{"document":{"slug":"rec-20260720-5200","title":"The PJM Industrial Customer Coalition, et al. submit Request for Rehearing and Clarification of the 06/18/2026 Order","issued":"2026-07-20","accession":"20260720-5200","docket":"ER26-1479-001","group":"PJM co-location compliance","filer":"PJMICC, et al.","kind":"rehearing request","file":"sources/filings/text/20260720-5200_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260720-5200","tier":"record","sha256":"9c2935ea9940c913ef17234924e3e919c59b0b426c35f174e803e715608c9fc3","pages":36,"tokens":12255,"emptyPages":[],"textThemes":["colo","adequacy","retail","flex"]},"pages":[{"page":1,"startToken":0,"endToken":213,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM Interconnection, L.L.C., et al.  \n \n \nLarge Loads Co-Located at Generating \nFacilities \n \nConstellation Energy, LLC \n        v.  \nPJM Interconnection, L.L.C. \n \nPJM Interconnection, L.L.C.\n \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n) \n)\n \n \nDocket Nos. EL25-49-002 \n                     EL25-49-000 \n \n \nAD24-11-001 \n \n \nEL25-20-001 \n(Consolidated) \n \nER26-1479-000\nREQUEST FOR REHEARING AND CLARIFICATION  \nOF THE INDUSTRIAL CUSTOMERS/AMTRAK \n \nPursuant to Rule 713 of the Federal Energy Regulatory Commission’s (“Commission” or \n“FERC”) Rules of Practice and Procedure,1 the PJM Industrial Customer Coalition (“PJMICC”), \nthe Industrial Energy Consumers of America (“IECA”), the American Forest and Paper \nAssociation (“AF&PA”) (collectively, “Industrials”), and the National Railroad Passenger \nCorporation (“Amtrak”) respectfully request rehearing and clarification of portions of the \nCommission’s June 18, 2026, Order on Rehearing, Clarification, Compliance Filing, and Paper \nHearing (“June Order”) in the above referenced proceeding.2  The Industrials/Amtrak respectfully \nask the Commission to 1) establish a retail Behind the Meter Generation (“BTMG”) netting \nthreshold of 200 Megawatts (“MW”); and 2) grant their rehearing requests regarding Qualifying \nFacilities (“QFs”) under the Public Utility Regulatory Policies Act of 1978 (“PURPA”), including \na QF’s right to be served with just and reasonable back-up and maintenance power. \n \n1 See 18 C.F.R. § 385.713. \n2 195 FERC ¶ 61,209 (Order entered Jun. 18, 2026) (hereinafter “June Order”)."},{"page":2,"startToken":213,"endToken":528,"text":"2 \n \n \nI. \nINTRODUCTION \nOn December 18, 2025, the Commission issued an order in the above-referenced \nproceeding (“December Order”) finding that the Open Access Transmission Tariff (“Tariff”) of \nPJM Interconnection, L.L.C. (“PJM”) is unjust and unreasonable due to the failure to address the \nrates, terms, and conditions of service with sufficient clarity or consistency that apply to generators \nserving Co-Located Load and Eligible Customers taking transmission service on behalf of Co-\nLocated Load.3  The December Order provided PJM with guidance to address co-located electrical \nconfigurations involving both generation and load behind a retail customer’s meter and also \ndirected PJM to make a compliance filing (“PJM Compliance Filing”)4 to implement the \nCommission’s finding that retail BTMG rules in the PJM Tariff are no longer just and reasonable.  \nOn January 20, 2026, PJMICC and IECA filed a rehearing/clarification request of the \nDecember Order (“Industrials’ Rehearing Request”), expressing appreciation for the \nCommission’s efforts to address resource adequacy in PJM through directing new transmission \nservices that intended to offer potential additional flexibility, clarity, and choice for consumers, \nbut cautioning the Commission as to its finding with respect to the existing BTMG rules.5 \nSpecifically, the Industrials’ Rehearing Request explained that the December Order’s application \nof the BTMG finding to traditional manufacturers and institutional customers was unfounded, \nunsubstantiated, contrary to longstanding rules and policies, inconsistent with cost causation \nprinciples, and, with respect to retail BTMG that are cogeneration facilities, contrary to treatment \n \n3 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217, at P 2 (2025) (hereinafter “December Order”). \n4 PJM Interconnection, L.L.C., 60-Day Compliance Filing for Co-Located Load Related Revisions to Open Access \nTransmission Tariff to Comply with Commission Order in Docket No. EL25-49, et al., (“PJM Compliance Filing”) \nDocket No. ER26-1479-000, at 10 (Feb. 23, 2026).  \n5 See generally Industrials’ Rehearing Request, FERC Docket No. EL25-49-000 et al. (filed Jan. 20, 2026)."},{"page":3,"startToken":528,"endToken":895,"text":"3 \n \n \nof cogeneration QFs under PURPA.6  PJMICC and IECA highlighted the December Order’s \nunnecessary infliction of harm to manufacturing customers with BTMG, to the grid, and to the \navailable pool of generation resources to serve the grid at a time of growing resource inadequacy.7   \nOn March 16, 2026, the Industrials and Amtrak filed a protest to PJM’s Compliance Filing \nin Docket No. ER26-1479, along with a supporting technical affidavit of James R. Dauphinais \n(“Dauphinais Affidavit”), challenging the proposed retail BTMG netting threshold of 50 MW, \nexplaining the unintended and adverse consequences of applying BTMG rule changes to \ntraditional large load customers that neither caused the problems facing the grid today nor present \nthe same reliability risks and speed-to-power demands of certain significantly larger computational \nloads.8 The Industrials/Amtrak substantiated a BTMG threshold of at least 200 MW, and Mr. \nDauphinais explained in detail why very large computational loads are differently situated than \ntraditional commercial and industrial customers using BTMG.9 Mr. Dauphinais further \ndemonstrated why PURPA QFs should be eligible for retail netting for their full load and \nemphasized that the FERC’s longstanding regulations governing rates for sales of back-up power \nor maintenance power to QFs must not be ignored, given that transmission is a key component of \nback-up maintenance power.10 Mr. Dauphinais also highlighted evidence in a regulatory \nproceeding in Michigan supporting a determination of defining large load at a 300 MW threshold.11   \n \n6 Public Utility Regulatory Policies Act, Pub. L. 95–617, title II, § 210, Nov. 9, 1978, as amended (codified at 16 \nU.S.C § 824a-3). \n7 Industrials’ Rehearing Request at 1-2 (the December Order “threatens to weaken some of the largest manufacturers \nin the PJM region” by rendering hundreds of megawatts of existing retail BTMG uneconomic and stalling new \nprojects).   \n8 Joint Protest and Comments of Industrial Customer Organizations and Amtrak, PJM Interconnection, L.L.C., Docket \nNo. ER26-1479-000 at 5-15 (filed Mar. 16, 2026) (hereinafter “Industrial/Amtrak Compliance Protest”).  \n9 Industrial/Amtrak Compliance Protest, Dauphinais Affidavit at 4-5, 12-13, 29-37.   \n10 Dauphinais Affidavit at 8-11, 26-29. \n11 Id. at 34, 38, Attachment 2 and Attachment 3 (showing that data centers are typically at 300 MW and above)."},{"page":4,"startToken":895,"endToken":1321,"text":"4 \n \n \nGiven the deleterious impact of FERC’s recent shift in BTMG netting policy on \nmanufacturers, institutional, and transportation customers, on April 13, 2026, PJMICC, IECA, and \nAmtrak filed a Petition for Review of the December Order with the Third Circuit Court of \nAppeals.12   \nTo be clear, the Industrials/Amtrak value the Commission’s efforts in the June Order to \nprotect existing manufacturing customers through the implementation of grandfathering \nprovisions and exemptions for certain cogeneration facilities.  During the June 18, 2026 Open \nMeeting, the Commission explained the June Order’s modifications to the December Order, and \nit was stated that “this Commission wants to safeguard American Industrials.”13 Industrials \nappreciate the Commission’s recognition of the importance of the manufacturing sector, which \nprovides critical supply chain inputs for industries nationwide, including for the energy industry \nand national defense.  \nUnfortunately, the June Order presents concrete, practical implementation difficulties that \nmay challenge the Commission’s intent to safeguard American manufacturing.14 The June Order \ndoes not fully protect all existing customers and investment-backed expectations in manufacturing \n \n12 See PJM Industrial Customer Coalition et al v. FERC, Case No. 26-1840 (3rd Cir.) (filed Apr. 13, 2026).   \n13 See June 18, 2026, Open Meeting at 11:43-12:41, available at https://www.ferc.gov/news-events/events/june-18-\n2026-open-meeting-10082025 (last accessed July 20, 2026). \n14 The June Order rejected and dismissed most of the Industrials’ arguments. See, e.g., June Order at PP 43 (disagreeing \nwith Industrial BTMG jurisdictional arguments), 73-77 (“We disagree with Industrials that changes to retail BTMG \nnetting rules are beyond the scope of this proceeding”), 81 (“We disagree with Industrials that the Commission failed \nto address prior precedent”), 82 (“We also disagree with Industrials that the Commission did not develop a sufficient \nrecord”), 83 (dismissing Industrials’ cost causation argument as “unpersuasive”), 87 (“We also disagree with \nIndustrials that the December Order unduly discriminates against Network Customers who manage costs by investing \nin generation as compared to Network Customers who manage costs by managing load”), 141 (rejecting Industrials’ \nargument that the Commission’s reliability concerns should not apply at all to cogeneration QFs categorically), 145 \n(denying Industrials clarification request that BTMG netting rules do not apply to capacity obligations), 148-149 \n(dismissing unlawful taking argument due to lack of finality), 153-154 (“we dismiss Industrials’ argument that any \nretail BTMG materiality threshold implemented will be insufficiently high for lack of finality”), 207-220 (implicitly \ndenying Industrials’ requesting 200 MW retail threshold by setting a 50 MW retail threshold for BTMG netting), 245 \nand 410-411 (declining to consider Industrials’ arguments around back-up and maintenance service for QFs)."},{"page":5,"startToken":1321,"endToken":1632,"text":"5 \n \n \nresources, especially given that the June Order places the burden on non-jurisdictional retail \nindustrial customers to navigate a PJM compliance process15 to show that “they are not the \nproblem.”  To claim a narrow exemption, the June Order requires manufacturers to demonstrate – \npotentially by hiring an outside consultant to conduct power flow studies – that they are not the \ncause of the resource adequacy, reliability, and cost shift pressures facing the grid.16  The June \nOrder also requires customers to navigate a yet-to-be-defined process to maintain grandfathering \nstatus (assuming they qualify).  Manufacturers are already operating on thin margins, with energy \nmanagers wearing multiple hats.  The Industrials/Amtrak respectfully ask the Commission to help \nmanufacturers avoid unnecessary red tape, cost increases, and business uncertainty by granting the \nrequested 200 MW threshold for BTMG netting. \nThe Commission’s new transmission services are innovative and creative and will help to \naddress several co-location and load growth challenges facing the industry. However, as a practical \nmatter, taking the new Firm Contract Demand (“FCD”) and Non-Firm Contract Demand \n(“NFCD”) transmission services is unlikely to be a viable, economic, and reliable option for all \nmanufacturers and traditional industrial customers. Moreover, the June Order will hurt American \nmanufacturing and disincentivize meaningful, on-site generation investments that could otherwise \nhelp to ameliorate the resource adequacy situation confronting PJM today and in the future. To \n \n15 See June Order at P 86 (“To the extent that any of the facilities discussed in Industrials’ six examples could \ndemonstrate that they do not present such concerns, they may fall within the exemption that we direct PJM to submit \nas part of the compliance filing”). \n16 June Order at P 246 (“certain cogeneration QFs should be exempted from the replacement rate upon a \ndemonstration that they do not present the reliability or resource adequacy concerns discussed in the December \nOrder”); see also id. at P 142."},{"page":6,"startToken":1632,"endToken":1962,"text":"6 \n \n \navoid unnecessary economic harm to manufacturers in PJM17 and to support manufacturers’ \nonshoring efforts,18 the Commission should grant rehearing on the issues raised herein.  \nII. \nBACKGROUND ON INDUSTRIALS AND AMTRAK  \nThe Industrials include associations of leading American manufacturing companies, trade-\nexposed electricity users, institutional users, and other energy-intensive customers, including \nhospitals, universities, and educational institutions. Together, the Industrials represent \norganizations producing well over $1 trillion in sales, including thousands of manufacturing \nfacilities and millions of family-sustaining jobs in the United States. These organizations produce \nthe raw materials and inputs necessary to sustain commerce and our overall standard of living. \nManufacturing employs over 15 million people in the United States19 and contributed $2.3 trillion \nto U.S. Gross Domestic Product (“GDP”) in 2023 (amounting to 10.2% of total U.S. GDP, \nmeasured in chained 2017 dollars).20 Manufacturing is unique compared to all other sectors. \nManufacturers are energy-intensive, frequently operate 24/7, are price-sensitive, and compete \nglobally. Small changes in electricity prices can have significant impacts on the competitiveness \nof existing facilities and serious implications for reshoring and expanding facilities and production \ncapabilities in the United States. Unlike the surge in large-load demands from data centers and \ncomputational workloads, industrial demand has been relatively flat and for manufacturers \n \n17 See “Big Tech data centers are driving up power bills at America’s Rust Belt factories,” Reuters (Laila Kearney) \n(July 7, 2026), available at https://www.reuters.com/business/energy/big-tech-data-centers-are-driving-up-power-\nbills-americas-rust-belt-factories-2026-07-07/ (last accessed July 20, 2026).   \n18 See “Data centers’ energy demand threatens Trump’s ‘Made in America’ plan,” Ars Technica (Jeremey Hsu) (July \n7, 2026), available at https://arstechnica.com/tech-policy/2026/07/us-manufacturers-energy-costs-soar-because-of-\nai-data-center-demand/  (last accessed July 20, 2026).   \n19 See U.S. Bureau of Labor Statistics (2024 data), available at https://www.bls.gov/cps/cpsaat18.htm (last accessed \nJuly 14, 2026). \n20 \nSee \nU.S. \nManufacturing \nEconomy, \nNIST, \navailable \nat \nhttps://www.nist.gov/el/applied-economics-\noffice/manufacturing/manufacturing-economy/total-us-manufacturing (last accessed July 20, 2026)."},{"page":7,"startToken":1962,"endToken":2264,"text":"7 \n \n \npositioned to expand facilities, expansion occurs carefully and deliberately over the long-term, \nwith years of planning and investment prior to committing to a facility addition or expansion. \nMany of the Industrials’ members have constructed, maintained, and operated substantial BTMG \nunits designed for operational efficiency and deeply integrated into their industrial processes. \nIndustrials’ members span industries as diverse as chemicals, plastics, steel, iron ore, aluminum, \npaper, food processing, fertilizer, insulation, glass, industrial gases, pharmaceuticals, building \nproducts, automotive, transportation, independent oil refining, cement, and more. Industrials also \ncomprise other institutional and service customers, such as universities and hospitals, some of \nwhich also operate retail BTMG. \nAmtrak is a corporation authorized by the Rail Passenger Service Act of 1970, currently \nset forth at 49 U.S.C. §§ 24101, et seq. Amtrak provides passenger rail service across the \ncontinental United States, including within the PJM footprint. Amtrak consumes substantial \namounts of electricity in its operations and requires reliable electric service to support its \noperations. While Amtrak is not a manufacturer, it is also an industrial customer of utility services. \nFor many years, Amtrak has harnessed retail BTMG in PJM to support its business operations and \nreliability imperatives. Amtrak’s interests align with the Industrials and reflect the wide-ranging \ntypes of bespoke retail BTMG arrangements that support the region’s and the nation’s economy.  \nIII. \nRESERVATION OF APPELLATE RIGHTS \nPursuant to Rule 713 of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § \n385.713, and Section 313(b) of the Federal Power Act, 16 U.S. Code § 825l, the Industrials \npreviously filed a request for rehearing of the December Order, followed by a petition for review \nwith the Third Circuit Court of Appeals (“Third Circuit Petition”). The Industrials/Amtrak \nexpressly reserve their right to continue to litigate, as necessary, the issues delineated in their Third"},{"page":8,"startToken":2264,"endToken":2629,"text":"8 \n \n \nCircuit Petition.21  This second rehearing request seeks to only address issues that were not \nfinalized in the December Order and only recently finalized in the June Order.  Accordingly, any \ndecision not to re-litigate or re-challenge issues that are already pending before the Third Circuit \nshall not constitute waiver or failure to exhaust administrative remedies. In the June Order, FERC \ntreated portions of the December Order as constituting final determinations, such as the general \nfinding on the unjustness and unreasonableness of retail BTMG netting,22 while treating other \nportions of the December Order as not final, such as the yet-to-be-determined threshold for netting \narrangements on a going-forward basis23 and arrangements for new transmission services.24   \nA second rehearing request is only necessary if FERC’s first order on rehearing “modified \nthe results of [the FERC’s initial December Order] in a significant way.”25 Such a “significant” \nmodification means a change in the outcome of the case, not merely a change in the Commission’s \nreasoning.26 The June Order did not necessarily modify the December Order in a significant way, \nbut the June Order did provide several substantive clarifications that materially impact the rights \nand opportunities of affected customers, and the June Order did, for the first time, address the \nspecific numerical threshold for retail netting and issues pertaining to PURPA, QFs, and \ncogeneration.  The Industrials/Amtrak focus this rehearing request on the June Order’s newly \naddressed issues while preserving, as necessary, the remaining unresolved issues raised in their \nThird Circuit Petition that were not granted in the June Order. In recognition of the need for \n \n21 See PJM Industrial Customer Coalition et al. v. FERC, Concise Summary of the Case, Case No. 26-1840 (filed \nApr. 16, 2026). \n22 See June Order at PP 3, 78, 81. \n23 See id. at P 153. \n24 See id. at P 106. \n25 See Smith Lake Improvement and Stakeholders Ass’n v. FERC, 809 F.3d 55, 56-57 (D.C. Cir. 2015) (quoting Town \nof Norwood, Mass. v. FERC, 906 F.2d 772, 775 (D.C. Cir. 1990)). \n26 Smith Lake, 809 F.3d at 56 (citing Allegheny Power v. FERC, 437 F.3d 1215, 1222 (D.C. Cir. 2006))."},{"page":9,"startToken":2629,"endToken":3025,"text":"9 \n \n \nregulatory certainty and legal durability for affected businesses, stakeholders, and regulators, the \nIndustrials/Amtrak are also filing this rehearing/clarification request to avoid the need for appellate \nlitigation.  \nIV. \nREQUEST FOR REHEARING \nA. \nSTATEMENT OF ISSUES/SPECIFICATION OF ERRORS \nPursuant to Rule 713(c),27 the Industrials/Amtrak respectfully submit that certain of the \nJune Order’s determinations with respect to PJM’s retail BMTG rules are arbitrary and capricious, \ndo not reflect reasoned decision-making, are insufficiently supported, and result in a rate outcome \nthat is unjust, unreasonable, unduly discriminatory, and preferential. Due to the specific errors \nidentified herein and the lack of a record upon which to base these determinations, the June Order \nshould be modified on rehearing if any of the Clarifications requested herein are not granted.  \nThe Industrials/Amtrak respectfully specify the following errors: \n1. \nThe June Order failed to engage with the evidence and arguments presented by \nthe Industrials/Amtrak that provided reasons a 200 MW or greater materiality \nthreshold (“Retail Threshold”) for Network Integration Transmission Service \n(“NITS”) netting rules is preferable to a 50 MW Retail Threshold. Sacramento \nMun. Util. Dist. v. FERC, 616 F.3d 520 (D.C. Cir. 2010); Midwest ISO \nTransmission Owners v. FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004); Motor \nVehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983).   \n2. \nWhile the June Order approved a narrow exemption for certain cogeneration QFs, \nthe exemption is unduly narrow because it does not clearly allow QFs with low \nreliability and system risks or strong performance histories to also be exempt from \nthe new netting rules, consistent with cost causation principles and the \nCommission’s QF Back-up Regulations. The June Order errs because it does not \nreflect reasoned decision-making regarding PURPA regulations requiring back-\nup service with specified assumptions, resulting in an error of law that deemed \nback-up service as unrelated to transmission service. 16 U.S.C. § 824d, 16 U.S.C. \n§ 825l(b); South Carolina Pub. Serv. Auth. v. FERC, 762 F.3d 41 (D.C. Cir. \n2014); Sacramento Mun. Util. Dist. v. FERC, 616 F.3d 520 (D.C. Cir. 2010); \nMidwest ISO Transmission Owners v. FERC, 373 F.3d 1361 (D.C. Cir. 2004); \nMotor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29 (1983); \n \n27 18 C.F.R. § 385.713(c)."},{"page":10,"startToken":3025,"endToken":3413,"text":"10 \n \n \nNew Eng. Power Generators Ass’n v. FERC, 881 F.3d 202 (D.C. Cir. 2018); \nExxonMobil Oil v. FERC, 487 F.3d 945 (D.C. Cir. 2007); New York v. FERC, \n535 U.S. 1 (2002); Transmission Access Policy Group v. FERC, 225 F.3d 667 \n(D.C. Cir. 2000); North Carolina Util. Comm’n v. FERC, 42 F.3d 659 (D.C. Cir. \n1994); N.J. Bd. of Pub. Utils. v. FERC, 744 F.3d 74 (3d Cir. 2014); Old Dominion \nElec. Coop. v. FERC, 898 F.3d 1254 (D.C. Cir. 2018); El Paso Elec. Co. v. FERC, \n76 F.4th 352 (5th Cir. 2023); BNP Paribas Energy Trading GP v. FERC, 743 \nF.3d 264 (D.C. Cir. 2014); K N Energy, Inc. v. FERC, 968 F.2d 1295 (D.C. Cir. \n1992); Natl’ Ass’n of Regulatory Util. Commis. v. FERC, 475 F.3d 1277 (D.C. \nCir. 2007).  \n3. \nThe June Order’s dismissal of the Industrials’ unlawful regulatory takings \nargument on the grounds of “lack of finality” is arbitrary and capricious and \ninconsistent with governing appellate precedent. U.S. Const. amend. V.; Lingle \nv. Chevron U.S.A., 544 U.S. 528 (2005); Loretto v. Teleprompter Manhattan \nCATV Corp., 458 U.S. 419 (1982); Lucas v. South Carolina Coastal Council, 505 \nU.S. 1003 (1992); Penn Central Trans. v. New York City, 438 U.S. 104 (1978).  \nB. \nARGUMENT \nIn the December Order and June Order, the Commission cites changing circumstances on \nthe transmission grid regarding reliability and resource adequacy risks as the underpinning reason \nthat BTMG rules must change.28 The expansive growth of super-sized computational load has \ndriven the need to ensure transmission services remain just and reasonable, and the \nIndustrials/Amtrak do not oppose the Commission’s primary reforms and policy objectives. \nHowever, the Industrials/Amtrak request rehearing on particular determinations in the June Order \nthat run crosswise with cost-causation principles, for which the Commission did not provide a \nreasoned explanation or engage with Industrials’/Amtrak’s underlying arguments. To allow \nAmerican industry to thrive and grow in PJM, these critical flaws in the June Order must be \naddressed. \nCourts have consistently affirmed the Commission’s responsibility to substantiate its \ndecisions with reasoned, principled decision-making when determining just and reasonable rates. \n \n28 See June Order at P 149 (citing December Order at P 186)."},{"page":11,"startToken":3413,"endToken":4000,"text":"11 \n \n \nThe D.C. Circuit Court of Appeals has held that the FERC must “adequately explain how the \nevidence it relied on supported the conclusion it reached.”29 The Commission does not meet its \nstatutory obligation under the Administrative Procedure Act (“APA”) when it does not adequately \nexplain its rationale for its rate-setting decisions.30  A Commission order will be reversed on review \nif it is arbitrary or capricious, reflects an abuse of discretion, is not otherwise in accordance with \nlaw, or is not supported by substantial evidence.31 To avoid an arbitrary and capricious decision or \none that does not reflect reasoned decision-making, the Commission must consider all important \naspects of the problem at issue.32 It is “well established that the Commission must ‘respond \nmeaningfully to the arguments raised before it.’”33 To satisfy its obligation to engage in reasoned \ndecision-making, the Commission must examine the relevant data and articulate a rational \nconnection between the facts found and the choices made.34 The Commission must reach its \n \n29 Emera Maine v. FERC, 854 F.3d 9, 28 (D.C. Cir. 2017) (citing Wis. Gas Co. v. FERC, 770 F.2d 1144, 1156 (D.C. \nCir. 1985)). The Commission’s broad mandate to set just and reasonable rates under the Federal Power Act does not \nrelieve the FERC of the requirement to engage in reasoned decision-making. New England Power Generators Ass’n, \nInc. v. FERC, 881 F.3d 202, 210 (D.C. Cir. 2018). While the FERC’s determinations regarding technical issues are \nentitled to deference, deference is not owed if the FERC “has not substantiated the application of its policy, either \nthrough the development of specific facts or by making a reasoned explanation.” El Paso Elec., 832 F.3d 495, 503 (5th \nCir. 2016) (quoting Fla. Gas Transmission Co. v. FERC, 876 F.2d 42, 45 (5th Cir. 1989)). \n30 See Missouri Public Service Com’n v. FERC, 234 F.3d 36, 40 (D.C. Cir. 2000) (reasoned and principled decision-\nmaking is essential). This comports with the design of the FPA, where Commissioners are directed to give their \nreasoning even where the Commission cannot come to a decision due to a tie vote. 16 U.S. Code § 824d(g)(1).  \n31 5 U.S.C. § 706(2)(A); Vistra Corp. v. FERC, 80 F.4th at 312; South Carolina Pub. Serv. Auth. v. FERC, 762 F.3d \n41, 55 (D.C. Cir. 2014); Sacramento Mun. Util. Dist. v. FERC, 616 F.3d 520, 528 (D.C. Cir. 2010).   \n32 See, e.g., Motor Vehicle Mfrs. Ass’n, 463 U.S. at 43 (1983) (“an agency rule would be arbitrary and capricious if \nthe agency . . . failed to consider an important aspect of the problem”); NorAm Gas Transmission Co. v. FERC, 148 \nF.3d 1158, 1165 (D.C. Cir. 1998) (“In previous cases, we have rejected agency orders when the Commission neglected \nto deal with an important part of the problem…”) (citing Laclede Gas Co. v. FERC, 997 F.2d 936, 945-48 (D.C. Cir. \n1993)); North Carolina Util. Comm’n v. FERC, 42 F.3d 659, 666 (D.C. Cir. 1994) (given the complexity of the issue, \nthe FERC must more fully explain its decision).     \n33 TransCanada Power Mktg. Ltd. v. FERC, 811 F.3d 1, 12 (D.C. Cir. 2015). \n34 Sacramento, 616 F.3d at 528; Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004) \n(quoting Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43 (1983))."},{"page":12,"startToken":4000,"endToken":4400,"text":"12 \n \n \nconclusion through decision-making that is “reasoned, principled, and based upon the record.”35 \nIf the Commission “does not provide a rational explanation for its action based on relevant data, \nthen that action is arbitrary and capricious.”36  \nThe Industrials/Amtrak raise three discrete BTMG-related issues on rehearing.  First, while \nthe 50 MW Retail Threshold approved by the Commission provides relief to smaller facilities (with \npresumptively lower grid impact) that may help mitigate some negative effects of the June Order, \nthe June Order neglected to meaningfully engage with substantive arguments for a threshold of at \nleast 200 MW for retail BTMG netting—in particular, the advantages of a 200 MW or greater \nthreshold over a 50 MW threshold.  Importantly, a threshold of at least 200 MW for retail BTMG \nnetting would allow FERC to focus on the impacts of new, super-sized load entrants (the prime \ncause of the resource adequacy and reliability constraints facing the grid) while retaining the \neffective and efficient structure that has fostered investment by industrial and institutional \ncustomers and encouraged efficient use of the grid.  \nSecond, the June Order granted a narrow exemption for certain QFs that have minimal use \nof the transmission system due to the configurations of their systems, whereby certain amounts of \nload are reduced if on-site generation were to trip off.37 While this exemption is appreciated and \nconsistent with cost causation, it is unduly narrow. The June Order clarified that all customers are \nqualified for up to 50 MW of netting regardless of their size. However, for QFs that exceed 50 \n \n35 New Eng. Power Generators Ass’n v. FERC, 881 F.3d 202, 210-11 (D.C. Cir. 2018); West Deptford Energy, LLC, \n766 F.3d 10, 20 (D.C. Cir. 2014); ExxonMobil Oil v. FERC, 487 F.3d 945, 953 (D.C. Cir. 2007); see New York v. \nFERC, 535 U.S. 1, 36 (2002); see also Transmission Access Policy Group v. FERC, 225 F.3d 667, 705, 716 (D.C. \nCir. 2000) (citing Associated Gas Distributors v. FERC, 824 F.2d 981, 1021 (D.C. Cir. 1987)); Colo. Interstate Gas \nCo. v. FERC, 146 F.3d 889, 893 (D.C. Cir. 1998).   \n36 La. PSC. V. FERC, 20 F.4th 1, 6-7 (D.C. Cir. 2021) (citing 5 U.S.C. § 706(2)(A) and Motor Vehicle Mfrs. Ass’n, \n463 U.S. at 43)).  \n37 June Order at P 142."},{"page":13,"startToken":4400,"endToken":4734,"text":"13 \n \n \nMW of BTMG and do not qualify for grandfathering, the June Order fails to provide a pathway to \ndemonstrate that systems are designed and maintained for minimal grid use. Even if a retail \ncustomer with a QF has 20 years of never coming online during a system peak, that customer is \nnow required under the December Order and June Order to pay transmission and capacity charges \nbased on a simple, theoretical “possible” use of the system.  Relatedly, the June Order also did not \nmeaningfully address its legal requirements that mandate certain assumptions for back-up service \nto QFs under PURPA, as set forth in 18 C.F.R. § 292.305 (“QF Back-up Regulations”). The \nCommission defers the Industrials/Amtrak’s arguments on this topic by asserting that the \nDecember Order’s directive “has no bearing on the rates at which a host utility provides backup \nservice to QFs.”38 However, this explanation in the June Order does not grapple with the regulatory \ntext, the purpose of PURPA, or the practical realities of how back-up service is priced and paid. \nThis is not only a legal error, but an economically damaging error for the future of American \nmanufacturing in the PJM region. The FERC should broaden its exemption to allow all QFs to \ncontinue to qualify for existing BTMG netting rules. \nFinally, the Industrials/Amtrak seek rehearing and clarification regarding the June Order’s \ndetermination that an unlawful takings claim is not yet ripe due to lack of finality. If the \nCommission were to continue to disagree with the rationale behind the regulatory takings claim, \nIndustrials/Amtrak ask the Commission to clarify and confirm when agency action is final so that \ninjured retail customers may timely seek redress for harms inflicted by FERC’s orders.   \nIn summary, granting this rehearing request in full would avoid discouraging future \ninvestment in America’s manufacturing and institutional sectors in PJM. While the grandfathering \nprovisions are appreciated by existing customers, even those who appear to qualify for \n \n38 June 2026 Order at P 245."},{"page":14,"startToken":4734,"endToken":5086,"text":"14 \n \n \ngrandfathering must, under the June Order, take great care to preserve that grandfathering to avoid \nadverse economic changes to their facilities. The Industrials/Amtrak respectfully request that the \nCommission adopt a 200 MW Retail Threshold and a broad exemption for QFs to preserve the \ninvestment environment in American manufacturing in the PJM region, consistent with cost \ncausation principles and Commission Regulations.  \n1. The June Order failed to engage with the evidence and arguments presented by \nthe Industrials/Amtrak that provided reasons a 200 MW or greater materiality \nthreshold for NITS netting rules is preferable to a 50 MW Retail Threshold. \nIn its December Order, FERC directed PJM to propose a materiality threshold, below \nwhich retail BTMG netting rules will continue in effect. PJM proposed a 50 MW Retail Threshold \nbased on generator size, with an alternative 200 MW Retail Threshold as an interim solution if \nFERC did not adopt PJM’s legacy treatment for existing on-site generation above 50 MW.39 The \nIndustrials/Amtrak supported a proposal for at least a 200 MW Retail Threshold to appropriately \nweigh the cost-causation balance of use of the system by “smaller” large load vs. the risks of super-\nsized load coming online. The Industrials/Amtrak argued that a threshold of at least 200 MW \nwould, as a practical matter, avoid making retail customers’ resource adequacy contributions \nuneconomic while still addressing the challenge of massive new loads entering the system.  \nIn the June Order, the Commission selected a 50 MW Retail Threshold, determining that \n“50 MW strikes a reasonable balance between a lower threshold, which may restrict netting more \n \n39 PJM stated in its Compliance Filing that if the Commission adopts a “higher interim materiality threshold of this \nsort at the start of the transition period, PJM commits to reviewing additional data from Transmission Owners on the \nextent and size of existing Retail BTMG. This data could inform whether the interim materiality threshold should be \nfurther refined in the future through a separate filing on compliance in this docket or, if necessary, pursuant to section \n205 of the Federal Power Act.” PJM Compliance Filing at 15."},{"page":15,"startToken":5086,"endToken":5426,"text":"15 \n \n \nthan necessary to respond to resource adequacy concerns, and a higher threshold, which would fail \nto address the resource adequacy concerns identified in the December Order.”40  \nThe Industrials/Amtrak request rehearing on the Retail Threshold issue because the \nCommission did not engage on most of the arguments for why PJM’s alternative proposal of 200 \nMW is superior to the main proposal of 50 MW. The June Order addressed economic harm to \nexisting BTMG arrangements through grandfathering; it also addressed arguments that a higher \nthreshold incentivizes generation to operate efficiently.41 However, the June Order did not address \nor refute any of the arguments presented by the Industrials/Amtrak concerning the objective bases \nfor at least 200 MW vs. 50 MW for a Retail Threshold. These arguments are summarized below. \nThe Industrials/Amtrak respectfully request that the Commission reconsider and address the \nfollowing objective bases for why a 200 MW Retail Threshold is preferable to a 50 MW Retail \nThreshold. \nFirst, a 200 MW Retail Threshold would focus on reliability challenges caused by super-\nsized load, causing the resource adequacy concerns, while avoiding chilling industrial and \ninstitutional investment. The Industrials/Amtrak presented evidence showing that most load \ngrowth is driven by large data centers of 200 MW or greater. These new entrants frequently have \nmassive capital behind them, enabling them to develop massive centers of load more quickly than \nany manufacturer or industrial seeking to expand operations. It is this growth that has driven many \nof the current challenges on the grid. As recognized by the D.C. Circuit Court of Appeals, under \n \n40 June Order at P 208. \n41 The Industrials/Amtrak respectfully note that in rejecting the grid efficiency argument, the Commission cited no \nevidence, study, or testimony explaining what will happen to grid efficiency with the changes to NITS netting rules. \nNITS with netting has efficiency incentives so deeply baked into the structure, it is unclear what changes will occur \non the grid when that incentive is reduced. See., e.g., June Order at P 211."},{"page":16,"startToken":5426,"endToken":5762,"text":"16 \n \n \nthe cost-causation principle, “costs are to be allocated to those who cause the costs to be incurred \nand reap the resulting benefits.”42  \nThe June Order does not develop, rely on, or reference any reliability performance and risk \nassessment as applied to traditional industrial, traditional, and transportation loads to justify the \napplication of the new netting rules to non-computational loads above 50 MW. Notably, the June \nOrder briefly recognizes in a footnote, the North American Electric Reliability Corporation’s \n(“NERC”) review and development of reliability standards specific to computational loads43 and \nsignals its concern with allowing “large loads like data centers to net.”44 However, the June Order \ndoes not substantiate the application of those same reliability and cost concerns for large data \ncenters to smaller, traditional industrial loads. Notably, since the issuance of the December Order, \nNERC has increasingly focused its attention on developing new reliability standards specific to \ncomputational loads, not other traditional large loads. Since the issuance of the June Order, the \nCommission on July 16, 2026, announced a new proceeding for Reliability Standard(s) Pertaining \nto Computational Load Integration in Docket No. RD26-7-000. Furthermore, on June 30, 2026, \nthe U.S. House of Representatives Committee on Energy and Commerce amended pending federal \nlegislation, the Ratepayer Protection Act, aimed at protecting existing customers from paying for \nnetwork upgrades triggered by data centers. In response to concerns raised by manufacturing \ngroups, the Large Load Customer definition in the pending legislation now applies only to \ncomputational loads, not to all large loads over 100 MW.45 The above statements and policy \n \n42 South Carolina Pub. Serv. Auth. v. FERC, 762 F.3d 41, 85 (D.C. Cir. 2014) (citing Natl’ Ass’n of Regulatory Util. \nCommis. v. FERC, 475 F.3d 1277, 1285 (D.C. Cir. 2007) (“NARUC”)). \n43 June Order at P 345, n. 792. \n44 June Order at P 79 (quoting December Order at P 186).   \n45 See https://www.congress.gov/119/meeting/house/119437/documents/BILLS-119-HR9340-A000370-Amdt-3.pdf \n(last accessed July 20, 2026)."},{"page":17,"startToken":5762,"endToken":6130,"text":"17 \n \n \nmovements reflect growing recognition that computational loads present different system impacts \nthan traditional large loads. Further, a large group of PJM transmission owners stated last year in \nthe Large Load ANOPR Proceeding that large data centers of 200 MW or greater are the primary \ndrivers of load growth.46  Because most industrial and institutional load is under 200 MW, and \nload greater than 200 MW (as opposed to 50 MW) is primarily the cause of present challenges on \nthe grid,47 the remedy must be tailored to address the cause.  \nSecond, a 200 MW Retail Threshold avoids major administrative disincentives for most \nindustrial and institutional loads to operate on-site generation by avoiding the need to force \nexisting retail customers into new and unfamiliar regulation. Left unchanged, the June Order \nwill force some large industrial and institutional customers to become FERC-regulated public \nutilities, secure PJM membership, and undertake related credit and risk requirements. The world \nof PJM is complex, and many retail customers are focused on providing the goods or services they \ndeliver every day—not being an energy company. Forcing such retail customers into new and \nunfamiliar regulation, PJM membership, and other federal requirements creates a substantial \nburden. There are sound policy and legislative reasons not to treat those integrated facilities as \npublic utilities or to burden them with the regulatory demands required of wholesale generators in \nPJM.   \n \n46 Reply Comments of the Indicated PJM Transmission Owners, Interconnection of Large Loads to the Interstate \nTransmission System, Docket No. RM26-4-000 (Dec. 5, 2025) (“To the extent the Commission asserts jurisdiction \nover large load interconnections, it should adopt a sufficiently narrow definition of ‘large load customer’ limited to \nlarge (200 MW or greater) data center customers. It is those customers that are primarily driving load increases.”). \n47 Dauphinais Affidavit at 34, 38, Attachment 2 and Attachment 3 (showing that data centers are typically at 300 MW \nand above). In reviewing relevant development in state regulatory proceedings in Michigan, Mr. Dauphinais \nhighlighted evidence supporting a determination of defining large load at a 300 MW threshold, given that most data \ncenters are at above 300 MW (whereas most manufacturers using more extensive BTMG operations would be below \n300 MW in load)."},{"page":18,"startToken":6130,"endToken":6458,"text":"18 \n \n \nFERC should do the same here by setting a sufficiently high threshold to avoid “death by \n1000 cuts” to the industrial and institutional customers who are retail customers and are \naccustomed to operating as such. PJM has offered to review data on the extent and size of existing \nretail BTMG.48 This proposal could mitigate FERC’s concern about PJM not planning for the full \nextent of behind-the-meter load, as it relates to BTMG under a reasonable Retail Threshold. \nThird, a 200 MW Retail Threshold aligns with regulatory logic and federal reference \npoints that identify various “tiers” of large load. While “large load” may mean different things \nin different contexts, the Industrials/Amtrak respectfully suggest that the Commission should \nconsider a size framework that recognizes that “large load” and “large generation” come in \ndifferent iterations. While various cutoffs have been proposed, the following federal reference \npoints make sense: \n PURPA’s reference point for “small” generation is 80 MW. These types of QFs are \ntermed “qualifying small power production facilities,” suggesting that medium or \nlarger generation categories would be above 80 MW.  \n Many large manufacturers come in this “middle” zone between “small” (under 80 MW) \nand “super-sized” (above 200 or 300 MW). For example, the largest industrial or \ninstitutional facility mentioned by the Commission in the June Order is reported to be \nslightly under 200 MW. \n Order 2023 and Order 2023-A also reflect this same logical grouping structure for \ngeneration sizing purposes. There, the Commission set forth tiers of study deposits, \n \n48 Compliance Filing at 15 (“Should the Commission adopt a higher interim materiality threshold of this sort at the \nstart of the transition period, PJM commits to reviewing additional data from Transmission Owners on the extent and \nsize of existing Retail BTMG. This data could inform whether the interim materiality threshold should be further \nrefined in the future through a separate filing on compliance in this docket or, if necessary, pursuant to section 205 of \nthe Federal Power Act.”)."},{"page":19,"startToken":6458,"endToken":6767,"text":"19 \n \n \nwith the lowest tier being generation under 80 MW, the middle tier being 80 MW to \nunder 200 MW, and the upper tier being 200 MW or above. \nWhile the Commission is not bound to any of these reference points, the Industrials/Amtrak \nbelieve that the Commission faces a critically important decision on the “middle tier” up to 200 \nMW. In that band sit some of America’s biggest manufacturing facilities, including steel, \nconsumer good producers, chemicals, pharmaceuticals, oil refineries, transportation providers, and \nothers, who have demonstrated for decades their reliable contributions to the grid. Many of these \nfacilities are cogeneration facilities and QFs, demonstrating efficiency and integrated load and \ngeneration, especially when there are thermal processes involved. The Industrials/Amtrak \nrespectfully request that the Commission set a Retail Threshold that allows for netting up to the \ntop of this “middle tier” at 200 MW. How FERC resolves this may determine the future of \nhundreds of megawatts of existing and planned on-site generation that would support resource \nadequacy efforts in the region. \nFourth, a 200 MW Retail Threshold emphasizes stable rules for customers, a more \ndurable approach than grandfathering, as demonstrated by Eastman and Amtrak. In Paragraph \n246 of the June Order, the Commission stated that “Eastman’s concern appears to be addressed,” \nmeaning that the Commission believes Eastman will qualify for grandfathering. However, even if \nEastman and other large industrial and institutional customers do qualify for grandfathering, \noperating subject to grandfathering creates substantial uncertainty. It also does not address the \nneed for facilities to expand and new ones to open, to realize the promise of American industry in \nPJM. The Administration and various PJM governors’ offices are pursuing economic development \nagendas that emphasize the importance of producing products in the United States. Most of the \nIndustrials’ members do just that, producing goods that are sold domestically and worldwide. They"},{"page":20,"startToken":6767,"endToken":7083,"text":"20 \n \n \nand similarly-situated businesses employ millions of Americans as part of the United States’ \nindustrial backbone. In the case of Amtrak, losing the ability to net transmission charges with the \ncontracted BTMG will significantly increase Amtrak’s operating costs and seriously affect the \nNortheast Corridor.49 Given Amtrak’s need for redundancy to support the reliability imperatives \nof Amtrak’s operations, Amtrak’s retail BTMG exceeds the 50 MW Retail Threshold proposed by \nPJM. Increasing the Retail Threshold to 200 MW would safely accommodate Amtrak’s contractual \narrangement without relying solely on grandfathered arrangements. \nThe Industrials/Amtrak respectfully request that the Commission reconsider the Retail \nThreshold. American industry is a vital part of the nation’s electric grid. While the June Order \nprovides some positive movement, without modification or clarification on certain key issues, it \nthreatens to harm American industry, weaken resource adequacy, and result in undue \ndiscrimination. The Industrials/Amtrak respectfully request that the Commission reconsider the \narguments raised herein and adopt a 200 MW Retail Threshold, leading to a better and more \ndurable resolution of relevant issues. \n2. While the June Order approved a narrow exemption for certain cogeneration \nQFs, the exemption is unduly narrow because it does not clearly allow QFs with \nlow reliability and system risks or strong performance histories to also be exempt \nfrom the new netting rules, consistent with cost causation principles and the \nCommission’s QF Back-up Regulations. \nIn the June Order, the Commission authorized changes to PJM’s BTMG rules because “the \nCommission found that PJM’s existing retail BTMG netting rules may lead to both reliability and \nresource adequacy risks because PJM, per its Tariff, is obligated to serve transmission customers \nusing BTMG but does not consider such customers in transmission and resource adequacy \n \n49 As explained previously, Amtrak relies on retail BTMG, generated at 25 Hz, to provide energy supply and black-\nstart capability to support the south end of Amtrak’s Northeast Corridor traction power."},{"page":21,"startToken":7083,"endToken":7429,"text":"21 \n \n \nplanning.”50 The Commission recognizes the potential that BTMG could trip offline or become \nunavailable, resulting in a large retail customer’s load appearing on the system. \nThe Commission also recognized in the June Order a narrow exemption for cogeneration \nQFs with precise characteristics, directing PJM to submit a process for exemption from the new \nretail BTMG netting rules for cogeneration QFs “if they demonstrate that they are integrated with \nload such that, when their generating facility trips offline, the load follows, and they thus do not \npresent the reliability or resource adequacy concerns discussed in the December Order.”51  \nWhile the exemption provided in the June Order is a step in the right direction, it is overly \nnarrow and does not reasonably account for cost-causation principles of bespoke behind-the-meter \narrangements that are designed and operated for minimum grid impact, particularly cogeneration \nQFs, which must meet efficiency standards and are generally designed to be deeply integrated with \nthe on-site load. As noted in PJM’s Compliance Filing, “existing retail BTMG arrangements with \nsuch contractual agreements and that otherwise have QF status have been in place and netted \nagainst Network Loads within PJM without known operational issues to date.”52American industry \nand institutions have developed countless customized configurations to support their heavy \noperational loads, and in many cases, to integrate directly with a manufacturing or heating/cooling \nprocess. However, under the December Order and June Order, aside from the existing industrial \nand institutional facilities that qualify for grandfathering, beyond the 50 MW Retail Threshold, no \npathway exists for most industrial and institutional facilities to demonstrate, and be rewarded for, \ntheir performance in operating their BTMG with minimal use of the grid, consistent with cost \n \n50 June Order at P 81. See also id. at P 16 (“retail BTMG netting rules may lead to both reliability and resource \nadequacy risks because PJM, per its Tariff, is obligated to serve transmission customers using BTMG but does not \nconsider such customers’ full gross load in transmission and resource adequacy planning”). \n51 Id. at P 142. \n52 PJM Compliance Filing at 10."},{"page":22,"startToken":7429,"endToken":7940,"text":"22 \n \n \ncausation principles. Instead of applying cost causation principles53 and seriously grappling with \ngeneral differences between QFs and other loads (particularly computational load), the June Order  \nrefers back to the generic concerns in Paragraph 186 of the December Order around resource \nadequacy, reliability, and cost shifting.54  \nFirst, the June Order’s limited QF exemption demonstrates the need for a broader \nexemption for other QFs with limited grid impacts. This exemption from the new gross NITS rule \nmakes sense because the QFs with those characteristics have a substantially lower risk profile. The \nrisk is minimized by the facility's configuration and/or operations. Accordingly, it would not be \njust and reasonable to charge them for NITS and capacity on a gross basis.    \nWhile this exemption addressed one particular configuration with minimal grid impacts, \nthe June Order neglected to address the limited reliability risk of other QFs, particularly \ncogeneration QFs, which are generally operated as highly reliable, efficient generation that takes \nstrain off the grid and are designed and operated to function during system peaks. \n \n53 Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1255 (D.C. Cir. 2018); see also El Paso Elec. Co. v. FERC, 76 \nF.4th 352, 357 (5th Cir. 2023); see also BNP Paribas Energy Trading GP v. FERC, 743 F.3d 264, 268 (D.C. Cir. \n2014) (The principle is a “matter of making sure that burden is matched with benefit.”); K N Energy, Inc. v. FERC, \n968 F.2d 1295, 1300 (D.C. Cir. 1992). \n54 See June Order at P 41 (citing December Order at P 186), P 81. Interestingly, the June Order appears to confirm that \nan in-depth cost causation analysis has not yet been completed.  The June Order asserts that the lack of Tariff clarity \n“introduces the risk that costs related to Co-Location Arrangements may not be allocated consistent with cost causation \nprinciples.” June Order at P 59 (emphasis added). As to BTMG arrangements, the entirety of the June Order’s \nreasoning that BTMG arrangements are no longer supported by cost causation principles hinges on the generic \nreference to “a change in circumstances,” yet the June Order tentatively asserts that “PJM’s existing retail BTMG \nnetting rules may lead to both reliability and resource adequacy risks.” June Order at P 81 (emphasis added). The June \nOrder’s inconclusiveness around the reliability and resource adequacy risks confirms that the Commission has not \nfully developed a performance and risk assessment. The Commission has not sufficiently examined the relevant data \nand considerations and has neither articulated a satisfactory explanation, nor provided a rational connection between \nthe facts found and the choice made. La. PSC v. FERC, 866 F.3d 426, (D.C. Cir. 2017); Midwest ISO Transmission \nOwners v. FERC, 373 F.3d 1361, 1368 (D.C. Cir. 2004) (quoting Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. \nIns. Co., 463 U.S. 29, 43 (1983)). As a result, applying the BTMG netting reforms to manufacturers and non-\ncomputational loads is arbitrary and capricious, is unsubstantiated, inconsistent with cost causation principles, and \ndoes not reflect reasoned decision-making."},{"page":23,"startToken":7940,"endToken":8349,"text":"23 \n \n \nThe June Order takes a valued step toward recognizing the cost-causation issues unique to \nlarge industrial and institutional users, but it is insufficient. Under the June Order, above the 50 \nMW threshold, there is no distinction between a retail customer whose generation operates 99% \nof the time and one that operates 50% of the time, despite dramatically different uses of the \ntransmission system. Not only is this a cost-causation issue (directly affecting the determination \nof a just and reasonable replacement rate), but rejecting performance-based exemptions also \neliminates a major incentive for efficient operations.  \nSecond, QFs warrant a broad exemption, or at least a pathway to an exemption, to obtain \nrates that comport with their performance, in accordance with cost causation principles. \nCongress enacted the PURPA nearly 50 years ago.55 PURPA directed the FERC to enact \nregulations to “encourage cogeneration and small power production, and to encourage geothermal \nsmall power production facilities of not more than 80 megawatts capacity.”56 While small power \nproduction QFs have an 80 MW limit, there is no size limitation for cogeneration QFs, and the \ndevelopment of QFs for manufacturers aligns with the fact that some cogeneration QFs certainly \nexceed PJM's current view of a Large Load being 50 MW. Under PURPA, electric utilities are \nrequired to offer QFs the opportunity to sell electric energy and to purchase electric energy output \nfrom those QFs.  \n \n55 PURPA is codified as Section 210 of the Federal Power Act (“Section 210”). 16 U.S.C. § 824a-3. Under PURPA, \nQFs fall into two broad categories: “qualifying small power production facilities,” which can be sized up to 80 MW, \nand “qualifying cogeneration facilities,” which have no size limit. Cogeneration QFs must achieve certain efficiency \nstandards and are highly efficient in their use of input fuels. Cogeneration QFs, which produce both electricity and \nheat from the same fuel source, make use of the “waste heat” in their manufacturing, heating, or cooling process. As \nexplained by Mr. Dauphinais in his Affidavit, “Cogeneration Facilities can achieve efficiencies in excess of 80%, by \nusing waste heat and avoiding electrical losses, compared to the efficiency of approximately 50% for conventional \nelectricity generation with a steam boiler.” Dauphinais Affidavit at P 11. \n56 16 U.S.C. § 824a-3(a) (emphasis added). PURPA requires electric utilities to offer to “(1) sell electric energy to \nqualifying cogeneration facilities and qualifying small power production facilities” and to offer to “(2) purchase \nelectric energy from such facilities.” Id."},{"page":24,"startToken":8349,"endToken":8671,"text":"24 \n \n \nMany QFs are highly efficient facilities, including cogeneration facilities, which produce \nboth electricity and heat from the same fuel source, then make use of the “waste heat” in industrial \noperations. As part of the congressional mandate, QFs are entitled to access to supplementary, \nback-up, maintenance, and interruptible power, pursuant to regulations.57 To maintain QF status, \nCommission regulations require certain QFs to meet specified efficiency standards. If there is a \nchange in any of the factors contributing to a QF’s certification as a QF, the QF owner is obligated \nto advise the Commission.58 Consequently, for both operational and regulatory reasons, many QFs \noperate with a high capacity factor, reliably operating during transmission peaks.59  \nWithout an appropriate exemption, cogeneration QFs operating with a strong track record \nof performance and a high capacity factor will suddenly be paying for transmission service they \ndo not use. Absent a grandfathering exemption, removal of netting without an available alternative \nwill be devastating to many industrial entities, including those that own cogeneration QFs, and in \nturn, damage the grid by rendering on-site generation uneconomic (and effectuating an unlawful \ntaking of private property), chilling future on-site generation investment, and harming both \nAmerican manufacturing and efforts to resolve the pending resource adequacy crisis in PJM. \nThird, the Commission failed to meaningfully engage with the PURPA QF Back-up \nRegulations requiring back-up service with specified assumptions, resulting in an error of \nlaw that deemed back-up service as unrelated to transmission service. Should the Commission \nwish to amend PURPA regulations, it must initiate notice-and-comment rulemaking procedures \nunder the APA.   \n \n57 18 C.F.R. § 292.305(b). \n58 18 C.F.R. § 292.307(f). \n59 Pursuant to PURPA, “the electrical, thermal, and chemical output” of a qualifying cogeneration facility must be \n“used fundamentally for industrial, commercial, or institutional purposes and is not intended fundamentally for sale \nto an electric utility.” 16 U.S.C. § 824a-3 (n)(1)(A)(ii)."},{"page":25,"startToken":8671,"endToken":8961,"text":"25 \n \n \nSection 292 of the Commission’s Regulations governs QFs. Under these Regulations, QFs \nare entitled access to supplementary power, back-up power, maintenance power, and interruptible \npower, and access to back-up power and maintenance power must meet certain requirements \ndefined in the Regulations (“Required QF Back-up Assumptions”). “Back-up power” is defined in \nthe regulations as “electric energy or capacity supplied by an electric utility to replace energy \nordinarily generated by a facility’s own generation equipment during an unscheduled outage of \nthe facility.”60 The Required QF Back-up Assumption is the requirement that rates for back-up or \nmaintenance power “[s]hall not be based upon an assumption (unless supported by factual data) \nthat forced outages or other reductions in electric output by all qualifying facilities on an electric \nutility’s system will occur simultaneously, or during the system peak, or both.” Bottom line:  \nRegulations enacting PURPA ensure that QFs have access to back-up and maintenance service \nthat meets the Required QF Back-up Assumptions regarding generator uptime. \nFor years, QFs in PJM have relied on the PJM Retail BTMG netting rules, which aligned \nwith the Required QF Backup Assumptions, because NITS with netting does not assume “that \nforced outages or other reductions in electric output . . . will occur simultaneously, during the \nsystem peak, or both.”61 Consequently, NITS provided a just and reasonable back-up service to \nQFs. In fact, some facilities that would otherwise be QFs allowed their QF status to expire because \nof the traditional NITS alignment with the Required QF Back-up Assumptions. \nIn the June Order, the Commission dismissed the Industrials/Amtrak’s arguments \nconcerning the Required QF Back-up Assumptions requirement in PURPA regulations. \nSpecifically, the June Order stated:  \n \n60 18 C.F.R. § 292.101. \n61 18 C.F.R. § 292.305(c)."},{"page":26,"startToken":8961,"endToken":9417,"text":"26 \n \n \nFirst, we clarify that the December Order’s replacement rate does not change any \nobligation under the Commission’s PURPA regulations regarding QFs’ access to \nsupplementary, back-up, maintenance, and interruptible power. The replacement \nrate applies only to Network Customers’ usage of NITS under the tariff, and \nnothing in the replacement rate undoes the [PURPA regulatory requirement] that, \nas to QFs, ‘each electric utility shall provide . . . Supplementary power, Back-up \npower, Maintenance power, and Interruptible power.’ While Industrials suggest \nthat removing netting rules may contradict Commission regulations that require \nback-up and maintenance services for cogeneration QFs, Industrials do not explain \nhow the replacement rate results in Industrials no longer being entitled to back-up \nand maintenance power under the Commission’s regulations.62 \n   \nThe June Order’s statement above serves as an admission that the June Order neither \nproperly addressed arguments brought before it, nor considered all important aspects of the \nproblem at issue.63 The Industrials/Amtrak provided detailed explanation of how neither the FCD \nand NCFD services nor the gross NITS approach meet the Required QF Back-up Assumptions.64 \nThe Industrials/Amtrak also sponsored an affidavit by a technical consultant explaining these same \nconcepts and outlining why the replacement rate does not meet the Required QF Back-up \nAssumptions. Industrials/Amtrak provided substantial evidence that the replacement rate negates \nthe express guarantee of a rate based on the Required QF Backup Assumptions, unless factual data \npoints out otherwise.65 The Industrials/Amtrak incorporate those arguments and the Dauphinais \n \n62 June Order at P 140 (emphasis added). \n63 Motor Vehicle Mfrs. Ass’n, 463 U.S. at 43 (1983) (“an agency rule would be arbitrary and capricious if the agency \n. . . failed to consider an important aspect of the problem”). \n64 See, e.g., Industrial/Amtrak Compliance Protest at 19; Responsive Brief of Industrial Customer Organizations and \nAmtrak, Docket Nos. EL25-49-000, EL25-49-001, AD24-11-000, EL25-20-000 (consolidated), at 13-19 (Mar 25, \n2026); Reply Brief of Industrial Customer Organizations and Amtrak, Docket Nos. EL25-49-000, EL25-49-001, \nAD24-11-000, EL25-20-000 (consolidated), at 5-9 (Apr. 24, 2026). \n65 As explained by Mr. Dauphinais, the current BTMG netting construct for NITS permits QFs to receive the back-up \npower they are guaranteed—back-up power that is charged without a default assumption that the back-up power will \nbe needed during peak times. If back-up services are needed during peak times, the current NITS design ensures \ncustomers pay for them by appropriately measuring peak usage. Dauphinais Affidavit at PP 28-29.  As explained by \nMr. Dauphinais, “With respect to the transmission component of back-up and maintenance power, Section 34.2 of the \nPJM Open Access Transmission Tariff (“PJM Tariff”) currently excludes the load served by the operating behind the \nmeter generation of a retail customer from that retail customer’s daily load for [NITS].”  He further states:"},{"page":27,"startToken":9417,"endToken":9790,"text":"27 \n \n \nAffidavit into this Rehearing Request by reference. \nAdditionally, the June Order fails to engage with the Industrials/Amtrak’s arguments on \nthis topic by asserting that the December Order’s directive “has no bearing on the rates at which a \nhost utility provides backup service to QFs.”66 However, this explanation leads to an arbitrary and \ncapricious result, because the Commission has not explained its interpretation of the regulatory \ntext, the purpose of PURPA, or the practical realities of how back-up service is priced and paid. \nThis is legal error with tangible adverse consequences for manufacturers in the PJM region. For \nthe following reasons, the Industrials/Amtrak respectfully request that the Commission grant \nreconsideration of this matter and ensure that all QFs have access to back-up service that aligns \nwith the Required QF Back-up Assumptions. \nFourth, the regulatory text of the QF Back-up Regulations indicates that the December \nOrder does, indeed, affect “the rates at which a host utility provides backup service to QFs.”67 \nIn the PURPA regulations, “rate” is defined as “any price, rate, charge, or classification made, \ndemanded, observed or received with respect to the sale or purchase of electric energy or capacity, \nor any rule, regulation, or practice respecting any such rate, charge, or classification, and any \n \nWhether a retail customer has behind the meter generation or not, its NITS charges are based on the \ndemand the retail customer has historically put on the transmission system at the time of the annual \npeak of the transmission pricing zone. Given zonal transmission costs under the PJM Tariff are \ncurrently allocated to load on an annual coincident peak demand basis, this netting approach is \nconsistent with cost causation. Furthermore, it is consistent with FERC’s rule for backup and \nmaintenance power for Qualifying Facilities as it does not assume that a retail customer’s behind \nthe meter Qualifying Facility will be experiencing an outage at the time of the annual transmission \nsystem peak and instead relies on factual data, in the form of the behind the meter Qualifying \nFacility’s historical performance during the time of the annual peak of the transmission pricing zone, \nwhen allocating transmission costs to the retail customer.   \nDauphinais Affidavit at PP 28-29.    \n66 June Order at P 245.  \n67 Id."},{"page":28,"startToken":9790,"endToken":10099,"text":"28 \n \n \ncontract pertaining to the sale or purchase of electric energy or capacity.”68 This definition is broad \nand does not limit itself to the “sticker price” alone, but to the components, practices, regulations, \nand even contracts related thereto. The Required QF Back-up Assumption is a regulation about a \n“rate” that is charged for back-up power. The rates for back-up power, like any retail rate, are \ndeveloped based on the underlying wholesale costs—transmission and capacity costs being \nsignificant components. The June Order’s argument that its determination on NITS does not have \n“bearing” on the ultimate back-up service rate is mistaken. \nAdditionally, it is important to note that the PURPA regulations’ definition of “rate” \nincludes not only energy, but capacity as well. Capacity, like energy, has a wholesale component, \nand the BTMG netting rules in the PJM Tariff currently involve both transmission and capacity \ncost responsibility. The Industrials/Amtrak must assume that, for customers not eligible to \ncontinue with netting, capacity charges will be calculated on a gross basis as well. Yet, the PURPA \nRegulations’ definition of “rate” includes capacity. The June Order erred by stating that the \nDecember Order has “no bearing” on the ultimate back-up service rate charged to a retail \ncustomer.69 The Commission is responsible to ensure back-up rates comply with the FERC \nregulations, including the wholesale components directly under its purview. \nFifth, NITS has a direct impact on back-up power rates in restructured states, so changes \nto NITS directly affect whether back-up service includes the Required QF Back-up Assumptions \nset forth in the Commission’s QF Back-up Regulations. In restructured states, NITS costs are an \nessential component of back-up power costs. For example, in PPL Electric Utilities Corporation’s \nTariff, the tariff sets a rate for Back-up service (distribution charge), but that same section makes \n \n68 18 CFR § 292.101. \n69 June Order at P 245."},{"page":29,"startToken":10099,"endToken":10395,"text":"29 \n \n \nclear that the customer is separately responsible for transmission costs. Consequently, the use of a \nback-up service can directly affect transmission cost responsibility, depending on how and when \nit is used. Back-up service, like any retail service, has the wholesale components built in. \nAlong those lines, accepting the June Order’s statement that the Commission’s directive in \nthe December Order “has no bearing on the rates at which a host utility provides backup service \nto QFs” would mean that QFs should be able to obtain back-up power without use of the \ntransmission system. However, this notion flies in the face of the December Order and June Order, \nwhich make clear that retail configurations (such as BTMG) affect the transmission system. The \nJune Order, addressing the Commission’s jurisdiction over BTMG, explains BTMG netting rules \nas “allow[ing] PJM to calculate the charges for transmission service in interstate commerce,” and \nnot “targeting retail sales from BTMG.”70 Similarly, while the FERC may not set local utilities’ \nretail back-up service rates, those rates are intimately connected with the transmission system and \nthe underlying costs of transmission, which are determined by the Commission. \nFinally, the QF Back-up Regulations essentially set a cost-causation requirement into \nthe QF back-up rates. As recognized by the D.C. Circuit Court of Appeals, the “cost-causation \nprinciple” has been recognized “for decades” by “the Commission and the courts.” Under the cost-\ncausation principle, “costs are to be allocated to those who cause the costs to be incurred and reap \nthe resulting benefits.”71  In essence, the PURPA regulations protect a cost-causation approach to \ncharging QFs for back-up power. Accordingly, the Commission should ensure QFs can access \n \n70 Id. at P 43. \n71 South Carolina, 762 F.3d at 85 (citing NARUC, 475 F.3d at 1285)."},{"page":30,"startToken":10395,"endToken":10827,"text":"30 \n \n \nback-up service with the Required QF Back-up Assumptions.72 \nIn conclusion, the June Order did not engage meaningfully with the FERC’s own \nregulations requiring that back-up power based on certain cost-based assumptions be made \navailable to QFs. With the changes to NITS netting rules, QFs that are not eligible for one of the \nCommission’s exemptions (i.e., limited QF exemption or grandfathering) do not have a clear \npathway forward to back-up service that is based on cost causation, and that respects the \nrequirements of the Regulations.73  \nThe December Order and June Order implement new ratemaking methodologies that are \ncontrary to the existing PURPA regulations. In another case, the D.C. Circuit Court of Appeals \ndetermined that the FERC’s implicit acceptance of a new methodology for setting fees for \nhydropower projects “marked a change in [FERC’s] own regulations.”74 As a result, the Court \nvacated FERC’s methodology update because FERC did not engage in the required notice-and-\n \n72 While PURPA regulations expressly recognize the need for QFs to occasionally draw from the grid, including for \noccasional unscheduled outages, that need is not limited to QFs. To function properly and under just and reasonable \nrates, other industrial, institutional, and transportation retail loads with on-site generation also require back-up service \nbased on cost-causation. Absent access to retail netting, there is a sound basis to provide back-up service that \nrecognizes the cost-causation principles of back-up and maintenance service for BTMG facilities that do not have QF \nstatus.  \n73 Mr. Dauphinais explains in the attached Affidavit the reasons neither Firm nor Non-Firm CDS provides a cost-\nbased back-up service for cogeneration QFs and similarly-situated retail customers. As to Firm CDS, Mr. Dauphinais \nstated: \nWhile Contract Demand Transmission Service would provide reliable backup and maintenance \npower, it would not provide it at rates that are consistent with cost causation or FERC’s rules for the \nrates for the provision of backup and maintenance power to Qualifying Facilities. Specifically, it \nrequires payments for the service based on the contracted amount. As a result, it would inherently \nassume, in violation of FERC’s rules for backup and maintenance power for Qualifying Facilities, \nthat forced outages or other reductions in electric output by all qualifying facilities on an electric \nutility's system will occur simultaneously, or during the system peak, or both, without any factual \ndata to support such an assumption. As I have discussed at length in this affidavit, this is not a \nreasonable assumption for Qualifying Cogeneration Facilities.   \nDauphinais Affidavit at P 44. \n74 City of Idaho Falls v. FERC, 629 F.3d 222, 223, 231 (D.C. Cir. 2011)."},{"page":31,"startToken":10827,"endToken":11150,"text":"31 \n \n \ncomment rulemaking procedures under Section 553 in the APA.75 If the June Order is allowed to \nstand in this regard, it would be a violation of APA notice and comment rulemaking procedures \nby issuing an order, outside the rulemaking process, that is contrary to FERC’s existing \nregulations. \n3. The June Order’s dismissal of the Industrials’ unlawful regulatory takings \nargument on the grounds of “lack of finality” is arbitrary and capricious and \ninconsistent with governing appellate precedent.   \nIn their rehearing request, the Industrials explained that the December Order indirectly \neffectuated an unlawful taking of private property without providing just compensation, in \nviolation of the Fifth Amendment.76  The Industrials provided examples to substantiate their \ntakings argument, including cases in which the owner is deprived of economically beneficial uses \nof the property due to government action.77  \n Assume a large manufacturing facility with two behind-the-meter CHP units totaling \napproximately 100 MW. The facilities have been operational for an extended period of \ntime and are QFs under PURPA, exporting and selling power into the PJM grid. The NITS \nand Capacity savings provide more than half of the value of the CHP units. Yet, the \nDecember Order directly threatens to put this manufacturer out of business, as the removal \nof the NITS savings alone would likely render the customer’s retail BTMG uneconomic, \nresulting in the shutdown of the existing units and the manufacturer’s inability to continue \noperating.78  \nThe Industrials explained that the December Order’s abrupt shift to a “gross load” approach to \ntransmission cost responsibility will leave the property at certain manufacturing sites with little to \nno economically beneficial remaining uses.79 The Industrials/Amtrak emphasized that the \n \n75 Id. \n76 Industrials Rehearing Request at 31-34. \n77 Id. at 33 (citing Lingle v. Chevron U.S.A., 544 U.S. 528, 538 (2005) (quoting Lucas v. South Carolina Coastal \nCouncil, 505 U.S. 1003, 1019 (1992)).  \n78 Id. at 32 (Example #2). \n79 Id."},{"page":32,"startToken":11150,"endToken":11512,"text":"32 \n \n \nDecember Order’s shift to the “gross load” approach causes substantial economic impacts and “has \ninterfered with distinct investment-backed expectations,” especially in the context of PURPA \nQFs.80 The June Order failed to engage these factual circumstances and instead dismissed the \nIndustrials’ regulatory takings argument with “little more than a hand wave,”81 contending that the \nargument lacked finality.82 \nBut the December Order was clear that it did not just tentatively find, as in a Show Cause \nOrder, that the existing retail BTMG netting rules may be unjust and unreasonable. Instead, the \nDecember Order definitively found that the BTMG rules in PJM’s Tariff “are no longer just and \nreasonable because loads with BTMG are not fully accounted for in resource adequacy \nplanning…”83 The June Order ignores this final determination and instead focuses on the lack of \n“a final decision on the applicability and design of the revised retail BTMG netting rule,”84 such \nas the MW threshold for permitting continued netting by using BTMG. The United States Supreme \nCourt has recently explained that, in the context of a regulatory taking, “[t]he finality requirement \nis relatively modest” and requires a showing that the final governmental action or regulation \ninflicts actual, concrete injury on the property of the affected party.85 In the December Order, the \nCommission made a final determination that directly and materially affects the cost of electric \nservice and operations for existing entities using BTMG retail netting. In the June Order, the \nCommission made a final determination to implement a 50 MW threshold for netting and \n \n80 Id. at 33-34 (citing Penn Central Trans. v. New York City, 438 U.S. 104, 124 (1978)). \n81 Del. Division of Pub. Advocate v. FERC, 3 F.4th 461, 429 (D.C. Cir. 2021). \n82 June Order at P 148. \n83 December 2025 Order at P 2 (emphasis added).   \n84 June Order at P 148.  \n85 Pakdel v. City and County of San Francisco, 594 U.S. 474, 478 (2021) (citing Suitum v. Tahoe Regional Planning \nAgency, 520 U.S. 725, 739 (1997) and Williamson Cty. Regional Planning Commission v. Hamilton Bank of Johnson \nCity, 473 U.S. 172, 193 (1985))."},{"page":33,"startToken":11512,"endToken":11865,"text":"33 \n \n \nenvisioned implementing grandfathering provisions and exemptions for certain existing customer \nBTMG arrangements. Accordingly, the takings argument is now ripe and continues to apply to \nany customer BTMG arrangements that do not qualify based on the 50 MW Retail Threshold or \nthrough the implementation of grandfathering or an exemption through the PJM compliance \nprocess.86 \n \nAs the June Order does throughout, it cites back to Paragraph 186 in the December Order, \nwhich only made generic, non-specific findings that “circumstances have changed since the \nCommission approved PJM’s retail BTMG netting rules such that these rules are no longer just and \nreasonable.”87  The June Order asserts that it engaged only in rate-setting and enjoys discretion to \nbalance the interests of the respective parties.88 The June Order then proceeds to cite a non-binding \nconcurring opinion for the proposition that the Takings Clause is satisfied when there is a “striking \nof a reasonable balance of competing interests.”89 But the June Order does not demonstrate the \nCommission has reasonably balanced any competing interests, let alone defined any applicable \nparties and their interests. The Commission has not shown that it made detailed findings to select \na rate “from the broad zone of reasonableness” to show that its selected rate is not confiscatory.90 \nMoreover, the June Order did not engage the economic arguments presented by the Industrials. \nInstead, the June Order arbitrarily and capriciously reasserted its reliance on generic findings in \nParagraph 186 in the December Order, which may apply in the context of larger computational \n \n86 See June Order at P 86 (explaining that Industrials must demonstrate why their facilities would not present the cost \nshift, reliability, or resource adequacy concerns discussed in the December Order) (citing December Order at P 186). \n87 Id. at P 149 (citing December Order at P 186). \n88 Id. \n89 Id. at P 149 (quoting Jersey Cent. Power & Light Co. v. FERC, 810 F.2d 1168, 1191 (D.C. Cir. 1987) (en banc) \n(Starr, J. concurring)).  \n90 See id. at P 149 at n. 380 (quoting In re Permian Basin Area Rate Cases, 390 U.S. 747, 770 (1968))."},{"page":34,"startToken":11865,"endToken":12094,"text":"34 \n \n \nloads co-locating with generation resources, but have not been shown to apply in the context of \nonsite generation at manufacturing facilities.     \nEven if the Commission substantively denies the unlawful takings claim, then \nIndustrials/Amtrak request the Commission in its order on rehearing to clarify that the Commission \nwill not procedurally challenge the ripeness of an unlawful takings claim if and/or when a \nmanufacturer or customer with BTMG advances such a claim upon concluding that it will lose all \nor part of its property value as a direct result of the Commission’s final determination with respect \nto BTMG netting.  The Industrials/Amtrak ask the Commission to clarify and confirm when \nagency action is final so that injured retail customers may timely seek redress for harms inflicted \nby FERC’s orders.91   \n \n \n \n91 The Industrials/Amtrak note that a favorable resolution of the relief requested in this rehearing request that resolves \nthe first two specifications of error raised in this rehearing request, supra at pp. 9-31, regarding the 200 MW threshold \nand the PURPA issues, would obviate the need for continued litigation of the takings claim pending before the Third \nCircuit.  The Industrials/Amtrak would only possibly need to participate in further litigation to help protect and defend \nany Commission determination to implement a 200 MW threshold and grant this rehearing request concerning the \nPURPA and QF issues raised herein."},{"page":35,"startToken":12094,"endToken":12192,"text":"35 \n \n \nV. \nCONCLUSION \nWHEREFORE, the Industrials/Amtrak respectfully request that the Commission grant \nrehearing of the June Order for the reasons set forth herein.   \n \n \n \n \n \nRespectfully submitted, \n \nBy: \n/s/ Susan E. Bruce \n \n \n \nSusan E. Bruce \nKenneth R. Stark \nMatthew L. Garber \nMcNees Wallace & Nurick LLC  \n100 Pine Street \nHarrisburg, PA  17101 \nTel: 717-232-8000 \nE-mail: sbruce@mcneeslaw.com \nE-mail: kstark@mcneeslaw.com \nE-mail: mgarber@mcneeslaw.com \n \nCounsel to the PJM Industrial Customer Coalition \n(“PJMICC”) the Industrial Energy Consumers of \nAmerica (“IECA”), the American Forest and Paper \nAssociation (“AF&PA”), and the National Railroad \nPassenger Corporation (“Amtrak”) \n \nDated: July 20, 2026"},{"page":36,"startToken":12192,"endToken":12255,"text":"CERTIFICATE OF SERVICE \n \nI hereby certify that I have this day served via first-class mail, electronic transmission, or \nhand-delivery the foregoing upon each person designated on the official service list compiled by \nthe Secretary in this proceeding.  \nDated this 20th day of July, 2026. \n \n \n     /s/ Matthew L. Garber \n \n \nMatthew L. Garber \n100 Pine Street \nHarrisburg, PA  17101 \nTel: 717-232-8000 \nE-mail: mgarber@mcneeslaw.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":7,"startToken":0,"endToken":214},{"p":2,"at":7,"title":"I. INTRODUCTION","method":"printed heading","endPage":6,"endAt":186,"startToken":214,"endToken":1658},{"p":6,"at":186,"title":"II. BACKGROUND ON INDUSTRIALS AND AMTRAK","method":"printed heading","endPage":7,"endAt":1589,"startToken":1658,"endToken":2180},{"p":7,"at":1589,"title":"III. RESERVATION OF APPELLATE RIGHTS","method":"printed heading","endPage":9,"endAt":228,"startToken":2180,"endToken":2658},{"p":9,"at":228,"title":"IV. REQUEST FOR REHEARING","method":"printed heading","endPage":9,"endAt":256,"startToken":2658,"endToken":2662},{"p":9,"at":256,"title":"A. STATEMENT OF ISSUES/SPECIFICATION OF ERRORS","method":"printed heading","endPage":10,"endAt":1188,"startToken":2662,"endToken":3256},{"p":10,"at":1188,"title":"B. ARGUMENT","method":"printed heading","endPage":35,"endAt":8,"startToken":3256,"endToken":12095},{"p":35,"at":8,"title":"V. CONCLUSION","method":"printed heading","endPage":36,"endAt":0,"startToken":12095,"endToken":12192},{"p":36,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":36,"endAt":435,"startToken":12192,"endToken":12255}]}