{"document":{"slug":"rec-20260803-5070","title":"Post-Conference Comments of Persistence Analytics Group LLC re the PJM Governance and Stakeholder Reforms","issued":"2026-08-03","accession":"20260803-5070","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"Individual No Affiliation","kind":"comments","file":"sources/filings/text/20260803-5070_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260803-5070","tier":"record","sha256":"e5967fee79e79837741afd47a3e3ee14f521c0094b9ccc5790552d9fbfacde5b","pages":5,"tokens":1042,"emptyPages":[],"textThemes":[]},"pages":[{"page":1,"startToken":0,"endToken":52,"text":"PUBLIC SUBMISSION\nPOST-CONFERENCE COMMENTS\nFederal Energy Regulatory Commission\nDocket No. AD26-7-000\nProceeding\nPJM Governance and Stakeholder Process Reforms\nSubmitted by\nPersistence Analytics Group LLC\nPrincipal\nNeil P. Osnato, Founder\nDate\nAugust 3, 2026\nGOVERNANCE MUST PRODUCE\nACCOUNTABILITY.\nASSUMPTIONS MUST BE VERIFIED BEFORE\nCOSTS ARE IMPOSED.\nInfrastructure Assumption Verification(TM) | Decision Assurance(TM)"},{"page":2,"startToken":52,"endToken":296,"text":"PERSISTENCE ANALYTICS GROUP LLC\nFERC Docket No. AD26-7-000 | PUBLIC\nPost-Conference Comments on PJM Governance and Stakeholder Reform\nPage 2\nCOVER LETTER\nFederal Energy Regulatory Commission\n888 First Street, NE\nWashington, DC 20426\nRe: Docket No. AD26-7-000 - PJM Governance and Stakeholder Process Reforms\nCommissioners:\nPersistence Analytics Group LLC respectfully submits these post-conference comments in response to the\nCommission's invitation for bold, actionable reforms to PJM Interconnection, L.L.C. governance and stakeholder\nprocesses.\nThe Commission should not accept governance reform that merely rearranges representation, modifies voting\nmechanics, or creates another layer of consultation. PJM is confronting decisions with system-wide financial and\nreliability consequences. Its governance must therefore establish clear responsibility for the evidence underlying\nthose decisions, the assumptions embedded in them, and the costs imposed when those assumptions fail.\nTHE OPERATING RULE IS SIMPLE:\nNO MATERIAL PLANNING ASSUMPTION WITHOUT A NAMED OWNER, A\nDOCUMENTED EVIDENTIARY BASIS, AND A PUBLIC ACCOUNTABILITY\nPATH.\nThis standard is especially urgent as PJM evaluates unprecedented large-load growth, transmission needs,\ncapacity procurement, interconnection readiness, and cost allocation. Announced demand is not the same as\nexecutable demand. Executable demand is not the same as durable demand. Governance that does not force\nthose distinctions into the decision record is not governance adequate to the risk.\nThe attached comments propose a direct accountability architecture: verified load classifications, assumption\nownership, decision-grade disclosure, independent challenge rights, full electrical cost-causation review, formal\nescalation, and measurable implementation deadlines.\nRespectfully submitted,\nNeil P. Osnato\nFounder\nPersistence Analytics Group LLC"},{"page":3,"startToken":296,"endToken":614,"text":"PERSISTENCE ANALYTICS GROUP LLC\nFERC Docket No. AD26-7-000 | PUBLIC\nPost-Conference Comments on PJM Governance and Stakeholder Reform\nPage 3\nPOST-CONFERENCE COMMENTS\nI. THE COMMISSION SHOULD DEFINE THE OUTCOME BEFORE REFORMING THE\nPROCESS\nThe purpose of PJM governance is not stakeholder participation for its own sake. The purpose is to produce\ntimely, evidence-based, reviewable decisions that preserve reliability, assign costs fairly, and withstand scrutiny\nafter capital is committed.\nAny reform package should be judged against one question: Does it make a responsible party answerable for\nthe assumptions that drive a material PJM decision? If the answer is no, the reform is procedural, not\noperational.\nII. PJM MUST CREATE A FORMAL ASSUMPTION-ACCOUNTABILITY RECORD\nFor each material planning, market, procurement, or cost-allocation decision, PJM should publish a concise\nassumption-accountability record identifying:\n• The decision owner: the PJM officer or committee accountable for the final recommendation.\n• The critical assumptions: load, timing, persistence, interconnection readiness, financing, operating profile,\nflexibility, retirement, supply, and cost-allocation assumptions.\n• The evidence: what was submitted, by whom, when it was validated, and what remains unverified.\n• The consequence range: the reliability, capital, market, and customer-cost outcomes if the assumptions are\nwrong.\n• The dissent and escalation path: how a material evidentiary challenge is preserved and elevated before\nimplementation.\nIII. LARGE-LOAD FORECASTS REQUIRE DECISION-GRADE CLASSIFICATION\nPJM should stop treating projected load as a single category. At minimum, large-load additions should be\nseparated into the following stages:\nClassification\nRequired meaning\nAnnounced\nPublicly stated or submitted, but not yet supported by enforceable commercial, site,\nequipment, power-delivery, and schedule evidence.\nCommitted\nSupported by defined financial obligations, deposits, contracts, or equivalent\ncommitments.\nElectrically executable\nInterconnection path, upstream reinforcement, equipment, permitting, and\nenergization dependencies are sufficiently established.\nOperationally durable\nThe expected operating profile, persistence, ramp behavior, curtailment capability,\nand withdrawal risk have been evaluated.\nPJM should disclose which classification supports each planning decision and prohibit a lower-confidence\nclassification from being presented as if it were a higher-confidence one."},{"page":4,"startToken":614,"endToken":951,"text":"PERSISTENCE ANALYTICS GROUP LLC\nFERC Docket No. AD26-7-000 | PUBLIC\nPost-Conference Comments on PJM Governance and Stakeholder Reform\nPage 4\nIV. COST CAUSATION MUST FOLLOW THE FULL ELECTRICAL CONSEQUENCE\nDirect customer funding of interconnection facilities can be appropriate, but governance fails if review ends at the\npoint of interconnection. A 1 GW to 3 GW customer can alter flows, contingencies, substation configuration, local\nreliability needs, and future expansion options across the broader network.\nPJM must therefore distinguish, on the record:\n• facilities uniquely required by the customer;\n• upstream reinforcements materially caused by the customer;\n• upgrades that produce measurable regional benefits; and\n• baseline needs that would exist without the customer.\nA shallow cost-causation methodology can socialize upstream costs even when the customer directly funds\nfacilities near the site. Governance reform must prevent that outcome.\nV. MATERIAL EVIDENTIARY CHALLENGES NEED INDEPENDENT ESCALATION\nA stakeholder process cannot police itself when voting power, commercial interests, and institutional incentives\nare embedded in the same decision. PJM should establish a formal independent review channel for disputes\ninvolving:\n• load forecast durability or readiness;\n• material cost-causation disputes;\n• use of confidential evidence that cannot be meaningfully tested;\n• assumption changes introduced after stakeholder review; and\n• decisions where the downside risk is transferred to customers who did not create it.\nThe review channel should have authority to require a written response, preserve minority evidence, and refer\nunresolved matters to the PJM Board or the Commission on a defined timetable.\nVI. THE SEPTEMBER DISPUTE-RESOLUTION PROCESS MUST END WITH\nDELIVERABLES\nThe Commission's facilitated process should not conclude with generalized principles. It should produce a public\nimplementation matrix containing:\n• Action: the exact reform to be implemented.\n• Owner: the accountable PJM body or officer.\n• Deadline: a fixed date, not an open-ended commitment.\n• Evidence of completion: tariff filing, manual revision, reporting protocol, or governance document.\n• Commission checkpoint: the date on which progress will be reviewed publicly.\nPJM DOES NOT NEED MORE PROCESS WITHOUT CONSEQUENCE.\nIT NEEDS GOVERNANCE THAT CAN IDENTIFY THE ASSUMPTION, NAME\nTHE OWNER, TEST THE EVIDENCE, TRACE THE COST, AND CORRECT\nTHE DECISION."},{"page":5,"startToken":951,"endToken":1042,"text":"PERSISTENCE ANALYTICS GROUP LLC\nFERC Docket No. AD26-7-000 | PUBLIC\nPost-Conference Comments on PJM Governance and Stakeholder Reform\nPage 5\nVII. CONCLUSION\nThe Commission should require PJM to convert governance reform into a durable accountability system.\nRepresentation matters. Voting matters. But neither is sufficient unless the resulting decisions are anchored to\nverified evidence, assigned ownership, transparent cost causation, and enforceable implementation.\nPersistence Analytics Group LLC respectfully requests that the Commission incorporate these accountability\nrequirements into the next phase of Docket No. AD26-7-000.\nRespectfully submitted,\nNeil P. Osnato\nFounder\nPersistence Analytics Group LLC"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":3,"endAt":166,"startToken":0,"endToken":317},{"p":3,"at":166,"title":"I. THE COMMISSION SHOULD DEFINE THE OUTCOME BEFORE REFORMING THE","method":"printed heading","endPage":3,"endAt":712,"startToken":317,"endToken":399},{"p":3,"at":712,"title":"II. PJM MUST CREATE A FORMAL ASSUMPTION-ACCOUNTABILITY RECORD","method":"printed heading","endPage":3,"endAt":1532,"startToken":399,"endToken":500},{"p":3,"at":1532,"title":"III. LARGE-LOAD FORECASTS REQUIRE DECISION-GRADE CLASSIFICATION","method":"printed heading","endPage":4,"endAt":141,"startToken":500,"endToken":633},{"p":4,"at":141,"title":"IV. COST CAUSATION MUST FOLLOW THE FULL ELECTRICAL CONSEQUENCE","method":"printed heading","endPage":4,"endAt":956,"startToken":633,"endToken":745},{"p":4,"at":956,"title":"V. MATERIAL EVIDENTIARY CHALLENGES NEED INDEPENDENT ESCALATION","method":"printed heading","endPage":4,"endAt":1729,"startToken":745,"endToken":850},{"p":4,"at":1729,"title":"VI. THE SEPTEMBER DISPUTE-RESOLUTION PROCESS MUST END WITH","method":"printed heading","endPage":5,"endAt":141,"startToken":850,"endToken":970},{"p":5,"at":141,"title":"VII. CONCLUSION","method":"printed heading","endPage":5,"endAt":714,"startToken":970,"endToken":1042}]}