{"document":{"slug":"rec-20260821-5122","title":"Comments of MAREC Action and Solar Energy Industries Association re PJM Governance and Stakeholder Reforms","issued":"2026-08-21","accession":"20260821-5122","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"Solar Energy Industries AssociationMAREC Action","kind":"comments","file":"sources/filings/text/20260821-5122_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5122","tier":"record","sha256":"cd38936dd9d7840bef3ba5212e17a566acc423926cd23e6120c3312798ae74fa","pages":15,"tokens":4227,"emptyPages":[],"textThemes":["adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":312,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \n) \nExploring The Current State of  \n \n)  \n Docket No. AD26-7-000 \n \nPJM Governance \n \n \n \n) \n \n \n \n  \n \nCOMMENTS OF MAREC ACTION AND  \nTHE SOLAR ENERGY INDUSTRIES ASSOCIATION  \n \nPursuant to the July 30, 2026 notice inviting comments,1 MAREC Action2 and the Solar \nEnergy Industries Association (“SEIA”)3 submit these recommended governance reforms for the \nPJM Interconnection, L.L.C. (“PJM”) Board and stakeholder process. \nMAREC Action and SEIA represent developers of all different sizes and business \nmodels. These run the gamut from small rooftop solar installers to large multinational \ncorporations. It includes both public and private companies, some are North American \nsubsidiaries of international companies, some are owned by pension funds or private equity \nfunds, are smaller owner-operated businesses. They have a variety of business models. Some are \nowner-operators, others build and sell projects, while others build projects under contract to \nother entities. But they all have something in common—they want to get generation projects \nbuilt in the PJM region to serve the growing load.  \nMany of these developers represented by MAREC Action and SEIA have project \ndevelopment experience outside of PJM, both in other Regional Transmission Organization \n(“RTO”) markets and in non-RTO regions. Some, that are subsidiaries of international \n \n1 Notice Requesting Post-Conference Comment, Docket No. AD26-7 (July 30, 2026). \n2 MAREC Action (informally, “Mid-Atlantic Renewable Energy Coalition”) is a coalition of over 40 utility-scale \nsolar, wind, and battery storage developers and manufacturers dedicated to the growth and development of \nrenewable energy across the PJM grid region. The views and opinions expressed in this filing do not necessarily \nreflect the official position of each individual member of MAREC Action. \n3 The comments contained in this filing represent the position of SEIA as a trade organization on behalf of the solar \nindustry, but do not necessarily reflect the views of any particular member with respect to any issue."},{"page":2,"startToken":312,"endToken":596,"text":"2 \n \ncompanies, also have project development experience outside the US. Many are actively \ninvolved in the stakeholder processes in other regions and have first-hand experience in what \nworks well and what needs improvement. The recommendations below are informed by these \ndiverse business models and stakeholder experiences.4 \nAs the Commission, PJM, and stakeholders begin the arbitration process, MAREC Action \nand SEIA request that these recommendations are considered and incorporated into the final \nreforms. \n \nI. \nStakeholders need insight into Board direction and decisions \nInsight into Board decisions is sorely lacking in PJM. Stakeholders have very little \nknowledge of how and why the Board acts as it does s. Many decisions in the recent past seem to \nbe rushed attempts to put out fires rather than deliberate well-planned decisions that would move \nPJM into the future. Short-term fixes seem to have become the norm. PJM has jumped from \nemergency to emergency, establishing reforms that are simultaneously rushed and too late. This \ncan be seen in the multiple uses of the Critical Issues Fast Path Process over the last few years \nthat have resulted in some major changes to the PJM markets with very little insight into how the \nBoard arrived at those decisions.   \nMeanwhile, reforms that could address many of the fundamental problems, such as \ncomprehensive transmission and generation interconnection planning, and energy and capacity \nmarket reforms, have fallen by the wayside. For years, as we watched other regions move to \nmore granular markets, stakeholders have told themselves, “this is the year PJM will enact \n \n4 MAREC Action and SEIA’s silence on a particular issue does not necessarily represent internal disagreement, \nacquiescence to the status quo, or agreement with any particular position taken in this proceeding."},{"page":3,"startToken":596,"endToken":934,"text":"3 \n \ncomprehensive market reforms that address systemic issues.” However, it seems these remain on \nthe side-lines or are bogged down in endless debates in the stakeholder process. MAREC Action \nand SEIA applaud PJM for their recent commitment to exploring capacity market reforms,5 but \nwe urge PJM to ensure that this is not an empty commitment. As PJM pursues these reforms, it \nmust do so with the input of its stakeholders and it must be transparent in its choices. \nA. \nRecommendation: The Board and PJM should work with stakeholders to \nidentify initiatives and develop an annual priorities plan. \nIdentifying initiatives and then setting annual priorities is fundamental to any \norganization. The Board and PJM staff need to work with stakeholders to identify critical needs \nand then prioritize the work. PJM has conducted some of this type of priority planning in the past \nbut then failed to hold to those priorities. To be fair, the constant putting out of fires has \ninterfered with this. However, if many of the long-time fundamental issues were identified \nearlier and worked on more holistically, the fires would not be as critical. Addressing these \nemergency needs must be done in the context of longer-term priorities. PJM just released a new \nstrategy document, Shaping a Powerful Change, PJM Five-Year Strategy.6 While this is a start, \nthe document is high-level and lacking in actionable elements. We hope that more is to come in \nthe form of an actual roadmap and workplan outlining the detailed policies and procedures that \nshould be prioritized and worked.  \nPJM need only look to its fellow Regional Transmission Organizations (RTOs) to see \ngood examples of annual prioritization exercises and plan development. In the Midcontinent \n \n5 See PJM Interconnection, L.L.C., Powering Reliability Through Market Design, May 6, 2026, \nhttps://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2026/20260506-powering-reliability-\nthrough-market-design.pdf.  \n6 See PJM Interconnection, L.L.C., Shaping a Power Change, PJM Five-Year Strategy, August 2026. \nhttps://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2026/20260819-shaping-a-powerful-\nchange-pjm-five-year-strategy.pdf"},{"page":4,"startToken":934,"endToken":1245,"text":"4 \n \nIndependent System Operating, Inc. (MISO), Reliability Imperatives set the direction on an \nannual basis. “MISO, its members, and its states have a shared responsibility to address the \nurgent and complex challenges facing the electric grid. We call this the Reliability Imperative.”7 \nThe Reliability Imperative Report (last updated in February 2026) is a living document created in \ncollaboration with all stakeholders to outline strategic priorities. The report evolves, assesses, \nand responds to the Reliability Imperative.8 \nSouthwest Power Pool, Inc. (SPP) has a Strategic Plan and Strategic Roadmap. The first \nstrategic plan was launched in 2021, Aspire 2026.9 It was a five-year plan covering 2021-2026 \nthat “sought to strengthen regional reliability, advance market development, and prepare its \nregion and business for the challenges and opportunities that lay ahead.”10 Earlier this year, SPP \nreleased the 2027-2031 Strategic Plan,11 which will define SPP’s activities over the next five \nyear. Complementary to, and aligned with, the Strategic Plan is the Strategic Roadmap that \noutlines the activities required to meet the goals of the Strategic Plan.12 \nEvery year starting in January, the California Independent System Operator, Corp. \n(CAISO) conducts an Annual Policy Initiatives Catalog and Roadmap Development Process that \n“prioritizes and sequences market design enhancements by soliciting policy initiative proposals \nfrom stakeholders, assessing stakeholder support for proposed policy initiatives, and \n \n7 Midcontinent Independent System Operator, Inc., Corporate Strategy, Reliability Imperative, \nhttps://www.misoenergy.org/meet-miso/MISO_Strategy/.  \n8 MISO, 2026 Reliability Imperative Report, February 2026, \nhttps://cdn.misoenergy.org/2026%20Reliability%20Imperative%20Report744320.pdf.  \n9 See SPP, Aspire 2026 July 14, 2021, https://www.spp.org/documents/65050/spp%20strategic%20plan%202021-\n2026.pdf. \n10 SPP, Strategic Plan, https://www.spp.org/about-us/strategic-plan/.  \n11 See SPP, Powering Progress Forward, https://www.spp.org/documents/76666/2027-\n2031%20strategic%20plan.pdf. \n12 SPP, Roadmap, https://www.spp.org/stakeholder-center/spp-roadmap/."},{"page":5,"startToken":1245,"endToken":1497,"text":"5 \n \ndocumenting a work plan, called the roadmap, for future policy initiatives.”13 This year, CAISO \nbifurcated its annual stakeholder process to create the 2026 Market Policy Catalog and \nRoadmap14 and the 2026 Infrastructure Policy Catalog and Roadmap.15 These tracks prioritize \nand sequence 2027-2029 market design and transmission enhancements based on stakeholder \nproposals and CAISO strategic goals. \nB. \nImprovements to Board Transparency \n1. \nRecommendation: The Board should host open meetings, publish roll \ncall votes, and issue decisional memos with their directives. \nPJM’s Board meetings are closed. Cursory, high-level minutes of those meetings are \nprovided after the Board meetings. This is not indicative of good governance. Transparency \nmeasures must be implemented to ensure that Members, States, and other stakeholders can \nengage effectively and meaningfully with the PJM Board. Essential transparency measures \ninclude open Board meetings, published roll call Board votes, detailed Board meetings minutes \nthat show the rationale for the Board’s vote, and decisional memos between the Board and PJM \nStaff. \n2. \nRecommendation: Board members should schedule regular meetings \nwith Members, States, and Stakeholders. \nAccess to the Board would be another important step towards good governance. \nAlthough the Board meets with the Liaison Committee and has private meetings with the \nOrganization of PJM States, Inc. (“OPSI”) Board three times a year, these meetings are not \n \n13 CAISO 2026 Annual Policy Initiatives Catalog and Roadmap Development Process, \nhttps://www.caiso.com/notices/2026-annual-policy-initiatives-catalog-and-roadmap-development-process--call-on-\n1-15-26.  \n14 Id. \n15 CAISO, 2026 Infrastructure Policy Catalog and Roadmap Process, \nhttps://stakeholdercenter.caiso.com/RecurringStakeholderProcesses/2026-Infrastructure-policy-catalog-and-\nroadmap-process."},{"page":6,"startToken":1497,"endToken":1869,"text":"6 \n \nenough. The Board should schedule regular meetings with Members, States, and Stakeholders, \nalong with detailed minutes of the meetings. Transparency of Board actions, as described above, \ncoupled with access to the Board, will more closely align accountability with responsibility. \nII. \nRecommendation: Consider moving to an advisory voting system. \nAs stated repeatedly throughout this proceeding, the PJM stakeholder process has become \nslow and unfocused. There are tools to speed up the process, like the Critical Issue Fast Path \nwhich is used to address “time-constrained major issues or existing work efforts that have not \nachieved, or are unlikely to achieve, consensus.”16 But, as PJM noted in its pre-conference \ncomments, the CIFP has recently resulted in failures to achieve any sort of consensus in a timely \nmanner.17 Such failures will likely continue to happen, since controversial issues cannot move \nforward without frustrating one group or another. PJM leadership and the Board must be \nempowered to make difficult decisions. Member advisory voting grants that power. \nAs a practical matter, moving to an advisory voting structure does not change the status \nquo. According to PJM, “PJM and its stakeholders reach consensus on the majority of issues \nconsidered.”18 And with respect to the CIFP process, the votes are already advisory.19 The \nrecommendations made in this proceeding will likely lead to more supported, and sustainable, \nproposals in the longer-term. However, in the near-term, PJM will be forced to make hard \ndecisions, and it must have the ability to act quickly and decisively. By moving to a member \n \n16 PJM Manual 34, Sec. 8.6.4, \nhttps://www.pjm.com/pjmfiles/directory/manuals/m34/index.html#Sections/Section_8_Consensus_Based_Issue_Res\nolution_at_the_Standing_Committee_Level_other_than_the_Senior_Standing_Committees.html. \n17 See PJM Comments at 4; see also Jacob Finkle comments calling the recent CIFP a failure. \n18 Prefiled Statement for Panelists from PJM Interconnection, L.L.C., for the PJM Governance and Stakeholder \nReforms Technical Conference at 1 (“PJM Comments”). \n19 PJM Manual 34, Sec. 8.6.4, \nhttps://www.pjm.com/pjmfiles/directory/manuals/m34/index.html#Sections/Section_8_Consensus_Based_Issue_Res\nolution_at_the_Standing_Committee_Level_other_than_the_Senior_Standing_Committees.html."},{"page":7,"startToken":1869,"endToken":2159,"text":"7 \n \nadvisory voting, PJM leadership and the Board can move forward without being bogged down \nby a drawn out, and as of recently, often-failing stakeholder process. \nThis advisory structure should not be viewed in isolation; it is one component of a \nbroader set of reforms needed to make PJM’s stakeholder process more effective and responsive \nand if this change is made it needs to be combined with the reforms discussed below. \nIII. \nThe PJM stakeholder process is in dire need of reform. \nOver the years, the process has become slow, unfocused,20 and polarizing.21 The \nrecommendations below would help create a stakeholder process that will ensure robust \nproposals that address concerns by different sectors and allow PJM to move quickly to address \nemerging issues. \nA. \nRecommendation: At beginning of stakeholder process, PJM staff should \nestablish the objectives any proposed solution must satisfy and what solutions \ncannot be entertained. \nMAREC Action and SEIA appreciate that PJM leadership welcomes multiple viewpoints \nthroughout the stakeholder process. Hearing from a wide range of stakeholders can create \nreforms that accomplish PJM’s goals while also reflecting operational realities and market needs. \nBut PJM and its stakeholders should not be spending hours discussing proposals that have \nelements that cannot be implemented because they are operationally infeasible. To create \nmeaningful reforms, PJM needs to refocus stakeholders on what solutions can be pursued. \nAt the start of each stakeholder process, PJM must clearly define the problem they are \nseeking to solve, the timeframe for action, and any operational limitations that may limit \nsolutions. PJM issue charges and problem statements do define the problem, set the timing, and \n \n20 Pre-filed Statement of Glen Thomas, President of PJM Power Providers Group at 4 (P3 Comments). \n21 PJM Comments at 3."},{"page":8,"startToken":2159,"endToken":2474,"text":"8 \n \ndefine what is out of scope.22 However, the issue charge could be more precise. Instead of \n“intermediate,” “near term,” and “far term,” timelines should identify when the proposal would \nbe filed at the Commission or when an appropriate Manual change will be made, such as “Q1 \n2027,” or “before December 31, 2026.” Further, while issue charges do outline what is “out of \nscope” in a proceeding, they do not reflect when a potential solution that is in scope may not be \navailable because of operational limitations. To the extent possible, PJM should identify these \nissues upfront. If PJM cannot, then it must have discretion to edit proposals throughout the \nstakeholder process, by removing part of, or the entire proposal, from consideration. PJM staff \nmust be able to state that a particular proposal is not operational and thus cannot be \nimplemented. \nA successful stakeholder process is one that sets forward clear guidelines earlier in the \nprocess and constant editing during the process. PJM must be clear in what it needs to \naccomplish, what it can do to meet those goals, and acknowledge where it does not have \nsufficient knowledge about a problem or market segment. \n \nB. \nRecommendation: PJM should provide a pathway for written comments and \nquestions on proposals that are publicly posted to a central location.  \nSeveral panelists noted in their pre-filed comments that stakeholder meetings are \nsometimes derailed for multiple hours by a small number of participants engaging in extended, \nunfocused discussion.23 In order to get in feedback, stakeholders are forced to resort to other \npathways to get PJM’s attention. Comments during stakeholder meetings, side conversations in \n \n22 See e.g. Hybrid Resources Market Model Selection, Issue Charge, https://www.pjm.com/-\n/media/DotCom/committees-groups/committees/mic/2026/20260805/20260805-item-04-2---hybrid-resources-\nmarket-model-selection---issue-charge.pdf.  \n23 Pre-filed Statement of Susan Bruce, Counsel for PJM Industrial Customer Coalition at 17 (“PJM ICC \nComments”)."},{"page":9,"startToken":2474,"endToken":2769,"text":"9 \n \nthe hallways of Valley Forge, and unpublished emails to PJM staff should not be how PJM \nworks with stakeholders to answer questions about its proposals and modify proposals to address \nlegitimate stakeholder concerns. These pathways lack clarity and transparency. It also prevents \nPJM from hearing from critical voices that may not be able to be in the hallways during the \nplethora of  meetings.  \nWhile focusing stakeholder discussions, PJM should provide opportunities to provide \nwritten feedback on its proposals. PJM does, sometimes, provide for the opportunity to submit \nwritten feedback, however, these requests for feedback are often late in the process and \ncomments are not always posted publicly. Further, there is little formality to the process, leaving \nstakeholders to guess as to when, or even if, PJM will accept written feedback. MAREC Action \nand SEIA recommend that PJM establish stakeholder feedback processes like those of the \nMidcontinent Independent System Operator, Inc. (MISO) and the California Independent System \nOperator, Corp. (CAISO). Both MISO and CAISO have dedicated pages on their websites where \nstakeholders can submit written feedback and ask clarifying questions.24 Both MISO and CAISO \nprovide written responses to that feedback. And both MISO and CAISO seek out that feedback \nearly and often in the stakeholder process, allowing them to acknowledge where there are gaps in \ntheir understanding.  \nIn providing for written feedback, PJM can hear from, and respond to, voices that may be \ndrowned out during stakeholder meetings. Further, it allows stakeholders to coordinate with each \nother and find common ground on proposals, ultimately leading to more supported proposals. \n \n \n24 See e.g. MISO, LLWG: Generation and Large Load Alignment, Stakeholder Feedback, \nhttps://www.misoenergy.org/engage/stakeholder-feedback/2026/llwg-generation-and-large-load-alignment-llwg-\n2026-6-20260716/; see also CAISO Initiative: Day-ahead market enhancements, \nhttps://stakeholdercenter.caiso.com/StakeholderInitiatives/Day-ahead-market-enhancements."},{"page":10,"startToken":2769,"endToken":2998,"text":"10 \n \nC. \nImprovements to polling: \nBecause MAREC Action and SEIA are recommending that PJM consider moving to an \nadvisory voting structure, the remaining recommendations in this section reflect changes to the \npolling process to allow PJM to gain more insight into the potential market impact on their tariff \nproposals. \n1. \nRecommendation: Throughout the process, PJM should conduct \npolling on specific elements of its proposals. \nIn addition to gaining critical input through written comments, PJM should seek input on \nindividual elements of a proposal, and should do so early and often throughout the stakeholder \nprocess. Polling reports should be divided out by sector and by business type. Voting on entire \nproposals could result in situations in which small, but impactful elements of a proposal are \nvoted down because they are attached to a proposal that has elements that are unworkable to \ncertain market participants. Polling specific elements of a proposal will allow PJM to understand \nwhat changes are necessary to develop a more supportive, and therefore more successful, \nproposal. \n2. \nRecommendation: When polling members, PJM should reflect poll \nresults with more granularity.  \nMAREC Action and SEIA’s member companies participate in PJM as generation \ndevelopers. Generation developers are spread between two different sectors: the Generation \nOwner sector and the Other Supplier sector. This split is because the Operating Agreement \ndifferentiates between incumbent resource owners, which are part of the Generation Owner"},{"page":11,"startToken":2998,"endToken":3398,"text":"11 \n \nsector,25 and non-incumbent resource owners, which are relegated to the Other Supplier sector.26 \nThe Other Supplier sector also serves as a catch-all sector, serving as the sector for any company \nthat does not fit within the requirements of the other sectors.27 Not only does this sector include \nnon-incumbent generation developers, it includes financiers, power marketers, demand response \naggregators, and consultants that specialize in representing wholesale market participants.28 \nWhile PSEG is technically correct when it notes that “the Generation Owner and Other Supplier \nsectors had less than half of their membership in attendance” at the most recent CIFP for Large \nLoads,29 the statement failed to consider that such a small percentage of the sectors voted in the \nrecent CIFP because the proposal is likely only relevant to that small percentage. \n \nPSEG’s statement reveals an underlying problem with the current sector structure: The \nsectors no longer reflect the diversity of stakeholders in PJM. This is not surprising. The sectors \nwere established more than 25 years ago, as part of PJM’s Order No. 2000 compliance filing.30 \nAnd the qualifications for the sectors have not changed since. Over that time, PJM has shifted \ngreatly. More independent power producers entered the market. Developers shifted from coal to \ngas to renewables. Distributed resources gained access to the wholesale markets.31 Large \ncustomers are shifting from traditional manufacturing to data centers that are both larger and \n \n25 PJM Operating Agreement, Sec. 1, Definitions (defining Generator Owner as a resource shall have cleared an \nRPM auction and has a Commission-jurisdictional interconnection agreement or wholesale market participation \nagreement.) \n26 PJM Operating Agreement, Sec. 1, Definitions (defining “Other Supplier” as a member that “(i) is engaged in \nbuying, selling or transmitting electric energy, capacity, ancillary services, financial transmission rights or other \nservices available under PJM's governing documents in or through the Interconnection or has a good faith intent to \ndo so, and” (ii) is not otherwise part of another sector.) \n27 Id.  \n28 https://www.pjm.com/about-pjm/member-services/membership-enrollment/full-member-enrollment  \n29 PSEG Comments at 8. \n30 Pennsylvania-New Jersey-Maryland Interconnection, 81 FERC ¶ 61,257, 62,262 (1997) (“The Members \nCommittee will consist of 5 sectors representing generation owners, other suppliers, transmission owners, electric \ndistributors, and end-use customers.”) \n31 Participation of Distributed Energy Resource Aggregations in Markets Operated by Regional Transmission \nOrganizations and Independent System Operators, 172 FERC ¶ 61,247 (2020) (“Order No. 2222”)."},{"page":12,"startToken":3398,"endToken":3799,"text":"12 \n \nhave different load profiles. The current sector structure never contemplated these market shifts \nand as a result, votes today do not tell the whole story of the industry impacts of a tariff change. \n \nFor PJM to get a better understanding of the impacts of its proposals, MAREC Action \nand SEIA recommend that, as PJM conducts polls, which again, should be early and often, PJM \nshould reflect not just the sectors in the polls, but various lines of business as well. PJM does \nreflect the various lines of business in its voting reports, which are posted several days after the \nvote is conducted,32 but because these votes are conducted so late in the process, the voting \nresults do little to provide PJM with any insights into what changes need to be made to the \nproposal to address industry concerns. Further, recent polls show that PJM does not delineate \nbetween lines of business.33 In order to reflect the lines of business in polling, MAREC Action \nand SEIA recommend that PJM adopt the categories of lines of business reflected in the voting \nreports.34 \n \nMAREC Action and SEIA do not recommend that PJM revise the Operating Agreement \nto redefine the sectors, as more research would be necessary to fully define those sectors. Such a \nchange is not necessary for PJM to modify its polling to capture and reflect industry feedback in \na way that provides a better understanding of the impacts of its proposals.  \n  \n \n32 See e.g. PJM Members Committee, Voting Results, Connect and Manage, at 6 (June 30, 2026), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/committees/mc/2026/20260630-special/mc-voting-\nresults---agenda-item-3a---pjm-cm-proposal.pdf (showing the voting results broken down by line of business in \nPJM).  \n33 See PJM, Governance and Stakeholder Process Poll Results (Aug. 12, 2026), https://www.pjm.com/-\n/media/DotCom/committees-groups/committees/mc/2026/20260819/20260819-item-10---1-governance-and-\nstakeholder-process-poll-results.pdf; see also PJM, CIFP - Reliability Backstop Procurement / Connect & Manage \nSummarized Poll Results (July 16, 2026), https://www.pjm.com/-/media/DotCom/committees-groups/cifp-\nrbp/postings/cifp-poll-results-with-comments.pdf.  \n34 See PJM Members Committee, Voting Results, Connect and Manage, at 6 (June 30, 2026), https://www.pjm.com/-\n/media/DotCom/committees-groups/committees/mc/2026/20260630-special/mc-voting-results---agenda-item-3a---\npjm-cm-proposal.pdf (reflecting the following lines of business: Ancillary Service Provider, Consumer Advocate, \nCurtailment Provider, Financial Trader, Industrial Customer, IOU, IPP, Project Developer, Public Power, Retail \nMarketer, and Wholesale Marketer)."},{"page":13,"startToken":3799,"endToken":4010,"text":"13 \n \nIV. \nStrengthening State Participation in the PJM Stakeholder Process \nState retail regulators have a statutory responsibility to ensure resource adequacy at the \nlowest reasonable cost and are directly accountable to consumers for retail electricity rates. Yet \nmany of the rules governing resource adequacy are developed through the PJM stakeholder \nprocess, in which state regulators lack a formal role sufficient to effectively advance and \nimplement their solutions. This disconnect between state responsibility and stakeholder authority \nshould be addressed by strengthening the states’ role in PJM governance. \nMAREC and SEIA support reforms that would provide states, through OPSI, with a more \nmeaningful and actionable voice in the PJM stakeholder process. Specifically, PJM Transmission \nOwners should make Section 205 filings on OPSI’s behalf when OPSI reaches consensus on cost \nallocation methods for regional transmission projects. In addition, if PJM is given authority to \nmake unilateral Section 205 filings, PJM should also be required to make filings on OPSI’s \nbehalf regarding regional transmission planning.  \nThese changes would better align PJM’s governance structure with practices already in \nplace in other RTOs. More importantly, these changes recognize the states’ statutory \nresponsibilities and ensure that the economic regulators accountable to retail consumers have a \nmeaningful, effective, and actionable voice in the PJM decisions that directly affect them."},{"page":14,"startToken":4010,"endToken":4086,"text":"14 \n \nV. \nConclusion  \nAs the Commission, PJM, and stakeholders move through this dispute resolution process, \nMAREC and SEIA request that these recommendations are reflected in the reforms adopted in \nthis proceeding.  \nEvan Vaughan,  \nExecutive Director  \nMAREC Action  \nPO Box 3335  \nSilver Spring, MD 20918  \n(202) 431-4640 \nevaughan@marec.us \nMelissa Alfano  \nSenior Director of Energy Markets and \nCounsel  \nSolar Energy Industries Association  \n1425 K St NW Ste. 1000  \nWashington, DC 20005  \n(202) 566-2873  \nmalfano@seia.org"},{"page":15,"startToken":4086,"endToken":4227,"text":"Appendix: List of Recommendations \nBoard Leadership and Transparency \n1. The Board and PJM should work with stakeholders to identify initiatives and develop an \nannual priorities plan. \n2. The Board should host open meetings, publish roll call votes, and issue decisional memos \nwith their directives. \n3. Board members should schedule regular meetings with Members, States, and \nStakeholders. \nStakeholders voting rights \n4. Consider moving to an advisory voting system. \nImprovements to the Stakeholder Process \n5. At beginning of stakeholder process, PJM staff should establish the objectives any \nsolution must satisfy and what solutions cannot be entertained. \n6. PJM should provide a pathway for written comments and questions on proposals that are \npublicly posted to a central location. \n7. Throughout the process, PJM should conduct polling on specific elements of its \nproposals. \n8. When polling members, PJM should reflect poll results with more granularity."}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":520,"startToken":0,"endToken":385},{"p":2,"at":520,"title":"I. Stakeholders need insight into Board direction and decisions","method":"printed heading","endPage":3,"endAt":472,"startToken":385,"endToken":675},{"p":3,"at":472,"title":"A. Recommendation: The Board and PJM should work with stakeholders to","method":"printed heading","endPage":5,"endAt":410,"startToken":675,"endToken":1303},{"p":5,"at":410,"title":"B. Improvements to Board Transparency","method":"printed heading","endPage":6,"endAt":289,"startToken":1303,"endToken":1537},{"p":6,"at":289,"title":"II. Recommendation: Consider moving to an advisory voting system.","method":"printed heading","endPage":7,"endAt":433,"startToken":1537,"endToken":1940},{"p":7,"at":433,"title":"III. The PJM stakeholder process is in dire need of reform.","method":"printed heading","endPage":7,"endAt":776,"startToken":1940,"endToken":1994},{"p":7,"at":776,"title":"A. Recommendation: At beginning of stakeholder process, PJM staff should","method":"printed heading","endPage":8,"endAt":1194,"startToken":1994,"endToken":2355},{"p":8,"at":1194,"title":"B. Recommendation: PJM should provide a pathway for written comments and","method":"printed heading","endPage":10,"endAt":6,"startToken":2355,"endToken":2770},{"p":10,"at":6,"title":"C. Improvements to polling:","method":"printed heading","endPage":13,"endAt":6,"startToken":2770,"endToken":3800},{"p":13,"at":6,"title":"IV. Strengthening State Participation in the PJM Stakeholder Process","method":"printed heading","endPage":14,"endAt":6,"startToken":3800,"endToken":4011},{"p":14,"at":6,"title":"V. Conclusion","method":"printed heading","endPage":15,"endAt":970,"startToken":4011,"endToken":4227}]}
