{"document":{"slug":"rec-20260821-5159","title":"Post-Technical Conference Comments of East Kentucky Power Cooperative, Inc. re PJM Governance and Stakeholder Reforms","issued":"2026-08-21","accession":"20260821-5159","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"East Kentucky Power Cooperative, Inc.","kind":"comments","file":"sources/filings/text/20260821-5159_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5159","tier":"record","sha256":"9d519f3f8b73918f5cd1159c5d1fbad40f898ebce7532d5f6621394c9afc2e4a","pages":12,"tokens":3175,"emptyPages":[],"textThemes":["adequacy","cost"]},"pages":[{"page":1,"startToken":0,"endToken":215,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Governance and \n) \nDocket No. AD26-7-000 \nStakeholder Reforms \n) \n \nPOST-TECHNICAL CONFERENCE COMMENTS OF \nEAST KENTUCKY POWER COOPERATIVE, INC. \n \nEast Kentucky Power Cooperative, Inc. (“EKPC”) appreciates the opportunity to \noffer these post-technical conference comments, including responding to the questions \nposed by the Commission. \nEKPC integrated into PJM in 2013. EKPC is a generation and transmission owning \ncooperative that serves 16 distribution owner-member cooperatives. EKPC is in the \nTransmission Owner sector of the PJM membership. EKPC actively engages in the PJM \nstakeholder process, including working across sectors to achieve consensus on contentious \nmatters. Most recently, EKPC co-sponsored the Reliability Backstop Procurement \nproposal that achieved a two-thirds, sector-weighted super-majority vote.1 Although there \nare examples where the PJM membership has been challenged to come to consensus, \ndeveloping an appropriately structured Reliability Backstop Procurement was not one. Of \ncourse, this is a key component to addressing the biggest challenge facing the PJM region \n \n1 A proposal co-sponsored by EKPC, Buckeye Power, Dominion Energy, Duke Energy Ohio, Duke Energy \nKentucky, Duquesne Light Company, Exelon, Old Dominion Electric Cooperative, PPL Electric Utilities \nCorp., Southern Maryland Electric Cooperative, and the Data Center Coalition (called the “Coalition” \nReliability Backstop Procurement (RBP) Proposal). The Coalition RBP Proposal is available here: \n20260630-item-02f---joint-edcs-and-data-center-coalition---rbp---executive-summary.pdf."},{"page":2,"startToken":215,"endToken":495,"text":"2 \nand, despite the complexity of the issues involved, EKPC helped to forge a consensus when \nPJM was unable to do so. \nIt is EKPC’s view that the current resource adequacy challenge in the PJM region \nmay partially be attributed to PJM’s failure to act appropriately and timely with respect to \nmatters within the Commission’s jurisdiction where PJM currently has the authority to \nmake filings under Section 205 of the Federal Power Act. However, EKPC firmly believes \nthat the current resource adequacy challenge is primarily driven by the failure of retail \nchoice states to impose appropriate requirements on those who serve retail load within their \nstate.2 In other words, those states have allowed: 1) existing load to be served by reliance \non PJM’s short-term markets; and 2) new load to connect to the system without requiring \nadequate power supplies to serve them. These state policies have effectively encouraged \nleaning on the wholesale power markets at a period in time when large amounts of \ndispatchable generation resources have been retired without replacement. Moreover, policy \nmakers in some of these states have condemned the PJM markets and the PJM Board and \nleadership for rapid escalations in retail energy prices when the negative impacts of their \nown state policies have adversely impacted the wholesale capacity market via increased \nRPM Capacity Market prices. \nEKPC fundamentally disagrees with how some have framed the challenge – that the \ncrisis was caused by flaws in PJM’s governance and ineffective stakeholder process. The \n \n2 See Letter from Don Mosier (EKPC CEO) to DOE Sec’y Wright and FERC Chairman Swett, dated August \n6, \n2026. \nMr. \nMosier’s \nletter \nis \nmade \navailable \nhere: \nhttps://elibrary.ferc.gov/eLibrary/filedownload?fileid=DE6EEFA0-9BE5-C0BF-9D32-9FF2CA500000."},{"page":3,"startToken":495,"endToken":782,"text":"3 \nstatus quo cannot solely be attributed to PJM’s action or lack of action. While there are \ncertain changes at PJM that would be constructive and appropriate to consider at this time \nto best ensure the region as a collective body navigates through this challenge successfully, \ncare must be exercised to not institutionalize politization in PJM’s governance and bulk \npower grid operations. \nA key theme in written and oral comments arising from the Technical Conference \nwas that there should be a clear delineation of responsibilities between PJM and the “states” \nto achieve resource adequacy and ensure it will persist into the future. In EKPC’s view, a \nclear delineation of roles and responsibilities to ensure resource adequacy (and associated \naccountability to faithfully execute those roles to fulfill those responsibilities) is the most \ncritical thing that must be accomplished under the Commission’s leadership through the \nAlternative Dispute Resolution process that the Commission initiated. Only then may \nstrategic action plans be developed by the states and PJM to ensure that their respective \nefforts work in concert, not conflict, with the overall resource adequacy objective. \nCollaboration between the federal authorities and state authorities through this effort must \nresult in clarity about what needs to happen in the thirteen states and District of Columbia \ncomprising the PJM region and how those actions mesh with, and harness, the benefits of \nthe wholesale power markets administered by PJM. This must happen regardless of \nwhether any specific additional role or responsibility be considered for states in the PJM \ngovernance or stakeholder process. Governors’ offices, state legislators and state \ncommissions have been engaged in this Technical Conference, but primarily led by leaders \nin those states where the requirement to own and operate generation adequate is divorced"},{"page":4,"startToken":782,"endToken":1066,"text":"4 \nfrom the obligation to meet customer load. Those are the various state entities that must act \nin their retail realm to ensure alignment with the overarching resource adequacy objective \nand action is undertaken to ensure there is no unreasonable leaning on the wholesale power \nmarkets. Ironically, the states with the greatest need to assure that their states achieve \naffordable energy rates are the very states calling for wholesale reform of PJM’s \ngovernance, despite the fact that it is their own state policies that have created the \naffordability concern. In some instances, state laws or state commission regulations will \nneed to be revised. It would be appropriate to receive commitments that those actions will \nbe assessed and undertaken before pressuring PJM to alter a governance structure that, \nhistorically, has worked relatively well. Indeed, that should be a condition of any state body \nbeing granted any specific role or responsibility in PJM’s governance or stakeholder \nprocess. \nEKPC offers its perspective on the questions below and appreciates that the \nCommission recognizes that these questions are inter-related and not exhaustive. EKPC \nalso offers an observation that potential acceptance of certain changes below would be \nconditioned on other changes simultaneously being made. \nPJM Board Independence \n \n \nQuestions/Comments \nYes No \n1) \nShould Board members’ terms be extended to five or more years? \nX \n \n \nComments: EKPC supports extending the term to 5 years. PJM is complex and \nthe decisions that the PJM Board is tasked to make require sufficient expertise \nthat sharpens over time and experience. Additionally, the result of Board \ndecisions may not fully come to bear within the three-year term of a Board \nmember. It is appropriate to have a time horizon that more likely ensures that a"},{"page":5,"startToken":1066,"endToken":1452,"text":"5 \n \nQuestions/Comments \nYes No \nBoard member will experience the longer-term outcome of decisions made. \n2) \nShould there be a maximum number of years that a Board member \nmay serve (e.g., 10 years)? \n \nX \n \nComments: If a Board member has effectively discharged their responsibilities, \nthere should be no Operating Agreement imposed limit on terms or years of \nservice. However, as a self-policing effort, it is appropriate for the Board to \nimpose term and age limits through their bylaws as the PJM Board currently \ndoes. \n3) \nShould the Board member qualification rules be revised to provide a \npreference for some Board members that reside in the PJM region? \nX \n \n \nComments: It is appropriate to require some tie to the region, being a resident or \nrelevant work experience. However, requiring residency during Board service \nterm should not be a requirement. It may limit qualified candidates who \notherwise had experience that satisfies the intention of a residency requirement. \n4) \nShould the conflict-of-interest rules be revised to reduce the cooling \noff period for Board members from two years to one year? \nX \n \n \nComments: A cooling off period is necessary to address actual or perceived \nconflicts of interest. A 2-year cooling off period reduces the candidate pool. A 1-\nyear cooling off period would be appropriate and is consistent with state and \nfederal lobbying rules and state and federal employment rules. \n5) \nShould restrictions on Board communications be relaxed to enable \nmore communication between the Board and stakeholders? \n \nX \n \nComments: The ex parte rules are intended to reinforce independence and \ntransparency. Relaxing them will disadvantage smaller, less-resourced market \nparticipants and shift stakeholder efforts from striving to achieve stakeholder \nconsensus to striving to influence Board decisions. This concern would be \nheightened should additional FPA Section 205 filing rights be afforded to the \nPJM Board. To the extent the term “stakeholders” encompasses states, it is \nappropriate for the PJM Board to meet with OPSI, as it does today. To have \nimpact on what governing document changes are filed with the Commission, \nhowever, the OPSI consensus position should be injected into the stakeholder \nprocess to be deliberated with those who own the assets, make financial decisions \nbased on the PJM rules. Such entities must fully understand the technical impacts \nof the proposals on their businesses. Members like EKPC owe a fiduciary duty as"},{"page":6,"startToken":1452,"endToken":1814,"text":"6 \n \nQuestions/Comments \nYes No \nwell as obligation to provide safe, adequate and reliable service to its owner-\nmembers who serve end-consumers. It is imperative that EKPC have an effective \nopportunity to weigh in on potential changes that may impact its ability to meet \nits obligations. \n6) \nIn order to increase transparency, should Board votes be made public \nor the Board be required to explain its reasoning?  \nX \n \n \nComments: The tally of “yeas” and “nays” would be beneficial to understand the \nlevel of consensus on positions. However, it is not necessary to report individual \nBoard member voting positions. Revealing individual votes may increase the \npotential for ex parte lobbying efforts targeting individual Board members, \nwhich may compromise the Board’s independence. Additionally, it would be \nbeneficial for the membership to understand the factors the Board considered in \nexplaining its reasoning for decisions involving changes to PJM governing \ndocuments. The Board makes numerous decisions, including those affecting PJM \nemployees and PJM operations. Those decisions do not need to be reported \npublicly or explained publicly. \n7) \nIn order to increase transparency, should some Board meetings be \nopen or available to the public? \n \nX \n \nComments:  \n8) \nShould PJM’s governing documents be revised to explicitly state that \nthe responsibility of PJM and its Board is to serve the public interest? \n \nX \n \nComments: PJM’s purpose is to ensure reliability at the lowest reasonable cost. It \nnecessarily needs focus on engineering and economics. Whereas, a “public \ninterest” standard necessarily involves broader factors, including those outside of \nPJM’s authority. \nPJM may only be charged with responsibilities that are consistent with the \nFederal Power Act. To the extent that the concept of public interest were limited \nto that embodied in the Federal Power Act, an appropriately caveated reference \nmay be considered. \nHowever, even such caveats are insufficient to address the elephant in the room. \nResource adequacy is the most significant challenge for the region to overcome. \nIncluding a reference to “public interest,” while ignoring the fact that PJM does \nnot possess all the authorities necessary to accomplish it, would likely further \nsubject PJM to political pressure and out-weighted criticism. Only upon \nestablishing a clear delineation of, and accountability for, roles and"},{"page":7,"startToken":1814,"endToken":2156,"text":"7 \n \nQuestions/Comments \nYes No \nresponsibilities between PJM and the states/DC to ensure resource adequacy \nwould it be appropriate to consider inserting “public interest” (caveated to ensure \nthat it is framed in the context of the Federal Power Act) in the PJM governing \ndocuments. PJM’s governing documents also would need to reflect the \naccountability that the states/DC have agreed to assume. Otherwise, PJM would \nbe upheld to a standard that its authorities alone cannot satisfy. Imposing such a \nsignificant legal standard would likely require authorization by Congress. \n9) \nShould state representatives have at least one voting member on the \nNominating Committee? \n \nX \n \nComments: This question is unclear. There are at least 3 bodies of state \ngovernment engaged in the governance discussions: state commissions, \ngovernors, and state legislators. This could be read to assume that one \nrepresentative for each state, or one representative of each of these 3 bodies. Or \nboth. \n10) \nShould PJM adopt public performance metrics and tie management \ncompensation to their achievement? \n \nX \n \nComments: This question is unclear. If it is suggesting that a public interest \nstandard could be translated to metrics for performance against which \nmanagement would be assessed, it is unclear how that could be done. Whereas, \nPJM’s Operating Agreement currently charges the PJM Board to ensure \nreliability as well as non-discriminatory, competitive wholesale markets. Those \nobjectives should be tied to management performance metrics. \n \nSection 205 Filing Rights \n \n \nQuestions/Comments \nYes No \n11) \nShould the stakeholder process be advisory, i.e., stakeholder votes \nonly inform the Board? \n \nX \n \nComments: For the stakeholder process to be advisory, the PJM Board would \nhave Section 205 filing rights over every governing document and stakeholder \nvotes would not result in any Section 205 filings, including “jump ball” filings. \nAdditionally, to the extent that the TOA-AC may be considered part of the \nstakeholder process, it would be inappropriate to suggest that the asset owners \nwho came together to enable the formation of PJM to not have a say in changes \nto the foundational agreement that governs the rules and responsibilities turned"},{"page":8,"startToken":2156,"endToken":2531,"text":"8 \n \nQuestions/Comments \nYes No \nover to PJM and those retained by the Transmission Owners. \n12) \nShould PJM have section 205 filing rights over the energy market and \nancillary services unencumbered by the requirement to obtain \napproval of two-thirds of the Members Committee? \n \nX \n \nComments: The current challenge is resource adequacy. PJM currently has \nSection 205 rights over its Tariff and the Reliability Assurance Agreement. \nThose are the operative governing documents to address the current challenge. \n13) \nShould PJM have section 205 filing rights over Regional \nTransmission Expansion Planning (RTEP) unencumbered by the \nrequirement to obtain approval of two-thirds of the Members \nCommittee? \nX \n \n \nComments: Providing PJM with Section 205 rights over the RTEP protocol must \nbe conditioned on appropriate dispute resolution procedures being established. \nAs noted above, EKPC owes a duty to its owner-members and must comply with \nstate regulations. It must have a meaningful opportunity to ensure that its \nperspectives are considered before changes that may impact its ability to plan its \nsystem are filed with the Commission. \n14) \nShould the Organization of PJM States Inc (OPSI) have “jump ball” \nrights over resource adequacy and transmission cost allocation filings \nwhen a supermajority of OPSI agrees on an alternative proposal? \n \nX \n \nComments: The PJM members (not OPSI), acting with a sector-weighted \nsupermajority, should be afforded “jump ball” rights over resource adequacy. \nTransmission cost allocation filing rights must remain with the Transmission \nOwners as they need the ability to ensure that their cost to build and maintain the \ntransmission system may be recovered. To the extent, however, that OPSI \nachieves a super-majority consensus on issues affecting resource adequacy or \ntransmission cost allocation, they should be afforded the opportunity to present \nthose perspectives to the PJM membership (for resource adequacy matters) or \nTOA-AC (for transmission cost allocation matters) and have those perspectives \nfully considered as proposals are being developed. Their input should be included \nand considered as part of the deliberative process, not something that occurs \nalongside or outside the deliberative process. In this way, OPSI may influence \nand essentially drive consensus to support a “jump ball” filing but not in and of \nthemselves submit a “jump ball” filing. We believe this suggestion is consistent \nwith the “jump ball” structure between NEPOOL and ISO New England."},{"page":9,"startToken":2531,"endToken":2773,"text":"9 \n \nQuestions/Comments \nYes No \n15) \nShould the Members Committee have “jump ball” filing rights over \nthe portions of the tariff where PJM has 205 filing rights when a \nsupermajority of stakeholders approves an alternative proposal? \nX \n \n \nComments: See above comment. \n \nStakeholder Process \n \n \nQuestions/Comments \nYes No \n16) \nShould the approval threshold in the Members Committee be lowered \nfrom two-thirds sector-weighted voting? \n \nX \n \nComments:  \n17) \nShould the voting rules barring affiliate votes, which apply to senior \nstanding committees, also apply to lower-level committees? \nX \n \n \nComments:  \n \nState Participation \n \n \nQuestions/Comments \nYes No \n18) \nIn addition to OPSI, should there be a second state representative \ngroup consisting of governors’ representatives and/or state legislators’ \nrepresentatives? \n \nX \n \nComments: Having multiple channels for state voices likely would result in \nconfusion for PJM and for the membership. It would be difficult to determine \nwhich voice should be considered if the voices expressed conflicting views. The \nstate perspective is valuable but should be channeled to best enable actionable \nimpact. Ultimately, it would be important to consider the role and responsibility \nof any state group in order to determine the appropriateness of a particular \nconfiguration of state representatives for purposes of influencing outcomes \naffecting PJM and its ability to satisfy its mandate under the Operating \nAgreement consistent with the Federal Power Act. As noted above, EKPC urges \nclarity in the delineation of roles and responsibilities (and accountability to fulfill \nthose responsibilities) between PJM and the states regarding resource adequacy."},{"page":10,"startToken":2773,"endToken":3011,"text":"10 \n \nQuestions/Comments \nYes No \n19) \nShould state representatives have a formal voting role in the \nstakeholder process (limited to certain topics, such as resource \nadequacy and regional transmission cost allocation) in addition to the \nconsumer advocate votes? \n \nX \n \nComments: There should be an opportunity for OPSI to insert its consensus view \non matters under deliberation in the PJM stakeholder process. That should be a \nstructured role enabling the offering of proposals, offering feedback on other’s \nproposals, asking questions, and seeking analysis or information. This, however, \nshould not be a formal voting role. EKPC supports the approach used in New \nEngland.  \n20) \nShould PJM be required to consult with OPSI prior to making a \nsection 205 filing related to resource adequacy and transmission cost \nallocation? \n \nX \n \nComments: There should be no explicit requirement that PJM consult with OPSI \nbefore it be permitted to submit a Section 205 filing with the Commission. \nHowever, it would be a good practice that PJM staff consult with OPSI \nthroughout the process in which the proposal is being developed. As noted in the \nresponse above, the New England model would invite the OPSI to engage \ndirectly in the stakeholder process so that the stakeholders too have a meaningful \nopportunity to engage with the ideas initiated by OPSI. Transparency and \nefficiency are reinforced by including OPSI in the process. Creating an entirely \nseparate process for engaging OPSI would conflict with transparency and \nefficiency objectives."},{"page":11,"startToken":3011,"endToken":3131,"text":"11 \nEKPC appreciates the opportunity to submit the foregoing comments in response to \nthe Commission’s questions. EKPC looks forward to continued dialogue on the important \ntopics discussed herein. \n \nRespectfully submitted, \n \n \nDenise R. Foster Cronin \nChief Compliance Officer and Senior Vice \nPresident \nEast Kentucky Power Cooperative, Inc. \n4775 Lexington Road, P.O. Box 707 \nWinchester, KY 40392-0707 \nTel.: 859-745-9615 \ndenise.cronin@ekpc.coop \n \nOn Behalf of \nEast Kentucky Power Cooperative, Inc. \n \n \n/s/ Daniel E. Frank  \n \nDaniel E. Frank \nAllison E.S. Salvia \nKelly A. Cuthbertson \nEversheds Sutherland (US) LLP \n700 Sixth St., N.W., Suite 700 \nWashington, DC 20001-3980 \nTel.: 202-383-0100 \ndanielfrank@eversheds-sutherland.com \nallisonsalvia@eversheds-sutherland.com \nkellycuthbertson@eversheds-sutherland.com \n \nCounsel for \nEast Kentucky Power Cooperative, Inc. \n \n \nDated: August 21, 2026"},{"page":12,"startToken":3131,"endToken":3175,"text":"Certificate of Service \n \nI hereby certify that I served the foregoing document upon each person designated \non the official service list compiled by the Secretary in this proceeding. \nDated at Washington, DC this 21st day of August, 2026. \nKelly A. Cuthbertson \n \nKelly A. Cuthbertson"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":12,"endAt":0,"startToken":0,"endToken":3131},{"p":12,"at":0,"title":"Certificate of Service","method":"printed heading","endPage":12,"endAt":285,"startToken":3131,"endToken":3175}]}