{"document":{"slug":"rec-20260821-5120","title":"Partial Protest and Comments of Dominion Energy Services, Inc. re PJM Interconnection, L.L.C.’s Reliability Backstop Procurement proposal","issued":"2026-08-21","accession":"20260821-5120","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"Dominion Energy Services, Inc.","kind":"protest","file":"sources/filings/text/20260821-5120_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5120","tier":"record","sha256":"4d2e1cc7ed2f4151e26cff006bf23aa71b5fdfcdb07d82b2eab21dab2e0721a3","pages":10,"tokens":2991,"emptyPages":[],"textThemes":["adequacy","cost"]},"pages":[{"page":1,"startToken":0,"endToken":270,"text":"1 \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM Interconnection, L.L.C. \n) \n) \n) \nER26-3380-000\n \n \nPARTIAL PROTEST AND COMMENTS OF DOMINION ENERGY SERVICES, INC. \n \n \nPursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“FERC” or “Commission”),1 Dominion Energy Services, Inc. on behalf \nof its affiliate, Virginia Electric and Power Company d/b/a Dominion Energy Virginia (“Dominion \nEnergy”), hereby submits the following generally supportive comments and partial protest with \nrespect to PJM’s proposed rules in the above captioned proceeding that would establish a one-time \nprocurement for new capacity to address resource adequacy challenges in the PJM Region.2   \nDominion Energy Virginia, a subsidiary of Dominion Energy, Inc., is a public service \ncorporation organized under the laws of the Commonwealth of Virginia and a public utility subject \nto regulation by the Commission and does business in the Commonwealth of Virginia and in the \nState of North Carolina. It is a regulated, vertically integrated public utility engaged in the \ngeneration, transmission, distribution, and sale of electric energy. Dominion Energy Virginia \nfurnishes electric service to approximately 2.8 million retail customers in its approximately 30,000 \nsquare miles of certificated service territory covering parts of Virginia and North Carolina. To \nprovide that service, Dominion Energy Virginia owns and operates a diverse fleet of nuclear, oil, \nbiomass, pumped storage, hydro, coal, solar, wind and natural gas-fired electric generating \n \n1 18 C.F.R. §§ 385.211 (2026). \n2 PJM Interconnection, L.L.C., Docket No. ER26-3380-000) (July 31, 2026)(“PJM Filing”). Dominion Energy filed \na “doc-less” intervention in this proceeding on August 4, 2026."},{"page":2,"startToken":270,"endToken":690,"text":"2 \n \ncapacity of approximately 21,000 megawatts. Dominion Energy Virginia owns 6,800 miles of \nelectric transmission lines in Virginia, North Carolina and West Virginia, which is operated by \nPJM. Dominion Energy Virginia joined PJM effective May 1, 2005, after obtaining prior approval \nfrom the Commission, the Virginia State Corporation Commission, and the North Carolina Utilities \nCommission.3 \nI. \nIntroduction \nThe PJM Filing proposes reforms to the PJM Open Access Transmission Tariff (“Tariff”) \nand the Reliability Assurance Agreement to establish a Reliability Backstop Procurement (“RBP”) \nthat creates a one-time procurement of new, incremental capacity to address ongoing resource \nadequacy challenges in the region that are driven by unprecedented load growth from large load \nin the PJM region.4  While PJM’s proposed RBP is a product of the Critical Issue Fast Past \n(“CIFP”) process, it is one of several feasible solutions that are aligned with the National Energy \nDominance Council’s (“NEDC”) and the PJM Governors’ statement of principles (“Statement of \nPrinciples”) and the PJM Board Letter.5   PJM proposes to commence the RBP on September 30, \n2026 to procure new capacity in response to the capacity shortfalls observed in the Reliability \nPricing Model (“RPM”) Auctions for the 2027/2028 and 2028/2029 Delivery Years (“DY”).6 \n \n3 PJM Interconnection, L.L.C., 109 FERC ¶ 61,012 (2004), on reh’g in part, 110 FERC ¶ 61,234 (2005); Ex Parte: \nIn the matter concerning the application of Virginia Electric and Power Company d/b/a Dominion Virginia Power \nfor approval of a plan to transfer functional and operational control of certain transmission facilities to a regional \ntransmission entity, V.S.C.C. Case No. PUE-2000-00551, Order Granting Approval (Nov. 10, 2004); In the Matter \nof Application of Virginia Electric and Power Company, d/b/a Dominion North Carolina Power, for Authority to \nTransfer Functional Control of Transmission Assets to PJM Interconnection, LLC, N.C.U.C. Docket No. E-22, Sub \n418, Order Approving Transfer Subject to Conditions (Apr. 19, 2005). \n4 Capitalized terms not otherwise defined herein have the meaning as defined in the Tariff, Amended and Restated \nOperating Agreement of PJM (“Operating Agreement”), RAA, and Consolidated Transmission Owners Agreement \n(“CTOA”). \n5 Statement of Principles Regarding PJM, National Energy Dominance Council, 2 (Jan. 16, 2026)(available at \nhttps://www.energy.gov/documents/statement-principles-regarding-pjm). Board Decisional Letter on Critical Issue \nFast Path - Large Load Additions, PJM Interconnection, L.L.C, (January 16, 2026)(available at \nhttps://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-disclosures/2026/20260116-pjm-board-\nletter-re-results-of-the-cifp-process-large-load-additions.pdf).   \n6 PJM Filing at p. 27."},{"page":3,"startToken":690,"endToken":1009,"text":"3 \n \nAs explained below, Dominion generally supports the RBP as a one-time procurement to \nbring the PJM region to a more stable state of resource adequacy and pave the way for holistic \nmarket design reforms that will support the infrastructure needed to reliably serve load growth in \nthe region.  However, Dominion Energy believes aspects of the PJM Filing’s proposed cost \nallocation for the RBP are unjust and unreasonable in the way that they determine each Electric \nDistributor (“ED”) zone/area’s share of the Final RBP Target.  Dominion Energy respectfully \nrequests the Commission approve the PJM Filing subject to PJM submitting a compliance filing \nto adjust the allocation methodology. \nII. \nComments \nThe RBP is not an answer to PJM’s resource adequacy problem but is a necessary stop-gap \nsolution to stabilize the region and allow for a more holistic review of the markets.  The PJM \nregion must address near-term deficiencies to begin focusing on the long-term solution, which is \nwhy Dominion Energy supports the RBP.  Ideally, the combination of PJM’s wholesale markets, \nresource adequacy and transmission planning, interconnection processes, and market participant \nobligations work together to reliably and affordably build out the infrastructure necessary to \nsupport future load growth.  PJM is not there yet, and it may take several years for any holistic \nreforms to have an impact.  For this reason, the RBP presents an opportunity to bring resource \nadequacy up to PJM’s reliability requirement through the procurement of new dispatchable \ngeneration needed in the region.    However, it is important to recognize that the ability of the RBP \nto attract significant new investment is because it offers long-term certainty required by developers \nthat is currently not afforded in the Reliability Pricing Model (“RPM”) design.  Future reforms of \nthe capacity and energy markets must address this issue: a 3-year forward auction sending a one-\nyear price signal can no longer be the sole means to attract the generation needed to meet future"},{"page":4,"startToken":1009,"endToken":1349,"text":"4 \n \nload growth.  The bilateral matching process initiated by PJM is a good first step to promoting the \ntypes of long-term contracting needed to attract new capacity outside the RPM Base Residual \nAuction (“BRA”), but future reforms must examine whether the incentives and obligations for \nLoad Serving Entities bringing on new large loads in the region is sufficient to bring the new \ncapacity required.7 \nIII. \nPartial Protest \nA. PJM’s proposed methodology for allocating the Final RBP Target to individual \nED zone/areas is unjust and unreasonable. \n \nDominion does not oppose the underlying principle of PJM’s cost allocation approach for \nthe RBP.  Recognizing that much of the shortfall experienced in the last two capacity auctions is \nattributable to Large Load adjustments added to the load forecasts, PJM proposes pro-rata \nallocation to ED zone/areas based on their share of forecasted load growth between the 2026/2027 \nand 2028/2029 Delivery Years (“MW Load Adjustment Share”).8  However, PJM’s proposed two-\nstep process fails to recognize that a portion of each ED zone/area’s Incremental Large Load Share \nwas covered by the past two capacity auctions.  Instead, PJM would require ED zone/areas seeking \nto fully offset their potential RBP allocation to demonstrate a capacity offset equivalent to their \nentire MW Load Adjustment Share rather than just their Initial RBP Target allocation.9  This leads \nto potential double charging for capacity requirements and is unjust and unreasonable.  \nTo understand the issue, it is probably best to first consider what should be the appropriate, \njust and reasonable RBP Target allocation and offset methodology and then contrast that with what \nPJM proposes.  Dominion agrees with PJM’s first step in the process whereby the Initial RBP \n \n7 Id. at p.30. \n8 Id. at p. 31. \n9 Id. at p. 32 (“The amount of capacity by which Qualifying RBP Offset UCAP MW may reduce the Initial RBP \nTarget will also be capped at the Load Adjustment for each Electric Distributor zone/area amount of summer 2028 \ndemand as set forth in the load forecast.”)"},{"page":5,"startToken":1349,"endToken":1682,"text":"5 \n \nTarget is allocated to each ED zone/area based on their ratio share of the forecasted load growth \nfrom the 2026/2027 Delivery Year to the 2028/2029 Delivery Year.10  Each ED zone/area then \nknows how much of the RBP UCAP MW they will be responsible for if there is no offsetting \ncapacity submitted to PJM.  If an ED zone/area has Qualifying RBP Offset UCAP MW (“RBP \nOffset”), it should be able to reduce their Initial RBP Target by that amount on a one for one basis.  \nFor example, if an ED zone/area has an Initial RBP Target allocation of 1000 UCAP MW and \ndemonstrates 900 UCAP MW of RBP Offsets, it will have a 100 UCAP MW share of the Final \nRBP Target and this will become its Reliability Backstop Obligation.  If the ED zone/area submits \nenough RBP Offsets to cover its entire Initial RBP Target allocation, then it should not receive a \nReliability Backstop Obligation or any further cost allocation for the RBP.  No additional allocation \nstep should be required. \nPJM does not follow this straightforward approach. Instead of using the Initial RBP Target \nallocation as the amount that can be offset by an ED zone/area, PJM’s proposal requires the ED \nzone/area to offset its MW Load Adjustment Share.  To illustrate, the Croop Affidavit’s example \nshows one ED zone/area fully offsetting its MW Load Adjustment Share (REC) and a second ED \nzone/area partially offsetting its MW Load Adjustment Share (ODEC).11  Since PJM’s proposal is \nanchored to the MW Load Adjustment values for purposes of offset, it requires a second step that \nconverts offsetting UCAP MW into their load MW equivalent to recalculate each ED zone/area’s \nfinal percentage share of the Final RBP Target.12  There are two significant issues with this \napproach. \n \n10 Proposed Tariff, Attachment DD, section 18.3(a). \n11 PJM Filing, Affidavit of Ms. Danielle Croop (“Croop Affidavit”), at p. 12. \n12 Id. at p. 13."},{"page":6,"startToken":1682,"endToken":2037,"text":"6 \n \nFirst, requiring ED zone/areas to offset their MW Load Adjustment Share fails to recognize \nthat the BRA has already procured capacity for a portion of that MW Load Adjustment Share.  \nConsider what PJM’s proposal requires at the region-wide level. The Initial RBP Target of 6,831.3 \nUCAP MW represents the amount of UCAP MW needed to bring the PJM region back to \ncompliance with the RTO Reliability Requirement for the 2028/2029 DY.13  To fully offset the \nneed for the RBP under PJM’s proposed allocation methodology, all identified ED zone/areas \nwould need to demonstrate 8,492.1 RBP Offsets (UCAP MWs), calculated by converting the \n9,033.2 MW region-wide Load Adjustment MW by the 2028/2029 BRA Forecast Pool \nRequirement of 0.9401. As a result, ED zone/areas are being asked to bring a surplus of 1,660.8 \nUCAP MWs—not needed to meet the Reliability Requirement—to ensure they do not receive a \nportion of the Final RBP Target. This surplus capacity represents an equivalent amount of load that \nparticipated in the 2028/2029 BRA and was covered by cleared capacity, meaning the load will \npay for those capacity costs during the Delivery Year.  Requiring ED zone/areas to offset their \nentire MW Load Adjustment Share to avoid having an RBP Obligation raises the possibility that \nthey will pay for redundant capacity, which is unjust and unreasonable. \nSecond, PJM’s proposed method for allocating the Final RBP Target to ED zone/areas \npresents unjust and unreasonable risks of disproportionally benefiting ED zone/areas that have not \nsecured capacity by socializing the benefit of Opt-Outs and RBP Offsets procured in one ED \nzone/area to all ED zone/areas. As discussed above, PJM requires ED zone/areas wishing to avoid \nan RBP Obligation to bring RBP Offsets exceeding their allocation of the Initial RBP Target. PJM’s \nproposal calculates the Final RBP Target as the Initial RBP Target minus RBP Offsets and Opt-\nOuts on a 1 MW to 1 MW basis. In this calculation, any RBP Offsets brought by an ED zone/area \n \n13 Id. at p. 2."},{"page":7,"startToken":2037,"endToken":2388,"text":"7 \n \nthat surpass their allocation of the Initial RBP Target are effectively credited to other ED zone/areas \nbecause the total pool of Final RBP Target MWs that are re-allocated out to ED zone/areas has \ndecreased by more than the offset-providing ED’s portion of the Initial RBP Target. PJM’s proposal \nunjustly transfers the benefits of an RBP Offset to zone/areas that do not take on the cost-\nobligations of procuring the RBP Offset MW; a clear violation of cost causation principles. \nFurthermore, the PJM cost allocation framework breaks down when allocating the Final RBP \nTarget if at least 6,831.3 MWs of RBP Offsets have been accepted because the Final RBP Target \nwill be set to zero. ED zone/areas that did not bring RBP Offsets will still have remaining MW \nLoad Adjustment Shares but will not bear any financial consequences for not bringing RBP Offsets \nbecause their Final RBP Obligation will be 0 MWs.  \nB. Subtracting Qualifying RBP Offset UCAP MW from Initial RBP Target \nallocations is a just and reasonable methodology for determining the final \nprocurement target for individual ED zone/areas. \n \nPJM rightfully determines the region-wide Final RBP Target as the Initial RBP Target \nminus Qualifying RBP Offset UCAP MWs and UCAP obligation value of loads opting out of the \nRBP.  However, an ED zone/areas share of the Final RBP Target should not be further adjusted \nbased on a recalculation of the MW Load Adjustment values.  Simply allowing ED zone/areas to \noffset their RBP Obligation up to their share of the Initial RBP Target satisfies the overarching \nRBP objective of securing a sufficient amount of capacity for PJM to meet, not exceed, its \nReliability Requirement. It avoids the potential for load to pay twice for capacity and eliminates \nthe potential for ED zone/areas that do not bring RBP Offsets to benefit from ED zone/areas that \ndo.  If the FERC chooses to accept the PJM proposal it should do so subject to PJM submitting a \ncompliance filing that allows ED zone/areas to offset their share of the Initial RBP Target by"},{"page":8,"startToken":2388,"endToken":2764,"text":"8 \n \nproviding RBP Offset UCAP MW equal to that share and not an amount equivalent to their MW \nLoad Adjustment Share. \nDominion Energy provides the following edits to PJM’s tariff amendments in sections 18.2 \nand 18.3 to effectuate the necessary change: \n18.2 Qualifying RBP Offset UCAP MW \n \n(e) The total quantity of Qualifying RBP Offset UCAP MW verified by the Office of the \nInterconnection and used to decrement the Initial RBP Target total amount allowed for each \nzone/area will be capped at the Load Adjustment for each Electric Distributor zone/area \nshare of the Initial RBP Target as calculated in Tariff, Attachment DD, Section 18.3(a) \namount of summer 2028 demand as set forth in the load forecast. \n \n18.3 Cost Allocation of RBP Charges, Credits, and Shortfall Charges \n \n(a) Cost Allocation to Electric Distributor zone/area \n \nThe Office of the Interconnection shall allocate the Initial RBP Target MW to each Electric \nDistributor’s zone/area using that zone/area’s pro-rata share of the difference between the \nforecasted Load Adjustments for the 2026/2027 Delivery Year and the 2028/2029 Delivery \nYear. \n \nThe difference between the forecasted Load Adjustments for the 2026/2027 and the \n2028/2029 Delivery Years Initial RBP Target MW allocated to each Electric Distributor’s \nzone/area shall be reduced for the purpose of this calculation to the extent: \n \n(i) \nan Electric Distributor, LSE, Transmission Owner, or other entity provides \nthe Office of Interconnection with evidence of Qualifying RBP Offset \nUCAP MW, in accordance with Tariff, Attachment DD, section 18.2 and as \nmay be further set forth in the PJM Manuals; or \n \n(ii) \nan Electric Distributor zone/area meets one of the opt-out provisions set \nforth in accordance with Tariff, Attachment DD, section 18.1(d). \n \nThe resulting reduced MW, floored at zero, is used to calculate the zone/area’s assigned \npro-rata share of the Final RBP Target MW. The zone/area’s assigned share of the Final \nRBP Target MW shall remain constant throughout the fixed, 15-year term. \n \nThe Office of the Interconnection shall allocate the total RBP Charges, assessed daily, to \nan Electric Distributor’s zone/area on a pro-rata basis using the zone/area’s assigned share \nof the total Final RBP Target MW across all zone/areas."},{"page":9,"startToken":2764,"endToken":2936,"text":"9 \n \nC. The Commission has the authority to direct modification of the Final RPB \nTarget Allocation. \n \nPJM has consented to modification of its proposal where such modification is consistent \nwith PJM’s overarching objectives.14 This change will not affect those objectives and will in fact \nbetter align with cost allocation principles and the design of the RBP.  This change will not have \nany adverse effect on other aspects of the design and should not cause any delay. \nIV. \nCONCLUSION \nDominion Energy respectively requests that the Commission grant PJM’s proposed Tariff \nrevisions subject to PJM submitting a compliance filing for the reasons discussed above.  \n \nRespectfully submitted, \n/s/ Wesley Walker \n \nWesley Walker \nManaging Counsel \nDominion Energy Services, Inc. \n120 Tredegar Street \nRichmond, VA 23219 \n(804)-819-2345 \nwesley.walker@dominionenergy.com \n/s/ James  G. Davis \n \nJames G. Davis \nRegulatory and Market Policy Senior Strategic \nAdvisor \nDominion Energy Services, Inc. \n120 Tredegar Street \nRichmond, VA 23219 \n(804)-819-2718 \njames.g.davis@dominionenergy.com \nOn behalf of Dominion Energy Services, Inc\n \n \n \n \n14 PJM Filing at pp. 3-4."},{"page":10,"startToken":2936,"endToken":2991,"text":"10 \n \nCERTIFICATE OF SERVICE \nI hereby certify that in accordance with Rule 2010 of the Commission’s \nRules of Practice and Procedure, 18 C.F.R. § 385.2010 (2026), I have served a copy of the \nforegoing to all parties on the official service list in these proceedings.   \n \n/s/ Wesley Walker\nWesley Walker\n \n \nAugust 21, 2026"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":400,"startToken":0,"endToken":328},{"p":2,"at":400,"title":"I. Introduction","method":"printed heading","endPage":3,"endAt":700,"startToken":328,"endToken":798},{"p":3,"at":700,"title":"II. Comments","method":"printed heading","endPage":4,"endAt":409,"startToken":798,"endToken":1074},{"p":4,"at":409,"title":"III. Partial Protest","method":"printed heading","endPage":4,"endAt":432,"startToken":1074,"endToken":1077},{"p":4,"at":432,"title":"A. PJM’s proposed methodology for allocating the Final RBP Target to individual","method":"printed heading","endPage":7,"endAt":922,"startToken":1077,"endToken":2195},{"p":7,"at":922,"title":"B. Subtracting Qualifying RBP Offset UCAP MW from Initial RBP Target","method":"printed heading","endPage":9,"endAt":5,"startToken":2195,"endToken":2765},{"p":9,"at":5,"title":"C. The Commission has the authority to direct modification of the Final RPB","method":"printed heading","endPage":9,"endAt":476,"startToken":2765,"endToken":2841},{"p":9,"at":476,"title":"IV. CONCLUSION","method":"printed heading","endPage":10,"endAt":6,"startToken":2841,"endToken":2937},{"p":10,"at":6,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":10,"endAt":325,"startToken":2937,"endToken":2991}]}