{"document":{"slug":"rec-20260821-5158","title":"Post-Conference Comments of Harvard Electricity Law Initiative in response to Questions 12 and 13 re PJM Governance and Stakeholder Reforms","issued":"2026-08-21","accession":"20260821-5158","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"Harvard Electricity Law Initiative","kind":"comments","file":"sources/filings/text/20260821-5158_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5158","tier":"record","sha256":"b9ac884a2be9c962d8b2ae6da76eb5f882416e84b5199843c829b6328bec4f0d","pages":31,"tokens":10411,"emptyPages":[],"textThemes":[]},"pages":[{"page":1,"startToken":0,"endToken":241,"text":"1 \n \nUNITED STATES OF AMERICA \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \nPJM Governance and Stakeholder Reforms \n \n) \n)   Docket No. AD26-7 \n) \n) \n) \n \nHarvard Electricity Law Initiative Response to \nQuestions 12 and 13 in the Notice Requesting  \nPost-Conference Comments1 \nQuestions 12 and 13 in the Appendix to the Notice Requesting Post-\nConference Comments ask whether PJM should have filing rights over energy and \nancillary services markets and regional planning. These issues are currently in the \nPJM Operating Agreement (OA), and any section 205 filing amending the energy \nmarket rules or planning protocols must be approved by the Members Committee. \nMoving either Schedule 1 (energy market) or Schedule 6 (regional planning) from \nthe OA to the Tariff would allow the PJM Board to file under section 205 without \nthe Members Committee’s approval.  This comment anticipatorily rebuts arguments \nthat transmission owners hold any control, beyond their share of the Members-\nCommittee vote, over filing rights for matters housed in the OA. \nTwo years ago, both the transmission owners and PJM asserted that \ntransmission-owner consent, expressed through amendments to the Consolidated \nTransmission Owners’ Agreement (CTOA) filed by the transmission owners under \nsection 205, was necessary to move Schedule 6 of the OA to the Tariff. The \nCommission denied PJM’s proposal to relocate Schedule 6 only because PJM \n \n1 The Harvard Electricity Law Initiative is an independent organization based at Harvard Law School’s \nEnvironmental & Energy Law Program. These comments do not represent the views of Harvard University or \nHarvard Law School."},{"page":2,"startToken":241,"endToken":636,"text":"2 \n \npackaged its filings with the transmission owners’ filing to amend the CTOA.2 \nHaving concluded that the CTOA amendments went “beyond changes to enable this \ntransfer” and were unjust and unreasonable and unduly discriminatory for reasons \nwholly unrelated to the proposed transfer, the Commission rejected the entire \npackage of filings.3 \nThe Commission then took no position on whether transmission-owner \nconsent was necessary to move Schedule 6 from the OA to the Tariff.4 In this \ncomment, we argue that transmission-owner consent is not necessary to move \nschedules from the OA to the Tariff. Should the Commission order or approve the \ntransfer of regional planning provisions from the OA to the Tariff, four non-\nsubstantive changes to the CTOA suffice to maintain the document’s accuracy. \nMoving OA Schedule 1 would not require any changes to the CTOA.  \nThe Members Committee Has Exclusive Authority to Amend the \nOperating Agreement with a Section 205 Filing \nThe relevant facts are uncontested. In 1997, the-then PJM utilities filed \nseveral documents to create an independent PJM Interconnection LLC.5 Section 8.8 \nof the utility-filed Operating Agreement granted the PJM Members Committee \nauthority to “amend any portion of this Agreement, including the Schedules hereto  \n \n2 Duquesne Light Co., PJM Interconnection, 189 FERC ¶ 61,181 at P 22 (2024) (“having rejected the CTOA \nAmendments on the merits, we dismiss the PJM Complaint”) [CTOA Rejection Order]; Duquesne Light Co., \nPJM Interconnection, 192 FERC ¶ 61,051 at P 21 (2025) [CTOA Rejection Rehearing Order]. \n3 CTOA Rejection Rehearing Order at P 22. \n4 CTOA Rejection Order at P 22, n. 47 (stating that the Commission took “no position as to whether PJM has \nthe legal authority to effectuate the changes proposed in the PJM Complaint or PJM Transfer Filing in the \nabsence of the CTOA Amendments or vice versa”); CTOA Rejection Rehearing Order at P 24. \n5 Atlantic City Electric, et al., 81 FERC ¶ 61,257, at p. 62,235 (1997) (“On June 2, 1997, Supporting Companies \nsubmitted a comprehensive filing to restructure the PJM Pool.”); CTOA Rejection Order at PP 3‒4; CTOA \nRejection Rehearing Order at P 6; see also PJM Initial Filing, Docket No. ER24-2338, at pp. 7–9  (Jun. 21, 2024); \nPJM Initial Filing, Docket No. EL24-119, at pp. 7–9  (Jun. 21, 2024); Utilities’ Initial Filing, Docket No. ER24-\n2336, at pp. 17–19  (Jun. 21, 2024)."},{"page":3,"startToken":636,"endToken":1044,"text":"3 \n \n. . . and file any such amendments . . . with FERC.”6  Since Commission approval of \nthe Operating Agreement in 1997, the PJM Members Committee has enjoyed \nexclusive authority over section 205 filings that amend the OA.7 PJM, the \ntransmission owners, and the Members Committee have acted accordingly for \nnearly 30 years.8 \nThe transmission owners cannot overwrite the Members Committee’s \nprivileges enshrined in the OA by amending the CTOA, and no CTOA amendments \nare needed to express transmission-owner consent to moving OA schedules to the \nTariff.9 Having “chose[n] to voluntarily give up, by contract, some of their ratefiling \nfreedom under section 205” when they filed the OA and the Commission approved it \nin 1997,10 the utilities now have no authority to approve or veto the transfer of the \nplanning protocol or other OA schedules to the PJM Tariff.  \nOnly trivial conforming amendments to the CTOA might be needed to ensure \nconsistency across PJM documents should the Commission order the transfer of any \nschedules from the OA to the Tariff. Acting under section 206, the Commission \ncould order the transmission owners to file any needed changes. The Mobile-Sierra \ndoctrine does not shield the CTOA from such trivial adjustments.11 \nOur analysis of the CTOA finds that that the document can already \naccommodate a Commission order transferring OA Schedules 1 to the Tariff. If the \n \n6 PJM Operating Agreement, sec. 8.8(ii) (emphasis added). The Appendix contains the OA filed in 1997, which \nincludes the same language.  \n7 CTOA Rejection Order at P 5, n.13; CTOA Rejection Rehearing Order at PP 8, 10. \n8 See, e.g., CTOA Rejection Order at P 8 (“Before the PJM Filings were submitted, PJM attempted to amend the \nOA by a vote of the Members Committee, which would have allowed PJM to file the OA revisions under FPA \nsection 205.”). \n9 See Harvard Electricity Law Initiative Protest, Docket No. ER24-2336, at pp. 8‒12 (Jul. 22, 2024); Harvard \nElectricity Law Initiative Response to Utilities’ Proposed Answer, Docket No. ER24-2336 (Sep. 4, 2024); \nHarvard Electricity Law Initiative Reply to Deficiency Letter Responses, Docket No. ER24-2336 (Oct. 30, 2024). \n10 Atlantic City Electric, et al. v. FERC, 295 F.3d 1, 10 (D.C. Cir. 2002). \n11 CTOA Rejection Rehearing Order at P 80 (finding that the relevant CTOA provisions are not entitled to \nMobile-Sierra protections as a matter of law and do not warrant those protections as a matter of discretion)."},{"page":4,"startToken":1044,"endToken":1341,"text":"4 \n \nCommission orders the transfer of the regional planning provisions, we believe that, \nat most, four non-substantive changes to the CTOA would ensure consistency across \nPJM’s governing documents. \nCTOA Changes Needed to Ensure Consistency Across PJM Documents if the \nCommission Orders Schedule 6 of the OA Moved to the Tariff \nCTOA Section \nDescription of Conforming Change \nDefinitions \nIn the definition of Regional Transmission Expansion Planning Protocol, \nReplace “Schedule 6 of the Operating Agreement” with “PJM Tariff, \nSchedule [ ]” \n4.1.4 \nFollowing “Operating Agreement,” add “and the PJM Tariff” \n6.3.3 \nDelete “Operating Agreement and the” \n6.3.4 \nDelete “or Operating Agreement” \nThe OA Does Not Require Transmission Owner Consent to Move \nSchedules from the Operating Agreement to the Tariff \nWhen it interprets an RTO governing document to determine which entity \nhas authority over a particular issue, the Commisison follows a two-step approach \nrooted in caselaw. Applying this framework, the OA cannot be read to empower the \ntransmission owners with special authority over how PJM transfers its filing rights. \nThe Commission summarized its approach to interpreting RTO governing \ndocuments in a 2020 proceeding about whether the CTOA delegated to PJM \nconsideration of end-of-life transmission projects.12 The Commission explained that \nto determine whether the PJM transmission owners delegated authority over a \nparticular issue, it first considers whether the relevant contract “unambiguously \naddresses the matter at issue.”13  \nThe Operating Agreement is unambiguous about the Members Committee’s \nexclusive role in authorizing section 205 filings that amend the OA. Section 8.8 \nspecifies that to amend the OA the Members Committee must act in accordance \n \n12 PJM Interconnection, 176 FERC ¶ 61,053 at P 13 (2021). \n13 Id. at P 14 (quoting Transmission Agency of N. Cal. v. FERC, 628 F.3d 538, 547 (D.C. Cir. 2010))."},{"page":5,"startToken":1341,"endToken":1729,"text":"5 \n \nwith section 18.6.14 Both the original OA aproved by the Commission in 1997 and \ncurrent section 18.6 stipulate that the OA may be amended “only upon”  \ni) submission of the amendment to the Board for its review and comments;  \nii) approval by the Members Committee pursuant to its voting rules in section 8.4; \nand iii) Commission approval.15 None of these conditions suggest that the utilities \nretain any authority over amendments to the OA or that changes involving filing \nrights are handled differently from other amendments. \nThe Commission’s contract-interpretation framework provides that to \ndetermine whether there is amiguity in an RTO governing document, it may \nconsider the “entire agreement.”16 The specifics of this inquiry will depend on which \nprovisions the Commission orders moved out of the OA. We briefly summarize \nrelevant evidence about Schedule 6.  \nOA provisions about regional planning specify roles for the PJM Board, PJM \nStaff, and the Members Committee. For instance, section 10.4 empowers PJM staff \nto plan regional transmission expansion.17 Section 7.7 empowers the PJM Board to \n“[a]pprove The Regional Transmission Expansion Plan in accordance with the \nprovisions of the Regional Transmission Expansion Planning Protocol set forth in \nOperating Agreement, Schedule 6.” Schedule 6 opens with: “[t]his Regional \nTransmission Expansion Planning Protocol shall govern the process by which \nthe Members shall rely upon [PJM Staff] to prepare a plan for the enhancement and \n \n14 There is a slight and non-substantive difference between the original 8.8(ii) and the current 8.8(ii). \nOriginal 8.8(ii): “In accordance with the provisions of Section 18.6 of this Agreement, amend any portion . . .”  \nCurrent 8.8(ii): “In accordance with the provisions of Operating Agreement, section 18.6, amend any portion . . .” \n15 CTOA Rejection Order at P 5, n.13 (emphasis added); see also Appendix. \n16 PJM Interconnection, 176 FERC ¶ 61,053 at P 14 (quoting Xcel Energy Servs. Inc. v. Am. Transmission Co., \nLLC, 140 FERC ¶ 61,058, at P 60 (2012)). \n17 See also CTOA Rejection Order at P 4 (noting that in 1997 the transmission owners transferred “to the Office \nof the Interconnection and the PJM Board, in accordance with the [OA], the responsibility for preparing a \n[RTEP] in accordance with the [RTEP] Protocol”); CTOA Rejection Rehearing Order at P 4."},{"page":6,"startToken":1729,"endToken":2059,"text":"6 \n \nexpansion of the Transmission Facilities.” None of these provisions can be read to \nhide a transmission-owner privilege to police PJM’s filing rights.18 \nFinally, the Commission can “look to extrinsic evidence,”19 including \n“statements, course of conduct, and contemporaneous correspondence, aimed at \ndiscerning the intent of the parties.”20 This inquiry would also be fact specific. With \nregard to Schedule 6, the utilities explained in the 2024 proceeding that their \nsurrender of control over the regional planning protocol was explicit, intentional, \nand complete. They summarize that in 1997 they wanted to retain control over the \ntariff while also attempting to comply with the Commission’s directive to give the \nnew PJM ISO “primary responsibility for transmission planning.”21 To meet these \ngoals, the utilities placed the planning rules in the OA because “the transmission \nowners did not control” that document.22 In other words, ceding all control over \nregional planning was the primary reason they put the planning rules in the OA \nand empowered the Members Committee with exclusive authority to authorize \namendments with section 205 filings.  \n \n18 The OA as filed by the utilities in June 1997 included section 18.1 that specified retained “transmission owner \nrights.” See Appendix. The Commission directed PJM to remove those provisions, “given that the same \nprovisions are included in the Owners Agreement.” Atlantic City Electric, et al., 81 FERC ¶ 61,257, at p. 62,274 \n(1997). Nonetheless, none of those retained rights, which the Commission did not accept and were not part of \nthe OA, suggest that the Members Committee’s authority over the regional planning protocol is non-exclusive.  \n19 PJM Interconnection, 176 FERC ¶ 61,053 at P 15 (citing Missouri River Energy Servs. v. FERC, 918 F.3d 954, \n958 (D.C. Cir. 2019)). \n20 Id. (quoting Farmland Industries, Inc. v. Grain Bd. of Iraq, 904 F.2d 732, 736 (D.C. Cir. 1990)).  \n21 Utilities’ Initial Filing, Docket No. ER24-2336, at pp. 17–18  (Jun. 21, 2024). \n22 Id. at p. 18."},{"page":7,"startToken":2059,"endToken":2335,"text":"7 \n \nThe Commission Should Reject Arguments that the CTOA \nClandestinely Requires Transmission Owner Consent to Transfer \nSchedules from the OA to the Tariff \nPJM and the transmission owners floated several theories about the \ntransmission owners’ apparent authority over the Operating Agreement and \nregional planning. We briefly recount and rebut the arguments they filed in 2024. \nFiling Rights Do Not “Ultimately Reside” with the Transmission Owners \nIn 2024, PJM claimed that “the rights to plan the PJM Transmission Owners’ \nfacilities, and any accompanying filing rights, ultimately reside with the PJM \nTransmission Owners and require PJM to obtain the Transmission Owners’ \nagreement to transfer.”23 As discussed, the filing rights currently reside with the \nMembers Committee, and the utilities did not retain any filing rights over the \nregional planning protocol.  \nFiling rights “ultimately reside” with the utilities in a limited sense that has \nno relevance here. Commission approval of a utility’s withdrawal from PJM would \nterminate various contractual commitments. Assuming the withdrawing utility is \nnot joining a different RTO, it would be out of compliance with the Commission’s \nOpen Access transmission standards. The utility would likely have the right to file a \nnew transmission tariff that meets Commission requirements, including about \nregional planning. In that sense, filing rights over matters that had been handled \nby the RTO would return to the transmission owner. That hypothetical would not be \nat issue if the Commission orders PJM to move schedules from the OA to the Tariff. \nSo long as a utility remains a CTOA signatory, filing rights over regional planning \ndo not “reside” with the utility. \n \n23 PJM Initial Filing, Docket No. ER24-2338, at pp. 7–9  (Jun. 21, 2024)."},{"page":8,"startToken":2335,"endToken":2671,"text":"8 \n \nThe “Scope and Configuration” of Planning Rights Do Not Encompass Filing \nRights over the Planning Protocol \nIn 2024, PJM claimed that the CTOA “specifies the scope and configuration” \nof the right to plan regional transmission expansion.24 PJM pointed to CTOA \nprovisions that delegate to PJM the responsibility to plan regional transmission \nexpansion. PJM then presumed that control over regional-planning filing rights are \nhidden in these CTOA provisions. PJM’s conclusion cannot be squared with the \nCommission’s approach to contract interpretation. \nAs summarized above, to determine whether the PJM transmission owners \ndelegated authority over a particular issue, the Commission first considers whether \nthe relevant contract “unambiguously addresses the matter at issue.”25 PJM did not \nclaim that the CTOA unambiguously allows the transmission owners to retain \nauthority over regional planning filing rights. To the contrary, PJM claimed that \nthe transmission owners’ rights are implied by the regional planning’s unambiguous \ndelegation of planning rights.  \nReading the “entire agreement” does not support PJM’s hidden-rights \ntheory.26 In CTOA Article 7, the parties used specific and unambiguous language to \ntransfer and reserve filing rights over various issues.27 It is implausible the parties \nwould have been so specific about transferring filing rights in Article 7 while also \nimplying that utilities retain a veto over filing rights transfers in the “scope and \nconfiguration” of the regional planning delegation.  \n \n24 PJM’s Response to the Deficiency Letter, Docket No. ER24-2338-001, at pp. 6, 8 (Oct. 9, 2024) \n25 PJM Interconnection, 176 FERC ¶ 61,053 at P 14 (2021). \n26 Id.  \n27 See, e.g., CTOA 7.5.1 – Filing of Changes in Terms and Conditions Under Section 205. (i) PJM shall have the \nexclusive and unilateral rights to file pursuant to Section 205 of the Federal Power Act and the FERC’s rules \nand regulations thereunder to make changes in or relating to the terms and conditions of the PJM Tariff \n(including but not limited to provisions relating to creditworthiness, billing, and defaults) as well as all charges \nfor recovery of PJM costs. . . ."},{"page":9,"startToken":2671,"endToken":2970,"text":"9 \nThe CTOA Does Not “Define the Location” of the Planning Protocol \nPJM claimed that the CTOA’s definition of the planning protocol demands \ntransmission-owner consent to any transfer of Schedule 6 to the Tariff.28 The \nCommission should not infer any substantive meaning from this cross-reference. \nArticle I of the CTOA defines the document’s key terms, including the \n“Regional Transmission Expansion Planning Protocol,” which “shall mean Schedule \n6 of the Operating Agreement, or any successor thereto.” That definition, according \nto PJM: 1) conditions the initial filing-rights transfer over regional planning from \nthe transmission owners in 1997 on the precise location of the planning protocol; \nand 2) provides the transmission owners with a right to veto any relocation of the \nplanning provision. \nThat’s a lot of weight for this definition to bear. PJM attached far more \nsignificance to that single cross-reference in the CTOA than it did to dozens of cross-\nreferences in its Tariff. To transfer of Schedule 6 into the Tariff, PJM proposed \nrevisions to approximately fifty tariff definitions or sections that would replace \nreferences to Schedule 6 of the Operating Agreement with references to the new \nlocation of the planning protocol in the Tariff.29 In its section 205 filing to \nimplement those changes, PJM “emphasize[d]” that these modifications were not \n“substantive.”30 PJM does not explain why an identical reference to Operating \nAgreement Schedule 6 in a single CTOA definition creates a legal right, while \ndozens of references in the Tariff are trivial.  \n28 PJM’s Response to the Deficiency Letter, Docket No. ER24-2338-001, at pp. 6‒7 (Oct. 9, 2024). \n29 See PJM Initial Filing, Docket No. ER24-2338 (Jun. 21, 2024). \n30 Id. at p. 29; id at p. 31, n. 67. See Attachment A to the filing for the full list of proposed changes."},{"page":10,"startToken":2970,"endToken":3308,"text":"10 \n \nD.C. Circuit Decisions about Filing Rights Do Not Prevent the Commission \nfrom Ordering the Changes Proposed in Questions 12 and 13 \nIn 2024, the utilities warned that if the Commission transfers authority over \nthe planning protocol to the PJM Board without utility consent it would be \n“exceed[ing] its jurisdiction under FPA section 206.”31 The legal problem, according \nto the utilities, is that transferring the Members Committee’s filing authority \nwithout utility consent would “require the Transmission Owners to cede their filing \nrights over planning in a manner other than what they voluntarily agreed to.”32 No \ncourt decision or Commission order suggests that utilities may so restrain the \nCommission’s section 206 authority. \nUnder the Atlantic City cases, the Commission “has no jurisdiction to . . . \nrequir[e] utilities to surrender their rights under § 205 of the FPA to make filings to \ninitiate rate changes.”33  The D.C. Circuit’s limited holding does not award the \nutilities control over filing rights that they voluntarily gave up by contract. In 2003, \nfollowing the second Atlantic City decision, the Commission understood that it could \nact under section 206 to modify a settlement agreement between PJM and the \nutilities that allocates filing rights, and that it could even grant a party additional \nfiling rights without transmission-owner consent.34 A section 206 order transferring \na schedule from the OA to the Tariff is well within the Commission’s authority. \n \n31 Motion for Leave to Answer and Answer of the PJM Transmission Owners, Docket No. ER24-2336, at p. 11 \n(Aug. 15, 2024). \n32 Id. \n33 Atlantic City Elec. Co. v. FERC, 329 F.3d 856, 859 (D.C. Cir. 2003); Maine Pub. Utils’ Comm’n v. FERC, 454 \nF.3d 278, 284 (D.C. Cir. 2006) (“the issue in Atlantic City was limited to the question of whether FERC had \njurisdiction . . . to oblige public utilities to cede their rights to make future filings under Section 205.”). \n34 PJM Interconnection, et al., 105 FERC ¶ 61,294 at P 33 (2003). Id. at P 33, n. 33."},{"page":11,"startToken":3308,"endToken":3373,"text":"11 \n \nCONCLUSION \nControl over the OA’s schedules is a matter between the Members \nCommittee, the PJM Board, and the Commission. The utilities’ endorsement via \nCTOA amendments of any transfer from the OA to the Tariff is legally irrelevant.  \n \n/s/ Ari Peskoe \n \n \nAri Peskoe \nHarvard Electricity Law Initiative \n6 Everett St., Suite 4133 \nCambridge, MA 02138 \n617.495.4425 \napeskoe@law.harvard.edu \nAugust 21, 2026"},{"page":12,"startToken":3373,"endToken":3407,"text":"--\n-\n-\n-\n97 JUN -2 AH 9: 00 \nFILING OF THE \nPJM SUPPORTING COMPANIES \nJUNE 2, 1997 \n· EC97-38 -000\nVOLUME I OF II \nORIGINAL \nHarvard Electricity Law Initiative Protest \nAppendix B - PJM's 1997 Operating Agreement\nB-1"},{"page":13,"startToken":3407,"endToken":3721,"text":"-\nBRUSSEL$. 8ELGIUM \nWARSAW. POLAND \nI-IONG KONG \nNEW YORK. NEW YORK \nATLANTA. GEORGIA \nRICHMOND. VIRGINIA \nHUNTON & WILLIAMS \n1000 K STREET, N.W. \nWASHINGTON, D.C. 20000-1100 \nTELEPHONE 120219!5!5-1!500 \nFACSIMILE 1202) 77B-2201 \nEC97-38 -00011 \nARNOLD H. QUINT \nBY HAND \nMs. Lois D. Cashell \nSecretary \nFederal Energy Regulatory Commission \n888 First Street, N.E., Room IA \nWashington, D.C. 20426 \nJune 2, 1997 \nAtlantic City Electric Company. et al. \nDear Ms. Cashell: \nORIGINAL \nMCLEAN. VIRGINIA \nNORF'OLK. VIRGINIA \nRALEIGH, NORTH CAROLINA \nCHARLOTTE, NORTH CAROLINA \nKNOXVILLE, T ENNESSEE \nFILE No.: 50943.000002 \nDIRECT DIAL: (202) 955-I 542 \nC \nr,' \nC \nL \n'­\nc: \nz \nI \nN \" \n::c \nI';-? \n.::­er \n--< •• , \ni •• •:: \nOn December 31, 1996, in Docket Nos. OA97-261-000 and ER97-1082-000, the \nmember companies of the Pennsylvania-New Jersey-Maryland Interconnection (PJM Pool) \nmade a compliance filing to implement the requirements of Order No. 888 for \"tight\" power \npools. In that filing, the PJM member companies committed to make a subsequent filing, \nfollowing further negotiations with stakeholders, to put in place an Independent System \nOperator (ISO) for the PJM Pool. The instant filing is made by the PJM Supporting \nCompanies!! pursuant to Sections 203 and 205 of the Federal Power Act to fulfill that prior \ncommitment. \nIn developing this filing, the Supporting Companies worked with a large group of \ninterested stakeholders in an effort to obtain as much consensus as possible. While complete \nconsensus could not be achieved, two major independent power producers, U.S. Generating \n11 Atlantic City Electric Company, Baltimore Gas and Electric Company, Delmarva \nPower & Light Company, Jersey Central Power & Light Company, Metropolitan Edison \nCompany, Pennsylvania Electric Company (the immediately preceding three utilities being \nsubsidiaries of GPU, Inc.), Pennsylvania Power & Light Company, Potomac Electric Power \nCompany and Public Service Electric and Gas Company. \n\\;>\\\u0004\u00051\nl'ERC-DOCKETED \nJUN 2 1997 \nNOTE: The \nPJM Utilities \nfiled the OA\nHarvard Electricity Law Initiative Protest \nAppendix B - PJM's 1997 Operating Agreement\nB-2"},{"page":14,"startToken":3721,"endToken":4092,"text":"HUNTON & WILLIAMS \nMs. Lois D. Cashell \nJune 2, 1997 \nPage 2 \nCompany and Cogen Technologies N.J. Venture, and two major power marketers, \nPanEnergy Trading and Market Services, L.L.C. and Citizens Lehman Power, L.P. (now \nCitizens Power L.L.C.), have authorized the Supporting Companies to advise the \nCommission that they are generally supportive of this proposal, subject to their review of the \nfinal package as filed. Each party has reservations about certain provisions and may offer \ncomments on or propose alternative treatment of these provisions in separate pleadings. For \nexample, Citizens continues to have questions about the use of locational marginal pricing. \nIn addition, Allegheny Electric Cooperative, Inc. has indicated to the Supporting Companies \nthat this filing is, in its opinion, preferable to the principal alternatives presented during the \nstakeholder process and will advise the Commission of its remaining reservations in a \nseparate pleading. \nThe Supporting Companies are submitting the following documents pursuant to \nSection 205 of the Federal Power Act and 18 C.F.R. § 35.13 (1997): \n1.\nAmended and Restated Operating Agreement of PJM Interconnection, L. L. C.,\ndated as of June 2, 1997 (Operating Agreement);\n2.\nTransmission Owners Agreement dated as of June 2, 1997 (Transmission\nOwners Agreement);\n3.\nPJM Open Access Transmission Tariff (PJM Tariff); and\n4.\nReliability Assurance Agreement Among Load Serving Entities in the PJM\nControl Area dated as of June 2, 1997 (Reliability Assurance Agreement).\nAttachment A hereto is a complete list of the documents provided. Nothing in this filing is \nintended to modify any existing contracts between the Supporting Companies and any other \nparties. \nI. Objectives of the Instant Filing\nThe December 31 compliance filing, which was accepted by the Commission by \nOrder dated February 28, 1997,l! included (i) changes in the PJM Interconnection \nAgreement to facilitate the participation of all market participants on a non-discriminatory \nbasis, and (ii) the PJM Open Access Transmission Tariff (PJM Tariff), under which all of \nthe public utilities in the PJM control area offered access to their transmission facilities under \n<' Mid-Continent Area Power Pool, 78 FERC 161,203 (1997) (February 28 Order). \nNOTE: The \nPJM Utilities \nfiled the OA\nHarvard Electricity Law Initiative Protest \nAppendix B - PJM's 1997 Operating Agreement\nB-3"},{"page":15,"startToken":4092,"endToken":4552,"text":"Ms. Lois D. Cashell \nJune 2, 1997 \nPage 3 \nHUNTON & WILLIAMS \nnon-pancaked rates and on terms that tracked the Commission's pro forma tariff. On \nApril 1, 1997, a filing was made to further modify the PJM Interconnection Agreement, \nconverting it into an Operating Agreement for a limited liability company (PJM \nInterconnection, L.L.C.) in order to permit an independent board of directors to exercise \noversight over the day-to-day operations of the PJM Pool. \nThis filing builds on the December 31 and April 1 filings, making only those \nadditional changes necessary to accomplish the following objectives: \n1.\nEstablish an ISO That Satisfies the Commission's Principles. Although the\nDecember 31 and April 1 filings provided for expanded participation in the PJM Pool and \nenhanced the independence of the PJM Pool's operator, formerly known as the PJM \nInterconnection Association Office, those filings did not purport to establish an ISO. This \nfiling modifies the governance provisions of the Operating Agreement to ensure that the \nOffice of the Interconnection, subject to the oversight of an independent PJM Board of \nManagers (PJM Board), will independently administer the day-to-day operations of the PJM \nPool, satisfying the Commission's criteria for ISOs set forth in Order No. 888, as clarified in \nAtlantic City Electric Co. et al., 77 FERC 161,148 (1996) (November 13 Order).l! The \nrevised governance provisions are a direct result of discussions among the Supporting \nCompanies and other stakeholders. The Operating Agreement establishes an ISO with \nresponsibility for system operations, administration of the PJM Tariff, and regional \ntransmission planning. No stakeholder or industry segment has the ability to control the \nISO' s functions or to prevent the ISO from acting. Moreover, the ISO will have a governing \nboard (the PJM Board) that is independent of any industry segment, and will have complete \nresponsibility for supervision and oversight of the day-to-day operations of the PJM control \narea. In addition, for those few matters that come before the members for action, the voting \nrights continue to be structured so that no one industry segment can either force or block \naction. These provisions, together with the continuing requirements of the Federal Power \nAct related to any change in the governing agreements and tariff, provide a system of checks \nand balances that will assure non-discriminatory, open access transmission service throughout \nthe PJM control area. \nThe Operating Agreement also has been modified to modernize outdated provisions of \nthe original PJM Agreement and to clarify the responsibilities of the ISO and the parties \nunder the Operating Agreement. \n,, Attachment B to this Transmittal Letter demonstrates how the Supporting Companies' \nproposal complies with each ISO requirement and addresses each of the concerns that was \nidentified in the November 13 Order. \nHarvard Electricity Law Initiative Protest \nAppendix B - PJM's 1997 Operating Agreement\nB-4"},{"page":16,"startToken":4552,"endToken":4579,"text":"AMENDED AND RESTATED \nOPERATING AGREEMENT \nOF \nPJM INTERCONNECTION, L.L.C. \nDated June 2, 1997 \nHarvard Electricity Law Initiative Protest \nAppendix B - PJM's 1997 Operating Agreement\nB-5"},{"page":17,"startToken":4579,"endToken":4848,"text":"1. 39 Related Parties. . ............................................................................... 7 \n1 .40 Reliability Assurance Agreement ........................................................... 7 \n1.41 Sector Votes . ................................................................................... 7 \n1.42 State .............................................................................................. 7 \n1.43 System . .......................................................................................... 7 \n1.44 Transmission Facilities . ...................................................................... 7 \n1.45 Transmission Owner . ......................................................................... 7 \n1.46 Transmission Owners Agreement ........................................................... 8 \n1.47 User Group . .................................................................................... 8 \n1.48 Voting Member ................................................................................ 8 \n1.49 Weighted Interest. ............................................................................. 8 \n-\n2. FORMATION, NAME; PLACE OF BUSINESS ................................................... 8 \n2.1 Formation of LLC; Certificate of Formation ............................................... 8 \n2.2 Name of LLC . ................................................................................... 9 \n2.3 Place of Business ................................................................................ 9 \n2.4 Registered Office and Registered Agent. ................................................... 9 \n3. PURPOSES AND POWERS OF LLC ................................................................. 9 \n3 . 1 Purposes. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 \n3.2 Powers . ........................................................................................... 9 \n4. EFFECTIVE DATE AND TERMINATION ........................................................ 10 \n4 .1 Effective Date and Termination . ............................................................ 10 \n4.2 Governing Law ................................................................................. 10 \n5. WORKING CAPITAL AND CAPITAL CONTRIBUTIONS .................................... 10 \n5.1 Funding of Working Capital and Capital Contributions ................................. 10 \n5.2 Contributions to Association . ................................................................ 11 \n6. TAX STATUS AND DISTRIBUTIONS ............................................................. 11 \n6.1 Tax Status . ...................................................................................... 11 \n6.2 Return of Capital Contributions . ............................................................ 11 \n6. 3 Liquidating Distribution. . .................................................................... 11 \n7. PJM BOARD .............................................................................................. 12 \n7 .1 Composition ..................................................................................... 12 \n7 .2 Qualifications ................................................................................... 12 \n7 .3 Term of Office .................................................................................. 12 \n7 .4 Quorum . ......................................................................................... 13 \n7 .5 Operating and Capital Budgets ............................................................... 13 \n7.5.1 Finance Committee ................................................................. 13 \n7.5.2 Adoption of Budgets . .............................................................. 13 \n7.6 By-laws . ......................................................................................... 14 \n7.7 Duties and Responsibilities of the PJM Board . ........................................... 14 \n8. MEMBERS COMMITTEE ............................................................................. 16 \n-\n8.1 Sectors . .......................................................................................... 16 \n8. l. l Desi.gnati.on . ........................................................................ 16 \n8.1.2 Related Parties . ..................................................................... 16 \n8. 2 Representatives . ................................................................................ 16 \n8.2.1 Appointment ........................................................................ 16 \nii \nHarvard Electricity Law Initiative Protest \nAppendix B - PJM's 1997 Operating Agreement\nB-6"},{"page":18,"startToken":4848,"endToken":5123,"text":"8.2.2 Regulatory Authorities ............................................................. 16 \n8.2.3 Initial Representatives . ............................................................ 17 \n8.2.4 Change of or Substitution for a Representative . .............................. 17 \n8.3 Meetings . ........................................................................................ 17 \n8.3.1 Regular and Special Meetings .................................................... 17 \n8.3.2 Attendance ........................................................................... 17 \n8.3.3 Quorum ............................................................................... 18 \n8.4 Manner of Acting . ............................................................................. 18 \n8.5 Chair and Vice Chair of the Members Committee . ...................................... 18 \n8.5.1 Selection and Term ................................................................. 18 \n8.5.2 Duties ................................................................................. 19 \n8.6 Other Committees .............................................................................. 19 \n8.7 User Groups ..................................................................................... 19 \n8.8 Powers of the Members Committee ......................................................... 19 \n9. OFFICERS ................................................................................................. 20 \n9.1 Election and Term . ............................................................................ 20 \n9.2 President ......................................................................................... 20 \n9. 3 Secretary ......................................................................................... 20 \n9 .4 Treasurer. . ...................................................................................... 21 \n9.5 Renewal of Officers; Vacancies . ............................................................ 21 \n9.6 Compensation ................................................................................... 21 \n10. OFFICE OF THE INTERCONNECTION ......................................................... 21 \n10 .1 Establishment .................................................................................. 21 \n10.2 Processes and Organization ................................................................. 21 \n10.3 Confidential Information . ................................................................... 22 \n10.4 Duties and Responsibilities . ................................................................ 22 \n11. MEMBERS ............................................................................................... 24 \n11.1 Management Rights . ......................................................................... 24 \n11.2 Other Activities . .............................................................................. 24 \n11.3 Member Responsibilities . ................................................................... 24 \n11.3.1 General. ............................................................................. 24 \n11.3.2 Facilities Planning and Operation .............................................. 25 \n11.3 .3 Electric Distributors .............................................................. 26 \n11.3.4 Reports to the Office of the Interconnection . ................................ 27 \n11.4 Regional Transmission Expansion Planning Protocol. ................................. 27 \n11. 5 Member Right to Petition ................................................................... 27 \n11.6 Membership Requirements .................................................................. 28 \n12. TRANSFERS OF MEMBERSHIP INTEREST ................................................... 29 \n13. INTERCHANGE ........................................................................................ 29 \n13.1 Interchange Arrangements with Non-Members . ........................................ 29 \n13.2 Energy Market . ............................................................................... 29 \n14. METERING .............................................................................................. 1-ſ \n14.1 Installation, Maintenance and Reading of Meters ....................................... 29 \n14.2 Metering Procedures . ........................................................................ 29 \n14.3 Integrated Megawatt-Hours ................................................................. 30 \niii \nHarvard Electricity Law Initiative Protest \nAppendix B - PJM's 1997 Operating Agreement\nB-7"},{"page":19,"startToken":5123,"endToken":5405,"text":"14.4 Meter Locations ............................................................................... 30 \n15. ENFORCEMENT OF OBLIGATIONS ............................................................. 30 \n15 .1 Failure to Meet Obligations ................................................................. 30 \n15.1.1 Termination of Market Buyer Rights .......................................... 30 \n15.1.2 Termination of Market Seller Rights . ......................................... 30 \n15.1.3 Payment of Bills ................................................................... 30 \n15.2 Enforcement of Obligations ................................................................. 31 \n15.3 Obligations to a Member in Default ....................................................... 31 \n15.4 Obligations of a Member in Default. ...................................................... 32 \n15.5 No Implied Waiver ........................................................................... 32 \n16. LIABILITY AND INDEMNITY ..................................................................... 32 \n16.1 Members . ...................................................................................... 32 \n16.2 LLC Indemnified Parties . ................................................................... 32 \n16.3 Worker' Compensation Claims ............................................................. 34 \n16 .4 Limitation of Liability . ...................................................................... 34 \n16.5 Resolution of Disputes ....................................................................... 34 \n16.6 Gross Negligence or Willful Misconduct. ................................................ 34 \n16.7 Insurance . ...................................................................................... 34 \n17. MEMBER REPRESENTATIONS, WARRANTIES AND COVENANTS .................. 35 \n17 .1 Representations and Warranties ............................................................ 35 \n-\n17 .1. 1 Organization and Existence . .................................................... 35 \n17.1.2 Power and Authority . ............................................................ 35 \n17 .1.3 Authorization and Enforceability ............................................... 35 \n17.1.4 No Government Consents . ...................................................... 35 \n17 .1.5 No Conflict or Breach ............................................................ 35 \n17.1.6 No Proceedings .................................................................... 36 \n17.2 Municipal Electric Systems ................................................................. 36 \n17. 3 Survival. ........................................................................................ 36 \n18. MISCELLANEOUS PROVISIONS ................................................................. 36 \n18 .1 Transmission Owners Rights . .............................................................. 36 \n18.2 Fiscal and Taxable Year ..................................................................... 37 \n18.3 Reports . ........................................................................................ 37 \n18.4 Bank Accounts; Checks, Notes and Drafts ............................................... 37 \n18.5 Books and Records . .......................................................................... 37 \n18.6 Amendment . ................................................................................... 38 \n18. 7 Interpretation . ................................................................................. 39 \n18.8 Severability . ................................................................................... 39 \n18.9 Force Majeure ................................................................................. 39 \n18 .10 Further Assurances ......................................................................... 39 \n18.11 Seal. ........................................................................................... 39 \n18 .12 Counterparts. . .............................................................................. .40 \nJ 8. J3 Costs of Meetings ........................................................................... 41) \n18.14 Notice . ........................................................................................ 40 \n18.15 Headings ..................................................................................... .40 \n18.16 No Third-Party Beneficiaries . ........................................................... .40 \nIV \nHarvard Electricity Law Initiative Protest \nAppendix B - PJM's 1997 Operating Agreement\nB-8"},{"page":20,"startToken":5405,"endToken":5655,"text":"1.3 Related PJM Agreements . ..................................................................... I \n2. PURPOSES AND OBJECTIVES ....................................................................... I \n2.1 Common and Uniform Procedures ........................................................... 1 \n2.2 Interpretation ..................................................................................... 1 \n3. NEGOTIATION AND MEDIATION ................................................................. 2 \n3.1 When Required . ................................................................................. 2 \n3 . 2 Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2 \n3.2.1 Initiation ............................................................................... 2 \n3.2.2 Selection of Mediator. .............................................................. 2 \n3.2.3 Advisory Mediator. ................................................................. 2 \n3.2.4 Mediation Process . .................................................................. 3 \n3.2.5 Mediator's Assessment . ............................................................ 3 \n3.3 Costs ............................................................................................... 4 \n4. ARBITRATION ........................................................................................... 4 \n4.1 When Required . ................................................................................. 4 \n4.2 Binding Decision . ............................................................................... 4 \n4.3 Initiation . ......................................................................................... 4 \n4.4 Selection of Arbitrator(s) . ..................................................................... 4 \n4.5 Procedures ........................................................................................ 5 \n4.6 Summary Disposition and Interim Measures ............................................... 5 \n4.6.1 Lack of Good Faith Basis . ......................................................... 5 \n4.6.2 Discovery Limits . ................................................................... 5 \n4.6.3 Interim Decision . .................................................................... 5 \n4. 7 Discovery of Facts .............................................................................. 5 \n4.7.1 Discovery Procedures ............................................................... 5 \n4. 7 .2 Procedures Arbitrator. .............................................................. 6 \n4. 8 Evidentiary Hearing . ........................................................................... 6 \n4. 9 Confidentiality ................................................................................... 6 \n4. 9 .1 Designation . .......................................................................... 6 \n4.9.2 Compulsory Disclosure ............................................................. 7 \n4.9.3 Public Information ................................................................... 7 \n4.10 Timetable ........................................................................................ 7 \n4.11 Advisory Interpretations ...................................................................... 7 \n4.12 Decisions ........................................................................................ 8 \n4.13 Costs ............................................................................................. 8 \n4.14 Enforcement . ................................................................................... 8 \n5. ALTERNATE DISPUTE RESOLUTION COMMITTEE ......................................... 8 \n5.1 Membership ...................................................................................... 8 \n5.1.1 Representatives ....................................................................... 8 \n5.1.2 Term ................................................................................... 9 \n5.2 Voting Requirements . .......................................................................... 9 \n5.3 Officers ........................................................................................... 9 \n5 .4 Meetings . ......................................................................................... 9 \n5. 5 Responsibilities .................................................................................. 9 \nSCHEDULE 6 -\nREGIONAL TRANSMISSION EXPANSION PLANNING PROTOCOL .. 1 \nix \nHarvard Electricity Law Initiative Protest \nAppendix B - PJM's 1997 Operating Agreement\nB-9"},{"page":21,"startToken":5655,"endToken":5901,"text":"1. REGIONAL TRANSMISSION EXPANSION PLANNING PROTOCOL ..................... 1 \n1.1 Purpose and Objectives .. .. .. . .. .. . . . . . . . . .. .. .. . . .. .. .. .. . .. .. .. .. .. .. .. . . .. .. .. .. .. .. .. .. .. . . 1 \n1.2 Conformity with NERC and MAAC Criteria .............................................. 1 \n1. 3 Establishment of Committees . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 \n1. 4 Contents of the Regional Transmission Expansion Plan ................................. 2 \n1. 5 Procedure for Development of the Regional Transmission Expansion Plan .......... 2 \n1.5.1 Commencement of the Process .................................................... 2 \n1.5.2 Development of Scope, Assumptions and Procedures ........................ 3 \n1.5.3 Scope of Studies ..................................................................... 3 \n1.5.4 Supply of Data ....................................................................... 3 \n1.5.5 Coordination of the Regional Transmission Expansion Plan ................ 3 \n1.5.6 Development of the Recommended Regional Transmission Expansion Plan3 \n1. 6 Approval of the Final Regional Transmission Expansion Plan ......................... 4 \n1. 7 Obligation to Build .............................................................................. 5 \n1.8 Relationship to the PJM Control Area Open Access Transmission PJM Tariff ...... 5 \nSCHEDULE 7 - UNDERFREQUENCY RELAY OBLICATIONS AND CHARGES .......... 1 \n1. UNDERFREQUENCY RELAY OBLIGATION .................................................... 1 \n1.1 Application . ...................................................................................... 1 \n1. 2 Obligations. .. .. .. .. .. .. .. . . .. .. . . . . . . . . . .. .. .. .. . .. .. .. . . .. .. .. .. .. .. .. . . . . . .. . . . . . . . . .. . . . .. . .. . 1 \n2. UNDERFREQUENCY RELAY CHARGES ......................................................... I \n3. DISTRIBUTION OF UNDERFREQUENCY RELAY CHARGES .............................. 2 \n3.1 Share of Charges . ............................................................................... 2 \n3.2 Allocation by the Office of the Interconnection ............................................ 2 \nSCHEDULE 8 -DELEGATION OF RELIABILITY RESPONSIBILITIES ....................... 1 \n1. DELEGATION ............................................................................................ 1 \n2. NEW PARTIES ............................................................................................ I \n3. IMPLEMENTATION OF RELIABILITY ASSURANCE AGREEMENT . .................... 1 \nSCHEDULE 9 - EMERGENCY PROCEDURE CHARGES ......................................... 1 \n1. EMERGENCY PROCEDURE CHARGE ............................................................ I \n2. DISTRIBUTION OF EMERGENCY PROCEDURE CHARGES ................................ I \n2. I Complying Parties. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1 \n2.2 All Parties . ....................................................................................... 2 \nX \nHarvard Electricity Law Initiative Protest \nAppendix B - PJM's 1997 Operating Agreement\nB-10"},{"page":22,"startToken":5901,"endToken":6370,"text":"-\n-\n-\n-\n• \nshall distribute to the Members for their information final annual budgets for the following \nfiscal year not later than 60 days prior to the beginning of each fiscal year of the LLC. \n7 .6 \nBy-laws. \nTo the extent not inconsistent with any provision of this Agreement, the PJM Board \nshall adopt such by-laws establishing procedures for the implementation of this Agreement as it \nmay deem appropriate, including but not limited to by-laws governing the scheduling, noticing \nand conduct of meetings of the PJM Board, selection of a Chair and Vice Chair of the PJM \nBoard, action by the PJM Board without a meeting, and the organization and responsibilities of \nstanding and special committees of the PJM Board. Such by-laws shall not modify or be \ninconsistent with any of the rights or obligations established by this Agreement. \n7.7 \nDuties and Responsibilities of the PJM Board. \nIn accordance with this Agreement, the PJM Board shall supervise and oversee all \nmatters pertaining to the Interconnection and the LLC, and carry out such other duties as are \nherein specified, including but not limited to the following duties and responsibilities: \ni) \nii) \nAs its primary responsibility, ensure that the President, the other officers \nof the LLC, and Office of the Interconnection perform the duties and \nresponsibilities set forth in this Agreement, including but not limited to \nthose set forth in Sections 9.2 through 9.4 and Section 10.4, in a manner \nconsistent with (A) the safe and reliable operation of the Interconnection, \n(B)\nthe creation and operation of a robust, competitive, and\nnon-discriminatory electric power market in the PJM Control Area, and\n(C) the principle that a Member or group of Members shall not have\nundue influence over the operation of the Interconnection;\nSelect the Officers of the LLC; \niii)\nAdopt budgets for the LLC;\niv)\nApprove the Regional Transmission Expansion Plan in accordance with\nthe provisions of the Regional Transmission Expansion Planning\nProtocol set forth in Schedule 6 of this Agreement.\nv) \nvi) \nOn its own initiative or at the request of a User Group as specified\nherein, submit to the Members Committee such proposed amendments to\nthis Agreement or any Schedule hereto, or a proposed new Schedule, as\nit may deem appropriate;\nPetition FERC to modify any provision of this Agreement or any\nSchedule or practice hereunder that the PJM Board believes to be unjust,\nunreasonable, or unduly discriminatory under Section 206 of the Federal\nPower Act, subject to the right of any Member or the Members to\nintervene in any resulting proceedings;\nvii)\nReview for consistency with the creation and operation of a robust,\ncompetitive and non-discriminatory electric power market in the PJM\nControl Area any change to rate design or to non-rate terms and\n14 \nHarvard Electricity Law Initiative Protest \nAppendix B - PJM's 1997 Operating Agreement\nB-11"},{"page":23,"startToken":6370,"endToken":6747,"text":"-\n-\n-\nconditions proposed by Transmission Owners for filing under Section \n205 of the Federal Power Act. \nviii)\nIf and to the extent it shall deem appropriate, intervene in any\nproceeding at FERC initiated by the Members in accordance with Section\n1 l.5(b), and participate in other state and federal regulatory proceedings\nrelating to the interests of the LLC;\nix)\nReview, in accordance with Section 15.1.3, determinations of the Office\nof the Interconnection with respect to events of default;\nx)\nAssess against the other Members in proportion to their Weighted\nInterest an amount equal to any payment to the Office of the\nInterconnection, including interest thereon, as to which a Member is in\ndefault;\nxi)\nEstablish reasonable sanctions for failure of a Member to comply with its\nobligations under this Agreement;\nxii)\nDirect the Office of the Interconnection on behalf of the LLC to take\nappropriate legal or regulatory action against a Member (A) to recover\nany unpaid amounts due from the Member to the Office of the\nInterconnection under this Agreement and to make whole any Members\nsubject to an assessment as a result of such unpaid amount, or (B) as may\notherwise be necessary to enforce the obligations of this Agreement;\nxiii)\nResolve claims by a Member that the Reliability Committee established\nby the Reliability Assurance Agreement has exercised its responsibilities\nin a manner inconsistent with the creation and operation of a robust,\ncompetitive and non-discriminatory electric power market in the P JM\nControl Area, upon due consideration of the views of the Member and of\nthe Reliability Committee, and of the need to preserve the reliability of\nelectric service in the PJM Control Area.\nxiv)\nSolicit the views of Members on, and commission from time to time as it\nshall deem appropriate independent reviews of, (A) the performance of\nthe PJM Interchange Energy Market, (B) compliance by Market\nParticipants with the rules and requirements of the PJM Interchange\nEnergy Market, and (C) the performance of the Office of the\nInterconnection under performance criteria proposed by the Members\nCommittee and approved by the PJM Board; and\nxv)\nTerminate a Member as may be appropriate under the terms of this\nAgreement.\n15 \nHarvard Electricity Law Initiative Protest \nAppendix B - PJM's 1997 Operating Agreement\nB-12"},{"page":24,"startToken":6747,"endToken":7223,"text":"-\n-\n-\n8.5.2 Duties. \nThe Chair shall call and preside at meetings of the Members Committee, and \nshall carry out such other responsibilities as the Members Committee shall assign. The Chair \nshall cause minutes of each meeting of the Members Committee to be taken and maintained, \nand shall cause notices of meetings of the Members Committee to be distributed. The Vice \nChair shall preside at meetings of the Members Committee in the absence of the Chair, and \nshall otherwise act for the Chair at the Chair's request. \n8.6 \nOther Committees. \n(a)\nThe Members Committee may form, select the membership, and oversee the\nactivities, of an Operating Committee, a Planning Committee, and an Energy Market \nCommittee as standing committees, and such other committees, subcommittees, task forces, \nworking groups or other bodies as it shall deem appropriate, to provide advice and \nrecommendations to the Members Committee or to the Office of the Interconnection as directed \nby the Members Committee. \n(b)\nThe Members Committee shall elect representatives to the Alternate Dispute\nResolution Committee as specified in the PJM Dispute Resolution Procedures. \n8.7 \nUser Groups. \n(a)\nAny five or more Members sharing a common interest may form a User Group,\nand may invite such other Members to join the User Group as the User Group shall deem \nappropriate. Notification of the formation of a User Group shall be provided to all members of \nthe Members Committee. \n(b)\nThe Members Committee shall create a User Group composed of representatives\nof bona fide public interest and environmental organizations that are interested in the activities \nof the LLC and are willing and able to participate in such a User Group. \n(c)\nMeetings of User Groups shall be open to all Members and the Office of the\nInterconnection. Notices and agendas of meetings of a User Group shall be provided to all \nMembers that ask to receive them. \n(d)\nAny recommendation or proposal for action adopted by affirmative vote of\nthree-fourths or more of the members of a User Group shall be circulated by the Office of the \nInterconnection to the representatives on the Members Committee and shall be considered by \nthe Members Committee at its next regular meeting occurring not earlier than 30 days after the \ncirculation of such notice. \n( e)\nIf the Members Committee does not adopt a recommendation or proposal\nsubmitted to it by a User Group, upon vote of nine-tenths or more of the members of the User \nGroup the recommendation or proposal may be submitted to the PJM Board for its \nconsideration in accordance with Section 7.7(v). \n8.8 \nPowers of the Members Committee. \nThe Members Committee, acting by adoption of a motion as specified in Section 8.4, \nshall have the power to take the actions specified in this Agreement, including: \n19 \nHarvard Electricity Law Initiative Protest \nAppendix B - PJM's 1997 Operating Agreement\nB-13"},{"page":25,"startToken":7223,"endToken":7740,"text":"i)\nElect the members of the PJM Board;\nii)\nIn accordance with the provisions of Section 18.6 of this Agreement,\namend any portion of this Agreement, including the Schedules hereto, or\ncreate new Schedules, and file any such amendments or new Schedules\nwith FERC or other regulatory body of competent jurisdiction;\niii)\nTerminate this Agreement; and\niv)\nProvide advice and recommendations to the PJM Board and the Office of\nthe Interconnection.\n9.1 \nElection and Term. \n9.\nOFFICERS\nThe officers of the LLC shall consist of a President, a Secretary and a Treasurer. The \nPJM Board may elect such other officers as it deems necessary to carry out the business of the \nLLC. All officers shall be elected by the PJM Board and shall hold office until the next annual \nmeeting of the PJM Board and until their successors are elected. Any number of offices may \nbe held by the same person, except that the offices of the President and Treasurer may not be \nheld by the same person. \n9 .2 \nPresident. \nThe PJM Board shall appoint a President and Chief Executive Officer of the LLC (the \n\"President\"). The President shall direct and supervise the day-to-day operation of the LLC, \nand shall report to the PJM Board. \nThe President shall be responsible for directing and \nsupervising the Office of the Interconnection in the performance of the duties and \nresponsibilities specified in Section 10.4. The President shall execute bonds, mortgages and \nother contracts requiring a seal, under the seal of the LLC, except where required or permitted \nby law to be otherwise signed and executed and except where the signing and execution thereof \nshall be expressly delegated by the board to some other officer or agent of the LLC. In the \nabsence of the President or in the event of his or her inability or refusal to act, and if a vice \npresident has been appointed by the PJM Board, the Vice President (or in the event there be \nmore than one Vice President, the Vice Presidents in the order designated by the PJM Board in \nits Minutes) shall perform the duties of the President, and when so acting, shall have all the \npowers of and be subject to all the restrictions upon the President. The Vice President shall \nperform such other duties and have such other powers as the PJM Board may from time to \ntime prescribe. \n9 .3 \nSecretary. \nThe Secretary shall attend all meetings of the PJM Board and record all the proceedings \n-\nof the meetings of the PJM Board in a minute book to be kept for that purpose and shall\nperform like duties for the standing committees or special committees when required. He or\nshe shall give, or cause to be given, notice of all special meetings of the PJM Board, and shall\nperform such other duties as may be prescribed by the PJM Board or President, under whose\nsupervision he or she shall be. He or she shall have custody of the corporate seal of the LLC,\n20 \nHarvard Electricity Law Initiative Protest \nAppendix B - PJM's 1997 Operating Agreement\nB-14"},{"page":26,"startToken":7740,"endToken":8109,"text":"-\n-\n-\n-\n-\n-\n-\n-\n-\n-\n-\n-\nshall request such Members as the President shall deem appropriate to participate in such \nprocesses and organization. \nAll such processes and organization shall be carried out in \naccordance with all applicable code of conduct or other functional separation requirements of \nFERC. \n10.3 \nConfidential Information. \nThe Office of the Interconnection shall comply with the requirements of Section 18. 17 \nwith respect to any proprietary or confidential information received from or about any \nMember. \n10.4 Duties and Responsibilities. \nThe Office of the Interconnection, under the direction of the President as supervised \nand overseen by the PJM Board, shall carry out the following duties and responsibilities, 111 \naccordance with the provisions of this Agreement: \ni)\nAdminister and implement this Agreement;\nii)\nPerform such functions in furtherance of this Agreement as the PJM\nBoard, acting within the scope of its duties and responsibilities under this\nAgreement, may direct;\niii)\nPrepare, maintain, update and disseminate the PJM Manuals;\niv)\nComply with MAAC and NERC operation and planning standards,\nprinciples and guidelines;\nv)\nMaintain an appropriately trained workforce, and such equipment and\nfacilities, including computer hardware and software and backup power\nsupplies, as necessary or appropriate to implement or administer this\nAgreement;\nvi)\nDirect the operation and coordinate the maintenance of the facilities of\nthe Interconnection used for both load and reactive supply, so as to\nmaintain reliability of service and obtain the benefits of pooling and\ninterchange consistent with this Agreement and the Reliability Assurance\nAgreement;\nvii)\nDirect the operation and coordinate the maintenance of the bulk power\nsupply facilities of the Interconnection with such facilities and systems of\nothers not party to this Agreement in accordance with agreements\nbetween the LLC and such other systems to secure reliability and\ncontinuity of service and other advantages of pooling on a regional basis;\nviii)\nPerform interchange accounting and maintain records pertaining to the\noperation \nof the \nPJM \nInterchange \nEnergy \nMarket and \nthe\nInterconnection;\nix)\nNotify the Members of the receipt of any application to become a\nMember, and of the action of the Office of the Interconnection on such\napplication, including but not limited to the completion of integration of\n22 \nHarvard Electricity Law Initiative Protest \nAppendix B - PJM's 1997 Operating Agreement\nB-15"},{"page":27,"startToken":8109,"endToken":8479,"text":"a new Member's system into the PJM Control Area as specified m \nSection l l.6(f); \nx)\nCalculate the Weighted Interest of each Member;\nxi)\nMaintain accurate records of the sectors in which each Voting Member is\nentitled to vote, and calculate the results of any vote taken in the\nMembers Committee;\nxii)\nFurnish appropriate information and reports as are required to keep the\nMembers regularly informed of the outlook for, the functioning of, and\nresults achieved by the Interconnection;\nxiii)\nFile with FERC on behalf of the Members any amendments to this\nAgreement or the Schedules hereto, any new Schedules hereto, and make\nany other regulatory filings on behalf of the Members or the LLC\nnecessary to implement this Agreement;\nxiv)\nAt the direction of the PJM Board, submit comments to regulatory\nauthorities on matters pertinent to the Interconnection;\nxv)\nConsult with the standing or other committees established pursuant to\nSection 8.6(a) on matters within the responsibility of the committee;\nxvi)\nPerform operating studies of the bulk power supply facilities of the\nInterconnection and make such recommendations and initiate such\nactions as may be necessary to maintain reliable operation of the\nInterconnection;\nxvii)\nAccept, on behalf of the Members, notices served under this Agreement;\nxviii)\nPerform those functions and undertake those responsibilities transferred\nto it under the Transmission Owners Agreement, including (A) direct the\noperation of the transmission facilities of the parties to the Transmission\nOwners Agreement, (B) administer the PJM Tariff, and (C) administer\nthe Regional Transmission Expansion Planning Protocol set forth as\nSchedule 6 to this Agreement.\nxix)\nPerform those functions and undertake those responsibilities transferred\nto it under the Reliability Assurance Agreement, as specified in Schedule\n8 of this Agreement.\nxx)\nMonitor the operation of the PJM Control Area, ensure that appropriate\nEmergency plans are in place and appropriate Emergency drills are\nconducted, declare the existence of an Emergency, and direct the\noperations of the Members as necessary to manage, alleviate or end an\nEmergency;\nxxi)\nIncorporate the grid reliability requirements applicable to nue-\\e-.;1\ngenerating units in the PJM Control Area planning and operating\nprinciples and practices; and\n23 \nHarvard Electricity Law Initiative Protest \nAppendix B - PJM's 1997 Operating Agreement\nB-16"},{"page":28,"startToken":8479,"endToken":8966,"text":"party or by which it or any of its properties is bound, or constitutes or will constitute a default \nthereunder or will result in the imposition of any lien upon any of its properties. \n17.1.6 No Proceedings. \nThere are no actions at law, suits in equity, proceedings or claims pending or, to \nthe knowledge of the Member, threatened against the Member before any federal, state, \nforeign or local court, tribunal or government agency or authority that might materially delay, \nprevent or hinder the performance by the Member of its obligations hereunder. \n17 .2 Municipal Electric Systems. \nAny provisions of Section 17 .1 notwithstanding, if any Member that is a municipal \nelectric system believes in good faith that the provisions of Sections 5. l(b) and 16.1 of this \nAgreement may not lawfully be applied to that Member under applicable state law governing \nmunicipal activities, the Member may request a waiver of the pertinent provisions of the \nAgreement. Any such request for waiver shall be supported by an opinion of counsel for the \nMember to the effect that the provision of the Agreement as to which waiver is sought may not \nlawfully be applied to the Member under applicable state law. The PJM Board shall have the \nright to have the opinion of the Member's counsel reviewed by counsel to the LLC. If the \nPJM Board concludes that either or both of Sections 5.l(b) and 16.1 of this Agreement may \nnot lawfully be applied to a municipal electric system Member, it shall waive the application of \nthe affected provision or provisions to such municipal Member. Any Member not permitted \nby law to indemnify the other Members shall not be indemnified by the other Members. \n17 .3 \nSurvival. \nAll representations and warranties contained in this Section 17 shall survive the \nexecution and delivery of this Agreement. \n18.\nMISCELLANEOUS PROVISIONS\n18.1 \nTransmission Owners Rights. \nNeither the PJM Board nor the Members Committee shall take any action which has the \neffect of modifying or limiting the following rights and obligations of Transmission Owners, \nwhich are hereby reserved to the Transmission Owners; provided, however, that the rights and \nobligations of the Transmission Owners set forth below shall be exercised in a manner \nconsistent with applicable obligations under the Federal Power Act and FERC's rules and \nregulations thereunder: \n(a)\nThe right at any time of Transmission Owners individually or collectively to file\npursuant to Section 205 of the Federal Power Act for any change in rates and charges for \ntransmission or an ancillary service that it deems necessary to recover its transmission revenue \nrequirements for providing service under the PJM Tariff. \n(b)\nThe right of Transmission Owners individually or collectively to adopt and\nimplement procedures to protect their electric facilities from physical damage or to prevent \ninjury or damage to persons or property. \n36 \nHarvard Electricity Law Initiative Protest \nAppendix B - PJM's 1997 Operating Agreement\nB-17"},{"page":29,"startToken":8966,"endToken":9489,"text":"-\n-\n-\n-\n-\n-\n-\n-\n(c)\nThe right of Transmission Owners individually or collectively to build, acquire,\nsell, dispose, retire, merge or otherwise transfer or convey all or any part of its or their assets, \nincluding but not limited to any Transmission Facilities, such right to include, but not be \nlimited to, the right, individually or collectively, to terminate the relationship with the LLC in \nconnection with the creation of a transmission company to own and/ or operate the \nTransmission Facilities of the Transmission Owners or any of them. \n(d)\nThe ability of Transmission Owners individually or collectively to take whatever\nactions it or they deem necessary to fulfill its or their obligations under local, state or federal \nlaw. \n(e)\nThe right of any Transmission Owner to withdraw from this Agreement in\naccordance with its provisions. \n18.2 Fiscal and Taxable Year. \nThe fiscal year and taxable year of the LLC shall be the calendar year. \n18.3 \nReports. \nEach year prior to the Annual Meeting of the Members, the PJM Board shall cause to \nbe prepared and distributed to the Members a report of the LLC's activities since the prior \nreport. \n18.4 Bank Accounts; Checks, Notes and Drafts. \n(a)\nFunds of the LLC shall be deposited in an account or accounts of a type, in\nform and name and in a bank(s) or other financial institution(s) which are participants in \nfederal insurance programs as selected by the PJM Board. The PJM Board shall arrange for \nthe appropriate conduct of such accounts. Funds may be withdrawn from such accounts only \nfor bona fide and legitimate LLC purposes and may from time to time be invested in such \nshort-term securities, money market funds, certificates of deposit or other liquid assets as the \nPJM Board deems appropriate. All checks or demands for money and notes of the LLC shall \nbe signed by any officer or by any other person designated by the PJM Board. \n(b)\nThe Members acknowledge that the PJM Board may maintain LLC funds in\naccounts, money market funds, certificates of deposit, other liquid assets in excess of the \ninsurance provided by the Federal Deposit Insurance Corporation, or other depository \ninsurance institutions and that the PJM Board shall not be accountable or liable for any loss of \nsuch funds resulting from failure or insolvency of the depository institution. \n(c)\nChecks, notes, drafts and other orders for the payment of money shall be signed\nby such persons as the PJM Board from time to time may authorize. When the PJM Board so \nauthorizes, the signature of any such person may be a facsimile. \n18.5 \nBooks and Records. \n(a)\nAt all times during the term of the LLC, the PJM Board shall keep, or cause to\nbe kept, full and accurate books of account, records and supporting documents, whic\\\\ <,,\\\\all \nreflect, completely, accurately and in reasonable detail, each transaction of the LLC. The \nbooks of account shall be maintained and tax returns prepared and filed on the method of \naccounting determined by the PJM Board. The books of account, records and all documents \n37 \nHarvard Electricity Law Initiative Protest \nAppendix B - PJM's 1997 Operating Agreement\nB-18"},{"page":30,"startToken":9489,"endToken":9949,"text":"-\n-\n-\n-\nand other writings of the LLC shall be kept and maintained at the principal office of the \nInterconnection. \n(b)\nThe PJM Board shall cause the Office of the Interconnection to keep at its\nprincipal office the following: \ni)\nA current list in alphabetical order of the full name and last known\nbusiness address of each Member, the Weighted Interest of each\nMember, and the Members Committee sector of each Voting Member;\nii)\nA copy of the Certificate of Formation and the Certificate of Conversion,\nand all Certificates of Amendment thereto;\niii)\nCopies of the LLC's federal, state, and local income tax returns and\nreports, if any, for the three most recent years; and\niv)\nCopies of the Operating Agreement, as amended, and of any financial\nstatements of the LLC for the three most recent years.\n18.6 Amendment. \n(a)\nExcept as provided by law or otherwise set forth herein, this Agreement,\nincluding any Schedule hereto, may be amended, or a new Schedule may be created, only \nupon: (i) submission of the proposed amendment to the PJM Board for its review and \ncomments; (ii) approval of the amendment or new Schedule by the Members Committee, after \nconsideration of the comments of the PJM Board, in accordance with Section 8.4, or written \nagreement to an amendment of all Members not in default at the time the amendment is agreed \nupon; and (iii) approval and/or acceptance for filing of the amendment by FERC and any other \nregulatory body with jurisdiction thereof as may be required by law. If and as necessary, the \nMembers Committee may file with FERC or other regulatory body of competent jurisdiction \nany amendment to this Agreement or to its Schedules or a new Schedule not filed by the Office \nof the Interconnection. \n(b)\nNotwithstanding the foregoing, an applicant eligible to become a Member in\naccordance with the procedures specified in this Agreement shall become a Member by \nexecuting a counterpart of this Agreement without the need for amendment of this Agreement \nor execution of such counterpart by any other Member. \n( c)\nEach of the following fundamental changes to the LLC shall require or be\ndeemed to require an amendment to this Agreement and shall require the prior approval of \nFERC: \ni)\nAdoption of any plan of merger or consolidation;\nii) \niii) \nAdoption of any plan of sale, lease or exchange of assets relating to all,\nor substantially all, of the property and assets of the LLC;\nAdoption of any plan of division relating to the division of the LLC into\ntwo or more corporations or other legal entities;\niv)\nAdoption of any plan relating to the conversion of the LLC into a stock\ncorporation;\n38 \nHarvard Electricity Law Initiative Protest \nAppendix B - PJM's 1997 Operating Agreement\nB-19"},{"page":31,"startToken":9949,"endToken":10411,"text":"v)\nAdoption of any proposal of voluntary dissolution; or\nvi)\nTaking any action which has the purpose or effect of the adoption of any\nplan or proposal described in items (i), (ii), (iii), (iv) or (v) above.\n18. 7 Interpretation.\nWherever the context may require, any noun or pronoun used herein shall include the \ncorresponding masculine, feminine or neuter forms. The singular form of nouns, pronouns \nand verbs shall include the plural and vice versa. \n18.8 \nSeverability. \nEach provision of this Agreement shall be considered severable and if for any reason \nany provision is determined by a court or regulatory authority of competent jurisdiction to be \ninvalid, void or unenforceable, the remaining provisions of this Agreement shall continue in \nfull force and effect and shall in no way be affected, impaired or invalidated, and such invalid, \nvoid or unenforceable provision shall be replaced with valid and enforceable provision or \nprovisions which otherwise give effect to the original intent of the invalid, void or \nunenforceable provision. \n18.9 \nForce Majeure. \nNo Member shall be liable to any other Member for damages or otherwise be in breach \nof this Agreement to the extent and during the period such Member's performance is prevented \nby any cause or causes beyond such Member's control and without such Member's fault or \nnegligence, including but not limited to any act, omission, or circumstance occasioned by or in \nconsequence of any act of God, labor disturbance, act of the public enemy, war, insurrection, \nriot, fire, storm or flood, explosion, breakage or accident to machinery or equipment, or \ncurtailment, order, regulation or restriction imposed by governmental, military or lawfully \nestablished civilian authorities; provided, however, that any such foregoing event shall not \nexcuse any payment obligation. Upon the occurrence of an event considered by a Member to \nconstitute a force majeure event, such Member shall use due diligence to endeavor to continue \nto perform its obligations as far as reasonably practicable and to remedy the event, provided \nthat no Member shall be required by this provision to settle any strike or labor dispute. \n18.10 Further Assurances. \nEach Member hereby agrees that it shall hereafter execute and deliver such further \ninstruments, provide all information and take or forbear such further acts and things as may be \nreasonably required or useful to carry out the intent and purpose of this Agreement and as are \nnot inconsistent with the terms hereof. \n18.11 Seal. \nThe seal of the LLC shall have inscribed thereon the name of the LLC, the year of its \norganization and the words \"Corporate Seal, Delaware.\" The seal may be used by causing it \nor a facsimile thereof to be impressed or affixed or reproduced or otherwise. \n39 \nHarvard Electricity Law Initiative Protest \nAppendix B - PJM's 1997 Operating Agreement\nB-20"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":11,"endAt":6,"startToken":0,"endToken":3309},{"p":11,"at":6,"title":"CONCLUSION","method":"printed heading","endPage":14,"endAt":1736,"startToken":3309,"endToken":3988},{"p":14,"at":1736,"title":"I. Objectives of the Instant Filing","method":"printed heading","endPage":31,"endAt":2896,"startToken":3988,"endToken":10411}]}