{"document":{"slug":"rec-20260821-5218","title":"Comments of the Office of the Ohio Consumers’ Counsel re the reforms to the governance of PJM Interconnection, L.L.C","issued":"2026-08-21","accession":"20260821-5218","docket":"AD26-7-000","group":"PJM governance and stakeholder reform vote","filer":"Office of the Ohio Consumers' Counsel","kind":"comments","file":"sources/filings/text/20260821-5218_001.txt","url":"https://elibrary.ferc.gov/eLibrary/filelist?accession_number=20260821-5218","tier":"record","sha256":"6baac5380242939cfc606fc94db3b66372ad89643f02d902f9abeb231b13a435","pages":40,"tokens":10888,"emptyPages":[],"textThemes":["cost","adequacy","flex"]},"pages":[{"page":1,"startToken":0,"endToken":102,"text":"UNITED STATES OF AMERICA \nBEFORE THE  \nFEDERAL ENERGY REGULATORY COMMISSION \n \n \n \n \n \nPJM Governance and Stakeholder Reforms \n) \n) \nDocket No. AD26-7-000 \n \n \nCOMMENTS  \nBY \nOFFICE OF THE OHIO CONSUMERS’ COUNSEL \n \n \n \nMaureen R. Willis  \nOhio Consumers’ Counsel \n \nAngela D. O’Brien \n \nDeputy Consumers’ Counsel  \n \nOffice of the Ohio Consumers’ Counsel \n65 East State Street, Suite 700 \nColumbus, Ohio 43215 \nTelephone: (614) 466-9531 \nangela.obrien@occ.ohio.gov \n \nDenise C. Goulet \nMcCarter & English, LLP \n1301 K Street, N.W. \nSuite 1000 West \nWashington, D.C. 20005 \n(202) 753-3400 \ndgoulet@mccarter.com \n \n \nSpecial Counsel to the Ohio Office of the Attorney \nGeneral for the Office of the Ohio Consumers’ \nCounsel"},{"page":2,"startToken":102,"endToken":207,"text":"i \nTABLE OF CONTENTS \n \nPAGE \n \nI.  \nINTRODUCTION ...............................................................................................................1 \nII.  \nREFORMS TO PJM GOVERNANCE STRUCTURE .......................................................3 \nA. \nPJM governance must expressly recognize affordability and the public interest. ...3 \nB. \nIndependent cost oversight on transmission projects is needed. ..............................4 \nC. \nEnhancing the PJM Attachment M-3 Supplemental Project process. .....................6 \nD. \nTransparency for PJM meetings. ...........................................................................10 \nIII. \nSTATE PARTICIPATION ................................................................................................10 \nIV.  \nSTAKEHOLDER PROCESS ............................................................................................11 \nA. \nConsumers need meaningful cost information before PJM makes decisions. .......11 \nB. \nStakeholder voting should prevent affiliate voting from overwhelming consumer \ninterests. .................................................................................................................13 \nC. \nPJM voting should be transparent. .........................................................................14 \nV.  \nPJM BOARD INDEPENDENCE ......................................................................................14 \nVI. \nSECTION 205 FILING RIGHTS ......................................................................................15 \nVII.  \nCONCLUSION ..................................................................................................................17"},{"page":3,"startToken":207,"endToken":415,"text":"1 \nUNITED STATES OF AMERICA \nBEFORE THE  \nFEDERAL ENERGY REGULATORY COMMISSION \n \nPJM Governance and Stakeholder Reforms \n) \n) \nDocket No. AD26-7-000 \n \n \nCOMMENTS  \nBY \nOFFICE OF THE OHIO CONSUMERS’ COUNSEL \n \n \nI.  \nINTRODUCTION \nThe Office of the Ohio Consumers’ Counsel (“OCC”), on behalf of Ohio’s residential \nutility consumers, respectfully submits these comments regarding reforms to the governance of \nPJM Interconnection, L.L.C. (“PJM”). \nThe Federal Energy Regulatory Commission’s (“FERC” or “Commission”) examination \nof PJM governance is both timely and necessary. Under the Federal Power Act, FERC is \nresponsible for protecting consumers from rates, terms, and conditions of wholesale electric \nservice that are unjust and unreasonable. Yet the institutional structure through which PJM \ndevelops the rules governing wholesale markets, resource adequacy, and transmission planning \ngives the consumers who ultimately pay those costs remarkably little leverage in the processes \nand decisions that produce them. That is problematic on many fronts.  \nThat imbalance matters. PJM serves approximately 67 million consumers across 14 \njurisdictions. But those consumers are represented in the PJM stakeholder process by only 14 \nstatutory consumer advocate votes—one for each jurisdiction. At the Standing Committee and \nSenior Task Force level, those consumer advocates constitute approximately 1.3 percent of \npotential voters. Even at the Markets and Reliability Committee (“MRC”) and Members"},{"page":4,"startToken":415,"endToken":640,"text":"2 \nCommittee (“MC”), where sector-weighted voting applies, consumer advocates account for only \na small portion of the voting influence. \nMeanwhile, entities with direct financial interests in PJM market rules and transmission \ndecisions comprise much of PJM’s membership and exercise substantial influence over the \ndevelopment of those rules. The result is a fundamental structural problem: many of the entities \nvoting on proposals governing wholesale electricity markets and transmission investment have a \nfinancial interest in the revenues those rules produce. At the same time, residential consumers \nwho ultimately pay the resulting charges, have comparatively little ability to shape those \nproposals. \nFERC should address that imbalance as a central component of PJM governance reform. \nBut there is more to be done.  \nGovernance reform should not merely redistribute authority among PJM’s existing \ninstitutional actors. It should make PJM more accountable to the public that it serves. That \nrequires, at minimum, making affordability and the public interest an express component of \nPJM’s responsibilities, implementing consumer safeguards for transmission planning, \nstrengthening the voices of statutory consumer advocates, improving transparency and cost \noversight, and ensuring that any expansion of the PJM Board’s authority is accompanied by \nmeaningful safeguards protecting consumers. \nOCC’s responses to the Commission’s specific list of questions attached to the Notice \nRequesting Post-Conference Comment issued in this docket on July 30, 2026, are appended as \nAttachment A to these comments."},{"page":5,"startToken":640,"endToken":940,"text":"3 \nII.  \nREFORMS TO PJM GOVERNANCE STRUCTURE \nA. \nPJM governance must expressly recognize affordability and the public \ninterest. \nPJM performs functions that profoundly affect the affordability and reliability of \nelectricity service for over 67 million Americans. Its capacity market, energy markets, and \ntransmission planning processes produce billions of dollars in costs that ultimately flow through \nto consumers’ electric bills. These electric transmission and supply charges comprise 60 to 70% \nof an Ohio household’s electricity bill, all pass-through charges from FERC and PJM.1  \nYet affordability is not embedded in PJM’s governance structure. Unlike reliability – \nwhich PJM expressly calls its “primary responsibility,” – affordability is not treated as a \ncomparable institutional obligation. PJM instead points to the states to address the retail impact \nof rising wholesale costs.2 \nReliability is indispensable. But reliability cannot mean reliability at any cost. The \nFederal Power Act’s consumer-protection mandate requires rates to be “just and reasonable.” \nEnergy markets and transmission planning should produce reliable service efficiently and at \nreasonable cost. \nPJM’s governing documents should expressly require PJM and its Board to act in the \npublic interest and to consider affordability alongside reliability. This should be a substantive \nobligation, not an aspirational statement. PJM should be required to evaluate the consumer cost \nconsequences of material proposals and major Board decisions. A governance structure that \nmeasures reliability consequences but does not meaningfully measure and consider consumer \n \n1 Public Utilities Commission of Ohio, Ohio Utility Rate Survey (June 2026).  \n2 PJM Interconnection, L.L.C., Docket Nos. EL 25-49-000 and -001, Informational Report, Exhibit A at 2 (Jan. 20, \n2026) (“PJM must be conscious of the affordability challenges facing the 67 million consumers in our footprint \ntoday. There is much that our states can be doing to contend with the higher wholesale costs at the retail level.”) \n(citation omitted)."},{"page":6,"startToken":940,"endToken":1190,"text":"4 \ncost consequences falls far short of providing just and reasonable rates for consumers. \nAffordability should accordingly become an institutional responsibility against which PJM’s \nperformance can be measured. \nB. \nIndependent cost oversight on transmission projects is needed. \nTransmission deserves particular attention in the form of an Independent Transmission \nMonitor. Transmission charges can account for up to 20% of an Ohio household’s electricity \nbill.3 \nPJM consumers face substantial and growing transmission costs. From 2017 through \n2025, Ohio transmission project costs have ballooned with over $16.4 billion in costs, with \nsupplemental projects accounting for 66% of those projects, $10.8 billion. 4 These huge \ntransmission bills to Ohio consumers emanate from massive transmission investment and the \ncost allocation methodologies used to collect that investment in regional and supplemental \ntransmission projects.  \nOhio consumers’ experience with supplemental transmission projects demonstrates the \nneed for independent transmission oversight. Under PJM’s existing framework, supplemental \nprojects are not subject to PJM review for need, prudence or cost-effectiveness. Yet the costs are \nrecovered from consumers through FERC-jurisdictional transmission rates.  \nIn Ohio, no one is filling that gap by reviewing these projects for prudence, need, or cost-\neffectiveness before consumers are required to pay for them. OCC’s 2023 complaint to FERC \nhighlighted the magnitude of the problem: based on data through 2022 available at the time of \nthat filing, Ohio utilities had added to local transmission infrastructures over approximately six \n \n3 PUCO, Ohio Utility Rate Survey (June 2026).  \n4 Sourced from PJM State of Ohio Infrastructure Reports 2017-2025."},{"page":7,"startToken":1190,"endToken":1452,"text":"5 \nyears nearly $6 billion in supplemental project costs that were not reviewed by any regulatory \nauthority for need, prudence or cost-effectiveness. This problem keeps growing. Supplemental \nProjects continue to make up the bulk of annual investment in transmission infrastructure. \nThis regulatory gap creates precisely the wrong incentive – utilities can pursue substantial \ntransmission investment without the meaningful, independent scrutiny that should precede the \nimposition of monopoly costs on captive consumers. The persistence of that gap also \ndemonstrates why governance reform cannot rely on existing institutions to correct themselves. \nOCC filed its complaint in September 2023 asking FERC to remedy the lack of regulatory \noversight and requested expedited treatment because additional projects and costs would \ncontinue accumulating while the complaint remained unresolved. True to form, subsequent \nsupplemental transmission spending has continued to increase. From 2023 to 2025, an additional \n$4.3 billion has been spent on Ohio supplemental transmission projects, bringing the total since \n2017 to over $10 billion. Nearly three years after filing the complaint, FERC still has not ruled \non OCC’s Complaint. Docket No. EL23-105-000 remains on the Commission’s list of pending \ncomplaints. \nYet there is no transmission equivalent of PJM’s Independent Market Monitor providing \ncomprehensive, independent scrutiny of transmission planning incentives, costs, and outcomes. \nThat gap is especially troubling for transmission projects receiving limited regional scrutiny, \nincluding transmission-owner Supplemental Projects that are proliferating in Ohio.  \nThe existing structure can create incentives favoring locally planned, cost-of-service \ntransmission investment over regional solutions that may provide broader benefits or greater \nefficiency. Consumers ultimately bear the consequences of those incentives through their electric \nbills."},{"page":8,"startToken":1452,"endToken":1702,"text":"6 \nAn independent transmission monitor would help close this accountability gap by \nproviding ongoing, independent scrutiny of the need, alternatives and costs associated with \ntransmission investment – including Supplemental Projects. This would replace the current \nprocess where consumers must rely on after-the-fact challenges to formula transmission rates \nwhile billions of dollars in costs continue to be incurred. An independent transmission monitor \nshould be structurally independent from PJM and transmission owners and should have sufficient \naccess to information to conduct meaningful analysis. \nIndependent oversight would not replace PJM’s planning responsibilities, existing state \noversight authority or the Commission’s jurisdiction. It would provide FERC, states, consumer \nadvocates, and stakeholders with an independent source of information needed to determine \nwhether billions of dollars in transmission investment are prudent, efficient, and beneficial to \nconsumers. \nC. \nEnhancing the PJM Attachment M-3 Supplemental Project process. \nThe growth in AI load interconnection requests is driving the need for improved local and \nSupplemental Project transmission planning processes. Although the Supplemental Projects are \nnot directly governed by the requirements of FERC Order No. 1920, the Commission’s recent \nactions reflect an increasing emphasis on transparent planning processes, meaningful stakeholder \nparticipation, cost-effective analyses, and well-supported planning records. Those essential \nelements are lacking in the present PJM process.  \nIn Order No. 1920, the Commission concluded that more forward-looking and \ntransparent transmission planning is necessary to ensure that transmission investments remain \njust and reasonable over the long term. While that rule principally addresses long-term regional \ntransmission planning, the policy objectives it advances – including transparency, robust"},{"page":9,"startToken":1702,"endToken":2021,"text":"7 \nplanning assumptions, and meaningful stakeholder engagement—are equally relevant to \ncustomer-driven supplemental transmission projects.  \nImportantly, Order No. 8905 required similar transparency, robust planning assumptions \nand meaningful stakeholder engagement in the local transmission planning process. In PJM, \nSupplemental Projects are part of the local planning process and must be planned in a manner \nthat encompasses these principles. \nThe PJM Attachment M-3 planning process for local transmission projects and \nSupplemental Projects embrace some, but not all these principles. OCC recognizes that FERC \naccepted the current PJM Attachment M-3 local transmission planning process in 2020 but notes \nthat FERC has more recently questioned whether that process is sufficient in its April 2022 \nSupplemental Notice of Technical Conference in Docket No. AD22-8-000. That Notice states: \nThe purpose of this conference is to explore measures to ensure \nsufficient transparency into and cost effectiveness of local and \nregional transmission planning decisions, including: (1) the role of \ncost management measures in ensuring the cost-effective \nidentification of local transmission needs (e.g., planning criteria) \nand solutions to address identified local transmission and regional \nreliability-related transmission needs; and (2) cost considerations \nand the processes through which transmission developers recover \ntheir costs to ensure just and reasonable transmission rates.6 \n \nAlthough FERC did not require changes to the local and Supplemental Project transmission \nplanning process in Order No. 1920, it clearly left the door open for improvements in that \nprocess.  \n \n5 Preventing Undue Discrimination and Preference in Transmission Service, Order No. 890, 118 FERC ¶ 61,119 at \nP 3, FERC Stats. & Regs. ¶ 31,241 (2007) (“Order No. 890”), order on reh’g, Order No. 890-A, 121 FERC ¶ \n61,297, FERC Stats. & Regs. ¶ 31,261 (2007) (“Order No. 890-A”); order on reh’g, Order No. 890-B, 123 FERC ¶ \n61,299 (2008); order on reh’g, Order No. 890-C, 126 FERC ¶ 61,228 (2009). \n6 Transmission Planning and Cost Management, Docket No. AD22-8-000, Supplemental Notice of Technical \nConference at 1, (July 22, 2022)."},{"page":10,"startToken":2021,"endToken":2263,"text":"8 \nIn a move toward creating greater transparency around that process, FERC recently \nissued show-cause orders directing several public utility transmission providers, including PJM \nin Docket No. EL26-67-000, to explain why aspects of their local and Supplemental Project \ntransmission planning processes remain just and reasonable under the Federal Power Act. These \nproceedings reflect FERC’s movement toward a broader regulatory focus on transparency, \njustification, cost-effectiveness and oversight of local and Supplemental Project transmission \ninvestments.  \nThese show cause proceedings reinforce the importance of ensuring that local and \nSupplemental transmission projects are supported by demonstrated need, prudent engineering, \ntransparent planning assumptions, project cost-effectiveness and a planning record sufficient to \npermit meaningful stakeholder review before significant investments are undertaken. These \nelements are missing from the current PJM Attachment M-3 planning process.  \nCustomer-driven project presentations to the Sub-regional RTEP committee and the \nTEAC committee should include additional information regarding the basis for projected load \ngrowth. Without disclosing confidential commercial information, transmission owners should \nidentify the extent to which projected customer demand is supported by executed service \nagreements, meaningful development milestones, or other objective indicators demonstrating the \nlikelihood that the projected load will materialize.  \nTransmission owners should be more fully discussing alternatives considered during \nproject development. For projects presented at the Solutions stage, stakeholders should \nunderstand not only the preferred solution but also the principle alternatives evaluated, the \nreasons those alternatives were not selected, and whether phased implementation, equipment \nupgrades, operational changes, or other lower-cost options were considered."},{"page":11,"startToken":2263,"endToken":2522,"text":"9 \nTransmission owners should also address substantive stakeholder comments as projects \nadvance through subsequent stages of the M-3 process. OCC is not suggesting that transmission \nowners be required to provide formal written responses to every comment. However, a brief \ndiscussion during subsequent TEAC presentations explaining whether significant stakeholder \nconcerns were considered and, where appropriate, how they were addressed, would strengthen \nthe planning record and improve stakeholder confidence in the process.  \nPJM and transmission owners should at a minimum provide information requested by \nstakeholders during these processes about specific planned projects. To date, despite several \nrequests by OCC for information as part of the July and August Attachment M-3 stakeholder \nprocesses in PJM, PJM and the Ohio transmission Owners still have not provided substantive \nresponses to OCC’s requests for information regarding specific projects.7 Those questions seek \ninformation related to the planning assumptions, alternatives considered and cost-efficiency of \ncertain identified proposed Supplemental Projects in Ohio. \nFinally, OCC encourages continued dialogue among PJM, transmission owners, states, \nconsumer advocates, and other stakeholders regarding the evolution of Supplemental Project \ntransmission planning, especially where those local transmission projects may be related to large \nload and Artificial Intelligence data centers. This customer-driven transmission investment \nrepresents a significant and growing component of transmission development throughout the \nPJM region, both in the Regional Transmission Expansion Planning process and in the \nAttachment M-3 Supplemental Project planning process. As planning practices continue to \nevolve, regular stakeholder discussions regarding transparency, planning assumptions, customer \ncommitments, and cost responsibility will help ensure that the M-3 process provides meaningful \n \n7 See Attachment B."},{"page":12,"startToken":2522,"endToken":2756,"text":"10 \nopportunities for stakeholder participation while supporting timely, reliable, and cost-effective \ntransmission planning. \nD. \nTransparency for PJM meetings. \nTransparency in PJM meetings and decision-making is essential. PJM makes decisions \nthat have enormous consequences for the over 67 million consumers who pay electric bills. \nDecisions affecting capacity and energy costs, transmission investment, market rules, and \nreliability should not be developed through closed-door discussions or processes that leave \nconsumers and their representatives unable to understand who advocated for outcomes and why. \nOpen meetings, accessible materials, meaningful opportunity for public and consumer \nparticipation, and a clear record of the basis for PJM’s decisions would promote accountability \nand public confidence. It would also help ensure that consumer affordability and broader public \ninterest receive meaningful consideration alongside the interests of PJM’s market participants. \nThe Board’s deliberations and decision-making should, whenever practicable, occur in meetings \nopen to stakeholders and the public, with limited exceptions only where confidentiality is legally \nor commercially required. \nIII. \nSTATE PARTICIPATION  \nState participation must be formalized- but state representation cannot substitute for \nconsumer representation. \nPJM governance reform should substantially strengthen the role of the states and the role \nof consumer advocates. FERC should recognize an important distinction: strengthening the “state \nvoice” is not synonymous with strengthening the consumer voice. \nState utility commissions, governors, legislators, environmental agencies, economic-\ndevelopment officials, and statutory consumer advocates perform different functions. State \ncommissions may balance reliability, utility financial integrity, economic development,"},{"page":13,"startToken":2756,"endToken":3013,"text":"11 \nenvironmental requirements, and other statutory considerations. Governors and legislatures \nlikewise balance numerous competing public-policy objectives. Statutory consumer advocates \nhave a different responsibility: protecting utility consumers, including residential consumers, \nfrom excessive, unjust and unreasonable utility costs. \nThose unique consumer interests often overlap with the states’ interests, but they are not \nidentical. Consumer advocates may agree with their state commissions on one issue and disagree \non another. PJM governance reform should preserve those independent perspectives rather than \nsubsuming consumer representation within a generalized category of “state interests.” \nAccordingly, FERC should strengthen the role of both representative voices in the processes. \nOPSI should receive meaningful jump-ball filing rights where a sufficiently broad \nconsensus of states supports an alternative to a PJM proposal. While the Commission has \nprovided for such filing rights in the context of cost allocation proposals for long-term regional \ntransmission projects in Order No. 1920, no similar rights exist for the Order No. 1000 and Order \nNo. 890 regional and local transmission planning processes. PJM should also be required to \nconsult formally with OPSI before any major section 205 filings, including significant resource-\nadequacy and transmission planning and cost allocation filings. At the same time, statutory \nconsumer advocates should retain an independent and meaningful role throughout PJM \ngovernance, including in the stakeholder process and in the selection of PJM Board members. \n \nIV.  \nSTAKEHOLDER PROCESS \nA. \nConsumers need meaningful cost information before PJM makes decisions. \nPJM cannot credibly claim that its processes produce cost-effective outcomes if neither \ndecision-makers nor stakeholders are routinely provided with information about what the"},{"page":14,"startToken":3013,"endToken":3278,"text":"12 \nproposals will cost consumers. Cost analysis should become an ordinary part of PJM governance \n– a part that is freely and timely shared with interested parties, including consumer advocates. \nFor material proposals advancing to the MRC or MC, PJM should provide a reasonable \nassessment of expected cost impacts sufficiently early for stakeholders to use that information in \nevaluating competing proposals. The analysis need not – and often cannot – predict costs with \nprecision. But uncertainty is not a justification for providing no analysis. \nPJM routinely analyzes complicated questions involving reliability, resource adequacy, \nmarket behavior, and system conditions under uncertain future assumptions. Consumer cost \nconsequences deserve comparable institutional attention. \nCost information would improve not only consumer protection but decision-making \nitself. Stakeholders could evaluate whether incremental reliability benefits justify incremental \ncosts, compare alternatives on a more informed basis, and identify proposals that accomplish the \nsame objective at lower consumer cost. \nFERC should require PJM to institutionalize meaningful and transparent cost-impact \nanalysis. FERC also should require PJM and the transmission owners to provide answers to \nspecific questions from stakeholders, including consumers advocates, about identified projects \nduring the stakeholder process. Such questions include information regarding cost analyses, \nplanning assumptions, alternatives considered and other cost impact data. There should be \nconsequences for PJM’s and/or the transmission owners’ failure to respond to such specific \nquestions about identified projects. In the absence of any realistic process for challenging the \nprudence, need for and cost-efficiency of local or Supplemental Projects in the formula \ntransmission rate challenge process, consumers must have access to information regarding these \nprojects during the transmission planning stage before construction begins."},{"page":15,"startToken":3278,"endToken":3557,"text":"13 \nB. \nStakeholder voting should prevent affiliate voting from overwhelming \nconsumer interests. \nPJM’s stakeholder process should facilitate genuine consensus rather than allow entities \nwith numerous affiliates to dominate the early stages of policy development. Ohio illustrates how \nPJM’s affiliate-voting rules dilute the consumer voice at the committees where proposals are \ndeveloped.  \nOCC, the statutory representative of 4.5 million residential households, receives one vote \nto represent Ohio’s residential utility consumers. Utilities participate through corporate families \nwith numerous PJM affiliates. For example, Ohio Power Company is part of the AEP corporate \nfamily, which includes multiple transmission, generation, and energy affiliates. Ohio Edison is \npart of the FirstEnergy corporate family. Duke Energy Ohio participates alongside other Duke \naffiliates. At Standing Committees and Senior Task Forces, where affiliate voting is permitted, \nthese corporate families can potentially exercise many multiple votes while OCC has one.  \nThat distinction is particularly important because the detailed work of designing PJM \nrules often occurs at Standing Committees and Senior Task Forces before proposals reach the \nMarkets and Reliability Committee (MRC) or the Members Committee (MC). While the MRC \nand MC may be governed by weighted sector voting requirements, the same is not true of the \nother Standing Committees and Task Forces. This can permit supply-side or other commercial \ninterests to advance proposals without meaningful support from those who represent the \nconsumers responsible for paying the resulting costs. That is fundamentally unfair.  \nBy the time proposals reach sector-weighted voting at the MRC and MC, it may be too \nlate for consumer interests to meaningfully shape their design. Those interests may instead be \nleft primarily with the ability to vote no on a proposal developed without their meaningful \nparticipation."},{"page":16,"startToken":3557,"endToken":3800,"text":"14 \nFERC should encourage PJM to address this structural problem by extending sector-\nweighted voting, or comparable protections against affiliate-vote dominance, to Standing \nCommittees and Senior Task Forces. Doing so would not silence any sector but rather would \nlevelize the playing field for all stakeholder interests. It would encourage those submitting \nproposals to attract support across sectors earlier in the development process, when compromise \ncan meaningfully affect their substance. \nC. \nPJM voting should be transparent. \nPJM should also disclose how individual member companies vote throughout the \nstakeholder process. Entities participating in PJM are voting on matters that affect more than \ntheir private commercial interests. They participate in developing rules affecting the reliability \nand cost of electricity service for approximately 67 million consumers. \nAggregate voting results provide insufficient accountability and can impede consensus-\nbuilding. When a proposal narrowly fails, stakeholders should be able to identify the concerns \npreventing agreement and determine whether modifications could produce broader support. \nTransparency would also eliminate inconsistent disclosure obligations. Some utilities \nmay already be required under state law to disclose PJM votes, while others are not. In contrast, \npublic consumer advocates operate under public-records requirements. PJM-wide disclosure \nwould establish a uniform standard that could easily be followed. Individual member votes \nshould be publicly available at all material levels of the stakeholder process. \nV.  \nPJM BOARD INDEPENDENCE \n \nPJM Board reform should increase public accountability while preserving board \nindependence. \nAny expansion of Board authority should be accompanied by greater Board \naccountability."},{"page":17,"startToken":3800,"endToken":4055,"text":"15 \nFirst, the Board’s required expertise should include meaningful experience with state \nregulation and consumer interests. PJM should include Board members who understand how \nwholesale market and transmission decisions ultimately appear on consumers’ retail electric \nbills. \nSecond, the process for selecting Board members should include greater state and \nconsumer participation. The Nominating Committee should include representation designated by \nstates as well as a statutory consumer advocate. Consumers should not depend upon occasional \nrotation within the End-Use Customer Sector for representation in selecting the individuals who \nultimately exercise enormous authority over costs paid by those consumers. \nThird, Board decision-making should be substantially more transparent. Board votes on \nsignificant matters should be disclosed, and the Board should provide meaningful explanations \nfor consequential decisions. Appropriate portions of Board meetings should also be open or \notherwise made available to stakeholders and the public. \nTransparency should not, however, come at the expense of independence. FERC should \nnot relax appropriate restrictions on private communication between individual Board members \nand interested market participants. Greater transparency in Board deliberations provides a better \nmeans of increasing accountability than expanding private access. \n \nVI. \nSECTION 205 FILING RIGHTS \nFERC should not expand the PJM Board’s Section 205 authority without corresponding \nconsumer and state safeguards. \nThe Commission should proceed cautiously before expanding or limiting the PJM \nBoard’s unilateral filing authority under section 205 of the Federal Power Act. The relevant \nquestion is not simply whether other RTO boards possess broader section 205 authority. The \nquestion is whether expanding or limiting authority to PJM’s Board, under PJM’s existing"},{"page":18,"startToken":4055,"endToken":4321,"text":"16 \ngovernance structure, would produce decision-making that better protects consumers and results \nin just and reasonable rates. \n \nMore importantly the Commission has already spoken on the concept of limiting the \nBoard’s existing filing rights related to transmission planning. In Docket Nos. ER24-2336, \nER24-2338 and EL24-119, the Commission rejected efforts by the Transmission Owners to \nprovide themselves with extensive, unilateral veto rights with respect to the transmission \nplanning process. In those cases, PJM and the Transmission Owners proposed to move the \nplanning process rules from the PJM Operating Agreement to the PJM Open Access \nTransmission Tariff and the Consolidated Transmission Owners’ Agreement. FERC found that \nsuch action would provide the Transmission Owners with undue influence over the transmission \nplanning process.8 The D.C. Circuit Court of Appeals affirmed the Commission’s rulings just \ntwo months ago.9 There is no reason to revisit these very recent decisions.  \nAt a minimum, PJM’s governing documents should first be revised to establish \naffordability and the public interest as express Board responsibilities. States and consumer \nadvocates should also receive meaningful “jump ball” filing rights that allow a sufficiently broad \nconsensus to present an alternative proposal to the Commission. \nProviding FERC with competing proposals would not displace the Commission’s \nultimate responsibility to determine what is just and reasonable. Instead, it would ensure that the \nCommission hears a meaningful alternative from governmental entities responsible for protecting \nconsumer interests. \n \n8 PJM Interconnection, L.L.C., 189 FERC ¶ 61,181(2024), order denying reh’g, 192 FERC ¶ 61,051 (2025). \n9 PJM Transmission Owners v. FERC, No. 25-1064 (D.C. Cir. June 5, 2026) (per curiam)."},{"page":19,"startToken":4321,"endToken":4479,"text":"17 \nVII.  CONCLUSION \nThe Commission should evaluate PJM governance reform from the perspective of the \nconsumers whom the Federal Power Act ultimately protects. The fundamental problem is not \nsimply whether authority resides with PJM’s Members Committee, its Board, or another \ninstitutional actor. The problem is whether PJM’s governance structure produces transparent, \naccountable, cost-conscious decisions consistent with just and reasonable rates. At the present \ntime, PJM’s governance structure is not doing the job.  \nThe reforms discussed in these OCC comments would not guarantee that every PJM \ndecision produces the outcome preferred by consumers, states, market participants, or any other \nconstituency. The reforms would, however, make it substantially more likely that decisions \naffecting tens of millions of consumers are made through a process that gives weight to \naffordability, provides meaningful public accountability, and supplies the Commission with the \ninformation and competing perspectives necessary to fulfill its responsibility under the Federal \nPower Act to protect consumers from unjust and unreasonable rates."},{"page":20,"startToken":4479,"endToken":4564,"text":"18 \nRespectfully submitted, \n \n/s/ Maureen R. Willis \nMaureen R. Willis (0020847) \nOhio Consumers’ Counsel \n \nAngela D. O’Brien (0097579) \nDeputy Consumers’ Counsel  \n \nOffice of the Ohio Consumers’ Counsel \n65 East State Street, Suite 700 \nColumbus, Ohio 43215 \nTelephone: (614) 286-7549 \nangela.obrien@occ.ohio.gov \n \nDenise C. Goulet \nMcCarter & English, LLP \n1301 K Street, N.W. \nSuite 1000 West \nWashington, D.C. 20005 \n(202) 753-3400 \ndgoulet@mccarter.com \n \n \nSpecial Counsel to the Ohio Office of the Attorney \nGeneral for the Office of the Ohio Consumers’ \nCounsel"},{"page":21,"startToken":4564,"endToken":4614,"text":"19 \nCERTIFICATE OF SERVICE \n \nI hereby certify that a copy of the foregoing Comments was served via electronic \ntransmission upon all parties of record on the Commission’s official service list in this \nproceeding on this 21st day of August 2026. \n \n \n \n \n \n \n/s/ Maureen R. Willis \n \n \n \n \n \n \nMaureen R. Willis \nOhio Consumers’ Counsel"},{"page":22,"startToken":4614,"endToken":4951,"text":"ATTACHMENT A \nOffice of the Ohio Consumers’ Counsel Response to Commission Questions in Notice \nRequesting Post-Conference Comments \nPJM Board Independence \nQuestions/Comments \nYes \nNo \n1) \nShould Board members’ terms be extended to five or more years? \nX \nComments: Longer terms for Board members could help ensure a more knowledgeable \nBoard with a longer-term perspective that is less susceptible to stakeholder pressure. \nHowever, terms should not be too long to reduce accountability to Members (including \nconsumer advocates) and make it more difficult to influence the Board when change is \nneeded. \n2) \nShould there be a maximum number of years that a Board member may \nserve (e.g., 10 years)? \nX \nComments: While a longer term may promote Board independence and allow members \nto develop greater institutional knowledge, a single term greater than five years without \nthe possibility of reelection would likely reduce accountability to Members and make \nthe Board too insulated from Member feedback. Some opportunity for periodic \nreevaluation of Board performance better balances independence with accountability. \nPeriodic refreshment in the board is a benefit.  \n3) \nShould the Board member qualification rules be revised to provide a \npreference for some Board members that reside in the PJM region? \nX \nComments: While Board members must act in the interests of the PJM region as a \nwhole, residing within the region helps ensure they remain connected to the \naffordability and reliability concerns experienced by the consumers ultimately served by \nPJM. Regional familiarity strengthens understanding of consumer impacts and state \npolicy. \n4) \nShould the conflict-of-interest rules be revised to reduce the cooling off \nperiod for Board members from two years to one year? \nX \nComments: The two-year cooling-off period helps preserve the Board’s independence \nby reducing conflicts of interest arising from recent employment with PJM Members. A \ncooling off period is required in Ohio when it comes to both the state consumer \nadvocate and the PUCO commissioners.  \n5) \nShould restrictions on Board communications be relaxed to enable more \ncommunication between the Board and stakeholders? \nX \nAttachment A \nPage 1 of 5"},{"page":23,"startToken":4951,"endToken":5255,"text":"Questions/Comments \nYes \nNo \n \nComments: FERC should not relax appropriate restrictions on private communications \nbetween individual Board members and interested market participants. Greater \ntransparency in Board deliberations provides a better means of increasing accountability \nthan expanding private access. \n6) \nIn order to increase transparency, should Board votes be made public or the \nBoard be required to explain its reasoning?  \nX \n \n \nComments: To promote transparency, Board votes on significant matters should be \ndisclosed, and the Board should provide meaningful explanations for consequential \ndecisions.  \n7) \nIn order to increase transparency, should some Board meetings be open or \navailable to the public? \nX \n \n \nComments: Appropriate portions of Board meetings should be open or otherwise made \navailable to stakeholders and the public. The Board’s deliberations and decision-making \nshould, whenever practicable, occur in meetings that are open to stakeholders and the \npublic, with limited exceptions only where confidentiality is legally or commercially \nrequired. \n8) \nShould PJM’s governing documents be revised to explicitly state that the \nresponsibility of PJM and its Board is to serve the public interest? \nX \n \n \nComments: PJM should expressly recognize in governing documents its obligation to \nserve the public interest and consider affordability as well as reliability of service for \nconsumers in the region.  \n9) \nShould state representatives have at least one voting member on the \nNominating Committee? \nX \n \n \nComments: States should have representation on the Nominating Committee. It \npromotes balanced governance and broader public accountability.  \n10) \nShould PJM adopt public performance metrics and tie management \ncompensation to their achievement? \n \nX \n \nComments: Tying PJM management compensation to achievement and public \nperformance metrics could result in PJM management focusing on reliability at all costs \nto the detriment of consumers who must pay high rates for transmission service. Energy \nmarkets and transmission planning should produce reliable service efficiently and at \nreasonable cost. \n \n \n \nAttachment A \nPage 2 of 5"},{"page":24,"startToken":5255,"endToken":5623,"text":"Section 205 Filing Rights \n \n \nQuestions/Comments \nYes \nNo \n11) \nShould the stakeholder process be advisory, i.e., stakeholder votes only \ninform the Board? \n \nX \n \nComments: The stakeholder process should not be reduced to one that is merely \nadvisory. The stakeholder process should provide an important mechanism for ensuring \nthat a broad range of perspectives, including those representing residential consumers- \nare meaningfully considered in decisions affecting reliability, markets, and costs. Before \nreducing the role of stakeholders, confidence is needed that stakeholder input is \nconsistently reflected in decision-making and that departures from stakeholder \nrecommendations are transparent and well explained. Having a meaningful stakeholder \nprocess promotes accountability, transparency, and better outcomes for consumers.  \n12) \nShould PJM have section 205 filing rights over the energy market and \nancillary services unencumbered by the requirement to obtain approval of \ntwo-thirds of the Members Committee? \n \nX \n \nComments: Expanding PJM’s section 205 filing rights without obtaining approval from \ntwo-thirds of the Members Committee could provide PJM or certain stakeholder sectors \nwith too much power. As noted in OCC’s comments, in Docket Nos. ER24-2336, \nER24-2338 and EL24-119, the Commission rejected efforts by the Transmission \nOwners to provide themselves with extensive, unilateral veto rights with respect to the \ntransmission planning process. In those cases, PJM and the Transmission Owners \nproposed to move the planning process rules from the PJM Operating Agreement to the \nPJM Open Access Transmission Tariff and the Consolidated Transmission Owners’ \nAgreement. FERC found that such action would provide the Transmission Owners with \nundue influence over the transmission planning process. The D.C. Circuit Court of \nAppeals recently affirmed the Commission’s rulings. \n13) \nShould PJM have section 205 filing rights over Regional Transmission \nExpansion Planning (RTEP) unencumbered by the requirement to obtain \napproval of two-thirds of the Members Committee? \n \nX \n \nComments: Expanding PJM’s section 205 filing rights without obtaining approval from \ntwo-thirds of the Members Committee could provide PJM or certain stakeholder sectors \nwith too much power. As noted in OCC’s comments, in Docket Nos. ER24-2336, \nER24-2338 and EL24-119, the Commission rejected efforts by the Transmission \nOwners to provide themselves with extensive, unilateral veto rights with respect to the \ntransmission planning process. In those cases, PJM and the Transmission Owners \nAttachment A \nPage 3 of 5"},{"page":25,"startToken":5623,"endToken":5923,"text":"Questions/Comments \nYes \nNo \nproposed to move the planning process rules from the PJM Operating Agreement to the \nPJM Open Access Transmission Tariff and the Consolidated Transmission Owners’ \nAgreement. FERC found that such action would provide the Transmission Owners with \nundue influence over the transmission planning process. The D.C. Circuit Court of \nAppeals recently affirmed the Commission’s rulings. \n14) \nShould the Organization of PJM States Inc (OPSI) have “jump ball” rights \nover resource adequacy and transmission cost allocation filings when a \nsupermajority of OPSI agrees on an alternative proposal? \nX \n \n \nComments: OPSI should receive meaningful jump-ball filing rights where a sufficiently \nbroad consensus of states supports an alternative to a PJM proposal. While the \nCommission has provided for such filing rights in the context of cost allocation \nproposals for long-term regional transmission projects in Order No. 1920, no similar \nrights exist for the Order No. 1000 and Order No. 890 regional and local transmission \nplanning processes. PJM should also be required to consult formally with OPSI before \nany major section 205 filings, including significant resource-adequacy and transmission \nplanning and cost allocation filings. Consumer advocates should also receive \nmeaningful “jump ball” filing rights that allow a sufficiently broad consensus to present \nan alternative proposal to the Commission. \n15) \nShould the Members Committee have “jump ball” filing rights over the \nportions of the tariff where PJM has 205 filing rights when a supermajority \nof stakeholders approves an alternative proposal? \n \nX \n \nComments: Permitting the Members Committee to have “jump ball” filing rights over \nthe PJM Board could result in improper influence by certain stakeholder sectors over \nresource adequacy, transmission planning and cost allocation filings. \n \nStakeholder Process \n \n \nQuestions/Comments \nYes \nNo \n16) \nShould the approval threshold in the Members Committee be lowered from \ntwo-thirds sector-weighted voting? \n \n \n \nComments:  \nAttachment A \nPage 4 of 5"},{"page":26,"startToken":5923,"endToken":6173,"text":"Questions/Comments \nYes \nNo \n17) \nShould the voting rules barring affiliate votes, which apply to senior \nstanding committees, also apply to lower-level committees? \nX \n \n \nComments: PJM’s current affiliate-voting rules at the lower-level committees unfairly \ndilute the consumer voice at the committees where proposals developed. As explained \nin OCC’s Comments, Consumer Advocates of the PJM states collectively have 14 total \nvotes at the lower-level committees, accounting for only 1.3 percent of the vote. \n \nState Participation \n \n \nQuestions/Comments \nYes \nNo \n18) \nIn addition to OPSI, should there be a second state representative group \nconsisting of governors’ representatives and/or state legislators’ \nrepresentatives? \nX \n \n \nComments: OCC supports an additional state representative group in addition to OPSI \nprovided there is no duplication of state efforts and no dilution of the consumer \nadvocacy roles of members of the Consumer Advocates of the PJM States. \n19) \nShould state representatives have a formal voting role in the stakeholder \nprocess (limited to certain topics, such as resource adequacy and regional \ntransmission cost allocation) in addition to the consumer advocate votes?  \nX \n \n \nComments: Providing state representatives with an informational voting role in the PJM \nstakeholder process would improve transparency without altering stakeholder voting \nrights.  \n20) \nShould PJM be required to consult with OPSI prior to making a section 205 \nfiling related to resource adequacy and transmission cost allocation?  \nX \n \n \nComments: Requiring PJM to consult with OPSI in this manner would provide great \ntransparency. In addition, this is required by FERC Order 1920-A. \n \nAttachment A \nPage 5 of 5"},{"page":27,"startToken":6173,"endToken":6507,"text":"65 E. State St., Suite 700  ⋅  Columbus, Ohio 43215  ⋅  614-466-8574  ⋅  www.occ.ohio.gov \nMaureen Willis \nOhio Consumers’ Counsel \nCheryl Grossman \nBoard Chair \nSTAKEHOLDER COMMENTS AND INFORMATION REQUESTS OF THE OHIO \nOFFICE OF THE CONSUMERS' COUNSEL \nRegarding Supplemental Transmission Projects Presented at the July 7, 2026, PJM \nTransmission Expansion Advisory Committee Meeting \nI.\nIntroduction\nThe Ohio Office of the Consumers' Counsel (OCC) appreciates the opportunity to submit these \nComments and Information Requests regarding the supplemental transmission projects presented by \nAmerican Electric Power (AEP), FirstEnergy ATSI (ATSI), Duke Energy Ohio (DEOK), and AES \nOhio (AES) at the July 7, 2026, meeting of the PJM Transmission Expansion Advisory Committee \n(TEAC). \nOCC submits these comments in support of the purposes of PJM's M-3 Supplemental Project \nProcess. As reflected in PJM Manual 14B, the Regional Transmission Expansion Planning Process \nis intended to promote transparency, facilitate meaningful stakeholder participation, and improve \ntransmission planning through the early identification and evaluation of planning assumptions, \ntransmission needs, proposed solutions, and local transmission plans. Transparency during the M-3 \nprocess benefits transmission owners, PJM, regulators, and consumers by promoting informed \ndiscussion regarding planning assumptions, project need, alternatives, and anticipated consumer \nimpact. OCC’s comments are intended to further these objectives by requesting information \nnecessary for stakeholders to meaningfully evaluate customer-driven supplemental transmission \nprojects.   \nOCC supports prudent transmission investment necessary to maintain a reliable and resilient \ntransmission system. At the same time, transmission investments are long-lived assets whose costs \nultimately may be borne by consumers. Accordingly, transmission planning should remain \ntransparent, data-driven, and consistent with the principle that costs should follow cost causation.  \nThese Comments and Information Requests are consistent with OCC's longstanding interest in \nensuring that supplemental transmission projects are supported by transparent planning \nassumptions, demonstrated need, prudent engineering, and appropriate consumer protections. \nNothing in these comments is intended to address the merits of any pending regulatory proceeding. \nRather, OCC seeks to ensure that the project-specific record developed through the M-3 process is \nas complete and transparent as possible. \nAttachment B\nPage 1 of 14"},{"page":28,"startToken":6507,"endToken":6802,"text":"July 16, 2026 \nPage 2 of 13 \n \n65 E. State St., Suite 700  ⋅  Columbus, Ohio 43215  ⋅  614-466-8574  ⋅  www.occ.ohio.gov \nII. \nThe Supplemental Transmission Projects \nA.  \nFirstEnergy ATSI – Need No. ATSI-2026-048 \nOCC appreciates FirstEnergy's presentation of Need No. ATSI-2026-048. Because this project is \nbeing presented during the Needs stage of the M-3 process, OCC's comments are directed to \nwhether the identified operational issue has been sufficiently documented to support advancement \nto the Solutions phase. \nUnlike the other Ohio presentations, ATSI's project is not customer driven. Rather, FirstEnergy \nidentifies an operational limitation associated with maintenance outages on the Chamberlain-\nHarding 345-kV S-21 transmission line caused by terminal equipment limitations.  \nTo facilitate meaningful stakeholder review, OCC respectfully requests additional information \nregarding the following.: \n1. The operational significance of the identified limitation, including how frequently the \nmaintenance condition occurs and whether it has resulted in operational restrictions, \ncongestion, or reliability concerns.  \n2. The applicable planning criteria supporting the identified need and whether the project is \nintended to address reliability, operational flexibility, asset management, or a combination \nof these objectives.  \n3. The expected operational benefits that would result from addressing the identified limitation.  \n4. As this project advances to the Solutions stage, the alternatives considered, including \nequipment replacement, operational measures, maintenance practices, and other lower-cost \noptions before more extensive transmission facilities are proposed.  \n5. Estimated customer benefits and expected project costs once potential solutions are \nidentified.  \nOCC appreciates that ATSI identified the specific operational issue prompting the project and \nencourages continued transparency as engineering alternatives are developed. \n \nB.  \nAmerican Electric Power – Need No. AEP-2026-AP007 \nOCC appreciates AEP's presentation of Need No. AEP-2026-AP007. Because this project is at \nthe Needs stage of the M-3 process, OCC's comments focus on whether AEP has adequately \nAttachment B\nPage 2 of 14"},{"page":29,"startToken":6802,"endToken":7132,"text":"July 16, 2026 \nPage 3 of 13 \n \n65 E. State St., Suite 700  ⋅  Columbus, Ohio 43215  ⋅  614-466-8574  ⋅  www.occ.ohio.gov \ndemonstrated that a transmission need exists and whether sufficient information has been provided \nto allow stakeholders to meaningfully evaluate that need. \nAEP's presentation identifies a request for 1,000 MW of new customer load in Boyd County, \nKentucky, by the fourth quarter of 2028 as the basis for the identified transmission need.  \nBecause this project is in the Needs stage, OCC respectfully requests additional information \nregarding: \n1. The planning assumptions supporting the projected 1,000 MW customer load.  \n2. Whether the requesting customer has executed a binding service agreement or achieved \nother significant development milestones.  \n3. Whether AEP evaluated scenarios in which the requested load is delayed, reduced, or does \nnot materialize.  \n4. The specific transmission planning criteria, thermal limitations, voltage concerns, or other \nsystem conditions giving rise to the identified need.  \n5. Whether the identified need would continue to exist under more conservative customer load \nassumptions.  \n6. Whether transmission facilities located within Ohio are expected to be constructed or \nupgraded to accommodate service to the Kentucky customer and, if so, whether Ohio \nconsumers may bear any portion of the resulting transmission costs.  \n7.  Does PJM and/or the transmission owner have any information as to whether the \nprospective load interconnection customer has submitted similarly sized project proposals in \nother locations on that transmission owner’s system, or in other transmission zones.  \n \n8.  Has PJM and/or the transmission owner conducted any analyses of the extent to which \nexisting loads need the expansions being considered for the large load interconnection to \nserve their needs now or in the future.  If so, please provide that information. \nBecause this project appears to arise from a specific customer request rather than existing reliability \nconcerns, OCC also requests an explanation of how future transmission investments associated with \nthis need will be planned and funded consistent with cost-causation principles. \n \n \nAttachment B\nPage 3 of 14"},{"page":30,"startToken":7132,"endToken":7424,"text":"July 16, 2026 \nPage 4 of 13 \n \n65 E. State St., Suite 700  ⋅  Columbus, Ohio 43215  ⋅  614-466-8574  ⋅  www.occ.ohio.gov \n \nC. \nDuke Energy Ohio – Need No. DEOK-2026-004 \nOCC appreciates Duke Energy Ohio's presentation of Need No. DEOK-2026-004. Because this \nproject is being presented during the Needs stage of the M-3 process, OCC's comments focus on \nwhether Duke has adequately demonstrated the need for additional transmission facilities and \nprovided sufficient information for stakeholders to evaluate that need. \nDuke Energy Ohio's presentation indicates that a customer previously requesting approximately 500 \nMW of load near Trenton, Ohio, now plans to increase its requested service by an additional 300 \nMW beginning in 2028.  \nAccordingly, OCC requests additional information regarding: \n1. The basis for the revised customer load forecast and what has changed since the prior need \npresentation.  \n2. Whether the additional load reflects expansion by the same customer or additional customer \ndevelopment.  \n3. The level of customer commitment supporting the revised forecast, including executed \nservice agreements and development milestones.  \n4. The specific transmission planning criteria demonstrating the need for additional \ntransmission facilities.  \n5. Whether the identified need remains under lower customer load assumptions.  \n6. Whether future transmission facilities can be developed in phases corresponding to \ndemonstrated customer commitments.  \n7. Does PJM and/or the transmission owner have any information as to whether the prospective \nload interconnection customer has submitted similarly sized project proposals in other \nlocations on that transmission owner’s system, or in other transmission zones.  \n \n8.  Has PJM and/or the transmission owner conducted any analyses of the extent to which \nexisting loads need the expansions being considered for the large load interconnection to \nserve their needs now or in the future.  If so, please provide that information. \n \nAttachment B\nPage 4 of 14"},{"page":31,"startToken":7424,"endToken":7727,"text":"July 16, 2026 \nPage 5 of 13 \n \n65 E. State St., Suite 700  ⋅  Columbus, Ohio 43215  ⋅  614-466-8574  ⋅  www.occ.ohio.gov \nBecause the identified need appears to arise from the expansion of a specific customer request, \nOCC also requests an explanation of how resulting transmission investments will be planned and \nfunded consistent with cost-causation principles and how existing residential consumers will be \nprotected from costs attributable primarily to serving new large-load customers. \n \nD. \nAES Ohio – Solution Presentations \nOCC appreciates AES Ohio's presentation of proposed solutions for customer-driven transmission \nneeds in the vicinity of the Fayette, Clinton, and Stuart substations. Because these projects are at \nthe Solutions stage of the M-3 process, OCC's comments focus on whether the selected \ntransmission facilities represent prudent, appropriately sized, and cost-effective solutions to the \nidentified needs. \nAES Ohio presented proposed transmission solutions associated with customer-driven projects in \nthe Fayette, Clinton, and Stuart areas. These projects are supported by projected customer requests \nreaching approximately 1.5 GW near Fayette, 500 MW near Clinton, and 1.3 GW near Stuart.  \nAES proposes approximately $589.8 million in transmission investment, including new 345-kV \ntransmission lines, substation expansions, capacitor installations, and customer delivery facilities.  \nBecause these projects are in the Solutions stage, OCC respectfully requests additional information \nregarding: \n1. The basis for concluding that the proposed facilities represent the most prudent and cost-\neffective solution to the identified needs.  \n2. The extent to which the projected customer demand is supported by executed service \nagreements or other significant development milestones.  \n3. Whether the proposed facilities have been appropriately sized based upon reasonably certain \ncustomer demand.  \n4. Whether portions of the proposed projects can be constructed in phases corresponding to \ndemonstrated customer commitments.  \n5. The alternatives evaluated, including phased implementation, operational alternatives, \nequipment upgrades, and lower-cost transmission configurations.  \nAttachment B\nPage 5 of 14"},{"page":32,"startToken":7727,"endToken":8079,"text":"July 16, 2026 \nPage 6 of 13 \n \n65 E. State St., Suite 700  ⋅  Columbus, Ohio 43215  ⋅  614-466-8574  ⋅  www.occ.ohio.gov \n6. Does PJM and/or the transmission owner have any information as to whether the prospective \nload interconnection customer has submitted similarly sized project proposals in other \nlocations on that transmission owner’s system, or in other transmission zones.  \n \n7.  Has PJM and/or the transmission owner conducted any analyses of the extent to which \nexisting loads need the expansions being considered for the large load interconnection to \nserve their needs now or in the future.  If so, please provide that information. \n \nWhile AES identified several transmission alternatives for the Fayette and Clinton projects, OCC \nrequests additional information regarding the comparative cost and performance of those \nalternatives.  \nFor the Stuart project, AES identified \"Alternatives: N/A.\" OCC requests an explanation of why \nno alternatives analysis was performed or presented.  \nFinally, because these projects appear to be undertaken primarily in response to customer requests, \nOCC requests an explanation of how resulting transmission investments will be funded in a manner \nconsistent with cost-causation principles and how existing residential consumers will be protected \nfrom bearing costs attributable primarily to serving new large-load customers. \nAES’s presentation relies on aggregated \"customer requests\" measured in hundreds or thousands of \nmegawatts.  Yet we are not being provided with sufficient information to evaluate the likelihood \nthat those requests will materialize. As customer-driven transmission investments become larger \nand more frequent, OCC encourages PJM and transmission owners to develop standardized \nreporting identifying the maturity of customer requests, the level of contractual commitment \nsupporting forecasted load, and the assumptions used in evaluating forecast uncertainty. Such \ninformation is essential to meaningful stakeholder review and to protecting consumers from the \ncosts of transmission investments that may ultimately prove unnecessary. \nGeneral Policy Discussion  \nThe recent increase in requests for large-load service—including data centers, advanced \nmanufacturing facilities, and other energy-intensive customers—is resulting in substantial \ntransmission investment throughout Ohio. Meaningful stakeholder review depends upon \nunderstanding not only the magnitude of projected customer load but also the certainty supporting \nthose forecasts. \n \n \n \nAttachment B\nPage 6 of 14"},{"page":33,"startToken":8079,"endToken":8458,"text":"July 16, 2026 \nPage 7 of 13 \n \n65 E. State St., Suite 700  ⋅  Columbus, Ohio 43215  ⋅  614-466-8574  ⋅  www.occ.ohio.gov \n1.  \nThe Need for Standardized Reporting  \nOCC encourages PJM and transmission owners to provide standardized reporting identifying: (1) \nprojected load attributable to native load, ordinary growth, and large-load customers; (2) whether \ncustomer load is supported by executed service agreements or other binding commitments; (3) \ncustomer development milestones; (4) anticipated in-service schedules; (5) sensitivity analyses for \ndelayed or cancelled projects; and (6) whether facilities can be phased as customer commitments \nmature. \n \n2.   \nThe Need for Transparency  \nCustomer-driven supplemental transmission projects differ in important respects from traditional \nreliability-driven transmission projects. Historically, many supplemental projects were developed to \naddress aging infrastructure, equipment replacement, operational flexibility, or identified reliability \nviolations based on existing system conditions. By contrast, customer-driven projects are often \ninitiated in anticipation of substantial future load growth associated with one or more specific \ncustomers seeking new or expanded electric service. As a result, these projects frequently depend \nupon assumptions regarding the timing, magnitude, and certainty of future customer demand rather \nthan existing system deficiencies. That distinction makes transparency regarding planning \nassumptions, customer commitments, forecast certainty, and project timing particularly important. \nWithout sufficient information regarding those underlying assumptions, stakeholders cannot \nmeaningfully evaluate whether the proposed transmission investment is appropriately timed, \nappropriately sized, or reasonably necessary to serve the anticipated customer load. \nThe projects presented at the July 7, 2026 TEAC meeting illustrate this distinction. Three of the \nfour Ohio projects were driven primarily by anticipated customer load growth, while one addressed \nan operational limitation on the existing transmission system. OCC's comments reflect those \ndifferences by applying a common set of planning principles while recognizing that the information \nnecessary to evaluate customer-driven projects is not identical to that required for traditional \nreliability or operational projects. \n3. \nThe Value of Phased in Construction in Customer-Driven Transmission Planning  \nAs customer-driven supplemental transmission projects continue to increase in size and complexity, \ntransmission owners should, where practical, evaluate whether proposed facilities can be developed \nin phases that correspond with demonstrated customer demand. Phased implementation is a well-\nestablished planning approach that allows infrastructure to be expanded as customer development \nprogresses while maintaining the flexibility necessary to provide reliable electric service. \nAttachment B\nPage 7 of 14"},{"page":34,"startToken":8458,"endToken":8887,"text":"July 16, 2026 \nPage 8 of 13 \n \n65 E. State St., Suite 700  ⋅  Columbus, Ohio 43215  ⋅  614-466-8574  ⋅  www.occ.ohio.gov \nFor projects driven by anticipated future load growth, phased construction may reduce the risk of \npremature investment if projected customer demand is delayed, reduced, or ultimately does not \nmaterialize. Rather than requiring the construction of facilities sized for the maximum projected \nload at the outset, phased implementation can allow transmission owners to provide service as \ncustomer commitments become more certain and system needs evolve. This approach can reduce \nthe likelihood that consumers will bear the costs of transmission facilities that exceed what is \nreasonably necessary to serve actual demand. \nAccordingly, OCC encourages transmission owners to discuss, as part of the M-3 process, whether \nphased implementation was considered during project development, the engineering and economic \nfactors supporting the selected approach, and how the proposed construction schedule aligns with \nanticipated customer development. Providing this information will improve transparency, \nstrengthen the planning record, and enhance stakeholder confidence that proposed investments are \nappropriately timed and appropriately sized for reasonably certain customer demand. Considering \nphased implementation where feasible does not delay necessary infrastructure or discourage \neconomic development. Rather, it reflects prudent utility planning by aligning the pace of \ninfrastructure investment with the pace of demonstrated customer demand, thereby reducing the \npotential for existing consumers to bear the costs of facilities constructed significantly in advance of \nneed, or that may be excess capacity if the AI loads fail to show up as projected. \nIII.  \nFederal Regulatory Context \nThe projects presented at this meeting arise during a period of significant evolution in federal \ntransmission planning policy.  The growth in AI load interconnection requests is driving the need \nfor improved local and Supplemental Project transmission planning processes that account for the \npotential cost impact of these local projects.  Although the Supplemental Projects presented through \nPJM’s M-3 process are not directly governed by the requirements of FERC Order No. 1920, the \nCommission’s recent actions reflect an increasing emphasis on transparent planning processes, \nmeaningful stakeholder participation, cost-effective analyses, and well-supported planning records.   \nIn Order No. 1920, the Commission concluded that more forward-looking and transparent \ntransmission planning is necessary to ensure that transmission investments remain just and \nreasonable over the long term.  While that rule principally addresses regional transmission planning, \nthe policy objectives it advances – including transparency, robust planning assumptions, and \nmeaningful stakeholder engagement—are equally relevant to customer-driven supplemental \ntransmission projects.  Importantly, Order No. 890 required similar transparency, robust planning \nassumptions and meaningful stakeholder engagement in the local transmission planning process.  In \nAttachment B\nPage 8 of 14"},{"page":35,"startToken":8887,"endToken":9260,"text":"July 16, 2026 \nPage 9 of 13 \n \n65 E. State St., Suite 700  ⋅  Columbus, Ohio 43215  ⋅  614-466-8574  ⋅  www.occ.ohio.gov \nPJM, Supplemental Projects are part of the local planning process and must be planned in a manner \nthat encompasses these principles. \nThe PJM Attachment M-3 planning process for local transmission projects and Supplemental \nProjects embrace some, but not all of these principles.  OCC recognizes that FERC accepted the \ncurrent PJM Attachment M-3 local transmission planning process in 2020, but notes that FERC has \nmore recently questioned whether that process is sufficient in its April 2022 Notice of Technical \nConference in Docket No. AD22-8-000.  That Notice states that: \nThe purpose of this conference is to explore measures to ensure sufficient \ntransparency into and cost effectiveness of local and regional transmission \nplanning decisions, including: (1) the role of cost management measures in \nensuring the cost-effective identification of local transmission needs (e.g., \nplanning criteria) and solutions to address identified local transmission and \nregional reliability-related transmission needs; and (2) cost considerations and \nthe processes through which transmission developers recover their costs to \nensure just and reasonable transmission rates. \n \nIt is this cost effectiveness obligation that is missing from the current PJM Attachment M-3 \nplanning process.   \n \nAlthough FERC did not require changes to the local and Supplemental Project transmission \nplanning process in Order No. 1920, it clearly left the door open for improvements in that process.   \nIn a move toward creating greater transparency around that process, FERC recently issued show-\ncause orders directing several public utility transmission providers, including PJM in Docket No. \nEL26-67-000, to explain why aspects of their local and Supplemental Project transmission planning \nprocesses remain just and reasonable under the Federal Power Act.  OCC recognizes that  the new \nshow cause proceedings do not control the disposition of the projects presented here.  However, \nthese proceedings reflect FERC’s movement toward a broader regulatory focus on transparency, \njustification, cost-effectiveness and oversight of local and Supplemental Project transmission \ninvestments.  \n \nThese show cause proceedings reinforce the importance of ensuring that local and Supplemental \ntransmission projects are supported by demonstrated need, prudent engineering, transparent \nplanning assumptions, project cost-effectiveness and a planning record sufficient to permit \nmeaningful stakeholder review before significant investments are undertaken.  \n \n \nAttachment B\nPage 9 of 14"},{"page":36,"startToken":9260,"endToken":9646,"text":"July 16, 2026 \nPage 10 of 13 \n \n65 E. State St., Suite 700  ⋅  Columbus, Ohio 43215  ⋅  614-466-8574  ⋅  www.occ.ohio.gov \nIV. \nConsumer Protection Principles \nAs supplemental transmission planning increasingly responds to requests from individual large-load \ncustomers rather than traditional reliability needs, several principles should guide the evaluation of \nproposed transmission investments.   \nFirst, transmission projects should be supported by a clearly demonstrated need based on objective \nand transparent planning analyses. Stakeholders should have sufficient information to understand \nthe assumptions underlying projected customer demand, the degree of certainty associated with \nthose forecasts, and the planning criteria giving rise to the identified need.  Without this \ninformation, stakeholders cannot meaningfully evaluate whether proposed facilities are necessary or \nappropriately sized.  \nSecond, transmission investments should reflect prudent utility planning. Proposed solutions should \nbe supported by reasonable engineering analyses, consideration of feasible alternatives, and where \nappropriate, opportunities for phased implementation that correspond to demonstrated customer \ncommitments.  Particularly for projects involving substantial capital investment, prudent planning \nrequires balancing the need to provide timely service to new consumers with the responsibility to \navoid premature, unnecessary or potentially abandoned infrastructure investments that may \nultimately be borne by existing consumers. \nThird, transmission investments should be developed and implemented in a manner consistent with \nlongstanding regulatory principle of cost causation. Consumers should have confidence that \ninvestments undertaken primarily to accommodate new large-load customers are planned and \nfunded in a manner that appropriately assigns costs to those AI customers, rather than shifting those \ncosts to existing residential and small business consumers. \nFinally, meaningful stakeholder participation is essential to maintaining confidence in the \ntransmission planning process.  The M-3 process should provide an opportunity for stakeholders to \nreview proposed transmission needs and solutions before significant investment decisions are \nfinalized.  That opportunity is meaningful only if stakeholders are provided sufficient information to \nunderstand the basis of proposed projects and if substantive stakeholder comments are thoughtfully \nconsidered as projects advances through the planning process. \nThese principles are not intended to impede or delay needed transmission investment. Rather, they \nare intended to ensure that customer driven transmission projects are supported by transparent \nplanning assumptions, prudent engineering, meaningful stakeholder review, and appropriate \nconsumer protections. As transmission planning continues to evolve in response to unprecedented \nlarge-load growth, adherence to these principles will strengthen confidence in the M-3 process and \nAttachment B\nPage 10 of 14"},{"page":37,"startToken":9646,"endToken":10022,"text":"July 16, 2026 \nPage 11 of 13 \n \n65 E. State St., Suite 700  ⋅  Columbus, Ohio 43215  ⋅  614-466-8574  ⋅  www.occ.ohio.gov \nhelp ensure that transmission investments are reliable, cost-effective, and fair to the consumers who \nultimately fund the electric system.   \nV. \n Enhancing the M-3 Supplemental Project Process  \nOCC appreciates PJM's efforts to improve transparency and stakeholder engagement through the \nM-3 Supplemental Project Process. As supplemental transmission planning evolves to address \nunprecedented growth in customer-driven load, there are opportunities to further strengthen the \nprocess while preserving the flexibility transmission owners need to respond to emerging system \nneeds. \nOCC recommends that future customer-driven project presentations include additional information \nregarding the basis for projected load growth. Without disclosing confidential commercial \ninformation, transmission owners should identify the extent to which projected customer demand is \nsupported by executed service agreements, meaningful development milestones, or other objective \nindicators demonstrating the likelihood that the projected load will materialize. Providing \nstakeholders with a better understanding of forecast certainty would improve confidence that \nproposed transmission investments are appropriately timed and sized. \nOCC encourages transmission owners to more fully discuss alternatives considered during project \ndevelopment. For projects presented at the Solutions stage, stakeholders should understand not only \nthe preferred solution but also the principal alternatives evaluated, the reasons those alternatives \nwere not selected, and whether phased implementation, equipment upgrades, operational changes, \nor other lower-cost options were considered. Such information would improve transparency and \nstrengthen stakeholder confidence that the selected solution represents the most prudent investment. \nOCC recommends that PJM encourage transmission owners to address substantive stakeholder \ncomments as projects advance through subsequent stages of the M-3 process. OCC is not suggesting \nthat transmission owners be required to provide formal written responses to every comment. \nHowever, a brief discussion during subsequent TEAC presentations explaining whether significant \nstakeholder concerns were considered and, where appropriate, how they were addressed would \nstrengthen the planning record and improve stakeholder confidence in the process. \nFinally, OCC encourages continued dialogue among PJM, transmission owners, states, consumer \nadvocates, and other stakeholders regarding the evolution of supplemental transmission planning. \nCustomer-driven transmission investment represents a significant and growing component of \ntransmission development throughout the PJM region. As planning practices continue to evolve, \nregular stakeholder discussions regarding transparency, planning assumptions, customer \nAttachment B\nPage 11 of 14"},{"page":38,"startToken":10022,"endToken":10355,"text":"July 16, 2026 \nPage 12 of 13 \n \n65 E. State St., Suite 700  ⋅  Columbus, Ohio 43215  ⋅  614-466-8574  ⋅  www.occ.ohio.gov \ncommitments, and cost responsibility will help ensure that the M-3 process continues to provide \nmeaningful opportunities for stakeholder participation while supporting timely, reliable, and cost-\neffective transmission planning. \nVI.  \nLooking Forward \nThe comments submitted herein are intended not only to address the specific supplemental \ntransmission projects presented at the July 7, 2026 TEAC meeting, but also to contribute to the \ncontinued evolution of a transparent, well-supported, and consumer-focused supplemental \ntransmission planning process. \nOCC recognizes that the electric industry is experiencing unprecedented changes driven by rapid \nload growth, technological advancement, and increasing demand for electric service from data \ncenters, advanced manufacturing facilities, and other large energy users. Transmission owners and \nPJM face the significant challenge of planning for this growth while maintaining system reliability \nand providing timely service to new customers. \nAt the same time, these changing conditions reinforce—not diminish—the importance of prudent \nplanning, transparency, and meaningful stakeholder participation. Customer-driven supplemental \ntransmission projects increasingly involve investments measured in billions of dollars and \ninfrastructure that may remain in service for decades. Such investments warrant planning \nassumptions and project development processes that provide stakeholders with sufficient \ninformation to understand the basis for the proposed investment and evaluate whether it is \nappropriately timed, appropriately sized, and consistent with sound utility planning practices. \nThe M-3 Supplemental Project Process can provide an important opportunity for stakeholders to \ncontribute constructively to transmission planning before significant investment decisions are \nfinalized. The effectiveness of that process, however, depends upon stakeholders receiving \nsufficient information to evaluate identified transmission needs, proposed solutions, and the \nassumptions supporting those decisions. \nThe OCC supports responsible transmission investment that maintains reliability, accommodates \nappropriate economic development, and protects consumers from unnecessary costs. Increased \ntransparency and continued stakeholder engagement will strengthen confidence in the supplemental \nplanning process and improve the quality of transmission planning decisions for the benefit of all \nstakeholders. \nAttachment B\nPage 12 of 14"},{"page":39,"startToken":10355,"endToken":10569,"text":"July 16, 2026 \nPage 13 of 13 \n \n65 E. State St., Suite 700  ⋅  Columbus, Ohio 43215  ⋅  614-466-8574  ⋅  www.occ.ohio.gov \nOCC appreciates PJM's continued commitment to stakeholder engagement and looks forward to \ncontinued participation in the M-3 Supplemental Project Process as transmission planning continues \nto evolve. \nVII.  Conclusion \nOCC appreciates the opportunity to submit these Comments regarding the supplemental \ntransmission projects presented at the July 7, 2026 TEAC meeting. The Office recognizes the \nimportance of timely transmission planning and supports investments that are necessary to maintain \nreliable electric service and accommodate responsible economic growth. \nThe observations and recommendations contained in these comments are intended to support the \nobjectives of the M-3 Supplemental Project Process by encouraging greater transparency, \nstrengthening the planning record, and facilitating informed stakeholder participation before \nsignificant transmission investments advance through the planning process. \nAccordingly, OCC respectfully requests that PJM include these comments in the planning record \nfor the referenced projects and encourage the applicable transmission owners to address the issues \nand requests for information raised here during the next stage of the M-3 process.  Doing so will \nenhance stakeholder confidence in the planning process and promote more informed transmission \nplanning decisions. \n \nRespectfully submitted, \n \nMaureen Willis \nOhio Consumers' Counsel \nOffice of the Ohio Consumers' Counsel \nAttachment B\nPage 13 of 14"},{"page":40,"startToken":10569,"endToken":10888,"text":"65 E. State St., Suite 700  ⋅  Columbus, Ohio 43215  ⋅  614-466-8574  ⋅  www.occ.ohio.gov \nMaureen Willis \nOhio Consumers’ Counsel \nCheryl Grossman \nBoard Chair \nFOLLOW UP TO STAKEHOLDER COMMENTS AND INFORMATION REQUESTS OF \nTHE OHIO OFFICE OF THE CONSUMERS' COUNSEL \n \nRegarding Supplemental Transmission Projects Presented at the July 7, 2026, PJM \nTransmission Expansion Advisory Committee Meeting \n \nRequest for Responses to Stakeholder Questions Regarding Ohio Supplemental Projects \nAt the Needs and Solutions meeting held last month, the Office of the Ohio Consumers' Counsel (\"OCC\") \nsubmitted several questions regarding proposed Ohio supplemental transmission projects. To date, those \nquestions have not been addressed. \nOCC respectfully requests that the applicable Transmission Owners provide written responses to the \noutstanding questions before these projects proceed further in the planning process. The questions concern \nmatters central to evaluating the proposed projects, including the basis for the identified need, underlying \nload forecast assumptions, customer commitments, consideration of alternatives, project scope, timing, and \nexpected consumer cost impacts. \nProviding responses will promote a complete and transparent planning record and facilitate meaningful \nstakeholder participation in PJM's planning process. Because the costs of supplemental transmission projects \nare ultimately borne by electricity consumers, stakeholders should have access to the information necessary \nto understand and evaluate the justification for the proposed investments. \nOCC notes that this request is separate from, and is not intended to address the merits of, any pending \nregulatory proceeding. However, the absence of responses to stakeholder questions underscores the \nimportance of transparency and a well-developed record for supplemental transmission projects. Written \nresponses will help ensure that stakeholders and decision-makers have information to assess whether the \nproposed projects represent prudent, cost-effective solutions to the identified system needs. \nAccordingly, OCC requests that the outstanding questions and the corresponding written responses be \nincluded in the planning record prior to further consideration of these projects. \nRespectfully submitted, \n \nMaureen Willis \nOhio Consumers' Counsel \nOffice of the Ohio Consumers' Counsel \nAttachment B\nPage 14 of 14"}],"sections":[{"p":1,"at":0,"title":"Opening text","method":"opening text","endPage":2,"endAt":3,"startToken":0,"endToken":103},{"p":2,"at":3,"title":"TABLE OF CONTENTS","method":"printed heading","endPage":2,"endAt":992,"startToken":103,"endToken":174},{"p":2,"at":992,"title":"B. Stakeholder voting should prevent affiliate voting from overwhelming consumer","method":"printed heading","endPage":3,"endAt":213,"startToken":174,"endToken":234},{"p":3,"at":213,"title":"I. INTRODUCTION","method":"printed heading","endPage":5,"endAt":3,"startToken":234,"endToken":641},{"p":5,"at":3,"title":"II. REFORMS TO PJM GOVERNANCE STRUCTURE","method":"printed heading","endPage":5,"endAt":46,"startToken":641,"endToken":647},{"p":5,"at":46,"title":"A. PJM governance must expressly recognize affordability and the public","method":"printed heading","endPage":6,"endAt":215,"startToken":647,"endToken":968},{"p":6,"at":215,"title":"B. Independent cost oversight on transmission projects is needed.","method":"printed heading","endPage":8,"endAt":995,"startToken":968,"endToken":1580},{"p":8,"at":995,"title":"C. Enhancing the PJM Attachment M-3 Supplemental Project process.","method":"printed heading","endPage":11,"endAt":1689,"startToken":1580,"endToken":2485},{"p":11,"at":1689,"title":"Attachment M-3 Supplemental Project planning process. As planning practices continue to","method":"printed heading","endPage":12,"endAt":127,"startToken":2485,"endToken":2535},{"p":12,"at":127,"title":"D. Transparency for PJM meetings.","method":"printed heading","endPage":12,"endAt":1214,"startToken":2535,"endToken":2678},{"p":12,"at":1214,"title":"III. STATE PARTICIPATION","method":"printed heading","endPage":13,"endAt":1636,"startToken":2678,"endToken":2977},{"p":13,"at":1636,"title":"IV. STAKEHOLDER PROCESS","method":"printed heading","endPage":13,"endAt":1663,"startToken":2977,"endToken":2980},{"p":13,"at":1663,"title":"A. Consumers need meaningful cost information before PJM makes decisions.","method":"printed heading","endPage":15,"endAt":4,"startToken":2980,"endToken":3279},{"p":15,"at":4,"title":"B. Stakeholder voting should prevent affiliate voting from overwhelming","method":"printed heading","endPage":16,"endAt":501,"startToken":3279,"endToken":3626},{"p":16,"at":501,"title":"C. PJM voting should be transparent.","method":"printed heading","endPage":16,"endAt":1607,"startToken":3626,"endToken":3773},{"p":16,"at":1607,"title":"V. PJM BOARD INDEPENDENCE","method":"printed heading","endPage":17,"endAt":1401,"startToken":3773,"endToken":3982},{"p":17,"at":1401,"title":"VI. SECTION 205 FILING RIGHTS","method":"printed heading","endPage":19,"endAt":4,"startToken":3982,"endToken":4322},{"p":19,"at":4,"title":"VII. CONCLUSION","method":"printed heading","endPage":21,"endAt":4,"startToken":4322,"endToken":4565},{"p":21,"at":4,"title":"CERTIFICATE OF SERVICE","method":"printed heading","endPage":22,"endAt":0,"startToken":4565,"endToken":4614},{"p":22,"at":0,"title":"ATTACHMENT A","method":"printed heading","endPage":22,"endAt":2211,"startToken":4614,"endToken":4945},{"p":22,"at":2211,"title":"Attachment A","method":"printed heading","endPage":23,"endAt":2167,"startToken":4945,"endToken":5249},{"p":23,"at":2167,"title":"Attachment A","method":"printed heading","endPage":24,"endAt":2607,"startToken":5249,"endToken":5617},{"p":24,"at":2607,"title":"Attachment A","method":"printed heading","endPage":25,"endAt":2075,"startToken":5617,"endToken":5917},{"p":25,"at":2075,"title":"Attachment A","method":"printed heading","endPage":26,"endAt":1710,"startToken":5917,"endToken":6167},{"p":26,"at":1710,"title":"Attachment A","method":"printed heading","endPage":27,"endAt":387,"startToken":6167,"endToken":6225},{"p":27,"at":387,"title":"I. Introduction","method":"printed heading","endPage":27,"endAt":2547,"startToken":6225,"endToken":6501},{"p":27,"at":2547,"title":"Attachment B","method":"printed heading","endPage":28,"endAt":122,"startToken":6501,"endToken":6528},{"p":28,"at":122,"title":"II. The Supplemental Transmission Projects","method":"printed heading","endPage":28,"endAt":167,"startToken":6528,"endToken":6533},{"p":28,"at":167,"title":"A. FirstEnergy ATSI – Need No. ATSI-2026-048","method":"printed heading","endPage":28,"endAt":1977,"startToken":6533,"endToken":6761},{"p":28,"at":1977,"title":"B. American Electric Power – Need No. AEP-2026-AP007","method":"printed heading","endPage":28,"endAt":2212,"startToken":6761,"endToken":6796},{"p":28,"at":2212,"title":"Attachment B","method":"printed heading","endPage":29,"endAt":2216,"startToken":6796,"endToken":7126},{"p":29,"at":2216,"title":"Attachment B","method":"printed heading","endPage":30,"endAt":124,"startToken":7126,"endToken":7153},{"p":30,"at":124,"title":"C. Duke Energy Ohio – Need No. DEOK-2026-004","method":"printed heading","endPage":30,"endAt":2008,"startToken":7153,"endToken":7418},{"p":30,"at":2008,"title":"Attachment B","method":"printed heading","endPage":31,"endAt":496,"startToken":7418,"endToken":7496},{"p":31,"at":496,"title":"D. AES Ohio – Solution Presentations","method":"printed heading","endPage":31,"endAt":2222,"startToken":7496,"endToken":7721},{"p":31,"at":2222,"title":"Attachment B","method":"printed heading","endPage":32,"endAt":2540,"startToken":7721,"endToken":8073},{"p":32,"at":2540,"title":"Attachment B","method":"printed heading","endPage":33,"endAt":2948,"startToken":8073,"endToken":8452},{"p":33,"at":2948,"title":"Attachment B","method":"printed heading","endPage":34,"endAt":1789,"startToken":8452,"endToken":8706},{"p":34,"at":1789,"title":"III. Federal Regulatory Context","method":"printed heading","endPage":34,"endAt":3174,"startToken":8706,"endToken":8881},{"p":34,"at":3174,"title":"Attachment B","method":"printed heading","endPage":35,"endAt":2665,"startToken":8881,"endToken":9254},{"p":35,"at":2665,"title":"Attachment B","method":"printed heading","endPage":36,"endAt":123,"startToken":9254,"endToken":9281},{"p":36,"at":123,"title":"IV. Consumer Protection Principles","method":"printed heading","endPage":36,"endAt":3022,"startToken":9281,"endToken":9640},{"p":36,"at":3022,"title":"Attachment B","method":"printed heading","endPage":37,"endAt":266,"startToken":9640,"endToken":9686},{"p":37,"at":266,"title":"V. Enhancing the M-3 Supplemental Project Process","method":"printed heading","endPage":37,"endAt":2958,"startToken":9686,"endToken":10016},{"p":37,"at":2958,"title":"Attachment B","method":"printed heading","endPage":38,"endAt":354,"startToken":10016,"endToken":10071},{"p":38,"at":354,"title":"VI. Looking Forward","method":"printed heading","endPage":38,"endAt":2593,"startToken":10071,"endToken":10349},{"p":38,"at":2593,"title":"Attachment B","method":"printed heading","endPage":39,"endAt":326,"startToken":10349,"endToken":10402},{"p":39,"at":326,"title":"VII. Conclusion","method":"printed heading","endPage":39,"endAt":1567,"startToken":10402,"endToken":10563},{"p":39,"at":1567,"title":"Attachment B","method":"printed heading","endPage":40,"endAt":2388,"startToken":10563,"endToken":10882},{"p":40,"at":2388,"title":"Attachment B","method":"printed heading","endPage":40,"endAt":2414,"startToken":10882,"endToken":10888}]}