{"document":{"slug":"rec-20260723-5034","title":"Comments Based on Research from the RTO Governance Research Network re the PJM Governance and Stakeholder Reforms","issued":"2026-07-23","accession":"20260723-5034","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"RTO Governance Research Network","kind":"comments","file":"sources/filings/text/20260723-5034_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260723-5034","tier":"record","sha256":"2d26696ce7d7f58fd7b75183a81a2b534cbb1410f3ec8a7beb88cfa27202de0b","pages":14,"tokens":5310,"emptyPages":[],"textThemes":["adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":336,"text":"1 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Governance and Stakeholder Reforms ) \n) \n) \nDocket No. AD26-7-000 \n \nCOMMENTS BASED ON RESEARCH FROM THE RTO GOVERNANCE \nRESEARCH NETWORK1 \nSUBMITTED BY DR. SETH BLUMSACK, PROFESSOR OF ENERGY POLICY AND \nECONOMICS AND DIRECTOR OF THE RTO GOVERNANCE RESEARCH \nNETWORK, PENN STATE UNIVERSITY \nI. \nIntroduction \nDrawing on research and editorial input from researchers affiliated with the RTO \nGovernance Research Network, I am pleased to submit these comments addressing a \nnumber of the Commission’s Questions posed under Docket AD26-7 related to \n \n1 The RTOGov researchers who contributed to these comments and/or are cited within include: Dr. Seth \nBlumsack, Professor of Energy Policy and Economics and Co-Director of the Penn State Center for Energy \nLaw and Policy, Pennsylvania State University; Michael H. Dworkin, JD., Professor Emeritus, Vermont \nLaw School; Lara Fowler, Teaching Professor, Penn State Dickinson Law School, Pennsylvania State \nUniversity; Dalten Fox, who performed research while a Graduate Student at Boise State University; \nMichael Helbing, Executive Director, Penn State University Center for Energy Law and Policy; Dr. \nNicholas Johnson, Associate Professor, Principia College; Kevin Jones, Institute for Energy and \nEnvironment, Vermont Law School; Dr. Lynne Kiesling, Director of the Institute for Regulatory Law and \nEconomics, Northwestern University; Dr. Andrew Kleit, Professor Emeritus of Energy Economics, \nPennsylvania State University, Dr. Stephanie Lenhart, Associate Professor, School of Public Service, Boise \nState University; Joshua Macey, Associate Professor, Yale Law School; Ari Peskoe, Director, Electricity \nLaw Initiative, Harvard Law School; Abe Silverman, Research Scholar, Johns Hopkins University; \nChristina Simeone, who performed research while a Senior Fellow, Kleinman Center for Energy Policy, \nUniversity of Pennsylvania; Zachary F. Teti, who performed research while a Graduate Student, \nPennsylvania State University; Daniel Walters, Associate Professor, Texas A&M Law School; Shelley \nWelton, Professor, Carey School of Law, University of Pennsylvania; Hannah Wiseman, Professor and \nCo-Director of the Penn State Center for Energy Law and Policy, Penn State Dickinson Law School, \nPennsylvania State University; Dr. Kyungjin Yoo, who performed research while a Graduate Student, \nPennsylvania State University."},{"page":2,"startToken":336,"endToken":565,"text":"2 \ngovernance of the PJM Interconnection. These comments are being filed in advance of \nthe Commission’s technical conference on July 23, 2026. \nFigure 1: The RTO Governance Network \nThe RTO Governance Research Network (“RTOGov”) is an interdisciplinary network of \nacademic researchers and practitioners with interests in the governance of regional \norganizations that plan, manage, and ensure reliable operation of interconnected bulk \npower systems. The RTOGov network is currently administered by the Center for \nEnergy Law and Policy at Penn State University, and engages affiliated researchers at \ndozens of academic institutions and interested non-academic organizations (Figure 1). \nRTOGov operates as an affiliation of independent researchers and organizations that \ndevelop research concepts to pursue under the RTOGov banner. Governance of PJM \nhas been studied by several researchers affiliated with RTOGov, and the purpose of this \ncomment is to collect and synthesize those research findings as they relate to the \nspecific issues identified by the Commission under the present Docket. Since this \ncomment synthesizes a number of research findings, it should not be taken to represent \nthe views of the network as a whole. \nThe RTOGov network was launched in 2019, and has received ongoing financial \nsupport from the Alfred P. Sloan Foundation, the Heising Simons Foundation, the \nNicholas Institute for Energy, Environment and Sustainability at Duke University and \nthe Center for Energy Law and Policy at Penn State University. Research papers,"},{"page":3,"startToken":565,"endToken":956,"text":"3 \npresentations and other written pieces forming the basis for these comments are freely \navailable at RTOGov’s web site, https://rtogov.org. \nII. \nThe Evolving Role of RTOs and Governance \nBefore addressing the Commission’s specific Questions related to PJM’s overall \ngovernance structure, it is useful to put this structure into some context. \nLenhart and Fox (2022) provide a useful overview of the governance structures of \nexisting U.S. ISOs and RTOs (including ERCOT, which is not FERC-jurisdictional). \nFERC-jurisdictional ISOs and RTOs have, for many years, needed to reconcile two \nbroad governance goals as laid out by the Commission (Lenart and Fox, 2022; Helbing, \n2023). RTOs needed to demonstrate independence from the commercial interests of \ntheir Membership (Order 888 and Order 2000) and also needed to demonstrate \nresponsiveness to their Members (Order 719). While there are differences among RTOs \nin how they have responded to these principles of independence and responsiveness, \nthere are some common features including independent Boards, roles for Member and \nNon-Member stakeholders and establishment of committees to represent interests of the \nstates. (As we will discuss later in this Comment, the state committee in PJM has \nperhaps the least formal role of any ISO/RTO.) \nTension in PJM’s governance process is not new. Johnson, et al. (2023) have \ndocumented the emergence of tensions in PJM’s governance process beginning well \nover a decade ago. As with the current situation in which PJM finds itself, the source of \nthe tensions described in Johnson, et al. (2023) can be traced in part to an evolution in \nthe roles that the RTO has needed to assume, without substantial corresponding \nevolution or adaptation in the RTO’s governance model. \nOne important aspect of PJM’s evolution is an incremental and ongoing expansion of \nthe organization’s activities in response to federal policy and legislation. PJM’s original \nmandate was narrowly defined in terms of reliability and open-access transmission \n(Welton, 2021). The Energy Policy Act of 2005 gave PJM and other RTOs new \nresponsibilities for reliability coordination and compliance. Introduction of the \nReliability Pricing Model capacity market shifted responsibility for resource adequacy \nprocurement to PJM. Transmission planning also created higher stakes for transmission \nowners and other Members following the issuance of Order 1000. \nA second important aspect of PJM’s evolution is the RTO as a focal point for \nimplementation of state policy, especially state preferences over power generation \ntechnologies."},{"page":4,"startToken":956,"endToken":1391,"text":"4 \nPJM’s governance model was built for an organization that was to be largely \ntechnocratic and administrative. That organization, however, has evolved into one that \nhas substantial market responsibilities. As Silverman (2026) has noted, RTOs describe \nthemselves as “policy-takers.” While this is true in one respect, the expanded role of \nRTOs (relative to their original conception) means that their rules and actions in \nplanning and markets have policy implications for consumers in the states that they \nserve (Welton, 2021). \n \nIII. \nComments on PJM’s Governance Structure \nThis section provides some responses to the first set of Questions posed by the \nCommission, focused on PJM’s governance structure and the roles of different actors in \nPJM governance. \nQuestion: What governance reforms would best improve accountability and responsiveness? \nResearch into structural governance reforms in PJM and other RTOs highlights \noverlapping categories of structural governance reform that would be helpful. The \ndiscussion here draws liberally from a few articles in particular - Yoo and Blumsack \n(2018a, 2018b), Welton (2021), Peskoe (2021 and 2023) and a forthcoming piece on filing \nrights from Macey (2027). A first set of reforms could make PJM a more efficient and \ndecisive institution. A second set of reforms would reduce the ability of incumbents to \nblock adaptation and change. A third set of reforms would scale back PJM’s \nresponsibilities to return it closer to its origin as a technical organization with reliability \ncontinuing to be its primary mission. We will discuss each of these in turn. \nFirst, PJM needs to be able to act quickly and independently. To that end, the RTO and \nthe public interest would be helped if the Board were to have (at least shared) filing \nrights over all major aspects of PJM’s functions – including regional transmission \nplanning and resource adequacy compliance. One aspect which makes PJM’s \ngovernance particularly complex is the number of separate governing documents with \ndifferent (unilateral) filing rights assigned. Consolidation of these governing documents \ninto the Open Access Transmission Tariff would give PJM a more streamlined \ngovernance structure. \nSecond, and relatedly, PJM should be independent of its members. That entails not \nsimply requiring that board members not have financial entanglements with PJM \nmembers, but also that the board nominating process include input from states; the \nmost straightforward way to accomplish this would be to include state representation \non the Board nominating committee and also to devise a mechanism for states to hold \nsome manner of filing rights as is the practice in both SPP and MISO. True \nindependence also means that PJM is able to make decisions independent of its \nmembership without ignoring Members’ viewpoints. Accomplishing this would mean a"},{"page":5,"startToken":1391,"endToken":1877,"text":"5 \nvastly reduced role for the stakeholder process as part of PJM governance, so that \nstakeholder voting would either be eliminated or would become advisory, as the \nstakeholder process is currently structured for MISO. The California ISO also features a \nstakeholder process whose role is purely advisory, but is fundamentally different from \nother ISOs/RTOs in that there is no formal plenary stakeholder committee and no \nvoting. \nIn the absence of eliminating stakeholder voting altogether, PJM should consider (with \nappropriate structural changes to prevent stalemates, as we discuss in our response to a \nsubsequent Question) expanding the use of an advisory stakeholder input mechanism \nsimilar to what it uses during its Critical Issue Fast Path process. This process provides \na structured way for stakeholders to provide input to the Board on its preferred options \nwhile retaining the decision-making authority of the Board itself. PJM could consider \nusing this type of process for any issue over which the Board possesses unilateral or \nshared §205 filing rights. \nThird, where possible, empower states–not PJM–to make politically salient decisions \nregarding resource adequacy. Reducing PJM’s role in capacity procurement sounds like \na market reform (which it would be) but perhaps more importantly it would represent a \nmajor governance reform by shifting some responsibility for resource adequacy away \nfrom the RTO. PJM was created to be a technocratic body. It was supposed to do \ntransmission planning, dispatch resources in real time, and play some role in resource \nadequacy compliance. Over the past twenty years, PJM has seen a great deal of mission \ncreep. Its role in capacity procurement through the Reliability Pricing Model (not just \ncompliance a la accreditation and margin requirement calculations) has been the source \nof a great deal of governance tension. One way to ameliorate this tension would be to \ngive PJM authority over technocratic aspects of resource adequacy but put states in a \nposition to conduct procurements themselves (ideally through mostly long-term \ncapacity contracts as happens in some other RTOs but that would be a matter for states \nto oversee). To that end, PJM could continue to establish reserve margins, accredit \ncapacity resources (if there is still a capacity market), and impose hedging \nrequirements.  \nQuestion: How does the division of Federal Power Act section 205 filing rights among PJM, \nTransmission Owners, and the Members Committee affect PJM’s ability to act effectively and \nquickly, when warranted, to address operational and market needs? \nPJM is nearly unique among ISOs and RTOs in having no concept of shared filing rights \nover any governing document. This structure in and of itself makes aspects of \ngovernance reform difficult because the Members retain sole filing rights over the \nOperating Agreement, which among other things covers the stakeholder process and \nthe election of Board members. \nAny structural governance reform in PJM is challenging because the RTO has been \nboxed in by its own governance structure. Making changes not only to filing rights but"},{"page":6,"startToken":1877,"endToken":2300,"text":"6 \nalso the stakeholder process, regional transmission planning and Board selection would \nrequire either sufficient support of PJM’s membership or a §206 finding that would \ninstigate change. The structural governance reforms to PJM that we have outlined \npreviously would mostly fall into this difficult category. We acknowledge the difficulty \nin implementation. \nQuestion: To what extent do provisions in PJM’s Operating Agreement, Transmission Owner \nAgreement, Open Access Transmission Tariff, Reliability Assurance Agreement, or Manuals \nimpede timely decision-making by PJM?   \nThree features of PJM’s governing documents      make it difficult for PJM to efficiently \npromote the public interest. First, under the Consolidated Transmission Owners’ \nAgreement, some filing rights – especially cost recovery for local transmission and \nplanning – remain with Transmission Owners (TOs). This exacerbates TO’s incentives \nto favor small supplemental projects over more efficient regional solutions (Peskoe \n2021, 2023; Macey, 2027). Second, TOs and retain certain withdrawal rights. The threat \nof withdrawal can make it difficult for PJM to enact important but controversial rules \n(Peskoe 2023; Macey 2027). Third, of the filing rights held by PJM (as opposed to TOs or \nother market participants), a large number reside in the Operating Agreement rather \nthan the Tariff. Matters that are governed by the Operating Agreement generally \nrequire sufficient support in a vote by the Members Committee. This is an onerous and \ntime-consuming process, and it gives various coalitions of Members the ability to veto \nor delay important market changes (Yoo and Blumsack 2018a, 2018b; Welton, 2021; \nJohnson et al., 2023; Macey 2027). In an ideal world, the Board would have more filing \nrights and would create other mechanisms to get stakeholder input surrounding tariff \nchanges.     .  \nQuestion: Recognizing regional differences, are there lessons from other regional transmission \norganization/independent system operator (RTO/ISO) governance structures that PJM could \nreasonably adopt to improve its responsiveness to the region’s operational and market \nchallenges? \n \nPJM is unique among RTOs and ISOs in having a governance structure in which states \nhave no formal authority. Aside from the New York ISO and California ISO as single-\nstate entities with clear connections to state legislative and policy preferences, \ngovernance structures in the three multi-state RTOs (aside from PJM) all feature a state \norganization or committee with a well-defined role. These state committees (the \nRegional States Committee in SPP, Organization of MISO States in MISO and New \nEngland States Committee On Electricity in ISO New England) differ in the extent of \ntheir responsibility, and governance structures in SPP and MISO provide a potential \nmodel for how the RTO may workably share filing rights with the states."},{"page":7,"startToken":2300,"endToken":2699,"text":"7 \nIV. \nComments on PJM’s Stakeholder Process \nThis section includes responses to the second set of Questions posed by the \nCommission, which focus on PJM’s stakeholder process.  \nQuestion: Do sector-weighted voting and existing voting thresholds strike the right balance \nbetween achieving consensus and taking timely action?   \nBased on existing research, the short answer to this Question is that PJM’s sector-\nweighted voting process has, at times, been highly challenged either to move \nstakeholders towards consensus or to send clear signals to the Board as to the \npreferences of stakeholders. Designing electricity markets via PJM’s stakeholder \nstructure has been fraught when the more contentious aspects of market design are at \nstake. The challenges that arise in PJM’s stakeholder voting stem from a couple of \nstructural facts about the stakeholder process. \n● PJM’s sector-weighted voting system makes it relatively easy for a minority of \nMembers to block proposals with which they disagree; \n● Differences in voting rules between the lower level committees and the plenary \nMembers Committee can lead to situations where proposals may emerge from \nlower level committees highly influenced by one set of Members only to be \ndefeated in the Members Committee by another set of Members. \nThe remainder of our response expands on these two critical points. \nLike some other RTOs (notably ISO New England and the New York ISO), PJM uses a \nsector-weighted voting procedure in the Members Committee. Under such a voting \nprocedure, each voter is assigned to a specific group, and then voting happens within \nthose groups. Perhaps the most well-known example of a sector-weighted voting \nsystem is the Electoral College used in U.S. Presidential elections. Under the Electoral \nCollege, voters are divided into groups based on the state in which they cast their vote, \nand each state’s voting outcome carries a different weight in the overall election. In \nPJM’s Members Committee, each vote-bearing Member chooses or is assigned to one of \nfive sectors based on the primary business area of each Member. Each of the five \nstakeholder sectors is given equal weight in PJM’s system, whereas those weights vary \nby sector in other RTOs (Lenhart and Fox, 2022; Yoo and Blumsack, 2018a).  \nThe five sectors are very uneven in terms of the total number of Members in each sector. \nTable 1, taken from PJM (2026) shows the membership distribution among the five \nstakeholder sectors. Voting members are permitted to cast votes in the Members and"},{"page":8,"startToken":2699,"endToken":3054,"text":"8 \nMarkets and Reliability Committees. Voting and Affiliate Members are permitted to \ncast votes in the lower level committees. \nTable 1. PJM Sectoral Stakeholder Membership (screen shot taken from PJM, 2026) \n  \nThe decision threshold in PJM’s Members Committee is sometimes described as \nrequiring a two-thirds supermajority in order for a voting item to be passed. This is \nsomething of a blunt description which masks how a voting item actually passes or \nfails. When presented with a voting item, votes in the Members Committee are tallied \nwithin their sectors. For each sector, a “voting score” is calculated which represents the \nfraction of “yes” votes that the voting item has attained within each sector. These voting \nscores are thus between zero and one for each sector. The voting scores across all five \nsectors are then summed, and if the resulting total exceeds 3.335, then the voting item \npasses. The “two thirds supermajority” refers to the fraction of the overall voting score \nthat a voting item must achieve in order to pass. It does not refer to the total number of \nvotes. Because the number of voting Members in the five sectors are so unequal, a \nvoting item can pass even if two-thirds of the voting Members do not support it. \nSimilarly, a voting item can fail even if two-thirds of the total number of voting \nMembers do support it.  \nBecause this system was devised by incumbent PJM Members, it is not surprising that \nsome research has found that the system benefits those incumbents who helped to \ndesign it (Welton 2021; Walters and Kleit 2022) and is purposefully slow to adapt in \nways that make it more difficult for new technologies or market actors to enter (Jones \n2017; Walters and Kleit 2022; Kiesling 2026). This has been interpreted to mean that \ntransmission owners can leverage “stagnant” governance structures for their own \nadvantage (Peskoe, 2023). It has also been interpreted to imply that suppliers exert \nsubstantial authority at the Members Committee level at the expense of consumers (this \nperception is reported in the academic literature, for example, by Yoo and Blumsack \n(2018b) and by Johnson, et al. (2023))."},{"page":9,"startToken":3054,"endToken":3502,"text":"9 \nAt the level of the Members Committee, however, the existing body of research does \nnot support the conclusion that one particular constituency or another consistently \nbenefits from the existing voting system or exercises political power over the voting \nsystem. The broader structural problem is that PJM’s sector-weighted voting structure \ncreates a broader “culture of ‘no’” when presented with difficult or contentious issues. \nSince PJM’s sector-weighted voting structure has five sectors that are equally weighted, \nany two sectors could vote together to block any voting item that they would prefer not \nmove forward. This is not just a theoretical possibility – it has happened repeatedly in \nthe PJM stakeholder process, particularly when contentious issues arise.  \nSeveral research papers have examined voting patterns in PJM’s Members Committee, \nincluding Yoo and Blumsack (2018a, 2018b), Johnson (2021), Teti and Blumsack (2024) \nand Johnson and Blumsack (2026). This work has found two fairly strong coalitions of \nMembers that (a) cross multiple defined sectors, and (b) tend to vote together on the \nmost contentious issues. One of these coalitions crosses the Generation Owner and \nTransmission Owner sectors and may be seen as a kind of supply side coalition. The \nother crosses the Electric Distributor and End Use Customer sectors and may be seen as \na kind of demand side coalition. Each of these coalitions has been able to block market \nreforms that they oppose. As illustrated in Yoo and Blumsack (2018a), Johnson (2021) \nand Johnson and Blumsack (2026) focused on capacity market votes, the supply side \ncoalition has been able to block reforms that (other things equal) may have lowered \ncapacity costs and led to lower installed capacity margins and the demand side \ncoalition has done the same for reforms that may have increased capacity costs and \ninstalled capacity margins. \nDifferential voting rules and treatment of affiliates in PJM’s lower-level stakeholder \ncommittees is another contributing factor to inaction and stalemate. In PJM’s standing \ncommittees, affiliates of individual Members are given individual votes when voting \ndoes occur. Based on data published by PJM (2026), this would seem to principally \nbenefit Members in the Generation Owner sector (which has more than twice the \nnumber of affiliates as voting Members) and the Transmission Owner sector (which has \nmore than three times the number of affiliates as voting Members). The Other Suppliers \nsector also has a substantial number of affiliates, but also has two-thirds of the total \nvoting Membership. \nThese differential voting rules for affiliates in the lower-level standing committees can \nconfer some agenda-setting political power on certain Membership sectors (Simeone, \n2021). It also creates an additional possibility for stalemate at the Members Committee - \nin which one Member constituency passes a proposal and sends it to the Members"},{"page":10,"startToken":3502,"endToken":3888,"text":"10 \nCommittee only to have it rejected at the Members Committee vote.  \nEvaluating the impact of affiliate voting in lower-level committees is not as \nstraightforward as in the Members Committee because the lower-level committee \ndeliberations are not made public with substantial detail. (This could be addressed by \nPJM as a measure of additional transparency.) One example of this dynamic which \nseems clear, however, involved a price formation proposal sent to the Members \nCommittee in February 2019. The proposal sent to the full Members Committee was \npresented by a supply-side Member in the lower-level Committee as a compromise \nmeasure. According to PJM reports, the proposal enjoyed broad support in that lower-\nlevel Committee (PJM, 2019). Once it reached the Members Committee, however, the \nproposal was defeated by a coalition of End Use Customers and Electric Distributors. \nQuestion: What transparency reforms would improve the quality of PJM’s stakeholder process \nand increase stakeholder confidence in its decision-making? \nIn some ways and at some levels, PJM’s stakeholder process is admirably transparent. \nMost meetings are open to public participation. Detailed voting reports from the \nMembers Committee, for example, are made public by PJM. This has enabled \nindependent analyses of decision-making activity within the Members Committee. PJM \ndoes not archive these materials in perpetuity – older voting reports from Members \nCommittee meetings are eventually removed from PJM’s public web site. This older \nmaterial has been independently archived by Teti and Blumsack (2021). While these \nvoting reports from the Members Committee are not in a format that is easily searchable \nor digestible, the reports are made public and they contain substantial detail regarding \nvoting activity at the level of individual Members. \nOther senior and standing committees do not feature this same level of transparency, \nand PJM could consider making detailed meeting information and voting data available \nfor those committees. Voting data for the Markets and Reliability Committee, for \nexample, does not have the same high level of detail as the Members Committee. Only \nthe aggregated sector-weighted voting results are recorded, making it difficult for \ninterested parties to see where voting items in that Committee were driven to passage \nor failure. Where voting happens in PJM’s lower-level standing committees, those \nresults are not always reported in a detailed way. (Other information from those \nmeetings is posted on PJM’s web site for a period of time.)"},{"page":11,"startToken":3888,"endToken":4288,"text":"11 \nQuestion: What reforms to the stakeholder process could ensure PJM can meet the region’s \nchallenges?  \nEarlier in this Comment, we discussed potential reforms to the allocation of §205 filing \nrights over PJM’s governing documents to ensure that the Board has ultimate (or at \nleast shared) authority over PJM’s organizational decision-making. We also discuss the \nbenefits of making stakeholder voting purely advisory (as is the case with MISO’s \nstakeholder process) or eliminating stakeholder voting altogether and providing an \nalternative mechanism for Members to provide input to the Board (as is the case with \nthe California ISO’s governance process). These reforms may themselves address \nexisting issues in PJM’s stakeholder process. Our response to this Question focuses on \nthe stakeholder process as it exists today. \nExisting research on PJM’s stakeholder process, particularly at the plenary Members \nCommittee level, suggests several potentially beneficial reforms. \n● Lowering the passage threshold in PJM’s sector-weighted voting. Reducing the \nthreshold to 3.0, for example, would maintain a supermajority while removing \nthe ability of some strong cross-sector coalitions to block voting items. Under \nsuch a threshold, for example, the 2019 price formation proposal would have \npassed the Members Committee. PJM currently has the highest passage \nthreshold among RTOs which use sector-weighted voting. The New York ISO \nuses a threshold of 58% for most voting items, while ISO New England uses a \nthreshold of 60% for market-related voting items. \n● Expanding the number of sectors would reduce the vote dilution that happens in \nthe Other Suppliers sector in particular. Expanded sector definitions could \nrepresent emerging aligned interests which are distinct but currently lumped \ninto a single sector (examples might include financial players, energy storage \ndevelopers and so forth). We note that simply expanding the number of sectors \nwill not in and of itself break up the strong voting coalitions that exist within the \nPJM stakeholder process, but in some cases could make it more difficult for \nexisting coalitions to block voting items so easily.  \n● PJM is unique among RTOs in the sheer size of its membership, in part because it \nopens membership up to a broad array of market participants in ways that some \nother RTOs do not (Lenhart and Fox, 2022). Reducing vote dilution could \npotentially encourage additional participation in the stakeholder process (as Teti \nand Blumsack (2024) write, the majority of PJM voting Members never cast \nvotes). Encouraging participation is a good goal, but realistically may also make"},{"page":12,"startToken":4288,"endToken":4664,"text":"12 \nquick decision-making more difficult. \n● PJM should consider structural changes to its sector-weighted voting process \nthat address the stalemate that can happen in the Members Committee. Several \npossible options exist. One is to use rank-choice voting or other tiebreaker \nmechanisms rather than having Members take individual votes on multiple \ncompeting proposals. Even with no other changes to the stakeholder process, \nsuch a shift would be appropriate for voting items involving changes to the Open \nAccess Transmission Tariff where the Board holds §205 filing rights and the role \nof deliberations at the Members Committee level is to signal a most-favored \nproposal to the Board. A second would be to change the nature of the decision \nthreshold to be based on support from a majority of the sectors rather than a \nstakeholder-wide weighted voting calculation. A third option would be to adopt \nan approach similar to that used in the SPP Markets and Operations Policy \nCommittee (MOPC), which is SPP’s equivalent to the Members Committee \n(Lenhart and Fox, 2022). SPP’s structure still weights votes, but uses only two \nsectors for voting (based on whether Members are transmission owners or users \nof other Members’ transmission systems). The voting calculation ensures that one \nsector cannot unilaterally defeat a voting item if there is sufficient support from \nthe other sector. \n● Eliminate affiliate voting, where voting is used in PJM’s lower level committees \n(below the Members Committee and Markets and Reliability Committee).  \nQuestion: What near-term reforms to stakeholder representation could PJM and its Members \ntake to improve speed in decision-making while preserving stakeholder input? \nEffective participation in PJM’s stakeholder process can require substantial resources in \nterms of staff time and technical knowledge. Teti and Blumsack (2024) report that over a \nthirteen-year period approximately 60% of voting-eligible Members did not cast a single \nvote in the Members Committee. More recently, voting results from PJM’s recent \nCritical Issue Fast Path proceeding on large load interconnection suggested that only a \nsmall percentage of voting-eligible Members in the Other Suppliers sector cast any \nvotes (including abstentions).  \nImproving the ability of more Members to effectively participate would improve \nstakeholder input without necessarily sacrificing speed when needed. A mechanism to \nbroaden the use of proxy participants, along with the resources to support those \nproxies, is one potential mechanism."},{"page":13,"startToken":4664,"endToken":5071,"text":"13 \nQuestion: Should PJM increase the use of fast-path or time-bound review procedures to expedite \ncommittee action on high-importance topics?  \nIn a sense, a mechanism like the Critical Issue Fast Path has elements that should be \nembraced more often – for the Members to express collective preferences to RTO \nleadership and the Board before the Board makes a decision on a filing to FERC, rather \nthan for the Members to have ultimate authority over decisions that should fall under \nthe Tariff. Even without reforms to §205 rights or other reforms to stakeholder voting, \nPJM could explore a process like the CIFP for all issues involving changes to governing \ndocuments over which the Board possesses §205 rights.  \nSuch a process, however, should have a mechanism (such as rank-choice voting) which \nwill drive Membership to communicate their most-preferred option(s) to the Board.  \nQuestion: Recognizing regional differences, are there lessons from other RTO/ISO stakeholder \nprocesses that PJM could reasonably adopt to improve speed in voting processes and stakeholder \nrepresentation? \nThere are multiple practices used in other ISOs and RTOs that could be considered for \nadoption in PJM. Both MISO and the California ISO have stakeholder processes that are \nmore advisory in nature than is the case in PJM. In the New York ISO and ISO New \nEngland, which use stakeholder-voting systems most closely resembling PJM’s, \nstakeholder voting may be contentious but research does not suggest that it has led to \nthe types of stalemates as in PJM. This may be due in part to the lower passage \nthreshold used in those RTOs. Finally, both New York ISO and ISO New England \n(along with other RTOs) have some mechanism for sharing filing rights among multiple \nparties. The breadth of unilateral filing rights held by PJM Members, as well as the \nseparation of filing rights over a number of different governing documents, is unique \namong RTOs and it itself a potential barrier to reforming PJM’s governance. \nWorks cited \nHelbing, M. D. (2023). Fifteen years later-literature perspectives on the impacts of \ndworkin and goldwasser and ferc order no. 719. Energy LJ, 44, 325. \nJohnson, N., Lenhart, S., & Blumsack, S. (2023). The Evolution of Participatory Policy-\nMaking for Regional Power Grids. Energy LJ, 44, 433. \nJohnson, N. (2021). Studies in the Governance of Regional Transmission Organizations, \nPh.D. Dissertation, Pennsylvania State University. \nJones, K. (2017). How the RTO Stakeholder Process Affects Market Efficiency. \nPublication available at https://www.rstreet.org/research/how-the-rto-stakeholder-\nprocess-affects-market-efficiency/"},{"page":14,"startToken":5071,"endToken":5310,"text":"14 \nKiesling, L. (2026). The promise and perils of exclusion: using institutional design \nprinciples and the theory of clubs to analyse regional transmission organization \ngovernance. Journal of Institutional Economics, 22, e7. \nLenhart, S., & Fox, D. (2022). Participatory democracy in dynamic contexts: A review of \nregional transmission organization governance in the United States. Energy Research & \nSocial Science, 83, 102345. \nMacey, J. (2027, forthcoming). Utility Filing Rights and the Grid’s Governance Problem. \nForthcoming in Yale LJ. \nPeskoe, A. (2021). Is the utility transmission syndicate forever?. Energy LJ, 42, 1. \nPeskoe, A. (2023). Replacing the Utility Transmission Syndicate's Control. Energy LJ, 44, \n447. \nPJM Interconnection (2026). Oversight and Transparency. Publication available at \nhttps://www.pjm.com/-/media/DotCom/about-pjm/newsroom/fact-\nsheets/oversight-and-transparency-fact-sheet.pdf \nPJM Interconnection (2019). Members Reject Compromise Proposal to Revamp Reserve \nPricing Rules. PJM Inside Lines, available at https://insidelines.pjm.com/members-\nreject-compromise-proposal-to-revamp-reserve-pricing-rules/. \nSilverman, A. (2026). Governance of Multi-State Electricity Markets for the 21st \nCentury. Publication available at https://energyinstitute.jhu.edu/governance-of-multi-\nstate-electricity-markets-for-the-21st-century/. \nWalters, D. E., & Kleit, A. N. (2022). Grid Governance in the Energy-Trilemma Era: \nRemedying the Democracy Deficit. Ala. L. Rev., 74, 1033. \nWelton, S. (2021). Rethinking grid governance for the climate change era. Cal. L. Rev., \n109, 209. \nYoo, K., & Blumsack, S. (2018a). Can capacity markets be designed by democracy?. \nJournal of Regulatory Economics, 53(2), 127-151. \nYoo, K., & Blumsack, S. (2018b). The political complexity of regional electricity policy \nformation. Complexity, 2018(1), 3493492."}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":374,"startToken":0,"endToken":51},{"p":1,"at":374,"title":"I. Introduction","method":"printed heading","endPage":3,"endAt":144,"startToken":51,"endToken":587},{"p":3,"at":144,"title":"II. The Evolving Role of RTOs and Governance","method":"printed heading","endPage":4,"endAt":537,"startToken":587,"endToken":1035},{"p":4,"at":537,"title":"III. Comments on PJM’s Governance Structure","method":"printed heading","endPage":7,"endAt":3,"startToken":1035,"endToken":2301},{"p":7,"at":3,"title":"IV. Comments on PJM’s Stakeholder Process","method":"printed heading","endPage":14,"endAt":1873,"startToken":2301,"endToken":5310}]}