{"document":{"slug":"rec-20260821-5090","title":"Motion to Intervene, Limited Protest, and Request for Clarification of PPL Electric Utilities Corporation","issued":"2026-08-21","accession":"20260821-5090","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"PPL Electric Utilities Corporation","kind":"protest","file":"sources/filings/text/20260821-5090_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5090","tier":"record","sha256":"0589c1aa3be8a3e6715f875e3a21524e44da019d67a4d23e0a74064b680ca122","pages":15,"tokens":4512,"emptyPages":[],"textThemes":["credit","adequacy","cost"]},"pages":[{"page":1,"startToken":0,"endToken":297,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C \n) \n) \n) \n                   Docket No. ER26-3380-000 \nMOTION TO INTERVENE, LIMITED PROTEST, \nAND REQUEST FOR CLARIFICATION OF  \nPPL ELECTRIC UTILITIES CORPORATION \nPursuant to Rules 211,1 212,2 and 2143 of the Federal Energy Regulatory \nCommission’s (“FERC” or the “Commission”) Rules of Practice and Procedure, PPL Electric \nUtilities Corporation (“PPL Electric”) respectfully moves to intervene in the above-captioned \nproceeding, provides the following limited protest (“Limited Protest”), and requests \nclarification. \nPPL Electric greatly appreciates the engagement of the PJM Interconnection, L.L.C. \n(“PJM”) stakeholder community and the work of the PJM Board and staff in acting to address \nthe capacity deficiencies arising from the 2027/2028 and 2028/2029 Reliability Pricing Model \n(“RPM”) Auctions, and is generally supportive of the Reliability Backstop Procurement \n(“RBP”) Filing.4 \nHowever, PPL Electric is compelled to submit this Limited Protest with respect to one \ncomponent of the RBP Filing concerning Transmission Owner exit.5  This component was \n \n1 18 C.F.R. § 385.211(a)(1) (“Any person may file a protest to object to any application, complaint, petition, order \nto show cause, notice of tariff or rate examination, or tariff or rate filing.”). \n2 18 C.F.R. § 385.212(a)(1) (“A motion may be filed: [a]t any time, unless otherwise provided.”). \n3 18 C.F.R. § 385.214(a)(3) (“Any person seeking to intervene to become a party, other than the entities specified \nin paragraphs (a)(1) and (a)(2) of this section, must file a motion to intervene.”).   \n4 PJM Interconnection, L.L.C., FPA Section 205 Filing of PJM Interconnection, L.L.C, Docket No. ER26-3380 \n(Jul. 31, 2026) (“RBP Filing”). \n5 Tariff, Attachment DD, Section 18.7 (hereafter, the “TO Exit Provisions”)."},{"page":2,"startToken":297,"endToken":602,"text":"2 \nneither contemplated nor discussed by any stakeholder during the Critical Issue Fast Path \n(“CIFP”) Process and appears to have been introduced only shortly before the filing was \nsubmitted. \nRecognizing that individual elements of the proposal may warrant separate treatment, \nPJM expressly invited the Commission to “modify and/or sever any element of the proposed \nTariff and RAA language to the extent necessary.”6  The Commission should do so here and \nreject the TO Exit Provisions of the RBP Filing, as discussed below in Section II. \nAdditionally, PPL Electric requests clarification on a specific credit collateral \ncontingency, as discussed below in Section III.   \nI. \nMOTION TO INTERVENE \nPPL Electric respectfully moves to intervene in the above-captioned proceeding.  PPL \nElectric is a Pennsylvania corporation and a wholly owned subsidiary of PPL Corporation.  \nPPL Electric is an owner of transmission facilities in PJM, distributes electricity to all retail \ncustomers within its service territory in central and eastern Pennsylvania, and is a provider of \nlast resort under Pennsylvania’s Electricity Generation Customer Choice and Competition Act, \n66 Pa.C.S.A. § 2801, et seq.  PPL Electric is a designated Load Serving Entity in PJM, and a \nsignatory to the PJM Consolidated Transmission Owners Agreement (“CTOA”) and the \nReliability Assurance Agreement Among Load Serving Entities in the PJM Region (“RAA”).7 \nOn July 31, 2026, PJM initiated the above-captioned Federal Power Act (“FPA”) \nsection 205 proceeding by submitting proposed Tariff and RAA revisions to establish the \n \n6 RBP Filing at 3. \n7 The RAA is currently located under PJM’s “Intra-PJM Tariffs” eTariff title, available here: \nhttps://etariff.ferc.gov/TariffBrowser.aspx?tid=1731. Terms not otherwise defined herein shall have the same \nmeaning as set forth in the RAA, the Open Access Transmission Tariff (“Tariff”), and the Amended and Restated \nOperating Agreement of PJM Interconnection, L.L.C. (“Operating Agreement”)."},{"page":3,"startToken":602,"endToken":893,"text":"3 \nRBP—a one-time procurement of new capacity to address resource adequacy challenges in the \nPJM Region stemming from insufficient commitments of capacity in the 2027/2028 and \n2028/2029 RPM Auctions. \nGiven the direct relationship between the RBP Filing and PPL Electric’s roles and \nresponsibilities within the PJM Region, PPL Electric has a direct, substantial, and independent \ninterest in this proceeding, which no other party can adequately represent, and respectfully \nrequests that the Commission grant this motion to intervene and that PPL Electric be afforded \nall the rights of a party to this proceeding. \nII. \nLIMITED PROTEST \n  The Commission should reject the TO Exit Provisions for the reasons discussed \nbelow in subsections II.A–D. \nA. The TO Exit Provisions Concern Transmission Owner Rights and Obligations \nand Therefore Belong in the CTOA. \nThe CTOA is the bilateral contract establishing the rights, obligations, and \ncommitments between PJM and the PJM Transmission Owners.  Indeed, the contract explicitly \ncodifies as one of its core purposes “[to] establish certain rights and obligations that will apply \nto the Parties and PJM.”8  By contrast, Attachment DD to the PJM Tariff is not a bilateral \ncontract establishing the rights, obligations, and commitments between PJM and the PJM \nTransmission Owners.  It is a Tariff9 of general applicability that contains the rules of PJM’s \n \n8 CTOA, Article 2. \n9 18 C.F.R. § 35.2(c)(1) (“The term tariff as used herein shall mean a statement of (1) electric service as defined \nin paragraph (a) of this section offered on a generally applicable basis, (2) rates and charges for or in connection \nwith that service, and (3) all classifications, practices, rules, or regulations which in any manner affect or relate \nto the aforementioned service, rates, and charges.”)."},{"page":4,"startToken":893,"endToken":1266,"text":"4 \ncapacity market, with its sole, self-identifying purpose as being to “set[] forth the terms and \nconditions governing the Reliability Pricing Model for the PJM Region.”10 \nThe Commission has been clear that the purpose of a PJM Governing Agreement is an \nimportant consideration in determining where particular provisions belong within the PJM \nGoverning Agreements.  As relevant here, the Commission has consistently found that rules \nthat “predominantly” affect the rights and responsibilities of the RTO and the Transmission \nOwners are appropriately included in the applicable Transmission Owner agreement (and in \nthe case of PJM specifically, in the CTOA).11  Proposed  Section 18.7 predominately affects \nthe rights and responsibilities of the PJM Transmission Owners and PJM.  Indeed, the \nprovision imposes new obligations solely on the PJM Transmission Owners while \ncorrespondingly relieving PJM of any responsibilities associated with those commitments.  \nThe text of proposed Section 18.7 confirms this conclusion: \n18.7 Exiting Transmission Owner RBP Obligations  \nIn \nthe \nevent \na \nTransmission \nOwner \nexits \nPJM \nInterconnection, L.L.C. and the quantity of load with the \nTransmission Owner is commensurate with the RBP Resources \nthat are located in that Transmission Owner’s territory, the \nTransmission Owner shall honor the remaining term of the \nRBP commitment.  \n(a) Exiting Transmission Owner with Committed RBP \nResources  \n \n \n10 PJM Tariff, Attachment DD, Section 1.  \n11 See, e.g., Duquesne Light Co., 189 FERC ¶ 61,181 at P 55 (2024) (“The Commission has previously \ndistinguished provisions that ‘affect only (or predominantly) the rights and responsibilities’ of the RTO and \ntransmission owners, which may appropriately be included in transmission owner agreements, and substantive \ninterconnection and transmission procedures that are more appropriately housed in other governing documents.”); \nOrder on Reh’g, 192 FERC ¶ 61,051 at P 73 (2025) (“Unlike the Overlap Provisions, the provisions that Indicated \nPJM TOs point to that are already included in the CTOA predominantly affect a PJM TO’s rights and \nresponsibilities rather than substantive transmission planning procedures.”).  See also ISO New England Inc., 106 \nFERC ¶ 61,280 (2004) (“We find that with the exception of those provisions that affect only (or predominantly) \nthe rights and responsibilities of RTO-NE and the Transmission Owners, i.e., Sections 6 and 7, Schedule 3.09(a) \ndoes not belong in the TOA . . .”)."},{"page":5,"startToken":1266,"endToken":1644,"text":"5 \nAny Transmission Owner seeking to exit PJM \nInterconnection, L.L.C. may, prior to exiting PJM, enter \ninto agreements that maintain appropriate rates, terms, and \nconditions that preserves the RBP commitments with the \nowners of RBP Resource(s) that have been committed \nthrough the Reliability Backstop Procurement that are \nlocated within the physical boundaries of the Transmission \nOwner’s Zone. PJM and PJM Settlement shall be relieved \nof any applicable RBP obligations made to RBP \nResources that are subject to such agreements. In the event \nno such agreement is made and such RBP Resource(s) can \nbe pseudo-tied into the PJM Region, the exiting \nTransmission Owner must, to the extent the Office of the \nInterconnection elects to retain such RBP Resource \nthroughout the term of its RBP commitment, pay all costs \nfor RBP Resources to pseudo-tie into the PJM Region so \nthat such resource meets the external Capacity Resource \neligibility requirements set forth in Tariff, Attachment DD, \nsection 5.5A prior to the Transmission Owner exiting PJM \nInterconnection, L.L.C. Any Transmission Owner seeking \nto exit PJM Interconnection, L.L.C. with RBP Resource(s) \nthat (i) are located within the physical boundaries of the \nTransmission Owner’s Zone and (ii) cannot be pseudo-tied \ninto the PJM Region, and/or which the Office of the \nInterconnection elects not to retain the RBP Resource as a \nCapacity Resource throughout the term of its RBP \ncommitment, shall pay costs associated with the remaining \nterm of the RBP Resource, the amount which shall be \ndetermined through a filing submitted under the Federal \nPower Act, prior to exiting PJM Interconnection, L.L.C. \nRevenues collected in such an event shall be credited to \nLoad Serving Entities that are allocated a share of the RBP \nCharges on a pro rata basis through the remaining term of \nthe RBP commitment.  \n \n(b) Exiting Transmission Owner with Load Allocated RBP \nCharges  \n \nAny Transmission Owner seeking to exit PJM \nInterconnection, L.L.C. with net load that has been \nallocated RBP Charges for RBP Resources not located \nwithin the physical boundaries of the Transmission \nOwner’s Zone may, prior to exiting PJM, enter into \nagreements that maintain appropriate rates, terms and \nconditions that preserves the RBP commitments with the \nowners of such RBP Resource(s). PJM and PJM"},{"page":6,"startToken":1644,"endToken":1958,"text":"6 \nSettlement shall be relieved of any applicable RBP \nobligations made to RBP Resources that are subject to \nsuch agreements. In the event no such agreement is made, \nthe exiting Transmission Owner must pay all forward \nobligations on an accelerated basis, the amount which \nshall be determined through a filing submitted under the \nFederal Power Act, prior to exiting PJM Interconnection, \nL.L.C. Any such revenues collected shall be distributed to \nthe RBP Resources under the standard daily RBP settlement \nschedule to such resources through the remaining term of \nthe RBP commitment. \n \n \nRules regarding the residual commitments and obligations of PJM Transmission Owners \nafter withdrawal are appropriately addressed in the CTOA.  Indeed, the CTOA already \ncontains provisions governing such obligations.  Section 3.4 of the CTOA is titled \n“Obligations After Withdrawal:” \n3.4 Obligations After Withdrawal, Transfer, or Assignment.  \nAny Party that withdraws from, transfers, or assigns this \nAgreement in accordance with Sections 3.2 or 3.3 hereof, shall \nremain liable for any and all obligations under this Agreement \nthat such Party incurred, that were incurred on behalf such \nParty, or that arose hereunder prior to the date upon which \nsuch Party’s withdrawal, transfer, or assignment became \neffective. Withdrawal from, transfer, or assignment of this \nAgreement shall not relieve such Party of any of its \nindemnification or liability obligations pursuant to Article 9 \nhereof for any events occurring prior to the time that its \nwithdrawal from this Agreement became effective. \n \nAs evidenced by Section 3.4, a PJM Transmission Owner’s obligations after withdrawal were \nspecifically contemplated, negotiated, and agreed to by PJM and the PJM Transmission \nOwners as part of the CTOA.  Moreover, the scope of these agreed-upon obligations consists \nof “any and all obligations under this Agreement that such Party incurred, that were incurred \non behalf [of] such Party, or that arose hereunder prior to the date upon which such Party’s"},{"page":7,"startToken":1958,"endToken":2374,"text":"7 \nwithdrawal, transfer, or assignment became effective.”12  Rather than addressing Transmission \nOwner withdrawal obligations through the CTOA, proposed Section 18.7 would create \nadditional withdrawal-related obligations via the PJM Tariff.  The Commission has repeatedly \nemphasized the importance of locating provisions within the Governing Agreements that \ncorrespond to the rights and obligations at issue, and PJM’s proposal is inconsistent with that \napproach.13 \nB. The TO Exit Provisions Raise Standards of Conduct Concerns, Allocate \nResponsibility for Capacity Commitments in a Manner That Warrants Further \nScrutiny, and Do Not Account for Differences Among Transmission Owners. \nBy their terms, the TO Exit Provisions apply to “any Transmission Owner seeking to \nexit PJM,” (emphasis added) and, as described above in Section II.A, seek to impose residual \ncommitments on “any” exiting Transmission Owner that are predicated on the continuing \nobligation of an exiting Transmission Owner to serve load within its service territory.14 \nThere are (at least) two significant flaws with this proposal.  First, the proposal ignores \nthe functional separation that must exist within a Transmission Owner’s organization.  For \nthose Transmission Owners that will also own RBP Resources, it is unclear how compliance \nwith the TO Exit Provisions could be effectuated in the absence of intimate coordination \n \n12 CTOA, Section 3.4. \n13 See supra note 11.  \n14 RBP Filing at 91-92 (“If a Transmission Owner leaves PJM and the load taken with the Transmission Owner \nis commensurate with the RBP Resources that are located in that Transmission Owner’s territory, the \nTransmission Owner is expected to honor the remaining term of the RBP commitment since it would need such \nresources to serve the loads in its service territory. However, in the event a Transmission Owner exits PJM and \ncommitted RBP Resources are physically in such Transmission Owner’s service territory, it would be \nunreasonable for PJM’s Members to continue paying for such excess RBP Resources if they no longer can provide \ncapacity to PJM (e.g., if the resource cannot be pseudo-tied into PJM as further explained below). Similarly, in \nthe event a Transmission Owner exits PJM with the net load that is removed with the Transmission Owner’s \ndeparture, it would be unreasonable for PJM’s remaining load to pay for the excess committed RBP Resources \nthat remain in the PJM Region. To address these potential scenarios, proposed Tariff, Attachment DD, sections \n18.7(a) and 18.7(b) put committed RBP Resources back in the same position they would have been in had the \nassociated Transmission Owner not exited PJM.”)."},{"page":8,"startToken":2374,"endToken":2683,"text":"8 \nbetween the organization’s transmission business and generation/marketing business.  \nSpecifically, the TO Exit Provisions require that the Transmission Owner enter into agreements \n“that maintain appropriate rates, terms, and conditions that preserve[] the RBP commitments \nwith the owners of the RBP Resources,” or else pay “all costs for RBP Resources to pseudo-\ntie,” and “pay costs associated with the remaining term of the RBP Resource.”  Yet such \ncontemplated coordination ignores the functional separation that Transmission Owners are \nrequired to adhere to under the Commission’s Standards of Conduct,15 whereby the \ntransmission function employees of a transmission-owning public utility must operate \nindependently of the marketing function employees.   \nSecond, not all Transmission Owners under the CTOA are Load Serving Entities that \nhave executed the RAA.  These terms are separate and distinct, with unique rights and \nobligations arising from their respective Governing Agreements.  The reason why PJM in the \nRBP Filing submitted extensive revisions to the RAA in order to effectuate the Reliability \nBackstop Procurement is because the RAA is the contract through which each signatory \nexplicitly stipulates that it “is a Load Serving Entity within the PJM Region,” and is \n“committing to share its Capacity Resources with the other Parties to reduce the overall reserve \nrequirements for the Parties while maintaining reliable service.”16  It makes sense then that \namong PJM’s Governing Agreements, the RAA would be a reasonable place to impose \nobligations on Load Serving Entities and allocate costs.  Yet not all PJM Transmission Owners \nare signatories to the RAA, nor are all PJM Transmission Owners Load Serving Entities.17  It \n \n15 18 C.F.R. Part 358. \n16 RAA at Recitals. \n17 CTOA signatories that are not Load Serving Entities include Essential Power Rock Springs, LLC, Neptune \nRegional Transmission System, LLC, Linden VFT, LLC, Hudson Transmission Partners, LLC, NextEra Energy \nTransmission MidAtlantic Indiana, Inc., and Silver Run Electric, LLC."},{"page":9,"startToken":2683,"endToken":3139,"text":"9 \nis thus unclear how the TO Exit Provisions would apply to every Transmission Owner seeking \nto exit PJM, because the proposal does not account for the distinction between Transmission \nOwners that are RAA signatories and those that are not.   \nC. The TO Exit Provisions Address a Contingency That PJM Acknowledges Is \nRemote and Would Unnecessarily Constrain Future Decision-Making. \nPJM acknowledges that “no Transmission Owner has formally sought to exit PJM at \nthis time.”18  PJM nevertheless argues that “however remote the possibility of a Transmission \nOwner exiting PJM during or prior to the 2042/2043 Delivery Year, it is imperative that rules \nare in place to ensure that, even in the event of a Transmission Owner exit, committed RBP \nResources will be made whole for the entire term of the commitment.”19  Yet this argument \noverlooks the fact that CTOA, Section 3.2 already requires several steps, including \nCommission authorization, that must be taken to effectuate a Transmission Owner’s \nwithdrawal from PJM,20 and as a practical matter, any such withdrawal would, by necessity, \ninvolve significant negotiations that account for the unique facts and circumstances present at \nthat time.  Just as a Transmission Owner’s integration into PJM necessitates careful \n \n18 RBP Filing at 90. \n19 Id. at 91. \n20 CTOA, Section 3.2 (“Any Party may withdraw from this Agreement upon ninety (90) days advance written \nnotice to PJM and the other Parties; provided that such withdrawal shall not be effective until the withdrawing \nParty has: (i) if its Transmission Facilities do not comprise an entire Control Area, satisfied all applicable \nstandards of NERC and the Applicable Regional Reliability Council for operating a Control Area or being \nincluded within an existing Control Area; (ii) put in place alternative arrangements for satisfaction of the FERC’s \nrequirements with respect to comparable transmission services; and (iii) made a filing with the FERC under \nSection 205 of the Federal Power Act to withdraw from this Agreement, and such filing has been approved, \naccepted without suspension, or if suspended, the suspension period has expired before the FERC has issued an \norder on the merits of the filing. Notwithstanding the forgoing, a Zero Revenue Requirement Party may withdraw \nfrom this Agreement in the particular circumstance of permanent removal of its owned Transmission Facilities \nfrom service, provided that such Party has: (a) provided written notice to PJM and the parties to the Operating \nAgreement at least twelve months in advance of the intended date of retirement of its owned Transmission \nFacilities, and (b) complied with all reasonable requirements of PJM for restoration, to the maximum extent \nreasonably attainable, of the PJM Transmission System to the same configuration and operational capability that \nexisted prior to such Party's installation of its owned Transmission Facilities.”)."},{"page":10,"startToken":3139,"endToken":3491,"text":"10 \ndeliberation, communication with and approval by state regulatory authorities, bilateral \nnegotiations, an “integration agreement,” and Commission approval,21 a Transmission \nOwner’s exit would correspondingly necessitate a similar process.  Proposed Section 18.7 \nwould unnecessarily constrain the parties involved in that process, including the Commission \nand state regulatory authorities, by preemptively mandating how the costs and contractual \narrangements of generation resources and load within an exiting Transmission Owner’s zone \nmust be treated.  To the extent that future facts and circumstances would lead the Commission \nor applicable state regulatory authorities to favor a different set of obligations and requirements \non generation resources and load within an exiting Transmission Owner’s zone, an FPA section \n206 action would be required to modify the rules codified in the PJM Tariff.  The Commission \nand state regulatory authorities need not address this issue preemptively, particularly given the \nabsence of any pending withdrawal requests and PJM’s own acknowledgement that the \npossibility of this contingency is “remote.”22 \nD. The Vagueness of PJM’s Transmission Owner Exit Provisions Violates FPA \nSection 205(c) and the Commission’s Implementing Regulations. \nThe Commission’s regulations implementing FPA section 205(c) are unambiguous—\nclarity and specificity are required when rates and charges are filed with the Commission. \nEvery public utility shall file with the Commission and post, in \nconformity with the requirements of this part, full and complete \nrate schedules and tariffs and those service agreements not \nmeeting the requirements of § 35.1(g), clearly and specifically \nsetting forth all rates and charges for any transmission or sale \nof electric energy subject to the jurisdiction of this \nCommission, the classifications, practices, rules and regulations \n \n21 A recent illustration of this process is available in Docket No. ER18-459, which involves the integration of \nOhio Valley Electric Corporation (“OVEC”). \n22 RBP Filing at 91 (“Therefore, however remote the possibility of a Transmission Owner exiting PJM during or \nprior to the 2042/2043 Delivery Year, it is imperative that rules are in place to ensure that, even in the event of a \nTransmission Owner exit, committed RBP Resources will be made whole for the entire term of the \ncommitment.”)."},{"page":11,"startToken":3491,"endToken":3783,"text":"11 \naffecting such rates, charges, classifications, services, rules, \nregulations or practices, as required by section 205(c) of the \nFederal Power Act (49 Stat. 851; 16 U.S.C. 824d(c)).23 \nThe Commission has explained that an RTO has “[an] obligation to set forth its Commission-\njurisdictional rates clearly and specifically in its tariff.”24  The need to set forth rates and \ncharges “clearly and specifically” is essential for the Commission’s own FPA section 205(c) \nanalysis, as “[a] minimum level of specificity within the tariff is necessary for the Commission \nto determine whether the charges that result are just and reasonable.”25  It is also important in \nfulfilling the fundamental purpose of FPA section 205(c) to provide notice to customers, as the \nrequirement “allows [] customers the opportunity to assess for themselves whether they were \nproperly charged.”26   \nThe TO Exit Provisions in proposed Section 18.17 fall short of this statutory \nrequirement and the Commission’s implementing regulations in 18 C.F.R. 35.1(a).  For \nexample, under the proposed language, a PJM Transmission Owner is required to pay “all costs \nfor RBP Resources to pseudo-tie into the PJM Region.”  The proposal does not define what \nconstitutes “all costs” or identify a limiting principle for determining when those costs have \nbeen paid, creating uncertainty regarding a Transmission Owner’s obligations under the \nprovision.   \nSimilar questions arise with respect to the requirements that a Transmission Owner \n“pay costs associated with the remaining term of the RBP Resource” and “pay all forward \nobligations on an accelerated basis.”  While PJM’s proposed language for these requirements \n \n23 18 C.F.R. § 35.1(a) (emphasis added). \n24 Cal. Indep. Sys. Operator Corp., 112 FERC ¶ 61,009 at P 114 (2005).  \n25 Id.   \n26 Id."},{"page":12,"startToken":3783,"endToken":4050,"text":"12 \nstipulates that the exact amount of these payments “shall be determined through a filing \nsubmitted under the Federal Power Act,” it is entirely unclear who (PJM, the RBP Resource, \nor the PJM Transmission Owner) would submit this filing, or what value the filing entity, \nwhoever it is, would actually request the Commission’s approval for.   \nAccordingly, PJM’s proposed Section 18.7 does not “clearly and specifically” set forth \nthe rates and charges that are to be imposed on an exiting Transmission Owner, and fails to \nsatisfy the requirements of FPA section 205(c) and the Commission’s implementing \nregulations.  At a minimum, the Commission cannot determine whether these charges are just \nand reasonable where the proposal fails to identify the scope of the obligations being imposed \nor the methodology by which they would be calculated. \nIII. \nREQUEST FOR CLARIFICATION \nPPL Electric requests that PJM provide additional clarity in its responsive pleading \nregarding its approach to a specific credit collateral contingency.  In the event that PJM does \nnot provide the requested clarity, PPL Electric respectfully requests that the Commission \narticulate its expectations regarding this contingency, and provide any additional guidance it \ndeems appropriate.    \nRegarding the collateral requirements for Load Serving Entities, PJM states that \n“[b]uyers of RBP UCAP MW, i.e., LSEs that have been allocated cost responsibility for RBP \nCharges . . . will be required to post RBP Collateral to mitigate the risk of potential defaults \nfrom non-payment of RBP Charges, while those LSEs not allocated cost responsibility \ngenerally will not have any credit requirement.”27   To this end, PJM explains that “the RPM \n \n27 RBP Filing at 111."},{"page":13,"startToken":4050,"endToken":4338,"text":"13 \ncredit requirement will be based on the level of RBP UCAP MW for which an LSE is allocated \ncost responsibility.”28   \nHowever, PJM then explains that “for LSEs serving load in an Electric Distributor \nzone/area in which no RBOs have been reported, an LSE’s ‘allocated RBP UCAP MW shall \nequal the Load Serving Entity’s pro-rata share of the Daily Unforced Capacity Obligation for \nthe zone/area as determined in RAA, Schedule 8.’”29  PPL Electric understands that if there \nare no RBOs reported to PJM for a zone with RBP UCAP MW assigned, or if there are \n“stranded” RBOs (because of how state or local regulatory authorities determine they should \nbe assigned) then the credit requirements will move to all Load Serving Entities in a zone based \non Peak Load Contributions reported to PJM.  Presumably, once credit requirements are \nassigned based on Peak Load Contributions, RBP charges will also flow to those Load Serving \nEntities for that Delivery Year, and possibly beyond. \nPPL Electric is concerned that this scenario could result in LSEs that do not serve large \nloads receiving these obligations, thereby having nowhere to assign them except to other (non-\nlarge load) customers.  This seems inconsistent with the Ratepayer Protection Pledge.30    PPL \nElectric requests that PJM provide guidance on what would happen if the additional Load \nServing Entities in the zone are unable to post collateral and default under this contingency.  \nIV. \nCONCLUSION \nWherefore, for the foregoing reasons, PPL Electric respectfully requests that the \nCommission grant PPL Electric’s timely intervention in this proceeding and accept this \n \n28 Id. at 118. \n29 Id.  \n30 \nRatepayer \nProtection \nPledge, \nThe \nWhite \nHouse \n(Mar. \n4, \n2026),  \nhttps://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/ (“Ratepayer Protection Pledge”)."},{"page":14,"startToken":4338,"endToken":4454,"text":"14 \nLimited Protest into the record.  PPL Electric also requests that PJM provide additional clarity \nin its responsive pleading regarding its approach to the specific credit collateral contingency \noutlined above, and if PJM does not, that the Commission articulate its expectations regarding \nthis contingency, and provide any additional guidance it deems appropriate. \n \nRespectfully submitted, \n \nSteven Nadel \nSenior Counsel \nPPL Services Corporation  \n645 Hamilton Street, Suite 601  \nAllentown, PA 18101  \nTel: (610) 774-4102 \nSMNadel@pplweb.com \n/s/ Thomas DeVita      \nThomas S. DeVita \nKimberly B. Frank \nK&L Gates LLP  \n1601 K Street, N.W.  \nWashington, DC 20006 \nTel: 202.778.9064 \nkimberly.frank@klgates.com \nthomas.devita@klgates.com \n \nCounsel for PPL Electric \nDated: August 21, 2026"},{"page":15,"startToken":4454,"endToken":4512,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary in this proceeding. \n \nRespectfully submitted, \n/s/ Stuart Robbins \nK&L Gates LLP \n1601 K Street, N.W. \nWashington, DC 20006 \nTel: 202-778-9148 \nstuart.robbins@klgates.com \n \nDated: August 21, 2026"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":679,"startToken":0,"endToken":400},{"p":2,"at":679,"title":"I. MOTION TO INTERVENE","method":"printed heading","endPage":3,"endAt":619,"startToken":400,"endToken":697},{"p":3,"at":619,"title":"II. LIMITED PROTEST","method":"printed heading","endPage":3,"endAt":752,"startToken":697,"endToken":718},{"p":3,"at":752,"title":"A. The TO Exit Provisions Concern Transmission Owner Rights and Obligations","method":"printed heading","endPage":7,"endAt":472,"startToken":718,"endToken":2021},{"p":7,"at":472,"title":"B. The TO Exit Provisions Raise Standards of Conduct Concerns, Allocate","method":"printed heading","endPage":9,"endAt":247,"startToken":2021,"endToken":2723},{"p":9,"at":247,"title":"C. The TO Exit Provisions Address a Contingency That PJM Acknowledges Is","method":"printed heading","endPage":10,"endAt":1159,"startToken":2723,"endToken":3299},{"p":10,"at":1159,"title":"D. The Vagueness of PJM’s Transmission Owner Exit Provisions Violates FPA","method":"printed heading","endPage":12,"endAt":855,"startToken":3299,"endToken":3917},{"p":12,"at":855,"title":"III. REQUEST FOR CLARIFICATION","method":"printed heading","endPage":13,"endAt":1456,"startToken":3917,"endToken":4286},{"p":13,"at":1456,"title":"IV. CONCLUSION","method":"printed heading","endPage":15,"endAt":0,"startToken":4286,"endToken":4454},{"p":15,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":15,"endAt":373,"startToken":4454,"endToken":4512}]}