{"document":{"slug":"rec-20260821-5175","title":"Motion to Intervene and Comments of Base Power Inc. re PJM Interconnection, L.L.C.’s 07/31/2026 filing","issued":"2026-08-21","accession":"20260821-5175","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"Base Power Company","kind":"comments","file":"sources/filings/text/20260821-5175_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5175","tier":"record","sha256":"b738bb73548051235e555b107d4f50485a007bb9fd7989e8a761acb1955e5c66","pages":10,"tokens":2478,"emptyPages":[],"textThemes":["registry","adequacy","flex"]},"pages":[{"page":1,"startToken":0,"endToken":241,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n) \nPJM Interconnection, L.L.C. \n) \n \n \nDocket No. ER26-3380-000 \n \n) \n \nMOTION TO INTERVENE AND COMMENTS  \nOF BASE POWER INC. \nPursuant to Rules 211, 212, and 214 of the Federal Energy Regulatory Commission’s \n(Commission) Rules of Practice and Procedure,1 Base Power, Inc. (Base) respectfully submits this \nmotion to intervene, together with comments on the filing of PJM Interconnection, L.L.C. (PJM) \nestablishing the Reliability Backstop Procurement (RBP), dated July 31, 2026.2 \nBase supports the RBP and the overall structure of the proposed auction.  Following the \ncapacity shortfalls from the last few auctions, PJM and its staff should be commended for \ndeveloping the RBP proposal on a compressed timeline to address the region’s needs.  Base \nparticularly appreciates PJM’s positive and constructive engagement with stakeholders on the \npeak-shaving opt-out structure.  Establishing the peak-shaving opt-out to reduce the Initial RBP \nTarget unlocks a key pathway to address the capacity shortage, mitigate system-wide costs, and \nreduce risks to ratepayers. \nIn these comments, Base requests two narrow drafting clarifications related to the peak \nshaving opt-out in proposed Tariff, Attachment DD, section 18.1(d).3  PJM’s clarification of these \n \n1 18 C.F.R. §§ 385.211, 385.212, 385.214 (2026). \n2 PJM Interconnection, L.L.C., Reliability Backstop Procurement to Address Resource Adequacy Concerns \nStemming from Large Loads, Docket No. ER26-3380-000 (filed July 31, 2026) (RBP Filing). \n3 Proposed Tariff, Attachment DD, § 18.1(d)."},{"page":2,"startToken":241,"endToken":529,"text":"2 \n \ntwo items will ensure the peak-shaving opt-out functions as intended, giving effect to state laws \nthat contemplate demand-flexibility programs, including contracted peak shaving. \nFirst, Base requests PJM to clarify that the peak-shaving decrement is not discounted and \nwill have a 1:1 ratio; in other words, every 1 MW of peak-shaving identified by an Electric \nDistributor will result in 1 MW decremented from the Initial RBP Target, with no adjustments.  \nThis clarification by PJM—easily effectuated by the removal of the phrase “up to” in Attachment \nDD Section 18.1(d)—will allow large loads to estimate the value of a commercial contract with \npeak-shaving providers and have confidence in finalizing those commercial arrangements without \ndelay. \nSecond, Base seeks clarification from PJM that, to qualify for the peak-shaving opt-out in \nthe RBP, the deadline for any Peak Shaving Adjustment plan submitted pursuant to the \nrequirements of Attachment DD-2 will be the September 2027 deadline (to be effective for the \n2028/2029 Delivery Year), not September 2026. \nI. \nMOTION TO INTERVENE \nRule 214 permits intervention where the movant “has or represents an interest which may \nbe directly affected by the outcome of the proceeding[.]”4 \nBase meets that standard.  Base is an energy technology company that deploys distributed \nbattery storage and aggregates its resources to provide energy and grid services, along with backup \npower for residential consumers.5  Base’s interest in this proceeding is direct and concrete.  Base \nis pursuing commercial arrangements in the PJM region that depend on the peak-shaving opt-out \nestablished in section 18.1(d).  The two clarifications identified below determine whether those \n \n4 18 C.F.R. § 385.214(b)(2). \n5 Base Power in the press, available at https://www.basepowercompany.com/press."},{"page":3,"startToken":529,"endToken":857,"text":"3 \n \narrangements can participate in the opt-out. Base’s interests would not be adequately represented \nby any other party.   \nThis motion is timely filed within the intervention period established by the Commission.  \nBase respectfully requests that the Commission grant this motion to intervene with full party status, \nand reserves the right to file comments, protests, answers, and briefs in this proceeding. \nII. \nCOMMENTS IN SUPPORT AND REQUESTS FOR CLARIFICATION \nBase supports PJM’s RBP proposal and appreciates PJM’s positive engagement with \nstakeholders on the peak-shaving opt-out structure.  The success of PJM’s RBP proposal, \nparticularly the peak-shaving opt-out provision, will depend on whether its implementation can be \nharmonized with qualifying peak-shaving programs established in PJM States, including those \nenacted by statutes in both New Jersey and Virginia.  This coordination reflects the cooperative \nfederalism approach that PJM has taken in recent reforms, and Base appreciates PJM’s willingness \nto work with stakeholders on these issues.  \nBelow, Base describes how state statutes like the newly enacted NJ Data Center Fair Share \nAct (DCFSA)6 and Va. Code Ann. § 56-596.7 (2026) create avenues for Electric Distributors and \nlarge loads to reduce demand during peak periods by delivering, funding, or procuring peak-\nshaving measures from other customers.  These state programs are consistent with the RBP peak-\nshaving opt-out and can be given full effect by PJM, so long as that opt-out is appropriately \nstructured.  With the two narrow clarifications requested herein, the PJM RBP proposal and the \nstate laws will work together to their fullest, complementary potential, to the benefit of all \nstakeholders.  Base does not object to other aspects of the RBP filing. \n \n6 The DCFSA (S731/A796) was signed into law on July 7, 2026 and has not yet been printed into a chapter law.  \nN.J. P.L.2026, C.32 (July 7, 2026) (to be codified at N.J. Rev. Stat. Title 48).  The Fourth Reprint is available at \nhttps://pub.njleg.state.nj.us/Bills/2026/A1000/796_R4.PDF."},{"page":4,"startToken":857,"endToken":1158,"text":"4 \n \nA. \nPJM’s Peak-Shaving Opt-Out Recognizes and Gives Effect to Efforts By \nStates To Establish Peak-Shaving Adjustment Programs. \nPolicymakers and regulators across the country are working diligently within their \nrespective jurisdictions to address unprecedented energy demand, striving to preserve the \nreliability and affordability of energy for everyday Americans. Coordinating these overlapping \nefforts will amplify their effectiveness, to the benefit of ratepayers.  PJM’s peak-shaving opt-out \ndoes precisely this by appropriately recognizing state-authorized peak-shaving programs, in a \nmanner consistent with ordinary-course capacity-procurement auctions in PJM. Two such state-\nauthorized peak-shaving programs are emblematic of this opportunity. \nIn Virginia, Va. Code Ann. § 56-596.7 establishes a framework for “voluntary demand \nflexibility program[s]” under which large loads may partner with third parties to peak-shave in \norder to maximize or reasonably maximize “electric grid system savings and improve reliability \nfor retail electric service customers.”7 The law expressly states that under such programs, large \nloads may “secure measurable and verifiable electric load reductions from other retail electric \nservice customers during time periods of peak system demand or other events that cause strain on \nthe electric grid,”8 directly authorizing large loads to contract with, fund, or purchase peak-shaving \nmeasures from third parties under the program.  \nSimilarly, New Jersey codified its peak-shaving programs in the DCFSA, which Governor \nSherrill signed into law on July 7, 2026.9  The DCFSA establishes a demand-reduction program \nfor “data center customers [to] contract directly with a third party for, or otherwise fund, verified \n \n7 Va. Code Ann. § 56-596.7(B)(1) (utilities); § 56-596.7(C)(1) (cooperatives).  \n8 Id. § 56-596.7(A) (defining “[d]emand flexibility”). \n9 Press Release, Office of the Governor, Governor Sherrill Announces Ratepayer Relief, Signs Major Legislation on \nEnergy, Saving New Jerseyans $1B Annually (July 7, 2026), \nhttps://www.nj.gov/governor/news/2026/20260707a.shtml."},{"page":5,"startToken":1158,"endToken":1459,"text":"5 \n \ndemand flexibility by other customers on the same electric public utility system.”10  The \nGovernor’s Office described the mechanism as a program “through which a new large load offsets \nits capacity obligation by paying to reduce demand elsewhere on the system,” and characterized it \nas “the first of its kind, driving accelerated deployment of distributed energy resources paid for by \ndata centers.”11  \nThe DCFSA was drafted to operate in conjunction with PJM’s capacity market \nmechanisms, including the RBP.  The statute provides that the demand-reduction trade program \nmust be designed “for compatibility with the load forecasting methods of the regional transmission \norganization, the Peak Shaving Adjustment of the regional transmission organization, or any \nsimilar mechanism used to reduce capacity needs, so that demand reductions verified under the \nprogram are reflected in the load forecast used by the regional transmission organization to procure \ncapacity, including any capacity procured under a backstop auction or similar mechanism.”12  In \nother words, the DCFSA explicitly contemplates coordination with PJM capacity-market \nmechanisms, including a backstop auction, directing the NJ BPU and public utilities to promptly \naccept bilateral and multilateral contracts for peak-shaving services so that such peak-shaving can \nbe appropriately recognized and accounted for by the deadlines established by PJM’s RBP \nprocess.13     \n \n10 DCFSA § 1.d(4). \n11 Press Release, supra note 9. \n12 DCFSA § 1.d(4)(c). \n13 The DCFSA statute requires each electric public utility to “submit Large Load Adjustments, Peak Shaving \nAdjustments, and customer peak load contribution to the regional transmission organization,” directing its utilities to \nbe submitting entities in a manner consistent with the role that proposed Tariff, Attachment DD, section 18.1(d) \nassigns to the Electric Distributor.  Id. § 1.b(8); see also id. § 1.h (contracts will be filed with the NJ BPU and “[t]he"},{"page":6,"startToken":1459,"endToken":1749,"text":"6 \n \nB. \nBase Requests PJM Make Two Narrow Clarifications on the RBP Proposal. \nTo ensure PJM’s peak-shaving opt-out captures these benefits, Base requests that PJM \nmake two discrete clarifications to its proposal. \n1. \nClarification that the Peak-Shaving Decrement is Not Discounted \nFirst, Base asks PJM to clarify that the peak-shaving amount submitted by the Electric \nDistributor is not discounted.  Section 18.1(d) provides that the Initial RBP Target “shall be further \ndecremented . . . by up to the associated MW quantity of load that participates in a peak shaving \nadjustment program.”14 By contrast, the transmittal letter says that “the Initial RBP Target will be \ndecremented by the amount specified by the Electric Distributor,”15 which implies a 1:1 decrement \nwith no discount.  Likewise, the Tariff’s own structure supports a reading that no discount was \nintended.  The preceding sentence of section 18.1(d) requires that an Electric Distributor’s opt-out \nrequest “shall specify the associated MW quantity of load in the zone/area that will be opted-out” \n(emphasis added). \nClarification on the value of the opt-out decrement is needed to allow commercial \narrangements to be finalized.  Otherwise, Base and other providers that seek to facilitate peak-\nshaving cannot determine what decrement a given amount of peak-shaving will produce. And \nwithout that certainty, peak shaving arrangements with large load counterparties cannot be priced \nor executed.  This clarification can be easily effectuated by removing the phrase “up to” in \nproposed Tariff, Attachment DD, Section 18.1(d), as follows: “shall be further decremented . . . \n \nboard shall accept the contract unless the board finds its terms are inconsistent” with certain other provisions of the \nlaw). \n14 Proposed Tariff, Attachment DD, § 18.1(d) (emphasis added). \n15 RBP Filing, Transmittal Letter at 46 (emphasis added)."},{"page":7,"startToken":1749,"endToken":2094,"text":"7 \n \nby up to the associated MW quantity of load that participates in a peak shaving adjustment \nprogram.”   \nPlacing this clarification in the Tariff rather than in the Manuals is also consistent with how \nthe Commission has treated the Peak Shaving Adjustment.  When the Commission accepted the \nPeak Shaving Adjustment in 2019, it directed PJM to move the terms and conditions of that \nprogram out of Manual 19 and into the Tariff, which is how Attachment DD-2 was created.16   \n2. \nClarification that the Deadline to Meet Attachment DD-2’s Requirements  \n  \nwill be September 2027 \n \nSecond, Base seeks clarification from PJM that, to qualify for the peak-shaving opt-out in \nthe RBP, the deadline for any Peak Shaving Adjustment plan submitted pursuant to the \nrequirements of Attachment DD-2 will be September 2027 (to be effective for the 2028/2029 \nDelivery Year), not September 2026.  This is a narrow clarification necessary to align the RBP \nopt-out with the procedural deadlines already established in Attachment DD-2.   \nSection 18.1(d) conditions the peak-shaving opt-out on programs “that are codified in state \nlaw and that also meet the requirements of Tariff, Attachment DD-2.”17  The challenge is that \nAttachment DD-2 was designed for a different purpose on a different schedule,18 and several of \nits requirements cannot be satisfied in time for the opening of the RBP bid window if not clarified.  \n \n16 PJM Interconnection, L.L.C., 167 FERC ¶ 61,114, at P 55 (2019) (directing PJM to incorporate the Peak Shaving \nAdjustment plan requirements of PJM Manual 19, Attachment D into the Tariff); PJM Interconnection, L.L.C., \nCompliance Filing, Docket No. ER19-511-002 (filed May 30, 2019); Letter Order, Docket No. ER19-511-002 (June \n26, 2019) (accepting Tariff, Attachment DD-2). \n17 Proposed Tariff, Attachment DD, § 18.1(d). \n18 Attachment DD-2 was originally crafted to feed a forecast adjustment into PJM’s load forecast for the annual \nauction cycle.  PJM Interconnection, L.L.C., 167 FERC ¶ 61,114, at P 9 (2019) (reciting PJM explanation that the \nPeak Shaving Adjustment is primarily an amendment to PJM’s existing load forecasting methodology)."},{"page":8,"startToken":2094,"endToken":2343,"text":"8 \n \nThe DCFSA, for example, was signed into law on July 7, 2026, so even though the law expressly \ncontemplates participation in the RBP, a September 2026 deadline would be challenging to meet.19 \nThis clarification would require no Tariff change and arguably follows from Attachment \nDD-2 itself, which ties the September deadline to the “next PJM load forecast update.”  The RBP \nruns on the already-published 2026 PJM Load Forecast.20  So a September 2026 plan would feed \na forecast that has no bearing on the Initial RBP Target; meanwhile, a September 2027 plan is the \nplan that would apply to the 2028/2029 Delivery Year. Confirming the September 2027 deadline \nwould preserve Attachment DD-2’s established procedural framework while providing qualifying \nstate-authorized peak-shaving programs a workable path to participate in the RBP, as contemplated \nby Section 18.1(d) and state law. \n \n \n \n19 For example, Attachment DD-2 operates on the annual load forecast cycle, but the PJM RBP opt-out operates on \nthe already-published 2026 PJM Load Forecast.  Likewise, a peak shaving program seeking a load forecast \nadjustment must file its plan with PJM no later than ten business days before September 30 in order to be reflected \nin the next PJM load forecast, and eligibility is limited to load reduction programs governed by a tariff or order \napproved by the RERRA.  Attachment DD-2, section A. \n20 See Croop Aff. ¶ 46 (initial allocation based on Load Adjustments “as set forth in PJM Table B9b from the 2026 \nPJM Load Forecast”)."},{"page":9,"startToken":2343,"endToken":2426,"text":"9 \n \nIII. \nCONCLUSION \nFor the foregoing reasons, Base respectfully requests that the Commission grant its motion \nto intervene with full party status.  If PJM makes the requested clarifications above, Base requests \nthat the Commission approve PJM’s RBP proposal in its entirety. \nDated: August 21, 2026 \nRespectfully submitted, \n \nZina Bash \nChief Legal Officer \nBase Power, Inc. \n205 E Riverside Dr. \nAustin, TX 78704 \nzina@basepowercompany.com \n \n/s/ Qingliu (Mary) Yang \nQingliu (Mary) Yang \nJuni PLLC \n214-449-8699 \nmary@junienergy.com \n \n \nCounsel for Base Power, Inc."},{"page":10,"startToken":2426,"endToken":2478,"text":"10 \n \nCERTIFICATE OF SERVICE \nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service list compiled by the Secretary of the Commission in this \nproceeding. \nDated: August 21, 2026 \n \n/s/ Qingliu (Mary) Yang \nQingliu (Mary) Yang \nJuni PLLC \n214-449-8699 \nmary@junienergy.com"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":1081,"startToken":0,"endToken":408},{"p":2,"at":1081,"title":"I. MOTION TO INTERVENE","method":"printed heading","endPage":3,"endAt":414,"startToken":408,"endToken":589},{"p":3,"at":414,"title":"II. COMMENTS IN SUPPORT AND REQUESTS FOR CLARIFICATION","method":"printed heading","endPage":4,"endAt":5,"startToken":589,"endToken":858},{"p":4,"at":5,"title":"A. PJM’s Peak-Shaving Opt-Out Recognizes and Gives Effect to Efforts By","method":"printed heading","endPage":6,"endAt":5,"startToken":858,"endToken":1460},{"p":6,"at":5,"title":"B. Base Requests PJM Make Two Narrow Clarifications on the RBP Proposal.","method":"printed heading","endPage":9,"endAt":5,"startToken":1460,"endToken":2344},{"p":9,"at":5,"title":"III. CONCLUSION","method":"printed heading","endPage":10,"endAt":6,"startToken":2344,"endToken":2427},{"p":10,"at":6,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":10,"endAt":338,"startToken":2427,"endToken":2478}]}