{"document":{"slug":"rec-20260821-5141","title":"Comments of Vitol Inc. offering perspectives on PJM governance arising from the Commissioner-led Technical Conference on 07/23/2026","issued":"2026-08-21","accession":"20260821-5141","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"Vitol Inc.","kind":"comments","file":"sources/filings/text/20260821-5141_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5141","tier":"record","sha256":"0605f4ee432332796ee81f997d3306084aecd9991aa9453ca1af71577b499a35","pages":11,"tokens":3362,"emptyPages":[],"textThemes":["cost","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":330,"text":"1 \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Governance and Stakeholder Reforms  \n) \nDocket No. AD26-7-000 \nCOMMENTS OF VITOL INC.  \n \nVitol appreciates the opportunity to offer perspectives on PJM governance arising from the \nCommissioner-led Technical Conference on July 23, 2026. A world leader in power \ncommodities, Vitol brings deep expertise in valuing power and its inputs. Within PJM, Vitol \nparticipates as a member of the “Other Supplier” sector, a classification that reflects its diverse \nbusiness interests including power trading, serving default-service requirements to utilities in \nseveral states, providing structured bilateral energy solutions, and developing solar and storage \nassets through its affiliate, VC Renewables LLC, which presently operates 120 MWAC of solar \nprojects in Pennsylvania and has developed dozens of projects across PJM.  Vitol’s primary \nrepresentative to PJM stakeholder committees also serves as the current Chair of the PJM \nMembers Committee. \nVitol agrees with the Commission that there are many opportunities to improve the PJM \ngovernance processes, expedite collective decision-making, and foster progress.  PJM faces \nsignificant challenges that stem from mostly exogenous factors: an influx of large loads, global \nsupply chain constraints, state policies that inhibit generation development, glacial transmission \ndevelopment speeds, and price shocks. PJM governance improvements may enable PJM, its \nMembers, states, and stakeholders to act prospectively and respond to such challenges more \nexpeditiously. \nGenerally, we seek: \n A PJM Board that is independent, includes diverse expertise, and is empowered to make \ndecisive, timely business judgements; \n  PJM Board and management accountability to all stakeholders for timely issue \nresolution1; \n Active state participation in the PJM governance process through defined roles that \nenable earlier engagement;  \n \n1 Throughout these comments the term “Members” references signatories to the PJM governing documents. \nStakeholders, which includes Members, refers to any person impacted by PJM decisions. “States” refers to \nthe 13 PJM constituent states and the District of Columbia.  It includes representatives of States, with primary \nreference state utility commission representatives and state executive branch representatives that are \nauthorized to represent the entire state."},{"page":2,"startToken":330,"endToken":703,"text":"2 \n \n Adherence to the Federal Power Act (FPA) and Commission orders establishing RTOs; \nand \n Stakeholder process efficiency and fairness. \n \nI. \n PJM Board Independence \nVitol agrees with the Technical Conference consensus that the PJM Board should be informed by \nstakeholder input but fully empowered to make courageous and timely decisions in the best \ninterest of maintaining PJM’s ability to meet current and future power needs while adhering to \nthe FPA and Commission orders establishing RTOs.   \n \n1) Should Board members’ terms be extended to five or more years? \nExtending Board member terms to five or more years might help insulate Board members from \nany undue Member influence arising from the need to secure re-nomination after the current \nthree-year terms. Renomination after a longer initial term could still be appropriate, although \nconsideration should be given to whether PJM Members or Board members are responsible for \nrenomination decisions. Extending Board member terms should be conditioned with other \nreforms, including open Board meetings and a more detailed written record of Board decision \nmaking. These transparency improvements provide Board member accountability consistent with \nthe term extension. Moreover, transparency measures permit stakeholders to assess individual \nBoard member performance and provide feedback to the Board that can inform their independent \nretention decisions. See further details in response to Question 6, below. \n \n2) Should there be a maximum number of years that a Board member may serve (e.g., 10 \nYears)? \nBoard term limits should be maintained. Historically, PJM Board members have been limited to \ntotal service of nine years (three, three-year terms), which has worked well. Balancing the need \nfor Board members to gain experience with a need for new perspectives is critical. However, the \nappropriate limit should be reconsidered if terms are extended beyond the present three-year \nterm. \n \n3) Should the Board member qualification rules be revised to provide a preference for some \nBoard members that reside in the PJM region? \nA residence requirement is not necessary. In our experience, there has been little, if any, \ndifference in Board members’ grasp of regional issues and culture because of where they live. \nUnderstanding regional issues and culture is certainly one element in a new Board member’s \nlearning curve, but it is far less important than understanding unique PJM policy, markets, and"},{"page":3,"startToken":703,"endToken":1043,"text":"3 \n \noperations features. If a residency requirement were to be instituted, then it should only apply to \na small fraction of the Board. \n \n4) Should the conflict-of-interest rules be revised to reduce the cooling off period for Board \nmembers from two years to one year? \nRetention of the existing conflict-of-interest rules is appropriate to diminish potential Board \ncandidate bias from recent PJM Member or state affiliations. There is no indication that the \ncurrent rule limits the pool of qualified candidates. \n \n5) Should restrictions on Board communications be relaxed to enable more communication \nbetween the Board and stakeholders? \nThe status quo works reasonably well to balance access to the Board while guarding against \nundue influence that might be levied without notice to all stakeholders. Board members are \nreadily accessible at various public PJM meetings and periodic state gatherings (e.g., OPSI and \nMACRUC meetings). Members and OPSI have both public and limited private group \nopportunities to meet with the Board. Any stakeholder can send public correspondence to the \nBoard at any time on any subject. However, if ex parte communication rules are loosened then it \nshould be conditioned with obligations for notice regarding private meetings.  \n \n6) In order to increase transparency, should Board votes be made public or the Board be \nrequired to explain its reasoning? \nBoard votes should be made public. Board decisions authorizing any FPA Sec. 205 or Sec. 206 \nfiling should be explained to demonstrate how the Board considered and weighed alternatives in \nauthorizing a PJM submittal. Specifically, if OPSI or a state governors’ organization provides a \nresource adequacy proposal backed by a supermajority of its members, PJM could be obligated \nwithin its FERC transmittal to explain its rationale for rejection of such proposal. \n \n7) In order to increase transparency, should some Board meetings be open or available to \nthe public? \nConsistent with practice in other RTOs, PJM Board meetings should be open to Members and \nauthorized state representatives, perhaps with limitations for sensitive corporate or operational \nmatters (e.g., personnel evaluations and Critical Energy Infrastructure Information-protected \nmatters)."},{"page":4,"startToken":1043,"endToken":1385,"text":"4 \n \n8) Should PJM’s governing documents be revised to explicitly state that the responsibility of \nPJM and its Board is to serve the public interest? \nRevising Section 7.7 of the PJM Operating Agreement to include a public interest standard may \nbe beneficial if the application of such a standard is clearly defined in a manner consistent with \nPJM’s obligations under the FPA and the Commission’s orders.  \n \n9) Should state representatives have at least one voting member on the Nominating \nCommittee? \nVitol supports adding one state representative to the diverse mix of Members and Board Member \nrepresentatives on the Nominating Committee.  The addition of a state representative may \nduplicate certain consumer interests, but the added consideration of broader state concerns \nshould enhance the committee’s perspectives. However, adding multiple state representatives \nwould result in over-representation of states and skew the balance of interests within the \ncommittee.  \n \n10) Should PJM adopt public performance metrics and tie management compensation to \ntheir achievement? \nAdditional details about the proposed metrics are required to fairly address this question. \nGenerally, stakeholders would benefit from understanding management motivations, but the \nBoard’s independent decisions regarding management oversight should not be unnecessarily \nencumbered by rigid metrics.  \n \nII. \nState Participation \nThe technical conference revealed clear, shared interests among the Commission, state \nrepresentatives, and many stakeholders for more formalized state participation and governance \nroles. Vitol supports some reforms that give states a greater opportunity for both engaging in \nstakeholder deliberations and conveying states’ interest to the PJM Board and management. \nHowever, new privileges extended to states should be coupled with accountability for timely, \nconcerted expression of the states’ interests.  \nCurrently, there are many opportunities for state engagement that have not been fully utilized by \nstate representatives.  States representatives are not unduly limited in their ability to participate \nin PJM committee deliberations, offer proposals, inject ideas, and influence PJM management \ndecision-making. There are many recent examples of such state influence.  Historically, some \nstate public service commission representatives have regularly participated in some stakeholder \ncommittees, but input is infrequent. State consumer advocates participate more regularly through"},{"page":5,"startToken":1385,"endToken":1780,"text":"5 \n \ntheir CAPS (Consumer Advocates of PJM States) representative.  Only recently – roughly \ncoincident with capacity market price escalation – have state representatives outside of PSC staff \nand CAPS become regularly involved in PJM committee deliberations. Through OPSI, states \nhave opportunities for closed door meetings with the PJM Board on multiple occasions each \nyear, similar to the opportunities afforded PJM Members. Notwithstanding existing opportunities \nfor state engagement, more can be done to help states advance their aims and to understand \nmatters under consideration by PJM management and Members.  Any such reforms must be \nconstructed to ensure state concerns are presented in a timely and actionable structure. \n \n18) In addition to OPSI, should there be a second state representative group consisting of \ngovernors’ representatives and/or state legislators’ representatives? \nCreation of additional state representative groups, in addition to OPSI, should be the prerogative \nof the states. Regardless, PJM governance would be more robust if OPSI obtained additional \nfunding to support full-time professional staff that can actively engage in stakeholder \ndeliberations alongside Members. Active OPSI representation could give state commissions and \nperhaps, by proxy, state policymakers greater in-depth understanding of the complexities and \ntrade-offs under consideration by PJM and stakeholders on any given issue. As seen in other \nRTOs, state governors may benefit from their own organization to develop strategic policy \nperspectives and engage with the PJM Board and management to relay those perspectives \n(similar to the New England States Committee on Electricity structure in ISO-New England). It \nis the states’ collective choice whether such governor organization would be administered \nseparately or in concert with OPSI. Regardless of the organization(s) states choose to enable, all \nsuch organization(s) must unambiguously express who is speaking on behalf of the states on any \ngiven matter.  Groups comprised of state legislators would not be able to speak clearly on behalf \nof the states since they represent only a fraction of a state with potentially diverse views from the \nstate executive branch.  \n \n19)  Should state representatives have a formal voting role in the stakeholder process \n(limited to certain topics, such as resource adequacy and regional transmission cost allocation) \nin addition to the consumer advocate votes? \nPJM and its Members value state input on matters under consideration by stakeholder \ncommittees.  To facilitate such input, states could be provided a non-voting ex officio role in PJM \ncommittee proceedings to express their interests throughout deliberations."},{"page":6,"startToken":1780,"endToken":2140,"text":"6 \n \n20) Should PJM be required to consult with OPSI prior to making a section 205 filing \nrelated to resource adequacy and transmission cost allocation? \n \nPJM consultation with OPSI prior to making Section 205 filings related to resource \nadequacy and transmission cost allocation could yield more informed PJM filings that align with \nstate interests. However, any consultation structure should neither impede PJM’s independent \ndecision making nor delay submissions to FERC. \n \n \nIII. \nSection 205 Filing Rights \nA legally-permissible allocation of Section 205 rights between PJM and its Members over the \nenergy and ancillary services markets and regional transmission planning function is possible. \nAppropriately structured, such an allocation would empower the Board to act independently, \nwhile retaining Members’ contractual rights over the energy and ancillary services and planning \nfunctions. \n \n11) Should the stakeholder process be advisory, i.e., stakeholder votes only inform the \nBoard? \nThe stakeholder process should be “advisory,” subject to Member retention of jump-ball Section \n205 rights. The PJM Board should be empowered to act independently, free from any stakeholder \nveto or delay of meritorious PJM proposals. Order No. 2000 makes independence the “bedrock” \nof RTO governance, while Order No. 719 requires inclusive, balanced, and responsive \nstakeholder processes, but not stakeholder control.2  The PJM Board should be fully empowered \nto direct PJM actions on its own accord. Empowering the PJM Board with the ability to make \nSection 205 filings regarding the energy and ancillary service markets and regional transmission \nplanning will enable the Board to make timely and courageous action, notwithstanding Member \nconsensus.  Extending Section 205 rights to the Operating Agreement would also make PJM \naccountable for presenting reforms to the Commission if Members are deadlocked or delayed. \nHowever, Board independence need not impede Members from submitting competing Section \n205 proposals, as discussed in response to Question 15. Member retention of jump-ball Section \n205 rights enables a supermajority of Members to develop consensus proposals that can enrich \nthe record before the Commission and check PJM intransigence. \n \n \n2 Regional Transmission Organizations, Order No. 2000, FERC Stats. & Regs. ¶ 31,089 (1999); Wholesale \nCompetition in Regions with Organized Electric Markets, Order No. 719, 125 FERC ¶ 61,071 at PP 477, 504 \n(2008)."},{"page":7,"startToken":2140,"endToken":2513,"text":"7 \n \n12)   Should PJM have section 205 filing rights over the energy market and ancillary services \nunencumbered by the requirement to obtain approval of two-thirds of the Members \nCommittee \nSubject to Member retention of jump-ball Section 205 rights, PJM should have Section 205 \nfiling rights over the energy market and ancillary services unencumbered by the requirement to \nobtain approval of two-thirds of the Members Committee.  \n \n13)  Should PJM have section 205 filing rights over Regional Transmission Expansion \nPlanning (RTEP) unencumbered by the requirement to obtain approval of two-thirds of \nthe Members Committee? \nSubject to Member retention of jump-ball Section 205 rights, PJM should have Section 205 \nfiling rights over Regional Transmission Expansion Planning (RTEP) unencumbered by the \nrequirement to obtain approval of two-thirds of the Members Committee.  \n \n14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource \nadequacy and transmission cost allocation filings when a supermajority of OPSI agrees \non an alternative proposal? \nStates should have a formal and meaningful consultative role in PJM governance, but OPSI \nshould not possess Section 205 jump-ball rights. Section 205 permits a public utility to propose \nchanges to its jurisdictional rates and practices, but OPSI and its member commissions are not \npublic utilities. In Massachusetts DPU v. FERC, the court sustained FERC’s rejection of a utility \nfiling compelled by a state regulator because Section 205 governs changes the utility itself \nproposes, not changes a state requires it to propose.3  OPSI may submit advisory alternatives, \nintervene, protest, or seek relief under Section 206, but should not compel PJM to advance a \nstate proposal under Section 205.  \nAlthough the FPA prohibits states from holding Section 205 rights, there is no prohibition against \nthe RTO engaging in timely and detailed consultation with the states in advance of such filing. \nPJM should gather state feedback, including any state-sponsored written proposal that would \nmodify or replace PJM’s proposed filing. To demonstrate that PJM has thoughtfully considered \nsuch feedback, it is reasonable for PJM to commit to addressing such feedback in a public \nresponse to OPSI, within a reasonable time after any Section 205 filing addressing resource \nadequacy or regional transmission cost allocation. \n \n \n3 Massachusetts DPU v. FERC, 729 F.2d 886, 887–90 (1st Cir. 1984)"},{"page":8,"startToken":2513,"endToken":2883,"text":"8 \n \n15) Should the Members Committee have “jump ball” filing rights over the portions of the \ntariff where PJM has 205 filing rights when a supermajority of stakeholders approves an \nalternative proposal? \nMembers should retain their present Section 205 rights which can be exercised upon a super-\nmajority vote of the Members Committee, but PJM should have the opportunity to make \nindependent Section 205 filings. PJM should be the Section 205 filer and should not be delayed \nor prevented from filing its preferred proposal.  However, if a supermajority of the Members \nCommittee approves one complete, germane alternative, PJM should include that alternative, its \nsupporting record, the voting results, and PJM’s reasons for rejecting it. This would resemble the \nCommission-approved ISO New England (ISO-NE)/ New England Power Pool (NEPOOL) \nprocess, under which ISO-NE retains primary filing authority but transmits a qualifying \nstakeholder alternative. Such a jump-ball mechanism should not authorize Members to compel a \nfiling where PJM proposes none or impair transmission owners’ separately held Section 205 \nrights. \n \nIV. \nStakeholder Process \nThere are many potential improvements that could be made to speed the stakeholder process, but \nthese are secondary in importance to the questions posed above. PJM’s stakeholder process is \ndesigned to identify stakeholder interests, generate ideas, evaluate ideas consistently, and \ndevelop consensus outcomes. While some modifications to voting protocols may be beneficial, \nthey are not the most significant impediment to the speed or quality of stakeholder process \noutcomes. Additionally, the institution of jump-ball 205 rights (as discussed above) would \ndiminish the import of the voting thresholds to authorize Section 205 filings over the energy and \nancillary services market and regional transmission planning.  \n \n16) Should the approval threshold in the Members Committee be lowered from two-thirds \nsector-weighted voting? \nWhile lowering the Members Committee approval threshold from its current two-thirds \nsupermajority could accelerate the passage of matters before it, any reduction should stop short \nof 60% — the minimum at which approval demands support from at least three sectors. A \nthreshold below that level would fail to secure adequately diverse Member representation. On the \nother hand, the present two-thirds requirement necessitates the support of at least four sectors; as \na consequence, any two sectors may pool their votes to exercise an effective veto."},{"page":9,"startToken":2883,"endToken":3163,"text":"9 \n \n17) Should the voting rules barring affiliate votes, which apply to senior standing \ncommittees, also apply to lower-level committees? \nAffiliate voting should be eliminated entirely. For a $5000 membership fee, any special purpose \nLLC under the ownership of Member can itself acquire membership and gain an affiliate vote \nthat conveys little information about the preference of the diverse Membership interests.  \nHowever, even if affiliate voting is eliminated, it does not naturally follow that sector-weighted \nvoting is appropriate throughout the stakeholder committees.  \nApplication of sector-weighted voting at lower-level committees is likely to impede idea \ngeneration and development.  Active participants at lower-level committees are often subject \nmatter experts, not ultimate decision-makers for a Member. Depending on the subject matter, \nthere may be only a small number of Members and a fraction of the sectors present (or their \npresence may be through a professional agent rather than an engineer, account, lawyer or other \nprofessional specifically versed in the matters the lower-level committee is undertaking). \nConsequently, application of sector-weighted voting may suffer from an insufficient quorum of \nthe five sectors to convey meaningful preferences to senior committees.  \nInstead of sector-weighted voting at the lower-level committees, a potentially better approach \nwould be allowing a simple majority vote of those present for a proposal to move forward to the \nmore rigorous sector-weighted voting applied to Standing Committees and Senior Committees.  \n \nV. \nConclusion \nVitol respectfully offers the responses above to the Commission’s Post Technical Conference \nqueries.  Addressing Board independence and state participation will enable PJM to move \nforward more swiftly and confidently.  Swift decisions from an empowered and informed PJM \nBoard will provide the Commission increased confidence in the proposals that the Board \npresents for consideration."},{"page":10,"startToken":3163,"endToken":3306,"text":"10 \n \nVI. \nCommunications and Correspondence \nAll communications and correspondence regarding this filing should be directed to:4 \nVijay D’Cruz \nSeth Cochran* \nVitol Inc. \n3425 West Alabama St, Houston TX 77027 \nHouston, TX 77027 \nPhone: (713) 230-1000 \nvad@vitol.com \nsco@vitol.com.  \nJason Barker* \nVC Renewables, LLC \n110 Edison Place, Suite 312 \nNewark, NJ 07102 \nPhone: (443) 613-3634 \nbja@vcrenewables.com \n* Persons authorized to receive service of all documents in this proceeding. \n \nRespectfully submitted, \n/s/ Vijay D’Cruz \nVijay D’Cruz \nGeneral Counsel, Americas \nVitol Inc. \n3425 West Alabama St.  \nHouston TX 77027 \n \nDated: August 21, 2026 \n \n \n4 The Vitol Companies respectfully request waiver of Rule 203(b)(3) of the Commission’s Rules of Practice and \nProcedure, 18 C.F.R. § 385.203(b)(3), to the extent necessary to permit designation of more than two persons \nfor service on its behalf in this proceeding."},{"page":11,"startToken":3306,"endToken":3362,"text":"11 \n \nCERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary in these proceedings. \nDated at Houston, TX, this 21st day of August, 2026. \n/s/ Edwin Cambero \nEdwin Cambero \nVitol Inc. \n3425 West Alabama St.  \nHouston TX 77027"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":145,"startToken":0,"endToken":349},{"p":2,"at":145,"title":"I. PJM Board Independence","method":"printed heading","endPage":4,"endAt":1395,"startToken":349,"endToken":1239},{"p":4,"at":1395,"title":"II. State Participation","method":"printed heading","endPage":6,"endAt":484,"startToken":1239,"endToken":1850},{"p":6,"at":484,"title":"III. Section 205 Filing Rights","method":"printed heading","endPage":8,"endAt":1134,"startToken":1850,"endToken":2680},{"p":8,"at":1134,"title":"IV. Stakeholder Process","method":"printed heading","endPage":9,"endAt":1600,"startToken":2680,"endToken":3108},{"p":9,"at":1600,"title":"V. Conclusion","method":"printed heading","endPage":10,"endAt":6,"startToken":3108,"endToken":3164},{"p":10,"at":6,"title":"VI. Communications and Correspondence","method":"printed heading","endPage":11,"endAt":6,"startToken":3164,"endToken":3307},{"p":11,"at":6,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":11,"endAt":345,"startToken":3307,"endToken":3362}]}