{"document":{"slug":"rec-20260821-5206","title":"Comments of Google LLC re PJM Interconnection, L.L.C.’s Reliability Backstop Procurement Proposal","issued":"2026-08-21","accession":"20260821-5206","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"Google LLC","kind":"comments","file":"sources/filings/text/20260821-5206_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5206","tier":"record","sha256":"c7048f2a68af2b1211dd13c9f1e9ed0ee00d1d06143601843c9447745cb2034c","pages":13,"tokens":3641,"emptyPages":[],"textThemes":["adequacy","cost","flex"]},"pages":[{"page":1,"startToken":0,"endToken":318,"text":"UNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \nPJM Interconnection, L.L.C. \n) \n)\n)\nDocket No. ER26-3380-000 \nCOMMENTS OF GOOGLE LLC  \nPursuant to Rule 211 of the Rules of Practice and Procedure of the Federal Energy \nRegulatory Commission (“Commission”),1 Google LLC (“Google”) hereby submits these \ncomments regarding PJM Interconnection, L.L.C.’s (“PJM”) Reliability Backstop Procurement \n(“RBP”) Proposal.  Google commends PJM for taking steps to ensure reliability, which must \nremain its first priority.  Nevertheless, while RBP may help maintain near-term resource adequacy, \nGoogle urges PJM to focus future efforts on reforms that incentivize new large loads to procure \nand bring their own new generation rather than relying on an interim, one-time solicitation, like \nRBP.  As explained below, Google believes that this bilateral contracting will do more to procure \nthe necessary supply—after all, there is no guarantee that RBP will procure enough GW to cover \nthe shortfall2—and do so in a way that meets future demand on a durable, forward-looking basis, \nrather than relying on measures that address only previously identified reliability needs.  A bilateral \napproach also does more to ensure the new supply meets the needs and preferences of new large \nload customers, unlocking the economic growth benefits that they can provide.  And it’s not just \n1 18 C.F.R. § 385.211 (2026). \n2 See PJM Interconnection, L.L.C., Transmittal, Docket No. ER26-3380-000, at 26 (filed Jul. 31, 2026) \n(“Transmittal”) (framing the RBP as a design intent rather than a guarantee); id. at 34 (recognizing that “the RBP aims\nto procure RBP Resources for up to a 15-year fixed term.” (emphasis added)); id. at 79 (acknowledging that the RBP \nmay “clear short of the Final RBP Target”); id. at 125 (“resetting the [RBA] to the 2032/2033 Delivery Year recognizes \nthat, even if the RBP successfully procures sufficient capacity to cover the shortfall, RBP Resource will need time to \nbecome operational.”)."},{"page":2,"startToken":318,"endToken":630,"text":"-2- \nGoogle that sees the promise of new large loads bilaterally contracting for new generation.  During \nthe RBP stakeholder process, in response to a Request for Information released by PJM, a \n“[m]ajority of parties expressed interest and preference to a bilateral contract over a central \nprocurement.”3  Respondents to the Request for Information spanned the large load, supply, and \nutilities sectors.4\nI.\nWHO WE ARE \nGoogle’s mission is to organize the world’s information and make it universally accessible \nand useful.  AI is critical to that mission.  Data centers necessary to serve Google’s customers \nconsume a large amount of electricity and require reliable electric service to operate.  As Google’s \nbusiness grows, so too does its demand for reliable, affordable, and clean electricity. \nII.\nCOMMENTS \nGoogle recognizes that the unprecedented load growth that PJM is currently experiencing \nis both a tremendous opportunity and a complex challenge.  The load growth reflects the \ndynamism of the nation’s technology sector, which can drive economic growth, create jobs, and \nsignificantly expand the tax base of the areas in which that growth occurs.  Those are real, \nverifiable benefits that accrue across the local, state, and national levels, and should be available \nto the communities that want to host the necessary digital and energy infrastructure.   \nBut those economic benefits must not come at the cost of sacrificing the reliability and \naffordability to which customers in those communities, and PJM more broadly, are rightly \naccustomed.  RBP may help protect against that result in the short term by procuring additional \n3 PJM Interconnection, L.L.C., Reliability Backstop Procurement Design, at 3 (May 27, 2026), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260527/20260527-item-05---reliability-\nbackstop-procurement-design---pjm-presentation---updated.pdf. \n4 See Charles River Associates, PJM Reliability Backstop RFI Summary, at 3 (May 27, 2026), \nhttps://www.pjm.com/-/media/DotCom/committees-groups/cifp-rbp/2026/20260527/20260527-informational-only--\n-reliability-backstop-rfi-summary---charles-river-associates.pdf."},{"page":3,"startToken":630,"endToken":962,"text":"-3- \ngeneration to ensure reliability and allocating the costs of that additional generation to the \nentities that caused the need for it, namely the new large loads that have not secured sufficient \ncapacity to offset their demand.  Anything else would be unjust and unreasonable and manifestly \ncontrary to the principles that Google has consistently supported through its Capacity \nCommitment Framework (“CCF”), as well as the White House’s Ratepayer Protection Pledge \nand the Statement of Principles from the National Energy Dominance Council and the PJM \nGovernors.5  But the Commission alone cannot ensure that result, as PJM itself acknowledged in \na letter to the region’s governors in May.  The retail level is where the rubber meets the road.  \nIndeed, as PJM stated, “if states have not established frameworks to appropriately allocate costs \nto new data center loads, it is unclear to which customers those costs would be assigned,” and “it \nappears possible to PJM that these costs will be allocated to other consumers.”6  To date, not all \nPJM states have taken comprehensive steps to establish and implement these contemplated \nframeworks across PJM’s diverse footprint.  If RBP is accepted, the states must take up the \nmantle and ensure that the costs of RBP are allocated in a manner that is just and reasonable and \nconsistent with the Ratepayer Protection Pledge.  Google stands ready to engage in that process \nto achieve that result. \nAnd while RBP may be a reasonable response to PJM’s current circumstances, a more \npermanent, long-term framework is necessary.  Constantly shifting, unpredictable regulatory \nconstructs undermine the investor confidence necessary to support the multi-billion-dollar \ninvestments in new capacity needed to ensure reliability and affordability over the long term.  \n5 \nGoogle, \nLLC, \nThe \nCapacity \nCommitment \nFramework, \nhttps://www.gstatic.com/marketing-\ncms/44/6b/dbb3456040b486886bb8aff87588/the-capacity-commitment-framework-ccf-jan.pdf.  \n6 Letter from David E. Mills, President and CEO, PJM to Governors of PJM States, PJM Interconnection, \nL.L.C. \n(May \n5, \n2026), \nhttps://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-\ndisclosures/2026/20260520-pjm-board-letter-to-several-govs-re-reliability-backstop-procurement.pdf."},{"page":4,"startToken":962,"endToken":1254,"text":"-4- \nThat is particularly true for regulatory changes that call into question or cast doubt upon \ncontracts, such as firm electric service agreements or bilateral contracts between generation and \nload, which were entered into in reliance on the rules in effect at the time of execution.  Rather \nthan accepting constant change and uncertainty, the Commission, PJM, and all stakeholders \nshould focus on developing the stable, predictable investment conditions that will facilitate the \ninvestments needed to extricate PJM from its present resource adequacy shortfall and maintain \nresource adequacy in the long-term.   \nFinally, Google also believes strongly that new capacity requires corresponding \ninvestments in the transmission infrastructure necessary to ensure that that capacity can be \ninterconnected promptly and used to serve load reliably.  Google has been transparent with \nutility partners about its plans for demand growth across PJM for years, including by signing \nlong-term contracts with utilities that provide clear growth projections and associated ramp rates.  \nYet the development of the energy infrastructure needed to accommodate that load growth and \nthe corresponding new capacity needed to protect other ratepayers has lagged badly behind.  \nWhile Google is prepared to bear the costs appropriately attributable to its growth, Google is not \nin a position to develop that transmission infrastructure unilaterally.  Accordingly, Google urges \nPJM not to lose sight of the need to proactively develop the transmission infrastructure that is \ncritical to maintaining reliability and affordability.    \n1. A Viable Long-Term Solution to PJM’s Capacity Shortfall is a Bring Your Own \nNew Capacity Framework that Protects Existing Ratepayers from Cost Shifts and \nStranded Asset Risk  \nGoogle has long advocated for the principle that new large loads should pay for the costs \nassociated with the increase in demand that they are driving and the strain that puts on existing"},{"page":5,"startToken":1254,"endToken":1570,"text":"-5- \ninfrastructure.  The CCF that Google has advocated for at the state level7 and the “Bring Your \nOwn New Capacity” (“BYONC”) framework that Google has advocated for at the federal level \nboth reflect that principle. \nAt the federal level, Google has consistently argued that new large loads must bring their \nown new generation to support the demands they place on existing electrical infrastructure, \nwhere existing structures, like the Reliability Pricing Model (“RPM”), have not secured adequate \nnew supply.8  Although not a silver bullet, requiring new large loads that interconnect to the grid \nto secure their own capacity is the single most important mechanism for shielding existing \ncustomers from adverse rate impacts of those new large loads.  Indeed, from the outset of PJM’s \nfirst Critical Issue Fast Path (“CIFP”) focused on large load issues, Google has supported this \nconcept, including through a BYONC framework with an accelerated pathway for new \ngeneration and new load to interconnect to the transmission system.9\nBYONC is the centerpiece of Google’s own procurement philosophy.  Google strives to \nserve every new MW of data center load with a new MW of capacity in the same balancing \nauthority, ensuring that its new large loads do not draw down on the reserve margin financed by \nexisting customers.10  This approach enables Google to choose the right size and mix of capacity \nassets to meet its needs, which can include demand-side resources that PJM’s existing rules do \n7 See Amanda Peterson Corio, Supporting the White House Ratepayer Protection Pledge: Google's Approach \nfor Responsible Energy Growth, Google Blog (Mar. 4, 2026), https://blog.google/innovation-and-ai/infrastructure-\nand-cloud/global-network/affordability-pledge-responsible-energy-growth/. \n8 See Comments of Google, LLC, Docket No. RM26-4 (filed Nov. 21, 2025) (“Google ANOPR Comments”). \n9 Letter of Brian George, Sr. Lead of U.S. Energy Mkts, Google, LLC (Aug. 27, 2025), at 6 (“Google CIFP \nLetter”). \n10 Google CIFP Letter at 2 & n. 10."},{"page":6,"startToken":1570,"endToken":1927,"text":"-6- \nnot accommodate.11  Google’s agreements with Voltus to unlock up to 100 MW of capacity from \ndistributed energy resources in PJM12 and with Indiana Michigan Power (I&M) to leverage \ndemand response to reduce I&M’s peak load13 are examples of the type of innovative solutions \nto the capacity shortfall that BYONC enables. In addition, as a customer-driven approach, \nBYONC allows Google and other data center developers to invest in capacity solutions that can \nscale to meet projected growth, which provides a forward-looking and more durable means to \nprotect customers from the demand-driven effects of new large loads than backward-looking \nmeasures like RBP.  In short, a BYONC framework can unlock more capacity and do so in \nadvance of the identified reliability needs—a result that is better for all PJM customers.  \nThe BYONC framework is also consistent with the White House’s Ratepayer Protection \nPledge, under which companies including Google have committed to build, bring, or buy the \nnew generation and electricity needed to meet their new demand and to pay for it whether or not \nthey ultimately use it, and the Statement of Principles from the National Energy Dominance \nCouncil and the PJM Governors.14\nOn the state level, Google’s CCF is built on five key pillars that complement a BYONC \napproach:   \n11 PJM’s existing demand response rules require unlimited availability, needlessly prohibiting demand response \ncapacity from participating in the market. Given the shortfall PJM faces, it should accommodate any and all MWs that \na capacity resource or market participant can physically supply. \n12 See Michael Terrell, We’ve signed a first-of-its-kind agreement with Voltus to create a smart capacity solution \nfor \nthe \ngrid, \nGoogle \nBlog \n(Jun. \n2, \n2026), \nhttps://blog.google/company-news/outreach-and-\ninitiatives/sustainability/voltus-agreement/.  \n13 See Michael Terrell, How we’re making data centers more flexible to benefit power grids, Google Blog (Aug. \n4, \n2025), \nhttps://blog.google/innovation-and-ai/infrastructure-and-cloud/global-network/how-were-making-data-\ncenters-more-flexible-to-benefit-power-grids/.  \n14Ratepayer \nProtection \nPledge, \nThe \nWhite \nHouse \n(Mar. \n4, \n2026), \nhttps://www.whitehouse.gov/releases/2026/03/ratepayer-protection-pledge/ \n(“Ratepayer \nProtection \nPledge”); \nStatement \nof \nPrinciples \nRegarding \nPJM, \nNational \nEnergy \nDominance \nCouncil \n(Jan. \n15, \n2026), \nhttps://www.energy.gov/documents/statement-principles-regarding-pjm (“NEDC/PJM Governors’ Principles”)."},{"page":7,"startToken":1927,"endToken":2249,"text":"-7- \n1. Non-Discriminatory Applicability: Terms should apply to all new large \nloads with an expected peak demand above a certain threshold.  Regulators \nshould avoid adoption of mandatory terms for specific end uses of \nelectricity.  \n2. Long-Term Commitment: New large loads should be required to sign a \nlong-term contract that ensures that the customer commits to providing \nsufficient revenue to cover the investments made on their behalf.  \nRegulators should consider flexibility for customers to ramp into their load \nover time.  \n3. Significant Minimum Charges:  New large loads should be required to pay \ncosts of power capacity (e.g., approximated via demand charges) at a \nsufficient minimum to guard against potential cost shifting in the event that \nmetered customer demand is significantly lower than planned for.  \n4. Upfront Collateral:  To ensure financial stability of the requesting customer, \nregulators should consider the appropriate role for upfront collateral to \nprovide financial assurance to the utility that the long-term contract \nminimums can be met.  \n5. Flexible and Transparent Fees for Modifications: To protect other \nratepayers, while also maintaining reasonable flexibility for new large \nloads, regulators should consider appropriate notice periods and fees for \ncontract cancellation or capacity reduction. \nGoogle has worked with industry stakeholders to refine retail tariffs so that they \nincorporate and/or reflect the protections and principles of the CCF.  For example, Google \ncollaborated with stakeholders representing diverse interests, including I&M, the Indiana Office \nof Utility Consumer Counselor, the Citizens Action Coalition, the Data Center Coalition, and \nother large load customers to reform I&M’s Industrial Power Tariff to protect existing retail \ncustomers from stranded asset risks.  The resulting tariff, which applies to 70-MW large loads at \na single site, includes a 12-year minimum contract term, an 80 percent minimum monthly billing \ndemand tied to the customer’s contract capacity, and exit fees.15  Google helped secure a \n15 See Order of the Commission, Cause No. 46097, Ind. Util. Reg. Comm’n (issued Feb. 19, 2025)."},{"page":8,"startToken":2249,"endToken":2581,"text":"-8- \nunanimous settlement,16 which illustrates that consumer protection and energy infrastructure \ndevelopment need not be at odds.  As of July 2026, the CCF has been adopted by 12 utilities in \n11 states. \n2. The Costs of the RBP Must Be Allocated in a Manner that Complies with Cost \nCausation, the CCF, the Ratepayer Protection Pledge, and the Statement of \nPrinciples from the NEDC and the PJM Governors \nAs noted above, Google recognizes that RBP may be a reasonable response to the current \nresource adequacy shortfall, but it should not become a permanent substitute for market-driven, \nlong-term mechanisms that deliver resource adequacy at just and reasonable rates.  Indeed, Google \nis concerned that, as things stand, RBP could lead to the sort of cost shifting that Google has long \nadvocated against and that would be inconsistent with both the Ratepayer Protection Pledge and \nthe National Energy Dominance Council and PJM Governors’ Statement of Principles.17  Because \nnot all states in PJM have separate mechanisms for allocating costs directly to large loads, there is \nno way to ensure that the costs of RBP can be allocated exclusively to those that have not already \ncovered their load.  It should be incumbent on PJM to proactively coordinate with states to ensure \nthat they have the retail mechanisms in place to properly allocate to new large loads the costs that \nRBP would impose.   \nTo that end, Google applauds and supports the collaborative effort announced by the \nVirginia State Corporation Commission (“VA SCC”) and the Data Center Coalition (“DCC”) to \ndevelop model state tariff provisions addressing the retail allocation of RBP costs, among other \nnecessary criteria (e.g., geographic matching of load and supply).  Such provisions are designed \nto assign RBP costs to the large load customers whose demand causes the need for those \n16 See Ind. Mich. Power Co., Cause No. 46097, Settlement Testimony of Justin B. Farr, at 2-5 (filed December \n4, 2024) (“Farr Settlement Testimony”). \n17 Ratepayer Protection Pledge; NEDC/PJM Governors’ Principles at 1."},{"page":9,"startToken":2581,"endToken":2882,"text":"-9- \nprocurements.  That is a necessary step to protect residential and existing commercial and \nindustrial customers from cost shifts.18  Google is committed to participating in that effort and \ndoing everything it reasonably can to help ensure adequate protections are in place, building on \nour proven track record of advancing responsible grid solutions.  In addition, given the importance \nof those efforts and the States’ exclusive authority over the retail cost allocation mechanisms, \nGoogle urges PJM to be prepared to accommodate the needs of the States, ensuring that they have \nthe information that they need and the costs are allocated on timelines that consider and reflect \nstate retail ratemaking processes.   \n3. PJM Must Make Progress to Address the Additional Factors Contributing to the \nCurrent Resource Adequacy Shortfall \nReforms that require new large loads to secure their own new capacity are a critical element \nof ensuring reliability and affordability.  Yet they are only part of the answer.  As Google has \nconsistently maintained, one of the chief barriers to the integration of new large loads in a manner \nthat does not undermine affordability and reliability are long interconnection timelines and the \n“[t]erawatts of new generation capacity [that] are stuck in interconnection queues because \ninadequate transmission infrastructure” renders interconnection too slow, too expensive, or both.19\nNew large loads cannot bring forth new capacity resources if those resources’ interconnection to \nthe transmission system is stymied or delayed due to unpredictable—and often high—network \nupgrade costs or delays in identifying or developing that infrastructure. \n18 Letter of Kelsey Bagot, Chair of Va. State Co. Comm’n and Josh Levi, President & Chief Exec. Off. of Data \nCtr. \nCoal. \n(Jun. \n30, \n2026), \nhttps://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/public-\ndisclosures/2026/20260630-va-scc-and-data-center-coalition-letter-re-cifp-connect-manage-reliability-backstop-\nprocurement.pdf (“VA SCC and DCC Letter”). \n19 Google ANOPR Comments at 3."},{"page":10,"startToken":2882,"endToken":3217,"text":"-10- \nFurther, PJM’s existing rules also unnecessarily limit the ability of new storage resources \nto use Surplus Interconnection Service (“SIS”) to provide additional capacity, even where Capacity \nInterconnection Rights (“CIRs”) at the same point of interconnection are underutilized.  Where \nstorage is added to an existing inverter-based resource, PJM requires the resources to operate as a \nsingle hybrid resource for the storage to access those CIRs, which can significantly limit the \ncommercial viability of the arrangement.20  And where storage is added to a non-inverter-based \nresource, such as a gas generator, PJM’s mixed-technology facility rules do not permit the storage \nresource to use those CIRs to increase the facility’s unforced capacity (“UCAP”) contribution at \nall.  \nThese barriers could be addressed through a relatively straightforward rule change allowing \nan existing resource with underutilized CIRs to allocate a portion of those rights to a new resource \ninterconnecting through SIS.  Because the surplus resource must be studied before receiving SIS, \nPJM can identify and impose any necessary restrictions through that process to address reliability, \noperational, or market-power concerns.  Such a reform could unlock significant amounts of \nadditional capacity from storage using existing interconnection capability and allow that capacity \nto come online more quickly. \nGoogle intends to work with PJM and its stakeholders to address these barriers promptly. \nGoogle is not asking the Commission to resolve these issues in this proceeding but respectfully \nrequests that the Commission encourage PJM to pursue reforms that make more efficient use of \nexisting interconnection capability as part of its ongoing efforts to address the region’s resource \n20 See PJM Interconnection, L.L.C., Problem/Opportunity Statement: Hybrid Resources Market Model Selection\n(Aug. 5, 2026), https://www.pjm.com/-/media/DotCom/committees-\ngroups/committees/mic/2026/20260805/20260805-item-04-1---hybrid-resources-market-model-selection---problem-\nstatement.pdf (storage resources cannot obtain capacity resource status through the surplus interconnection process \nunless it becomes a hybrid resource, which presents “potentially insurmountable challenge[s] . . . and limit[s] SIS as \na pathway for PJM to obtain much-needed capacity that can come online more rapidly.”)."},{"page":11,"startToken":3217,"endToken":3500,"text":"-11- \nadequacy challenges.  If these barriers cannot be addressed expeditiously through the stakeholder \nprocess, further Commission attention may be warranted. \nAlthough Google recognizes the significant progress that PJM has made and continues to \npursue on interconnection reform, these issues remain a major reason why, at the moment, supply \nis not keeping up with demand.  Resolving that imbalance also requires coordinated, holistic \ntransmission planning processes that reflect the growing demands placed on the grid by both new \ndemand and new supply.  Given the scale, pace, and volume of large load interconnection requests \nas well as the corresponding scale, pace, and volume of new generator interconnection requests—\nboth of which contribute significantly to the need for new transmission infrastructure—\ntransmission planners must have a realistic picture of the generators and large loads planning to \ninterconnect to the transmission grid so that they can develop the transmission system that \naccommodates both sides of the supply and demand equation.  Only then will PJM have the \ninfrastructure foundation needed to maintain resource adequacy at just and reasonable rates and \ncapitalize on the economic opportunity that load growth presents without succumbing to its \nchallenges.   \nIII.\nCONCLUSION \nPJM is right to focus on ensuring reliability and affordability.  However, a more enduring \nstructural approach is preferable to perpetual reliance on RBP or similar stopgap mechanisms.  \nBYONC frameworks can unlock more capacity, do so in advance of the relevant reliability needs, \nand automatically ensure that the costs of new demand are borne by the entities that cause those \ncosts.  That is a much better result for PJM and all its stakeholders.  Accordingly, BYONC should \nform the foundation for future PJM and Commission efforts to address the demand-driven effects \nof new large loads."},{"page":12,"startToken":3500,"endToken":3581,"text":"-12- \nRespectfully submitted, \n/s/ Brian George \nBrian George \nSr. Lead, US Energy Markets  \nElizabeth Savage \nStrategic Negotiator \nGoogle LLC \n655 New York Ave., NW \nWashington, DC 20001 \n(202) 999-0990 \nbriangeorge@google.com\neomsavage@google.com\n /s/ Matthew Christiansen\nMatthew Christiansen \nBryan Shpall \nRachel Neuburger \nJenae Sharp \nWilson Sonsini Goodrich & Rosati \n1700 K Street NW \nFifth Floor \nWashington, DC 20006 \n(617) 598-7871 \nmchristiansen@wsgr.com\nbshpall@wsgr.com\nrneuburger@wsgr.com\njmsharp@wsgr.com\nCounsel for Google LLC\nDated:  August 21, 2026"},{"page":13,"startToken":3581,"endToken":3641,"text":"CERTIFICATE OF SERVICE\nI hereby certify that I have this day served the foregoing document upon each person \ndesignated on the official service lists compiled by the Secretary of the Commission in these \nproceedings. \nDated:  August 21, 2026 \nSan Francisco, CA \n/s/ Jenae Sharp \nJenae Sharp \nWilson Sonsini Goodrich & Rosati \nOne Market Plaza,  \nSpear Tower #3300 \nSan Francisco, CA 94105"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":409,"startToken":0,"endToken":381},{"p":2,"at":409,"title":"I. WHO WE ARE","method":"printed heading","endPage":2,"endAt":805,"startToken":381,"endToken":441},{"p":2,"at":805,"title":"II. COMMENTS","method":"printed heading","endPage":11,"endAt":1305,"startToken":441,"endToken":3405},{"p":11,"at":1305,"title":"III. CONCLUSION","method":"printed heading","endPage":13,"endAt":0,"startToken":3405,"endToken":3581},{"p":13,"at":0,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":13,"endAt":388,"startToken":3581,"endToken":3641}]}