{"document":{"slug":"rec-20260721-5049","title":"Pre-Conference Comments of the Organization of PJM States, Inc. for the PJM Governance and Stakeholder Reforms Technical Conference","issued":"2026-07-21","accession":"20260721-5049","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"Organization of PJM States, Inc.","kind":"comments","file":"sources/filings/text/20260721-5049_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260721-5049","tier":"record","sha256":"4ef965e94646cda24db04f1ad39ec63fb1ead339720becdb243e89035fa4427b","pages":21,"tokens":7799,"emptyPages":[],"textThemes":["adequacy","cost","retail"]},"pages":[{"page":1,"startToken":0,"endToken":293,"text":"1 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Governance and Stakeholder Reforms  \n) \n \nDocket No. AD26-7-000 \n \nPRE-CONFERENCE COMMENTS OF THE  \nORGANIZATION OF PJM STATES, INC. \n \nPJM’s governance structure and stakeholder process were developed for a different era. \nRetail regulators are charged with ensuring adequate electric service at reasonable cost, but they \nare increasingly unable to fulfill that responsibility as regional rules developed through PJM’s \nstakeholder process and approved by FERC determine a growing share of the costs and reliability \noutcomes experienced by retail customers. Without a formal means of placing state-developed \nproposals before FERC in a form the Commission can accept, retail regulators remain accountable \nfor outcomes they have little power to formally shape. The Organization of PJM States, Inc. \n(“OPSI”) therefore appreciates the Commission convening this technical conference.1 OPSI offers \ntargeted, implementable reforms to improve PJM’s independence, decision-making, and \naccountability. \nFirst, PJM should have additional independence to propose changes to the governing \ndocuments containing the rules and processes it administers. Second, should OPSI agree on \nresource adequacy or transmission cost allocation reforms, PJM or the Transmission Owners \n(“TOs”) should provide that solution to FERC in a way that FERC can accept it. OPSI as an \norganization was created “to promote and protect the public interest in the provision of reliable \nand reasonably priced electric service within the PJM Control Area,”2 and its formal role within \n \n1 These comments were unanimously approved by the OPSI Board on July 20, 2026. \n2 PJM Interconnection, L.L.C. and the Organization of PJM States, Inc., Memorandum of Understanding Between the \nPJM Interconnection and the Organization of PJM States, Inc. (June 1, 2005), available at: https://opsi.us/wp-\ncontent/uploads/2020/02/OPSI_PJM_MOU_executed_June_8_2005-1-1.pdf."},{"page":2,"startToken":293,"endToken":589,"text":"2 \nPJM’s governance framework should be commensurate with that responsibility. At best, the PJM \nstakeholder process and the independent judgment of the PJM Board of Managers may \napproximate the public interest, but neither is a direct replacement for the judgment of those who \nare statutorily obligated to promote the public interest and are ultimately responsible for retail \ncustomers’ bills. Retail regulators need a more formal means of presenting their proposals to the \nCommission on a level playing field with PJM and the TOs. Third, PJM’s Tariff should formally \nrecognize the PJM Governors’ Collaborative and vest it with certain rights and responsibilities \nwithin PJM’s governance framework and stakeholder process. Additionally, PJM should establish \na process through which the Governors’ Collaborative may advance state-identified issues through \nthe stakeholder process over the objection of members and a way for OPSI and the PJM Board to \njointly prioritize work more effectively.  \nAs discussed below, OPSI believes the mutually reinforcing effect of these reforms, and \nothers discussed below, will improve both the speed with which PJM can bring needed changes to \nFERC in the near-term and the quality of proposals that come before the Commission over the \nlong-term. \nI. \nCOMMENTS \nIn May 2005, OPSI incorporated with the express purpose of serving as the PJM Regional \nState Committee, maintaining an organization of the states and providing a means for the states to \nact collaboratively with PJM when doing so would be in the public interest.3 OPSI entered into a \nMemorandum of Understanding with PJM on June 1, 2005 to facilitate communication and take \ncooperative action “to promote and protect the public interest in the provision of reliable and \n \n3 OPSI, State of Delaware Certificate of Incorporation (May 5, 2005) available at: https://opsi.us/wp-\ncontent/uploads/2018/08/OPSI-Articles-of-Incorporation.pdf."},{"page":3,"startToken":589,"endToken":910,"text":"3 \nreasonably priced electric service within the PJM Control Area.”4 In October 2005, PJM filed an \namendment to the PJM Open Access Transmission Tariff (“Tariff”) to provide a mechanism for \nOPSI’s funding and described OPSI as a “group formed to coordinate state involvement in affairs \nrelated to PJM.”5 PJM wrote “PJM Members should welcome the formation of an RSC that is \nconceived with the limited and constructive objectives of coordinating state policies and serving \nas a conduit for information between the states and the RTO.”6  \nThe Commission accepted OPSI’s funding mechanism on December 20, 2005, noting that \n“[T]he Commission has recognized state authority affecting such matters as transmission and \ncapacity planning is crucial to the development of efficient energy markets” and that “OPSI has \nmuch to offer in formulating policies for the PJM region.”7 FERC wrote, “The formation of OPSI \nwill help PJM to regularize its processes of interacting with the states to achieve the objectives of \nthe RTO…,” and OPSI “has the potential to bring public policy perspectives to PJM’s deliberations \non issues such as the adequacy of resources to meet projected growth levels in the region.”8 \nFor more than twenty years, OPSI has played a crucial role in important conversations at \nboth PJM and before the Commission by:  \n- \npromoting settlement negotiations establishing an external, independent Market \nMonitoring Unit in PJM in 2007 and 2008,9  \n \n4 PJM Interconnection, L.L.C. and the Organization of PJM States, Inc., Memorandum of Understanding Between the \nPJM Interconnection and the Organization of PJM States, Inc. (June 1, 2005), available at: https://opsi.us/wp-\ncontent/uploads/2020/02/OPSI_PJM_MOU_executed_June_8_2005-1-1.pdf. \n5 PJM Interconnection, L.L.C., Transmittal Letter, Docket No. ER06-78-000 (October 27, 2005). \n6 Id. at 3. \n7 113 FERC ¶ 61,292 (2005) at P 5 and 32. \n8 Id. at P 33. \n9 See FERC Docket No. EL07-58."},{"page":4,"startToken":910,"endToken":1379,"text":"4 \n- \nproviding constructive comments on transmission cost management10 and in Order No. \n100011 in the early 2010s, and Order No. 1920 transmission cost allocation \nconversations, in the 2020s,12  \n- \nproviding timely13 and persistent14 advocacy for public interest solutions in response to \nevolving dynamics within the PJM resource adequacy construct, in 2024, on issues like \nReliability Must Run procedures, Must Offer Requirements for Capacity Resources, \nand capacity market price formation that resulted in quick solutions the Commission \naccepted,15 and \n- \nadvocating for public interest solutions on topics as technical as the multi-schedule \nselection process in the Day-Ahead Energy Market16 among countless others over the \npast 20 years.17 \n \nIn addition to formal communication both within the PJM Stakeholder Process and before \nthe Commission, OPSI meets with the PJM Board of Managers three times each year in person \nand with PJM’s CEO and Board Committees as necessary. OPSI has found this arrangement to be \nvaluable but offers the following comments to further enhance PJM’s ability to carry out its core \nfunctions and enhance the ability of the states to offer the public interest perspective both within \nthe PJM Stakeholder Process and before the Commission. \n \n \n \n10 OPSI, Comments of the Organization of PJM States, Inc., Docket No. AD22-8-000 (Mar. 23, 2023). \n11 See OPSI, OPSI Resolution OPSI-2012-1, available at: https://opsi.us/wp-content/uploads/2018/08/OPSI-2012-\n1.pdf, OPSI, Letter to the PJM Board of Managers Re: State Agreement Approach (June 12, 2012), available at: \nhttps://opsi.us/wp-content/uploads/2018/08/State_Agreement_1_letter.pdf; OPSI, Motion to Intervene and Comments \nof the Organization of PJM States, Docket No. ER13-198-000 (Dec. 10, 2012), and OPSI, Letter Re: Docket Nos. \nER14-2864-000 and ER14-2867-000 available at: https://opsi.us/wp-content/uploads/2025/05/OPSI-Multi-value-\nresponse.pdf.  \n12 Building for the Future Through Electric Regional Transmission Planning and Cost Allocation, Unopposed Motion \nfor Extension of Time and Request for Expedited Consideration of PARSEC and PJM Transmission Owners, Docket \nNo. RM21-17 (June 4, 2026). \n13 OPSI, Letter to the PJM Board of Managers (Sept. 27, 2024) available at: https://opsi.us/wp-\ncontent/uploads/2024/09/OPSI-BRA-RESPONSE-LETTER-2024.09.27.pdf. \n14 OPSI Letter to the PJM Board of Managers (November 21, 2024) available at: https://opsi.us/wp-\ncontent/uploads/2024/11/OPSI-RPM-Proposal-Letter-2024.11.21.pdf; OPSI, Letter to the PJM Board of Managers \n(Dec. 17, 2024) available at: https://opsi.us/wp-content/uploads/2025/01/OPSI-LETTER-Capacity-Market-Must-\nOffer-Exemption.pdf. \n15 PJM Interconnection, L.L.C., 190 FERC ¶ 61,088 (2025), PJM Interconnection, L.L.C., 190 FERC ¶ 61,117 (2025). \n16 OPSI, Protest of the Organization of PJM States, Inc. (Mar. 22, 2024), available at https://opsi.us/wp-\ncontent/uploads/2024/05/ER24-1387-Multi-Schedule-Selection-Protest-2024.03.22.pdf and 187 FERC ¶ 61,051. \n17 OPSI, Resolutions and Filings available at: https://opsi.us/resolutions-and-filings/."},{"page":5,"startToken":1379,"endToken":1713,"text":"5 \nPanel 1 - Q4. How does the division of Federal Power Act section 205 filing \nrights among PJM, Transmission Owners, and the Members Committee affect \nPJM’s ability to act effectively and quickly, when warranted, to address \noperational and market needs? \n \nPanel 1 - Q5. To what extent do provisions in PJM’s Operating Agreement, \nTransmission Owner Agreement, Open Access Transmission Tariff, \nReliability Assurance Agreement, or Manuals impede timely decision-making \nby PJM? \n \n \nMost saliently, PJM has no independent, unilateral authority to amend the PJM Operating \nAgreement (“OA”). Instead, PJM must obtain the approval of the PJM Members Committee \n(“MC”) before it may propose amendments to the OA under FPA Section 205. The OA contains \nmany provisions critical to PJM’s functioning, including its transmission planning rules, energy \nmarket rules, and rules governing PJM’s purpose and authority. Additionally, the MC, itself, has \nthe power to amend the OA pursuant to a 2/3 sector-weighted vote of the membership,18 and PJM \nis required to file those agreements for FERC’s consideration under FPA 205.19 Even when the \ntwo-thirds sector-weighted vote is merely advisory, setting such a high threshold for consensus \noften transforms stakeholder voting into an exercise in veto power rather than a process that \npromotes collaboration.  \nAccordingly, if PJM believes it is in the best interests of the organization to modify any \nprovision of the OA, it must receive 2/3 support of the members to even bring that proposal before \nthe Commission under Section 205 of the FPA. This impedes PJM’s ability to timely address many \ncritical issues, and forecloses valuable conversations between states, stakeholders, and the PJM \nBoard, recognizing that even if they agree, the Board is powerless to unilaterally propose to FERC \nmodifications to the OA. This inability for the PJM Board to propose changes not only delays or \nprevents progress on issues related to the OA but has the potential to negatively affect other aspects \n \n18 PJM, Operating Agreement at §§ 8.4, 8.8.ii and 18.6. \n19 Id. at §10.4.xiii."},{"page":6,"startToken":1713,"endToken":2065,"text":"6 \nof PJM’s processes. For example, if PJM identifies a need to revise its transmission-planning or \nenergy-market rules to promote resource adequacy but lacks a viable path to advance those \nchanges, it may be forced to attempt to reform rules within its control. That approach may produce \na less optimal and less targeted solution than addressing the transmission or energy-market issue \ndirectly. \nAs an example, PJM attempted to relocate its regional transmission planning rules from \nthe OA to the Tariff in 2024, but because the Members did not support PJM’s proposal,20 PJM had \nto file an FPA Section 206 complaint, which the Commission ultimately rejected, showing the \ndifficulty PJM has in asserting its independence over some of the most important rules it \nadministers.21 \nRecommendation 1: PJM should have the authority to independently and \nunilaterally propose changes to the OA under Section 205 of the FPA. PJM’s \ninability to independently file changes to the OA is a relic of PJM’s formation as \nan Independent System Operator (“ISO”), and in order to provide PJM with the \nindependence and agency it needs, the Commission should correct this. \n \nWhen PJM’s founding members made their initial filing requesting PJM be recognized as \nan ISO, they proposed to put many important provisions in the PJM Tariff. FERC found that \nlocating many of the foundational PJM ISO rules in the Tariff would have prevented PJM from \nbeing truly independent since a single sector had the ability to modify the Tariff at the time.22 \nTherefore, FERC rejected PJM’s initial ISO filing.23  \nUpon refiling, the only other document available to house the rules PJM needed to \nadminister to become an ISO was the OA. The PJM Supporting Companies wrote that placing the \n \n20 PJM, Supplemental Voting Results, PJM Members Committee (May 6, 2024) available at: https://www.pjm.com/-\n/media/DotCom/committees-groups/committees/mc/2024/20240506-annual/mc-voting-results---item-08---proposed-\noa-and-tariff-revisions-effectuating-the-transfer-of-the-regional-transmission-expansion-planning-protocol.pdf. \n21 PJM Interconnection, L.L.C., 189 FERC ¶ 61,181 (2024) and PJM Interconnection, L.L.C., 192 FERC ¶ 61,051 \n(2025). \n22 Atlantic City et. al., 77 FERC ¶ 61,148 at p. 37. \n23 Id."},{"page":7,"startToken":2065,"endToken":2502,"text":"7 \ngovernance and other rules in the OA and only allowing PJM to file FPA 205 filings to amend \nthem pursuant to a 2/3 sector weighted vote provided “a system of checks and balances that will \nassure non-discriminatory, open access transmission service throughout the PJM control area.”24 \nFERC wrote that this arrangement satisfied Order No. 888’s Independence Principle.25  \nWhile this alternative was certainly better than placing these rules in a document that could \nbe amended with the approval of only a single sector, it did not equate to the level of true \nindependence over the rules as exists in other RTOs. Even through the development and \nimplementation of FERC Order No. 2000, PJM remained a membership-based organization first \nand foremost, as it is today, and PJM and FERC balanced those interests as they considered PJM’s \ngovernance framework.26  \nOPSI raises this not to diminish the value of eliciting and understanding the important \nperspectives of PJM’s Members. To the contrary, conversations within the PJM stakeholder \nprocess are extremely beneficial in identifying solutions to many of the region’s most pressing \nchallenges, especially when the process reflects consensus of stakeholders and/or efficiently \narticulates problems and potential solutions. However, for example, in recent stakeholder \nprocesses on the rapid integration of new large loads, PJM’s stakeholder process has struggled to \n \n24 Atlantic City Electric Company et al., Filing of the PJM Supporting Companies, Docket No. EC97-38-000 and \nER97-3189-000 p. 3 (June 2, 1997).  \n25 Atlantic City et. al., 81 FERC 61,257 at p. 63 (1997) (“The Commission approves the ISO governance structure \nfiled by Supporting Companies. The PJM Board has the broad technical skills that are necessary to manage the ISO \nand it possesses the requisite independence from the transmission owners that the Commission previously found to be \nlacking in Supporting Companies’ prior restructuring application. ISO Principle No. 1 provides that a governance \nstructure should fairly represent all users of the transmission system. We believe that the Members Committee \nestablished by the PJM Operating Agreement fairly represents the broadest possible users of the ISO… Therefore, no \nmodification is required to satisfy ISO Principle No. 1.”). \n26 PJM Interconnection L.L.C., Order No. 2000 Compliance Filing at p. 15 (Oct. 11, 2000) (“While the PJM members \n(i.e., the market participants) have certain powers, those powers have been carefully limited and balanced. The PJM \nMembers Committee may elect the PJM Board from a slate of candidates selected by an independent consultant; it \nmay form additional advisory committees; it may amend and terminate the PJM Operating Agreement (subject to \nCommission approval); and it may advise the PJM Board.”)."},{"page":8,"startToken":2502,"endToken":2845,"text":"8 \nidentify consensus.27 Further, far too often the PJM stakeholder process becomes a vehicle for \nrepetition and delay rather than producing focused feedback that can inform PJM Board decisions. \nEven if the stakeholder process functions perfectly, recognizing that none of the over 1,000 voting \nmembers at PJM are tasked with defending and promoting the public interest, it is unreasonable to \nbelieve that this process will consistently produce proposals that do just that, as will be discussed \nin the next section. \nPanel 1 - Q3. What governance reforms would best improve accountability \nand responsiveness? \n \nPanel 1 - Q6. Recognizing regional differences, are there lessons from other \nregional transmission organization/independent system operator (RTO/ISO) \ngovernance structures that PJM could reasonably adopt to improve its \nresponsiveness to the region’s operational and market challenges? \n \nAs discussed in Recommendation 1, giving PJM independence over the OA would bring \nPJM’s governance process in line with the advisory nature of the membership in other RTOs and \nwould be a step in the right direction, but it is not the only needed change.28 In addition to PJM \nindependence, one notable model allows either RTO Members or the states to compel filings under \nSection 205 of the FPA. In the ISO-NE context this is called a “jump-ball” filing.29 Importantly, \nthough, ISO-NE retains independence to file its own proposal. Similarly, and more broadly, the \nSouthwest Power Pool-Regional State Committee (“SPP-RSC”) has the authority to compel SPP \nto make filings on resource adequacy rules pursuant to their authority to “determine the approach \nfor resource adequacy across the entire region.”30 It is clear that RTOs can agree to a condition to \n \n27 See PJM, Special MC – Critical Issues Fast Path, Large Load Additions (Nov. 19, 2025). See also PJM, Special MC \n(June 30, 2026). \n28 See Exeter Associates, Governance Structures and Practices in the FERC-Jurisdictional ISOs/RTOs (Feb. 2021), \navailable at: https://nescoe.com/wp-content/uploads/2021/02/ISO-\nRTOGovernanceStructureandPractices_19Feb2021.pdf. \n29 Id. at p. 3-10 citing ISO-NE, Participants Agreement, Section 11.1.5. \n30 SPP Bylaws, Section 7.2."},{"page":9,"startToken":2845,"endToken":3142,"text":"9 \nmake filings on behalf of other entities using their own authority to make filings under FPA Section \n205.  \nRecommendation 2A: Accordingly, OPSI recommends that PJM agree to, and \nmake a filing to effectuate, a requirement that PJM make FPA Section 205 filings \non OPSI’s behalf, when OPSI agrees to changes to the RAA or sections of the Tariff \nPJM controls. \n \nRetail electric regulators in the PJM region are directly accountable to retail customers and \nare required to ensure resource adequacy at the lowest cost. However, many important resource \nadequacy rules are addressed in PJM’s stakeholder process and before the Commission, leaving \ntraditional economic regulators of the electric industry without a formal or meaningful avenue to \nadvance their own solutions before the federal regulator responsible for approving those very same \nregional rules. This leaves regulators with little control over the regional processes that ultimately \ndetermine the costs assigned to those customers and places them in an untenable position. \nPJM’s CEO has indicated that many important decisions about the value of reliability and \nfunctioning of PJM’s markets in maintaining resource adequacy “belong to the people and \ninstitutions with democratic accountability for their consequences.”31 OPSI agrees. States are the \ntraditional economic regulators responsible for resource adequacy. They should not lose any \nformal role merely because they rely on interstate infrastructure to obtain the economic and \nreliability benefits of regional coordination or are impacted by rules and regulations of a FERC \napproved private entity affecting their authority over planning for their own vertically integrated \nsupply choices. OPSI therefore believes retail regulators should have an appropriate role in \ndetermining the region’s approach to resource adequacy. \n \n31 \nDavid \nE. \nMills, \nLetter \nto \nStakeholders \n(May \n6, \n2026) \navailable \nat: \nhttps://www.pjm.com/-\n/media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-through-market-\ndesign.pdf."},{"page":10,"startToken":3142,"endToken":3574,"text":"10 \nMost directly, PJM has unilateral authority over the Reliability Assurance Agreement \n(“RAA”) and most of the Tariff.32 Attachment DD to the Tariff contains rules governing PJM’s \nReliability Pricing Model (“RPM”), but there are also critically important resource adequacy rules \nlocated in PJM’s RAA on the Fixed Resource Requirement Alternative,33 PJM’s Forecast Pool \nRequirement,34 and rules related to the capability and deliverability of generation,35 among others. \nAs will certainly be noted at the technical conference, all states in SPP are vertically \nintegrated, whereas many states in PJM are restructured. OPSI does not see the fact that many \nretail jurisdictions in PJM are restructured as fundamentally diminishing their interest in, or the \nprudence of, granting PJM states a more formal role in determining the resource adequacy \napproach in the region. To the contrary, it underscores the important role states should have in \nPJM – because much of PJM relies on the market for resource adequacy, it is more important than \never that states have a formal role in shaping those market rules. Moreover, states that remain fully \nregulated but whose vertically integrated utilities have been allowed to join PJM are subject to \nPJM's directives regarding the timing, amount and location of their capacity choices.  Therefore, \nthose states have an interest in a more formal role in determining the resource adequacy approach \nin the region. \nA formal state role would improve the quality of PJM’s decision-making by ensuring that \nregional proposals reflect the statutory responsibilities and practical concerns of retail regulators. \n \n32 PJM Tariff, Section 9.2 (a) (“(a) PJM shall have the exclusive and unilateral right to file pursuant to Section 205 of \nthe Federal Power Act and the FERC's rules and regulations thereunder to make changes in or relating to the terms \nand conditions of the PJM Tariff (including but not limited to provisions relating to creditworthiness, billing, and \ndefaults) as well as all charges for recovery of PJM costs.  PJM shall not have any Section 205 filing rights with \nrespect to the subject matters described in the first sentence of Section 9.1(a) of this Tariff.  PJM shall not have \nany Section 205 filing rights with respect to the provisions of the PJM Tariff listed in Section 9.1(d) and (e).”). PJM \nRAA, Section 16.4 (“This Agreement may be amended only by action of the PJM Board…The PJM Office of the \nInterconnection shall file with FERC any amendment to this Agreement approved by the PJM Board.”). \n33 RAA Schedule 8.1. \n34 Id. at Schedule 4 and 4.1. \n35 Id. at Schedule 10."},{"page":11,"startToken":3574,"endToken":4038,"text":"11 \nMore structured state participation earlier in PJM processes would also promote more substantive \ndialogue regarding the assumptions, alternatives, and consumer impacts underlying proposed \nreforms. Indeed, SPP described a real-world example of how increased formal filing rights for \nretail regulators can lead to more constructive conversations with the RTO, even outside a formal \nfiling process.36 Further, this should lead to more robust analysis, including the development and \nevaluation of additional scenarios that may not otherwise receive meaningful consideration. It \nwould also promote greater transparency into PJM’s reasoning and allow states to assess more \neffectively how regional resource adequacy decisions will affect retail customers.  \nEqually, and importantly, as recognized in FERC Orders Nos. 1920, 1920-A, and 1920-\nB37, state involvement in planning and transmission cost allocation is likely to promote more \nefficient outcomes for consumers. OPSI appreciates the role that the Commission provided states \nin Order No. 1920-A and has been engaging with the PJM Transmission Owners to develop a cost \nallocation framework for PJM’s long-term planning practices. OPSI believes that it would be \nequally beneficial to apply the lessons learned through this process to PJM’s other regional \ntransmission planning and cost allocation frameworks. \n \n36 Multi-State Technical Conference, Summit on the State of PJM Interconnection, RTO Governance: Lessons \nLearned from Other Regions, September 2025 PJM Governors Meeting 20:51–21:12 (Sept. 22, 2025) (remarks of \nLeonard \nTao, \nDirector \nof \nFERC \nPolicy, \nSouthwest \nPower \nPool), \navailable \nat \nhttps://mcusercontent.com/16acb34ffcb6673b17aa36bad/files/c0a1c8ac-22b0-54c3-68fb-\nebeb17c29b38/Transcript.pdf (“The biggest impact on that is not the fact that we file, because we very rarely do. It’s \nhow states then show up in the cost allocation conversation and increasingly the planning conversation as well. … It’s \none of these things where the legal provision then unlocks a different—it’s a full shift in how the process operates on \nthe ground that, in some ways, is detached from the legal process or the actual filing rights. But because that’s there \nin the background, the conversation is just fundamentally different.”). \n37 Building for the Future Through Elec. Reg’l Transmission Planning & Cost Allocation, Order No. 1920, 187 FERC \n¶ 61,068, at P 1364 (2024) (Transmission Facilities “selected through Long-Term Regional Transmission Planning \ncould help increase stakeholder—and state—support for those facilities, which, in turn, may increase the likelihood \nthat those facilities are sited and ultimately developed with fewer costly delays and better ensure just and reasonable \nCommission-jurisdictional rates.”); Building for the Future Through Elec. Reg’l Transmission Planning & Cost \nAllocation, Order No. 1920-A, 189 FERC ¶ 61,126, at P 3 (2024) (“[M]eaningful engagement with states is critical to \nthe success of the Long-Term Regional Transmission Planning reforms established in Order No. 1920 . . . [These \nmodifications] will increase the likelihood that Long-Term Regional Transmission Planning results in efficient and \ncost-effective transmission investment.”)."},{"page":12,"startToken":4038,"endToken":4578,"text":"12 \nRecommendation 2B: The PJM Transmission Owners should agree to, and make \na filing to effectuate, a requirement that the TOs make FPA Section 205 filings on \nOPSI’s behalf when OPSI comes to an agreement on cost allocation methods for \nregional transmission projects. \n \nAs stated above, retail regulators are closest to the retail customers whose bills are greatly \nimpacted by the transmission cost-allocation methodologies used in the PJM region. Nothing in \nRecommendations 2A, 2B, or 2C is intended to infringe upon or weaken the FPA Section 205 \nrights of either PJM or the Transmission Owners, or to prevent them from utilizing those rights to \nthe fullest extent. That is not what SPP proposed in its Order No. 2000 compliance filing, and it is \nnot what OPSI is asking for here. The context and history in PJM is different than SPP, and \ncontrolling precedent in Atlantic City v. FERC prevents FERC from involuntarily transferring the \nPJM TOs’ FPA Section 205 filing rights to PJM pursuant to its creation as an RTO, writing that \nby doing this, “FERC thereby eliminated the very thing that the statute was designed to protect — \nthe ability of the utility owner to ‘set the rates it will charge prospective customers, and change \nthem at will’”.38 However, the D.C. Circuit wrote in the very next line in Atlantic City, “Of course, \nutilities may choose to voluntarily give up, by contract, some of their rate-filing freedom under \nsection 205.”39 To be clear, OPSI is not asking that they give up any40 of their filing authority \n \n38 Atlantic City, 295 F.3d at 10 (quoting City of Cleveland v. FPC, 525 F.2d 845, 855 (D.C. Cir. 1976)). \n39 Id. \n40 Atlantic City Electric Co. v. FERC, 295 F.3d 1, 6, 10–11 (D.C. Cir. 2002) (“Rather than permit unilateral filings by \nthe individual utilities as provided in section 205, FERC found that PJM-OI had the ‘right and responsibility to \nparticipate in the development of any such revisions and to intervene in any proceedings pertaining to such filings.’ \nThus as FERC would have it, only the ISO could propose changes in rate design. . . . FERC cannot point to any statute \ngiving it authority for its unprecedented decision to require the utility petitioners to cede rights expressly given to \nthem in section 205 of the Federal Power Act. . . . Yet here, FERC purports to deny the utility petitioners any ability \nto initiate rate design changes with respect to services provided with their own assets. . . . FERC thereby eliminated \nthe very thing that the statute was designed to protect—the ability of the utility owner to ‘set the rates it will charge \nprospective customers, and change them at will,’ subject to review by the Commission. . . . In sum, FERC lacks the \nauthority to require the petitioners to cede their right under section 205 of the Act to file changes in rate design with \nthe Commission.” (emphasis in original) (quoting City of Cleveland v. FPC, 525 F.2d 845, 855 (D.C. Cir. 1976))). \nOPSI notes that Atlantic City addressed FERC’s attempt to require the transmission owners to fully surrender their \nSection 205 filing rights to PJM and to deny the transmission owners any ability to initiate rate-design changes. OPSI \n(continued)"},{"page":13,"startToken":4578,"endToken":4947,"text":"13 \nunder FPA Section 205. Instead, OPSI is simply requesting that they add a condition to these \nrights, voluntarily, to make a filing on behalf of the states in the same manner that \ntransmission providers in SPP, MISO, and ISO-NE have done.  \nThat collaboration will enable PJM to reach public-interest outcomes more often. \nCooperation among PJM, the TOs, and OPSI means PJM will be better positioned not only to plan \ntransmission, but also to support the development of needed infrastructure, which ultimately \nsupports PJM’s ability to implement efficient markets. To develop generation and transmission \ninfrastructure efficiently, there must be state buy-in and fair prices for retail customers. Providing \nan opportunity for revisions to regional transmission cost-allocation methods when supported by \nretail regulators in the PJM region will give them much-needed accountability and the ability to \nplace public-interest proposals before the Commission, with the Commission retaining ultimate \nauthority to determine whether cost-allocation proposals are just and reasonable. \nIncreasing OPSI’s ability to advance FPA Section 205 filings on these important issues \nwill promote more efficient transmission development and more durable solutions more quickly, \nwhile reducing the likelihood of protracted litigation over cost allocation by giving states an earlier \nand more meaningful role in the process. OPSI recognizes the long legal history associated with \nthe transfer and exercise of FPA 205 filing rights. In rejecting the original SPP-RSC proposal, but \nrecognizing a proposal from Arkansas and Missouri Commissions that proposed various subjects \non which SPP should make a filing under FPA Section 205 on behalf of the states,41 the \n \nproposes only that the Transmission Owners agree to apply a condition to their Section 205 filing rights that would \nnot affect their ability to make Section 205 filings. Those facts make OPSI’s recommendation fundamentally different \nfrom the circumstances and proposal prohibited in Atlantic City. \n41 Southwest Power Pool, Inc., Joint Comments of the Public Service Commissions of Arkansas and Missouri, Docket \nNos. RT04-01-000 and ER04-48 (Nov. 26, 2003) (The RSC shall determine for SPP: decisions on the allocation of \nphysical transmission capacity or the financial rights equivalent; decisions on postage stamp versus license plate rate \ndesign; decisions on how incremental transmission capacity will be funded (except for those related to routine \n(continued)"},{"page":14,"startToken":4947,"endToken":5587,"text":"14 \nCommission wrote that the SPP-RSC should have several important authorities and directed SPP \nto provide them in a compliance filing.42  Chair Wood agreed, writing, “In this order, I would have \naccepted SPP’s revised Bylaws with regard to the role of the Regional State Committee and would \nhave directed the addition of certain additional language taken from the Supporting Commissions’ \npleading.”43 But notably, there were concerns identified by commenters and Commissioner \nKelliher, including “whether a Regional State Committee can require a Regional Transmission \nOrganization to make a filing to the Commission.”44 Nonetheless, SPP adopted the Commission’s \nrecommendation verbatim including the language in footnote 42 of these comments, and the \nCommission approved this provision.45  \n \nmaintenance and operations and other minor upgrades), and the costs allocated among transmission users; decisions \non rate design issues including “through and out rates,” export rates or similar tariff mechanisms that should be used \nto minimize cost-shifting among transmission customer groups or zones; decisions supplemental to FERC as to market \npower monitoring measures; decisions as to regional transmission planning and expansion issues that affect cost \nresponsibility among transmission owners and load serving entities; decisions as to requests for waiver(s) of any non-\nprice terms and conditions that may be incompatible with bundled retail service needs; and decisions on \nimplementation of wholesale markets beyond the energy imbalance market. Once the RSC reaches a decision on the \nmethodology that would be used on the issues listed above, SPP shall file this methodology pursuant to Section 205 \nof the Federal Power Act. In addition to this filing made on behalf of the RSC, SPP, any individual member or \nregulatory body may intervene pursuant to their respective Section 205 filing rights and propose an alternative \nmethodology. On matters referred to in this paragraph for which the RSC may provide direction to SPP, a decision of \nthe RSC requires affirmative votes of two-thirds of the members voting. If the RSC is unable to reach a timely decision \non any of these matters, SPP may file its own proposal regarding any of these matters pursuant to Section 205 of the \nFederal Power Act.”). \n42 Southwest Power Pool, Inc. 106 FERC ¶ 61,110, PP 219–221 (2004) (“The RSC should have primary responsibility \nfor determining regional proposals and the transition process in the following areas:  (1) whether and to what extent \nparticipant funding would be used for transmission enhancements; (2) whether license plate or postage stamp rates \nwill be used for the regional access charge; (3) FTR allocation where a locational price methodology is used; and (4) \nthe transition mechanism to be used to assure that existing firm customers receive FTRs equivalent to the customers’ \nexisting firm rights.  If the RSC reaches a decision on the methodology that would be used, SPP would file this \nmethodology pursuant to Section 205 of the FPA. SPP can also file its own proposal pursuant to Section 205.The RSC \nshould also determine the approach for resource adequacy across the entire region.  In addition, with respect to \ntransmission planning, the RSC should determine whether transmission upgrades for remote resources will be included \nin the regional transmission planning process and the role of transmission owners in proposing transmission upgrades \nin the regional planning process. Finally, the alternate proposal the Supporting Commissions filed provides for an \naffirmative vote of two-thirds of the RSC members voting to require a Section 205 filing. We do not believe that this \nelement of the RSC structure needs to be included in SPP’s Bylaws.  Rather, the RSC should determine its voting \nstructure, make such structure known, and, when a measure is passed in accordance with such structure, inform SPP.”). \n43 Southwest Power Pool, Inc., 106 FERC ¶ 61,110 (2004) (Wood, Chairman, concurring). \n44 Id. (Kelliher, Comm’r, concurring). \n45 Southwest Power Pool, Inc., 108 FERC ¶ 61,003, PP 118–120 (2004)."},{"page":15,"startToken":5587,"endToken":5976,"text":"15 \nThe following extracts show how the other three multi-state RTOs have conditioned FPA \n205 filing rights to compel filings on behalf of their state regulators or provided an important \nresource adequacy right to the states, as in the MISO context: \nSPP \nThe [Regional State Committee] has primary responsibility for determining \nregional proposals and the transition process in the following areas:  \n \n(a) whether and to what extent participant funding will be used for transmission \nenhancements;  \n \n(b) whether license plate or postage stamp rates will be used for the regional access \ncharge;  \n \n(c) financial transmission rights (FTR) allocation, where a locational price \nmethodology is used; and  \n \n(d) the transition mechanism to be used to assure that existing firm customers \nreceive FTRs equivalent to the customers’ existing firm rights.  \n \nThe RSC will also determine the approach for resource adequacy across the entire \nregion. In addition, with respect to transmission planning, the RSC will determine \nwhether transmission upgrades for remote resources will be included in the regional \ntransmission planning process and the role of transmission owners in proposing \ntransmission upgrades in the regional planning process.  \n \nAs the RSC reaches decisions on the methodology that will be used to address any \nof these issues, SPP will file this methodology pursuant to Section 205 of the \nFederal Power Act. However, nothing in this section prohibits SPP from filing its \nown related proposal(s) pursuant to Section 205 of the Federal Power Act.46 \n \nMISO \nAt any point during the stakeholder process developing a proposal seeking to \namend an existing regional cost allocation methodology or develop a new cost \nallocation methodology as per Article II, Section II.E.3.b of this Appendix K, the \n[Organization of MISO States] Committee may undertake to develop and request \nMISO file an OMS Committee alternative cost-allocation methodology, so long as \n66% of all of the OMS Committee voting members agree to this undertaking and \npursuant to Section II.E.3.a of this Appendix K. At the end of the stakeholder \nprocess MISO will either file with FERC a new transmission cost allocation \nmethodology, a change to an existing transmission cost allocation methodology or \nwill provide the OMS Committee with a written explanation of its decision not to \n \n46 SPP Bylaws at Section 7.2. See Southwest Power Pool, Inc. 108 FERC ¶ 61,003 at P 118-120 (2004)."},{"page":16,"startToken":5976,"endToken":6429,"text":"16 \nfile changes to the Tariff. If MISO does not file changes to the Tariff, no OMS \nalternative cost-allocation methodology will be filed with FERC by MISO.47 \n \nThe Transmission Provider will determine a Planning Reserve Margin (PRM) in \nterms of Unforced Capacity for each Season using analytical study methods \ndescribed in Section 68A.2, provided that if a state regulatory authority establishes \na PRM for its regulated entities that is higher or lower than the PRM determined by \nthe Transmission Provider, then the state regulatory authority-established PRM will \napply to the Coincident Peak Demand of LSEs under that state’s jurisdiction.48 \n \nISO-NE \nIf the Regional State Committee opposes the [Participating Transmission Owners’] \nproposal to change the cost allocation provisions set forth in Schedules 11 or 12 of \nthe ISO OATT as of the Operations Date (or the successors thereto), the PTOs may \nmake the Section 205 filing to modify the cost allocation provisions set forth in \nSchedules 11 or 12 of the ISO OATT as of the Operations Date (or the successors \nthereto); provided that: (1) such filing may not go into effect until FERC has \napproved the filing; (2) the Regional State Committee will have the right to provide \nthe PTOs with an alternative proposal to change the cost allocation provisions set \nforth in Schedules 11 or 12 of the ISO OATT as of the Operations Date (or the \nsuccessors thereto) which the PTOs will include in their Section 205 filing and \nwhich will be considered on an equal footing with the PTOs’ proposal in the FERC \nproceeding, and (3) such alternative proposal shall not adversely affect the rights \nof the affected PTO(s) to fully recover their FERC-allowed revenue requirements \nand the amount of incentive payments associated with FERC-allowed incentive \narrangements for the PTO(s) or result in any costs previously approved or accepted \nfor recovery under either a federal or state-jurisdictional rate thereafter becoming \nunrecoverable under either a federal or state-jurisdictional rate.49 \n \nAnd further, in a new state-agreed-upon process that FERC approved in 2024, FERC \napproved a process by which the New England States Committee on Electricity (“NESCOE”) can \nrequest alternative cost allocation methods for Longer-Term Transmission Upgrades through a \nformal written request to the ISO.50 For projects with a benefit-to-cost ratio greater than 1.0, \nNESCOE can request a specific, alternative cost allocation—this allows the incremental costs for \naddressing longer-term needs to be allocated differently than the default method. For projects that \n \n47 MISO Transmission Owners Agreement, Appendix K, 2.E.  \n48 MISO Tariff Module E-1 - 68A.1 - Establishment of Planning Reserve Margins. \n49 ISO-NE Transmission Operating Agreement, Article II, 3.04(h)(vi)(C). \n50 ISO New England, Inc., 188 FERC ¶ 61,010 (2024)."},{"page":17,"startToken":6429,"endToken":6741,"text":"17 \ndo not meet the 1.0 benefit-to-cost ratio, NESCOE can request the specific cost allocation method \nfor the portion of costs that is not covered by regional benefits and will be funded by voluntarily \nparticipating states. \n \nRecommendation 2C: Should PJM receive the authority to make unilateral FPA \nSection 205 filings in line with Recommendation 1 above, PJM should further agree \nto attach a condition to those rights that would require it to make filings on OPSI’s \nbehalf on important regional transmission planning and markets rules located in the \nOA. \n \nExpanding upon the examples above, should FERC agree and direct that PJM have \nexpanded independent filing authority over provisions of the OA, it is appropriate that PJM make \nfilings on OPSI’s behalf related to these provisions as well. OPSI recognizes this goes beyond the \narrangements in other regions, but the interest in state involvement in transmission planning and \nenergy markets applies just as equally to state involvement in resource adequacy and transmission \ncost allocation issues. The rules on these matters greatly affect retail customers and warrant a \ngreater role for the states in getting public interest proposals before the Commission.  \nPanel 1 - Q2. How should states, through the Organization of PJM States, Inc. \nor other structures, interface with the Board to enable the region to meet \noperational and market challenges while respecting PJM’s independence? \n \nEnhancing the role of OPSI, as described above, would meaningfully improve the \ngovernance framework in PJM by allowing both RTO and state public-interest informed filings to \ncome before the Commission.  \nRecommendation 3: OPSI supports formal recognition of the PJM Governors’ \nCollaborative in the PJM Tariff. \n \n \nOPSI welcomes the expanded engagement of state and local executives and believes that \ntheir voice has the potential to provide much needed leadership to guide PJM through increasingly \nchallenging policy debates and foster clarity when there is indecisiveness or a lack of consensus."},{"page":18,"startToken":6741,"endToken":7069,"text":"18 \nFirst, this Governors’ Collaborative should have the ability to propose problem statements and \nissue charges directly to the PJM Board, avoiding the need to receive supermajority support from \nPJM Members to initiate stakeholder processes on issues that are important to the states. This \nwould allow the PJM Board to direct a process to further define issues and identify solutions in \nareas important to the states. This process would allow the PJM Board to decide whether state-\nsponsored issues should be elevated and advanced in the face of PJM Member opposition. Second, \nthis group should be able to recommend proposals to the PJM Board of Managers when there is a \nlack of consensus at the end of a stakeholder process, providing timely direction to the PJM Board \nof Managers in some circumstances. And finally, this group should be able to appoint three \nmembers to the PJM Board Nominating Committee. It is important that the Collaborative establish \nbinding internal rules to ensure its appointees represent the diverse political and energy policy \nperspectives of the 14 PJM jurisdictions and that any action the Collaborative takes represents \nbroad consensus of state and local executives in the PJM region. This suite of rights and \nresponsibilities has the potential to bring the region’s executives into the PJM’s stakeholder and \ngovernance processes and elevate an important voice in conversations on the most pressing issues \nthe region faces. \nPanel 2 - Q3. Are there structured opportunities in the stakeholder process for state \nparticipation (e.g., defined consultation windows, joint technical sessions) to provide \ninput on topics that are of interest to the states? \n \nPanel 2 - Q5. What reforms to the stakeholder process could ensure PJM can meet \nthe region’s challenges? \n \nAs stated throughout these comments, states are responsible for overseeing retail bills, but \nthey have little ability to influence many of the regional costs that ultimately appear on those bills. \nJust as important as giving states a meaningful avenue to place proposals before FERC is giving"},{"page":19,"startToken":7069,"endToken":7362,"text":"19 \nstates a meaningful ability to provide leadership within the PJM stakeholder process and elevate \ncertain issues for discussion, even over stakeholder objection. \nThe current stakeholder process does not provide the states with a meaningful way to \nprioritize issues of particular importance to retail regulators and the customers they represent. \nInstead, states must generally rely on the ordinary stakeholder process to identify problems, \ndevelop solutions, and recommend those solutions to the PJM Board for implementation. That \nstructure leaves state-priority issues dependent on whether other stakeholders choose to advance \nthem and whether they can survive a process not specifically designed to address the states’ public-\ninterest responsibilities. \nThe Governors’ Collaborative should be able to advance issue charges and problem \nstatements, even over Member objection, where the Board agrees that doing so is appropriate. The \nprocess should be structured to produce timely, practical recommendations that stakeholders and \nMembers can support. At its conclusion, the PJM Board should retain authority to accept, reject, \nor otherwise act on the recommended solutions based on the record developed through that \nprocess. Separately, PJM should establish a process through which OPSI may identify priority \nissues for consideration by the PJM Board. If OPSI and the Board agree that an issue should be \nprioritized, the Board should be able to direct a focused stakeholder process to define the problem, \nevaluate alternatives, and identify solutions. \nTo improve transparency, PJM should publicly disclose firm-level voting results for all \ncommittees, except for Board elections and matters involving personnel or compensation. Greater \ntransparency would improve accountability, provide a clearer record of stakeholder positions, and \nallow the Board, regulators, and the public to better evaluate the level and breadth of support for \nproposals. Further, PJM’s stakeholder process has ballooned to fill many hours of most days"},{"page":20,"startToken":7362,"endToken":7678,"text":"20 \nthroughout the year. PJM’s stakeholder process could benefit from increased focus and efficiency \nby soliciting a wider range of perspectives and reducing repetition. Consistent voting rules should \nbe applied throughout PJM’s stakeholder process. Lower-level committees, where issues are first \ndeveloped and refined, should use the same sector-weighted voting framework that governs senior \nstanding committees. This would ensure that proposals advance based on a consistent expression \nof stakeholder support rather than changing voting standards as they move through the process. \nAnd finally, to better promote Board member independence and improve the quality of \ndialogue between the PJM Board of Managers, states, and stakeholders, the Commission should \nconsider the following reforms. First, Board member terms should be lengthened to strengthen \nindependence and encourage a longer-term perspective. Longer board member terms, balanced \nwith term limits, could ensure that Board members would be able to act independently without \nbeing concerned that voting stakeholders dissatisfied with those Board decisions would easily deny \nthem reappointment.  Second, the PJM Board’s ex parte restrictions should be revised to allow the \nPJM Board to engage in more regular and meaningful discussions with states and all stakeholders. \nAny reduction in ex parte restrictions should be accompanied by greater transparency regarding \nthe Board’s interactions, including enhanced reporting on discussions at both Liaison Committee \nmeetings and PJM Board of Managers meetings, which are currently closed to the states. Finally, \nwhile it is important that Board members have broad experience and understand wholesale power \nmarkets beyond the PJM region, candidates with deep knowledge of PJM and the region it serves \nshould not be disadvantaged simply because they reside in or have worked within the footprint. \nII. \nCONCLUSION \nThe combined effect of these recommendations has the potential to more meaningfully \nincorporate the voice of the states and promote the quicker identification and acceptance of \nsolutions to solve the region’s most pressing needs. Consensus in PJM is only becoming more"},{"page":21,"startToken":7678,"endToken":7799,"text":"21 \ndifficult to achieve, and creating formal pathways for state leadership where consensus exists \nstands to better situate PJM to tackle the biggest issues it faces. OPSI’s goal is to give PJM and \nFERC additional tools to protect consumers by enabling stronger leadership from each when \nappropriate. OPSI appreciates the opportunity to provide these pre-conference comments and \nlooks forward to the technical conference on July 23. \n \nRespectfully Submitted, \n \nBenjamin B. Sloan \nExecutive Director \nOrganization of PJM States, Inc. \n700 Barksdale Road, Suite 1 \nNewark, DE 19711 \n601-214-8481 \nben@opsi.us \n \nEllen B. Egen \nDirector of Legal and Regulatory Affairs \nOrganization of PJM States, Inc. \n700 Barksdale Road, Suite 1 \nNewark, DE 19711 \n(336) 254-4915 \nellen@opsi.us \n \nDated: July 20, 2026"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":1293,"startToken":0,"endToken":486},{"p":2,"at":1293,"title":"I. COMMENTS","method":"printed heading","endPage":9,"endAt":1874,"startToken":486,"endToken":3119},{"p":9,"at":1874,"title":"E. Mills,","method":"printed heading","endPage":20,"endAt":1919,"startToken":3119,"endToken":7635},{"p":20,"at":1919,"title":"II. CONCLUSION","method":"printed heading","endPage":21,"endAt":807,"startToken":7635,"endToken":7799}]}