \nindirectly interconnected with Transmission Provider's Transmission System. . . .  \nThe Transmission Provider reserves the right to Interrupt, in whole or in part, \nNon-Firm Point-To-Point Transmission Service provided under the Tariff for \neconomic reasons in order to accommodate (1) a request for Firm Transmission \nService, (2) a request for Non-Firm Point-To-Point Transmission Service of \ngreater duration, (3) a request for Non-Firm Point-To-Point Transmission Service \n \n17 See Levitt Affidavit."},{"page":10,"startToken":2762,"endToken":3056,"text":"10 \nof equal duration with a higher price, or (4) transmission service for Network \nCustomers from non-designated resources.18 \nNotably, the point-to-point curtailment language in the tariff includes both a relative \npriority order of curtailment and a description of the general reliability circumstances that trigger \nwhen the service may be curtailed, thus providing a bound on how much curtailment could be \nanticipated based on a range of potential system conditions. To satisfy the rule of reason, the \nCommission must require PJM to provide at least this same level of specificity regarding the \ncircumstances pursuant to which the new transmission services may be curtailed.  \nPJM could satisfy such a requirement by, for example, describing in its tariff the potential \nreliability trigger. For instance, the tariff could allow for reliability-based curtailment when (1) \nan emergency or other unforeseen condition threatens to impair or degrade the reliability of the \nTransmission System or the systems directly and indirectly interconnected with Transmission \nProvider’s Transmission System, as evaluated consistent with NERC reliability standards, or (2) \nwhen no generating resource is available (i.e., not on outage or otherwise unable to be brought \non-line in a timely manner) to serve the customer. Under the rubric of this broad framework, \nPJM could then set forth the specific curtailment triggers in its manuals. For example, as Levitt \nexplains, PJM should set forth specific resource adequacy and transmission security curtailment \ntriggers (including both pre- and post-contingency actions), so as to support commercial \ninvestments and reliable system operations.19  \nProviding this basic (or even a much more detailed) set of curtailment guidelines in the \ntariff would not compromise PJM’s ability to preserve system reliability in varying operating \n \n18 PJM, Intra-PJM Tariffs, OATT, § II.14.7 Curtailment or Interruption of Service.  \n19 Levitt Affidavit at 8-11."},{"page":11,"startToken":3056,"endToken":3326,"text":"11 \nconditions, and is in fact necessary to ensure the service terms are just and reasonable and not \nunduly discriminatory. Rather, as set forth in Levitt’s affidavit, greater detail from PJM would \nenhance orderly system operations. Providing at least a general description of curtailment \ntriggers in the tariff will enhance reliability by supporting greater use of non-firm NITS and \ncontract demand transmission services. In fact, based on our commercial experiences as long-\nstanding developers of co-located load, generation, and storage resources, at least this level of \ncertainty is necessary for a material number of projects to use these services. By their nature, \nthese services each give PJM a greater set of curtailment options than were the customers to \ninstead take NITS. In contrast, failure to provide even the general circumstances when \ncurtailment may occur is not just and reasonable because it will not support investments that \navoid costly and inefficient transmission system buildout. This was the very basis of the \nCommission’s co-location order.20 Additionally, leaving curtailment decisions unbounded and at \nthe complete discretion of PJM risks introducing the prospect of discriminatory treatment of \nsimilarly situated transmission customers. Without even general curtailment conditions, PJM \nneed not work to call curtailment consistently across customers or time based on verifiable \nreliability conditions. The prospect of differential treatment will further undermine customer \ninterest in these services and can introduce undue discrimination in the practical application of \n \n20 See PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 at P 160 (Dec. 2025) (“December Co-\nLocation Order”) (highlighting the potential avoidance of transmission system costs as a \nprincipal benefit of the new transmission services)."},{"page":12,"startToken":3326,"endToken":3671,"text":"12 \nthe tariff.21 These risks can be resolved by including “a standard set of procedures as part of the \nOATT.”22 \nClarification about the need for some general guidelines on curtailment trigger, beyond \njust that which may but need not necessarily be implied by curtailment priority order, is \nnecessary to achieve the Commission’s objectives.   \nIII. \nThe Commission Should Clarify that PJM Must Allow Load Taking Interim NITS to \nRely on Any Resource Not Obligated to Deliver to PJM or Another Entity \nThe Commission’s Order addresses the question whether an Interim NITS customer may \naccess a Co-Located Generator during curtailments (i.e., the transmission customer’s curtailment \nobligation is reduced according to the output of its Co-Located Generator). It finds that “it is just \nand reasonable to prohibit the Eligible Customer taking Interim NITS on behalf of Co-Located \nLoad from drawing energy from the Co-Located Generator when the Eligible Customer is \ncurtailed, if the Co-Located Generator is a capacity resource.”23 At the same time, however, the \nCommission identifies two specific circumstances where “such a restriction would not be \napplicable”24: (1) “if the associated Co-Located Generator does not yet have any interconnection \nservice or has only provisional interconnection service”; or (2) “if the associated Co-Located \nGenerator is seeking capacity resource status, but [has] not yet obtained such status.”25  \n \n21 E.ON Climate & Renewables N. Am., LLC, 137 FERC ¶ 61,076, at P38 (2011) (“The \nCommission would find any policy that creates opportunities for such discriminatory behavior to \nbe unacceptable”). \n22 Standardization of Generator Interconnection Agreements and Procedures, Order No. 2003, \n104 FERC ¶ 61,103, at P 11 (2003), order on reh'g, Order No. 2003-A, 106 FERC ¶ 61,220, \norder on reh'g, Order No. 2003-B, 109 FERC ¶ 61,287 (2004), order on reh'g, Order No. 2003-C, \n111 FERC ¶ 61,401 (2005), aff'd sub nom. Nat'l Ass'n of Regulatory Util. Comm'rs v. FERC, 475 \nF.3d 1277 (D.C. Cir. 2007) (“A standard set of procedures as part of the OATT . . . will minimize \nopportunities for undue discrimination”). \n23 Order at P 576. \n24 Id. \n25 Id."},{"page":13,"startToken":3671,"endToken":3972,"text":"13 \nThe reasonable implication of these findings is that a co-located resource may be relied \nupon where it is not a Generation Capacity Resource under the PJM tariff or is not otherwise \nobligated to deliver its services to PJM or another entity apart from the relevant transmission \ncustomer taking Interim NITS. Eolian agrees that it is reasonable to bar resources from \ndelivering solely to the Interim NITS customer when they are obligated to serve Network Load.26 \nHowever, clarification is needed to confirm that all resources not obligated to deliver to PJM or \nanother entity are eligible to support Interim NITS customers, because the Commission \nexplicitly requires tariff modification only with regard to the specific circumstances it \ndiscusses27—leaving out additional circumstances for which a co-located resource could provide \ncapacity to its co-located load without being a Generation Capacity Resource. To more \ncompletely effectuate the principle that the Commission is reasonably aiming at, it should make \nclear that PJM must allow a transmission customer taking Interim NITS to rely on any resource \nwhenever it is not obligated to deliver to PJM or another entity apart from the relevant load \ntaking Interim NITS.  \nThe key challenge which the Commission’s ordering language does not necessarily \novercome is that for Interim NITS to be commercially workable, most loads must be able to rely \nupon a co-located or electrically proximate resource until the load’s network upgrades are \ncompleted. Where the load is developed in conjunction with a new generation resource, the \nload’s network upgrades may not be completed on the same timeline as network upgrades \nrequired to interconnect the storage or generation capacity resource. If the interconnection of \nnon-provisional CIRs proceeds faster than that of firm service to load, the Interim NITS \n \n26 Id. (“capacity resources have an obligation to serve Network Load”). \n27 Id."},{"page":14,"startToken":3972,"endToken":4321,"text":"14 \ncustomer will nonetheless still need to rely on the co-located generator. For many, if not most, \nlarge load customers, the prospect of curtailment without access to a co-located generator or \nstorage resource to help avoid outage is not commercially tenable. Such large load customers are \nunlikely to invest, directly or through offtake agreements, in co-located or electrically proximate \ngeneration if they cannot rely on such generation before network upgrades are completed and \nNITS is provided. As a result, the very services that the Commission has found are necessary are \nlikely to go underutilized, substantially undermining the policy objectives that the Commission is \nseeking.28 Put simply, if transmission customers are not given tools to control their own \ncurtailment risk when relying on Interim NITS, the service will not facilitate more timely access \nto the transmission system. \nBut this challenge is addressable through clarification of the Commission’s language and \nthrough PJM’s development of new interconnection service options pursuant to the \nCommission’s June 18 large load show cause order.29 While the Commission offers only two \nspecific examples of cases where the Interim NITS customer may rely on generation resources, \nthere is a broader range of circumstances where co-located or electrically proximate generation \nshould be able to be relied upon. For example, PJM offers Energy Resource Interconnection \nService, pursuant to which resources may obtain interconnection rights that do not grant them \nGeneration Capacity Resource status, or otherwise obligate them to deliver to PJM.30 PJM may \n \n28 See, e.g., December Co-Location Order at P 201 (finding “that this new interim, non-firm \ntransmission service will facilitate the timely provision of transmission service to Eligible \nCustomers taking transmission service on behalf of Co-Located Loads”). \n29 See PJM Interconnection, L.L.C., 195 FERC ¶ 61,211, at PP 95-101 (2026) (preliminarily \nfinding that PJM must provide new generator interconnection study procedures and services to \nprevent “unnecessary interconnection delays” and “unnecessary delays and costs on transmission \ncustomers”). \n30 See, e.g., PJM Manual 14A, at section 5 (2026) (explaining how PJM offers Energy Resource \ninterconnection service in addition to Capacity Resource interconnection service)."},{"page":15,"startToken":4321,"endToken":4630,"text":"15 \ndevelop future interconnection pathways, such as generator interconnection mechanisms in \nresponse to the Commission’s June 18 show cause order,31 which either do not vest a resource \nwith Generation Capacity Resource status or else facilitate the delay in such status pending an \ninterim period where the resource is dedicated to the load with which it is paired. In addition, \ntransmission customers taking Interim NITS may seek to rely on behind-the-meter resources. \nWhere these resources are not used to enable the associated load to offer into the capacity market \nas demand response, their capacity is not committed to PJM. The Commission’s Order expressly \nextends eligibility for the new transmission services to “Eligible Customers taking transmission \nservice on behalf of load with BTMG” because such customers “are willing and able to limit \ntheir energy withdrawals from the transmission system under certain conditions.”32 This \nconclusion would make little sense were such customers unable to rely on their behind-the-meter \ngeneration to support the load when Interim NITS is curtailed. \nIn the event that the Commission intended to limit load to relying on co-located \ngenerators under only the explicitly named circumstances, it should reverse that position on \nrehearing. It would be unjust and unreasonable to bar Interim NITS from relying on non-capacity \nresources. This is true both because workable commercial arrangements necessary to support \nInterim NITS rely on the ability of transmission customers to rely on non-capacity resources to \nprevent curtailment, and because Commission precedent dictates that resources should be \npermitted to offer the services that they are technically capable of providing.  \n Further, it would not be just and reasonable and would be unduly discriminatory to \nrestrict the use of such resources to prevent curtailment when such use would be consistent with \n \n31 See PJM Interconnection, L.L.C., 195 FERC ¶ 61,211, at PP 95-101 (2026).  \n32 Order at P 91."},{"page":16,"startToken":4630,"endToken":5034,"text":"16 \ntheir reliability obligations and reliable system operations. While the Commission reasonably \nrests its prohibition of reliance on capacity resources upon the determination that “capacity \nresources have an obligation to serve Network Load,”33 this logic does not extend to prohibiting \nreliance on resources that are not obligated to offer into the capacity market, or that do not clear \nthe market to take on a capacity commitment where such resources have not otherwise \ncommitted themselves to deliver to another entity. Commission precedent supports the \nproposition that it is unjust and unreasonable for RTOs to foreclose the ability of resources to sell \nservices where they are technically capable of providing them.34 Just as barriers to wholesale \nmarket participation of energy storage resources reduces market competition and thereby \ncontribute to unjust and unreasonable rates, barriers to the use of resources technically capable of \nsupporting Interim NITS customers will limit the use of that service below efficient levels and \nthereby render rates unjust and unreasonable. Moreover, barring use of generation, storage, or \nother resources to meet the demand of Interim NITS customers during a curtailment event when \nsuch resources are—like the resources in the specific circumstances identified by the \nCommission—technically capable of providing service to Interim NITS customers and free from \nNetwork Load capacity service obligations, would constitute undue discrimination.35 \n \n33 Id. P 576. \n34 See, e.g., Order No. 841, 162 FERC ¶ 61,127, at PP 19-20 (2018) (finding that tariffs are \nunjust and unreasonable where they impose barriers to wholesale market participation by energy \nstorage resources technically capable of providing service).  \n35 16 U.S.C. § 824d(b); Associated Gas Distributors v. FERC, 824 F.2d 981, 998 (D.C. Cir. 1987) \n(the Act's \"concern about undue discrimination\" extends to all similarly situated parties); Consol. \nEdison Co. of N.Y. v. FERC, 45 F.4th 265, 281 (D.C. Cir. 2022) (The Commission must provide \nan adequate explanation to justify treating similarly situated parties differently\") (cleaned up); El \nPaso Natural Gas Co. Aera Energy, L.L.C., 104 FERC ¶ 61,045, at P 115 (2003) \n(\"Discrimination is undue when there is a difference in rates or services among similarly situated \ncustomers that is not justified by some legitimate factor.\"); N.Y. Indep. Sys. Operator, Inc., 162 \nFERC ¶ 61,124, at P 10 (2018) (finding entities are similarly situated where they are “equally \ncapable of providing [a] service, notwithstanding other significant differences.”)."},{"page":17,"startToken":5034,"endToken":5123,"text":"17 \n For the foregoing reasons, the Commission should grant the requested clarifications or, \nin the alternative, grant rehearing. \n \n \nRespectfully submitted, \n \n/s/ Eric Stoutenburg \nEric Stoutenburg \nEolian L.P. \n988 Howard Ave. Suite 200,  \nBurlingame, CA 94010 \neric.stoutenburg@eolianenergy.com \n \n/s/ Gabe Tabak \nGabe Tabak \nHead of Energy Policy \nVerrus, LLC \n918 N Rengstorff Ave. \nMountain View, CA 94043 \ngabe@verrusdata.com \n \n/s/ Judith Judson \nJudith Judson \nExecutive Vice President of Regulatory and Polcy \nCalibrant Energy \n4830 W. Kennedy Blvd, Suite 600 \nTampa, Florida 33609 \njudith.judson@calibrantenergy.com"},{"page":18,"startToken":5123,"endToken":5181,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary of the Commission in this \nproceeding. \n \nDated: July 20, 2026 \n/s/ Eric Stoutenburg \nEric Stoutenburg \nEolian L.P. \n988 Howard Ave. Suite 200,  \nBurlingame, CA 94010 \neric.stoutenburg@eolianenergy.com"},{"page":19,"startToken":5181,"endToken":5183,"text":"Attachment A"},{"page":20,"startToken":5183,"endToken":5257,"text":"Affidavit of Andrew Levitt \nDocket No. EL25-49-000 et al. | Page 1 of 13 \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et al., \n \nDocket Nos. EL25-49-000 \n                      EL25-49-002 \nLarge Loads Co-Located at Generating \nFacilities \n                      AD24-11-001 \nConstellation Energy Generation L.L.C. \nv. \nPJM Interconnection, L.L.C. \n                      EL25-20-001 \n                      (consolidated) \n \n \nPJM Interconnection, L.L.C. \n                      ER26-1479-000 \nAFFIDAVIT OF \nANDREW LEVITT  \nON BEHALF OF \nEOLIAN, L.P. \nJuly 20, 2026"},{"page":21,"startToken":5257,"endToken":5663,"text":"Affidavit of Andrew Levitt \nDocket No. EL25-49-000 et al. | Page 2 of 13 \nI. \nQUALIFICATIONS \n1 \nMy name is Andrew Levitt. I am a Senior Consultant at The Brattle Group (Brattle).  \n2 \nI am an expert on wholesale market design and reliability implications of changes in the power \n3 \nsystem. I have consulted to Independent System Operators and Regional Transmission \n4 \nOrganizations (ISO/RTOs) such as the Midcontinent Independent System Operator (MISO), the \n5 \nNew York Independent System Operator (NYISO), the Alberta Electric System Operator \n6 \n(AESO), and the Independent Electricity System Operator (IESO) of Ontario, and helped other \n7 \nclients navigate ISO/RTO changes nationwide. Prior to joining Brattle in 2022, I was on staff at \n8 \nPJM for seven years (most recently as Lead Market Designer), where I developed reforms to \n9 \nreliably integrate new resource types. I hold an MMP from the University of Delaware and a BSc \n10 \nin physics from the University of Toronto. \n11 \nI have worked extensively on the benefits of co-located load and generation and how these \n12 \narrangements can be facilitated to reduce costs, achieve faster connection of new loads and \n13 \ngeneration, and ensure reliability. This includes co-authored affidavits and reports in prior filings \n14 \nbefore the Federal Energy Regulatory Commission (FERC or Commission) on co-location \n15 \nincluding an affidavit on behalf of Eolian filed in FERC Docket No. RM26-4-000 \n16 \non Interconnection of Large Loads to the Interstate Transmission System and a report on behalf \n17 \nof Bloom Energy filed in Docket EL25-49-000 on Accelerating the Integration of New Co-\n18 \nlocated Generation and Loads.1 \n19 \nII. \nASSIGNMENT AND SUMMARY \n20 \nI was asked by Eolian, L.P. to assess the recent Commission Order on Rehearing, Clarification, \n21 \nand Compliance Filing (addressing co-located large loads),2 focused on enhancing PJM’s process \n22 \nfor interconnecting and serving large loads and paired generation. We were asked to assess \n23 \n \n1  \nAffidavit of Andrew Levitt, Aniruddh Mohan, Ryan Quint, and Sirisha Tanneeru on Behalf of Eolian Energy, \nInc., before the Federal Energy Regulatory Commission in the matter of Interconnection of Large Loads to the \nInterstate Transmission System, Docket No. RM26-4-000, November 21, 2025; A. Levitt, J. Pfeifenberger, and \nA. Mohan, Accelerating the Integration of New Co-located Generation and Loads, prepared for Bloom Energy \nas part of Docket No. EL25-49-000, April 23, 2025. \n2  \nPJM Interconnection, L.L.C., 195 FERC ¶ 61,209 (2026) (PJM Co-location Rehearing Order)."},{"page":22,"startToken":5663,"endToken":6038,"text":"Affidavit of Andrew Levitt \nDocket No. EL25-49-000 et al. | Page 3 of 13 \ncertain provisions in the order, the impacts of any challenges, and recommend potential paths \n1 \nforward. Specifically, this affidavit addresses the implications of omitting from the tariff details \n2 \nof the conditions under which a paired generator and large load would be curtailed.  \n3 \nWe explain that substantial uncertainties about expected curtailment volumes are associated with \n4 \nthe vague and operationally unbounded description of curtailment conditions that PJM is \n5 \nexpected to file, and that this can substantially impact commercial viability and efficiency. We \n6 \nset forth potential principles that would more precisely define curtailment conditions and allow \n7 \nfor less uncertain projections of potential curtailment volumes. We discuss different options for \n8 \nmandatory resource adequacy and transmission security curtailment triggers.  \n9 \nWe identify a NERC-defined Energy Emergency Action level 2 (EEA 2) as a suitable mandatory \n10 \ntrigger for resource adequacy, and market-based dispatch of a dispatchable load as a suitable \n11 \ntrigger for transmission security, with a cap on bid prices (e.g., $3,700/MWh, as for certain \n12 \ndemand response in PJM today) serving to communicate a desire to continue purchasing energy \n13 \nuntil conventional economic actions to maintain transmission security have been exhausted. \n14 \nFinally, we point to tariff language related to other curtailable service products in PJM to support \n15 \nthe principles associated with triggering these load reductions, and the associated Commission \n16 \nprecedent.  \n17 \nIII. \nBACKGROUND \n18 \nIn February 2025, the Commission initiated a show cause proceeding investigating whether \n19 \nsections of PJM’s tariff related to co-location of generation with loads are just and reasonable. \n20 \nFERC’s subsequent Order on December 18, 2025 found that PJM’s Tariff did not address with \n21 \nsufficient clarity and consistency the rates, terms, and conditions applicable to generators serving \n22 \nco-located load, nor those applicable to eligible customers taking transmission service on behalf \n23 \nof such load. It required PJM to submit a compliance filing, and initiated paper hearing \n24 \nprocedures.3 These submissions informed the Commission’s PJM co-location Rehearing Order \n25 \nissued on June 18, 2026, setting aside some portions of the December co-location Order, \n26 \n \n3  \nPJM Interconnection, LLC, 193 FERC ¶ 61,217 (2025) (December co-location Order)."},{"page":23,"startToken":6038,"endToken":6374,"text":"Affidavit of Andrew Levitt \nDocket No. EL25-49-000 et al. | Page 4 of 13 \naccepting portions of PJM’s compliance filing, and requiring PJM to implement further \n1 \ncompliance directives.4  \n2 \nIV. \nCURTAILMENT TRIGGERS \n3 \nIV.A. Problem Statement: The Benefits of Non-Firm Service Are \n4 \nImpacted by Unclear Curtailment Risk \n5 \nPJM’s recently approved proposal features unbounded uncertainty in the curtailment risk for \n6 \nlarge loads paired with generators seeking to use one of the Commission’s new transmission \n7 \nservices. PJM’s approved framework establishes that such large load curtailment will be called \n8 \nbefore pre-emergency demand response, but is silent on the types of conditions after which such \n9 \nlarge load curtailment will be called.5 The upper limit of potential curtailments is therefore \n10 \nunbounded, creating unnecessary uncertainty. A principled approach can be developed that \n11 \nmeets the reliability exigencies and relative priority of the non-firm large load transmission \n12 \nservices without entailing such unnecessary curtailment.  That can be achieved by establishing \n13 \nprinciples for curtailment conditions or triggers, and describing the specific reliability conditions \n14 \nthat would cause PJM to issue a curtailment directive to non-firm CDS or Interim NITS \n15 \ncustomers. \n16 \nThis underlying curtailment trigger is not a minor feature of the new FERC-required \n17 \ntransmission services, but one of the key attributes that determines the value of the service and \n18 \nthe associated impacts of the new large load on the balance of transmission customers. From the \n19 \nviewpoint of prospective large-load customers, understanding curtailment triggers and the range \n20 \nof potential curtailment volumes and patterns is critically important. The difference between a \n21 \nservice curtailed only during defined emergency conditions and one curtailed based on broad \n22 \noperational discretion is not small, and will directly impact the investment feasibility, \n23 \ncharacteristics, and impact of each of these services. As an example, a financial model \n24 \nsupporting a co-location investment will need assumptions regarding expected curtailment hours, \n25 \n \n4  \nPJM co-location Rehearing Order.  \n5  \nPJM co-location Rehearing Order at P 551."},{"page":24,"startToken":6374,"endToken":6734,"text":"Affidavit of Andrew Levitt \nDocket No. EL25-49-000 et al. | Page 5 of 13 \nmaximum event duration, seasonal concentration, event time, and whether curtailment is tied to \n1 \nconditions affecting the specific delivery path or to broader PJM system conditions. Specified \n2 \ncurtailment triggers allow for a more refined assessment of how these assumptions will evolve \n3 \nover time in the presence of growing large loads and emerging system dynamics.  \n4 \nIV.B. \nThe Solution is to Specify Principles for Curtailment \n5 \nTriggers in the Tariff \n6 \nIn the PJM co-location Rehearing Order, the Commission specified that PJM must “specify the \n7 \ncurtailment priority” of the new transmission services in its Tariff, while leaving specific \n8 \nimplementation details for inclusion in the relevant PJM manuals.6 The Commission found that \n9 \nthis structure “provides transmission customers sufficient certainty as to their priority relative to \n10 \nother transmission services and ensures that PJM has sufficient flexibility to preserve system \n11 \nreliability in varying operating conditions.”7 However, this structure entails substantial \n12 \ndrawbacks for commercial viability and efficiency as noted above. The solution is to require that \n13 \nPJM file in its Tariff specific curtailment principles that would enable market participants to \n14 \ndevelop a more precise assessment of curtailment risk. \n15 \nFurther, such Tariff-specified curtailment principles are consistent with prior Commission \n16 \ndecisions regarding other types of curtailable load products in PJM, including firm and non-firm \n17 \nPoint-to-Point (PTP) transmission service, and the suite of pre-emergency and emergency \n18 \nDemand Response (DR) programs offered in PJM’s markets. In these cases, the Commission \n19 \nrequired or accepted Tariff language describing the circumstances in which load reduction or \n20 \ncurtailments would be required. The Commission has previously held that descriptions of \n21 \ncurtailment triggers for various transmission and market services materially affected rates, \n22 \ncharges, terms of service and were appropriately included in the PJM Tariff. Given this \n23 \nprecedent, we suggest that similar Tariff-level principles could apply to non-firm CDS and \n24 \nInterim NITS, with the benefit of improving efficiency of investment and commercial viability \n25 \n \n6  \nPJM co-location Rehearing Order at P 552.  \n7  \nPJM co-location Rehearing Order at P 552."},{"page":25,"startToken":6734,"endToken":7177,"text":"Affidavit of Andrew Levitt \nDocket No. EL25-49-000 et al. | Page 6 of 13 \nfor co-located arrangements. The implementation details of these principles would still be left for \n1 \nspecification in PJM’s business practice manuals. \n2 \nPJM’s Tariff provisions on PTP transmission service were required by the Commission to \n3 \ninclude a description of curtailment triggers and associated system conditions. These descriptions \n4 \nextend beyond a sequence of relative curtailment priorities, as the Commission has required in \n5 \nthe PJM co-location Rehearing Order. PJM’s current Tariff provisions on PTP service trace back \n6 \nto the service provisions required by the Commission in Order 888.8 Subsequently, in Order 890, \n7 \nthe Commission reaffirmed pro-forma tariff language detailing the circumstances under which \n8 \nfirm and non-firm P2P transmission could be curtailed, explaining that these pro-forma Tariff \n9 \nprovisions “establish the terms and conditions under which a transmission provider may curtail \n10 \nservice to maintain reliable operation of the system.”9 The Tariff provisions themselves do not \n11 \nprovide a detailed operational framework (as would exist in the PJM manuals), but do provide a \n12 \ngeneral description of the conditions in which curtailments would occur.10 \n13 \nSimilarly, in the context of PJM’s DR programs, the PJM Tariff more directly specifies the \n14 \noperational expectations of both the pre-emergency and emergency DR categories, as found in \n15 \nAttachment K Appendix § 8.5 (pre-emergency) and 8.6 (emergency). The Tariff explains that a \n16 \n“pre-emergency event is implemented when economic resources are not adequate to serve load \n17 \nand maintain reserves or maintain system reliability, and prior to proceeding into emergency \n18 \nprocedures.”11 Similarly, the Tariff explains that emergency DR is triggered “coincident with the \n19 \ndeclaration of a Maximum Generation emergency,” “whenever economic generating capacity is \n20 \nnot adequate to serve load and maintain reserves or maintain system reliability.”12 The Tariff \n21 \n \n8  \nPromoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public \nUtilities, Order No. 888, 75 FERC ¶ 61,080 at 337-339 (1996). \n9  \nPreventing Undue Discrimination and Preference in Transmission Service , Order No. 890, 72 FR 12,266 at P \n1620 (2007) (describing the Commission maintaining existing pro-forma language regarding transmission \ncurtailments).  \n10  See, e.g., PJM OATT at § 14.7 (“The Transmission Provider reserves the right to Curtail, in whole or in \npart, Non-Firm Point-To-Point Transmission Service provided under the Tariff for reliability reasons when an \nemergency or other unforeseen condition threatens to impair or degrade the reliability of the Transmission \nSystem or the systems directly and indirectly interconnected with Transmission Provider's Transmission \nSystem.”) \n11  PJM OATT Attachment K Appendix § 8.5.  \n12  PJM OATT Attachment K Appendix § 8.6."},{"page":26,"startToken":7177,"endToken":7664,"text":"Affidavit of Andrew Levitt \nDocket No. EL25-49-000 et al. | Page 7 of 13 \nlanguage describing these pre-emergency and emergency conditions does not unreasonably \n1 \nrestrain PJM, instead providing PJM dispatchers express flexibility while simultaneously \n2 \nproviding market participants with a sense of the likely system conditions during which \n3 \ncurtailment responsibilities will be triggered.13  \n4 \nNotably, the genesis of PJM’s pre-emergency DR product stemmed from a challenge \n5 \nexperienced by PJM dispatchers related to the curtailment trigger for the previous generation of \n6 \nPJM DR products.14 Previously, triggering DR would initiate emergency conditions. To resolve \n7 \nthese challenges, PJM filed a series of Tariff revisions defining its pre-emergency and \n8 \nemergency DR frameworks, including the dispatch triggers and the implications for emergency \n9 \nprocedures.15 In light of the significant magnitude of forecasted large load additions, we observe \n10 \nthe potential for the lack of Tariff detail to create further challenges to dispatch coordination. At \n11 \nthe least, the degree of curtailment is likely to directly impact the efficiency, commercial \n12 \nviability, and speed to power ultimately enabled by these innovative transmission services \n13 \nconceived by the Commission.  \n14 \n \n13  PJM OATT Attachment K Appendix § 8.5 (pre-emergency)(“Understanding the primary responsibility of \nthe Office of the Interconnection to maintain system security, the Office of the Interconnection will strive to \nexhaust, but it is not obligated to exhaust, all economic resources prior to initiating a pre-emergency event”); \nPJM OATT Attachment K Appendix § 8.6 (emergency)(“PJM will dispatch the resources of all Emergency \nLoad Response Program participants (not already dispatched under the Economic Load Response Program) \nbased on the availability, location, minimum notification time, dispatch price and/or quantity of load reduction \nneeded, subject to transmission constraints in the PJM Region.  To give PJM dispatchers the flexibility to \naddress reliability concerns in the most effective and timely manner and invoke the resources that offer the most \nassurance of effective relief of emergency conditions, the dispatch of Demand Resource Registrations may not \nbe based solely on the least-cost resources since such dispatch shall be based not only on price, but also on \navailability, location, minimum notification time and/or quantity of megawatts of load or load reduction \nneeded”). \n14  PJM Interconnection L.L.C., 147 FERC ¶ 61,103 (2014) At PP 6-7 (“PJM notes, for example, that on two \noccasions (on July 18, 2013 and September 11, 2013) its dispatchers called on demand response when system \nconditions gave rise to the expectation that PJM was facing emergency conditions. PJM states that on both \noccasions these emergency conditions failed to materialize… PJM concludes that its existing rules have created \noperational inefficiencies, due to PJM’s current inability to call on demand response without first initiating \nemergency procedures, and PJM’s current inability to call on these demand response resources in a more \nprecise, targeted manner”). \n15  PJM Interconnection L.L.C., 147 FERC ¶ 61,103 (2014) At P 6."},{"page":27,"startToken":7664,"endToken":8014,"text":"Affidavit of Andrew Levitt \nDocket No. EL25-49-000 et al. | Page 8 of 13 \nIV.C. \nPrinciples for Curtailment Triggers: Preserving Reliability \n1 \nWhile Avoiding Excess Mandatory Curtailment \n2 \nWe outline potential principles for curtailment triggers to maintain reliability and meet the \n3 \nCommission’s other objectives, including maximizing the benefits of non-firm transmission \n4 \nservices. Triggers apply to two categories of reliability: (1) resource adequacy (ensuring \n5 \nsufficient supply) and (2) transmission security (keeping power flows within line limits). The \n6 \nimpact these triggers are likely to have on the durability and adoption of the transmission service, \n7 \ndescribed below, strongly indicates that these provisions materially affect rates, charges, and \n8 \nterms of these transmission services.  \n9 \nIn the first instance, triggers need to be able to maintain reliability so that the co-location \n10 \narrangement has a net zero impact on resource adequacy and on transmission security. Second, \n11 \nthey should feature comparable treatment to similarly situated participants. Third, they should be \n12 \nreasonably well specified so that participants can assess curtailment risk without unnecessary \n13 \nuncertainty. Fourth, they should not require more curtailment than necessary for meeting the \n14 \nother principles.  \n15 \nIn general, these principles can be adhered to by mandating net withdrawal reductions only after \n16 \nordinary economic actions have been exhausted, with such mandates grouped together with other \n17 \ncomparable curtailments. Indeed, PJM themselves have stated this principle, stating that: “…all \n18 \ngenerating resources that are available (i.e., not on outage or otherwise unable to be brought on-\n19 \nline in a timely manner) will be utilized to serve the Interim NITS customer. The Interim NITS \n20 \ncustomer would only be curtailed after these actions are taken and if the system is in an \n21 \nunreliable state due to transmission system violations or capacity/reserve shortages.”16 To avoid \n22 \nunnecessary uncertainty in curtailment volumes that significantly impacts commercial viability \n23 \nof the non-firm large load transmission services, PJM need only file this principle in its Tariff.  \n24 \n \n16  PJM Interconnection L.L.C., Reply Brief, filed in Docket No. EL25-49-000 April 24, 2026, page 20."},{"page":28,"startToken":8014,"endToken":8420,"text":"Affidavit of Andrew Levitt \nDocket No. EL25-49-000 et al. | Page 9 of 13 \nIV.C.1.a. Resource Adequacy Triggers \n1 \nAn RTO or other grid operator is “resource adequate” when it has sufficient generation to serve \n2 \nload except under the most severe operating conditions. If a system does not satisfy resource \n3 \nadequacy criteria, operators may need to rely on excessive curtailments of firm load (rotating \n4 \nbrownouts) to keep supply and demand in balance. For a paired generator and load arrangement, \n5 \nthe fundamental resource adequacy curtailment trigger is a systemwide shortage in maintaining \n6 \nthe supply-demand balance.  \n7 \nSuch shortages are commonly identified through a NERC-defined energy emergency alert \n8 \n(EEA).17 EEA Level 1 indicates that all available generation is in use; EEA Level 2 indicates that \n9 \nload management procedures are in effect; and EEA Level 3 indicates that firm load interruption, \n10 \ni.e., a rolling brownout, is imminent or already underway. Comparable emergency actions could \n11 \noccur after the issuance of EEA Level 1 (prior to pre-emergency DR, with among the largest \n12 \ncurtailment exposure), during the dispatch of pre-emergency DR (prior to EEA Level 2), or \n13 \nduring PJM Emergency Procedures Step 2 (which includes issuance of EEA Level 2 and \n14 \nsimultaneous dispatch of emergency DR, the least frequent trigger that would meet definitional \n15 \nreliability need and maximize commercial viability).18  \n16 \nThis choice of trigger would have significant impacts on curtailment volumes: over the last 24 \n17 \nmonths, PJM has had zero EEA 3 events, two emergency demand response deployment events \n18 \n(amounting to EEA 2 events) of 4 and 7.5 hours, and twenty-two pre-emergency demand \n19 \nresponse deployment events lasting between 4.5 and 10 hours, with a median of 7.5 hours \n20 \nduration.19 This directional trend in curtailment frequency and duration of the EEA levels is a \n21 \nfeature of their design, but the absolute value may change as supply conditions continue to \n22 \ntighten, while weather may revert to the mean relative to the unusually high maximum \n23 \ntemperatures in PJM during the 2025 and 2026 summers.  \n24 \nAccordingly, to remain consistent with NERC definitions surrounding emergency procedures, \n25 \nthe resource adequacy triggers for serving non-firm load (or net grid withdrawals) would occur at \n26 \n \n17  NERC, EOP-011-4 Emergency Operations.  \n18  See PJM Manual 13 at § 2.3.2. \n19  PJM, Emergency Procedures – Postings, accessed July 12, 2026."},{"page":29,"startToken":8420,"endToken":8839,"text":"Affidavit of Andrew Levitt \nDocket No. EL25-49-000 et al. | Page 10 of 13 \nEEA 2, alongside other emergency load management curtailments and prior to initiating load \n1 \nshed. Strictly speaking, using EEA 3 as the dispatch trigger for reducing net transmission \n2 \nwithdrawals would preserve resource adequacy (reducing the incidence of actual firm load shed) \n3 \nwhile producing the least frequent curtailment. However, it does not score well for the \n4 \n“comparable treatment” principle we outline above, since curtailment of net withdrawals from \n5 \nco-location arrangements is effectively a form of load management, and EEA 2 corresponds to \n6 \n“load management procedures in effect.” A trigger that is coincident with deployment of pre-\n7 \nemergency demand response in PJM would also score well for comparable treatment, although it \n8 \nwould exhibit substantially more curtailment volume. Given PJM’s unique sequencing of load \n9 \nmanagement dispatch prior to the defined NERC emergency action level commensurate with \n10 \nload management procedures, and desire to maintain conservative operations, resource adequacy \n11 \ntriggers consistent with those of pre-emergency demand response might also be appropriate. \n12 \nPJM’s current proposal to trigger curtailments before even pre-emergency DR is called upon \n13 \ndoes not score well for comparable treatment, and results in more curtailment volume than \n14 \nnecessary and reasonable.  \n15 \nIV.C.1.b. Transmission Security Triggers \n16 \nTransmission security is required to keep power flows within the operating limits of transmission \n17 \nfacilities and maintain other reliability parameters, such as voltage and stability, within \n18 \nacceptable bounds. Because grid conditions can change instantly, transmission facilities must \n19 \nremain within their limits even after a single contingency, such as the loss of a generating unit or \n20 \ntransmission line. For transmission security, we outline two possible categories of triggers: 1) \n21 \npre-contingency actions, such as operator-directed dispatch and curtailment, and 2) post-\n22 \ncontingency actions, made available by automated remedial action schemes (RAS). To preserve \n23 \ntransmission security, a load with co-located generation (or paired generation in an electrically-\n24 \nequivalent location) must reduce net grid withdrawals to zero when the grid operator (or an \n25 \nautomated RAS) determines that doing so is necessary.20 \n26 \n \n20  Under certain unlikely extreme conditions, especially when there are no protection schemes protecting against \ninternal contingencies associated with loss of co-located generation units, gross load may need to be curtailed to \nzero. However, adequate design of facilities can relegate these conditions to extremely low probability, \ncomparable to the probability of curtailing ordinary firm load due to transmission security conditions."},{"page":30,"startToken":8839,"endToken":9288,"text":"Affidavit of Andrew Levitt \nDocket No. EL25-49-000 et al. | Page 11 of 13 \nFor transmission security events, PJM can determine the need for curtailment through Security \n1 \nConstrained Economic Dispatch (SCED), Security Constrained Unit Commitment (SCUC), or \n2 \nother operational planning tools. Because reducing net withdrawals generally requires curtailing \n3 \nhigh-value load, the efficient approach is to treat that curtailment as a high-cost reliability action \n4 \nand use it only after ordinary economic alternatives, including generator redispatch, have been \n5 \nexhausted. This can be achieved by configuring the load as a dispatchable asset with a high \n6 \nwillingness to pay reflected in a bid price at some cap (such as $2,000/MWh, the offer cap for \n7 \nsetting price as a generator, or $3,700/MWh, the bid cap for price-sensitive demand in the PJM \n8 \nday-ahead market).21  \n9 \nA SCED-based approach would likely set nodal market clearing prices for energy at the bid price \n10 \nduring curtailment. A SCUC-based approach may be less direct, especially because it can \n11 \ninclude other values such as shut-down cost and no-load cost that would not be reflected in \n12 \nprices even after being dispatched to reduce net withdrawals. Either way, the dispatch signal \n13 \ncoming from the PJM market engine can serve as the mandatory directive to reduce non-firm \n14 \nload or net withdrawals at a co-location arrangement. The ability to bid at the price cap serves to \n15 \nmeet the principle of exhausting economic actions prior to relying on the withdrawal reduction to \n16 \nmaintain transmission security, thereby avoiding inefficient curtailment when not strictly needed.  \n17 \nThis approach has the virtue of using the same mechanism by which co-location arrangements \n18 \ncan voluntarily reduce net withdrawals economically in response to market prices. This would be \n19 \nexpected when the marginal cost of the co-located generation is lower than market prices, or \n20 \nwhen the site has been enabled with low-cost load flexibility.  \n21 \nFor cases where SCED dispatch does not meet the instantaneous reliability needs, RASs are \n22 \nuseful to enable the automated reduction of net load (from the paired load and associated \n23 \ngeneration) immediately upon appearance of certain reliability threshold conditions. These \n24 \nconditions typically involve a contingency, such as the sudden loss of an internal generating unit \n25 \nor a nearby transmission line. RAS is a well-established technology and can be relied upon for \n26 \nensuring transmission security if it conforms with reliability guidelines, such as those published \n27 \n \n21  See PJM Manual 11 at § 2.3.2.1 (Fixed and Price Sensitive Demand Bid Business Rules), 2.3.3.2 (Generator \nSchedules), 2.17 (Applying Transmission Constraint Penalty Factors in the Market Clearing Engine)."},{"page":31,"startToken":9288,"endToken":9596,"text":"Affidavit of Andrew Levitt \nDocket No. EL25-49-000 et al. | Page 12 of 13 \nby reliability operators who are already utilizing RAS for similar applications (WECC, CAISO, \n1 \nand the AEMO in Australia).22 \n2 \nIn practice, a RAS initiates reductions in grid withdrawals from a co-location arrangement only \n3 \nafter a contingency has actually occurred, which may be a low-probability event. Operator-\n4 \ninitiated dispatch, by contrast, tends to reduce net withdrawals from a co-location arrangement \n5 \nfor the full period during which such a reduction may be needed to prevent a hypothetical \n6 \ncontingency from causing an overload. For example, a conventional operator-initiated approach \n7 \nmay require curtailing a large load for the duration of a multi-week planned transmission outage \n8 \n(so a second transmission outage would not cause a reliability violation), while a RAS approach \n9 \nwould require no curtailments during that entire period (unless there were an unexpected second \n10 \ntransmission contingency were to actually occur, which is very unlikely). The duration and \n11 \nfrequency of withdrawal reductions therefore are much greater for operator-initiated dispatch \n12 \nthan for RAS-based curtailments. RAS use thus supports commercial feasibility, where \n13 \nappropriate to grid conditions and the capabilities of a co-location arrangement. RAS also allows \n14 \nfor the full utilization of transmission capability by offering automated curtailments in response \n15 \nto a transmission contingency, whereas operator-initiated dispatch requires holding back \n16 \ntransmission headroom in case that contingency were to occur.23 \n17 \n \n22  WECC, Remedial Action Scheme Design Guide (July, 2022); California ISO Planning Standards (February 2, \n2023), at § III; AESO, Remedial Action Scheme Guidelines (September 27, 2022).  \n23  See Levitt, Thomas, Pfeifenberger, Felmus, Remedial Action Schemes (RAS) to Quickly and Affordably \nConnect New Generation and Large Loads, presented to FERC staff (June 22, 2026). Available at \nhttps://www.brattle.com/wp-content/uploads/2026/06/Remedial-Action-Schemes-RAS-to-Quickly-and-\nAffordably-Connect-New-Generation-and-Large-Loads.pdf"},{"page":32,"startToken":9596,"endToken":9651,"text":"Affidavit of Andrew Levitt \nDocket No. EL25-49-000 et al. | Page 13 of 13 \nAffidavit of Andrew Levitt  \n \nI, Andrew Levitt, do hereby swear that I have authored the Affidavit of Andrew Levitt \nand the statements contained therein are true and accurate to the best of my knowledge and \nbelief.  \nAndrew Levitt  \n \n \nDate: July 20, 2026"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":1593,"startToken":0,"endToken":717},{"p":3,"at":1593,"title":"II. The Commission Should Clarify that PJM Must Describe the General Reliability","method":"printed heading","endPage":12,"endAt":348,"startToken":717,"endToken":3381},{"p":12,"at":348,"title":"III. The Commission Should Clarify that PJM Must Allow Load Taking Interim NITS to","method":"printed heading","endPage":18,"endAt":0,"startToken":3381,"endToken":5123},{"p":18,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":19,"endAt":0,"startToken":5123,"endToken":5181},{"p":19,"at":0,"title":"Attachment A","method":"printed heading","endPage":21,"endAt":74,"startToken":5181,"endToken":5270},{"p":21,"at":74,"title":"I. QUALIFICATIONS","method":"printed heading","endPage":21,"endAt":1690,"startToken":5270,"endToken":5525},{"p":21,"at":1690,"title":"II. ASSIGNMENT AND SUMMARY","method":"printed heading","endPage":21,"endAt":2349,"startToken":5525,"endToken":5624},{"p":21,"at":2349,"title":"A. Mohan, Accelerating the Integration of New Co-located Generation and Loads, prepared for Bloom Energy","method":"printed heading","endPage":22,"endAt":1654,"startToken":5624,"endToken":5907},{"p":22,"at":1654,"title":"III. BACKGROUND","method":"printed heading","endPage":23,"endAt":193,"startToken":5907,"endToken":6068},{"p":23,"at":193,"title":"IV. CURTAILMENT TRIGGERS","method":"printed heading","endPage":32,"endAt":334,"startToken":6068,"endToken":9651}]}