{"document":{"slug":"rec-20260728-5072","title":"Motion for Extension of Time for Specified Compliance Requirements and Request for Expedited Treatment of PJM Interconnection, L.L.C","issued":"2026-07-28","accession":"20260728-5072","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"PJM Interconnection, L.L.C.","kind":"motion","file":"sources/filings/text/20260728-5072_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260728-5072","tier":"record","sha256":"6ba8341a67967cf13354abc2b3251c6f80c35099a5ca2d5692d13af2fb499069","pages":10,"tokens":2419,"emptyPages":[],"textThemes":["study","colo","procedure"]},"pages":[{"page":1,"startToken":0,"endToken":201,"text":"UNITED STATES OF AMERICA \nBEFORE THE  \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et al. \nLarge Loads Co-Located at Generating Facilities  \nConstellation Energy Generation, LLC \nv.  \nPJM Interconnection, L.L.C. \nPJM Interconnection, L.L.C. \nDocket Nos. EL25-49-002 \nEL25-49-000 \n \nAD24-11-001 \n \n \nEL25-20-001 \n(consolidated) \n \n \n \n \nER26-1479-000 \n \n \n \nMOTION FOR EXTENSION OF TIME FOR SPECIFIED COMPLIANCE \nREQUIREMENTS AND REQUEST FOR EXPEDITED TREATMENT OF PJM \nINTERCONNECTION, L.L.C.  \nPursuant to Rule 212 of the Federal Energy Regulatory Commission’s \n(“Commission”) Rules of Practice and Procedure,1 PJM Interconnection, L.L.C. (“PJM”) \nmoves for an extension of time to comply with certain requirements in the Order on \nRehearing, Clarification, Compliance Filing, and Paper Hearing issued June 18, 2026 \n(“Compliance Order”).2  Specifically, PJM requests that the Commission grant a ninety-\nday extension for certain compliance requirements (noted below) that implicate directives \nin the show cause order on large loads issued the same day (“Large Load Order”).3  If the \nrequested relief is granted, PJM will still make a compliance filing on August 17, 2026, \n \n1 18 C.F.R. § 385.212. \n2 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209 (2026). \n3 See PJM Interconnection, L.L.C., 195 FERC ¶ 61,211 (2026)."},{"page":2,"startToken":201,"endToken":467,"text":"2 \naddressing several important compliance directives, including relating to Interim Network \nIntegration Transmission Service (“NITS”).  However, many of the changes to PJM’s Open \nAccess Transmission Tariff (“Tariff”) required by the Compliance Order will serve as the \nfoundation for the Large Load Order’s reforms.  To ensure that certain compliance changes \nin this proceeding align with the directives in the Large Load Order in a holistic fashion, \nPJM must consider these related requirements together.  This requires additional time.  PJM \nhas developed a plan to finalize the foundational portions of the compliance filing in this \nproceeding in conjunction with the development of a Federal Power Act (“FPA”) \nsection 2054 filing to respond to the Large Load Order.  To allow time for stakeholder \nengagement and feedback on the changes, PJM plans to make the resulting filings by early \nto mid-November.   \nAbsent further Commission action, the entirety of PJM’s compliance filing is due \nAugust 17, 2026.  Accordingly, PJM is moving to hold the Large Load proceeding in \nabeyance for ninety days5 and seeking a ninety-day extension of certain directives in the \nCompliance Order, while pledging to submit a partial compliance filing on August 17, \n2026 to reflect PJM’s continuous and ongoing efforts to implement the Commission’s \nreforms.  PJM requests the Commission grant expedited treatment to act on this motion \nwithin ten days, by August 6, 2026, in the interest of regulatory certainty.  \n \n4 16 U.S.C. § 824d. \n5 PJM Interconnection, L.L.C., Motion of PJM Interconnection, L.L.C. to Hold Proceeding in Abeyance and \nRequest for Shortened Answer Period and Expedited Treatment, Docket No. EL26-67-000 (July 28, 2026)."},{"page":3,"startToken":467,"endToken":736,"text":"3 \nI. \nBACKGROUND \nA. \nCo-Located Load Proceeding \nThe Commission initiated this proceeding on December 18, 2025.6  Following \nmultiple compliance filings and paper hearing submissions, the Commission issued the \nCompliance Order on June 18, 2026 accepting most of PJM’s proposed Tariff changes, but \ndirecting PJM to make a number of additional Tariff changes within sixty days.7  Among \nother changes, the Compliance Order directed PJM to  clarify the study process for \ninterconnecting Co-Located Loads,8 make new transmission services available to \ncustomers with behind the meter generation (“BTMG”) that are willing and able to limit \ntheir withdrawals from the transmission system,9 and clarify the operational requirements \nfor customers taking service on behalf of large loads.10 \nB. \nLarge Load Proceeding \nAlso on June 18, 2026, the Commission initiated a new show cause proceeding via \nthe Large Load Order.11  The Large Load Order found that several aspects of PJM’s Tariff \nappeared unjust and unreasonable due to the lack of specific procedures for integrating \nlarge loads, including a lack of procedures for interconnection studies, processing \ntransmission service requests, and constructing network upgrades without cost shifting.12  \nThe Large Load Order also found PJM’s Tariff appeared to be unjust and unreasonable due \n \n6 PJM Interconnection, L.L.C., 193 FERC ¶ 61,217 (2025). \n7 See, e.g., Compliance Order at P 280 (directing PJM to revise Tariff to specify what information about \nnecessary studies will be available in the manuals). \n8 Id. at PP 370-74. \n9 Id. at P 91. \n10 See id. at P 65. \n11 Id. at P 1. \n12 Large Load Order at PP 60, 65, 77."},{"page":4,"startToken":736,"endToken":1019,"text":"4 \nto a lack of transmission service options for customers serving large loads that are willing \nand able to limit their withdrawals from the transmission system.13  Additionally, the Large \nLoad Order found that PJM’s Tariff appeared to be unjust and unreasonable due to a lack \nof mechanisms to ensure that costs are not shifted between transmission customers.14 \nTo address these issues, the Large Load Order directed PJM to make two \ncompliance filings.15  First, the Large Load Order directed PJM to submit an informational \nfiling within thirty days to explain how PJM intends to ensure that it has adequate \ngeneration to serve existing and new large loads.16  Second, the Large Load Order directed \nPJM to submit within sixty days a compliance filing to explain whether its Tariff remains \njust and reasonable in light of the issues identified in the order or to propose Tariff changes \nthat would remedy the identified concerns.17  The Commission noted that it would entertain \nrequests to hold the show cause proceedings in abeyance if PJM demonstrated a plan to \npropose changes pursuant to FPA section 205.18 \nC. \nOverlap Between Proceedings \nThe compliance changes directed in this proceeding significantly relate to or \noverlap with the directives in the Large Load Order in three major areas: expansion of new \ntransmission services, study procedures, and operational requirements.   \nFirst, the Compliance Order and the Large Load Order both directed PJM to expand \nthe availability of new transmission services.  The Compliance Order directed PJM to make \n \n13 Id. at P 86.  \n14 Id. at P 77. \n15 Id. at ordering paras. (A) & (B). \n16 Id. at P 4. \n17 Id. at ordering para (B). \n18 Id. at P 39."},{"page":5,"startToken":1019,"endToken":1333,"text":"5 \nthe new transmission services available to customers taking service on behalf of load with \nBTMG that are willing and able to limit their withdrawals from the transmission system.19 \nTo accomplish this, the Commission directed PJM to either add a definition of “Eligible \nLoad” that encompasses both customers serving both Co-Located Load and load with \nBTMG or to propose comparable Tariff revisions.20  At the same time, the Large Load \nOrder directed PJM to propose Tariff changes to make those same new transmission \nservices available to flexible large loads or explain why it need not do so.21  Thus, PJM \nwill consider the potential impacts on flexible large loads in crafting Tariff revisions to \nexpand the new transmission services to customers serving load with BTMG. \nSecond, the Compliance Order and the Large Load Order both directed PJM to \nenhance its study procedures.  The Compliance Order directed PJM to revise the Tariff to \nadopt more detailed study procedures for firm contract demand transmission service and \nnon-firm contract demand transmission service that mirror existing cluster study \nprocedures.22  Similarly, in the Large Load Order, the Commission directed PJM to either \npropose study procedures for customers requesting service on behalf of large loads that can \nidentify necessary network upgrades within 60-90 days or explain why it need not do so.23  \nThus, PJM will determine how to integrate these large loads into its study processes.  \nThird, the Compliance Order directed PJM to revise the Tariff to provide additional \ndetail regarding the operational requirements and necessary control technologies to be \n \n19 Compliance Order at P 91 (directing PJM to expand new transmission services to customers serving those \nwith BTMG that are willing and able to limit withdrawals from the transmission system). \n20 Compliance Order at P 91. \n21 Large Load Order at P 87. \n22 Compliance Order at P 370. \n23 Large Load Order at P 63."},{"page":6,"startToken":1333,"endToken":1622,"text":"6 \nemployed for customers taking new transmission services on behalf of Eligible Load.24  \nSimilarly, the Large Load Order directed PJM to evaluate what operational requirements \nare appropriate for customers taking service on behalf of large loads.25  Thus, PJM must \neither set operational requirements that encompass the various categories of co-located and \nlarge loads or determine what operational requirements are appropriate for large loads \nspecifically to ensure treatment that is not unduly discriminatory.  \nD. \nCompliance Plan \nPJM will submit a partial compliance filing on August 17, 2026 in this docket to \nreflect its ongoing efforts to implement these important reforms.  Nevertheless, PJM plans \nto address the related portions of the Compliance Order’s directives and the response to the \nLarge Load Order in a coordinated suite of filings (i.e., a compliance filing for the \nCompliance Order and an FPA section 205 filing to address the Large Load Order reforms).  \nBecause a number of the changes in this proceeding will either overlap with or serve as the \nfoundation for the Large Load FPA section 205 changes, PJM intends to develop the \nchanges together to ensure a consistent, unified approach.   \nPJM has or will be scheduling stakeholder engagement sessions to both share and \nreceive feedback on PJM’s proposal (including aspects of the co-located load compliance \nfiling) on July 30, 2026, August 18, 2026, and September 16, 2026.26  PJM proposes to \nsubmit its remaining compliance filing in this docket at the same time as the FPA section \n205 filing responding to the Large Load Order to present a holistic and unified solution to \nthe various reforms.   \n \n24 Compliance Order at PP 482, 541. \n25 Large Load Order at P 64. \n26 If additional sessions are necessary, PJM would schedule them."},{"page":7,"startToken":1622,"endToken":1891,"text":"7 \nII. \nMOTION FOR EXTENSION OF TIME  \nThe Commission may extend compliance deadlines for good cause.27  Here, good \ncause exists to grant a ninety-day extension of the compliance requirements specified \nherein to allow PJM to develop the remaining aspects of its Co-Located Load compliance \nfiling in conjunction with the FPA section 205 filing being developed in response to the \nLarge Load Order.   \nPJM has worked to address the Compliance Order’s directives with all due speed \nand will be in a position to comply with many of them within sixty days.  For example, \nPJM will file Tariff changes addressing many important issues in the Compliance Order to \nprovide immediate certainty to developers and commence physical interconnection-related \nstudies of proposed Co-Located Load configurations.  In particular, by August 17, 2026, \nPJM will submit a compliance filing that addresses Commission-directed changes to: \ncertain defined terms in Tariff, Part I; certain terms for NITS pursuant to Tariff, Part III; \nadditional details regarding the Necessary Study process that will be specified in the \nmanuals; and the provision of interim NITS.28     \nGiven the interrelated nature of a number of the other requirements in the \nCompliance Order and Large Load Order, a coordinated approach on the remaining \ncompliance matters is appropriate for consistency and efficiency.  As noted above, both \norders require PJM to propose Tariff changes to address the study procedures to \ninterconnect Co-Located/Large Loads, make new transmission services available for \ncustomers that are willing and able to limit their withdrawals, and specify operational \n \n27 See 18 C.F.R. § 385.2008. \n28 See, e.g., Compliance Order at PP 91, 102-103, 264, 307."},{"page":8,"startToken":1891,"endToken":2211,"text":"8 \nrequirements for Co-Located/Large Loads.29  PJM proposes to address these interrelated \nrequirements in a suite of filings to be submitted by early to mid-November following a \nperiod of intensive stakeholder engagement and feedback.  To allow time for that process, \nPJM moved to hold the proceedings on the Large Load Order in abeyance for a period of \nninety days.30  To allow for a coordinated approach, PJM is requesting the same ninety-\nday extension of the related requirements here for good cause shown (including PJM’s \npledge to submit a partial compliance filing by August 17, 2026, as noted above).    \nIII. \nREQUEST FOR EXPEDITED TREATMENT  \nPJM respectfully requests that the Commission consider this motion on an \nexpedited basis to act on this request within ten days of filing, by August 6, 2026.  Absent \nCommission action, PJM’s filings for both the Compliance Order and the Large Load \nOrder are due August 17, 2026.  PJM has already moved for the Commission to hold the \nLarge Load Order proceeding in abeyance for ninety days and to act on that request by \nAugust 6, 2026.  Given the impending deadline and PJM’s plans for combined stakeholder \nengagement, PJM requests that the Commission rule on this motion within ten days, by \nAugust 6, 2026, in the interest of regulatory certainty.   \n \n29 Compliance Order at PP 370-74 (directing additional Tariff changes regarding the study procedures for \nCo-Located Loads); Large Load Order at P 86 (directing Tariff changes to make transmission services \navailable to those willing and able to limit withdrawals from the transmission system); Compliance Order at \nP 91 (directing PJM to expand new transmission services to customers serving those with BTMG that are \nwilling and able to limit withdrawals from the transmission system). \n30 PJM Interconnection, L.L.C., Motion of PJM Interconnection, L.L.C. to Hold Proceeding in Abeyance and \nRequest for Shortened Answer Period and Expedited Treatment, Docket No. EL26-67-000 (July 28, 2026)."},{"page":9,"startToken":2211,"endToken":2346,"text":"9 \nIV. \nCONCLUSION  \nFor the reasons stated above, PJM requests the Commission (i) grant a ninety-day \nextension of time for the specified compliance obligations in the Compliance Order and \n(ii) expeditiously act on this motion within ten days, by August 6, 2026. \nRespectfully submitted, \n/s/ Ruth M. Porter \n \nCraig Glazer \nVice President – Federal Government Policy \nPJM Interconnection, L.L.C. \n1200 G Street, NW, Suite 600 \nWashington, DC 20005 \n(202) 423-4743 \ncraig.glazer@pjm.com \nWendy B. Warren \nRuth M. Porter \nWRIGHT & TALISMAN, P.C. \n1200 G Street, NW, Suite 600 \nWashington, DC 20005 \n(202) 393-1200 \nwarren@wrightlaw.com \nporter@wrightlaw.com \nMark J. Stanisz \nAssociate General Counsel \nPJM Interconnection, L.L.C. \n2750 Monroe Blvd. \nAudubon, PA 19403 \n(610) 666-8800 \nmark.stanisz@pjm.com \n \n \n \n \n \nCounsel for \nPJM Interconnection, L.L.C. \n \nJuly 28, 2026"},{"page":10,"startToken":2346,"endToken":2419,"text":"CERTIFICATE OF SERVICE  \n \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary in this proceeding. \nDated at Washington, DC, this 28th day of July 2026. \n/s/ Ruth M. Porter \n \nRuth M. Porter \nWRIGHT & TALISMAN, P.C.  \n1200 G Street NW, Suite 600  \nWashington, DC 20005-3898  \n(202) 393-1200  \nporter@wrightlaw.com \n \nAttorney for PJM Interconnection, L.L.C."}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":3,"startToken":0,"endToken":468},{"p":3,"at":3,"title":"I. BACKGROUND","method":"printed heading","endPage":3,"endAt":19,"startToken":468,"endToken":470},{"p":3,"at":19,"title":"A. Co-Located Load Proceeding","method":"printed heading","endPage":3,"endAt":790,"startToken":470,"endToken":584},{"p":3,"at":790,"title":"B. Large Load Proceeding","method":"printed heading","endPage":4,"endAt":1122,"startToken":584,"endToken":921},{"p":4,"at":1122,"title":"C. Overlap Between Proceedings","method":"printed heading","endPage":6,"endAt":520,"startToken":921,"endToken":1407},{"p":6,"at":520,"title":"D. Compliance Plan","method":"printed heading","endPage":7,"endAt":3,"startToken":1407,"endToken":1623},{"p":7,"at":3,"title":"II. MOTION FOR EXTENSION OF TIME","method":"printed heading","endPage":8,"endAt":618,"startToken":1623,"endToken":1991},{"p":8,"at":618,"title":"III. REQUEST FOR EXPEDITED TREATMENT","method":"printed heading","endPage":9,"endAt":3,"startToken":1991,"endToken":2212},{"p":9,"at":3,"title":"IV. CONCLUSION","method":"printed heading","endPage":10,"endAt":0,"startToken":2212,"endToken":2346},{"p":10,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":10,"endAt":457,"startToken":2346,"endToken":2419}]}