{"document":{"slug":"rec-20260821-5192","title":"Comments of New Jersey Board of Public Utilities in response to PJM Interconnection, L.L.C.’s Reliability Backstop Procurement proposal","issued":"2026-08-21","accession":"20260821-5192","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"New Jersey Board of Public Utilities","kind":"comments","file":"sources/filings/text/20260821-5192_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5192","tier":"record","sha256":"a7a03785f2bf814d03d29c4273c63f1c48ffe2f1b1bd940c76a7aef5c6f59cff","pages":9,"tokens":2332,"emptyPages":[],"textThemes":["credit","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":274,"text":"1 \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, LLC  \n  \n  \n) \n)  \n   \n   \n   \n                                 \n                     Docket No. ER26-3380-000\n                                         \n  \n \nCOMMENTS OF THE NEW JERSEY BOARD OF PUBLIC UTILITIES \nThe New Jersey Board of Public Utilities (“Board”) files these comments in response to \nPJM Interconnection, L.L.C.’s (“PJM”) revisions to the PJM Open Access Transmission Tariff \n(“Tariff”) and the Reliability Assurance Agreement Among Load Serving Entities to establish the \nReliability Backstop Procurement (“RBP”).  The Board appreciates the haste with which this \nproposal was filed and underscores the importance of moving forward with this proposal amid \nsignificant regional resource adequacy concerns.  While there are certain elements to the RBP that \nthe Board would have pursued differently, the Board overall supports PJM’s proposal. \nI. \nThe RBP Addresses System Reliability Needs \nFirst, the Board supports the Tariff revisions to add the targeted one-time procurement RBP \nstarting in 2026, rather than relying on existing Tariff language which states that the Reliability \nBackstop Auction (“RBA”) will be triggered only after three Base Residual Auctions (“BRA”) \nclear sufficiently short of capacity.  The BRAs for the 2027/2028 and 2028/2029 Delivery Years \n(“DY”) have cleared short by 6.61 and 6.8 GW,2 respectively, and this deficit is only predicted to \n \n1 PJM Auction Procures 134,479 MW of Generation Resources, PJM Interconnection, L.L.C., 1 (Dec. 17, 2025), \nhttps://www.pjm.com/-/media/DotCom/about-pjm/newsroom/2025-releases/20251217-pjm-auction procures-\n134479-mw-of-generation-resources.pdf [https://perma.cc/A89W-W99B]. \n2 2028/2029 Base Residual Auction Report, PJM Interconnection, L.L.C., 3 (July 14, 2026), https://www.pjm.com/-\n/media/DotCom/markets-ops/rpm/rpm-auction-info/2028-2029/2028-2029-bra results-report.pdf \n[https://perma.cc/A53K-TXXY]."},{"page":2,"startToken":274,"endToken":634,"text":"2 \n \ngrow:  PJM predicts summer peak load increases of 65.7 GW over the next 10 years and 96.7 GW \nover the next 20 years.3  Meanwhile, significant barriers to new supply resources remain.  New \nsupply developers face higher overall costs and market risks due to a variety of factors, including \nuncertainty surrounding future load forecasts and federal policy, expected capacity market reforms, \nexisting supply chain constraints, siting and permitting challenges, and a recently backlogged \ninterconnection queue.  PJM itself has found that new ideas and reforms are needed to bring new \nsupply to the market – the current market structures and one-year price signal no longer provide \nrevenue streams that are sufficiently high or dependable for many new supply developers in this \nenvironment.4   \nThe Board similarly issued a report on August 12 noting that the current capacity market \ncould not bring new supply to the market and provide reliability at lowest cost for ratepayers.5  \nAmong the conclusions and recommendations in the report, the Board noted that (1) data center \nlarge loads are the primary causes of the supply shortfall and should be required to pay for the new \ngeneration they require,6 and (2) long-term contracts can help provide price certainty for new \ninvestments in generation.7  Therefore, among the myriad reforms PJM is pursuing to address this \nsupply-and-demand imbalance, the RBP addresses an important gap.  \nThe best way to manage the needs for large loads is through bilateral contracts – that way, \nthe large loads can work directly with developers to manage the costs and risks of building new \n \n3 PJM Interconnection, L.L.C., 2026 Load Forecast Report Tables tbl.  B1 (2026), https://www.pjm.com/-\n/media/DotCom/planning/res-adeq/load-forecast/2026-load-report tables.xlsx. \n4 See generally, PJM Interconnection, L.L.C., Powering Reliability Through Market Design (May 2026) (“PJM’s \nMarket Report”), https://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2026/20260506-\npowering-reliability-through-market-design.pdf. \n5 N.J. Bd. of Pub. Utils., An Investigation of PJM’s Capacity Market (Aug. 2026), \nhttps://nj.gov/bpu/pdf/reports/AN_INVESTIGATION_OF_PJMs_CAPACITY_MARKET_FINAL_8.12.26.pdf \n6 Id. at ii, 64. \n7 Id. at ii, 66."},{"page":3,"startToken":634,"endToken":951,"text":"3 \n \nsupply.  Bilateral contracts between new large loads and new supply resources are the most \neffective way to protect ratepayers from costs and risks associated with load growth from data \ncenters.  Therefore, the Board appreciates how PJM’s RBP proposal encourages bilateral contracts \nbetween incoming large loads and qualifying new supply resources.  This includes PJM’s retention \nof Charles River Associates to facilitate confidential and bilateral matchmaking, the offset of new \nlarge loads that have procured capacity from the initial RBP target, coupled with an allocation of \nRBP costs only to those that have not procured their own capacity, and the broader eligibility of \nresources that qualify for bilateral contracts compared to the RBP.  The Board hopes the bilateral \nmatchmaking process underway meaningfully reduces the procurement target and subsequent \ncosts from the RBP, as these contracts help insulate customers from the risks and costs attributable \nto these new large loads.   \nThe RBP’s centralized procurement terms, which provide a price commitment of up to 15 \nyears for qualified new supply resources, will also help attract new supply resources.  The Board \nsupports PJM’s proposed Tariff revisions to conduct this backstop before waiting for an additional \nBRA to clear short.  The Board also supports assigning the costs of this procurement to zones in \nproportion to their expected large load additions.  This is necessary to ensure large loads can be \nmade responsible for the costs, while recognizing that states have ultimate authority over retail \ncost allocations.  This RBP effort is a step in the right direction today – but, in the long term, PJM \nmust continue to coordinate with stakeholders to develop robust reforms in its Powering Reliability \nThrough Market Design workstream.   \nThe above support does not come without some concerns worth noting, however.  The \nBoard understands PJM’s reasoning for basing the central procurement target amount on the \n2028/2029 BRA shortfall of 6.8 GW, despite the Joint Electric Distribution Companies and Data"},{"page":4,"startToken":951,"endToken":1269,"text":"4 \n \nCenter Coalition proposal—the only proposal to receive more than two-thirds sector-weighted \nmember support—recommending a subscription-based procurement target.  To be clear, because \na significant portion of this load growth is due to data center demand, the Board thinks that a \nsubscription-based or “buy-bid” central procurement amount would have been better able to \nprotect ratepayers from costs and risks associated with load growth from data centers and their \nuncertain load forecasts, as the procurement amount would be directly attributable to distinct data \ncenters.  Therefore, the procurement target could be directly aligned to interested large loads, and \ncosts would be allocated with more accuracy to these incoming large loads.  However, the Board \nrealizes that this would require additional time before the backstop could be initiated and \nunderstands the importance of running this backstop procurement promptly.  The Board will work \nclosely with other state entities and utilities to ensure that these costs are properly allocated to \nincoming data centers.   \nFurthermore, while the Board appreciates many of the requirements and the standardization \nof eligible supply resources for the RBP, the Board would have liked to see more flexibility for the \nparticipation of demand response (“DR”) and distributed energy resources (“DER”).  DR and DER \nresources are intrinsically very different from generating resources, and requiring these resources \nto provide “customer agreements or binding commitments with identified locations and customer \nnames” that can serve the MW for 15 years is very onerous.8  DR and DER resources build their \nbusiness models expecting customer turnover; it is not reasonable to expect these resources to pre-\nspecify customers for the RBP contract period.  The Board thinks PJM should have pursued more \nflexible options for these resources – allowing these resources, for instance, to replace contracted \ncustomers to satisfy the RBP obligation.  The Board recommends more flexibility for DR and DER \n \n8 PJM Interconnection, L.L.C., Initiating Filing at 74, Docket No. ER26-3380 (July 31, 2026)."},{"page":5,"startToken":1269,"endToken":1664,"text":"5 \n \nresources to encourage greater participation and unlock demand-side tools for the region in an \nenvironment where they are sorely needed.  \nThe Board also has concerns about the opportunity for market power to arise in PJM’s \nselection process.  Specifically, projects with an earlier Delivery Year may be overly favored over \ncost concerns.  In PJM’s centralized procurement, resources with earlier Delivery Years are chosen \nfirst, up to the maximum willingness-to-pay cap of $555/MW-day UCAP; however, if these \nresources lead to a higher average price in early DYs and don’t initially clear, they can clear later \nin the process if lower-cost resources selected in later DYs create “room in the budget” to select \nthese higher-cost, earlier-DY offers.  PJM, stakeholders, and the Federal Energy Regulatory \nCommission (“FERC”) should monitor the results of the RBP to ensure it produces an efficient \noutcome with just and reasonable results.  Similarly, the Board has concerns that the pay-as-bid \nmarket structure, compared to PJM’s uniform clearing price in the capacity market, would create \ninefficient market outcomes or allow for market manipulation.  PJM and FERC must monitor, as \nmuch as possible, how this structure affects auction results.9   \nFinally, the Board has concerns about the collateral requirements for LSEs.10  The Board \nappreciates PJM’s efforts intended to protect consumers from the risk of stranded RBP costs.  \nHowever, the Board is concerned that the size of the collateral requirements may make it difficult \nfor LSEs to secure the required collateral.  In theory, an LSE would pass on the collateral costs to \n \n9 PJM lists the benefits of a pay-as-bid model in its filing to support its proposed auction structure.  However, this \nmarket design does not inherently provide lower costs to customers, as the PJM filing suggests.  In a pay-as-bid \nmarket structure, developers are unlikely to bid at their marginal cost, for they would not make a profit.  Instead, \ndevelopers are expected to bid strategically by submitting offers near an estimated market-clearing price, with larger \nmarket participants often having more resources to forecast the clearing price and bid at or near those forecasts.  \nUltimately, however, it will be difficult to assess the competitiveness and efficiency of this RBP under the pay-as-bid \nstructure because stakeholders will not have access to the data and models developers used to set their final bid \nprice.   \n10 PJM Interconnection, L.L.C., Initiating Filing at 114, ER26-2563 (July 31, 2026)."},{"page":6,"startToken":1664,"endToken":1972,"text":"6 \n \nthe large load, but there may need to be additional forcing mechanisms in restructured states where \nretail choice and default service has been the assumed retail system.  This type of collateral \nrequirement will put pressure on the retail-jurisdictional authorities to ensure the collateral \nobligation does not fall upon ratepayers.  While the Board does not provide a solution at this time, \nthe Board and stakeholders could have used additional time to build a more thoughtful collateral \nsystem.   \nThe Board hopes that the RBP will succeed and attract new resources to the PJM system \nto address large load growth.  The Board also hopes that PJM, FERC, and all stakeholders will \ntake the lessons learned from this process and the results to inform future market reform efforts. \nII. \nThe RBP Opt-Out and Needed Clarification \nThe Board appreciates PJM’s opt-out provisions that complement certain state laws.  New \nJersey recently passed the Data Center Fair Share Act (“Act”) to help protect customers from the \nload impacts of new data centers in the state.11  The Act aims to provide data centers the \nopportunity to offset their load contributions through voluntary load reduction agreements with \nthird parties.  Under one such available program specifically mentioned in the Act, the peak \nshaving adjustment (“PSA”), as detailed in PJM’s tariff under Attachment DD-2, a zone’s load can \nbe offset by committed load reduction programs.  The Act notes that data center participation in \nsuch programs should relieve the data center from RBP costs and other related obligations. \n \nPJM’s RBP proposal provides an opt-out that allows electric distribution companies \n(“EDC”) to decrement their associated MW quantity of load that participates in PSA programs.  \nThis opt-out appears aimed at complementing and working with the Act, and the Board appreciates \nPJM’s consideration.  However, the Board thinks clarifications are needed to ensure the option is \n \n11 P.L. 2026, c.32."},{"page":7,"startToken":1972,"endToken":2202,"text":"7 \nworkable within the RBP timeline.  Namely, it is currently unclear whether the RBP opt-out \nsubmission requires full compliance with Attachment DD-2 in time for the centralized \nprocurement or whether program details under Attachment DD-2 can be accomplished later.  PJM \nshould clarify that planned PSAs can qualify for the opt-out – MW for MW – if they are being \npursued under requirements codified in state law even if program details are not yet finalized.  The \nEDC, New Jersey, and related stakeholders would then have time to fully develop their PSA \nprograms in advance of the 2028/2029 Delivery Year and would submit such final details when \nneeded under Attachment DD-2, which would be September 2027.  New Jersey looks forward to \nparticipating in this effort and hopes that participation will be workable within the RBP deadlines. \nThese types of efforts can help unlock efficient ways to incorporate large loads into the grid, and \nthe Board truly appreciates PJM’s efforts to accommodate these state efforts. \nIII. \nConclusion   \nThe Board thinks PJM’s proposal strikes a good balance between prioritizing both least-\ncost resources and those that can interconnect to the grid most quickly.  Granted, if the Board had \ndesigned the RBP to its own specifications, it may have made some reasonable changes. \nNonetheless, the Board ultimately supports PJM’s RBP proposal and the Board recommends \napproving it so PJM can run the central procurement in 2026."},{"page":8,"startToken":2202,"endToken":2256,"text":"8                   \n \nMICHAEL ZUCKERMAN \nACTING ATTORNEY GENERAL  \nOF NEW JERSEY  \nBy: /s/ Steven Chaplar  \nDeputy Attorney General \nDepartment of Law and Public Safety \nDivision of Law \nP.O. Box 112 \nTrenton, NJ 08625 \nSteven.chaplar@law.njoag.gov  \nAttorneys for the New Jersey Board of \nPublic Utilities    \nDated: August 21, 2026 \nTrenton, New Jersey   \nRespectfully,"},{"page":9,"startToken":2256,"endToken":2332,"text":"9 \n \nCERTIFICATE OF SERVICE \nI hereby certify that, on this 21st day of August, 2026, I have caused the foregoing \ndocument to be served upon each party designated on the official service list compiled by the \nSecretary in this proceeding, by email. \nBy: /s/ Steven Chaplar \nSteven Chaplar \n \n \n \n \n \n \nDeputy Attorney General \n \n   \n \n \n \n \nNew Jersey Office of the Attorney General \nDepartment of Law & Public Safety  \nP.O. Box 112  \nTrenton, New Jersey 08625  \nSteven.chaplar@law.njoag.gov"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":964,"startToken":0,"endToken":120},{"p":1,"at":964,"title":"I. The RBP Addresses System Reliability Needs","method":"printed heading","endPage":6,"endAt":792,"startToken":120,"endToken":1789},{"p":6,"at":792,"title":"II. The RBP Opt-Out and Needed Clarification","method":"printed heading","endPage":7,"endAt":1028,"startToken":1789,"endToken":2133},{"p":7,"at":1028,"title":"III. Conclusion","method":"printed heading","endPage":9,"endAt":5,"startToken":2133,"endToken":2257},{"p":9,"at":5,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":9,"endAt":492,"startToken":2257,"endToken":2332}]}