{"document":{"slug":"rec-20260821-5105","title":"Comments of the Solar Energy Industries Association in response to PJM Interconnection, L.L.C.’s Reliability Backstop Procurement proposal","issued":"2026-08-21","accession":"20260821-5105","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"Solar Energy Industries Association","kind":"comments","file":"sources/filings/text/20260821-5105_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5105","tier":"record","sha256":"40a7a394cb93a51d7ee54a026e31bbb939e260a539ba6478939540f0995a53e4","pages":14,"tokens":4195,"emptyPages":[],"textThemes":["adequacy","cost","study"]},"pages":[{"page":1,"startToken":0,"endToken":287,"text":"UNITED STATES OF AMERICA\nBEFORE THE\nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \n) \n) \n)\nDocket No. ER26-3380-000\nCOMMENTS OF THE SOLAR ENERGY INDUSTRIES ASSOCIATION \nPursuant to Rule 213 of the Federal Energy Regulatory Commission’s (“Commission”) \nRules of Practice and Procedure,1 the Solar Energy Industries Association (“SEIA”)2 hereby \nsubmits these comments in response to PJM Interconnection, L.L.C.’s (“PJM”) filing proposing a \nReliability Backstop Procurement (“RBP Proposal”). PJM filed the RBP Proposal pursuant to \nSection 205 of the Federal Power Act (“FPA”),3 proposing revisions to the PJM Open Access \nTransmission Tariff (“Tariff”) and the Reliability Assurance Agreement Among Load Serving \nEntities (“RAA”) to establish a one-time procurement mechanism to address resource adequacy \nshortfalls in the PJM Region.4 As set forth below, SEIA does not oppose the RBP Proposal and \nsubmits these comments to identify targeted areas where the Commission and PJM may wish to \nconsider refinements that could further unlock capacity participation and reduce procurement \ncosts. \n1 18 C.F.R. § 385.213 (2026). \n2 SEIA is the national trade association of the solar energy industry. As the voice of the industry, SEIA works to \nsupport solar as it becomes a mainstream and significant energy source by expanding markets, reducing costs, \nincreasing reliability, removing market barriers, and providing education on the benefits of solar energy. The \ncomments contained in this filing represent the position of SEIA as a trade organization on behalf of the solar industry, \nbut do not necessarily reflect the views of any particular member with respect to any issue. \n3 16 U.S.C. § 824d (2024). \n4 Capitalized terms not defined herein have the same meaning as in the PJM Tariff, RAA or the RBP Proposal, as \napplicable."},{"page":2,"startToken":287,"endToken":622,"text":"2 \nI.\nINTRODUCTION\nSEIA does not oppose PJM’s RBP Proposal as a necessary and timely response to the \nresource adequacy challenges facing the PJM Region. The recent Base Residual Auctions \n(“BRAs”) for the 2027/2028 and 2028/2029 Delivery Years each cleared 5.6% below the PJM \nRegion Installed Reserve Margin of 20%,5 driven primarily by unprecedented additions of large \nloads—particularly data centers—that have outpaced supply additions. PJM’s proposal to conduct \na one-time backstop procurement to secure approximately 6,831.3 MW of Unforced Capacity \n(“UCAP”) is a reasonable mechanism to address this shortfall, particularly given the immense \npressure from states, governors, and the White House for PJM to act expeditiously.6\nIndeed, the RBP Proposal represents a measured approach to address a serious reliability \nconcern. PJM has designed the procurement initiative to balance urgency with market principles—\nincluding a pay-as-bid structure,7 a bilateral contracting offset mechanism,8 and a Contract for \nDifference (“CfD”) settlement approach that mitigates ratepayer costs. While SEIA commends \nPJM for bringing this proposal forward under extraordinary time constraints, SEIA respectfully \noffers the following comments to identify areas where the Commission and PJM may wish to \nconsider refinements that could further unlock capacity participation and reduce procurement \ncosts—both in connection with the RBP and, where applicable, in the broader capacity market \nreforms that PJM and the Commission may undertake in subsequent proceedings. \n5 See RBP Proposal at 124 (explaining that the 2027/2028 and 2028/2029 Base Residual Auctions each cleared 5.6% \nbelow the PJM Region Installed Reserve Margin of 20%). \n6 See Statement of Principles Regarding PJM, National Energy Dominance Council, 1 (Jan. 16, 2026), available at: \nhttps://www.energy.gov/documents/statement-principles-regarding-pjm (“NEDC/PJM Governors’ Principles”) \n(calling for a backstop auction no later than September 2026). \n7 See RBP Proposal at 65–67 (proposing a pay-as-bid clearing structure for the RBP). \n8 See id. at 35–42 (describing the Qualifying RBP Offset UCAP MW mechanism by which bilateral contracts reduce \nthe procurement target)."},{"page":3,"startToken":622,"endToken":971,"text":"3 \nII.\nCOMMENTS \nA.\nELCC Uncertainty and Commercial Operation Date Requirements May \nLimit Timely Capacity Participation. \nThe RBP Proposal requires successful resources to commit to a fixed period of 15 Delivery \nYears beginning with the 2028/2029 Delivery Year9 and to achieve commercial operation \n(“COD”) by no later than June 1, 2032. While SEIA does not oppose the 15-year term or the COD \nrequirement, it identifies two concerns with how these parameters interact with existing capacity \nmarket rules in ways that may limit participation and increase procurement costs.  \nFirst, there is a temporal mismatch: the RBP is designed to address a shortfall beginning in \nthe 2028/2029 Delivery Year, yet resources are not required to achieve COD until June 1, 2032. \nSEIA notes that PJM’s proposed clearing structure10 partially addresses this concern by ranking \noffers first by the earliest Delivery Year in which capacity would be available and then by least \ncost—thereby prioritizing resources that can deliver capacity sooner. However, the COD deadline \nitself warrants further attention, as discussed below.11\nSecond, the 15-year commitment exposes resources to long-duration ELCC variability that \nis difficult or impossible for an individual resource to underwrite—a challenge that exists \nindependent of PJM’s clearing structure and that may deter participation from resources that could \notherwise contribute to meeting the reliability need. \nWhile PJM captures ELCC decline in its published 10-year forecast, PJM has not published \na forecast out to 15 years.12 An individual RBP resource cannot control, predict, or hedge its ELCC \n9 See RBP Proposal at 34. \n10 See Proposed Tariff, Attachment DD, section 18.5(f)(ii) (providing that RBP Sell Offers shall be selected “in rank \norder from earliest to latest offered Delivery Year, and then in least-cost order based on the levelized cost ($/MW-\nday) of UCAP MW over the fixed 15-year term, until the Final RBP Target is satisfied”). \n11 See id. at 39. \n12 See PJM Interconnection, L.L.C., Preliminary ELCC Class Ratings for Period 2026/2027 Through 2034/2035, \navailable \nat: \nhttps://www.pjm.com/-/media/DotCom/planning/res-adeq/elcc/preliminary-elcc-class-ratings-for-\nperiod-2026-2027-through-2034-2035.ashx."},{"page":4,"startToken":971,"endToken":1360,"text":"4 \naccreditation 10 to 15 years into the future. The result is that rational developers will either embed \na disproportionate risk premium in their bids or decline to participate.13 SEIA supports the concept \nof a fixed-for-floating ELCC mechanism—whereby a resource’s RBP contract volume would be \nset based on PJM’s published ELCC forecast at the time of commitment, while year-over-year \nvariance between the forecast and actual ELCC flows into RPM settlement, where such variability \nalready manifests annually for all resources. This approach would decouple the developer’s long-\nterm revenue certainty from uncontrollable ELCC fluctuations, yielding lower, more competitive \nbid prices.14\nTurning to the COD requirement, the June 1, 2032 deadline is too late to address the \nimmediate shortfall PJM faces. The 2028/2029 BRA cleared 6,831.3 MW short of the PJM Region \nReliability Requirement.15 PJM should not have to wait four years for generation to come online. \nSolar, energy storage, and demand response resources—which have the shortest construction \ntimelines of any asset class—are the marginal resources of capacity during this period and can \ndeliver timely UCAP. At the same time, because PJM’s transmission expansion planning process \naddresses deliverability needs reactively—identifying and constructing network upgrades only \nafter capacity has been committed—larger resources that require significant network upgrades to \nbecome deliverable may not achieve full deliverability by June 1, 2032. This is particularly true \ngiven documented network upgrade construction timelines of three to five years or more in the \n13See REV Renewables, LS Power, Middle River Power & Geronimo Power, PJM Reliability Backstop Procurement \nDesign — Executive Summary, at 2 (June 30, 2026), available at: https://www.pjm.com/-/media/DotCom/committees-\ngroups/cifp-rbp/2026/20260630/20260630-item-02k---rev-renewables--ls-power---mrp---geronimo---rbp---\nexecutive-summary.pdf. \n14See id. (explaining that an individual RBP resource cannot control, predict, or hedge its ELCC accreditation 10 to \n15 years into the future, and that unhedgeable long-duration ELCC uncertainty will command a risk premium above \nexpected loss); see also MN8 Energy, Feedback on Select RBP Design Components, at 3 (June 11, 2026), available \nat: https://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260611/20260611-item-04d---mn8-\nenergy-presentation.pdf (proposing a fixed-for-floating class ELCC mechanism and noting that today’s project \nfinancing environment necessitates conservative views on capacity attributes, which is reflected in higher bid prices). \n15 See RBP Proposal at 7."},{"page":5,"startToken":1360,"endToken":1733,"text":"5 \nPJM region. PJM itself publicly acknowledged in a January 2026 stakeholder meeting that \nsignificant new capacity additions are unlikely to come online before 2032 due to, among other \nfactors, transmission constraints.16 While the COD requirement cannot account for all real-world \nissues,17 this limitation should be considered in evaluating the effectiveness of the RBP. SEIA \ntherefore urges PJM to prioritize timely UCAP and to ensure that resources capable of delivering \ncapacity sooner are appropriately valued. \nIn light of these challenges, SEIA encourages the Commission and PJM to provide greater \ncapacity certainty to all resources to maximize participation in the RBP. This includes stability in \nELCC accreditation values and broader capacity market reforms that would give prospective \nparticipants confidence in projecting their obligations and revenues over the commitment period. \nThe RFI administered by Charles River Associates identified over 100 GW of prospective supply \ninterested in participating;18 ensuring that market rules support—rather than discourage—this \nparticipation is essential to achieving the lowest possible procurement costs for ratepayers. \nAccordingly, SEIA recommends that PJM and the Commission address ELCC accreditation \nuncertainty and prioritize timely UCAP delivery—both of which would expand the pool of \ncompetitive offers and reduce procurement costs for ratepayers. \n16 See Devin Leith-Yessian, Government-Proposed “Backstop” Auction to Test PJM Stakeholder Process, RTO\nINSIDER (Jan. 26, 2026), available at: https://www.rtoinsider.com/124178-government-proposed-backstop-auction-\ntest-pjm-stakeholder-process/ (“Even with a backstop auction, [David] Mills [PJM board chair and interim CEO] said \nthere are significant barriers to getting new resources built, including transmission upgrades, financing, tariffs, siting, \npermitting and supply chain constraints. Significant new capacity is unlikely to be available until 2032.”). \n17 See PJM Interconnection, L.L.C., 195 FERC ¶ 61,197, at P 43 (2026); see also PJM Interconnection, L.L.C., 190 \nFERC ¶ 61,084, at P 157 (2025). \n18 See RBP Proposal at 68 (noting the RFI administered by Charles River Associates identified over 100 GW of \nprospective supply interested in participating); see also PJM Reliability Backstop RFI Summary, Charles River \nAssociates, at 5 (May 27, 2026), available at: https://www.pjm.com/-/media/DotCom/committees-groups/cifp-\nrbp/2026/20260527/20260527-informational-only---reliability-backstop-rfi-summary---charles-river-associates.pdf\n(reporting 397 potential supply-side projects by 87 entities, representing approximately 136 GW in total potential \ncapacity)."},{"page":6,"startToken":1733,"endToken":2026,"text":"6 \nB.\nThe Compressed Timeline for Bilateral Contracting May Result in Higher \nProcurement Costs. \nThe compressed timeline for the RBP procurement window may limit bilateral contracting \nopportunities and result in unnecessarily higher auction clearing prices. While SEIA does not \noppose the RBP Proposal in principle, it notes that without sufficient time for load-serving entities \nand prospective suppliers to negotiate bilateral contracts, the Qualifying RBP Offset mechanism \nmay not achieve its intended effect of reducing the procurement target. PJM is targeting \ncommencement of the procurement window on September 30, 2026, with a three-week offer \nsubmission window and clearing concluding six weeks thereafter.19\nIndeed, the RBP Proposal appropriately incorporates a mechanism by which bilateral \ncontracts and self-supply arrangements for new capacity serving new load reduce the Initial RBP \nTarget through the Qualifying RBP Offset. In theory, this mechanism should exert downward \npressure on auction prices by reducing the quantity of capacity that must be procured through the \ncompetitive auction process.20 However, SEIA is concerned that the accelerated timeline from \nPJM Board approval on July 27, 2026, to the anticipated September 30, 2026 procurement \ncommencement may not provide sufficient opportunity for load-serving entities and prospective \nsuppliers to negotiate and execute the bilateral contracts that would qualify as offsets. In turn, if \nthe time available for bilateral contracting proves insufficient, fewer Qualifying RBP Offsets may \nbe available to reduce the Final RBP Target, and the resulting auction may clear a larger volume \nof capacity at potentially higher prices than would otherwise be necessary. SEIA encourages the \nCommission and PJM to monitor the effectiveness of the bilateral contracting mechanism and to \n19 See id. at 32, 48 (describing the offer submission window of three weeks, with clearing and selection concluding \nsix weeks thereafter). \n20 See id."},{"page":7,"startToken":2026,"endToken":2305,"text":"7 \nconsider adjustments if the compressed timeline proves insufficient to support meaningful bilateral \nengagement. \nSEIA recognizes that PJM and the Commission are under immense pressure—including \nfrom the thirteen PJM-state governors and the National Energy Dominance Council, whose joint \nstatement of principles21 urged expeditious action—for this procurement to proceed on an \nexpedited basis, and that the fundamental timeline is unlikely to change. SEIA is lodging this \nconcern into the record insofar as the current RBP may set precedent for future central \nprocurements. \nC.\nRecommendations for Unlocking Additional Capacity \nIn order to enable PJM to unlock additional capacity and reduce procurement costs, SEIA \nrespectfully offers the following recommendations for the Commission’s and PJM’s consideration: \nFirst, PJM should offer a fixed-for-floating ELCC swap option for resources \nparticipating in the RBP and for bilateral arrangements qualifying as RBP Offsets. Year-over-\nyear volatility in ELCC accreditation values creates significant uncertainty for resources \ncontemplating long-term commitments such as those required by the RBP. Stabilizing ELCC \nvalues—whether through longer averaging periods22 or other mechanisms—would give \nprospective participants greater confidence in projecting their capacity revenues over the 15-year \ncommitment period and would thereby encourage broader participation. When a resource can \nreasonably forecast its accredited capacity value over the commitment term, it can underwrite \nfinancing and commit to a 15-year obligation with confidence that its revenues will support the \ninvestment. Absent such predictability, resources face the risk that declining ELCC values will \n21 See NEDC/PJM Governors’ Principles at 1. \n22 Cf. PJM Interconnection, L.L.C., 186 FERC ¶ 61,080 (2024) (accepting PJM’s transition from average to marginal \nELCC methodology, reflecting the Commission’s ongoing consideration of ELCC approaches that balance accuracy \nwith predictability)."},{"page":8,"startToken":2305,"endToken":2673,"text":"8 \nerode their revenue stream below the level needed to service project debt, deterring participation \nin the RBP altogether.\nSecond, the Commission should consider whether the minimum contract length for \nbilateral arrangements under the RBP is sufficient to enable meaningful bilateral contracting.23\nThe minimum five-year contract requirement for bilateral arrangements24 qualifying as RBP \nOffsets may be insufficient to enable meaningful bilateral contracting. While parties are free to \nnegotiate contracts of any length, the five-year minimum effectively sets a floor that, as a practical \nmatter, is likely to define the standard term for bilateral arrangements under the RBP Proposal. \nProject economics and financing structures for new capacity resources typically require a \ncommitment term closer to ten years to justify the capital investment and development risk \nassociated with new generation. To the extent the Commission can encourage bilateral contracting \nby providing clarity that longer-term bilateral arrangements are acceptable and supported under \nthe Qualifying RBP Offset framework, such action would incentivize supply participation in \nbilateral contracting and thereby reduce reliance on the auction, with attendant downward pressure \non clearing prices.\nThird, moving beyond the RBP, PJM and the Commission should pursue seasonal \ncapacity markets.25 A seasonal market construct would better align capacity obligations with the \nperiods in which resources can deliver capacity value, recognizing that different resource types \ncontribute to reliability in different seasons. Seasonal markets would enable a broader array of \n23 See Proposed Tariff, Attachment DD, section 18.2(c)(i). \n24 Proposed Tariff, Attachment DD, section 18.2(c)(i); see also RBP Proposal at 39–40 (explaining that bilateral \ncontracts must have a minimum term of at least five Delivery Years to qualify as Qualifying RBP Offset UCAP MW). \n25 See PJM Interconnection, L.L.C., 186 FERC ¶ 61,080, at P 293 (2024) (encouraging PJM to continue evaluating \nwhether and how a seasonal capacity construct could support reliability and efficiency); see also Transmittal Letter of \nPJM Interconnection, L.L.C., Docket No. ER24-99-000, at 18 (Oct. 13, 2023) (stating that “PJM and its stakeholders \nare committed to continuing to assess the design of PJM’s capacity construct, including whether and how a seasonal \ncapacity market could help support reliability and efficiency in the PJM region”)."},{"page":9,"startToken":2673,"endToken":3024,"text":"9 \nresources to participate in meeting PJM’s reliability needs, including resources whose \ncontributions are concentrated in particular seasons. Because ELCCs depend heavily on the \nbalance of reliability risk between seasons, seasonal capacity markets should also reduce ELCC \nvolatility, improving the hedging value of resources and making them easier to underwrite.26 This \nreform would complement the RBP by expanding the pool of resources willing and able to make \nlong-term capacity commitments. \nFourth, PJM and the Commission should address the commercial barriers that prevent \nsurplus interconnection service from delivering additional accredited capacity to the system.\nPJM’s surplus interconnection service allows new resources to use interconnection rights at \nexisting points of interconnection, providing a pathway for developers to add capacity to existing \nrenewable sites with minimal network upgrades and through an expedited interconnection \nprocess.27 The Commission recently accepted PJM’s proposed tariff revisions in Docket No. \nER25-778-000 to remove engineering barriers that previously blocked surplus interconnection \nrequests—including the elimination of the “materiality” review that effectively denied most \nsurplus requests before any study could be performed.28 However, significant commercial barriers \nremain that prevent surplus interconnection from delivering its full potential. \nUnder the current framework, surplus resources face a potentially unworkable choice. \nBecause PJM’s Tariff only grants capacity interconnection rights (“CIRs”) and ELCC \n26 See Comments of MN8 Energy, PJM CIFP – Large Load Additions Stakeholder Process, at 22 (Nov. 19, 2025), \navailable \nat: \nhttps://www.pjm.com/-/media/DotCom/committees-groups/cifp-lla/2025/20251119/20251119-\nstakeholder-written-comments.pdf (discussing capacity market reforms needed for a developer to enter into medium- \nto long-term contracts). \n27 See PJM Tariff, Part VIII, Subpart E, § 414 (Surplus Interconnection Service). \n28 See PJM Interconnection, L.L.C., 190 FERC ¶ 61,083, at PP 30, 33 (2025) (accepting PJM’s proposed tariff \nrevisions to remove eligibility restrictions on surplus interconnection service and facilitate the rapid expansion of \ngenerating facilities on PJM’s system); see also Comments of the Clean Energy Associations, Docket No. ER25-778-\n000, at 1–3 (Jan. 13, 2025) (“Clean Energy Associations Surplus Comments”) (urging Commission acceptance of \nPJM’s surplus interconnection reforms as a pathway to unlock GWs of storage capacity)."},{"page":10,"startToken":3024,"endToken":3416,"text":"10 \naccreditation to surplus resources that merge with the existing facility as a single hybrid resource,29\na developer seeking capacity value through surplus interconnection must elect hybrid treatment—\nwhich potentially requires unwinding existing power purchase agreements, tax equity structures, \nand lender arrangements. The alternative—interconnecting independently as a co-located \nresource—preserves independent financing but limits the surplus resource to energy-only market \nparticipation, forfeiting capacity value entirely. Because hybrid treatment requires combined \nmarket participation as a single resource,30 it does not allow for component-level settlement, and \ncapacity performance penalty risk cannot be isolated from the host resource. Lenders to the \nexisting facility will rarely consent to the addition of a surplus resource under these conditions, \nbecause it exposes the existing project to performance liability arising from a resource it does not \nown or control. This effectively renders the surplus interconnection pathway commercially \nunavailable for many projects, regardless of whether the interconnection path is clear. \nTo address these barriers and unlock the significant capacity potential of surplus \ninterconnection, SEIA recommends three reforms. First, PJM should enable surplus resources to \nobtain independently recognized and bankable capacity positions—distinct from the host \nresource—without requiring the wholesale restructuring of existing commercial arrangements. \nThis could be achieved through several mechanisms, including: (i) split UCAP settlement between \ncomponent accounts; or (ii) CIR transfer mechanisms between co-located resources.31 Whichever \n29 See PJM Tariff, Part VIII, Subpart E, § 414 (Surplus Interconnection Service); see also Hybrid Resources Market \nModel Selection—Problem Statement, PJM Interconnection, L.L.C. (Aug. 2026) (“Hybrid PS/IC”), available at: \nhttps://www.pjm.com/-/media/DotCom/committees-groups/committees/mic/2026/20260805/20260805-item-04-1---\nhybrid-resources-market-model-selection---problem-statement.pdf (recognizing that under current rules, the only \npathway for surplus resources to obtain capacity value is to become a hybrid resource with the existing project). \n30 See Hybrid PS/IC (discussing issues relating to hybrid resource combined market participation as a single market \nunit in PJM’s energy, capacity, and ancillary services markets). \n31 Under PJM’s current framework, a surplus interconnection arrangement results in a revised or amended Generation \nInterconnection Agreement for the existing facility, rather than a separate, standalone GIA for the surplus resource. \nSee PJM Tariff, Part VIII, Subpart E, § 414(B)(2) (providing that a “revised Interconnection Service Agreement or \nGeneration Interconnection Agreement will be prepared and issued to the owner of the existing or planned Generating"},{"page":11,"startToken":3416,"endToken":3726,"text":"11 \nmechanism is adopted, the objective should be to provide each component of a surplus \narrangement with independent settlement, revenue allocation, and penalty isolation necessary to \nsupport separate financing.  \nSecond, whether adopted in connection with the foregoing reforms or as a standalone \nmeasure, PJM should establish clear protections ensuring that a default or performance issue \narising from the surplus resource cannot create cross-default risk or otherwise interfere with the \nexisting resource’s GIA or operations. This protection is essential to obtaining lender consent: \nabsent an explicit structural separation of liability, lenders to the existing facility will not approve \nthe addition of a surplus resource that could jeopardize the project’s existing financing and \noperational arrangements.  \nThird, SEIA encourages PJM to evaluate whether additional resources or process \nmodifications can be devoted to surplus interconnection studies to reduce the time from application \nto completion, particularly for projects that could deliver capacity within the RBP’s timeframe. \nThe Commission’s acceptance of PJM’s Docket No. ER25-778-000 reforms removed the prior \nautomatic disqualifications that blocked surplus requests, but developers now need timely study \ncompletion to bring resources online within the timeframes contemplated by the RBP.32 Together, \nthese reforms—addressing commercial structure, lender protections, and study timelines for \nsurplus interconnection—would enable surplus interconnection to serve as a meaningful near-term \npathway for delivering additional accredited capacity to the PJM system, potentially unlocking \nFacility”). This structure means the surplus resource’s market participation, obligations, and potential liabilities are \nhoused within the existing project’s agreement, creating the cross-default risk discussed above. \n32 See PJM Interconnection, L.L.C., 190 FERC ¶ 61,083 at PP 30, 33–34 (accepting revisions that expand availability \nof surplus interconnection service and noting that PJM’s proposal “should expand the use of surplus interconnection \nservice and allow additional capacity resources to connect to the PJM system”); see also Clean Energy Associations \nSurplus Comments at 3 & n.10."},{"page":12,"startToken":3726,"endToken":4024,"text":"12 \ngigawatts of storage and other resources that are positioned to connect quickly at existing points \nof interconnection.33\nThese reforms are not prerequisites for Commission acceptance of the RBP Proposal, but \nrather constructive improvements that would enhance the effectiveness of the procurement and \naddress resource adequacy challenges on a forward-going basis. Moreover, while SEIA raises \nthese concerns in the context of the RBP, the principles underlying these recommendations—\nincluding the need for predictable capacity accreditation, sufficient time for bilateral contracting, \nand workable commercial frameworks for surplus interconnection—are not limited to this \nproceeding and warrant the Commission’s attention as it considers broader capacity market \nreforms. Indeed, the NEDC and PJM Governors’ Principles—which, as the RBP Proposal \nacknowledges, inform the design and objectives of the RBP—contemplate a subsequent “return to \nmarket fundamentals” and continued refinement of PJM’s capacity market framework,34 and these \nrecommendations are consistent with that ongoing effort. \nIII.\nCONCLUSION\nFor the foregoing reasons, SEIA respectfully submits that while the RBP Proposal \nrepresents a necessary and timely response to PJM’s resource adequacy challenges, the \nCommission should consider the refinements identified herein—including accommodations for \nbilateral contracting timelines, measures to provide capacity certainty over the commitment term, \nremoval of commercial barriers to surplus interconnection, and reforms to unlock additional \nparticipation—as it evaluates the RBP Proposal as a means of securing the timely addition of new \ncapacity. To the extent the Commission identifies opportunities to incorporate such improvements, \n33 See Clean Energy Associations Surplus Comments at 3. \n34 See NEDC/PJM Governors’ Principles at 1 (urging PJM to “embark on a stakeholder process to reform the capacity \nmarket to ensure long-term viability and prevent consumers from bearing excessive ongoing costs”); see also RBP \nProposal at 6–8 (citing and implementing the NEDC/PJM Governors’ Principles)."},{"page":13,"startToken":4024,"endToken":4149,"text":"13 \nwhether in its order on the RBP Proposal or in subsequent proceedings, doing so would further the \nshared objective of procuring sufficient capacity at the lowest reasonable cost. SEIA supports \nPJM’s effort to address the resource adequacy shortfall on an expedited basis and appreciates the \nopportunity to provide these comments. \nRespectfully submitted, \nMelissa Alfano  \nSenior Director of Energy Markets and \nCounsel  \nSolar Energy Industries Association  \n1425 K St NW Ste. 1000  \nWashington, DC 20005  \n(202) 566-2873  \nmalfano@seia.org\n/s/ Steven Shparber \nSteven Shparber \nOmar Bustami \nMintz, Levin, Cohn, Ferris, Glovsky and \nPopeo, P.C. \n555 12th Street NW, Suite 1100 \nWashington, D.C. 20004 \n(202) 434-7417 \nSShparber@mintz.com\nOBustami@mintz.com \nCounsel to the Solar Energy Industries \nAssociation \nDated: August 21, 2026"},{"page":14,"startToken":4149,"endToken":4195,"text":"CERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary in this proceeding. \nDated at Washington, DC, this 21st day of August, 2026. \n/s/ Steven Shparber \nSteven Shparber"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":3,"startToken":0,"endToken":288},{"p":2,"at":3,"title":"I. INTRODUCTION","method":"printed heading","endPage":3,"endAt":3,"startToken":288,"endToken":623},{"p":3,"at":3,"title":"II. COMMENTS","method":"printed heading","endPage":3,"endAt":17,"startToken":623,"endToken":625},{"p":3,"at":17,"title":"A. ELCC Uncertainty and Commercial Operation Date Requirements May","method":"printed heading","endPage":6,"endAt":3,"startToken":625,"endToken":1734},{"p":6,"at":3,"title":"B. The Compressed Timeline for Bilateral Contracting May Result in Higher","method":"printed heading","endPage":7,"endAt":583,"startToken":1734,"endToken":2109},{"p":7,"at":583,"title":"C. Recommendations for Unlocking Additional Capacity","method":"printed heading","endPage":12,"endAt":1105,"startToken":2109,"endToken":3878},{"p":12,"at":1105,"title":"III. CONCLUSION","method":"printed heading","endPage":14,"endAt":0,"startToken":3878,"endToken":4149},{"p":14,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":14,"endAt":290,"startToken":4149,"endToken":4195}]}