{"document":{"slug":"rec-20260820-5015","title":"Motion to Intervene and Protest of Nicholas Max Neal and David Neal, Delaware Standard Offer Service Ratepayers re PJM Interconnection, L.L.C.’s 07/31/2026…","issued":"2026-08-20","accession":"20260820-5015","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"Individual No Affiliation","kind":"protest","file":"sources/filings/text/20260820-5015_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260820-5015","tier":"record","sha256":"371dad7c1b1c4fd24417d6a2f99f7adf1df87928a5a5084896a67bb0aba2eb7e","pages":20,"tokens":5253,"emptyPages":[],"textThemes":["adequacy","registry","cost","study"]},"pages":[{"page":1,"startToken":0,"endToken":229,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \nDocket No. ER26-3380-000 \n \nMOTION TO INTERVENE AND PROTEST OF NICHOLAS MAX NEAL AND \nDAVID NEAL, DELAWARE STANDARD OFFER SERVICE RATEPAYERS \nPursuant to Rules 211 and 214 of the Commission's Rules of Practice and Procedure, 18 C.F.R. \n§§ 385.211, 385.214, and the Commission's notice of August 6, 2026, Nicholas Max Neal (\"the \nCustomer\") and David Neal (\"Mr. Neal\") (together, \"Movants\") respectfully move to intervene in \nthe above-captioned proceeding and protest, in part, the July 31, 2026 filing of PJM \nInterconnection, L.L.C. (\"PJM\") in Docket No. ER26-3380-000 (Accession No. 20260731-5214) \n(the \"RBP Filing\"). \nI. PRELIMINARY STATEMENT \n1. Movants do not ask the Commission to reject the RBP Filing. Movants do not allege \nthat PJM has acted in bad faith. Movants do not contend that the Reliability Backstop \nProcurement (\"RBP\") is unnecessary, or that PJM's resource adequacy concerns are unfounded. \n2. Movants' objection is narrow. PJM asks the Commission to authorize a novel, one-time \nprocurement of capacity commitments of up to fifteen years, extending through the 2042/2043 \nDelivery Year, in a quantity defined by the output of PJM's ELCC/Reserve Requirement Study \nmodel. Yet the RBP Filing does not disclose to the Commission the independent evaluation of \nthat model which PJM itself commissioned and received in December 2025, nor PJM's own"},{"page":2,"startToken":229,"endToken":501,"text":"published sensitivity analyses quantifying how far the model's output moves when identified \nmodeling questions are resolved one way or another. \n3. Those analyses are material because they move the answer in both directions, and by \namounts that are not small relative to the procurement PJM proposes. Movants candidly disclose \nbelow that the single most-discussed correction — crediting increased thermal generating \ncapability in cold weather — is, on PJM's own analysis, outweighed by a separate correction that \nincreases the reserve requirement. That is precisely Movants' point. The relevant fact is not that \nPJM's number is too high. The relevant fact is that PJM's own work product shows the number to \nbe materially unstable across unresolved modeling choices, and PJM proposes to commit \ncustomers to fifteen-year obligations sized by it without placing that instability before the \nCommission. \n4. This concern is not hypothetical. In the 2024/2025 Base Residual Auction, PJM \nproduced an erroneous Locational Deliverability Area Reliability Requirement for the DPL \nSouth Zone — a sub-area of Movants' own distribution zone. The consequence, after the auction \nwas re-run, was an additional $182.8 million in cost for 1.9 percent more capacity. The resulting \nlitigation — brought by, among others, the Delaware Public Service Commission and the \nDelaware Division of the Public Advocate — was remanded to this Commission by the United \nStates Court of Appeals for the District of Columbia Circuit on January 13, 2026, and remains \nunresolved. \n5. The relief Movants request is modest and lies comfortably within the Commission's \nauthority. PJM has itself consented, \"to facilitate Commission approval,\" to the Commission's \nexercise of authority to modify the proposed Tariff and RAA language under NRG Power"},{"page":3,"startToken":501,"endToken":771,"text":"Marketing, LLC v. FERC, where such modification is consistent with the filing's overarching \nobjectives. RBP Filing, transmittal § V, at 130–31. Movants ask the Commission to condition \nacceptance on PJM demonstrating what the procurement target should be once the modeling \nquestions identified by PJM's own consultant are applied — the substitution of a substantiated \nnumber for an unsubstantiated one, and nothing more. \nII. MOTION TO INTERVENE \nA. Identity of Movants \n6. The Customer is a retail electric customer of Delmarva Power & Light Company \n(\"DPL\"), taking service in the State of Delaware within the DPL transmission zone of the PJM \nRegion under DPL Service Classification MGS-S (Medium General Service — Secondary). The \nCustomer has not selected a competitive electricity supplier and therefore receives Standard \nOffer Service (\"SOS\") from DPL. Under DPL's Delaware retail tariff, MGS-S constitutes its own \nFixed Price SOS Customer Group. See DPL, P.S.C. Del. No. 8 — Electric, Rider \"SOS\" § A. \n7. Mr. Neal was the DPL customer of record for the same premises, under the same \nService Classification MGS-S and likewise taking Standard Offer Service, until approximately \nAugust 2025. Mr. Neal is presently obligated, under a written contract with the Customer, to \nreimburse the Customer for the electric charges billed at that premises. Mr. Neal therefore bears \nthe economic burden of the Standard Offer Service charges that are the subject of this protest, \nnotwithstanding that he is no longer the customer of record. \n8. Movants appear on their own behalf and are not represented by counsel. Movants state \nthese facts precisely because the accuracy of a party's asserted interest is the foundation of its \nright to be heard."},{"page":4,"startToken":771,"endToken":1077,"text":"B. Movants' Interest \n9. Rule 214(b)(2) requires that a movant show that it \"has or represents an interest which \nmay be directly affected by the outcome of the proceeding,\" or that \"the movant's participation is \nin the public interest.\" 18 C.F.R. § 385.214(b)(2)(ii), (iii). The Customer satisfies the former \ndirectly. Mr. Neal satisfies it by virtue of his contractual obligation to pay the charges at issue; in \nthe alternative, his participation is in the public interest under Rule 214(b)(2)(iii), as the person \nwho in fact bears the charges described below and as the former customer of record with direct \nknowledge of the premises' service history. Both Movants' participation is in the public interest: \nfew, if any, end-use Delaware Standard Offer Service customers appear in the Commission's \nproceedings at all. \n10. The Customer pays a stated, demand-denominated supply charge for capacity. DPL's \nMGS-S schedule states the Standard Offer Service supply charge as \"Supply Capacity, Energy \nand Ancillary,\" billed at stated Demand Rates of $15.397739/kW and $9.413973/kW, together \nwith stated energy rates. DPL's Rider \"SOS\" § B provides that the Standard Offer Service Rate \n\"will include the costs for energy, capacity and ancillary services as reflected in the awarded \nelectric supply prices for specific services in each year.\" \n11. The mechanism by which PJM capacity prices enter that charge is documented by the \nDelaware Public Service Commission's own technical consultant. In its report on DPL's 2026 \nSOS procurement, Liberty Consulting Group explained that \"[b]idders use $/MW-day capacity \nauction prices to create a capacity component (in $/MWh) of their SOS bid prices,\" and that \n\"[l]ower load factor customer classes ... feel a greater impact from capacity prices than high load \nfactor ... customers since they have fewer MWh over which to spread their demand-based \ncapacity charges.\""},{"page":5,"startToken":1077,"endToken":1372,"text":"12. The Customer's supply is procured and repriced annually. The Liberty report \ndescribes the two-year supply blocks used for the residential and small commercial procurement \ngroup and the single-year blocks used for the Customer's class. Movants note candidly that \nLiberty attributes the 2026 increase in MGS supply prices principally to energy rather than \ncapacity — the capacity prices applicable to the single-year classes \"remained almost \nunchanged\" year over year. Movants accordingly claim no past capacity overcharge. Their \nconcern is prospective: because the Customer's class reprices every year, each successive Base \nResidual Auction — and any change in PJM's reliability requirement or capacity market \noutcomes — is reflected in the wholesale supply prices bid to serve the Customer's class in the \nnext annual procurement. The effect passes to Mr. Neal through the reimbursement obligation \ndescribed in paragraph 7. \n13. PJM's prior reliability-requirement error arose in Movants' own distribution zone. The \ncoalition whose section 206 complaint the D.C. Circuit revived — including the Delaware Public \nService Commission and the Delaware Division of the Public Advocate — is described by that \ncourt as \"the DPL Customers.\" Movants take and pay for service in the DPL zone; their premises \nlies outside the DPL South sub-zone in which that error's direct price effects fell, and they cite \nthe episode for the narrower propositions stated in Part IV below. \n14. Movants do not assert that they will be directly assessed RBP Charges. As discussed \nin Part VII below, PJM's illustrative allocation does not assign RBP UCAP MW to the DPL \nzone, and PJM's 2026 Load Forecast Table B9b shows no load adjustment for that zone. \nMovants' interest arises from the effect of the reliability model, and of this proceeding's \ndisposition of it, on the capacity costs embedded in the wholesale supply prices that set the"},{"page":6,"startToken":1372,"endToken":1614,"text":"Customer's Standard Offer Service rate, and from the matters raised in Part VII concerning the \ndurability of cost allocation over a fifteen-year term. \n15. Whether or not Delaware's state agencies participate in this docket, no other party \nrepresents Movants' particular interest as end-use Standard Offer Service customers who bear the \ncharges described above. Movants' participation will not disrupt this proceeding, will not delay \nit, and imposes no burden on any party. \n16. Movants accordingly request that the Commission grant this motion and accord each \nof them party status. \nIII. BACKGROUND \nA. The RBP Filing \n17. On July 31, 2026, PJM submitted a filing under section 205 of the Federal Power Act \ncaptioned Reliability Backstop Procurement to Address Resource Adequacy Concerns Stemming \nfrom Large Loads, requesting an effective date of September 29, 2026. \n18. PJM proposes a one-time procurement of new capacity, with commitments \"for a \nfixed term of up to 15 years, starting with the 2028/2029 Delivery Year and ending with the \n2042/2043 Delivery Year.\" \n19. PJM proposes to procure a quantity equal to the \"Final RBP Target,\" which \"will \ninitially be based on the observed MW UCAP shortfall in the BRA for PJM's 2028/2029 \nDelivery Year, i.e., the Initial RBP Target.\" The Final RBP Target is derived from the Initial \nRBP Target by subtracting verified Qualifying RBP Offset UCAP MW and specified opt-outs. \nRBP Filing, transmittal at 31–33; proposed Tariff, Attachment DD, §§ 18.1, 18.2."},{"page":7,"startToken":1614,"endToken":1889,"text":"20. The Initial RBP Target is 6,831.3 MW. That figure is the amount by which the \n2028/2029 Base Residual Auction cleared short of the PJM Region Reliability Requirement — \ndefined in PJM's Tariff as the Forecast Pool Requirement multiplied by the Preliminary PJM \nRegion Peak Load Forecast, less the Unforced Capacity Obligations of Fixed Resource \nRequirement Entities. The auction cleared at the market price cap of $325/MW-day. PJM states \nthat the 2027/2028 Base Residual Auction likewise cleared 6,623 MW short, at a cap of \n$333.44/MW-day. \n21. The procurement quantity is therefore not merely informed by PJM's reliability \nmodel. It is defined by it. The Forecast Pool Requirement and the Reliability Requirement are \noutputs of PJM's ELCC/Reserve Requirement Study model. On these facts — where both \nauctions cleared short at the administrative price cap — an error of X MW in the Reliability \nRequirement produces an error of approximately X MW in the Initial RBP Target, and a \ncorresponding error in the quantity of fifteen-year commitments PJM would enter. \nB. PJM's independent evaluation of that model \n22. In December 2025, Energy and Environmental Economics, Inc. (\"E3\") delivered to \nPJM a report titled PJM ELCC / RRS Model Evaluation. E3 states that it \"was retained by PJM to \nindependently assess PJM's Effective Load Carrying Capability / Reserve Requirement Study \nModel ... for alignment with industry best practices in loss-of-load-probability ... modeling,\" and \nnotes that \"[t]he outputs of the ELCC/RRS model are used directly in PJM's capacity market.\" \nThe report is provided as Attachment A hereto. \n23. E3 identified fourteen \"Considerations for Improvement,\" presented \"[i]n order of \napproximate prioritization.\" Three are directly pertinent."},{"page":8,"startToken":1889,"endToken":2157,"text":"24. Consideration 4 — \"Use more temporal granularity to model capability and \ndeliverability of unlimited resources.\" E3's evaluation states that this \"[r]eflects resource \ncapability changing with temperature conditions, increasing model accuracy,\" and assigns it an \nImpact Level of: \"High impact. Approximately ~8 GW of additional unlimited resource \ncapability in the winter months, ~1% IRM reduction.\" E3 records the implementation difficulty \nas \"Low difficulty to implement a seasonal approach (which PJM has already done).\" \n25. Consideration 6 — \"De-weight historical resource performance events as new \nresource performance events under similar weather conditions occur.\" E3 explains that \"[t]he \ncurrent PJM model methodology draws resource performance profiles from historical \nperformance during the years 2012-2024,\" that \"[a]ny resource performance day within that time \nperiod is selectable by the model with equal probability,\" and that consequently a resource \"that \nperforms poorly but implements weatherization, better fuel security, or other enhancements \nwould still be modeled with its pre-enhancement performance.\" \n26. Consideration 3 — \"Update the scrambling process to draw resource performance \nfrom the same weather conditions used to synthesize load.\" E3 assigns this a \"[m]odest to high \nimpact on IRM and ELCC values as indicated by PJM sensitivity analysis,\" and notes \"[l]ow \nimplementation effort given that PJM has already built this functionality to test impacts as part of \nPackage C.\" \n27. Movants disclose, as they must, E3's overall qualification: \"E3 does not view \nimplementation of any of these considerations as strictly necessary for the continued use of the \ncurrent model in the administration of the capacity market. Instead, they are intended to support \ncontinued improvement of PJM's reliability modeling framework over time.\""},{"page":9,"startToken":2157,"endToken":2438,"text":"28. That qualification is important but it does not answer the question presented here. E3 \nwas engaged to assess whether PJM's model remains fit for continued use in administering the \ncapacity market — an annual, self-correcting process in which each Delivery Year's requirement \nis recalculated and each auction reprices. E3 was not asked, and did not opine, whether the \nmodel's output is a sufficient basis for a novel, one-time procurement of commitments extending \nfifteen years into the future, which by design cannot be recalculated annually. The distinction is \nthe entire subject of this protest. \nC. PJM's own sensitivity analyses \n29. On May 22, 2025, PJM presented to the ELCC Senior Task Force a set of sensitivity \nanalyses on the same model, provided as Attachment B hereto. PJM's results include the \nfollowing, in PJM's own words: \nSensitivity \nPJM's stated result \n5. \"WICAP\" — reflect higher winter output \nfor unlimited resources \n\"Decrease in overall system risk (IRM drops \nand system is less tight)\" \n4. \"Align\" — improve alignment of load \nscenarios with temperature bins \n\"Significant increase in overall system risk \n(IRM increases and system is tight)\" \n7. \"WICAP & Align\" \n\"Increase in overall system risk (IRM \nincreases and system is tighter)... Impact of \n'Align' is stronger than impact of 'WICAP'\" \n8. \"WICAP & NoPV1WSE\" \n\"Decrease in overall system risk (IRM drops \nand system is less tight)... Almost [all] of \nLOLH is in the summer season\" \n \n30. PJM quantified the winter capability question directly. Comparing summer and \nwinter ICAP for unlimited resources across nuclear, coal, gas combined cycle, gas combustion \nturbine, diesel, steam and other thermal classes, PJM's table shows 163,149 MW of summer \nICAP against 171,710 MW of winter ICAP — a difference of 8,561 MW."},{"page":10,"startToken":2438,"endToken":2717,"text":"31. PJM's own comparison of results states: \"Removing PV1 and WSE forced outages \neliminates the majority of winter risk (even when paired with the 'Align' sensitivity),\" and that \n\"[t]he 'Align' sensitivity increases winter risk and overall risk. However, this increase is \nmitigated when coupled with the 'WICAP' sensitivity.\" \n32. Movants disclaim any suggestion that these sensitivities establish that PJM's \nreliability requirement is too high. PJM's Sensitivity 7 shows the opposite when two identified \ncorrections are combined. Movants bring them to the Commission's attention because, taken \ntogether, they demonstrate that the Reliability Requirement — and therefore the RBP Target — \nis materially sensitive to modeling choices that PJM's own consultant has identified as \nunresolved, in amounts of the same order of magnitude as the 6,831.3 MW PJM proposes to \nprocure for fifteen years. \nD. What the RBP Filing says about any of this \n33. The RBP Filing does not engage any of it. Movants have searched the complete \nfiling, including its attachments and testimony. The filing refers to \"ELCC\" approximately 200 \ntimes, and refers to the \"Installed Reserve Margin\" in definitional tariff provisions and as an \nobserved benchmark — the transmittal reports that both recent auctions \"cleared 5.6% below the \nPJM Region Installed Reserve Margin of 20%.\" RBP Filing, transmittal at 124. It contains no \nreference to E3 or to Energy and Environmental Economics; no reference to \"WICAP\"; no \nreference to \"winter capability\"; and no reference to the \"Reserve Requirement Study.\" Its seven \nreferences to \"sensitivity\" or \"sensitivities\" concern Optional Interconnection Studies and the \ncalculation of RBP settlements, not reliability modeling. Nowhere does the filing address how \nthe Reliability Requirement was derived, the independent evaluation PJM commissioned of the"},{"page":11,"startToken":2717,"endToken":3009,"text":"model that derives it, or PJM's own analyses of how far the derivation moves under identified \ncorrections. \nIV. THE COMMISSION SHOULD NOT FIND THE PROCUREMENT \nQUANTITY JUST AND REASONABLE ON THIS RECORD \n34. Under section 205, PJM bears the burden of showing that its proposal is just and \nreasonable. 16 U.S.C. § 824d(e). Where the central quantitative term of a proposal — here, how \nmuch capacity to buy, and for how long — is the output of a model, PJM's burden includes some \ndemonstration that the output is a reasonable basis for the commitment proposed. \n35. PJM has not made that demonstration. It has described the shortfall as an observed \nauction outcome, which it is, without addressing the fact that the outcome is measured against a \nmodeled requirement whose known sensitivities PJM has studied and not disclosed here. \n36. The fifteen-year term is what makes this dispositive. In the ordinary Base Residual \nAuction, an error in the reliability requirement is bounded: the Delivery Year ends, the model is \nre-run, and the market reprices. PJM's own conduct illustrates the point — PJM revised its peak \nload forecast for 2030 downward by 875 MW in its 2026 Long-Term Load Forecast \"due to \nforecasting improvements.\" PJM corrects its inputs when its methods improve, and customers \nreceive the benefit at the next auction. \n37. The RBP has no such self-correction. Commitments run to the 2042/2043 Delivery \nYear. If the Initial RBP Target is materially overstated because of a modeling question that \nPJM's consultant identified in December 2025 and PJM resolves in 2027 or 2028, customers in \nthe zones allocated RBP Charges will nonetheless pay for the resulting commitments for as long \nas fifteen years — and every customer in the PJM Region, Movants included, will continue to"},{"page":12,"startToken":3009,"endToken":3331,"text":"bear the effects of the modeled requirement through each annual auction and the supply prices \nbuilt upon it. The asymmetry between a correctable annual process and an uncorrectable long-\nterm commitment is the reason the modeling record should be before the Commission now. \n38. That asymmetry is not theoretical. In the 2024/2025 Base Residual Auction, PJM's \nLDA Reliability Requirement for the DPL South Zone — a Locational Deliverability Area \nwithin Movants' distribution zone — rested on the assumption that certain suppliers would bid; \nthey did not, and the requirement was not corrected. On re-run, the auction cleared at the price \ncap and PJM procured 1.9 percent more capacity at an additional cost of $182.8 million. See Md. \nOffice of People's Counsel v. FERC, No. 24-1353 (D.C. Cir. Jan. 13, 2026), granting pet. for \nreview of PJM Load Parties v. PJM Interconnection, LLC, 189 FERC ¶ 61,199 (2024). The \nDelaware Public Service Commission and the Delaware Division of the Public Advocate were \namong the complainants. The matter is on remand and unresolved. \n39. Movants do not contend that the DPL South episode governs this proceeding, and \nrecognize that the D.C. Circuit expressly declined to hold that any refund is due. Movants cite it \nfor a narrower proposition: PJM's reliability requirement calculations have previously proved \nmaterially erroneous, at substantial cost, in a sub-zone of Movants' own distribution zone, and \nthe Commission has recent and direct experience of how difficult such an error is to remedy after \nthe fact. The prudent course is verification before commitment, not litigation afterward. \n40. The Independent Market Monitor's findings reinforce the need for verification. In its \nanalysis of the 2027/2028 Base Residual Auction — the first of the two shortfall auctions PJM \ninvokes — the Monitor concluded that the auction's results \"were not competitive as a result of \nthe inclusion of large new data center loads in the load forecast, the lack of a queue for the"},{"page":13,"startToken":3331,"endToken":3641,"text":"addition of large new data center loads, the performance assessment interval (PAI) penalties that \nare part of the CP design, PJM's ELCC approach, the definition of market seller offer caps, the \nfailure to extend the RPM must offer requirement to demand resources, and the product \ndefinition and lack of market power mitigation for demand resources.\" Monitoring Analytics, \nAnalysis of the 2027/2028 RPM Base Residual Auction, Part B, at 2 (July 9, 2026). The Monitor \nfurther concluded that \"[t]he BRA prices do not reflect supply and demand fundamentals but \nreflect, in significant part, PJM decisions about the definition of supply and demand,\" and that \n\"capacity market prices can be significantly affected by forecast data center load that bears little \nknown resemblance to reality.\" Id. at 2, 4. \n41. Movants take no position on the Monitor's proposed remedies, and note that the \nMonitor's report addresses the 2027/2028 auction rather than the 2028/2029 auction from which \nthe Initial RBP Target is drawn — though the Monitor warns the identified problems \"will \ncontinue to result in even higher prices unless the related issues are addressed.\" Id. at 8. Movants \ncite the report for one proposition: the \"observed\" shortfall that defines the Initial RBP Target is \nnot a pure market datum. By the assessment of PJM's own independent Market Monitor, it \nreflects, in significant part, administrative determinations — including the ELCC approach and a \nload forecast incorporating large-load projections of uncertain reliability. A figure of that \ncharacter should be substantiated before it fixes fifteen years of procurement obligations. \nV. PJM SIMULTANEOUSLY PROPOSES TO DEFER THE TARIFF'S OWN \nMANDATED INVESTIGATION OF THE SHORTFALL'S CAUSES \n42. PJM's existing Tariff already requires the inquiry Movants seek. As PJM's own \ntransmittal acknowledges, the Tariff contains an \"existing requirement for PJM to investigate the \ncause for clearing short of the reliability requirement and to recommend corrective action.\" RBP"},{"page":14,"startToken":3641,"endToken":3913,"text":"Filing, transmittal at 124. And PJM's own footnote quotes the 2027/2028 BRA Report: the \nshortfall \"constitutes a triggering event as defined in the PJM Tariff, mandating an investigation \nto determine the root causes of the region's failure to secure sufficient resource adequacy.\" Id. at \n124 n.308. \n43. Yet the RBP Filing proposes to reset that investigation and corrective-action \nobligation to the 2032/2033 Delivery Year, on the stated rationale that doing so \"avoids posting \nsubstantively repetitive reports should the BRAs continue to clear short in the intervening \nDelivery Years.\" Id. at 124. The filing does not state whether the root-cause investigation already \nmandated by the 2027/2028 shortfall has been completed, and no such analysis appears in the \nfiling. \n44. The juxtaposition is the problem. PJM proposes to (a) procure up to fifteen years of \ncapacity commitments sized by the shortfall, while (b) deferring until 2032/2033 the Tariff's own \nmandated investigation into the causes of that shortfall. Whatever the administrative convenience \nof avoiding repetitive reports, the sequence is backwards: the root-cause analysis the Tariff \nalready requires should be completed and placed on the record before long-duration \ncommitments are fixed by the number it examines — not five Delivery Years after. \nVI. THE RELIEF REQUESTED IS AVAILABLE UNDER SECTION 205 \n45. Movants recognize that in a section 205 proceeding the Commission's role is to \ndetermine whether the rate the utility has filed is just and reasonable, and that the Commission \nmay not impose modifications resulting in \"an entirely different rate design\" from the utility's \nproposal. NRG Power Mktg., LLC v. FERC, 862 F.3d 108, 114–16 (D.C. Cir. 2017)."},{"page":15,"startToken":3913,"endToken":4215,"text":"46. No such limit is implicated here, for two independent reasons. First, PJM has \nconsented. The RBP Filing states that \"to facilitate Commission approval and prompt opening of \nthe RBP procurement window, PJM consents to the Commission's exercise of authority to \nmodify and/or sever the proposed Tariff and RAA language, as needed and permitted under the \nFPA and NRG Power Marketing, where such modification is consistent with PJM's overarching \nobjectives in this filing,\" and asks only that the Commission \"expressly prescribe the revised rate \nor rule in its order.\" RBP Filing, transmittal § V, at 130–31. Conditioning acceptance on \nsubstantiation of the procurement target is consistent with PJM's stated overarching objective — \nprocuring capacity to meet the Region's actual resource adequacy need — and alters no element \nof the RBP's design. \n47. Second, the condition sought substitutes one number for another — the precise \noperation the D.C. Circuit has approved. In Aera Energy LLC v. FERC, 789 F.3d 184, 190–92 \n(D.C. Cir. 2015) — quoted by PJM's own filing at note 318 — the court affirmed a conditional \nacceptance that \"simply required [the utility] to substitute one number for another.\" A Final RBP \nTarget substantiated against the modeling questions identified by PJM's own consultant leaves \nevery design element of the RBP untouched: the same procurement mechanism, the same \neligibility rules, the same commitment term, the same allocation methodology. Only the quantity \nchanges, and only if the substantiation shows it should. \n48. In the alternative, and independent of consent: requiring an applicant to substantiate \nthe central quantitative term of its own filing is not redesign at all — it is the application of the \napplicant's burden of proof under section 205(e). The Commission may also accept and suspend \nthe filing for a nominal period and set the procurement quantity for further proceedings, or"},{"page":16,"startToken":4215,"endToken":4502,"text":"accept the mechanism while directing that the Final RBP Target be established in a compliance \nfiling supported by the analyses identified herein. \nVII. COST ALLOCATION: THE PROPOSAL RESTS ON STATE ACTION \nTHAT HAS NOT OCCURRED \n49. PJM proposes to allocate the Final RBP Target first to Electric Distributor zones by \nforecasted load growth, and then to Load Serving Entities in a manner that \"permits states to \ndetermine the appropriate allocation of RBP UCAP MW to specific LSEs and/or end-use \ncustomers, thus allowing Relevant Electric Retail Regulatory Authorities ('RERRA') to \nappropriately assign costs to their respective retail customers, including data centers.\" \n50. Movants state candidly that PJM's zonal step does not, on PJM's illustrative example, \nallocate RBP UCAP MW to the DPL zone, and that PJM's 2026 Load Forecast Table B9b shows \nno load adjustment for the DPL zone in any year from 2026 through 2046. To that extent PJM's \nallocation directs cost toward the zones whose forecast load growth gives rise to the shortfall, \nand Movants do not criticize that design. \n51. Movants' concern is with what happens when the design's premise fails. PJM states \nthat \"[s]hould the relevant RERRA(s) decline to communicate RBO MW to the relevant Electric \nDistributors ..., PJM has proposed to apply a backup default cost allocation.\" The protection PJM \noffers to existing customers thus depends on affirmative, discretionary action by state regulators \nthat has not yet occurred, over a term of up to fifteen years. \n52. PJM further relies on the Statement of Principles Regarding PJM issued January 16, \n2026, in which the governors of the PJM states \"agreed to ... [u]se their Authorities to Allocate \nCosts to Data Centers and Protect Residential Customers.\" Movants do not question the sincerity"},{"page":17,"startToken":4502,"endToken":4744,"text":"of that commitment. It is, however, a statement of intent by persons who are not parties to this \nproceeding and who cannot be bound by any order the Commission issues here. A section 205 \nfiling must be shown just and reasonable on its own terms. \n53. Delaware illustrates the gap. The Delaware Public Service Commission opened its \nlarge load tariff proceeding, Docket No. 25-0826, in October 2025 — announcing the effort as \none to ensure that \"large load facilities, like data centers, do not shift costs to other ratepayers.\" \nDel. PSC, Delaware PSC Opens Docket for Large Load Tariff, Pauses Interconnections (Oct. \n14, 2025). That proceeding remains pending. Delaware has not yet adopted the rate structures on \nwhich PJM's allocation design depends. \n54. Movants therefore request that the Commission require PJM to specify the backup \ndefault cost allocation with particularity and to demonstrate that it is just and reasonable as \napplied to zones and customer classes that neither caused nor benefit from the shortfall, \nincluding in the event a RERRA does not act within the RBP timeline. \nVIII. REQUESTED RELIEF \n55. Movants respectfully request that the Commission: \n(a) grant this motion to intervene and accord each Movant party status; \n(b) direct PJM to address on the record in this proceeding the E3 PJM ELCC / RRS Model \nEvaluation (December 2025) (Attachment A hereto) and PJM's ELCC Senior Task Force \nsensitivity analyses (May 22, 2025) (Attachment B hereto), and their implications for the RBP \nTarget;"},{"page":18,"startToken":4744,"endToken":4972,"text":"(c) consistent with PJM's consent to modification, condition acceptance of the RBP Filing on \nPJM demonstrating the Final RBP Target calculated under the modeling questions identified by \nE3, including at minimum E3's Considerations 3, 4 and 6, individually and in combination, or \nexplaining why each does not materially affect the Target; \n(d) direct PJM to complete and file the root-cause investigation and corrective-action \nrecommendations already required by its Tariff in respect of the 2027/2028 and 2028/2029 \nshortfalls before RBP commitments are finalized, and decline to accept — or condition — the \nproposed deferral of that investigation obligation to the 2032/2033 Delivery Year; \n(e) require PJM to specify the backup default cost allocation applicable where a RERRA does \nnot communicate RBO MW, and to demonstrate that it is just and reasonable; \n(f) in the alternative, accept and suspend the filing for a nominal period and establish further \nproceedings limited to the RBP Target and cost allocation; and \n(g) grant such other relief as the Commission deems just and reasonable. \n56. Movants do not request that the Commission reject the RBP Filing, and do not oppose \nPJM proceeding with the RBP mechanism on a schedule that permits the matters above to be \naddressed. \nATTACHMENTS \nAttachment A — Energy and Environmental Economics, Inc., PJM ELCC / RRS Model \nEvaluation (December 2025) (presented to the PJM ELCC Senior Task Force, Dec. 9, 2025)."},{"page":19,"startToken":4972,"endToken":5153,"text":"Attachment B — PJM Interconnection, L.L.C., ELCC Accreditation Methodology: Update on \nSensitivity Analyses (ELCC Senior Task Force, May 22, 2025). \nIX. COMMUNICATIONS \n57. Communications regarding this proceeding should be addressed to: \nNicholas Max Neal \n111 Centrenest Lane \nWilmington, Delaware 19807 \nTelephone: (845) 263-0012 \nEmail: max@nicholasneal.com \n \nDavid Neal \n111 Centrenest Lane \nWilmington, Delaware 19807 \nTelephone: (646) 509-3146 \nEmail: shaun@shaunneal.com \n \nX. CONCLUSION \n58. PJM asks the Commission to authorize commitments of up to fifteen years, in a \nquantity set by a model, without telling the Commission what its own consultant said about that \nmodel or what its own sensitivity analyses showed — while proposing to defer, until 2032/2033, \nthe investigation of the shortfall's causes that PJM's Tariff already mandates. Movants ask only \nthat PJM be required to substantiate the number before the commitments are made, and that the \nCommission satisfy itself that the resulting quantity is just and reasonable. For the foregoing \nreasons, Movants respectfully request that the Commission grant this motion to intervene and the \nrelief requested herein. \nRespectfully submitted, \n/s/ Nicholas Max Neal               /s/ David Neal"},{"page":20,"startToken":5153,"endToken":5253,"text":"_______________________________     _______________________________ \nNicholas Max Neal                   David Neal \n111 Centrenest Lane                 111 Centrenest Lane \nWilmington, Delaware 19807          Wilmington, Delaware 19807 \n(845) 263-0012                      (646) 509-3146 \nmax@nicholasneal.com                shaun@shaunneal.com \n \nPro se                              Pro se \n \nDated: August 20, 2026 \nCERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each person designated \non the official service list compiled by the Secretary in this proceeding, in accordance with Rule \n2010 of the Commission's Rules of Practice and Procedure, 18 C.F.R. § 385.2010. \nDated at Wilmington, Delaware, this 20th day of August, 2026. \n/s/ David Neal \n_______________________________ \nDavid Neal"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":728,"startToken":0,"endToken":111},{"p":1,"at":728,"title":"I. PRELIMINARY STATEMENT","method":"printed heading","endPage":3,"endAt":425,"startToken":111,"endToken":562},{"p":3,"at":425,"title":"II. MOTION TO INTERVENE","method":"printed heading","endPage":3,"endAt":450,"startToken":562,"endToken":566},{"p":3,"at":450,"title":"A. Identity of Movants","method":"printed heading","endPage":4,"endAt":0,"startToken":566,"endToken":771},{"p":4,"at":0,"title":"B. Movants' Interest","method":"printed heading","endPage":6,"endAt":589,"startToken":771,"endToken":1460},{"p":6,"at":589,"title":"III. BACKGROUND","method":"printed heading","endPage":6,"endAt":606,"startToken":1460,"endToken":1462},{"p":6,"at":606,"title":"A. The RBP Filing","method":"printed heading","endPage":7,"endAt":1073,"startToken":1462,"endToken":1788},{"p":7,"at":1073,"title":"B. PJM's independent evaluation of that model","method":"printed heading","endPage":9,"endAt":609,"startToken":1788,"endToken":2250},{"p":9,"at":609,"title":"C. PJM's own sensitivity analyses","method":"printed heading","endPage":10,"endAt":901,"startToken":2250,"endToken":2571},{"p":10,"at":901,"title":"D. What the RBP Filing says about any of this","method":"printed heading","endPage":11,"endAt":109,"startToken":2571,"endToken":2734},{"p":11,"at":109,"title":"IV. THE COMMISSION SHOULD NOT FIND THE PROCUREMENT","method":"printed heading","endPage":13,"endAt":1655,"startToken":2734,"endToken":3586},{"p":13,"at":1655,"title":"V. PJM SIMULTANEOUSLY PROPOSES TO DEFER THE TARIFF'S OWN","method":"printed heading","endPage":16,"endAt":148,"startToken":3586,"endToken":4237},{"p":16,"at":148,"title":"VII. COST ALLOCATION: THE PROPOSAL RESTS ON STATE ACTION","method":"printed heading","endPage":17,"endAt":1102,"startToken":4237,"endToken":4678},{"p":17,"at":1102,"title":"VIII. REQUESTED RELIEF","method":"printed heading","endPage":19,"endAt":149,"startToken":4678,"endToken":4993},{"p":19,"at":149,"title":"IX. COMMUNICATIONS","method":"printed heading","endPage":19,"endAt":483,"startToken":4993,"endToken":5035},{"p":19,"at":483,"title":"X. CONCLUSION","method":"printed heading","endPage":20,"endAt":419,"startToken":5035,"endToken":5188},{"p":20,"at":419,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":20,"endAt":843,"startToken":5188,"endToken":5253}]}