{"document":{"slug":"rec-20260721-4000","title":"Pre-filed Statement of Judge Kelsey A. Bagot, Chair and Commissioner, Virginia State Corporation Commission, for the PJM Governance and Stakeholder Reforms…","issued":"2026-07-21","accession":"20260721-4000","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"VIRGINIA STATE CORPORATION COMMISSION","kind":"testimony","file":"sources/filings/text/20260721-4000_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260721-4000","tier":"record","sha256":"e542b6cc9227279d93d3868b1979209ecbd7d97545a7a0fa4ce3b7e07dd73f31","pages":3,"tokens":1267,"emptyPages":[],"textThemes":[]},"pages":[{"page":1,"startToken":0,"endToken":441,"text":"PJM Governance and Stakeholder Reforms \nDocket No. AD26-7-000 \n \n1 \n \nPre-Conference Comments of \nKelsey A. Bagot, Chair, Virginia State Corporation Commission \n \nThe issues facing regional power grids, including the one operated by PJM Interconnection, L.L.C. \n(“PJM”), have become more complicated in recent years.  As the PJM stakeholder process has failed \nto drive meaningful and timely outcomes for the most critical of issues facing PJM, trust among (and \nbetween) stakeholders has eroded.  \nThere are three overarching concerns that challenge the ongoing efficacy of PJM as an independent \nregional transmission operator as compared to other RTOs/ISOs: \n(i) \nthe PJM Board is not sufficiently independent, undermining stakeholder confidence in the \nimpartiality and durability of Board decision-making;  \n(ii) \nthe PJM stakeholder process is prone to delay and gridlock, impeding PJM’s ability to \ntake timely action or requiring PJM to pursue less-optimal solutions; and,  \n(iii) \nState representatives feel their concerns are neither acknowledged nor sufficiently \naddressed by voting Members or PJM, resulting in states using blunt measures to force \noutcomes regardless of how disruptive they may be to the markets PJM operations or to \nachieving resource adequacy. \nAddressing these challenges requires solutions that enable PJM to engage in independent, \ncomprehensive decision-making, with the benefit of all stakeholder input, and without creating more \ncomplexity or gridlock.  Reforms should be targeted, purposeful, and – where appropriate – iterative \nor incremental.  These objectives can be achieved by consideration of the following reforms, which \nfall within two broad, and interrelated, categories: (1) establishing greater PJM Board independence \nand (2) defining calibrated, appropriate roles for the States.   \n1. \nEnsuring Board Independence  \nStates are not currently voting Members of PJM – an intentional decision made at the time of PJM’s \ncreation.  However, the input of state regulators, like that of voting Members and all other \nstakeholders, serves an essential purpose: educating PJM and the PJM Board on the operational, \nfinancial, legal, and consumer trade-offs of action contemplated by the Board.  While Members \nnaturally advance solutions that protect their interests, state elected officials and regulatory \ncommissions are directly accountable to the retail consumers they are mandated to protect and are \nuniquely positioned to understand the challenges facing their particular jurisdictions.  Moreover, \nactions taken by PJM can be undermined or made less effective if states are unclear, unable, or \nunwilling to fully enable PJM’s intended outcomes.  \nThe appropriate system of governance would balance PJM’s access to the knowledge, experience, \nand innovation of all its stakeholders, including the States, on an advisory basis, against the authority \nof the Board to take action, independent from undue influence of any of its stakeholders. To get \ncloser to this balance, given the present challenges, the following recommendations merit \nconsideration:"},{"page":2,"startToken":441,"endToken":955,"text":"PJM Governance and Stakeholder Reforms \nDocket No. AD26-7-000 \n \n2 \n \n• \nSection 205 Filing Rights: Section 205 filing authority (with certain limited exceptions, e.g., \ntransmission rate-setting or cost allocation) should rest firmly with the PJM Board. The \nBoard’s decision-making should be advised by outcomes of the stakeholder process but \nshould not be constrained by it.  This will prevent procedural gridlock when decisive action is \nrequired and allow the Board to pursue the most optimal solutions without unnecessary legal \nhurdles.  Currently, the Board is often unable to move forward with critical reforms because \none or more elements require changes to the Operating Agreement, requiring a degree of \nMembers Committee support that is not always achievable.  Allowing the Board to tailor \nreforms, considering the guidance received from the stakeholder process but not beholden to \nspecified stakeholder proposals, would enable the Board to act comprehensively and \nindependently where it is now prevented from doing so.  \n \n• \nBoard Terms & Candidate Pool: Board members’ terms should be extended so the Board can \nengage in long(er)-term decision-making and benefit from institutional expertise and \nexperience gained over time.  At the same time, prohibitions on serving consecutive terms \nshould be considered to allow the Board to take independent action without regard toward \npotential renomination.  Additionally, at least one or more candidates with regulatory \nexperience, preferably at the retail level, should be given preference to ensure that the Board \nand the actions it takes benefit from the perspective of an individual familiar with striking a \nbalance that fairly accounts for the interests of the retail end-user.  Finally, preference should \nbe given to candidates with professional experience in the PJM region.  \n \n• \nNominating Committee: State interests should be adequately represented on the Board \nNominating Committee.  Specifically, the States should have the ability to appoint three new \nNominating Committee members.  For a Board candidate to move forward, the candidate \nshould be supported by at least two of the three new state-appointed members.  \n \n2. \nCrafting Appropriate Roles for State Leadership and Regulators  \nReforms must recognize the distinct roles and perspectives of state elected officials (e.g., Governors) \nversus utility commissions (e.g., PUCs/OPSI).   \n• \nState Elected Officials (Governors): Governors hold a distinct political mandate. Their input \nwould be well leveraged, for example, through holding/appointing seats on the Nominating \nCommittee and/or selecting state representation on the Board.  The Governors’ \nrepresentatives should also have a seat on the Strategic Steering Committee discussed below.  \n \n• \nState Utility Commissions & OPSI:  The States have long advocated for “jump-ball” 205 \nfiling rights over resource adequacy and transmission cost allocation issues at PJM.  Under \nthe current regime, where the PJM Board lacks sufficient independence or authority to take \ntimely action, Section 205 filing rights would enable OPSI to force action when state \nperspectives are not reflected in PJM proposals or when the PJM stakeholder process has \nstagnated.  To the extent concerns about Board independence and authority are adequately \naddressed, Section 205 filing right for OPSI may no longer be desirable or necessary. (This \nposition differs from OPSI’s position, which views increased PJM Board independence and \nOPSI Section 205 filing rights as complementary reforms.)"},{"page":3,"startToken":955,"endToken":1267,"text":"PJM Governance and Stakeholder Reforms \nDocket No. AD26-7-000 \n \n3 \n \nThat said, the durability and efficacy of many PJM outcomes require meaningful \nconsideration of state perspectives.  As a result, the following additional reforms should be \nconsidered:  \n- \nStrategic Steering Committee: OPSI (and potentially the Governors) should meet \nannually with the Board and other Members as the Strategic Steering Committee to \ncollaborate on developing and approving PJM’s annual strategic plan. OPSI’s voice in \nthis process should have equal weight as other Member representatives.  At present, the \nplan is developed without direct participation by OPSI. \n \n- \nPre-205 Filing Consultation Requirement: To the extent such a process would not result \nin undue delays, PJM and the PJM Transmission Owners should be required to engage in \na pre-filing consultation with OPSI to solicit OPSI feedback and collaboration.  This \nprocess should (i) provide adequate time for OPSI to review and provide meaningful \nfeedback on any proposed filing, and (ii) require the filing entity (PJM/TOs) to explain in \nthe body of the filing why it rejected any recommendations made by OPSI in the \nconsultation process.  To hold OPSI accountable, any such process should be clearly \ndefined and time-limited. \n- \nNon-Tariff Process Enhancements: Today, PJM is already enabled to improve state \nengagement through efforts that require no 205 filing at FERC to implement.  For \nexample, PJM can serve as a technical resource to the States in working through \nproposed reforms.  State engagement processes should be standardized and more clearly \ndefined to allow PJM to (i) help enable consensus among the States, where possible, (ii) \nelucidate areas where continued refinement of reforms might result in additional \ncooperative action among the States, and/or (iii) highlight where State policies create \nimpediments to cooperative action.  Under new leadership, PJM has already \ndemonstrated its increased commitment in working with OPSI and other state \nrepresentatives.  Continued improvements should not be held up awaiting other potential \ngovernance reforms."}],"sections":[{"p":1,"at":0,"title":"Pages 1 to 3","method":"page range","endPage":3,"endAt":2145,"startToken":0,"endToken":1267}]}