{"document":{"slug":"rec-20260821-5114","title":"Post-Conference Comments of PJM Legislators' Collaborative and the National Caucus of Environmental Legislators re PJM Governance and Stakeholder Reforms","issued":"2026-08-21","accession":"20260821-5114","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"National Caucus of Environmental LegislatorsPJM Legislators' Collaborative","kind":"comments","file":"sources/filings/text/20260821-5114_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5114","tier":"record","sha256":"24879f86d6bb66697b20d3e10225c475c3e35a462f4900a9c143d703d4508d79","pages":7,"tokens":2221,"emptyPages":[],"textThemes":["cost"]},"pages":[{"page":1,"startToken":0,"endToken":310,"text":"PJM LEGISLATORS’ COLLABORATIVE & NCEL POST-CONFERENCE COMMENTS \nUNITED STATES OF AMERICA \n \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Governance and Stakeholder Reforms  \nDocket No. AD26-7-000 \nCOMMENTS OF THE PJM LEGISLATORS’ COLLABORATIVE AND THE NATIONAL \nCAUCUS OF ENVIRONMENTAL LEGISLATORS \n \nAugust 20, 2026 \nIntroduction \nThe PJM Legislators’ Collaborative and the National Caucus of Environmental Legislators \n(NCEL) are pleased to submit these post-conference comments and appreciate the opportunity to \ncontinue engaging with the Commission on these important issues. We welcome the discussion \ngenerated by the technical conference and look forward to participating in the dispute resolution \nprocess. We remain committed to working constructively with FERC, PJM, and other \nstakeholders. \n \nThe comments below are organized into three sections. First, we provide an overview of the \nrecommendations and priorities outlined in our initial filings. Second, we provide a more \ndetailed discussion of our regional state committee proposal. Third, we respond directly to the \nquestions the Commission posed in its post-conference request for comments. We offer these \ncomments as a starting point for further discussion and are open to continued dialogue and \nnegotiation with PJM, the states, FERC, and other stakeholders to develop a governance \nframework that reflects the interests and responsibilities of the states and the ratepayers they \nrepresent.  \nPJM Legislators’ Collaborative and NCEL Governance and Stakeholder Reform \nFiling \nIn recent comments submitted to FERC, the PJM Legislators’ Collaborative and NCEL outlined \nfive key recommendations designed to improve outcomes for consumers across the region: \n●​ Establish a Public Interest Mission: Explicitly require PJM to legally balance reliability \nand affordability while serving the public interest in all major decisions. This public \ninterest mandate should be incorporated into PJM’s Operating Agreement and Section 9 \nof the Open Access Transmission Tariff.  \n●​ Strengthen the Role of States: Create a regional state committee with meaningful \nauthority to participate in market rule and cost allocation decisions. More details on this \ncommittee's structure are below. \n1"},{"page":2,"startToken":310,"endToken":733,"text":"PJM LEGISLATORS’ COLLABORATIVE & NCEL POST-CONFERENCE COMMENTS \n●​ Increase Board Independence and Accountability: Give states a role in nominating \nBoard members and ensure FERC holds the Board accountable to measurable \nperformance standards.  \n●​ Reform the Stakeholder Process: Extend weighted voting to prevent large firms and \ntheir affiliates from dominating voting, while providing consumer advocates with the \nresources to participate effectively.  \n●​ Improve Transparency: Record, publish, and archive all stakeholder and Board \nmeetings, votes, Board rationales, planning assumptions, and cost analyses. These \nproceedings influence billions of dollars in regional investments and require public \noversight. Also allow media access to all stakeholder meetings.  \nPJM State Committee Proposal \nBuilding on our original filings, the PJM Legislators’ Collaborative and NCEL propose creating \na States Committee within PJM (“PJMSC”) to represent state interests in PJM governance and \nensure state perspectives are reflected in rule and tariff changes PJM considers and files with \nFERC. Through structured, formal engagement with PJM staff and governance bodies, the \nPJMSC would represent the interests of ratepayers across the PJM region who depend on \naffordable and reliable electricity.  \nCritically, the PJMSC must include state legislator representation. Much of the work needed to \naddress PJM’s resource adequacy, reliability, and affordability challenges will require long-term \npartnership between PJM and the States. As FERC Commissioner David Rosner noted in a \nconcurring opinion, solving these challenges “will take partnership with states given their \nauthority over resource procurement and generation and transmission siting.” PJM leadership has \nmade similar comments, with Executive Vice President Asim Haque noting in a Utility Dive \nop-ed that “it will require the entire industry to work in the solutions space, including those \nworking within state frameworks, to successfully navigate through this supply/demand challenge \nand resulting affordability concerns.” \nState regulators and governors are essential partners in this process, and state legislators have a \ndistinct and equally important role. Legislatures enact the laws that establish the authority, \nmandates, and policy direction under which the executive branch and regulators operate. They \nalso play a critical role in shaping the broader policy framework, including resource \nprocurement, siting, utility regulation, and consumer protection. State legislative action is \nfrequently necessary to implement new policies, amendments, and changes to statutory authority \nthat are key to solving PJM’s reliability and affordability challenges. Excluding state legislator \nrepresentation from the PJMSC would create a critical governance gap and would undermine \nefforts to align communication and coordination between PJM and the states. \nA new state committee within PJM – with appointees from state legislatures, governors' offices, \nand regulators – would create a meaningful forum for advancing policy initiatives that integrate \n2"},{"page":3,"startToken":733,"endToken":1172,"text":"PJM LEGISLATORS’ COLLABORATIVE & NCEL POST-CONFERENCE COMMENTS \nstate lawmaking into the regional energy framework. It would also give PJM a direct, explicit \nopportunity to engage lawmakers on regional issues that require legislative action, rather than the \nindirect and ad hoc engagement it currently relies on.  \nThe Legislators’ Collaborative and NCEL propose that the PJMSC have the characteristics \noutlined below: \n●​ Establishment and funding: The PJMSC would be established and funded through the \nPJM tariff at a level sufficient to maintain robust technical staff and expertise, \nindependent of PJM management.  \n●​ State representation: Each state would be permitted to appoint up to four delegates, \nwith no more than one delegate appointed by each of the following: the Governor’s \nOffice; the relevant state regulatory agency, such as the state utility commission the state \nHouse; and the state Senate. Each state fully within PJM would receive four votes. States \nonly partially within PJM would receive two votes, with each delegate receiving one-half \nvote.1 Each individual casts their own vote, and consensus within each state is not \nrequired. \n●​ Leadership: The PJMSC would nominate and elect its own officers, including a \nPresident, Treasurer, and other leadership positions. \n●​ Shared filing rights: The PJMSC would have shared Section 205 filing rights over the \nPJM Tariff and Operating Agreement, using a “jump-ball” structure similar to those \nemployed by other RTOs. Where the PJMSC supports a proposal different from that of \nthe PJM Board, PJM would be required to file both proposals with FERC, provided the \nPJMSC proposal has received an internal simple majority of votes (if there is a tied vote, \nno action will be taken). FERC would then determine which proposal to accept. \n●​ Communication, data transparency, and information access: The PJMSC would have \nregular opportunities to meet directly with the PJM Board and engage with PJM staff, \nwith the PJM Board required to respond to meeting requests within a timely period. To \npromote transparency and informed participation, the PJMSC and its staff would be \nprovided timely access to relevant models, data, and analyses underlying proposed rule or \ntariff changes, including those related to load forecasting and resource accreditation. The \nPJMSC would also have explicit rights to commission independent studies on \naffordability, reliability, and emerging load trends.  \n \n \n \n1 Rationale: The Collaborative and NCEL determined that weighting votes based on whether a state is \nfully or partially within the PJM footprint is important to reflect the differing levels of engagement and \nvested interest in PJM between these states. This approach is preferable to weighting votes based on the \nnumber of ratepayers in PJM, which could disproportionately diminish the voice of smaller states that are \nfully within the PJM footprint.  \n3"},{"page":4,"startToken":1172,"endToken":1476,"text":"PJM LEGISLATORS’ COLLABORATIVE & NCEL POST-CONFERENCE COMMENTS \n \nPost Conference Comments \n \nPJM Board Independence \n \n \nQuestions/Comments \nYes \nNo \n1) \nShould Board members’ terms be extended to five or more years? \nX \n \n \nComments: Yes, to insulate members from retention concerns when making difficult decisions. \n \n2) \nShould there be a maximum number of years that a Board member may serve (e.g., 10 \nyears)? \nX \n \n \nComments: \n3) \nShould the Board member qualification rules be revised to provide a preference for some \nBoard members that reside in the PJM region? \n \n \n \nComments:   \n4) \nShould the conflict-of-interest rules be revised to reduce the cooling-off period for Board \nmembers from two years to one year? \n \n \n \nComments:  \n5) \nShould restrictions on Board communications be relaxed to enable more communication \nbetween the Board and stakeholders? \nX \n \n \nComments: Yes, the current restrictions prevent otherwise fruitful discussions between the Board and \nstakeholders, particularly with state policy actors, including legislators and governors.  \n6) \nIn order to increase transparency, should Board votes be made public or the Board be \nrequired to explain its reasoning?  \nX \n \n \nComments: Decisions made at the Board level ultimately result in billions of dollars in costs for 67 million \nratepayers, and those bearing the costs have a right to understand the evidence and rationale behind those \ndeterminations. Requiring public votes and written justifications, detailing the specific problems addressed, \nthe alternatives considered, and the projected cost impacts, would ensure that Board decisions are not \narbitrary and are truly aligned with the public interest. \n7) \nIn order to increase transparency, should some Board meetings be open or available to the \npublic? \nX \n \n \nComments: Yes, we recommend that PJM record and archive all Board and stakeholder meetings in a \nsearchable database.  \n8) \nShould PJM’s governing documents be revised to explicitly state that the responsibility of \nPJM and its Board is to serve the public interest? \nX \n \n4"},{"page":5,"startToken":1476,"endToken":1827,"text":"PJM LEGISLATORS’ COLLABORATIVE & NCEL POST-CONFERENCE COMMENTS \n \nQuestions/Comments \nYes \nNo \n \nComments:  This is a top priority for legislators who work to serve the public interest and need a partner in \nPJM to do the same. It is also consistent with other regions, where the ISOs/RTOs are already organized as \nnon-profit or public benefits organizations.  \n9) \nShould state representatives have at least one voting member on the Nominating Committee? \nX \n \n \nComments: States need at least 3 representatives on the Nominating Committee (one legislator, regulator, \nand governors’ representative). One representative on the Nominating Committee will be ineffective at \nensuring state perspectives are considered; therefore, three members is the minimum the Commission \nshould consider. The PJM State Committee would choose the representatives.   \n10) \nShould PJM adopt public performance metrics and tie management compensation to their \nachievement? \nX \n \n \nComments: Yes, but this needs to be done very carefully to ensure it aligns with public interest goals. In \naddition, on page 6 of the PJM Legislators’ Collaborative filing, we recommend “formal and quantifiable \nperformance metrics that the Board should be held accountable to,” including “load forecasting and queue \nexecution speed as performance metrics.”   \n \nSection 205 Filing Rights \n \n \nQuestions/Comments \nYes \nNo \n11) \nShould the stakeholder process be advisory, i.e., stakeholder votes only inform the Board? \n \n \n \nComments:  \n12) \nShould PJM have section 205 filing rights over the energy market and ancillary services \nunencumbered by the requirement to obtain approval of two-thirds of the Members \nCommittee? \nX \n \n \nComments: Yes, but this must  be accompanied by the public interest criteria incorporated into the PJM \nGoverning documents and Section 9 of the Open Access Transmission Tariff. \n13) \nShould PJM have section 205 filing rights over Regional Transmission Expansion Planning \n(RTEP) unencumbered by the requirement to obtain approval of two-thirds of the Members \nCommittee? \nX \n \n \nComments:   \n14) \nShould the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource \nadequacy and transmission cost allocation filings when a supermajority of OPSI agrees on \nan alternative proposal? \n \n \n \nComments: A regional state committee — including regulators, state legislators, and Governors —  \nshould have filing rights over PJM’s Tariff and Operating Agreement.  \n5"},{"page":6,"startToken":1827,"endToken":2197,"text":"PJM LEGISLATORS’ COLLABORATIVE & NCEL POST-CONFERENCE COMMENTS \n \nQuestions/Comments \nYes \nNo \n15) \nShould the Members Committee have “jump ball” filing rights over the portions of the \ntariff where PJM has 205 filing rights when a supermajority of stakeholders approves an \nalternative proposal? \n \n \n \nComments:  \n \nStakeholder Process \n \n \nQuestions/Comments \nYes \nNo \n16) \nShould the approval threshold in the Members Committee be lowered from two-thirds \nsector-weighted voting? \nX \n \n \nComments: The current two-thirds requirement allows relatively small coalitions of stakeholders to block \nproposals indefinitely. The Collaborative’s core recommendation is for FERC to \"enhance the Board’s \nability to act when stakeholder processes reach deadlock.” This would ensure the Board has the flexibility \nto prioritize the public interest even when the stakeholder process fails to reach the two-thirds consensus. \n17) \nShould the voting rules barring affiliate votes, which apply to senior standing committees, \nalso apply to lower-level committees? \nX \n \n \nComments: Yes, affiliate votes can dominate lower-level committees.  \n \nState Participation \n \n \nQuestions/Comments \nYes \nNo \n18) \nIn addition to OPSI, should there be a second state representative group consisting of \ngovernors’ representatives and/or state legislators’ representatives? \nX \n \n \nComments: Yes to state representatives, but no to a separate group. We recommend one singular state \nrepresentative group consisting of governors’ representatives, state legislators’ representatives, and \nregulator representatives. This organization should be able to come and seek reasonable amounts of \nfunding from PJM.  \n19) \nShould state representatives have a formal voting role in the stakeholder process (limited to \ncertain topics, such as resource adequacy and regional transmission cost allocation) in \naddition to the consumer advocate votes?   \nX \n \n \nComments: First and foremost, create a regional state committee for regulators, Governors’ offices, and \nlegislators to weigh in at a higher level than the stakeholder process. In addition, state representatives \nshould have formal voting rights, but this must not be treated as a binary trade-off for a regional state \ncommittee, independent state filing rights, the integration of a public interest standard into PJM \ndecision-making, and a direct state voice on the board nominating committee. Voting rights must also be \npaired with fundamental reforms to the sector-weighted voting process.  \n20) \nShould PJM be required to consult with OPSI prior to making a section 205 filing related to \nresource adequacy and transmission cost allocation? \nX \n \n6"},{"page":7,"startToken":2197,"endToken":2221,"text":"PJM LEGISLATORS’ COLLABORATIVE & NCEL POST-CONFERENCE COMMENTS \n \nQuestions/Comments \nYes \nNo \n \nComments:  PJM should be required to consult with the new regional state committee.  \n \n7"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":317,"startToken":0,"endToken":38},{"p":1,"at":317,"title":"Introduction","method":"printed heading","endPage":7,"endAt":186,"startToken":38,"endToken":2221}]}