{"document":{"slug":"rec-20260821-5155","title":"Comments of Institute for Policy Integrity at New York University School of Law on PJM Interconnection, L.L.C.’s Section 205 filing to implement Reliability…","issued":"2026-08-21","accession":"20260821-5155","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"Institute for Policy Integrity, New York University School o","kind":"comments","file":"sources/filings/text/20260821-5155_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5155","tier":"record","sha256":"3612692fabec68ad39504542d18f8e7080b2187d23829edd7306fbf454134a2d","pages":29,"tokens":10326,"emptyPages":[],"textThemes":["adequacy","cost","registry","flex"]},"pages":[{"page":1,"startToken":0,"endToken":259,"text":"1 \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM Interconnection, L.L.C.  \n \n \n \n \nDocket No. ER26-3380-000 \n \n \nCOMMENTS OF THE INSTITUTE FOR POLICY INTEGRITY  \nAT NEW YORK UNIVERSITY SCHOOL OF LAW ON  \nPJM INTERCONNECTION, L.L.C. SECTION 205 FILING  \nTO IMPLEMENT RELIABILITY BACKSTOP PROCUREMENT \n \n \n \nThe Institute for Policy Integrity at New York University School of Law (Policy \nIntegrity)1 respectfully submits the following comments to the Federal Energy Regulatory \nCommission (FERC) regarding PJM Interconnection, L.L.C. (PJM)’s Federal Power Act (FPA) \nSection 205 proposed tariff implementing Reliability Backstop Procurement (RBP). Policy \nIntegrity is a non-partisan think tank dedicated to improving the quality of government \ndecisionmaking through advocacy and scholarship in the fields of administrative law, economics, \nand public policy.  \nOn July 31, 2026, pursuant to Section 205 of the FPA, PJM filed for revisions to its Open \nAccess Transmission Tariff to implement RBP, which will include a Reliability Backstop \nAuction (Backstop Auction). These revisions are designed to address the capacity shortfall in the \n2028/2029 Base Residual Auction (BRA, or Legacy Capacity Market) and future BRA shortfalls \nthat PJM anticipates will occur.2 Part I of these comments provides context for PJM’s proposed \ntariff revisions. Part II explains that FERC should reject PJM’s proposed tariff because PJM has \n \n1 This document does not purport to present the views, if any, of New York University School of Law.  \n2 PJM Interconnection, L.L.C., Reliability Backstop Procurement to Address Resource Adequacy Concerns \nStemming from Large Loads, 7-8, 27-28 (filed July 31, 2026) (hereinafter, Tariff Filing)."},{"page":2,"startToken":259,"endToken":698,"text":"2 \nfailed, for multiple reasons, to meet its burden to show that the Backstop Auction is just and \nreasonable. These reasons include: \n1) PJM cannot sufficiently determine whether long-term, systemic problems exist in the \ncapacity market before three consecutive BRA shortfalls occur; \n2) The Backstop Auction will not isolate the Legacy Capacity Market from the costs of \nlarge load growth; \n3) PJM can address its resource adequacy problems at lower cost and with less risk of \ncost-shifting through other means. \nPart III asserts, in the alternative, that FERC should find that PJM can demonstrate its \nproposed tariff is just and reasonable only if PJM amends the design of the Backstop Auction to \nmitigate the likelihood that it will result in unjust and unreasonable rates.3 Part III sets out tariff \namendments that PJM can adopt to reduce the risk that its tariff will result in unjust and \nunreasonable rates. \nI. \nBACKGROUND \nOn December 17, 2025, PJM announced that the 2027/2028 BRA cleared 6,623 MW \nshort of its procurement target.4 In a report investigating the causes of this shortfall, PJM \n \n3 In its tariff filing, PJM notes that it “consents to the Commission’s exercise of authority to modify and/or sever any \nelement of the proposed Tariff . . . to the extent necessary and permitted under section 205 of the FPA and NRG \nPower Marketing, LLC v. FERC, where such modification and/or severance is consistent with PJM’s overarching \nobjectives in this filing.” Tariff Filing, supra n. 2, 5. While NRG Marketing limits FERC’s ability to unilaterally \npropose modifications to section 205 tariff filings, PJM has the authority to consent to accept FERC’s proposed \nmodifications. 862 F.3d 108, 114 (D.C. Cir. 2017).  \n4 PJM Interconnection, L.L.C., 2027/2028 BASE RESIDUAL AUCTION TARGET SHORTFALL REPORT 1-2 (Feb. 9, \n2026), https://perma.cc/Z5A7-GYJ2 (hereinafter, BRA Shortfall Report); PJM Auction Procures 13,479 MW of \nGeneration Resources, PJM INSIDE LINES (Dec. 17, 2025), https://perma.cc/2P3E-4Z75. PJM’s procurement target \nfor the BRA is based on load forecasts submitted by Electric Distribution Companies (EDCs) for each zone. PJM \nManual 19: Load Forecasting and Analysis, Section 1.1 (June 30, 2026), https://perma.cc/7KMP-FY3K (hereinafter, \nPJM Manual 19). PJM may implement future BRAs with more reliable load forecasts, since the PJM Board recently \ndirected PJM Staff to implement a host of reforms to the load forecasting process, including state review of large \nload additions, addressing duplicative requests, and the use of additional third-party review and increased \ntransparency. PJM Board Decisional Letter on Critical Issue Fast Path - Large Load Additions, 2 (Jan. 16, 2026), \nhttps://perma.cc/3HXP-SYJF."},{"page":3,"startToken":698,"endToken":1077,"text":"3 \npredicted that capacity market shortfalls would likely continue over the next decade, driven by \nforecasted demand growth from data centers and other customers.5 PJM’s report also found that \nthe administrative price collar imposed on the capacity market likely exacerbated the deficit.6 \nOn January 15, 2026, the White House Natural Energy Dominance Council and the PJM \nGovernors’ Coalition signed a “Statement of Principles Regarding PJM” (Statement of \nPrinciples), which directed PJM to “[p]rovide 15-year price certainty for new capacity \nresources.”7 The Statement of Principles suggested PJM could provide price certainty by \n“holding a Reliability Backstop Auction to procure new capacity resources commencing no later \nthan September 2026.”8 In response, the PJM Board initiated a Critical Issue Fast Path (CIFP) \nprocess to develop an RBP proposal and PJM subsequently convened a series of stakeholder \nmeetings to solicit feedback.9 In the same CIFP, PJM also solicited stakeholder feedback on \nInterim Resource Adequacy Service (IRAS), formerly denoted “Connect and Manage,” a \nprogram that would require new large loads to bring their own new capacity to the grid, or be \nsubject to interruptible service under certain emergency conditions.10 On July 14, 2026, in the \nmidst of the RBP stakeholder process, PJM announced that the 2028/2029 BRA cleared short of \nits procurement target by 6,831 MW.11 \n \n5 If FERC approves the IRAS proposal that PJM recently submitted, then PJM’s predictions of future capacity \nmarket shortfalls become significantly less likely. See infra § II.D.1 for further discussion.  \n6 See generally BRA Shortfall Report, supra n. 4. \n7 White House National Energy Dominance Council & PJM Governors’ Coalition, Statement of Principles \nRegarding PJM (Jan. 15, 2026), https://perma.cc/8U3F-U79Q (hereinafter, Statement of Principles).  \n8 Id. \n9 PJM Interconnection, L.L.C., Reliability Backstop Procurement Issue Charge, 1 (Apr. 10, 2026), \nhttps://perma.cc/MQ3E-ZFN9; PJM Interconnection, L.L.C., Critical Issue Fast Path - Reliability Backstop \nProcurement / Connect & Manage Landing Page (accessed Aug. 11, 2026), https://perma.cc/ZU49-2CRA.  \n10 PJM Interconnection, L.L.C., Reliability Backstop Procurement Issue Charge (May 22, 2026), \nhttps://perma.cc/RTH7-95HT.  \n11 PJM Capacity Auction Procures 138,318 MW of Generation Resources as Work Continues to Address Growing \nElectricity Demand, PJM INSIDE LINES (July 14, 2026), https://perma.cc/3THF-LHPQ."},{"page":4,"startToken":1077,"endToken":1458,"text":"4 \n \nPJM’s final RBP proposal comprises two elements to occur in parallel, only one of which \nrequires FERC approval. First, PJM will facilitate matching between customers and suppliers \nwho want to enter bilateral capacity contracts. PJM’s consultant issued a Request for Proposals \non June 9, 2026, and the matching process will occur over the course of six to nine months, \nexpected to start in late August.12 PJM need not amend the tariff for this private contracting \nprocess because PJM will merely facilitate voluntary negotiations and not participate as a party. \nSecond, PJM proposes to run a Backstop Auction, starting on September 30, 2026, to procure \nenough capacity to cover the 2028/2029 BRA shortfall.13 That Backstop Auction would be \nsubject to the following proposed rules: \n● The Backstop Auction would accept supply bids only from “new”14 capacity resources, \nwhich can have an in-service date any time after the 2028/2029 DY and before June \n2032; \n● The Backstop Auction would secure capacity for 15-year terms. If a supplier bids \ncapacity that will begin service later than 2028/2029 DY, the contract term would extend \nto the remainder of the 15-year term (e.g., a generator coming online in 2032 would only \nhave a ten-year contract); \n \n12 Tariff Filing, supra n. 2, 30-31; PJM Interconnection, L.L.C., CIFP Reliability Backstop Procurement - PJM \nBoard Decision, 1 (July 31, 2026), https://perma.cc/EA2Q-X5JD (hereinafter, RBP Board Decision); Charles River \nAssociates, PJM Reliability Backstop Procurement Bilateral Request for Proposal (June 9, 2026), \nhttps://perma.cc/BN29-2UAF.  \n13 PJM will target September 30, 2026 to begin bid solicitation, which would close three weeks later (October 21, \n2026). The subsequent clearing and selection process would conclude six weeks after the offer submission window \ncloses, and the sellers would be notified as soon as practicable once the backstop auction ends. Tariff Filing, supra \nn. 2, 27, 48. The initial target for the backstop auction is approximately 6.8 GW, which PJM will reduce based on \nevidence of bilateral contracts for new capacity. See infra fn. 16. \n14 PJM defines “new” capacity to determine which supply qualifies to bid into the backstop auction more narrowly \nthan PJM defines “new” capacity to determine what qualifies to decrement the procurement target. Tariff Filing, \nsupra n. 2, 36, 51."},{"page":5,"startToken":1458,"endToken":1946,"text":"5 \n● Each Backstop Auction contract would work as a “contract for differences” against future \ncapacity auction prices with PJM as the counterparty;15  \n● The procurement target would be set as the amount of the 2028/29 BRA shortfall, less \nany capacity secured in bilateral contracts prior to the Backstop Auction or subject to \nstate peak shaving laws;16 \n● The auction mechanism would be “pay-as-bid”17 with a price cap set at $555/MW-day \nUCAP (1.5 x Net Cost of New Entry) for the volume-weighted average of the levelized \ncost of all selected offers;18 \n● PJM would allocate Backstop Auction costs to zones based on each zone’s pro rata share \nof the total costs. PJM would then allocate costs within zones to Load Serving Entities \n(LSEs) based on cost allocation methodologies submitted by the state or Relevant \nElectric Retail Regulatory Authority (RERRA);      \n● If states or RERRAs do not provide PJM with a cost allocation methodology, PJM would \nrevert to using Peak Load Contribution to allocate Backstop Auction costs among \nLSEs.19  \n \n15 E.g. For any capacity contracted in the RBP for 2030, suppliers will bid that capacity into the 2030 BRA at $0, \nand either suppliers or Load Serving Entities (LSEs) will pay the difference between the RBP price and the BRA \nprice, depending on which is higher. So, for example, if the BRA clears at $100/MW-day, but PJM accepts a \nsupplier’s bid for capacity at $200/MW-day in the backstop auction, that supplier would receive $100/MW-day in \nthe BRA, and PJM would compensate that supplier with an additional $100/MW-day, so the supplier receives a total \nof $200/MW-day. Conversely, if the BRA clears at $200/MW-day, and the backstop auction clears at $100/MW-\nday, the suppliers would have to pay back $100/MW-day to the LSEs and would effectively receive a total of \n$100/MW-day.  \n16 The window for suppliers to submit bids will run three weeks after the auction opening date (PJM proposes that \nthis will start on September 30, 2026, but acknowledges that there may be delays). If the auction opens on \nSeptember 30, as proposed, the window for bid solicitation will close on October 21, 2026. At any time during this \nwindow, LSEs can submit evidence of bilateral contracts and PJM will subtract these contracts from the \nprocurement target.  \n17 Under a pay-as-bid system, suppliers are paid the amount of the bid they offer, as opposed to the clearing price.  \n18 For example, a supplier could bid in an offer over $555/MW-day and its bid may still be accepted if enough other \nsuppliers bid in below the price cap, such that the overall average of all bids remains below $555/MW-day.  \n19 Tariff Filing, supra n. 2, 97-99. There are limited opt-out provisions for (1) zones that can demonstrate an \ninability to allocate costs to large loads; and (2) states that demonstrate they have peak-shaving programs codified in"},{"page":6,"startToken":1946,"endToken":2226,"text":"6 \nII. \nFERC should reject the proposed tariff revisions because PJM has failed to \ndemonstrate that the Backstop Auction is just and reasonable. \n \nPJM has not met its burden to demonstrate that the Backstop Auction is just and \nreasonable for the following reasons:  \n1) PJM has not adequately explained why it is appropriate to run the Backstop \nAuction before three consecutive BRA shortfalls indicate long-term, systemic \nmarket problems;  \n2) PJM has not adequately explained why the Backstop Auction is appropriate given \nthat it will not isolate the capacity market from the impacts of large load growth; \nand  \n3) PJM has not adequately explained why the Backstop Auction is warranted given \nthat other alternatives will address the same problems at lower cost and with less \nrisk of cost-shifting.  \nBecause PJM cannot demonstrate that its proposed tariff is within the zone of \nreasonableness and has not provided substantial evidence showing that the revisions will result in \njust and reasonable rates, FERC should reject the proposed tariff revisions.20  \nA. PJM must prove that its proposed tariff revisions are just and reasonable \nand supported by substantial evidence.  \n \nUnder FPA section 205, a party seeking to revise its tariff bears the burden of proof to \ndemonstrate that its revisions will result in “just and reasonable” rates.21 The just and reasonable \n \nstate law. Id. at 44-45. PJM indicates that the first category is “designed to address a limited regulatory gap faced by \ncooperatives and municipal utilities whose rates are not regulated by the states.” Id.  \n20 16 U.S.C. § 824d(e); New York Pub. Serv. Comm’n v. FERC, 104 F.4th 886, 890 (D.C. Cir. 2024) (NYPSC v. \nFERC). \n21 See id."},{"page":7,"startToken":2226,"endToken":2704,"text":"7 \nstandard requires “a balancing of investor and consumer interests.”22 Rates must be high enough \nto allow utilities to recover their costs and maintain financial integrity, but they must be low \nenough to avoid imposing excessive costs on consumers.23 Rates may also be unjust and \nunreasonable if they fail to ensure reliable service, or do not assign costs to customers “roughly \ncommensurate” according to who benefits from such costs.24 FERC must find that a rate \nproponent has provided “substantial evidence” that its filing is just and reasonable before FERC \ncan approve the revised tariff.25 This inquiry is equivalent to “arbitrary and capricious” review \nunder the Administrative Procedure Act.26  \nPJM filed its revised tariff pursuant to section 205, which requires PJM to prove that its \nproposed revisions are just and reasonable, i.e., that its rates will not excessively burden \nconsumers, unfairly allocate costs, or lead to reliability problems. If FERC finds that PJM has \nnot provided substantial evidence supporting its assertion that the proposed tariff revisions are \njust and reasonable, FERC must reject the filing.27    \n \n22 Federal Power Comm’n v. Hope Natural Gas Co., 320 U.S. 591, 603 (1944) (finding that the just and reasonable \nstandard requires a balancing of investor and consumer interests); Jersey Cent. Power & Light v. FERC, 810 F.2d \n1168, 1172 (D.C. Cir. 1987) (applying the Hope holding to electric rates).  \n23 Id.; NYPSC v. FERC, 104 F.4th at 890 (“[T]here is not a single ‘just and reasonable rate’ but rather a “zone of \nreasonableness” bounded “on one end by investor interest and [on] the other by the public interest against excessive \nrates.”). \n24 Advanced Energy Mgmt. All. v. FERC, 860 F.3d 656, 661 (D.C. Cir. 2017) (finding that failure to provide reliable \nservice is relevant to the just and reasonable standard); Old Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1255 \n(D.C. Cir. 2018) (Old Dominion) (establishing the cost causation principle); Ill. Commerce Comm’n v. FERC, 576 \nF.3d 470, 477 (7th Cir. 2009) (finding that the cost causation principle requires benefits to be “roughly \ncommensurate” with costs) (ICC v. FERC).  \n25 16 U.S.C. § 824l(b); New Jersey Bd. of Public Utils. v. FERC, 744 F.3d 74, 93 (3rd Cir. 2014) (finding that the \nsubstantial evidence standard requires “more than a scintilla, but . . . less than a preponderance of the evidence.”) \n(NJBPU v. FERC).  \n26 Maryland People’s Counsel v. FERC, 761 F.2d 768, 774 (D.C. Cir. 1985) (finding that the “substantial evidence” \nstandard is equivalent to “arbitrary and capricious” review under the Administrative Procedure Act); Ass’n of Data \nProcessing Service Orgs. v. Bd. of Governors of the Fed. Reserve Sys., 745 F.2d 677, 681-86 (D.C. Cir. 1984).  \n27 See NJBPU v. FERC, 744 F.3d at 93 (elaborating on the “substantial evidence” standard)."},{"page":8,"startToken":2704,"endToken":3061,"text":"8 \nB. FERC should reject the proposed tariff because PJM has not adequately \nexplained why it is appropriate to run the Backstop Auction before three \nconsecutive BRA shortfalls indicate long-term, systemic market problems.  \n \nPJM’s current tariff authorizes PJM to hold a reliability backstop auction when three \nconsecutive BRAs clear short of the procurement target.28 It is important that PJM can run a \nbackstop auction only when there are long-term systemic issues in the BRA, not based on short-\nterm market dynamics, because consistent and stable market rules are critical for investment. \nFERC should reject the revised tariff because PJM has not provided substantial evidence to \njustify its decision to depart from the backstop provisions in its existing tariff, particularly given \nrapid and substantial reform occurring at the state and federal levels.29  \nAlthough the BRA cleared short of its target two years in a row, these shortfalls do not \nprovide sufficient evidence that revising PJM’s current tariff is warranted. First, it is unclear \nwhether the two BRA shortfalls would count towards triggering a backstop auction. The current \ntariff triggers a backstop auction only after three consecutive BRA shortfalls.30 But the tariff \ncontemplates that BRAs will acquire capacity three years in advance of the targeted delivery \nyear. PJM has strayed from the auction schedule stipulated in the tariff and held the last two \nauctions to acquire capacity for delivery years closely proximate to the auction year.31 Because \nof these delays, PJM has demonstrated evidence for only two near-term years of capacity \nshortfalls.32 PJM has not adequately explained why two years of near-term predicted capacity \nshortfalls are sufficient to identify systemic problems in the BRA, when the current tariff \n \n28 PJM Interconnection, L.L.C., Open Access Transmission Tariff, Attachment DD, section 16 (effective July 31, \n2026) (hereinafter, Tariff). \n29 16 U.S.C. § 824l(b); NJBPU v. FERC, 744 F.3d at 93 (establishing the “substantial evidence” standard).   \n30 Tariff, supra n. 28, Attachment DD, section 16.  \n31 FERC Order Delays Capacity Auction to Allow for Consideration of Resource Adequacy Reform, PJM INSIDE \nLINES (June 12, 2023), https://perma.cc/9QVK-YF3G.  \n32 See id."},{"page":9,"startToken":3061,"endToken":3427,"text":"9 \nrequires PJM to establish a showing of long-term resource adequacy issues (i.e., shortfalls \nexpected in three, four, and five years in the future) before authorizing a backstop auction.  \nSecond, PJM has not adequately explained why tariff revisions are appropriate \nconsidering recent efforts to encourage more investment in capacity resources and to accelerate \nresource interconnections. PJM and its member states initiated a slew of reforms after the \n2027/2028 BRA shortfall specifically designed to bring more supply online. These reforms need \ntime to work. PJM recently implemented comprehensive interconnection reform to clear its \nqueue backlog and substantially reduce waiting times.33 The window for the first group of \napplicants under PJM’s new “first ready, first served” interconnection process concluded in April \n2026 with over 800 projects representing 220 GW of capacity.34 PJM recently filed tariff \nrevisions to reform its interconnection process even further to comply with Order 2023.35 These \nreforms are pending before the Commission and PJM will likely implement them soon.36 FERC \nalso recently approved PJM’s proposal for an Expedited Interconnection Track, a temporary \nprocess to quickly advance large projects that address urgent capacity needs.37 This new program \ntook effect July 31, 2026, so PJM would not be able to judge its effectiveness before running the \nBackstop Auction.  \nPJM member states are also acting to attract investment in capacity. Virginia passed a \nlaw in April 2026 that comprehensively reformed the solar siting process, creating a uniform \n \n33 PJM Interconnection, L.L.C., New, Faster Generation Interconnection Process Fact Sheet (May 21, 2026), \nhttps://perma.cc/T79X-RQAP.  \n34 Over 800 New Generation Projects Seek to Connect Under PJM’s Reformed Process, PJM INSIDE LINES (Apr. 29, \n2026) https://perma.cc/4DAR-4RQP.  \n35 PJM Interconnection, L.L.C., Order Nos. 2023 and 2023-A Further Compliance Filing of PJM Interconnection, \nL.L.C., Accession No. 20260615-5149 (filed June 15, 2026). \n36 See id.  \n37 PJM Interconnection, L.L.C., Order Accepting Tariff Revisions, 195 FERC ¶ 61,197, P 1 (2026); see also Order \nAccepting Tariff Revisions re PJM Interconnection, L.L.C., 190 FERC ¶ 61,084, (2025) (approving PJM’s one-time \nReliability Resource Initiative to open an interconnection transition cycle to 50 additional shovel-ready projects)."},{"page":10,"startToken":3427,"endToken":3799,"text":"10 \nstatewide process that exempts larger solar projects from certain local regulations.38 Virginia also \ncreated a task force to advance energy affordability and distributed energy, and passed a law \nincreasing battery storage targets for state utilities.39 In New Jersey, Governor Mikie Sherrill \nsigned legislation to launch a new procurement process for nuclear generation.40 In \nPennsylvania, the legislature passed a bill to improve load forecast transparency, which may \nimpact PJM’s demand growth projections.41  \nPJM has not explained how or why the proposed tariff revisions are appropriate given \nthese recent developments, including its own efforts to get new resources online more quickly.  \nPJM has not adequately explained why it is appropriate to lock in new capacity contracts for 15-\nyear terms when state and regional reforms will likely result in more abundant supply for future \nBRAs. Accordingly, FERC should not approve the tariff revisions because PJM has not \nadequately explained or provided substantial evidence that its departure from the terms of the \ncurrent tariff is just and reasonable.  \nC. The Backstop Auction will not isolate the Legacy Capacity Market from the \nimpacts of large load growth.  \n \n \nPJM has not adequately justified its decision to run the Backstop Auction given that the \nBackstop Auction will not shield the Legacy Capacity Market from the rate impacts of large load \ngrowth. Running a backstop auction, regardless of how PJM designs it, will inevitably impact the \n \n38 Code of Virginia §§ 15.2-2288.7-8.  \n39 Virginia Acts of Assembly, 2026 Reconvened Session, Chapter 997, S 223 (approved Apr. 22, 2026) (establishing \nthe task force); Code of Virginia § 56-585.5 (enacting increased storage targets for Virginia utilities).  \n40 State of New Jersey Governor Mikie Sherrill, Governor Sherrill Signs Legislation Launching Procurement \nProcess for New Nuclear Energy & Setting Strong Safeguards to Protect Ratepayers from Costs (July 13, 2026), \nhttps://perma.cc/9S98-WZGB.  \n41 Diana DiGangi, Pennsylvania data centers face increased oversight under new law, UTILITYDIVE (July 14, 2026), \nhttps://perma.cc/EF3J-BQQQ. PJM has taken additional measures to reform load forecasting, such as contracting \nconsultant Charles River Associates to conduct a third-party verification of large load forecasts. Emmanuel Bobbio, \nPJM INTERCONNECTION, L.L.C., Third-Party Review of Large Load Adjustments (June 5, 2026), \nhttps://perma.cc/M2CF-PE9P."},{"page":11,"startToken":3799,"endToken":4174,"text":"11 \nLegacy Capacity Market. As proposed, the Backstop Auction and the Legacy Capacity Market \nare tied together by a contract-for-differences structure. Each supplier who clears a bid in the \nBackstop Auction would also have to bid its committed capacity into the Legacy Capacity \nMarket at $0.42 Suppliers would then receive the BRA clearing price, either topped up or \nsubtracted, to match the price they received in the Backstop Auction.43 Under this structure, the \nresults of the Backstop Auction would inevitably affect prices in the Legacy Capacity Market. \nAnd these effects would persist for the next 15 years because capacity committed through the \nBackstop Auction must also bid into the BRA for each year of its contract. Even if PJM did not \nopt to run the Backstop Auction as a contract-for-differences, any version of a backstop auction \nwould still affect the Legacy Capacity Market. PJM would still have to account for capacity \ncommitted through a backstop auction by adjusting the BRA procurement target.44  \n \nThe exact relationship between the Backstop Auction and the Legacy Capacity Market \nwould change depending on how accurately PJM sets the procurement target for the Backstop \nAuction. PJM sets the procurement target for the Legacy Capacity Market based on load \nforecasts submitted by Electric Distribution Companies (EDCs), and PJM proposes to set the \nprocurement target for the Backstop Auction as the amount of shortfall in the 2028/2029 BRA, \napproximately 6.8 GW.45 If PJM has set the target too high and procures more capacity in the \nBackstop Auction than is actually necessary to serve data centers, the offer requirement for new \nbackstop resources will depress clearing prices in the Legacy Capacity Market. The BRA \nclearing price would fall because capacity committed through the Backstop Auction would flood \n \n42 Tariff Filing, supra n. 2, 56.  \n43 See supra n. 15 for example and explanation. Capacity committed through bilateral contracts also must bid into \nthe Legacy Capacity Market. Tariff, supra n. 28, § 6.6.  \n44 In its tariff filing, PJM argued that the contract-for-differences structure is just and reasonable, but it did not \nprovide any reason for choosing the contract-for-differences structure over any alternatives. Tariff Filing, supra n. 2, \n80-81.  \n45 PJM Manual 19, supra n. 4, Section 1.1."},{"page":12,"startToken":4174,"endToken":4666,"text":"12 \nthe Legacy Capacity Market with supply priced at $0. If the Backstop Auction depresses the \nprices in the Legacy Capacity Market enough, prices may not be high enough to compensate \nexisting suppliers, and they may retire, leading to resource adequacy problems. If enough \ngenerators retire, it could force PJM to rely on expensive emergency procedures, such as \nReliability Must Run (RMR) agreements or requesting the Department of Energy (DOE) to issue \nemergency orders under FPA section 202(c).46 Even if the market eventually responds to these \nretirements with price increases, PJM would still be forced to rely in the short-term on costly, \nand inefficient reliability fixes may impose excessive burden on consumers, which could result \nin unjust and unreasonable rates. \n \nIf PJM has set the procurement target too low, and procures less capacity than data \ncenters need, it could lead to similar outcomes. In a tight market for supply, there may not be \nenough capacity to meet the procurement target for both the Backstop Auction and the Legacy \nCapacity Market. A tight supply market is not an unlikely scenario, since supply is scarce in \nPJM, due to a variety of problems including supply chain shortages and interconnection queue \ndelays.47 When there is not enough supply to go around, suppliers will be more likely to offer \ntheir resources into the Backstop Auction, which has a higher price cap than the upcoming \n2029/2030 BRA.48 The Backstop Auction may also be appealing to resources that are further \n \n46 RMRs are short-term contracts which transmission providers use to retain generators that are necessary to address \nimmediate reliability problems until a long-term solution is implemented. Transmission providers can also request \nthat the DOE issue an FPA 202(c) emergency order, which mandates certain power plants to continue running past \ntheir planned retirement dates. A recent report found that DOE 202(c) mandates could cost ratepayers between $3.1 \nbillion and $5.9 billion per year, depending on how many plants DOE mandates to remain open. MICHAEL GOGGIN, \nGRID STRATEGIES LLC, THE COST OF FEDERAL MANDATES TO RETAIN FOSSIL-BURNING POWER PLANTS 9 (Aug. \n2025) https://perma.cc/94M2-HQUD (hereinafter, 202(c) Report).  \n47 BRA Shortfall Report, supra n. 4, 5.  \n48 Tariff Filing, supra n. 2, 61. Even though suppliers must bid capacity committed through the backstop auction \ninto the BRA, the BRA price cap does not apply to backstop auction resources. The backstop auction is likely to be \nmore attractive to suppliers than the BRA as long as the BRA has a price cap lower than the backstop auction. But \neven if the BRA price collar expires, suppliers may still prefer to bid into the backstop auction because it has a \nflexible “soft cap” which may accept offers above the $555/MW-day price cap, as long as the average cost per MW-\nhour is less than $555/MW-day. By contrast, even without the $325/MW-day price collar imposed on the BRA, the"},{"page":13,"startToken":4666,"endToken":5033,"text":"13 \nadvanced in the interconnection queue, such as projects approved under the Reliability Resource \nInitiative (RRI), because the Backstop Auction offers price certainty for 15 years, whereas the \nLegacy Capacity Market offers one-year contracts.49  \nIf enough suppliers opt for the Backstop Auction instead of the Legacy Capacity Market, \nthe Legacy Capacity Market may not be able to maintain resource adequacy as large loads come \nonline. Thus, the Backstop Auction would not insulate non-large load ratepayers from the \nimpacts of large load growth. If PJM implements IRAS, more new large load growth than \nexpected will not cause problems for the Legacy Capacity Market, since the new large loads \nwould be interruptible unless they bring their own new capacity. But if FERC does not approve \nIRAS, the Backstop Auction would likely lead to resource adequacy issues in the Legacy \nCapacity Market, which may require PJM to implement costly short-term reliability fixes.50 \nAllowing the costs of new large load growth to bleed into the Legacy Capacity Market would be \ninconsistent with the Statement of Principles, which instructed PJM to “allocate the cost of any \nnew capacity through the . . . Reliability Backstop Auction to load serving entities (LSEs) with \nnew data centers that have not self-procured new capacity or agreed to be curtailable.”51 The \nBackstop Auction may also be unjust and unreasonable if it cannot isolate the impacts of large \nload growth from the Legacy Capacity Market because the auction would not allocate costs \n“roughly commensurate” to the customers which incurred those costs.52 \n \nBRA typically has a “hard cap” reflecting the maximum price that demand is willing to pay for new capacity, set at \nthe cost of new entry, which varies from region to region. CONGR. RSCH. SERV., PJM’S ELECTRIC CAPACITY \nMARKET: BACKGROUND AND CURRENT ISSUES 5 (June 2025), https://www.congress.gov/crs-product/R48553 \n(hereinafter, CRS Report). \n49 PJM Chooses 51 Generation Resource Projects to Address Near-Term Electricity Demand Growth, PJM INSIDE \nLINES (May 2, 2025), https://perma.cc/A48B-UY7N.  \n50 See 202(c) Report, supra n. 46, 9.  \n51 Statement of Principles, supra n. 8.  \n52 Old Dominion, 898 F.3d at 1255 (establishing the cost causation principle); ICC v. FERC, 576 F.3d at 477."},{"page":14,"startToken":5033,"endToken":5373,"text":"14 \nD. FERC should reject the tariff revisions because PJM can address its resource \nadequacy mechanisms through other means at lower cost and with less risk \nof cost-shifting. \n \nThere is no single just and reasonable rate, and PJM may choose from a range of options \nwithin the “zone of reasonableness.”53 Nevertheless, PJM must adequately explain and support \nits decisions with substantial evidence in order to meet its burden to demonstrate that the \nproposed tariff is just and reasonable.54 Here, PJM has failed to carry its burden because PJM has \nnot adequately explained its decision to amend the tariff. While PJM’s tariff filing cites demand \ngrowth and generator retirements as reasons to run the Backstop Auction earlier than the current \ntariff authorizes, PJM does not explain why it is opting to hold the Backstop Auction given that \nexisting or forthcoming resource adequacy mechanisms would solve the same problems at lower \ncost and with less risk of resulting in unjust and unreasonable rates.55  \nPJM is more likely to achieve just and reasonable rates by implementing IRAS, \nencouraging the bilateral trading process among sophisticated large loads, and focusing on its \ncapacity market redesign efforts than by implementing a Backstop Auction with fixed, 15-year \nterms. Considering this alternative, PJM has not adequately explained its decision to resolve its \nresource adequacy problems through the Backstop Auction.  \n1. Implementing IRAS is more likely to result in just and reasonable \nrates. \n \nPJM has not adequately explained why tariff revisions are appropriate considering that \nthe IRAS proposal is still pending before FERC. If accepted, IRAS would be a significant step \ntoward resolving the resource adequacy and affordability problems posed by large load growth. \nA mandatory IRAS system would incentivize new large loads to bring their own new capacity, \n \n53  NYPSC v. FERC, 104 F.4th at 890 (finding that rates must fall within a zone of reasonableness). \n54 16 U.S.C. § 824l(b); NJBPU v. FERC, 744 F.3d at 93 (elaborating on the “substantial evidence” standard).  \n55 Tariff Filing, supra n. 2, 28."},{"page":15,"startToken":5373,"endToken":5707,"text":"15 \nbecause they will be subject to interruptible service if they do not do so.56 If large loads do not \nbring their own capacity, IRAS would mitigate the need for PJM to procure expensive capacity \nresources for large loads, because they will be interruptible under certain conditions when the \ngrid is stressed.57 IRAS advances affordability because PJM would not have to procure as much \ncapacity (costs that may be difficult to allocate perfectly to large loads). IRAS advances resource \nadequacy because PJM would be less likely to face capacity shortfalls if large load customers \nwere interruptible. Both benefits are likely to result in just and reasonable rates because \nincreased affordability and reliability reduce the likelihood that large load growth will burden \ncustomers who are not responsible for the capacity deficits caused by large loads. PJM has not \nadequately explained why the Backstop Auction is appropriate given that its IRAS proposal \nwould solve the same problems at a lower cost and with less risk of cost-shifting. \n2. Bilateral trading for sophisticated large loads is less likely to result in \nunjust and unreasonable rates than the Backstop Auction.  \n \nPJM has not adequately explained why the Backstop Auction is appropriate given that \navailable alternatives, such as the bilateral trading process, are less likely to result in unjust and \nunreasonable rates. PJM can and should act to further encourage bilateral trading among \nsophisticated large load customers.   \na) Bilateral trading for sophisticated large load customers is less \nlikely to result in unjust and unreasonable rates. \n      \n Bilateral trading for sophisticated large loads, in conjunction with IRAS, is less likely to \nresult in unjust and unreasonable rates because bilateral trading will address PJM’s resource \nadequacy issues at lower cost and with less risk of cost-shifting than the Backstop Auction. \n \n56 PJM Interconnection, L.L.C., Proposal of PJM Interconnection, L.L.C. to Establish Interim Resource Adequacy \nand a Large Load Registry to Address System Reliability, 21-22, Accession No. 20260813-5118 (filed Aug. 13, \n2026) (hereinafter, IRAS Filing).  \n57 Id."},{"page":16,"startToken":5707,"endToken":6042,"text":"16 \nUnlike the Backstop Auction, bilateral trading (1) avoids the need to develop artificial proxies \nfor demand, (2) allows sophisticated parties to reach greater efficiencies through customized \ncontracts, and (3) more precisely allocates costs to the parties responsible for incurring greater \ncapacity needs.  \nFirst, bilateral contracting is less likely to result in unjust and unreasonable rates because \nit does not require PJM to develop artificial indicators of demand. Under any version of the \nBackstop Auction, PJM must select proxies for demand. Demand includes the quantity of \ncapacity customers wish to purchase (the procurement target) and customers’ “willingness-to-\npay” for that capacity (the price cap, usually derived from the net cost of new entry). PJM \nproposes to approximate willingness-to-pay by creating a “soft cap” on the levelized cost per \nMW of capacity at $555/MW-day.58 As opposed to a “hard cap,” like a price collar or a price \ncap, the soft cap would allow bids over the limit as long as the total average paid per MW does \nnot surpass $555/MW-day.59 While centralized auctions are generally considered to result in \nmore efficient price discovery than private contracts, it is less likely that the Backstop Auction \nwill accurately and efficiently balance the dynamics of supply and demand since PJM has to \nselect artificial proxies for demand and willingness-to-pay.  \nAdditionally, the Backstop Auction may not result in efficient price signals because the \nauction, as designed, encourages participants to place speculative bids not based on actual \nmarginal costs. For example, PJM proposes to run the Backstop Auction under a pay-as-bid \nformat, as opposed to the single-clearing price format. Under this design, suppliers may try to \nmaximize profit and their odds of clearing by guessing the clearing price and the offer \n \n58 Tariff Filing, supra n. 2, 61.  \n59 In the absence of a price collar, PJM generally applies a price cap based on a proxy for demand’s maximum \n“willingness-to-pay” which is based on regional net cost of new entry. See CRS Report, supra n. 48, 5."},{"page":17,"startToken":6042,"endToken":6449,"text":"17 \ndistribution (i.e., the various prices at which other suppliers will bid into the auction). This \ndesign is not ideal because a market which encourages bidders to speculate may not strike the \nright balance between keeping prices affordable and compensating suppliers enough to make a \nreasonable return on investment.60  \nIt is not clear that PJM would achieve improved market efficiencies even by running the \nauction with a hard cap. With a hard cap and a pay-as-bid format, suppliers may be incentivized \nto bid right at the cap regardless of their marginal costs, raising prices for customers. Regardless \nof the market design, running a backstop auction would force PJM to make administrative \ndecisions to approximate real-world market forces. Making these decisions is particularly \ndifficult in the context of large load growth, since so much of this demand is speculative.61 And \nif PJM incorrectly gauges its proxies, the Backstop Auction will either not procure enough \ncapacity, leading to potential reliability problems, or procure too much capacity, leading to \naffordability problems and excessive consumer burden.62 Conversely, bilateral trading does not \nrequire PJM to make artificial design choices under rapidly evolving conditions. PJM can avoid \nthe design choices required by centralized auctions by relying on bilateral contracts, which are \nthus less likely to result in unjust and unreasonable rates.  \n \n60 Single clearing price auctions are typically more efficient than pay-as-bid, but the combination of pay-as-bid and \nthe soft cap makes the outcomes difficult to predict. See ALFRED E. KHAN, ET AL., BLUE RIBBON PANEL REPORT, \nPRICING IN THE CALIFORNIA POWER EXCHANGE ELECTRICITY MARKET: SHOULD CALIFORNIA SWITCH FROM A \nUNIFORM PRICING TO PAY-AS-BID PRICING? 3 (Jan. 2001), https://perma.cc/YJ6P-XJPV.  \n61 Even when data center loads materialize, their energy consumption can be less than anticipated. E3, FORECASTING \nLARGE LOADS IN THE AGE OF AI AND DATA CENTERS 3 (Dec. 2025) https://perma.cc/F8FU-WUCR (hereinafter, \nLarge Load Forecasting White Paper). Or they may increasingly favor behind the meter bilateral, private supply \narrangements with resources that are not grid-connected. See Disha Raychaudhuri & Valerie Volcovici, Pollution \nfrom Musk’s unpermitted xAI power project hits hardest in Black communities, REUTERS (July 14, 2026) \nhttps://perma.cc/P3E5-5BCD; Marlene Wilden, Texas approves AI data center co-location next to wind farm, with \ncurtailment caveats, UTILITYDIVE (July 30, 2026), https://perma.cc/A7WB-BPFA.  \n62 NYPSC v. FERC, 104 F.4th at 890 (finding that just and reasonable rates cannot impose “excessive burden” on \nconsumers)."},{"page":18,"startToken":6449,"endToken":6839,"text":"18 \nSecond, bilateral contracting is less likely to result in unjust and unreasonable rates \nbecause it allows for customization. All contracts in the Backstop Auction would have the same \nterms and product definitions, aside from some variation in term length.63 But matching data \ncenters with supply can involve complex, non-standard transactions. Some data centers may \nprefer to contract for higher or lower reliability standards.64 Other companies may be interested \nin nontraditional supply options that cannot easily bid into the market. For example, Google \nrecently contracted with Voltus, Inc., a virtual power plant operator, to purchase capacity in the \nform of aggregated distributed energy resources.65 Bilateral contracts can also include complex \nrisk hedging provisions such as price indexing, which can benefit consumers if prices drop years \nafter the contract is executed.66 For these types of complex transactions, centralized auctions may \ninhibit communication between buyers and sellers and preclude efficiencies from creative \ncontract design that could lower prices and benefit both suppliers and customers.67 Because \ncentralized auctions cannot capture the efficiencies likely to arise in bilateral contracts between \nsophisticated large loads and energy resources, the backstop is more likely to result in unjust and \nunreasonable rates. \nThird, bilateral contracts are less likely to result in unjust and unreasonable rates because \nthey are more likely to allocate data center costs to LSEs that actually serve data centers, or to \n \n63 Tariff Filing, supra n. 2, 54.  \n64 Herman K. Trabish, Data centers are ready to negotiate flexibility for speed, UTILITYDIVE (June 26, 2026), \nhttps://perma.cc/EMG2-CJX2.  \n65 Voltus and Google to Deliver Grid Capacity and Local Economic Benefits Through Bring Your Own Capacity \nAgreement, VOLTUS (June 2, 2026), https://perma.cc/P25B-28LM. Although PJM’s proposed tariff revisions would \nallow DER to participate in the backstop auction, its requirement for DER providers to provide agreements with \neach of its providers up front, for a 15-year auction, is an onerous disincentive and may be prohibitive for this type \nof supply. See infra § III.C.  \n66 See e.g., Nicola Bartolini, Silvia Romagnoli & Amia Santini, Renewing Reliability: Valuation and Credit Risk \nAdjustments for Renewable Power Purchase Agreements 2-3 (arXiv, Working Paper No. 2607.04781v1, 2026) \nhttps://perma.cc/QS8N-7Q49.  \n67 NYPSC v. FERC, 104 F.4th at 890 (finding that just and reasonable rates cannot impose “excessive burden” on \nconsumers)."},{"page":19,"startToken":6839,"endToken":7216,"text":"19 \nthe data centers themselves. Precise cost allocation is consistent with the Statement of Principles \nand the White House Ratepayer Protection Pledge, in which leading data center companies in the \nUnited States committed to paying for their own capacity and infrastructure costs.68 PJM would \nrequire all LSEs to participate in the Backstop Auction, unless they qualify for one of the two \nlimited opt-out categories, and would allocate costs to each zone based on the zone’s pro rata \nshare of the procurement target. Within each zone, PJM would allocate costs to LSEs based on a \ncost allocation method provided by the relevant state or RERRA.69 But it is not likely that PJM \nwill be able to accurately predict how large load growth will develop in each zone over the next \n15 years.70  \nWhile PJM does not have to ensure perfect cost causation to achieve just and reasonable \nrates, PJM does have to demonstrate that it allocates rate burdens “roughly commensurate” with \nbenefit.71 Given that the Backstop Auction is acquiring capacity so far in advance and for such \nlong contract terms, it is likely that new large load demand will materialize much differently than \nforecasts predict.72 If this is the case, PJM’s cost allocation for the Backstop Auction is unlikely \nto even be “roughly commensurate” with the participants who receive the benefit of that \ncapacity. Bilateral contracts, on the other hand, directly allocate capacity costs to LSEs serving \nlarge loads, or to the large loads themselves. While bilateral contracts may not perfectly isolate \nresidential ratepayers from data center costs, this allocation is more likely to result in just and \n \n68 White House Ratepayer Protection Pledge (Mar. 4, 2026), https://perma.cc/TW4A-3UMN (hereinafter, Ratepayer \nProtection Pledge).  \n69 Tariff Filing, supra n. 2, 97-99.  \n70 See generally Large Load Forecasting White Paper, supra n. 61. For example, AEP Ohio cut its large load \nforecast by more than 50% after regulators approved a new large load tariff. Ethan Howland, Manufacturers say \nAEP Ohio still inflating data center demand after halving forecast, UTILITYDIVE (Feb. 6, 2026), \nhttps://perma.cc/UT57-LYLQ.  \n71 Old Dominion, 898 F.3d at 1255; ICC v. FERC, 576 F.3d at 477. \n72 See generally Large Load Forecasting White Paper, supra n. 61."},{"page":20,"startToken":7216,"endToken":7596,"text":"20 \nreasonable wholesale rates because the parties who incur the need for new capacity will be the \nonly ones paying for it.73 \nb) PJM can play a valuable role in facilitating more bilateral \ntrades among sophisticated large load customers.  \n \nPJM can play a valuable role in the bilateral trading process by serving as a matchmaker \nbetween supply and demand, setting clear rules for interruptible service, and providing \ntransparent information about the expected cost of network upgrades. First, PJM can add value \nthrough the facilitated bilateral matchmaking program it has proposed to operate in parallel with \nthe Backstop Auction. This approach, preferred by most PJM members, may speed up the \ncontracting process and lower overall costs, since PJM’s service as a facilitator may reduce \ntransaction costs associated with these negotiations.74  \nSecond, PJM will encourage more bilateral contracts by setting clear rules implementing \nIRAS. If FERC approves it, IRAS will make service to new large loads interruptible under \ncertain conditions if they do not commit to bringing their own new capacity before connecting to \nthe grid.75 Finalizing the rules and operating procedures will reduce uncertainty for market \nparticipants, which will further expedite bilateral negotiations by setting out clear rules of the \nroad. \nThird, PJM can add value and reduce uncertainty in the bilateral trading process by \nincreasing transparency on the cost of transmission network upgrades necessary to serve new \n \n73  Old Dominion, 898 F.3d at 1255 (establishing the cost causation principle). If an LSE serving data centers \nexecutes a bilateral contract with a supplier, the LSE may still spread the cost of that capacity to its non-data center \ncustomers. But this is a matter of retail cost allocation, which is outside FERC’s jurisdiction. 16 U.S.C. § 824(a). \nAdditionally, even if LSEs do not perfectly allocate costs to data centers, allocating costs to LSEs with data center \nload is an improvement over the backstop auction, which may allocate backstop auction costs to LSEs with no data \ncenters at all. \n74 Critical Issue Fast Path - Reliability Backstop Procurement PJM Proposal 3, PJM INTERCONNECTION, L.L.C. \n(Apr. 16, 2026), https://perma.cc/2RSW-J9EL.  \n75 CIFP Framework for Service During Periods of Insufficient Resource Adequacy - PJM Proposal, PJM \nINTERCONNECTION, L.L.C. (July 31, 2026), https://perma.cc/CP8R-UVKH."},{"page":21,"startToken":7596,"endToken":7953,"text":"21 \nsupply. Transmission costs are a significant element of the cost of providing power.76 Suppliers \nmust pay for the cost of network upgrades to serve their new supply, but it can be difficult to \npredict what these costs will be.77 The resulting uncertainty makes it difficult to include these \ncosts upfront in long-term bilateral contracts and forces many projects to drop out of the \ninterconnection queue altogether. PJM is in the best position to predict these costs, and it can \nreduce uncertainty in bilateral negotiations by providing this information to developers. PJM \ncould provide this information by implementing something similar to the Consolidated Planning \nProcess (CPP), which is being pioneered by Southwest Power Pool Inc. (SPP), or develop a plan \nto improve network upgrade transparency that is more tailored to the PJM region.78  \nPJM should encourage more bilateral trading and rely on its existing resource adequacy \nmechanisms because PJM has failed to demonstrate that the Backstop Auction will yield a just \nand reasonable rate. The bilateral trading process would move more quickly and have greater \nbenefits for ratepayers if PJM served as a matchmaker between supply and demand, finalized a \nmandatory IRAS framework, and increased transparency around the cost of network upgrades.  \n3. The capacity market redesign is likely to result in just and reasonable \nrates.  \n \nPJM has not adequately explained why the Backstop Auction is appropriate given that it \nmay disrupt PJM’s efforts to holistically redesign the capacity market. PJM is in the process of \nreconsidering the fundamentals of its market design.79 Depending on how the process goes, PJM \nmay transition to an energy-only market or adopt some other mechanism(s) to better ensure \nresource adequacy. PJM’s reformed capacity market may also include a larger role for the states \n \n76 U.S. ENERGY INFO. ADMIN., Annual Energy Outlook 2026, Reference Case, Table 8 (Apr. 2026), \nhttps://perma.cc/RK7V-28PN.  \n77 Southwest Power Pool, Inc., 194 FERC ¶ 61,192, P 11 (2026) (CPP Order).  \n78 CPP Order, 194 FERC ¶ 61,192, at P 11.  \n79 See generally POWERING RELIABILITY THROUGH MARKET DESIGN, PJM INTERCONNECTION, L.L.C. (May 2026), \nhttps://perma.cc/3MHN-CGMU."},{"page":22,"startToken":7953,"endToken":8263,"text":"22 \nto ensure resource adequacy. For example, New Jersey has indicated interest in directing its \nLSEs to procure a fixed percentage of long-term capacity as a hedge against future price \nvolatility.80 PJM may adopt tariff revisions that support state-level efforts to operationalize the \nRatepayer Protection Pledge and ensure just and reasonable rates at the wholesale level.81 \nImplementing the Backstop Auction would complicate efforts to reform PJM’s resource \nadequacy mechanisms because the Backstop Auction, as proposed, is structurally tied to the \nLegacy Capacity Market. It is possible that PJM may be able to find some way to structure \npayments for Backstop Auction capacity commitments that replaces the role of Legacy Capacity \nMarket, such as developing a proxy for capacity market prices if the BRA no longer exists at \nsome point in the next 15 years. But such a structure would add another layer of administrative \ncomplexity both to the implementation of the Backstop Auction, and to PJM’s efforts to reform \nits capacity market. PJM’s long-term efforts to reform its markets are critical to PJM’s ability to \nachieve just and reasonable rates. For this reason, FERC should reject the proposed tariff \nrevisions.  \nOnce PJM implements IRAS, takes further steps to encourage bilateral trading among \nsophisticated large loads, and fully commits to its capacity market redesign efforts, PJM will \nhave the necessary tools in place to meet its resource adequacy problems through just and \nreasonable rates. PJM’s return to its normal three-year forward schedule for BRAs, and the \nongoing implementation of Order 2023 interconnection reforms will also contribute to improved \nresource adequacy. Each of these reforms is close to implementation. For this reason, FERC \nshould reject the proposed tariff revisions.  \n \n80 MAHALA LAHVIS, ET AL., NEW JERSEY BD. OF PUB. UTIL., AN INVESTIGATION OF PJM’S CAPACITY MARKET 72 \n(Aug. 2026), https://perma.cc/847T-995D.  \n81 Ratepayer Protection Pledge, supra n. 68."},{"page":23,"startToken":8263,"endToken":8663,"text":"23 \nIII. \nIf FERC permits PJM to implement the Backstop Auction, FERC should require \nPJM to adjust its proposed market design to mitigate the risk that the Backstop \nAuction will result in unjust and unreasonable rates.  \n \nFERC should reject the proposed tariff revisions because the Backstop Auction is not just \nand reasonable. But if FERC permits PJM to implement the Backstop Auction, it should require \nPJM to implement adjustments to the proposed market design which reduce the risk that the \nBackstop Auction will result in unjust and unreasonable rates.82 FERC should require PJM to \nadjust its proposed market design to mitigate the risks of over-procurement, unfair cost \nallocation, and overpaying for capacity.  \nA. FERC should require PJM to adjust the Backstop Auction design to mitigate \nthe risk of over-procuring capacity. \n \n \nThe Backstop Auction, as filed, is likely to result in unjust and unreasonable rates \nbecause it does not contain sufficient measures to protect against the risk of procuring too much \ncapacity. Over-procuring capacity can lead to unjust and unreasonable rates because it can \nimpose an excessive burden on ratepayers without providing commensurate reliability benefits.83 \nFERC should find that PJM cannot meet its burden to demonstrate its proposed tariff revisions \nare just and reasonable unless PJM adopts amendments that mitigate the risk of capacity over-\nprocurement. To that end, FERC should instruct PJM to amend its filing to set the procurement \ntarget by soliciting voluntary commitments from large loads (i.e., the large load opt-in or \n“subscription” model) and to delay the auction start date after the bilateral matching process \n \n82 In its tariff filing, PJM notes that it “consents to the Commission’s exercise of authority to modify and/or sever \nany element of the proposed Tariff . . . to the extent necessary and permitted under section 205 of the FPA and NRG \nPower Marketing, LLC v. FERC, where such modification and/or severance is consistent with PJM’s overarching \nobjectives in this filing.” Tariff Filing, supra n. 2, 5. While NRG Marketing limits FERC’s ability to unilaterally \npropose modifications to section 205 tariff filings, PJM has the authority to consent to accept FERC’s proposed \nmodifications. NRG Power Mktg., LLC v. FERC, 862 F.3d at 114. \n83 NextEra Energy Resources, LLC v. FERC, 898 F.3d 14, 20 (D.C. Cir. 2018) (finding that a tariff which leads to \noverprocurement of capacity may be considered in the just and reasonable standard)."},{"page":24,"startToken":8663,"endToken":8998,"text":"24 \nconcludes. At a minimum, FERC should request that PJM clarify that orders from state public \nutility commissions suffice to meet the Backstop Auction peak-shaving exemption.  \nFirst, FERC should find that PJM cannot use the 2028/2029 BRA shortfall as the \nBackstop Auction procurement target because it is an arbitrary quantity not based on any long-\nterm load growth forecasts. PJM proposes to set the procurement target for the Backstop Auction \nas the 2028/2029 BRA capacity shortfall.84 PJM chose this number based on forecasts for one \ndelivery year and did not forecast capacity needs over the next 15 years. Given that large load \ndemand forecasts vary dramatically, an artificial target set by PJM is likely less efficient than a \ntarget based on large load’s actual willingness-to-pay.85 \nFERC should direct PJM to adopt the subscription model proposed by the Joint Electric \nDistribution Companies and the Data Center Coalition. The subscription model was the only \nproposal to garner a majority of stakeholder votes in the CIFP–and for good reason.86 Under the \nsubscription model, large loads would voluntarily report how much capacity they want procured \non their behalf and PJM would use that number to set the procurement target for the Backstop \nAuction.87 If PJM does not have to rely on speculative demand growth forecasts, it would reduce \nthe risk of over-procurement. Data centers would likely be more realistic about their capacity \nneeds if they have to put down collateral. The subscription model would also simplify the cost \nallocation process because PJM would directly allocate costs to the large loads that opt into the \nBackstop Auction. The subscription model would mitigate the significant risk that the Backstop \n \n84 Tariff Filing, supra n. 2, 31.  \n85 See generally Large Load Forecasting White Paper, supra n. 61.  \n86 CIFP – Reliability Backstop Procurement/Connect & Manage Summarized Poll Results, PJM INTERCONNECTION, \nL.L.C. (July 2026), https://perma.cc/Q4A7-7PQ6.  \n87 Joint EDCs & Data Center Coalition, Reliability Backstop Procurement Package (July 2026), \nhttps://perma.cc/HNN2-YK8R."},{"page":25,"startToken":8998,"endToken":9332,"text":"25 \nAuction would result in unjust and unreasonable rates since each of these benefits would lead to \nmore precise cost allocation and lower capacity costs for wholesale customers.88 \n \nSecond, if FERC does not instruct PJM to adopt the subscription model, FERC should, at \na minimum, instruct PJM to mitigate over-procurement risk by clarifying that the opt-out \nprovision for states with peak-shaving programs applies broadly. FERC should direct PJM to \nclarify that the tariff provision which allows states to opt out of the Backstop Auction if they \nhave peak-shaving programs “codified in state law” applies to state statutes and orders issued by \na state public utility commission. Some states have passed legislation codifying peak-shaving \nprograms, but it is also common for states to implement these types of programs through orders \nissued by the public utility commission.89 Public utility commission orders are enforceable and \nbinding, so PJM must recognize their validity for the purpose of the limited exception to \nparticipation in the Backstop Auction. This clarification can mitigate the risk that the Backstop \nAuction would over-procure capacity and excessively burden consumers, resulting in unjust and \nunreasonable rates.  \nThird, regardless of whether FERC directs PJM to adopt the subscription model or clarify \nthe peak-shaving exemption, FERC should also direct PJM to delay the start of the Backstop \nAuction to allow time for companies to execute bilateral contracts and for states to implement \npeak-shaving programs. According to PJM’s own survey, most market participants would prefer \n \n88 See Old Dominion, 898 F.3d at 1255 (establishing the cost causation principle); NYPSC v. FERC, 104 F.4th at 890 \n(finding that just and reasonable rates cannot pose “excessive burden” on consumers). \n89 See California Emergency Load Reduction Program, CAL. PUB. UTIL. COMM’N (accessed Aug. 21, 2026), \nhttps://perma.cc/CGV7-ZW53; New York State Dept. Pub. Service, Commission Improves Customer-Centered \nElectric Demand Response Programs (Apr. 2026), https://dps.ny.gov/news/commission-improves-customer-\ncentered-electric-demand-response-programs; Pub. Util. Comm’n of Texas, Project No. 56966, 16 TAC § 25.186, \nhttps://perma.cc/C2KF-62S3."},{"page":26,"startToken":9332,"endToken":9614,"text":"26 \nto purchase capacity through bilateral trades rather than through a centralized auction.90 PJM is \nfacilitating a bilateral matchmaking program to encourage these types of contracts, but the \nmatchmaking process will not conclude until February 2027 at the earliest. PJM should allow \ntime for parties to reach these agreements, which will offset the procurement target for the \nBackstop Auction. Offsetting the procurement target will help protect against the unjust and \nunreasonable rates that would result from over-procuring capacity for 15-year terms.  \nDelaying the auction start date would also allow time for states to implement peak-\nshaving programs. PJM filed the tariff revisions on July 31, 2026, which only leaves states with \ntwo months' notice if they wish to take advantage of the exception and do not already have \nstatutorily mandated peak-shaving programs in place. Pushing back the start date would allow \ntime for states and market participants to take actions that offset the procurement target, reducing \nthe risk that the Backstop Auction would lock in expensive long-term contracts that burden \nconsumers unnecessarily.  \nB. FERC should require PJM to adjust Backstop Auction design to mitigate the \nrisk of unfair cost allocation.  \n \nPJM proposes to assign the costs of the Backstop Auction to zones based on their pro rata \nshare of the procurement target, and then to allocate costs to LSEs based cost allocation \nmechanisms submitted by the relevant state or RERRA. Within each zone, PJM has stated that \nEDCs will have to create mechanisms to allocate costs to individual retail customers prior to the \n \n90 CIFP – Reliability Backstop Procurement Proposal, PJM INTERCONNECTION, L.L.C. (July 2026), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260630/20260630-item-02a---pjm-\nreliability-backstop-procurement-proposal---paper.pdf."},{"page":27,"startToken":9614,"endToken":9930,"text":"27 \ndate on which the capacity acquired in the Backstop Auction will bid into the BRA for the \ndelivery year it will be operational.91  \nApplying this cost allocation methodology to the Backstop Auction would not be just and \nreasonable because it entails serious risk that customers will pay for benefits that they do not \nreceive. For the BRA, assigning capacity obligations to zones based on their pro rata share of the \nprocurement target works well because PJM can reasonably predict an LSE’s capacity needs \nthree years forward by extrapolating from the LSE’s existing customer base. But predictions are \nmore difficult for the Backstop Auction, which would obtain capacity for 15-year terms. EDCs \ncannot reasonably predict an LSE’s over such a long time horizon. Also, it is difficult to \nextrapolate capacity needs from an LSE’s existing customer base because the Backstop Auction \nserves large load growth, much of which may be speculative and has not contracted with an LSE \nfor service.  \nAlthough states and electric distributors may be able to reallocate costs among retail \ncustomers, this does not resolve the problem that large loads may not materialize as expected on \nthe zonal level. If large load growth is expected in the Mid-Atlantic zone, but it actually \nmaterializes in the Western Region, LSEs in the Mid-Atlantic zone would still have to bear those \ncosts. This cost allocation problem sits squarely within PJM’s jurisdiction because incorrectly \nassigning capacity costs at the zonal level affects wholesale customers, not just retail \ncustomers.92  \nTo mitigate this cost-shifting problem, PJM should allow LSEs to trade capacity credits \nwith each other across different zones to serve load growth as needed. This provision was part of \n \n91 Tariff Filing, supra n. 2, at 96.  \n92 16 U.S.C. § 824(a); FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 277 (2016) (elaborating on the extent of \nFERC’s jurisdiction over wholesale rates)."},{"page":28,"startToken":9930,"endToken":10239,"text":"28 \nan earlier iteration of the Backstop Auction and has since been removed. Without taking steps to \naccount for the speculative nature of large load growth forecasts over the next 15 years, PJM’s \nproposed tariff revisions are unjust and unreasonable because there is a strong possibility that \nwholesale non-large load customers may have to pay for capacity costs from which they do not \nbenefit.93  \nC. FERC should require PJM to adjust the Backstop Auction design to avoid \noverpaying for capacity.  \n \nFERC should instruct PJM that it cannot demonstrate its proposed market design is just \nand reasonable unless PJM adopts measures to mitigate the risk that the Backstop Auction will \nimpose excessive burden on consumers. To do this, FERC should require PJM to eliminate the \nrequirement that demand response resources must have a 15-year agreement in place to \nparticipate in the Backstop Auction.94 Demand response resources are some of the least \nexpensive capacity resources available and imposing onerous restrictions on their participation \nwill artificially increase costs.95 PJM allows other resources to place bids for capacity service \nbeginning in 2032, so requiring demand response suppliers to commit starting in 2028/2029 DY \nis unduly discriminatory.96  \nIV. \nConclusion \n \n \nFERC should reject PJM’s proposed tariff revisions because the Backstop Auction is not \njust and reasonable. In the alternative, if FERC is inclined to permit PJM to implement some \nversion of the Backstop Auction, FERC should require PJM to refile its proposed tariff with \n \n93 See Old Dominion, 898 F.3d at 1255 (establishing the cost causation principle). \n94 Tariff Filing, supra n. 2, 54. \n95 See generally ACEE, FASTER AND CHEAPER: DEMAND RESPONSE SOLUTIONS FOR RAPID LOAD GROWTH (Feb. \n2026), (Feb. 2026), https://perma.cc/4SQM-CU37 (report finding that demand response is one of the lowest cost \nresources to serve electricity demand). \n96 16 U.S.C. § 824d(b)."},{"page":29,"startToken":10239,"endToken":10326,"text":"29 \nadjustments that will mitigate the substantial risk that the rates resulting from the Backstop \nAuction will be unjust and unreasonable.  \n \nRespectfully submitted, \n/s/ Jennifer Danis \nJennifer Danis \nFederal Energy Policy Director \nInstitute for Policy Integrity \n139 MacDougal Street \nNew York, NY 10012 \njennifer.danis@nyu.edu \n \n/s/ Christoph Graf \nChristoph Graf \nSenior Economist \nInstitute for Policy Integrity \n139 MacDougal Street \nNew York, NY 10012 \n \n/s/ Natalie Friedberg \nNatalie Friedberg \nLegal Fellow \nInstitute for Policy Integrity \n139 MacDougal Street \nNew York, NY 10012 \n \n \nDated: August 21, 2026"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":922,"startToken":0,"endToken":408},{"p":2,"at":922,"title":"I. BACKGROUND","method":"printed heading","endPage":6,"endAt":3,"startToken":408,"endToken":1947},{"p":6,"at":3,"title":"II. FERC should reject the proposed tariff revisions because PJM has failed to","method":"printed heading","endPage":6,"endAt":1070,"startToken":1947,"endToken":2112},{"p":6,"at":1070,"title":"A. PJM must prove that its proposed tariff revisions are just and reasonable","method":"printed heading","endPage":8,"endAt":3,"startToken":2112,"endToken":2705},{"p":8,"at":3,"title":"B. FERC should reject the proposed tariff because PJM has not adequately","method":"printed heading","endPage":10,"endAt":1122,"startToken":2705,"endToken":3597},{"p":10,"at":1122,"title":"C. The Backstop Auction will not isolate the Legacy Capacity Market from the","method":"printed heading","endPage":14,"endAt":4,"startToken":3597,"endToken":5034},{"p":14,"at":4,"title":"D. FERC should reject the tariff revisions because PJM can address its resource","method":"printed heading","endPage":23,"endAt":4,"startToken":5034,"endToken":8264},{"p":23,"at":4,"title":"III. If FERC permits PJM to implement the Backstop Auction, FERC should require","method":"printed heading","endPage":23,"endAt":727,"startToken":8264,"endToken":8376},{"p":23,"at":727,"title":"A. FERC should require PJM to adjust the Backstop Auction design to mitigate","method":"printed heading","endPage":26,"endAt":1153,"startToken":8376,"endToken":9505},{"p":26,"at":1153,"title":"B. FERC should require PJM to adjust Backstop Auction design to mitigate the","method":"printed heading","endPage":28,"endAt":404,"startToken":9505,"endToken":9995},{"p":28,"at":404,"title":"C. FERC should require PJM to adjust the Backstop Auction design to avoid","method":"printed heading","endPage":28,"endAt":1277,"startToken":9995,"endToken":10127},{"p":28,"at":1277,"title":"IV. Conclusion","method":"printed heading","endPage":29,"endAt":624,"startToken":10127,"endToken":10326}]}