{"document":{"slug":"rec-20260723-5035","title":"Comments of Senator Scott A. Surovell, chair of Energy Commission of Virginia, re the PJM Governance and Stakeholder Reforms","issued":"2026-07-23","accession":"20260723-5035","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"Energy Commission of Virginia","kind":"comments","file":"sources/filings/text/20260723-5035_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260723-5035","tier":"record","sha256":"ed826b654c4ccd380df8232b37d8eac8a603680f99691a523ec4efc8205905ac","pages":3,"tokens":990,"emptyPages":[],"textThemes":[]},"pages":[{"page":1,"startToken":0,"endToken":288,"text":"UNITED STATES OF AMERICA \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Governance and Stakeholder Reforms \nDocket No. AD26-7-000 \nJuly 22, 2026 \nHonorable Laura V. Swett, Chair \nHonorable David Rosner, Commissioner \nHonorable Lindsay S. See, Commissioner \nHonorable Judy W. Chang, Commissioner \nHonorable David A. LaCerte, Commissioner   \nFederal Energy Regulatory Commission, Commissioner \n888 First Street \nWashington, DC 20426 \n \n \n \n \n \nre:  \nComments of Chair of Virginia Energy Commission  \nDear Commissioners: \nI commend FERC for addressing governance issues at PJM and appreciate the opportunity to \ncomment on this criƟcal issue aﬀecƟng our region.  I chair the Energy Commission of Virginia (formerly \nknown as the Commission on Electric UƟlity RegulaƟon, or CEUR). The Energy Commission of Virginia is \nthe standing legislaƟve commission established by the Virginia General Assembly to vet and discuss \ncomplex uƟlity issues on behalf of the General Assembly’s 140 members.  Our primary responsibility is to \nto report to the General Assembly and Governor on recommendaƟons to maintain reliable service in the \nCommonwealth while preserving the Commonwealth's posiƟon as a low-cost electricity market.  We \ncannot achieve either of these criƟcal standards without a highly funcƟoning regional electricity grid and \nenergy market.  We appreciate the complex role that PJM serves as the RTO/ISO.   \nIf Governors are provided any kind of role or input into PJM governance, then state legislators \nshould have equal access to engage meaningfully in the PJM decision-making and governance process, \nsimilar to the access provided to our state uƟlity regulators.  State legislators serve with disƟnct \nfuncƟons, as a coequal branch under the ConsƟtuƟon of Virginia.  Both execuƟve and legislaƟve \nbranches should have access to PJM regional governance processes given their independent powers. It is \nour understanding that governors have asked for a role in the PJM governance process.  If governors are"},{"page":2,"startToken":288,"endToken":735,"text":"given a role, there should also be a means for state legislatures to parƟcipate, given that there is not \nalways poliƟcal alignment between governors’ oﬃces and state legislatures.  \nVirginia’s uƟlity regulator is the State CorporaƟon Commission, whose Judges of the Commission \n(“Commissioners”) are appointed through the legislaƟve branch. To ensure more eﬀecƟve coordinaƟon \nand address increasing challenges, I am fully supporƟve of granƟng more authority to the OrganizaƟon \nof PJM States, Inc. (OPSI) to ensure more eﬀecƟve load forecasƟng, PJM wholesale and capacity market \ncondiƟons and beƩer transmission planning, to name a few key consideraƟons.  \nLike my colleagues from the NaƟonal Caucus of Environmental Legislators (NCEL), I believe it is \ncrucial that FERC prioriƟze reforms that ensure states can engage meaningfully in PJM governance and \nstakeholder processes and have access to suﬃcient informaƟon.  States have authority over essenƟal \nenergy policy maƩers including siƟng, permiƫng, generaƟon and retail cost allocaƟon. It is imperaƟve \nfor states to have a voice in the regional decisions PJM is making that aﬀect our state’s economy, health \nand safety, through transmission planning, energy markets, and resource adequacy.  \nLike others in this process, I encourage FERC to review surrounding regions and build on the \nprecedents and lessons learned from other bodies, such as the New England States CommiƩee on \nElectricity (NESCOE) and the Southwest Power Pool’s (SPP) Regional State CommiƩee (RSC). \nVirginia has greatly beneﬁted from the PJM regional compact, leveraging the region’s assets to \nhelp achieve energy reliability through access to the wholesale market.  There are numerous regional \ntopics that should be addressed holisƟcally through the governance and stakeholder processes at PJM, \nincluding but not limited to load growth forecasts, inter-state transmission projects, and regional or \nstate-based environmental goals, such as electric uƟlity decarbonizaƟon and renewable porƞolio \nstandards. Having dedicated voice for legislaƟve perspecƟves in PJM governance will enhance regional \nprogress to overcome the challenges of our Ɵme.   \nI echo the recommendaƟons of NCEL and implore FERC to take acƟon on their recommendaƟons \nas follows: \n● Establish a formal governance role for a new or exisƟng organizaƟon represenƟng state \ninterests, including legislators. This role could be based on the “direcƟon to ﬁle” and regional \npolicy funcƟons exercised by state enƟƟes in other regions, such as the RSC in SPP or ISO-NE’s \nNESCOE. \n● Provide a seat on the NominaƟng CommiƩee for the PJM Board to a representaƟve from the \nstates. \n● Modify the Board makeup requirements to provide two addiƟonal seats, including a seat to \nrepresent the interests of states and a seat to represent the interests of end-use customers.  \n● Amend PJM’s foundaƟonal operaƟng agreement to codify an explicit public interest mandate \nthat requires PJM to balance system reliability and market eﬃciency with public interest \nobjecƟves."},{"page":3,"startToken":735,"endToken":990,"text":"● Strengthen transparency by allowing designated representaƟves of PJM state governments to \naƩend Liaison CommiƩee meeƟngs. \n \nThe pracƟcal modiﬁcaƟons and adjustments to the PJM stakeholder process, as oﬀered by NCEL, \nto ensure eﬀecƟve and transparent decision-making are good policy suggesƟons: \n● Record all PJM Stakeholder MeeƟngs and make these recordings publicly available.  \n● Implement sector-weighted voƟng in the Standing CommiƩees to align commiƩee work with \nthe ulƟmate stakeholder decision-making process. \n● Publish and disseminate records of voƟng results taken in all PJM commiƩees, task forces, and \nsimilar standing, ad-hoc, or issue-speciﬁc stakeholder groups. \n● Allow media to be present in all stakeholder process meeƟngs. \n● Require cost impact analyses to be presented during the First Read at the Senior Standing \nCommiƩees. \n \nThese governance reforms would help ensure that PJM's decision-making beƩer reﬂects the \nprioriƟes of the states it serves, while bringing more transparency and accountability to a system my \nconsƟtuents – and all Virginians – depend on. Aﬀordability and grid modernizaƟon are challenges too big \nfor any one enƟty to tackle alone — they require all of us at the table. I and the Energy Commission of \nVirginia remain commiƩed to working with PJM, FERC and other key stakeholders to bring down costs \nand deliver the reliable power Virginians expect. \nVery Truly Yours, \n \n \n \nSenator Scott A. Surovell \n34th District \nChair, Energy Commission of Virginia \n \ncc: \nGovernor Abigail D. Spanberger  \nSenator Brian J. Feldman, MD, 15th District \nSenator R. Creigh Deeds, Chair, Senate Commerce and Labor CommiƩee \nDelegate Jeion A. Ward, Chair, House Labor and Commerce CommiƩee \nHonorable Kelsey Baggot, Chair, Virginia State CorporaƟon Commission"}],"sections":[{"p":1,"at":0,"title":"Pages 1 to 3","method":"page range","endPage":3,"endAt":1801,"startToken":0,"endToken":990}]}