{"document":{"slug":"rec-20260821-5211","title":"Motion to Intervene and Comments of CPV Power Holdings, LP re PJM Interconnection, L.L.C.’s 07/31/2026 filing","issued":"2026-08-21","accession":"20260821-5211","docket":"ER26-3380-000","group":"PJM Reliability Backstop Procurement","filer":"CPV Power Holdings, LP","kind":"comments","file":"sources/filings/text/20260821-5211_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5211","tier":"record","sha256":"b578bffe34df708f488313314d064bd01099e7029b814ae86c076569b1e35ba4","pages":7,"tokens":1971,"emptyPages":[],"textThemes":["study","adequacy"]},"pages":[{"page":1,"startToken":0,"endToken":287,"text":"DCACTIVE-88550388.3 \n \n \n1 \n \nUNITED STATES OF AMERICA \nBEFORE THE \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Interconnection, L.L.C.  \n) \nDocket No. ER26-3380-000 \nMotion to Intervene and Comments of CPV Power Holdings, LP \nPursuant to Rules 212 and 214 of the Federal Energy Regulatory Commission’s (“FERC” \nor “Commission”) Rules of Practice and Procedure,1 CPV Power Holdings, LP (“CPV”) moves \nto intervene and comment on the July 31, 2026 filing by PJM Interconnection, L.L.C. (“PJM”) in \nthe above-captioned proceeding.2 In the RBP Proposal, PJM proposes revisions to the PJM Open \nAccess Transmission Tariff (“Tariff”) and the Reliability Assurance Agreement Among Load \nServing Entities to implement the Reliability Backstop Procurement (“RBP”) framework—a \none-time mechanism for procuring new capacity to address PJM’s resource adequacy shortfalls.   \nI. \nSUMMARY \nCPV supports the RBP Proposal and believes it is a critical step toward restoring resource \nadequacy in the PJM region. PJM is facing a significant capacity shortfall as observed by the \n2028/29 Base Residual Auction, which fell 6,831 MW short of the Reliability Requirement. \nLoad forecasts indicate that this shortfall is expected to grow considerably over the next 5–10 \nyears, primarily driven by large load additions and data center growth. The RBP is a necessary \nand timely response to this growing resource adequacy challenge.  \nCPV participated throughout the months-long Critical Issues Fast Path (“CIFP”) \nproceeding that culminated in the RBP Proposal and appreciates PJM’s efforts to develop a \nnecessary and timely response to the resource adequacy shortfalls facing the PJM region. The \n \n118 C.F.R. §§ 385.212 and 385.214 (2025). \n2PJM Interconnection, L.L.C., Docket No. ER26-3380-000, “Reliability Backstop Procurement to Address Resource \nAdequacy Concerns Stemming from Large Loads” (July 31, 2026) (“RBP Proposal”)."},{"page":2,"startToken":287,"endToken":617,"text":"DCACTIVE-88550388.3 \n \n \n2 \n \nRBP Proposal combines feedback from the diverse group of parties that participated in the CIFP \nto yield an overall package that aims to protect ratepayer interests while still providing the \ndecisive action that the moment calls for.  \nA confluence of conditions in recent years, including interconnection queue delays, \nsignificant increases in equipment and development costs, supply chain constraints, and extended \nconstruction durations, has made bringing new generation resources online increasingly difficult. \nDespite these conditions, companies including CPV have continued to develop new generation \nprojects, many of which are in the late stages of development and have the potential to enter \nconstruction in the near term. Absent immediate action to facilitate the financing and \nconstruction of these late-stage projects, it is unlikely that new generation will be built at the \nscale necessary to keep pace with expected load growth. The RBP Proposal will use gating \ncriteria to evaluate sponsor credentials and development progress and determine which are most \nlikely to enter service, while distinguishing between advanced and more speculative projects. \nThe selection process will then select projects in least-cost order, subject to prioritization based \non expected in-service dates,3 and provide them with the long-term commitments needed in \ntoday’s environment to enable them to reach financial close, commence construction, and \nultimately reach commercial operations. \nWhile supportive of the RBP Proposal, in reviewing PJM’s July 31, 2026, filing in this \nproceeding, CPV identified one issue with the gating criteria language that requires clarification \nto avoid causing confusion about the gating requirements, inadvertently narrowing the pool of \n \n3Given the significant weight placed on expected in-service dates in the RBP selection process, rigorous application \nof the gating criteria will be particularly important to ensure that proposed commercial operation dates are realistic \nand projects are assigned to the appropriate Delivery Year. Otherwise, the selection methodology could result in a \nsignificantly higher-cost project being selected based on a perceived timing advantage that ultimately may not \nmaterialize, with little or no corresponding reliability benefit."},{"page":3,"startToken":617,"endToken":850,"text":"DCACTIVE-88550388.3 \n \n \n3 \n \neligible projects, and undermining the effectiveness of the procurement. Specifically, the site \ncontrol requirement of the RBP’s gating criteria applicable to RBP Sell Offers, set forth in \nAttachment DD § 18.5(f)(i)(2), appears to contain a drafting error that could unintentionally \nexclude projects currently in PJM’s interconnection queue that have already satisfied applicable \nsite control requirements under existing Tariff provisions. CPV does not believe PJM intended \nthis result and proposes a narrow revision to the Tariff language to clarify its intended \napplication. With this limited clarification, CPV respectfully urges the Commission to act by, \nand accept the RBP Proposal and Tariff changes subject to a compliance filing effective, \nSeptember 29, 2026, as PJM requested.4 \nII. \nMOTION TO INTERVENE  \nCPV and its affiliates develop, own, and operate electric generating facilities that \nparticipate in the PJM markets. PJM’s RBP Proposal and associated Tariff changes will directly \nand substantially affect CPV and its affiliates. Accordingly, CPV has a direct and substantial \ninterest in the outcome of this proceeding that no other party can adequately represent. CPV’s \nparticipation is in the public interest, and it respectfully requests that the Commission grant this \ntimely filed motion to intervene. \nIII. \nCOMMENTS  \nAlthough CPV generally supports the RBP Proposal, it respectfully submits the following \ncomments addressing one discrete issue: PJM’s proposed site control requirement applicable to \nRBP Sell Offers. \n \n4RBP Proposal at 2–4."},{"page":4,"startToken":850,"endToken":1234,"text":"DCACTIVE-88550388.3 \n \n \n4 \n \nUnder the RBP Proposal, a seller must satisfy certain gating criteria to submit a valid \nRBP Sell Offer for RBP UCAP MW.5 Among those criteria, PJM proposes to require a seller to \nprovide evidence of 100% site control in Attachment DD § 18.5(f)(i)(2) of its proposed Tariff \nchanges: \nEvidence of 100% Site Control for each of the Generating Facility (including the \nlocation of the main step-up transformer), the Interconnection Facilities, and the \nInterconnection Switchyard (as defined in the PJM Manuals) for a term of at least \nthree years from the date of submission of the Application.6 \n \nAs discussed below, CPV has identified two related aspects of this provision that warrant \nclarification to avoid unnecessarily narrowing the pool of eligible sellers and \nundermining the effectiveness of the RBP. \nThe proposed section 18.5(f)(i)(2) requires a seller to demonstrate site control for a term \nof at least three years from the date of submission of the “Application.” The Tariff’s existing \ndefinition of Application, however, has no connection to the RBP.7 Notably, PJM does not use \nthe term “Application” in the RBP Proposal to describe a seller’s submission; instead, PJM \nconsistently uses “RBP Sell Offer” to describe the mechanism by which sellers offer to sell RBP \nResources. This strongly indicates that PJM intended to reference the date of submission of the \nRBP Sell Offer.8  \nSecond, as drafted, the proposed section 18.5(f)(i)(2) does not appear to account for \nsellers with generation projects currently active in PJM’s interconnection queue that have already \n \n5See RBP Proposal at 71–74; Proposed Tariff, Attachment DD, § 18.5(f)(i). \n6RBP Proposal at 73, n.189; Proposed Tariff, Attachment DD, § 18.5(f)(i)(2). \n7See RBP Proposal at 1, n.1 (“Capitalized terms not otherwise defined herein have the meaning as defined in the \nTariff, Amended and Restated Operating Agreement of PJM [], RAA, and Consolidated Transmission Owners \nAgreement [].”); see PJM Tariff, Part 1, § 1, Definitions – Application (“‘Application’ shall mean a request by \nan Eligible Customer for transmission service pursuant to the provisions of the Tariff.”). \n8The RBP Sell Offer is defined as “an offer to sell RBP Resources in the Reliability Backstop Procurement.” RBP \nProposal at 46, n.122; Proposed Tariff, Definitions – RBP Sell Offer."},{"page":5,"startToken":1234,"endToken":1571,"text":"DCACTIVE-88550388.3 \n \n \n5 \n \nsatisfied the applicable site control requirements under PJM’s existing Tariff. PJM’s existing \ninterconnection procedures require generation project developers to demonstrate site control as a \ncondition of advancing through the queue.9 Requiring such developers to separately satisfy a new \nthree-year requirement on limited notice could impose an  unnecessary additional burden on \nsellers that have already demonstrated to PJM’s satisfaction that they possess the requisite site \ncontrol for their generating facility and related infrastructure under PJM’s existing generator \ninterconnection procedures, and risks disqualifying advanced projects from the RBP. \nFor example, projects in Transition Cycle #1 and Transition Cycle #2, which have \nreached advanced stages of the interconnection process , have already demonstrated site control \nas a prerequisite to their continued advancement through the queue. Yet under section \n18.5(f)(i)(2) as currently proposed, these projects could inadvertently be excluded from \nparticipation in the RBP based solely on the discrepancies between the two sets of site control \nrequirements. Such an outcome would unnecessarily limit the pool of eligible resources, contrary \nto the RBP’s stated objective of selecting resources “most likely to go into service and provide \nneeded capacity.”10 Based on this objective, and the extensive discussions during the CIFP \nproceeding, CPV does not believe that this was PJM’s intent with the site control gating \ncriteria.11  \n \n9See Tariff, Part VII, Subpart A, section 302 (explaining that a developer in PJM’s Transition Cycle must meet \nnumerous site control requirements throughout the interconnection process); id. at Part VIII, Subpart A, section 302 \n(explaining that a developer in PJM’s regular cycle must meet numerous site control requirements throughout the \ninterconnection process). \n10RBP Proposal at 71. \n11See PJM Interconnection, L.L.C., CIFP – Reliability Backstop Procurement – Options and Packages Matrix – \nUpdated, Row 13, Selection Process (June 29, 2026) (providing, as part of PJM’s proposal, “Evidence of site control \nconsistent with PJM Tariff Part VII, Subpart A, Section 302, and PJM Tariff Part VIII, Subpart A, Section 402”) \n(“RBP Options Matrix”), available at https://www.pjm.com/committees-and-groups/cifp-rbp."},{"page":6,"startToken":1571,"endToken":1845,"text":"DCACTIVE-88550388.3 \n \n \n6 \n \nTo remedy these concerns, CPV respectfully requests that the Commission direct PJM to \nsubmit revisions to section 18.5(f)(i)(2) in a compliance filing,12 as follows: \nFor projects without an active queue position, eEvidence of 100% Site Control \nfor each of the Generating Facility (including the location of the main step-up \ntransformer), the Interconnection Facilities, and the Interconnection Switchyard \n(as defined in the PJM Manuals) for a term of at least three years from the date of \nsubmission of the Application RBP Sell Offer. \nThis limited revision would preserve PJM’s site control requirement for projects without \nactive queue positions while recognizing that projects already in the interconnection queue are \nsubject to existing site control requirements under the Tariff. The revision would therefore \nclarify the requirement by using terminology applicable to the RBP Proposal and avoid \nunintentionally excluding advanced projects without altering the overall design of the RBP \nProposal. \nIV. \nCOMMUNICATIONS \nPlease address all notices and communications regarding this proceeding to the following \npersons who are also designated for service in this proceeding: \nJonathan Odell \nExecutive Vice President and General Counsel \nCompetitive Power Ventures, Inc. \n8403 Colesville Road, Suite 915 \nSilver Spring, MD  20910 \nTel:  (240) 723-2300 \njodell@cpv.com \n \n \nDeborah A. Carpentier \nKathy Lowrey \nCrowell & Moring LLP \n600 Fifth Street, NW \nWashington, DC 20001 \nTel: (202) 624-2857 \ndcarpentier@crowell.com \nklowrey@crowell.com  \n \n \n12PJM consents to the Commission using its authority under NRG Power Marketing, LLC v. FERC, 862 F.3d 108 \n(D.C. Cir. 2017) to “modify and/or sever any element of the proposed Tariff and RAA language to the extent \nnecessary . . . .” RBP Proposal at 3."},{"page":7,"startToken":1845,"endToken":1971,"text":"DCACTIVE-88550388.3 \n \n \n7 \n \nV. \nCONCLUSION \nFor the foregoing reasons, CPV respectfully requests the Commission to grant its \nrequests herein, and to act on PJM’s RBP Proposal by, and accept the related Tariff changes, \nsubject to a compliance filing, effective, September 29, 2026, as requested by PJM..   \n \nRespectfully submitted, \n \n \n \n \n \n \n \n \n \n \nAugust 21, 2026 \n/s/   Deborah A. Carpentier     \nDeborah A. Carpentier \nKathy Lowrey \nCrowell & Moring LLP \n600 Fifth Street, NW \nWashington, DC 20001 \nTel: (202) 624-2857 \ndcarpentier@crowell.com \nklowrey@crowell.com \n  \nCounsel for CPV Power Holdings, LP \n \nCERTIFICATE OF SERVICE \nI hereby certify that on this 21st day of August, 2026, a copy of the foregoing document \nhas been electronically served upon each person designated on the official service list in this \nproceeding. \n \n/s/  Kathy Lowrey         \nKathy Lowrey"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":1,"endAt":865,"startToken":0,"endToken":125},{"p":1,"at":865,"title":"I. SUMMARY","method":"printed heading","endPage":3,"endAt":826,"startToken":125,"endToken":737},{"p":3,"at":826,"title":"II. MOTION TO INTERVENE","method":"printed heading","endPage":3,"endAt":1364,"startToken":737,"endToken":816},{"p":3,"at":1364,"title":"III. COMMENTS","method":"printed heading","endPage":6,"endAt":1043,"startToken":816,"endToken":1725},{"p":6,"at":1043,"title":"IV. COMMUNICATIONS","method":"printed heading","endPage":7,"endAt":30,"startToken":1725,"endToken":1848},{"p":7,"at":30,"title":"V. CONCLUSION","method":"printed heading","endPage":7,"endAt":618,"startToken":1848,"endToken":1930},{"p":7,"at":618,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":7,"endAt":883,"startToken":1930,"endToken":1971}]}