{"document":{"slug":"rec-20260818-5146","title":"Motion for Leave to Answer and Answer of Vistra Corp. to Northern Virginia Electric Cooperative, Inc.'s 07/29/2026 Motion for Clarification of the…","issued":"2026-08-18","accession":"20260818-5146","docket":"EL25-49-000","group":"PJM co-location compliance","filer":"Vistra Corp.","kind":"rehearing request","file":"sources/filings/text/20260818-5146_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260818-5146","tier":"record","sha256":"61b0834eda5f4ca9c6a152461bf7d65f518d4ae588e8607fd74b1eb2ce037fe6","pages":8,"tokens":2140,"emptyPages":[],"textThemes":[]},"pages":[{"page":1,"startToken":0,"endToken":220,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C., et al. \nLarge Loads Co-Located at Generating Facilities \nConstellation Energy Generation, LLC \nv. \nPJM Interconnection, L.L.C. \nPJM Interconnection, L.L.C. \n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\n)\nDocket Nos. EL25-49-002 \n                     EL25-49-000 \nDocket No. AD24-11-001 \nDocket No. EL25-20-001 \n                  (consolidated) \nDocket No. ER26-1479-000 \nMOTION FOR LEAVE TO ANSWER AND ANSWER OF VISTRA CORP. TO \nNOVEC’S MOTION FOR CLARIFICATION \nPursuant to Rules 212 and 213 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“Commission” or “FERC”),1 Vistra Corp. (“Vistra”) hereby moves to \nanswer and answers the pleading that Northern Virginia Electric Cooperative, Inc. (“NOVEC”) \nfiled on July 29, 2026,2 in the above-captioned proceeding.  Although styled as a motion for \nclarification, NOVEC’s motion is in reality an impermissible, out-of-time request for rehearing \nbecause it contests determinations the Commission made in its June 18, 2026 order in the above-\ncaptioned dockets (“June 2026 Order”).3  Because NOVEC’s pleading was filed after the statutory \ndeadline for requests for rehearing, it must be denied as untimely.  \n1 18 C.F.R. §§ 385.212, 385.213. \n2 PJM Interconnection, L.L.C., Motion for Clarification of NOVEC, Docket No. EL25-49-000 (filed July 29, \n2026) (“NOVEC Filing”). \n3 PJM Interconnection, L.L.C., 195 FERC ¶ 61,209 (2026) (“June 2026 Order”)."},{"page":2,"startToken":220,"endToken":657,"text":"-2- \nI.\nMOTION FOR LEAVE TO ANSWER \nAlthough the Commission’s procedural rules generally do not allow answers to requests \nfor rehearing, the Commission may permit them for good cause.4  The Commission frequently \naccepts answers that clarify the issues before the Commission, ensure a complete record, or \notherwise assist the Commission in its decision-making.5  Vistra respectfully requests that the \nCommission accept this answer to clarify that NOVEC’s motion is in fact, a request for rehearing.  \nII.\nANSWER \nA. The Commission should reject NOVEC’s motion as an untimely request for \nrehearing. \nAlthough NOVEC styles its filing as a motion for clarification, the substance of the filing \ndirectly contests the merits of the Commission’s June 2026 Order, which renders the pleading a \nrequest for rehearing.  The Commission categorizes pleadings based on their “substance,” not \n“party-bestowed title.”6  As NOVEC acknowledges, the Commission “concluded” in the June \n2026 Order that the record “[did] not adequately substantiate the need for an additional [Grid \nReliance Charge] at this time” or provide sufficient information on “how such a charge should be \n4 18 C.F.R. § 385.213(a)(2) (“An answer may not be made to a protest, an answer, a motion for oral argument, or \na request for rehearing, unless otherwise ordered by the decisional authority.”). \n5 See, e.g., PJM Interconnection, L.L.C., 182 FERC ¶ 61,073, at P 13 (2023) (accepting answers to answers that \n“provided information that assisted us in our decision-making process.”); New Fortress Energy LLC, \n174 FERC ¶ 61,207, at P 7 (2021) (accepting answers because they provided information that assisted the \nCommission’s decision-making process); Alaska Gasline Dev. Corp., 171 FERC ¶ 61,134, at P 7 (2020) (accepting \nanswers that “clarify the concerns raised and provide information that has assisted in our decision making.”); Saltville \nGas Storage Co., L.L.C., 164 FERC ¶ 61,212, at P 2 n.6 (2018) (accepting answers that “assist the Commission in \nunderstanding the issues raised, and will ensure a complete record.”). \n6 San Diego Gas & Elec. Co. v. Sellers of Energy & Ancillary Servs., 133 FERC ¶ 61,014, at P 15 (2010) (“While \nPG&E has styled this filing as a motion for clarification, we are not obligated to accept a filing solely on the basis of \nits party-bestowed title.  Instead, we examine the substance of the pleading.  We find that PG&E’s motion cannot be \ninterpreted to be a motion for clarification because PG&E is not asking that we clarify any previous Commission \norder.  Rather, we find PG&E’s motion to be an untimely attempt by PG&E to seek rehearing of a prior Commission \norder.”)"},{"page":3,"startToken":657,"endToken":1034,"text":"-3- \ncalculated and assessed.”7  The Commission was crystal clear that “experience with the actual use \nof these new transmission services” is necessary to create the record the Commission would need \nto support any revised proposal for a Grid Reliance Charge.8  In response, NOVEC “respectfully \ndisagrees that the record does not substantiate the need for an additional charge.”9  That \n“disagree[ment]” directly contradicts the Commission’s determination on both the now-rejected \nGrid Reliance Charge and the evidence on which that determination was based.  NOVEC asks the \nCommission to “clarify” that it did not mean what it said in determining that “experience with the \nactual use” of the new transmission services is a necessary prerequisite for any future proposals \nsimilar to the Grid Reliance Charge.10  Disagreement with clear findings is not grounds for \nclarification.11  Rather, it is grounds for requesting rehearing, which NOVEC chose not to pursue \nwithin the timeframe allotted by the Federal Power Act. \nFurther, NOVEC mischaracterizes clear Commission statements as ambiguous.  For \nexample, NOVEC argues, “it is not clear what additional support the Commission believes it \nwould have needed to support approval of a rate akin to or serving the purpose of the proposed \nGrid Reliance Charge.”12  On the contrary, the Commission was quite explicit:  \n7 NOVEC Filing at 4 (quoting June 2026 Order at P 455). \n8 June 2026 Order at PP 455-456. \n9 NOVEC Filing at 5 (emphasis removed). \n10 NOVEC Filing at 6-7 (“The Commission also suggested that ‘experience with the actual use’ of the new \ntransmission services would help support its understanding . . . NOVEC accordingly requests that the Commission \nclarify that it is not requiring actual experience with the new transmission services before any filing may be submitted \nand that the Commission will consider proposals if filed prior to Eligible Customers actually beginning to serve Co-\nLocated Loads.”). \n11 Supra note 6 (explaining that a motion for clarification must be asking the Commission to clarify a previous \norder); see also Erie Blvd. Hydropower, L.P., 118 FERC ¶ 61,196, at P 11 (2007) (“To the extent that GIPA and \nAdirondack seek clarification or reconsideration, styling an improper request for rehearing as a motion for clarification \nor motion for reconsideration cannot cure its deficiencies.”). \n12 NOVEC Filing at 5."},{"page":4,"startToken":1034,"endToken":1342,"text":"-4- \nIn particular, the record contains insufficient description of the potential nature or \nmagnitude of the cited benefits or the potential costs that transmission providers or \nowners may incur when providing these benefits to Eligible Customers on behalf of Co-\nLocated Loads.  For example, Indicated TOs state that, even where an Eligible Customer \nhas requested FCD or NFCD transmission service for 0 MW, a large Co-Location \nArrangement will still depend on the transmission system for a suite of synchronization \nsupport services, such as stable frequency, inertia, stability services (damping, angle \nstability), fault current capability, and ride-through and protection coordination.  \nHowever, beyond briefly listing such benefits, the record lacks specificity regarding \nwhat these services are, what costs they involve, and how they benefit Eligible \nCustomers on behalf of Co-Located Loads.13\nNOVEC disregards this direct statement of missing evidence as merely a request for “cost \nsupport for the rate itself,” ignoring that the Commission also found a lack of specificity on the \nnature of the services and their benefits.14\nNOVEC’s explains that it “did not seek rehearing on this issue because NOVEC expects \nthat the PJM stakeholder process will result in submission of another proposal for the \nCommission’s consideration.”15  Setting aside the troubling implication that some PJM \nstakeholders might intend to ignore the Commission’s determination on this issue, NOVEC’s \nexplanation cannot rehabilitate its flawed pleading.  Ongoing PJM stakeholder processes have no \nbearing on the statutory deadline for seeking rehearing or other Commission rules of procedure.   \nInstead of filing a timely request for rehearing, NOVEC filed a mislabeled motion for \nclarification 41 days after the June 2026 Order, well outside the statutory requirements for requests \nfor rehearing.  Under Section 313 of the Federal Power Act, requests for rehearing must be made \n13 June 2026 Order at P 455.  \n14 NOVEC Filing at 6. \n15 NOVEC Filing at 5."},{"page":5,"startToken":1342,"endToken":1741,"text":"-5- \nwithin 30 days,16 and courts interpret this as a bright-line rule that even the Commission lacks \ndiscretion to extend.17  The Commission must deny NOVEC’s filing as untimely.18\nB. The Commission’s clear conclusion on the Grid Reliance Charge is correct.  \nLooking past NOVEC’s procedural error, NOVEC is also wrong on the merits.  The \nCommission’s rejection of the Grid Reliance Charge was the right decision.  The proposed Grid \nReliance Charge would have applied equally to customers who use the grid in completely different \nways, from customers that never reserve service to customers that frequently reserve significant \namounts of service.  Non-Firm Contract Demand Transmission Service customers who never \nreserve transmission service to pull energy from the grid and rely on it only for black start and \nregulation services would have been forced to pay for something other than those services.  That \nis not consistent with cost causation principles, and it would have been a departure from the \nCommission’s long-standing policy requiring transmission providers to offer and price ancillary \nservices separately.19\nIn any event, the Commission’s decision to wait until the new transmission services are \nimplemented before considering proposals similar to the Grid Reliance Charge makes sense.  By \nwaiting for evidence of how parties use the new transmission services, the Commission can best \nevaluate whether gaps remain in the new transmission service rate structure.  Vistra’s position is \n16 16 U.S.C. § 825l(a) (“[A] party may apply for a rehearing within thirty days after the issuance of such order.”). \n17 San Diego Gas & Elec. Co. v. Sellers of Energy & Ancillary Servs., 133 FERC ¶ 61,014 at P 20 (“[C]ourts have \nrepeatedly recognized that the Commission has no discretion to extend the deadline.” (citing Boston Gas Co. v. FERC, \n575 F.2d 975 (1st Cir. 1978), Dayton Power & Light Co. v. FPC, 251 F.2d 875, 877 (D.C. Cir. 1957))). \n18 San Diego Gas & Elec. Co. v. Sellers of Energy & Ancillary Servs., 133 FERC ¶ 61,014 at P 20 (“Accordingly, \nthe Commission itself has long held that we lack the authority to consider requests for rehearing filed more than 30 \ndays after the issuance of a Commission order.” (citing Southern California Edison Co., 116 FERC ¶ 61,287, at P 17 \n(2006))). \n19 PJM Interconnection, L.L.C., Response Brief of Vistra Corp., Docket No. EL25-49-000, at 18-23 (filed March \n25, 2026) (“Vistra March 2026 Response Brief”)."},{"page":6,"startToken":1741,"endToken":2004,"text":"-6- \nthat a customer using the grid solely for regulation and black start service is relying very little on \nthe grid.20  If substantial evidence gathered through actual use of the new transmission services \neventually shows otherwise, and PJM is able to demonstrate that the new transmission service rates \nallow certain customers to receive grid services that they do not pay for, the Commission can \nrevisit the issue based on that evidence, consistent with the June 2026 Order.  Unless and until \nreal-world experience with the new transmission services produces such evidence, there is no \nevidence demonstrating that the alleged problem the Grid Reliance Charge was intended to solve \nis even a problem at all—much less that it warrants creation of a new charge for an ill-defined \nservice with no identified benefits.  Accordingly, the Commission should reject NOVEC’s attempt \nto resurrect this issue in this proceeding and should review skeptically any attempt, by NOVEC or \nothers, to relitigate this issue through PJM’s eventual compliance filing in response to the June \n2026 Order. \nIII.\nConclusion \nNOVEC’s motion is in reality an untimely rehearing request that must be rejected as a \nmatter of law.  Rejecting NOVEC’s pleading is also consistent with the June 2026 Order.  Co-\nlocation arrangements are poised to relieve the growing stress of large load growth on the PJM \ngrid, and this docket aims to create clear and readily implementable rules to facilitate those \narrangements.  Vistra urges the Commission to resist NOVEC’s attempt to inject ambiguity into \nunambiguous Commission holdings.  \n[Signatures on Next Page]\n20 Vistra March 2026 Response Brief at 21."},{"page":7,"startToken":2004,"endToken":2083,"text":"-7- \nRespectfully submitted, \n/s/ J. Arnold Quinn         \nJ. Arnold Quinn\nSVP of Regulatory Policy \nAndrew Weinstein\nVice President, FERC Market Policy\nVistra Corp.\n325 7th Street NW\nSuite 520\nWashington, DC 20004\narnie.quinn@vistracorp.com \nandrew.weinstein@vistracorp.com\n________________\nNicholas M. Gladd\nSarah Greenberg\nKatie Mansur\nWilson Sonsini Goodrich & Rosati\n1700 K Street NW\nFifth Floor\nWashington, DC 20006\n(617) 598-7871\nngladd@wsgr.com\nsgreenberg@wsgr.com\ncmansur@wsgr.com\nCounsel for Vistra Corp.\nDated:  August 18, 2026"},{"page":8,"startToken":2083,"endToken":2140,"text":"CERTIFICATE OF SERVICE\nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service lists compiled by the Secretary of the Commission in these \nproceedings. \nDated:  August 18, 2026 \nWashington, D.C. \n/s/ Katie Mansur  \nWilson Sonsini Goodrich & Rosati \n1700 K Street NW \nFifth Floor \nWashington, DC 20006"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":5,"startToken":0,"endToken":221},{"p":2,"at":5,"title":"I. MOTION FOR LEAVE TO ANSWER","method":"printed heading","endPage":2,"endAt":504,"startToken":221,"endToken":296},{"p":2,"at":504,"title":"II. ANSWER","method":"printed heading","endPage":2,"endAt":516,"startToken":296,"endToken":298},{"p":2,"at":516,"title":"A. The Commission should reject NOVEC’s motion as an untimely request for","method":"printed heading","endPage":5,"endAt":183,"startToken":298,"endToken":1373},{"p":5,"at":183,"title":"B. The Commission’s clear conclusion on the Grid Reliance Charge is correct.","method":"printed heading","endPage":6,"endAt":1096,"startToken":1373,"endToken":1913},{"p":6,"at":1096,"title":"III. Conclusion","method":"printed heading","endPage":8,"endAt":0,"startToken":1913,"endToken":2083},{"p":8,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":8,"endAt":365,"startToken":2083,"endToken":2140}]}