{"document":{"slug":"rec-20260821-5144","title":"Post-Technical Conference Comments of Duke Energy Ohio, Inc. and Duke Energy Kentucky, Inc. re PJM Governance and Stakeholder Reforms","issued":"2026-08-21","accession":"20260821-5144","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"Duke Energy Ohio, Inc. and Duke Energy Kentucky, Inc.","kind":"comments","file":"sources/filings/text/20260821-5144_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5144","tier":"record","sha256":"c782102eda8b5c1ae3e4cc3833abf141c30ba0d231f234dad1c818312dfda22d","pages":8,"tokens":2545,"emptyPages":[],"textThemes":["cost","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":252,"text":"1 \n \nUNITED STATES OF AMERICA \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \n \n \n \n \n \n \n) \nPJM Governance and Stakeholder Reforms \n \n) \nDocket No. AD26-7 \n \n \n \n \n \n \n \n \n) \n \nPOST-TECHNICAL CONFERENCE COMMENTS \nOF  \nDUKE ENERGY OHIO, INC. AND DUKE ENERGY KENTUCKY, INC.  \n \n \nOn July 23, 2026, the Federal Energy Regulatory Commission (“FERC” or the \n“Commission”) convened a technical conference in this docket to discuss PJM Interconnection, \nL.L.C. (“PJM”) governance and stakeholder processes, with a particular focus on identifying and \nevaluating concrete, actionable reforms to improve PJM’s ability to address operational and market \nneeds in a timely and efficient manner. On July 30, 2026, the Commission issued a notice inviting \ninterested parties to file post-conference comments, including responding to a list of questions \nposed by the Commission regarding potential PJM governance reforms. Duke Energy Kentucky, \nInc. and Duke Energy Ohio, Inc. (“collectively, “Duke Energy’) hereby submit comments to the \nquestions posed by the Commission.1  Duke Energy Kentucky, Inc. and Duke Energy Ohio, Inc. \nare transmission-owning utilities within PJM and are PJM members in the Transmission Owner \nsector. Duke Energy provides electric service to 920,000 customers in Kentucky and Ohio. Duke \nEnergy appreciates the Commission’s initiative and active engagement to investigate reforms that \ncan improve PJM’s ability to meet the needs of the moment and ensure the independence and \nreliable operation of PJM in the long-term.  \n \nListed below are the questions posed by the Commission and Duke Energy’s responses:  \n \n \n1 On August 17, 2026, Duke Energy Ohio, Inc. and Duke Energy Kentucky, Inc. submitted a doc-less motion to \nintervene in this docket."},{"page":2,"startToken":252,"endToken":610,"text":"2 \n \nPJM Board Independence \n1. Should Board members’ terms be extended to five or more years? \nNo. Duke Energy supports a three-year board term, with the opportunity for \nrenomination, and opposes extending board terms to five years or more because shorter \nterms promote responsiveness to industry changes, facilitate replacement of directors \nwhen concerns arise, and align with prevailing RTO/ISO governance standard practice \namong RTOs/ISOs. \n \n2. Should there be a maximum number of years that a Board member may serve (e.g., \n10 years)? \n \nYes. Term limits reinforce both independence and accountability while preserving a \nboard’s ability to benefit from experienced leadership. We recommend three, three-year \nterms for the maximum term of nine years. However, limited extensions can preserve \nneeded expertise while maintaining the discipline of a term-limit framework. \nConsequently, Duke Energy supports stakeholder approval for exceeding the maximum \nnine-year term to no more than two, three-year terms.  \n \n3. Should the Board member qualification rules be revised to provide a preference for \nsome Board members that reside in the PJM region? \n \nYes. Duke Energy believes there is value in having a portion of the PJM Board reside \nwithin the PJM footprint. Regional residence can provide practical familiarity with the \nstates, communities, reliability concerns, and consumer impacts within the PJM region. \nHowever, residency should be treated as a preference rather than a mandatory \nqualification. A strict requirement could unnecessarily limit the pool of qualified, \nindependent candidates and should not outweigh the need to select Board members with \nthe appropriate expertise, independence, and judgment to oversee PJM effectively. \n \n4. Should the conflict-of-interest rules be revised to reduce the cooling off period for \nBoard members from two years to one year? \n \nYes. Duke Energy supports reducing the cooling-off period from two years to one year. A \none-year period provides meaningful separation from prior employment or stakeholder \naffiliations while avoiding an unnecessarily restrictive barrier to qualified candidates. \nGiven the complexity and pace of change in PJM’s markets, reliability obligations, and \ntransmission planning responsibilities, the Board benefits from access to individuals with \ncurrent and relevant experience. Any remaining conflict concerns can be appropriately \naddressed through robust disclosure, recusal, and ongoing conflict-of-interest safeguards."},{"page":3,"startToken":610,"endToken":1024,"text":"3 \n \n5. Should restrictions on Board communications be relaxed to enable more \ncommunication between the Board and stakeholders? \n \nNo. Duke Energy believes that PJM’s restrictions should remain in place because they \npreserve the independence and impartiality of the Board’s decision-making process. \nPermitting unrestricted communications between individual stakeholders and Board \nmembers could create the perception that certain interests receive preferential access or \ninfluence over Board deliberations. The current restrictions promote fairness, \ntransparency, and stakeholder confidence that Board decisions are based on the record \nthrough PJM’s open stakeholder processes rather than private advocacy. However, PJM \ncould adopt a “Board Reception” approach similar to other RTOs/ISOs where \nstakeholders are allowed to speak to Board members at events such as the PJM Annual \nMeeting concerning any issue of interest for up to 3 hours.  \n \n6. In order to increase transparency, should Board votes be made public or the Board \nbe required to explain its reasoning?  \n \nYes, with some exception. Duke Energy supports increased transparency into Board \nvoting and reasoning where appropriate, as doing so can enhance accountability and \nstakeholder confidence in PJM governance. However, any requirement to make Board \nsessions or explanations public should preserve the ability of the Board to maintain \nconfidentiality for matters that are appropriately addressed in executive sessions, \nincluding personnel, compensation, legal, privileged, commercially sensitive, \ncybersecurity, or other confidential matters. This approach balances the value of \ntransparency with the need for candid Board deliberation and responsible governance \n \n7. In order to increase transparency, should some Board meetings be open or available \nto the public? \n \nYes, with some exception. Duke Energy supports making appropriate portions of some \nBoard meetings open or publicly available to enhance transparency and stakeholder \nconfidence. However, public access should not extend to matters appropriately addressed \nin executive sessions, including personnel, compensation, legal, privileged, commercially \nsensitive, cybersecurity, or other confidential matters. This strikes a balance between \nvisibility into Board governance while preserving the Board’s ability to deliberate \ncandidly and responsively on sensitive issues.  \n \n8. Should PJM’s governing documents be revised to explicitly state that the \nresponsibility of PJM and its Board is to serve the public interest? \n \nNo. Duke Energy does not believe additional language is necessary. PJM’s governing \ndocuments already require the Board to oversee PJM in a manner consistent with the safe \nand reliable operation of the PJM Region, and the creation and operation of robust, \ncompetitive, and nondiscriminatory electric power markets. Those obligations are core \nexpressions of public interest in the RTO context. Adding a separate, generalized public"},{"page":4,"startToken":1024,"endToken":1370,"text":"4 \n \ninterest standard could create ambiguity and invite disputes over competing \ninterpretations of that term, without improving PJM’s existing obligations to reliability, \nmarket integrity, nondiscrimination, and independence. \n \n9. Should state representatives have at least one voting member on the Nominating \nCommittee? \n \nNo. While Duke Energy believes that input from the states is important, we do not \nsupport giving state representatives a voting member on PJM’s Nominating Committee. \nPJM’s Nominating Committee is structured around representatives elected from the \nMembers Committee sectors. Creating a voting role for state representatives would \nrequire a broader change to PJM’s sector-based governance structure and could disrupt \nthe balance among existing stakeholder sectors. It could also blur the independence of the \nBoard nomination process by creating the perception that Board selection is influenced \nby governmental or state policy priorities. State input is important and necessary, but it \nshould continue to be provided through OPSI, stakeholder engagement and FERC \nproceedings rather than through a formal vote on Board nominations.  \n \n10. Should PJM adopt public performance metrics and tie management compensation \nto their achievement? \n \nYes. Duke Energy supports the development of PJM management performance metrics \nand believes stakeholder awareness and input are important. However, Duke Energy does \nnot support posting those performance metrics broadly on PJM’s public website. Instead, \nPJM should circulate the proposed metrics to the Members Committee sectors for \ncomment and input before the metrics are finalized, while preserving appropriate \nconfidentiality for compensation-related and other sensitive information. \n \nSection 205 Filing Rights \n \n11. Should the stakeholder process be advisory, i.e., stakeholder votes only inform the \nBoard? \n \nYes. While a deliberative stakeholder process is important to understanding various \nperspectives and enabling coordinated regional decision-making, under the current PJM \ngovernance structure, the stakeholder process can too often forestall action if the matter is \nfinancially significant to vested stakeholder interests, operationally sensitive, or \notherwise polarizing. PJM needs to be able to take more timely and decisive action. \nConverting the stakeholder process to an advisory process would balance the need for \nstakeholder input with PJM’s need for independence and ability to take decisive action on \ncritical issues."},{"page":5,"startToken":1370,"endToken":1749,"text":"5 \n \n12. Should PJM have section 205 filing rights over the energy market and ancillary \nservices unencumbered by the requirement to obtain approval of two-thirds of the \nMembers Committee? \n \nYes. Duke Energy supports PJM having Section 205 filing rights over the energy and \nancillary services market rules. Energy and ancillary services market operation and \ndesign are core to PJM operations, and PJM should have the unilateral authority to take \ntimely and decisive action, informed by stakeholder input.  \n \n \n \n13. Should PJM have section 205 filing rights over Regional Transmission Expansion \nPlanning (RTEP) unencumbered by the requirement to obtain approval of two-\nthirds of the Members Committee? \n \nYes, with important limitations. Duke Energy supported the agreement between PJM and \nPJM transmission owners to provide PJM section 205 filing rights over the RTEP as a \npackage with other revisions and updates to the Consolidated Transmission Owners.2  \nWhile that agreement and related filings were rejected by the Commission,3 Duke Energy \ncontinues to support PJM having Section 205 filing rights over the RTEP, as long as other \nkey revisions and updates to the Consolidated Transmission Owners Agreement are also \nmade.  \n \n14. Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over \nresource adequacy and transmission cost allocation filings when a supermajority of \nOPSI agrees on an alternative proposal? \n \nNo. Duke Energy does not support granting OPSI “jump ball” rights over resource \nadequacy or transmission cost allocation filings, even where a supermajority of OPSI \nsupports an alternative proposal. Resource adequacy and transmission cost allocation are \ncore tariff matters that require coordinated regional decision-making, stakeholder input, \nand independent PJM judgment subject to Commission review. Providing OPSI with \nseparate filing rights on these issues would risk elevating state policy preferences over \nthe balanced, sector-based stakeholder process and could undermine PJM’s independence \nin administering its FERC-approved responsibilities. OPSI’s perspectives are important \nand should continue to inform PJM through existing consultation, stakeholder processes, \nand participation in Commission proceedings, but those perspectives should not create a \nparallel filing pathway that could complicate or delay timely regional reforms. \n \n \n2 See Duquesne Light Co., Amendments to the Consolidated Transmission Owners Agreement, Docket No. ER24-\n2336-000 (filed Jun. 21, 2024).  \n3 Duquesne Light Co., et al., 189 FERC ¶ 61,181 (2024), reh’g order, 192 FERC ¶ 61,051 (2025)."},{"page":6,"startToken":1749,"endToken":2107,"text":"6 \n \n15. Should the Members Committee have “jump ball” filing rights over the portions of \nthe tariff where PJM has 205 filing rights when a supermajority of stakeholders \napproves an alternative proposal? \n \nNo. Duke Energy does not support granting the Members Committee “jump ball” filing \nrights over portions of the tariff where PJM has section 205 filing rights, even where a \nsupermajority of stakeholders supports an alternative proposal. Where PJM is assigned \nsection 205 filing authority, PJM must be able to exercise that authority independently \nand efficiently to carry out its FERC-approved responsibilities for reliable operations, \nmarket administration, and timely regional reforms. Creating a parallel Members \nCommittee filing right over the same tariff provisions would undermine the purpose of \nassigning those filing rights to PJM, risk duplicative or competing filings, and could \ndelay needed reforms. Stakeholder input remains essential and should continue to inform \nPJM’s decision-making through the stakeholder process and Commission proceedings, \nbut that input should not displace PJM’s independent filing authority in areas where the \ntariff assigns PJM section 205 rights. \n \nStakeholder Process \n \n16. Should the approval threshold in the Members Committee be lowered from two-\nthirds sector-weighted voting? \n \nNo. Duke Energy does not support lowering the Members Committee approval threshold \nfrom the current two-thirds sector-weighted voting standard. The existing threshold helps \nensure that significant stakeholder-supported changes reflect broad consensus across \nPJM’s diverse sectors rather than the preferences of a narrow majority or a single sector \ncoalition. Maintaining the two-thirds sector-weighted vote protects the balance embedded \nin PJM’s stakeholder governance structure, encourages compromise among sectors with \ndifferent interests, and reinforces confidence that proposals advancing through the \nMembers Committee have substantial cross-sector support. Lowering the threshold could \nweaken that consensus-based model and increase the risk that contested reforms move \nforward without sufficient stakeholder alignment. \n \n17. Should the voting rules barring affiliate votes, which apply to senior standing \ncommittees, also apply to lower-level committees? \n \nYes. Duke Energy supports applying affiliate voting restrictions not only to senior \nstanding committees but also to lower-level committees. Although lower-level \ncommittees may not make final decisions, they often shape, refine, and advance \nproposals that ultimately move through stakeholder process. Allowing affiliates to cast"},{"page":7,"startToken":2107,"endToken":2447,"text":"7 \n \nmultiple votes at those lower-level stages can provide disproportionate influence over the \ndevelopment of proposals before they reach higher-level committees for consideration.  \n \nState Participation \n \n18. In addition to OPSI, should there be a second state representative group consisting \nof governors’ representatives and/or state legislators’ representatives? \n \nNo. Duke Energy does not support creating a second state representative group consisting \nof governors’ representatives or state legislators’ representatives. OPSI already provides \nan established mechanism for state regulatory perspectives to be communicated to PJM \nand stakeholders. Creating an additional governmental organization could duplicate \nexisting channels, create uncertainty regarding which entity speaks for a state, and add \ncomplexity to an already extensive governance and stakeholder process. While state input \nis important, it should be provided through clear and existing channels in a manner that \npreserves PJM’s independence, supports timely decision-making, and avoids introducing \npolitical considerations into technical reliability and market governance matters. \n \n19. Should state representatives have a formal voting role in the stakeholder process \n(limited to certain topics, such as resource adequacy and regional transmission cost \nallocation) in addition to the consumer advocate votes?  \n \nNo. Duke Energy does not support granting state representatives a formal voting role in \nthe PJM stakeholder process. State input is important and should continue to be \nconsidered through OPSI, FERC proceedings, stakeholder engagement, and other \nexisting channels. However, providing state representatives with formal voting rights \ncould blur the distinction between state policy advocacy and PJM’s independent \nresponsibility to administer reliable operations and nondiscriminatory markets under its \nFERC-approved governing documents. It also could disrupt the balance of PJM’s sector-\nbased stakeholder process and add complexity to already challenging market, resource \nadequacy, and transmission cost allocation reforms. \n \n20. Should PJM be required to consult with OPSI prior to making a section 205 filing \nrelated to resource adequacy and transmission cost allocation? \n \nNo. We are concerned that such a requirement would impede PJM’s independence. OPSI \nhas opportunities to provide feedback through the current Stakeholder process. Additional \nconsultation requirements could create delays and impediments to PJM taking decisive \naction when needed."},{"page":8,"startToken":2447,"endToken":2545,"text":"8 \n \nConclusion \n \n \nWe appreciate the Commission encouraging stakeholders and interested parties to \nshare their recommendations and suggestions for ways to enhance the responsiveness of PJM to \nchanging market and industry conditions while at the same time maintaining reliability and \nindependence. We are looking forward to participating in the upcoming discussions and are \nhopeful that constructive revisions to the PJM process will result.  \n \nRespectfully submitted, \n__/s/ Molly Suda_________________ \nMolly Suda \nDeputy General Counsel \n1301 Pennsylvania Ave. NW, Suite 200 \nWashington, DC 20004 \n202-824-8011 \nmolly.suda@duke-energy.com \n \nAttorney for Duke Energy  \n \nCC:  Official Service List for Docket No. AD26-7"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":8,"endAt":5,"startToken":0,"endToken":2448},{"p":8,"at":5,"title":"Conclusion","method":"printed heading","endPage":8,"endAt":728,"startToken":2448,"endToken":2545}]}